Earnings call
EMS Q3 FY26 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
About half of EMS Limited's order book of about Rs.1,150-odd crores was procured in Q2 and Q3, respectively, and was in the design phase, where expenditure was being incurred but no revenue could be generated until site execution began. The company said its PAT may remain around 15% as an average for this year, rather than matching the 18%-19% PAT of previous years, because competitiveness was increasing. The company had started pre-engineering on projects of around Rs.1,100 crores; engineering was in the approval phase and could take another month or so before revenue generation began when work started in the field. Uttarakhand saw unexpectedly huge rainfall and natural disasters in Q2, and the extension of the monsoon into Q3 resulted in the company losing about 15-to-20 days; the company mainly focused on repair and revamping work in progress in Q3, with additional time lost to remobilization and repair of executed works. The company expects its flex sheet and paper business to generate a profit of about 5% over revenue.
The numbers management gave
Results
- Uttarakhand saw unexpectedly huge rainfall and natural disasters in Q2, and the extension of the monsoon into Q3 resulted in the company losing about 15-to-20 days; the company mainly focused on repair and revamping work in progress in Q3, with additional time lost to remobilization and repair of executed works.
Show source
So, in Q3, our work was mainly focused on repair and revamping of the work-in progress and due to extension of the monsoon to Q3, about 15-to-20 days were lost in the Q3, and after that, when the work resumed, a lot of time was lost to remobilization and repair of the executed works.
- The company incurred expenditure against 50% of its order book at the design and engineering stage but could not book receivables or bill the department; expenses included mobilization, site establishment and procurement of raw materials, and management said subsequent billing would allow revenue to be billed against expenditure already carried out and improve margins.
Show source
But we have to book expenses in mobilization, site establishment, procurement of raw materials, etc., So, going forward, in the next quarter, as the billing starts, we will be able to bill revenue against the expenditure already carried out.
- The company said it would get more than 15% or at least 15% for this financial year, and that its PAT was 15.86% on a nine-month basis.
Show source
So, on a nine-month basis, it is still 15.86% PAT.
- About Rs.800-odd crores in excess of EMS Limited's work order came from Uttarakhand, where the company expected to book a major portion of revenue; the work involved digging up roads and laying pipelines, but unexpected heavy rainfall, landslides and natural disasters in Q2 and prolonged government disaster management prevented execution and revenue booking in the state.
Show source
Due to unexpectedly heavy rainfall and the landslides and natural disasters that took place in that state in the Q2, we expected it to recover by Q3, but the disaster management taken up by government that took some time more than what we expected and we could not execute or book revenue in that state.
- The company maintained growth of 20% in 2023 after falling in 2021 and 2022 following COVID, and covered the shortfall over an eight-year span.
Show source
But we maintain the growth of 20% in 2023 and we covered it up of the eight years span.
- The company did not meet expectations for PAT in this quarter.
Show source
So, as closing comments, definitely we could not meet the expectation in this quarter as a result in PAT.
Show 8 more statements
Money and capital
- The company said it takes 60-days-to-120-days, averaging 90 days, to receive receivables after expenditure, and that it requires three months of working capital; for Rs.1,000 crores turnover it mostly requires Rs.250 crores of working capital, less 20% EBITDA, or about Rs.20 crores to have on hand.
Show source
Say Rs.1,000 crores turnover, so we require mostly Rs.250 crores as a working capital, minus 20% EBITDA, that is about Rs.20 crores we have to have in our hands as a working capital.
- The company is committed to reduce its loan against shares from Rs.210-odd crores borrowed from NBFCs to 100 crores by the end of this quarter; it has paid Rs.70 crores.
Show source
We are committed to bring it down to 100 crores by end of this quarter.
- Borrowing reached Rs.210 crores and has been reduced to Rs.140 crores; it has repaid about Rs.70 crores of principal along with interest, plans to reduce principal to less than Rs.100 crores by the end of this financial year, and plans to repay the whole amount in the next financial year.
Show source
And we are planning to reduce the principal amount to less than Rs.100 crores by the end of this financial year and repay the whole amount in the next financial year.
- The company said its working-capital figure fluctuates quarter by quarter because civil engineering projects on the ground can face problems such as unclear land and rainy-season impacts.
Show source
But this figure fluctuates a lot quarter-by-quarter because civil engineering projects on ground, they may face so many problems.
- Factory is self-sufficient and does not require funding from the company.
Show source
It does not require any funding from the company.
- The money borrowed against the pledged shares was used to invest in lands and properties.
Show source
Harish Kumar Kansal: So that money was used to invest in lands and properties.
- The promoter pledged shares to start a real estate business.
Show source
Ashish Tomar: Yes, to start that is for a real estate business.
- The pledged shares can be released only after EMS Limited repays the whole borrowed amount. Replaced by a later filing.
Show source
The shares that are pledged with can only be released after we repay the whole amount.
What it expects ahead
What management expects
- The company said its PAT may remain around 15% as an average for this year, rather than matching the 18%-19% PAT of previous years, because competitiveness was increasing.
Show source
So, it may remain around 15% as an average for this year.
- For FY26, EMS Limited expected PAT to be above 15% and EBITDA in excess of 22-23%.
Show source
EBITDA in excess of 22-23%.
- The company said it would maintain PAT of about 17%-18% in the future, as it had done over the company's 10-11-year history.
Show source
And otherwise, for the next thing, we will remain about 17%-18% of the PAT as we have done in the history of the 10-11 years of the company's history.
- The company said it would grow by about 40%-50% as per its order book.
Show source
We will grow by about 40%-50%.
- The company said Q4 would be better than Q3, and that it would make strong progress in Q1 of the next financial year because its order book in design and pre-engineering phases would generate revenue.
Show source
But, if you will compare it after the Q4, then Q4 will definitely be better than Q3.
- The company said Q4 would be better and that in Q1 of the next fiscal year it would overtake the previous year.
Show source
And Q1 of the next fiscal year, we will overtake it, definitely from the previous year.
Show 8 more statements
What management expects
- The company said heavy rain and disasters led the administration responsible for development work to prioritize disaster restoration, stopping the company's work at times; management said the current quarter would be much better and that the company would outpace Q1 of the next financial year.
Show source
Otherwise, we assure you that this quarter will be much, much better, and we will definitely outpace from the Q1 of the next financial year.
- The company will revamp its performance in this quarter and expects high growth in the first quarter of the next fiscal.
Show source
And we will definitely revamp it in this quarter and the first quarter of the next fiscal, we will see high growth and everything will be perfectly matched.
- The company said it would be back on track from the next quarter of the financial year. Replaced by a later filing.
Show source
Apart from that, we would like to reassure you that from the next quarter of the financial year, we would be on our path to recovery and would be back on track.
- The company said it thought it could resume its overall business pace by the next quarter. Replaced by a later filing.
Show source
But, on overall business side, we think we can resume our pace by next quarter.
- The company is confident it will make up for unmet expectations next year if it cannot meet them this year. Replaced by a later filing.
Show source
And next year we will do the cover up of the whole things.
Orders
- About half of EMS Limited's order book of about Rs.1,150-odd crores was procured in Q2 and Q3, respectively, and was in the design phase, where expenditure was being incurred but no revenue could be generated until site execution began.
Show source
Along with that, almost half of the order book that we currently have about Rs.1,150-odd crores, was procured in Q2 and Q3, respectively.
- The company has an order book of more than Rs.2,200 crores as of now and expects it to increase by up to Rs.3,000 crores in Q1 of the next financial year; it expects Rs.1,000 crores of orders, which may arrive in the first or second week of April because bidding can be litigated.
Show source
So, we have bidded, but we are expecting the order book to increase by up to Rs.3,000 crores in the Q1 of the next financial year.
- Order book is expected to be around Rs.3,000 crores in Q1, after it can exhaust almost Rs.200 crores of its Rs.2,200 crores order book in this quarter.
Show source
So, in Q1 we will definitely have the order book of around Rs.3,000 crores because Rs.2,200 crores, and in this quarter, we can exhaust it by Rs.200 crores almost, and of course we can have Rs.3,000 crores in Q1 of the next financial year.
What it is building and selling
Projects and capacity
- The company had started pre-engineering on projects of around Rs.1,100 crores; engineering was in the approval phase and could take another month or so before revenue generation began when work started in the field.
Show source
So, we have now started our pre-engineering in certain projects, that is of around Rs.1,100 crores projects.
- The company said Rs.1,100-1,200 crores of new projects were falling in the current and previous quarters, and that projects took around four to five months to generate revenue, with revenue starting after four, five or six months.
Show source
And eventually, this is the cycle that Rs.1,100-1,200 crores new projects are falling in this quarter, previous one and this one.
- The plant is producing about 800-900 tons of output and may reach output of about 1,100-plus tons in the coming financial year.
Show source
And it can reach an output of about 1,100-plus tons in the coming financial year.
- Four big projects came in the current quarter, compared with one project in one quarter and two projects in another quarter previously.
Show source
And Page 3 of 12 now the four big projects have come in this quarter only.
Segments
- The company expects its flex sheet and paper business to generate a profit of about 5% over revenue.
Show source
We initially were not enthusiastic to run it, but since it was a running factory, when we realized that it can give us a profit of about 5% over revenue in that business also.
- The company will keep running the factory but would not invest further money if its profit starts to decline.
Show source
But we would not invest any further money if it starts to decline.
Everything else said on the call
Group structure
- The company took a factory from NCLT as collateral with banks against its non-funding bank guarantees, and the factory came with land.
Show source
As we have already clarified this in previous calls also, we took that factory from NCLT to put it as collateral with banks against our non-funding bank guarantees, etc., So that land came with an established factory.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
C.A. Garvit Goyal: Good morning to the team. My question is specifically to Mr. Kansal. In the opening remarks, management is saying we face some challenges up to 15-days of Q3. But at the same time, in the last con call when we spoke to Mr. Kansal, Mr. Kansal said, October month delivered very good execution in terms of executing the project. So, where is the difference? I am not understanding. Last con call, people were very confident and now you are saying there were some issues in Uttarakhand and we were not able to deliver the project. So, where is the gap, sir? Your own words are not matching this con call and the previous con call.
Answer, harish kansal
Harish Kumar Kansal: Okay. I got your point and I am H.K. Kansal speaking again. Actually, in last con call, we thought that we will cover it up in two months, particularly in November and December. But in civil works and on the road works, there was some disaster management also in Uttarakhand and the administration is also with us. Because administration always directs that this work has to be started now after the security and safety of the citizens. So, definitely we started in first, second week of October, but it could not be with that pace which we wanted basically to cover up the things.
Answer, harish kansal
So, it got a bit late. And second thing, as far as revenue generation is concerned, out of those Rs.2,200 crores order book, we could start the work of about Rs.1,100 crores in Page 2 of 12 Calcutta, Ayodhya, Agra and Fatehpur, which was started in mid of October for design investigations and all other things and slight procurements also. So, we have done the expenditure on these projects of Rs.1,100 crores, but there was no milestone achieved for which we could achieve the receivables or could receive the revenue. That is why revenue received is definitely less. And margins are even in more pressure because expenditure is done and the receipts could not be made. So, that happened. And in civil engineering, this is not a simple industry basically.
Answer, harish kansal
It depends upon so many things. So, we could not do that. And it is definitely not as per our expectations, not as per your expectations. And let me tell you again that company is not in any type of financial distress or any order book distress or anything. But this is just a phase of time that in the quarter-ended December '25, we could not perform as we thought and we assured you in the last con call. And again, we are assuring that in this quarter, we will try to cover certain things. But definitely, now, we are of the opinion that in two months or something, we will not be able to cover up to that extent.
Answer, harish kansal
But, if you will compare it after the Q4, then Q4 will definitely be better than Q3. And Q1 of the next financial year, we will definitely progress very hard, because our order book which is under design and pre-engineering phases, we will definitely develop a lot of revenue from that. So, I think this is the explanation which I can give. And this is from the management side.
Question
C.A. Garvit Goyal: When you say Q4 will be better than Q3, Q3 is already, I would say, like a very lower level, right? So, even if it is a normal application, that will look like it is better than Q3. So, can you put a number to it like whether the situation has improved now? From when the situation was improved, from when the recovery started, is it from the January month or from the February month, can you give some color on that?
Answer, harish kansal
Harish Kumar Kansal: Yes. Actually, there are two things. If we compare Q4, Q3 from the last Q3, that is QoQ, then we are definitely not to the expectation. As far as PAT or EBITDA is concerned, this is in line with the industry, but this is not in line with our records. Actually, we have done in last 10-years PAT around 18%, 19% or 20%, EBITDA 26%, 27%, which is not in that line. Still, if you compare it with the other peers, that is in line with the other companies. But not as per our expectation… definitely not.
Answer, harish kansal
So, we have now started our pre-engineering in certain projects, that is of around Rs.1,100 crores projects. Engineering is in the approval phase, but it may take another one month or so. And then we will start generating the revenue, because once the work will come in the field, then the revenue will be generated. So, Q4, we will get better. And Q1 of the next fiscal year, we will overtake it, definitely from the previous year. So, we are a bit conservative for that, because we are not giving any aggressive guidelines for this quarter. Again, because this is civil engineering work, it takes time to revamp for pre-engineering.
Answer, harish kansal
And eventually, this is the cycle that Rs.1,100-1,200 crores new projects are falling in this quarter, previous one and this one. So, that takes around four, five months to give the revenue. Otherwise, expenditures are always there for soil investigations, for design, surveying and everything. And revenue starts coming after four, five, six months. So, previously what used to happen, one project has come in one quarter, two projects have come in another quarter. And Page 3 of 12 now the four big projects have come in this quarter only. So, this is looking like that.
Answer, harish kansal
But we are very sure that we will not disappoint any of you or any of us. And we will definitely do whatever we are committing. But next quarter will not cover the hope the entire thing of the whole year. So, it will start aggressive cover up from the Q1 of the next fiscal and covering in the Q4 also in comparison to Q3 of this year. Thank you.
Question
Kaushal Sharma: Can you please tell me what is the current order book as of December 2025 and what kind of order inflows are we expecting in next one, two years to the target?
Answer, harish kansal
Harish Kumar Kansal: Unexecuted order book is around Rs.2,200 crores as of now.
Question
Kaushal Sharma: And what kind of order inflows are we expecting going ahead?
Answer, harish kansal
Harish Kumar Kansal: We are very aggressively bidding now. Because Delhi Jal Board had started tenders, you must be knowing, and we are bidding in about Rs.2,000 crores tenders in Delhi Jal Board and other places. So, we are expecting it to enhance in next three, four months by about Rs.1,000 crores.
Question
Kaushal Sharma: And what is our winning ratio on an average?
Answer, harish kansal
Harish Kumar Kansal: Actually, our winning ratio used to be 10-15%, but as competition is increasing, we have become a bit aggressive for that, and we are planning to get our win ratio enhanced up to 20%. And we are still bidding and bidding in every place. So, Rs.1,000 crores we are expecting in next three, four months to achieve the order.
Question
Kaushal Sharma: And sir, as you said that there was a challenging phase in Q3. But if I compare Q2 to Q3 performance, the sales grew around 15%, but our cost of raw material grew around 25%, and the other expenses grew 34%. So, could you please highlight what kind of key expenses and other expenses grew a lot more than sales growth and the cost of raw material?
Answer, harish kansal
Harish Kumar Kansal: As I told you, there are three, four phases of any project. Once the tender is awarded, agreement is made, then the extensive surveys are started. And certain procurements, certain Page 4 of 12 vendors are decided. So, on site, certain deployment of the employees has to be done for proper monitoring and liaising with the government agencies. So, there are expenses in investigations, surveys, and we have to start some procurement also, which are the delayed things. For example, I have to lay the 100-Kms sewer line. So, 100-Kms procurement of pipe or manholes, I cannot make in a single step.
Answer, harish kansal
So, we start doing it after tentative finalization of the designs. But, for that, that is not a milestone in the eyes of the government authority. So, the payment does not come as a revenue or even as a receivable. Because there are certain milestones, though it is an item rate contract, but certain items have to be executed. So, it is not converted. So, expenditures are shown, expenditures are apparent in the balance sheet or in the account. But receivables are not.
Answer, harish kansal
That is why our EBITDA and PAT has impacted that much. So, this will recover. But definitely, it will not match with that 18%-19% PAT as in the previous years because competitiveness is increasing definitely. So, it may remain around 15% as an average for this year.
Question
Kaushal Sharma: But the expenses booked in the P&L is again the sales that you executed and booked in the particular Q3. So, the expenditure pertaining to that sales should be recorded in the P&L. So, that is why I am asking. The sales growth is 15%. But your cost of raw material and other expenses grew faster than sales.
Answer, ashish tomar
Ashish Tomar: That is because some expenditure was done against 50% of our order book, which is at the stage of design and engineering. So, we cannot book receivables or bill it to the department. But we have to book expenses in mobilization, site establishment, procurement of raw materials, etc., So, going forward, in the next quarter, as the billing starts, we will be able to bill revenue against the expenditure already carried out. And that would also lead to improvement in the margins.
Question
Kaushal Sharma: So, what kind of EBITDA margin we are closing in this financial year, what is our expectation in terms of EBITDA and PAT for FY26?
Answer, ashish tomar
Ashish Tomar: For FY26, we expect it to be above 15%. That is PAT. EBITDA in excess of 22-23%.
Question
Kaushal Sharma: 22%-23%. And what is our current trade receivable as of December 2025? And what is the portion of more than six months? And the ratio of unbilled revenue as well showing in the balance sheet?
Answer, ashish tomar
Ashish Tomar: So, the unbilled revenue is about Rs.283 crores.
Question
Kaushal Sharma: And more than six months, sir? Page 5 of 12 Ashish Tomar: Almost Rs.120-odd crores is less than six months.
Answer, ashish tomar
And other than that, it is more than six months out of Rs.500 crores.
Show 13 more questions
Question
Kaushal Sharma: It is quite heavy in our trade receivables. Are we expecting any provisioning or something or any challenge, are we expecting over there?
Answer, ashish tomar
Ashish Tomar: That was a mistake on my part. The Rs.500 crores is the total sum of all the receivables. That includes unbilled and billed also. So, the unbilled portion is Rs.283 crores. Less than six months is about Rs. 116 crores. Six months to one year is about Rs. 23 crores. One year to two years is about Rs.87 lakhs.
Question
Udit Mittal: So, I just wanted to enquire about your interest cost. I was looking that your interest costs have gone up significantly higher. So, what is the level of current debt and what is the borrowing plan going forward? Is the company facing any working capital issues?
Answer, ashish tomar
Ashish Tomar: So, the interest costs have ballooned because of a loan of about Rs.25 crores that we took against the HAM project that is in Mirzapur Ghazipur STPs Pvt. Ltd. which is a subsidiary of EMS Ltd. So, that was a HAM project for which we have taken this loan. So, that would have led to escalation in the interest costs.
Question
Udit Mittal: And what is the level of current debt?
Answer, ashish tomar
Ashish Tomar: So, that would be around Rs.700 crores is our exposure to the banks which includes Rs.650 crores of non-fund-based bank guarantees, and about Rs.50 crores in shape of cash credit limit and this loan that I told you about.
Question
Udit Mittal: So, any plans of further borrowing or something like that?
Answer, harish kansal
Harish Kumar Kansal: No plans on expanding in our borrowings. The facilities that we have are sufficient for execution of our projects.
Question
Udit Mittal: One more thing I just wanted to know. Recently, you had given a disclosure of the promoter holding getting pledged. So, what was the reason of the pledge and is there any timeline to reduce the pledge?
Answer, ashish tomar
Ashish Tomar: So, we took loan of about Rs.210 crores, out of which we have already paid about Rs.70 crores and the current outstanding stands at Rs.140 crores. Within this financial year, we will reduce it to about Rs.100 crores, and by next financial year, this would be settled. So, this was secured Page 6 of 12 to make some investments in the promoter side. No company funds were involved in this. The loan was in personal capacity only.
Question
Udit Mittal: Okay. Thank you.
Answer, ashish tomar
Ashish Tomar: Actually, we could not get the full question. But what we could get is that probably you are asking that in the last con call, which was somewhere in the middle of October or in the middle of November, that we would have known the situation about this quarter's results also. That is what probably you are asking. And why we could not project better than what we have done. I think this is a question if you can confirm and then I will try to answer it? Ahmed: Yes, that is one question. And the other question was that like you have said that by FY27, the promoters will reduce pledging to zero.
Answer, ashish tomar
So, we will definitely get it more than 15% or at least 15% for this financial year. And otherwise, for the next thing, we will remain about 17%-18% of the PAT as we have done in the history of the 10-11 years of the company's history. So, this is eventual portion of this quarter. So, on a nine-month basis, it is still 15.86% PAT. So, we are not behind 15% if we take the nine-month period. But if you take the quarter only, so I have explained it that in a quarter, you can start certain projects which have the expenditure side stronger than the receivable side. So, that is what happened in this quarter.
Answer, ashish tomar
Ashish Tomar: Yes, this is cyclic. Once we execute the work, we get the receivables and the 90-days we take as the receivable amount. So, this is 60-days-to-120-days and sometimes as an average, we take it 90-days period after expenditure. So, 90-days revenue, that is three months working capital we always require. Say Rs.1,000 crores turnover, so we require mostly Rs.250 crores as a working capital, minus 20% EBITDA, that is about Rs.20 crores we have to have in our hands as a working capital. But this figure fluctuates a lot quarter-by-quarter because civil engineering projects on ground, they may face so many problems. Sometimes the land is not clear, sometimes as we have seen in these two quarters that rainy season has affected so much.
Answer, ashish tomar
In Q2, it affected so much. In Q3, we tried to revamp it and to reorganize it. But, once there is a heavy rain, there are some disasters also. So, the administration which look after the development work, they also give the priority to the disaster restoration. So, that took some time and certain times we were stopped to do the work. Otherwise, we assure you that this quarter will be much, much better, and we will definitely outpace from the Q1 of the next financial year. There is no doubt about it.
Answer, ashish tomar
Ashish Tomar: We will grow as per order book is concerned. We will grow by about 40%-50%. Nishita: Okay. Thank you so much.
Answer, ashish tomar
Ashish Tomar: Yes, so first I would like to explain or give answer to your second question. I would request you to please understand the nature of the business. The projects that we get vary from year-to- year and state-to-state. So, as a coincidence, the major portion of the revenue that we expected to book, was to come from Uttarakhand as about Rs.800-odd crores in excess of our work order comes from that state. The work that we do involves digging up of roads and laying the pipelines in that area. Due to unexpectedly heavy rainfall and the landslides and natural disasters that took place in that state in the Q2, we expected it to recover by Q3, but the disaster management taken up by government that took some time more than what we expected and we could not execute or book revenue in that state. But, on overall business side, we think we can resume our pace by next quarter.
Answer, ashish tomar
This quarter will likely still be affected. As far as loan against share is concerned, out of Rs.210-odd crores that we took from NBFCs, Rs.70 crores has been paid. We are committed to bring it down to 100 crores by end of this quarter. And the shares that are pledged can only be released after we pay the whole amount. Page 9 of 12 Azar: I would like to have a rebuttal over here. Now that you have the visibility of Q4 and you say Q4 will still be affected and Q1 onwards you will outpace. Can we safely project that FY27 would be better than FY25?
Question
Amit Agicha: What is the long-term strategic rationale behind entering the flex sheet and paper? What would the revenue, EBITDA target be?
Answer, ashish tomar
Ashish Tomar: Yes, sir. As we have already clarified this in previous calls also, we took that factory from NCLT to put it as collateral with banks against our non-funding bank guarantees, etc., So that land came with an established factory. We initially were not enthusiastic to run it, but since it was a running factory, when we realized that it can give us a profit of about 5% over revenue in that business also. So, that is an additional benefit to the company. It is self-sufficient. It does not require any funding from the company. So, we are letting it run.
Answer, ashish tomar
And if it maintains this profit or it improves, then much better. But we would not invest any further money if it starts to decline. So that we would like to clarify.
Question
Amit Agicha: So, in your view, do you think production will scale up?
Answer, ashish tomar
Ashish Tomar: Sir, it might be possible in future. But till now, I think that plant is producing about 800-900 tons of output. And it can reach an output of about 1,100-plus tons in the coming financial year. Page 10 of 12 Amit Agicha: I appreciate your answer.
Question
C.A. Garvit Goyal: Hi. Thank you for the follow-up. In continuation with the earlier participant, I think she asked about the exit order book for this financial year. And you said 40%-50% growth. I think the answer was not what she was expecting. So, can you just clarify what is the expected order book that people are anticipating after execution of this quarter, maybe the new order inflows that you are anticipating in the next two months, so what will be the order book look like as on 31st March, 2026?
Answer, ashish tomar
Ashish Tomar: We are having the order book of more than Rs.2,200 crores as of now. We are expecting Rs.1,000 crores but that could not be a date like 31st March because that could come in the first week of April, second week of April or something. Because bidding process sometimes get litigated also. So, we have bidded, but we are expecting the order book to increase by up to Rs.3,000 crores in the Q1 of the next financial year. That is for sure. Because we do not want to give much optimistic guidelines type of thing that 31st March could not be that date. Because sometimes you bid and there is some dispute, resolution, boards where it goes and the final LOI or agreement is performed, it may take four, five months altogether.
Answer, ashish tomar
So, we are bidding. There are some bids under pipeline, some under technical evaluations and in different stages. So, in Q1 we will definitely have the order book of around Rs.3,000 crores because Rs.2,200 crores, and in this quarter, we can exhaust it by Rs.200 crores almost, and of course we can have Rs.3,000 crores in Q1 of the next financial year.
Question
C.A. Garvit Goyal: All right. And secondly on the pledge part, I may have missed the earlier communication on that. Can you please clarify what is the exact purpose of this pledge?
Answer, harish kansal
Harish Kumar Kansal: So that money was used to invest in lands and properties.
Question
C.A. Garvit Goyal: So that means the promoter is basically pledging the shares to having its own land and properties in the personal capacity. That is what you are saying?
Answer, ashish tomar
Ashish Tomar: Yes, to start that is for a real estate business.
Question
C.A. Garvit Goyal: So, I am trying to understand what is the thought process like when are we planning to reduce it to zero percent, like again earlier participant also mentioned about it, he said earlier we were speaking about FY26 and now we are speaking about FY27?
Answer, ashish tomar
Ashish Tomar: Yes, sir. We went up to Rs.210 crores of money borrowed. We have reduced it to Rs.140 crores. We have repaid about Rs.70 crores of the principal amount along with interest. And we are planning to reduce the principal amount to less than Rs.100 crores by the end of this financial year and repay the whole amount in the next financial year. The shares that are pledged with can only be released after we repay the whole amount.
Question
C.A. Garvit Goyal: Okay. Thank you.
Answer, harish kansal
Harish Kumar Kansal: I am H.K. Kansal speaking, CEO of the company. So, as closing comments, definitely we could not meet the expectation in this quarter as a result in PAT. But we can assure that we are on the right track and right path. We are aggressively bidding. Company is not in any financial distress or any type of distress. And we will definitely revamp it in this quarter and the first quarter of the next fiscal, we will see high growth and everything will be perfectly matched.
Answer, harish kansal
Actually, we have also faced the same situation after the COVID and we fall in 2021 and 2022. But we maintain the growth of 20% in 2023 and we covered it up of the eight years span. So, we are confident that in this year, if we are not able to match with the expectation, we will definitely be aggressive on next year. And next year we will do the cover up of the whole things. Thank you so much.
Questions about this call
- When was the EMS Q3 FY26 earnings call transcript filed?
- EMS filed the transcript with the exchange on 17 Feb 2026. This page is built from that transcript.
- What does this page list?
- 35 statements from the transcript across 7 topics, 19 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 23 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.