Azad Engineering Q2 FY26 earnings call: Azad Engineering Limited anticipates significantly stronger performance in the second half of FY '26 as production at its new facilities ramps up

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company anticipates significantly stronger performance in the second half of FY '26 as production at its new facilities ramps up. The company expected to complete Phase 1 over the next 12 months, after which Phase 2 would start; its revenue guidance over the next 3 to 4 years was not dependent on the second facility coming in. Revenue in Q2 FY '26 was INR143 crores, up 28.1% year-on-year. Wallet share of customer spend across energy, aerospace and defence, and oil and gas is about 1% to 1.5%. The company received Phase 2 of the contract with Mitsubishi to supply highly engineered complex rotating and stationary airfoils for advanced gas and thermal power turbine engines; the combined contract value with MHI now stands at INR1,387 crores.

The numbers management gave

Results

  • Revenue in Q2 FY '26 was INR143 crores, up 28.1% year-on-year.
    Show source
    Financially, this has been our best ever quarterly and half-yearly performance with Q2 FY '26 revenues reaching to INR143 crores, up year-on-year by 28.1%.
  • Reported EBITDA margin improved from 35.7% in Q2 FY '25 to 36% in Q2 FY '26, while its PAT margin increased from 18.9% to 23.1% during the same period last year.
    Show source
    Our reported EBITDA margins improved from 35.7% in Q2 FY '25 to 36% in Q2 FY '26, while the PAT margin increased from 18.9% to 23.1% during the same period last year.
  • The company reported revenue of INR277 crores in H1 FY '26 compared to INR210 crores in H1 FY '25.
    Show source
    Looking at our half-yearly performance, we reported a revenue of INR277 crores in H1 FY '26 compared to INR210 crores in H1 FY '25.
  • Reported EBITDA margin was 36.0% and PAT margin was 22.7% in H1 FY '26.
    Show source
    Reported EBITDA margin was 36.0%, while PAT margin was 22.7%.
  • Energy and Oil and Gas segment contributed 81.5% of revenue on a half-yearly basis in H1 FY '26.
    Show source
    On a half-yearly basis, the contribution to revenue from Energy and Oil and Gas reported 81.5% .
  • Aerospace and Defence segment contributed approximately INR24 crores, or 16.9% of revenues, in Q2 FY '26, representing 34% year-on-year growth.
    Show source
    This segment contributed 16.9% of our revenues for Q2 FY '26 at INR24 crores approximately, representing a 34% year-on-year growth.
Show 12 more statements

Results

  • Aerospace and Defence segment reported an increase of about 30% in H1 FY '26 compared with H1 of FY '25.
    Show source
    Our half-yearly performance reported an increase of about 30% as compared to H1 of FY '25.
  • EBITDA was INR51.36 crores, with an EBITDA margin of 36.02%, in Q2 FY '26.
    Show source
    On EBITDA and EBITDA margin side, EBITDA stood at INR51.36 crores with EBITDA margin of 36.02%.
  • Raw material consumption reduced in Q2 FY '26 because of onboarding domestic suppliers and enhancing its supply chain.
    Show source
    Raw material consumption has reduced during this particular quarter because of onboarding of domestic suppliers and enhancing our supply chain excellence.
  • Employee cost experienced a slight uptick in Q2 FY '26, driven by ongoing expansion efforts and strengthening of its management team.
    Show source
    Employee cost experienced a slight uptick driven by ongoing expansion efforts and the strengthening of our management team.
  • Other income increased in Q2 FY '26 mainly due to interest income on fixed deposits from unspent QIP funds, contributing positively to the bottom line.
    Show source
    Other income increased mainly due to interest income on fixed deposits from the unspent QIP funds contributing positively to the bottom line.
  • Net profit was INR33 crores in quarter 2, a 57% increase compared with INR21 crores in quarter 2 FY '25, reflecting improved operational efficiency and revenue growth.
    Show source
    Profitability, net profit stood at INR33 crores, showcasing a 57% increase compared to INR21 crores in quarter 2 FY '25, this emphasis our improved operational efficiency and revenue growth.
  • Revenue from operation rose to INR277 crores in H1 FY '26, a 32.1% increase over H1 FY '25.
    Show source
    The revenue from operation rose to INR277 crores, making a 32.1% increase over H1 FY '25.
  • EBITDA margin improved to 36% in H1 FY '26 from 34.71% in H1 FY '25, driven by better cost management and optimized consumption.
    Show source
    EBITDA margin it has improved to 36% from 34.71% in H1 FY '25, driven by better cost management and optimized consumption.
  • PAT grew 65% in H1 FY '26.
    Show source
    PAT growth, a remarkable 65%, underscoring our financial strength and capacity to scale.
  • Receivable and inventory levels were in line with FY '25 based on annualized data in H1 FY '26.
    Show source
    On the working capital side, receivable and inventory level are in line with FY '25 based on annualized data.
  • The company was delivering 36% margin.
    Show source
    Page 14 of 20 Azad Engineering Limited November 03, 2025 Vishnu Malpani: No, we are already delivering 36% margin.

Money and capital

  • The company had deployed roughly about INR213 crores in capex so far.
    Show source
    So I think if you look at the deployment in capex, we've deployed roughly about INR213 crores so far that has been deployed.

What it expects ahead

What management expects

  • The company anticipates significantly stronger performance in the second half of FY '26 as production at its new facilities ramps up.
    Show source
    With production at our new facilities steadily ramping up, we anticipate a significantly stronger performance in the second half of FY '26 and remain confident in achieving as projected 25% to 30% top line growth for the year.
  • 25% to 30% growth guidance takes into account the massive demand it sees across each of its customers.
    Show source
    Page 10 of 20 Azad Engineering Limited November 03, 2025 So when we talk about our growth guidance and when our Chairman spoke about growth guidance of 25% to 30%, that is taking into account the massive demand that we see across each of our customers.
  • Incremental asset turn was expected to be in the range of 1.7 to 1.8, progressively taking it towards 2, based on its INR700 crores QIP raise.
    Show source
    But if you want to understand what is the kind of revenue potential that you will see basis the deployment, so you should look at our QIP raise of INR700 crores and look at the incremental asset turn that we are building for this business, which should be in the range of 1.7 to 1.8, right, and progressively taking it towards 2.
  • The company anticipates even stronger performance in the second half of FY26 and remains confident in achieving projected topline growth of 25% to 30% for the year.
    Show source
    With production at our new facilities steadily ramping up, we anticipate a significantly stronger performance in the second half of FY '26 and remain confident in achieving as projected 25% to 30% top line growth for the year.

What it is building and selling

Projects and capacity

  • The company expected to complete Phase 1 over the next 12 months, after which Phase 2 would start; its revenue guidance over the next 3 to 4 years was not dependent on the second facility coming in.
    Show source
    So we will be complete -- so over the next 12 months, we should be completing Phase 1, right?
  • The company inaugurated a new lean manufacturing facility for Siemens at its Hyderabad plant.
    Show source
    We recently inaugurated one of a new lean manufacturing facility for Siemens at our Hyderabad plant.
  • The company has three dedicated lean factories inaugurated at the new site.
    Show source
    With this, we now have three dedicated lean factories inaugurated at the new site.
  • The company is establishing a supply chain to facilitate raw material sourcing via its distribution network, aiming to resolve minimum order quantity challenges, improve procurement agility, ensure timely availability of raw materials and lower the inventory cycle.
    Show source
    The initiative aims to resolve the minimum order quantity challenge, improve procurement agility and ensure timely availability of raw materials with lower inventory cycle.
  • The company said it was on target to achieve all the operational milestones it had for the business. Replaced by a later filing.
    Show source
    So I would say that we are on target to achieve all the operational milestones that we have for the business.

Demand and pricing

  • Wallet share of customer spend across energy, aerospace and defence, and oil and gas is about 1% to 1.5%.
    Show source
    So our wallet share is only about 1.5%.
Show 8 more statements

Segments

  • Azad VTC Private Limited, Azad Engineering Limited's subsidiary, achieved NADCAP accreditation for coatings.
    Show source
    I'm also pleased to share that Azad VTC Private Limited, our subsidiary has achieved NADCAP accreditation for coatings.

Deals and partners

  • The company received Phase 2 of the contract with Mitsubishi to supply highly engineered complex rotating and stationary airfoils for advanced gas and thermal power turbine engines; the combined contract value with MHI now stands at INR1,387 crores.
    Show source
    With this expansion, the combined contract value with MHI now stands at INR1,387 crores, a strong testament to our technical excellence, our growing strategic relationship with the company.
  • The company signed Phase 1 of the Mitsubishi contract in November 2024 and inaugurated the facility in March 2025.
    Show source
    So if you look at Mitsubishi, we signed Phase 1 of the contract in November 2024. and then we inaugurated the facility in March 2025.
  • The company signed Phase 2 of the Mitsubishi contract a few weeks before the call.
    Show source
    And then now just a few weeks ago, we signed Phase 2 of that contract.
  • New facility will support and supply highly engineered complex rotating and stationary airfoils, along with critical components of assemblies and assemblies for advanced gas, industrial and thermal float turbine engines.
    Show source
    This state-of-the-art facility will support and supply of highly engineered complex rotating and stationary airfoils, along with critical components of assemblies and assemblies for advanced gas, industrial and thermal float turbine engines.
  • The company aims to meet Siemens Energy's global demand in the power generation and essential industrial sectors through the expansion.
    Show source
    Through this expansion, we aim to meet Siemens Energy's global demand in the power generation and essential industrial sectors.
  • The company has recently signed an MOU with Safran, providing a business opportunity to grow on the engine manufacturing side.
    Show source
    In aerospace and defence, along with the other initiatives, we've recently signed an MOU with Safran, which also gives the business opportunity to grow on the engine manufacturing side and affirms our credibility on the global stage.
  • The company was in the process of qualifying the Rolls-Royce aircraft engine component and would start some deliveries next financial year.
    Show source
    Next financial year, we'll start some deliveries.

Risks, rules and outside factors

Outside factors

  • Exports accounted for 93.9% of Azad Engineering Limited's revenue, and the company said its inflows and outflows provide a natural hedge.
    Show source
    So today, we can say 93.9%, to be precise, is exports.
  • The company has a cap of 5% fluctuation under its long-term contracts; it bears fluctuations of plus or minus 5%, and above that the customer either increases the price or asks its supplier to reduce the price.
    Show source
    So what we do is we have a cap of 5% fluctuation.
  • The company had not seen any impact from tariffs or proactive communications changing the way it was doing business, and its deliveries were lined up for the next 6 to 8 months with purchase orders in hand.
    Show source
    Our deliveries have been lined up for the next 6 to 8 months and purchase orders are with us.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Amit Dixit: Okay. Just a follow-up on this. Now since we are also seeing some of the companies coming up with aerospace-grade titanium and they are also getting qualified or in the process of getting qualified with the same set of suppliers. So do we expect that in aerospace as well due to the indigenous procurement, we can see this further coming down in future?

    Answer, rakesh chopdar

    Rakesh Chopdar: Hello Amitji, Rakesh this side. So the question on the super alloys, right? This is something quite tricky. Unless and otherwise, our OEMs agree to take that task of qualifying the supplier, we would love to buy the material domestic, but we are bound to go through the process. The OEM -- we should have a clearance from our OEM that we can buy the material from the local -- the indigenous material. So we are in talks with our OEMs so that we can propose these Indian mills and then we can see that. We look forward to it.

  2. Question

    Amit Dixit: Great. The second one is essentially on Safran MOU, again, a big step, I would say. So does it mean that now we are qualified with all the -- sorry, I mean, we have an MOU/ contract with almost all the global manufacturers because I believe only Safran was missing from that list that you had. So what does it mean for us in terms of domestic ecosystem? If we look at it, Safran is getting quite active procuring material for both the LEAP-1A, LEAP-1B engines. Also, Safran is one of the front runners for AMCA engine program. So how do we see this going forward with Safran? Page 6 of 20 Azad Engineering Limited November 03, 2025 And the part B of the question is that with AMCA now get

    Answer, rakesh chopdar

    Rakesh Chopdar: Okay. So on the Safran, yes, this is the first relationship kicked off with Safran. And as everyone is aware, Amitji, that Azad is specialized in the finish of the engines, the rotating and stationary components. And if you try to see getting the recognition from these large OEMs, so the first OEM which we could break in was the Rolls-Royce. We got into both commercial as well as the defence engine programs. And that thing, we initiated the discussion initially. We had an assessment.

    Answer, rakesh chopdar

    We signed MOU, then we -- technical assessment happened and then we got into the contract. So this is a basic step which everyone has to follow. So with Safran, this is the second step. The assessment is done and MOU is signed. And definitely, this is one of big breakthrough, which is going to get ultimately turned into a contract. Right? That's with Safran.

    Answer, rakesh chopdar

    And there's one more OEM, which we are expecting very soon for a similar part, the pattern which we would like to get into. So as you rightly said, all the major OEMs, we should have it very shortly.

  3. Question

    Amit Dixit: Okay. And the involvement in the domestic engine ecosystem?

    Answer, rakesh chopdar

    Rakesh Chopdar: Sorry, yes. So yes, you're right. We are in discussions with a couple of OEMs for sure, for particularly the project you mentioned. And we are having very advanced discussions, which we are very hopeful to get into -- we are already engaged with them, to b e honest with you, we already engaged with them. And I think the way it will go because it's not really sure, it's the engine with AMCA has gone to Safran or Rolls -Royce or we are not sure. And either ways, all the OEMs are with us. It doesn't matter wherever it goes for Azad's prospective for AMCA, whet her it's Safran or Rolls -Royce or anyone else, we are there in the race with all the 4 OEMs.

    Answer, rakesh chopdar

    Amit Dixit: Great. That's nice to know. Just a follow -up on this, sir. This Safran MOU, you mentioned that the assessment has happened. So typically, how much time it will take for you to get the final contract?

    Answer, rakesh chopdar

    Rakesh Chopdar: Very soon, Amitji, very soon, not only with Safran, other OEMs also, you will come to know very soon about more details as this is a defence application program. So I cannot speak much on this.

  4. Question

    Like in the FY '24 earnings call, management has guided that FY '26 would be a big shift and an inflection point for revenue growth. And more recently, in the Q4 FY '25 and Q1 FY '26 calls, the commentary has shifted to describing FY '26 as years of stabilization, consolidation. So with the ramp-up being -- and with the ramp-up being challenging and shift expected after this stabilization is complete. So could you help us reconcile this change?

    Answer, rakesh chopdar

    Rakesh Chopdar: Yes. Jai, I think we are very consistent in the guidance what we are giving, and we are very consistent in the achievements what we are achieving versus the guidance. And if you see the last not one, two, you can see many quarters. And the guidance versus the achievements are definitely matching. Now coming to the growth trajectory, it's just December '23 is we have done the IPO. And technically, it's been hardly 17, 18 months, we have the fund and the amount of what's been happening on trying to build these facilities, okay, the facilities which we are building are massive. They are not something small like we add 5 machines, 10 machine or 50 machines.

    Answer, rakesh chopdar

    That facility is coming what we are, to be honest, is 10x what we are in. So, if we try to just build the infrastructure of 500,000 to 600,000 square feet, that itself takes not less than -- if you go super speed, not less than 2 to 3 years. But we appreciate -- I appreciate my team, which is parallelly taking care of the existing growth, parallelly taking care of the machines and planning, parallelly taking care of the constructions of the facilities. And this is a huge amount of work which happens. And if I talk about the time line, I think the team has done a great job in such a short time, they inaugurated three facilities and stabilizing them, getting the machines inside, arranging the manpower. And we are not talking about two-digit things. We're all talking three digit.

    Answer, rakesh chopdar

    If you talk about manpower or square feet or the construction or the machines and everything is an important stuff where we have to find the logistics, the 5-axis machines, the training program. And it's not -- it's a big marathon task, which is happening. So in this context, we would say we are struggling at the moment to manage the growth, to manage the facilities, to manage the customers, to manage the contracts, quite a job. That's the reason we mentioned that the team is doing a great, great, great job. So the stabilization means all these activities as these are all -- it doesn't continue all long. Once for all the factories will be done, once for all the machines will come and then we finish up and then we go ahead with the productions and then we call, okay, we are now stabilized. Page 8 of 20 Azad Engineering Limited November 03, 2025 Jai Chauhan: Understood, sir.

  5. Question

    Makes sense. So is it fair to say that full nonlinear growth impact from the new capacity is now more of an FY '27 story with FY '26 being, year focused on commissioning of this new dedicated lean factories?

    Answer, rakesh chopdar

    Rakesh Chopdar: Yes. So, Jai, this is not -- again, this is a parallel activity going on. Whatever value-add creation happens, it's just supporting -- it's just supporting the stresses, which is being made within the team where we all are working 24/7 to stabilize the new facility, to stabilize the existing growth, to stabilize the existing facility here, right? So everything is going in parallel. That's a beautiful planning happened in Azad. In such a short time, I request you to please visit us and then you can imagine the amount of work being done, and it is substantially great. We are building one of the world's best Best factory, the most innovation center you can see highly -- you will see some great technology under the roof built in such a short time, which is really, really remarkable.

    Answer, rakesh chopdar

    So I request you to please visit our new facility. You will have an idea what I'm speaking.

  6. Question

    Jai Chauhan: Sure, sir. We'll definitely try to set it up after this call. And sir, I have one more question on the contract part. So you have mentioned the margins are largely stable due to long-term contracts and fixed pricing with customers, but you have some exposure like to high-value alloys and foreign exchange fluctuations. So how does the company mitigate this raw material price volatility and currency risk? And is there any clauses or hedging mechanisms in place to protect.

    Answer, rakesh chopdar

    Rakesh Chopdar: So if you notice Azad's exports are 95% -- 94%, 95% and so hence, we have a natural hedge, okay? The inflows and outflows are natural hedge. And it's been years we have been working in this and 90% plus was always Azad's revenue was exports, right, from inception. So today, we can say 93.9%, to be precise, is exports. So the risk of that factory is always covered and it is covered.

  7. Question

    Jai Chauhan: But for the fluctuation in the raw material prices, do we have any clause for the sale?

    Answer, rakesh chopdar

    Rakesh Chopdar: Yes, we have. We have. So as I mentioned to Amitji also, he was the last question that we have approved sources from our OEMs. So we are only supposed to buy raw material from their approved sources. So when the price agreement happens, it is a tri-party price agreement, right? So we have no choice. We have to go to the only supplier they send us, correct?

    Answer, rakesh chopdar

    So they can dictate terms. So what we show is, okay, this is, say example, $10 or $1 a kilo price is fixed and the contracts are long term and we see a 5 year, 7 years contract. So what we do is we have a cap of 5% fluctuation. A 5% fluctuation, we write them, we tell them Azad is going to bear the 5%, absorb Page 9 of 20 Azad Engineering Limited November 03, 2025 5% fluctuation plus or minus, we'll do it. Above that, either you increase the price or ask your supplier to reduce the price. So that's also covered.

  8. Question

    Jai Chauhan: Understood, sir. Understood. And sir, also, like since you have long-term contracts with global OEMs, do these contracts include any termination or cancellation clauses as we invest a lot in our capex and we have a huge risk there. So is there any safeguard or lock-in mechanisms?

    Answer, rakesh chopdar

    Rakesh Chopdar: Every contract has that. Every contract has you know, that we can cancel. So if you don't perform, definitely, they can cancel the contract, right? Yes. So these are very standard contracts, which are favouring both of them. It's a win-win situation for both. And we are talking with the large OEMs.

    Answer, rakesh chopdar

    There are some companies which we see every day, okay? We -- if you see our customer base, they are like very reputed companies, right? So, they honor and we also honor what they do to an extent. It's not new to us now, right? So we have some history with every OEM, and they have their own experience.

  9. Question

    Jai Chauhan: Understood, sir. And sir, one on the product side. We are mostly in the compressor airfoils, you would say, right? And the company is part of --.

    Answer, rakesh chopdar

    Rakesh Chopdar: Not exactly. We started with that. Now we have expanded our portfolio in and around the entire engine. So compressor, combustion, exhaust, we are there everywhere.

  10. Question

    Jai Chauhan: So because I think we are not in single crystal blades, right, which is in the Stage 1 of the...

    Answer, rakesh chopdar

    Rakesh Chopdar: No, not yet Moderator: The next question is from the line of Vikash Singh from ICICI Securities.

    Answer, vishnu malpani

    Vishnu Malpani: Yes. Thank you, Vikashji, for the question. So if you look at our wallet share with respect to our customer spend, whether it is energy, aerospace and defence and oil and gas, we are at about 1%, 1.5% of where if we could be. So our wallet share is only about 1.5%. So the headroom for growth is definitely massive which is also visible in the contracts that we're signing, right? So if you look at Mitsubishi, we signed Phase 1 of the contract in November 2024. and then we inaugurated the facility in March 2025. And then now just a few weeks ago, we signed Phase 2 of that contract.

    Answer, vishnu malpani

    This is a clear sign that the demand for the products that Azad is making is very, very high, and this should continue for a longer period. Page 10 of 20 Azad Engineering Limited November 03, 2025 So when we talk about our growth guidance and when our Chairman spoke about growth guidance of 25% to 30%, that is taking into account the massive demand that we see across each of our customers. And one of the reasons we are building dedicated plants is because each of these customers can take us to the consolidated revenues that we are delivering as a business over time.

Show 10 more questions
  1. Question

    Vikash Singh: Noted. And sir, these plants that you have commissioned right now, so can you just give us the peak utilization time lines for the already existing commissioned plant and the next three or four sheds which are -- would be coming?

    Answer, vishnu malpani

    Vishnu Malpani: So this is something that's happening in parallel, right? So while the existing facilities that have been inaugurated are getting operational and the facility that has been operational is ramping up production. So our sense is that over the next about 12 months, we would want to finish the entire plant in terms of construction, including move our manpower base to there. We are building a housing colony for our employees so that we are able to stabilize operations there. So in about 12 months, infrastructure should be up and running. And then slowly after that, you will see each of the plant reaching its max capacity, right? But this should happen progressively.

  2. Question

    Vikash Singh: So should we take 18 to 24 months as a peak utilization for the new plant?

    Answer, vishnu malpani

    Vishnu Malpani: I would urge you to look at it from a revenue guidance perspective and not from a utilization perspective. So I would urge you to think of our business from that and look at 30% -- 25% to 30% growth year-on-year across our segments and then you'll be able to derive it, which is very, very good, right? So -- and we've maintained the guidance. We've beaten our guidance. So don't look at it from a utilization of capacity perspective, look at it from this perspective, otherwise, because we are working on different product lines, different machines. So if you look at it from a utilization perspective, it may not give you the correct direction, but look at it from a revenue guidance that we've shared with you.

  3. Question

    Vikash Singh: Any update on that forging plant basically?

    Answer, vishnu malpani

    Vishnu Malpani: So yes. So out of the sheds that we've inaugurated factories that we've inaugurated for customers, there were 3 factories, one for Siemens, Mitsubishi and one for GE Steam. We've also had our forging plant, which is already in operation partly. So we are setting that up. And while the other plants get operational, this should also come up. Page 11 of 20 Azad Engineering Limited November 03, 2025 So there are a few equipment that have been installed, deployed and are running and the others are work-in-progress. See, we are trying to -- it is important that everybody appreciates that this is a very complex project management exercise, right?

    Answer, vishnu malpani

    Mr. Chopdar touched upon it. We are building factories which are 10x the size. We are deploying machines which are equivalent to what we have. We are hiring people, training them, ensuring that our machines are not idle. And all of this have to move parallelly while we have to grow at 30%, 35%, we have to not compromise on our margins. So this was a pretty complex project management, and I think we should credit Azad's vision and execution for it. So I would say that we are on target to achieve all the operational milestones that we have for the business.

    Answer, vishnu malpani

    And this is massive, right? You've seen the facility firsthand to see the scale that we are looking at.

  4. Question

    Rakesh Roy: My first question is related to the Siemens plant. As you mentioned, your Siemens plant is already completed. So can we expect number from Q4 or Q1 next year?

    Answer, vishnu malpani

    Vishnu Malpani: Thank you for your question. I think we attempted to address it in the last call as well -- in the last question as well. See, we are inaugurating plants, deploying machines and slowly ramping up production. So obviously, in the H2 of this year, there will be contribution that you will see. But to what extent we'll be only able to talk about it in the next quarter, right? Because the machines have -- are in the process of getting deployed and employees are being deployed in that. But we will hit our revenue guidance that we've spoken about.

    Answer, vishnu malpani

    We've already delivered INR277 crores, and we are on -- if you look at our ARR, we are on an ARR of about INR577 crores today. So we should look at it, whether it comes out of the Siemens facility or the other dedicated facilities, we should hit our revenue guidance.

  5. Question

    Rakesh Roy: Regarding Safran MOU, what product we are going to make and how much time it takes to validate the product from the Safran side? Page 12 of 20 Azad Engineering Limited November 03, 2025 Rakesh Chopdar: Actually, Safran is a defence division.

    Answer, rakesh chopdar

    So we can't reveal any more details on the -- as it's a defence project for Safran, it is a defence military engine. So we can't -- we are not supposed to speak to anything like that.

  6. Question

    Rakesh Roy: Okay. And how much is time take to validate the product or same thing. Is it titanium or superalloy product, sir?

    Answer, rakesh chopdar

    Rakesh Chopdar: We can't reveal anything. Sorry for this, but it is a defence thing, and we have signed an NDA with them.

    Answer, vishnu malpani

    Vishnu Malpani: See, I think the point -- so Mr. Rakesh, I think the point that you need to look at is, I think from an opportunity perspective, Azad today has relationship with all the engine -- aero engine manufacturers globally, right? And so that is important. And we are also, like we said, we operate in highly engineered and critical parts, which are mission and life critical. So we are going to be making critical parts for their platform. So this is an opportunity that will obviously convert from MOU to contract, qualification, production and then ramp up. So this is the normal cycle of how every OEM's journey happens with a supplier like Azad. So it should follow the same thing.

    Answer, rakesh chopdar

    Rakesh Chopdar: Another point I would like to add, please make a note on these engines. These engines are not an easy subject. These engines are the heart of an aircraft, whether it's a military or a civil. If these giants are signing up with Azad, definitely, it's a big validation. That's the key. That's the key. Once these validations, it's a big validation of companies like Safran or Rolls-Royce coming in, working with Azad for these life critical components, it's one of a big thing.

    Answer, rakesh chopdar

    It's one of a big thing. And definitely, they find value in that. Definitely, they find the capability. That's the reason we are there in the picture. So when we talk initially what you signed up and how much time it takes, this is not -- this is the point where this takes a lot of time -- it takes a lot of time to get these products in the engine. It doesn't just -- we have a contract and we just start supplying the parts like that because this business is different. They have a lot of qualifications in it.

    Answer, rakesh chopdar

    There are a lot of approvals involved in this. So it takes its own time. So I request you, gentlemen, so please visit us, and we can show you more in detail.

  7. Question

    Rakesh Roy: It's 5-year contract. Or any idea to get third phase also from Mitsubishi? Page 13 of 20 Azad Engineering Limited November 03, 2025 Rakesh Chopdar: As we ramp up capacity, we are always open.

    Answer, vishnu malpani

    Is there room further for margins to improve from here on or the... Page 14 of 20 Azad Engineering Limited November 03, 2025 Vishnu Malpani: No, we are already delivering 36% margin.

    Answer, vishnu malpani

    Vishnu Malpani: So thank you for the question. So I think if you look at the deployment in capex, we've deployed roughly about INR213 crores so far that has been deployed. But if you want to understand what is the kind of revenue potential that you will see basis the deployment, so you should look at our QIP raise of INR700 crores and look at the incremental asset turn that we are building for this business, which should be in the range of 1.7 to 1.8, right, and progressively taking it towards 2. So if you look at that deployment over the next few years, you should be able to understand what is the kind of revenue potential that the business would have with this deployment. Koushik: Sir, please correct me. Am I right by assuming that 2,500 will be the total top line that we can achieve with the total capex that we are into?

    Answer, vishnu malpani

    Vishnu Malpani: I mean I would urge you to do the math yourself at 25% to 30% growth year-on-year from here and look at the asset turn deployment of INR700 crores at 1.7x, 1.8x, and you will get the number. So I would not want to talk about what is the number because we are not giving any other guidance, but 25% to 30%, and you should be able to get your answer there. Page 16 of 20 Azad Engineering Limited November 03, 2025 Koushik: Got it.. Thanks for that. And second thing, sir, like also, there was another question on that, the GTRE engine part. So once we have this engine completely coming into our existence, what kind of orders that we can see or like what is this specifically mean to India as a country and what Azad will be getting benefit out of it completely?

  8. Question

    Jainis Chheda: Yes. I just wanted to ask in terms of tariffs, if you can throw some light as to how are they affecting you, if at all? And what are the countermeasures that you are taking?

    Answer, vishnu malpani

    Vishnu Malpani: So, thank you for the question. I think we've addressed this before. Tariffs as a situation has been ever evolving either for both for our customers and for us. We haven't seen any impact or proactive communications that is changing any -- that is changing the way we are doing business today. Our deliveries have been lined up for the next 6 to 8 months and purchase orders are with us. So, we are not seeing any change from that perspective, right? And you anyway know our price differential between Azad and the country.

  9. Question

    Nishant Agarwal: The first phase...

    Answer, vishnu malpani

    Vishnu Malpani: Yes. So we will be complete -- so over the next 12 months, we should be completing Phase 1, right? And then post which Phase 2 will start. But any revenue guidance that we're giving over the next 3 to 4 years is not dependent on the second facility coming in.

  10. Question

    Nishant Agarwal: Okay. And how are we on the Rolls-Royce aircraft engine component, what the order that we have got. So when are we going to start production for that?

    Answer, vishnu malpani

    Vishnu Malpani: So we are in the process of qualification. Next financial year, we'll start some deliveries.

Questions about this call

When was the Azad Engineering Q2 FY26 earnings call transcript filed?
Azad Engineering filed the transcript with the exchange on 8 Nov 2025. This page is built from that transcript.
What does this page list?
39 statements from the transcript across 8 topics, 29 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 20 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.