Garden Reach Shipbuilders & Engineers Q2 FY26 earnings call: Garden Reach Shipbuilders & Engineers Limited's order book stood at ₹20,205.56 crores as on 30th September

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Order book stood at ₹20,205.56 crores as on 30th September. Three projects, one for the Coast Guard and two for the Navy, have had RFPs issued: Eighteen SPV projects for the Coast Guard, five Next-Generation Survey Vessels for the Navy and two Multi-Purpose Vessels for the Navy; their total likely order value is approximately ₹8,700 crores. The third ship in Garden Reach Shipbuilders & Engineers Limited's P-17 Alpha project has completed nearly 60% of construction and is moving towards delivery during mid-2026. Revenue from operations increased year-on-year from ₹1,153 crores to ₹1,677 crores, registering growth of 45%, in Q2 FY 26. The company has ₹283 crores of own funds and ₹2,874 crores of project funds parked for payments to partners or other requirements, and is planning for the current year.

The numbers management gave

Results

  • Revenue from operations increased year-on-year from ₹1,153 crores to ₹1,677 crores, registering growth of 45%, in Q2 FY 26.
    Show source
    Our revenue from operations year-on-year has gone up from ₹1,153 crores to ₹1,677 crores, registering a growth of 45%.
  • Total income moved up by 42% and its profit after tax increased from ₹98 crores to ₹154 crores, registering growth of 57%, in Q2 FY 26.
    Show source
    Similarly, the total income has moved up by 42%, with the profit after tax moving from ₹98 crores to ₹154 crores registering a growth of 57%.
  • In the last 2 quarters, Garden Reach Shipbuilders & Engineers recognized revenue of around ₹2,942 crores while its order book dropped only by around ₹2,000 crores, meaning it obtained around ₹900 crores of orders during this quarter.
    Show source
    I n the last 2 quarters, we have actually recognized revenue to the tune of around ₹2,942 crores whereas our order book has dropped only by around ₹2,000 crores, which means around ₹900 crores of orders we already obtained during this quarter.

Money and capital

  • The company has ₹283 crores of own funds and ₹2,874 crores of project funds parked for payments to partners or other requirements, and is planning for the current year.
    Show source
    Hari: See, our own funds are ₹283 crores and project funds are ₹2,874 crores, which we have parked so that the payment especially from our side is for our partners or for other requirements.

What it expects ahead

What management expects

  • Three projects, one for the Coast Guard and two for the Navy, have had RFPs issued: Eighteen SPV projects for the Coast Guard, five Next-Generation Survey Vessels for the Navy and two Multi-Purpose Vessels for the Navy; their total likely order value is approximately ₹8,700 crores.
    Show source
    The total likely order value is approximately ₹8,700 crores between these three projects.
  • Seven more projects have been accorded Approval of Necessity (AoN) by the Defence Acquisition Council over the last one year: the P-17 Bravo project of 7 ships, Mine Counter Measure Vessel (MCMV) - 12 ships, Fast Interceptor Craft - 120 vessels, 18 FIBs, 31 Next-Generation Waterjet FACs, 4 LPDs, and 5 NOPVs between Navy and Coast Guard.
    Show source
    These include the P -17 Bravo project of 7 ships, the Mine Counter Measure Vessel (MCMV) - 12 ships, the Fast Interceptor Craft - 120 vessels, 18 FIBs, 31 Next-Generation Waterjet FACs, 4 LPDs, and 5 NOPVs between Navy and Coast Guard.
  • The AoN value for the P-17 Bravo project is approximately ₹70,000 crores, the Mine Counter Measure Vessel is about ₹32,000 crores, and LPD is around ₹35,000 crores.
    Show source
    And the high-value projects among these are the P-17 Bravo, the AoN value itself is approximately ₹70,000 crores , the Mine Counter Measure Vessel is about ₹32,000 crores , and LPD around ₹35,000 crores.
  • The seven projects for which the DAC has accorded AoN, together with the pre-RFPs, have an estimated value of ₹1,52,000 crores, based on a consolidated estimate.
    Show source
    So, all put together, these seven projects for which the AoN has been accorded the value comes to approximately ₹1,52,000 crores.
  • The company expects the projects covered by the MoI with a European client to gain some traction over the next 6 months.
    Show source
    So, we expect these projects to gain some traction over the next 6 months.
  • The company is confident of ending the financial year with an order book plus ₹50,000 crores, almost 100% more than its highest-ever order book position.
    Show source
    And we are confident of ending the financial year with an order book plus ₹50,000 crores, which is well above the highest order book position that the company ever had.
Show 34 more statements

What management expects

  • The LPD project is a 4-ship project with an order value likely to the tune of around ₹35,000 crores.
    Show source
    The 4-ship project with an order value likely to the tune of around ₹35,000 crores.
  • The Landing Platform Dock project is expected to take about 2 to 2.5 years from now for the contract to be signed.
    Show source
    So about 2 to 2.5 years from now, the contract is expected to be signed.
  • The Landing Platform Dock project duration will be around 48 months for the first ship, with one ship thereafter every 6 months.
    Show source
    And as per my understanding, the project duration will be around 48 months i.e. 4 years for the first ship and every 6 months for one ship thereafter.
  • Many orders for the Next-Generation Corvette project could trickle down during FY '27 starting from the first half onwards.
    Show source
    So, they can be rest assured that many of these orders could trickle-down during FY '27 starting from the first half onwards.
  • For conventional shipbuilding, the PAT margin would be around 7.5 percentage, and Garden Reach Shipbuilders & Engineers expects to get well beyond that on the NGC order.
    Show source
    But this being a high- value project, I would just state - I'll go back to what I normally say shipbuilding in conventional shipbuilding, good margin, the PAT margin would be around 7.5 percentage, and we can assure our investors and partners that we'll be getting well beyond that.
  • The company expects the RFP for the P-17 Bravo project to come out during the current financial year, expected during the end of Q4 FY '26.
    Show source
    So, as I said, RFP is expected during the end of Q4 FY '26.
  • The company is targeting an order book of approximately ₹50,000 crores by the end of FY '26.
    Show source
    All put together, we should end the financial year with around ₹50,000 crores.
  • If Garden Reach Shipbuilders & Engineers Limited gets the P-17 Bravo, its order book could increase as predicted, with either 4 ships in the best-case scenario or 3 ships in the worst-case scenario.
    Show source
    And if we get the P -17 Bravo, let's take the best-case scenario of 4 ships coming to us or the worst-case scenario of 3 ships coming to us, the order could go up exactly the way you predicted.
  • The company expects a definite, consistent upward movement in FY '26 and FY '27, followed by a plateau for 2 years and then a spike.
    Show source
    FY '26, FY '27, you will see a definite upward movement, consistent upward movement, then it could plateau out for 2 years and then the spike will start again.
  • The company expects complex commercial vessels, including exploration vessels or hybrid vessels, to have good margins, and expects complex platforms with higher margins to be available in another 1 year to 2 years.
    Show source
    I expect another 1 year to 2 years, it should be very much there.
  • The company said it will deliver growth between 25% and 30%.
    Show source
    We have been maintaining about 25% to 30% year-on-year growth and we expect to maintain similar trend during the current financial year too.
  • While waiting for high-ticket items like the NGC order to be contracted, Garden Reach Shipbuilders & Engineers is getting orders for small projects such as commercial ships and research vessels so revenue does not drop in the coming year.
    Show source
    Page 6 of 14 What we are doing is rather while waiting for high- ticket items like the NGC order to be contracted, we are meanwhile getting orders for small -small projects be it for commercial ships, research vessels, so that the revenue does not drop in the coming year.

Orders

  • Order book stood at ₹20,205.56 crores as on 30th September.
    Show source
    Coming to the order book that the company had as on 30 th September, our order book stood at ₹20,205.56 crores.
  • Order book comprised 10 shipbuilding projects consisting of 43 platforms, including 13 warships for the Indian Navy: two P-17 Alpha Advanced Frigate, one Survey Vessel (Large), 6 Anti-Submarine Shallow Water Crafts, and 4 Next-Generation Offshore Patrol Vessel.
    Show source
    These include 13 warships for the Indian Navy, i.e . two P -17 Alpha A dvanced Frigate, one Survey Vessel (Large), 6 Anti-Submarine Shallow Water Crafts, and 4 Next-Generation Offshore Patrol Vessel.
  • The company has been deployed L1 in the high-value Next-Generation Corvette project and expects the contract to be signed in the next 3 to 4 months.
    Show source
    As you are aware, we have been deployed L1 in this project, a high-value project.
  • The total order value for each Next-Generation Corvette ship is almost ₹51,000 crores.
    Show source
    Total order value for each ship is to the tune of almost ₹51,000 crores.
  • The P-17 Bravo project is expected to be split between two shipyards, with the L1 shipyard taking 4 and the L2 shipyard taking 3.
    Show source
    With our Bravo ship project not likely, it will be split between two shipyards, the L1 shipyard taking 4, and the L2 shipyard taking 3.
  • The company successfully completed the acceptance trials of its Naval Surface Gun and expects more orders for the 30 mm gun from the Navy and the Coast Guard.
    Show source
    So, we have started with the Naval Surface Gun in collaboration with an establishment partner and happy to inform you that we already successfully completed the acceptance trials of this Naval Surface Gun and with the success of the equipment, the gun, we expect more orders from the Navy and the Coast Guard, because both Navy and the Coast Guard have requirement of the 30 mm Guns for their medium-sized and small-sized platform, which they have in large number.
  • The company has received an RFP for 7 more Naval Surface Guns, which are under final negotiations for contract conclusion.
    Show source
    To answer your question with respect to, yes, we have received an RFP for 7 more guns, which are under the final negotiations for contract conclusion.
  • The company has received an inquiry for nearly 50 guns.
    Show source
    We have received an inquiry for nearly 50 guns.
  • The company has 10 contract-signed guns, 7 guns in liquid form and 49 guns at a very nascent stage in its basket, and expects the contract for the 7 guns to be signed soon.
    Show source
    We expect the contract to be signed soon and the 49 at a very nascent stage.
  • The AoN cost could vary by ₹2,000 crores, in addition to the ₹8,700 crores pre-RFP order value.
    Show source
    It could be maybe, see this is AoN cost, it could vary ₹2,000 crores, so, plus this ₹8,700 crores RFP.
  • The Ministry of Shipping has aggregated demand from non-defense PSUs, including ONGC, for 207 commercial vessels, including MR tankers, LR tankers, platform support capacity, Supramax, Aframax and Panamax type of tankers vessels.
    Show source
    And the number of platforms at various places are identif ied so far is 207.
  • Order for the NGC could be around ₹30,000 crores.
    Show source
    As you rightly said, of course, I would like to just make a slight correction to the NGC figure, that could be to the tune of around ₹30,000 crores order.
  • Remaining order balance for the P-17 Alpha project is around ₹9,500 crores.
    Show source
    The P -17 Alpha project, the spending remaining order balance order values around ₹9,500 crores.
  • Anti-Submarine Shallow Water Craft order is around ₹3,075 crores.
    Show source
    The Anti -Submarine Shallow Water Craft is around ₹3,075 crores.
  • Survey Vessel (Large) order is around ₹400 crores.
    Show source
    The Survey Vessel (Large) is around ₹400 crores.
  • Next-Generation Offshore Patrol Vessel order is around ₹3,250 crores, and its 30mm Naval Surface Gun order is around ₹150 crores.
    Show source
    The Next -Generation Offshore Patrol Vessel is around ₹3,250 crores and the 30mm Naval Surface Gun is around ₹150 crores.
  • Ocean Research Vessel order is around ₹750 crores, Acoustic Research Ship order around ₹220 crores, West Bengal Electric Ferry order about ₹220 crores, Coast Research Vessels order around ₹460 crores, Multi-Purpose Vessels for the German plant order around ₹5,400 crores, and remaining dredger order value about ₹95 crores.
    Show source
    Page 11 of 14 The Multi-Purpose Vessels for the German plant around ₹5,400 crores and the remaining order value on the dredger is about ₹95 crores.
  • Shipbuilding order book is around ₹19,856 crores, with 83% from defence platforms and 17% from non-defence platforms.
    Show source
    But now we have reached stage of ₹19,856 crores, 83% is coming from defence and balance 17% is coming from non-defence platforms.
  • The project value for the next two ships, including the ship almost ready for delivery, the large ships and Base and Depot spares, is ₹9,400 odd crores.
    Show source
    So, this actual project value for the next 2 ships, the one which is ready, almost ready for delivery plus the large ships plus the Base and Depot spares all put together, it comes to ₹9,400 odd crores.
  • Current order book is ₹23,000- odd crore and, unless it gets fresh orders, is expected to come down to around ₹22,000 crore something by end of this financial year; it is expected to last, including new projects signed, up to 2029.
    Show source
    When we started this financial year, our order book was around ₹22,000 crores.
  • The company has submitted bids for two of the three projects with issued RFPs, and bid submission for the third project is understood to be towards the end of this month.
    Show source
    GRSE has already submitted a bids of two of these projects and the third project the bid submission, as I understand, is towards the end of this month.
  • The Next-Generation Corvette contract has not been delayed with respect to award of contract.
    Show source
    And at the outset, the project has not been delayed with respect to award of contract.

What it is building and selling

Projects and capacity

  • The third ship in Garden Reach Shipbuilders & Engineers Limited's P-17 Alpha project has completed nearly 60% of construction and is moving towards delivery during mid-2026.
    Show source
    The third ship, the last of this project has completed nearly 60% of construction and it's moving towards this delivery schedule during mid-2026.
  • In Garden Reach Shipbuilders & Engineers Limited's 4-ship Survey Vessel (Large) project, three ships have been delivered and the fourth ship has achieved nearly 85% physical progress of construction, completed Contractor Sea Trials, and is planned for delivery during February, 2026.
    Show source
    This is a 4 -ship project, three ships have already been delivered and the fourth ship has achieved nearly 85% physical progress of construction and has successfully completed the Contractor Sea Trials.
  • In Garden Reach Shipbuilders & Engineers Limited's Anti-Submarine Shallow Water Craft project, the fourth and fifth ships have achieved nearly 80% and 72% physical progress of construction, respectively, and the company is targeting delivery of both during the first half of 2026.
    Show source
    The fourth and fifth ship has achieved nearly 80% and 72% physical progress of construction, respectively and we are targeting delivery of both these ships during the first half of 2026.
  • The sixth, seventh and eighth ships in Garden Reach Shipbuilders & Engineers Limited's Anti-Submarine Shallow Water Craft project have construction progress ranging from 65% to 70%, and the company will complete the project by end of next year.
    Show source
    The balance three ships, the 6th, 7th,and 8th, have progress of construction ranging from 65% to 70% and by end of next year, we will be completing the Anti -Submarine Shallow Water Craft project.
  • In Garden Reach Shipbuilders & Engineers Limited's Next Generation Offshore Patrol Vessel project, two ships have achieved nearly 60-plus percentage physical progress and the next two ships are around 52% progress of construction; the first two ships shall be launched during early 2026 and the next two during the latter half of 2026, with delivery scheduled by 2028 as per contract.
    Show source
    Those two ships have achieved nearly 60 -plus percentage of physical progress, and the next two ships are around 52% progress of construction.
  • The company is undertaking a World Bank funding Hybrid Vessel project for the Government of West Bengal comprising 13 vessels: seven 100 pax passengers and 6 200 pax passengers; delivery shall commence from early 2026 and project completion is scheduled by 2027.
    Show source
    This is the World Bank funding project, 13 vessels: seven vessels 100 pax passengers and 6 vessels 200 pax passengers.
Show 15 more statements

Projects and capacity

  • The first vessel in Garden Reach Shipbuilders & Engineers Limited's export Multi-purpose vessels project for a German client has been completed, and delivery of the vessels is expected to be completed by 2029.
    Show source
    Of that, first vessel has already been completed.
  • Low-value project, about ₹135 crores, is on track, with delivery of the vessel planned during mid-2027.
    Show source
    Next project is the low -value project, about ₹135 crores project.
  • Delivery of Garden Reach Shipbuilders & Engineers Limited's Ocean Going, Acoustic Research Ship, and Coastal Research Vessels is planned between 2027 and 2028.
    Show source
    The Ocean Going, the Acoustic Research Ship, and the Coastal Research Vessels, the delivery of these vessels are planned between 2027 and 2028.
  • The company has identified areas for its brownfield facility in West Bengal, taken charge of at least 2 of the 3 areas, and started development of these areas.
    Show source
    And the process has already started, areas are identified, taken on charge atleast 2 of the 3 areas, and we have started the development of these areas.
  • The company estimates a conservative 3 to 4 years for its greenfield expansion plan to fructify.
    Show source
    So , considering that, I would put a conservative time of about 3 to 4 years for greenfield expansion plan to fructify.
  • The company intends to complete its 8-ship Anti-Submarine Shallow Water Craft project by FY27.
    Show source
    Both the ships have since been commissioned into the Indian Navy and the third ship has completed her final machinery trials and is getting ready for delivery.
  • The company targeted shipbuilding capacity for 28 ships concurrently and is at 24 ships now.
    Show source
    And with this background, we had systematically prepared our capacity enhancement plan and our shipbuilding capacity increased from 24 ships concurrent construction to 28 ships during 2024-2025 and with the ongoing modernization, we intend to increasing this to 32 ships by 2026.
  • The company is undertaking a brownfield expansion in three pockets in West Bengal and a greenfield shipyard in the West Coast.
    Show source
    So, we are going in for a brownfield expansion between West Bengal in three pockets, and I mean the pockets in three separate areas and a greenfield shipyard in the West Coast.
  • The company has identified an area for its West Coast project, and preparation of the DPR is in progress.
    Show source
    The DPR preparation is currently in progress.
  • First vessel project has kick started. Replaced by a later filing.
    Show source
    The first vessel project has kick started.

Deals and partners

  • Export Multi-purpose vessels project for a German client increased from an initial 4 ships to 8 and thereafter 12, with an option for another two vessels.
    Show source
    Just to put things in perspective, this was initially a 4-ship project, then the quantum got increased to 8 and thereafter 12, with an option for another two vessels.
  • The company has signed an MoI with a European client for Multi-purpose vessels akin to vessels for which it has already signed the contract; the parties are still in discussion stage.
    Show source
    In addition, we have already, GRSE, has already signed an MoI with a European client for Multi-purpose vessels akin towards vessels for which we already signed the contract.
  • MDL, HSL, GRSE, Cochin Shipyard and L&T are expected players in the Landing Platform Dock project.
    Show source
    The three of us i.e., MDL, HSL, GRSE plus Cochin Shipyard plus L&T. This is the expected players in the field for this project.
  • For the Next-Generation Corvette project, the partner range could be from MSME to major global OEMs.
    Show source
    Now, in this contract being a high-value contract for an advanced platform, the partner range could be from MSME to major global OEMs.
  • The company will place orders with major OEMs and MSMEs during the pre-production period based on the design and maturity.
    Show source
    During this period, we will be placing orders to all our partners, the major OEMs, as well as the MSMEs based on the design and maturity.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Congratulations for a good set of numbers. A couple of questions from my side, sir. One is the recently approved AoNs of ₹79,000- odd crores, there was a mention of LPD ov er there. So just wanted to understand the qua ntum of LPD that could be there and then secondly, who all are in the fray for this particular platform? And part C of the question is that how long it will take for us to build this LPD, if we get the contract?

    Answer, p.r hari

    P.R. Hari: Thank you, Mr. Amit. You're absolutely right. The last DAC meeting, they have accorded AoNs for various projects including the LPD project. This is a high-value project that consists of 4-ship project. The 4-ship project with an order value likely to the tune of around ₹35,000 crores. Next question, who all.

    Answer, p.r hari

    The three of us i.e., MDL, HSL, GRSE plus Cochin Shipyard plus L&T. This is the expected players in the field for this project. And normally, it takes about 1 year to 1.5 years for the RFP to be issued from the time of the accord of AoN. And from the time of RFP issuance, it takes about a year for the contract, including L1 declaration contract to be signed. So about 2 to 2.5 years from now, the contract is expected to be signed. And as per my understanding, the project duration will be around 48 months i.e. 4 years for the first ship and every 6 months for one ship thereafter. That is my apprehension.

  2. Question

    Amit Dixit: Okay, sir, that's very helpful. The second question is essentially on Next -Generation Corvette. So, the project, the awarding of contra ct has been, I think, delayed quite a bit. Where we are actually on this, there were certain defence companies who mentioned on their call that they are expecting some trickle -down orders for this next year. But unless and until it is awarded, it's very difficult to see how they can get the trickle-down orders. So just wanted your thoughts on this, where are we actually and when can we expect the decision on this?

    Answer, p.r hari

    P.R. Hari: As our defence partners are waiting for our trickle -down orders, we are waiting for the main order. And at the outset, the project has not been delayed with respect to award of contract. This is a natural process. Once the L1 is declared, there will be a price negotiation and then the contract and it is a high-value order. Total order value for each ship is to the tune of almost ₹51,000 crores. So, naturally, it will take a finite amount of time for the contract to be concluded.

    Answer, p.r hari

    I am happy to inform you that the contract negotiations are in final stages, and we expect the contract to be signed in the next 3 to 4 months, which means in this financial year. Now, in this contract being a high-value contract for an advanced platform, the partner range could be from MSME to major global OEMs. So, for a major project like this, there is pre - production time that has been awarded. So, from the time of award of contract, there is a pre- production, pre-determined time that is awarded. During this period, we will be placing orders to all our partners, the major OEMs, as well as the MSMEs based on the design and maturity. So, they can be rest assured that many of these orders could trickle-down during FY '27 starting from the first half onwards. With the contracts signing likely during Q4 of this year.

  3. Question

    Amit Dixit: Okay, sir, that's very helpful. The third one, and if I may, and this is the last question from my side, is that, if you see we are actually cruising at a very good execution as of now. But the old book is also diminishing. So, until we hit really the pressure on NGC and Landing Platform Dock, do you foresee that in the next, let's say, 3 to 4 quarters will face a period where there's significant earnings decline just because we would have exhausted our order book?

    Answer, p.r hari

    P.R. Hari: Okay. I wi ll put it this way. When we started this financial year, our order book was around ₹22,000 crores. I n the last 2 quarters, we have actually recognized revenue to the tune of around ₹2,942 crores whereas our order book has dropped only by around ₹2,000 crores, which means around ₹900 crores of orders we already obtained during this quarter. Page 6 of 14 What we are doing is rather while waiting for high- ticket items like the NGC order to be contracted, we are meanwhile getting orders for small -small projects be it for commercial ships, research vessels, so that the revenue does not drop in the coming year. To answer your direct question regarding, is there any likelihood of revenue depletion in the coming few quarters?

    Answer, p.r hari

    No. I don't expect that purely because, the P-17 Alpha project is very much on even as of now a nd so the second major project, the A nti-Submarine Shallow Water Craft project. And those two projects are likely to extend to one of them mid of next year and the second one end of next year. So, I don't see any revenue depletion in the next 2 to 3 or 3 to 4 quarters. I hope that answers your question. Thank you.

  4. Question

    Krishna Doshi: Congratulations, on a great set of numbers, sir. Sir, my first question would be with regards to the NGC order. So, I was just trying to understand like what kind of margins are we looking at in the NGC order? If you could just possibly give us a range or something?

    Answer, p.r hari

    P.R. Hari: See, always trick questions are welcome, just trend on the margin. Okay , and see, this project has been won on competition, and I hope you are aware of that. But this being a high- value project, I would just state - I'll go back to what I normally say shipbuilding in conventional shipbuilding, good margin, the PAT margin would be around 7.5 percentage, and we can assure our investors and partners that we'll be getting well beyond that. So, margins will not be wafered there.

  5. Question

    Krishna Doshi: Perfect. Okay, sir. Sir, my second question would be that we've seen like significantly higher gross margins in this quarter, but we ha ve also seen a spike when it comes to the subcontracting cost and other expenses. So, if you could please elaborate, what were this cost attributed to?

    Answer, p.r hari

    P.R. Hari: Thank you. One, you mentioned about the higher margins this quarter and also increase in subcontracting costs. As a strategy, our non -core jobs, including a certain amount of construction activities are outsourced. So, it is not natural that as the overall revenue increases, the subcontracting cost also increases, and that is purely a natural phenomenon, and no matter of concern. Now coming to margins. Right now, we are recognizing maximum revenues from the P-17 Alpha project.

    Answer, p.r hari

    The second ship has reached a stage where the trial phase has started, the equipment installation has been completed. So, this being a definite profit-making project. So, the revenue recognition as well as margins are good during this quarter. And the same trend is likely to continue in the next quarter too, where the project is likely to be in a similar pace even in the next quarter.

  6. Question

    Krishna Doshi: Just the last question that our revenue guidance has always been in the range of 25% to 30%. However, in the first half only, we have delivered a revenue growth of around 38%, if you see year-on-year in the first half. So, do we now want to revise our revenue guidance upwards?

    Answer, p.r hari

    P.R. Hari: See, you're absolutely right. We have been maintaining about 25% to 30% year-on-year growth and we expect to maintain similar trend during the current financial year too.

  7. Question

    Sai Vijay: Sir, my question is regarding the upcoming P -17 Bravo project. When is the RFP expected? I think you mentioned around 2 calls back that it should be released soon, right? Page 7 of 14 P.R.

    Answer, p.r hari

    Hari: Thank you, Mr. Sai. Yes, we are also waiting for the P-17 Bravo project having now raised almost 2/3 of the P -17 Alpha project. Yes, the AoN has already been accorded by the DAC about, I think, about 8 months back. We expect the RFP to come out during the current financial year. With our Bravo ship project not likely, it will be split between two shipyards, the L1 shipyard taking 4, and the L2 shipyard taking 3. So, as I said, RFP is expected during the end of Q4 FY '26.

  8. Question

    Sai Vijay: Sir, you already have gi ven your experience with P -17 Alpha, how confident are you about winning the order? And also, could you just share the shipyards names participating in the bid?

    Answer, p.r hari

    P.R. Hari: Okay. So, from my information, about 4 shipyards were there. So, the probability is very high. MDL, GRSE, L&P and Cochin Shipyard. These are the four shipyards who have been shortlisted for this project as of now. And we expect it to remain in the same fashion.

    Answer, p.r hari

    And yes, see, I don't know whether you remember or not, when we started discu ssing the NGC project almost 2.5 years back, we have been, by the management, GRSE has been continuously stating that with the experience gained from the projects executed by GRSE for the Navy, we will be bidding in such a fashion as to win the bid and we have won the bid. So, I would like to maintain the same confidence that with the experience of having built the P -17 Alpha frigate, we will be bidding in such a fashion to bring those people in Bravo.

  9. Question

    Ayush Agrawal: Weapon systems, Naval Gun procurement part.

    Answer, p.r hari

    P.R. Hari: Okay. Got it. So as a diversified company, as you are aware, as our name states, Garden Reach Shipbuilders & Engineers Ltd, unlike any other conventional shipyard, we are a fully diversified company, and one of our products is Weapon. So, we have started with the Naval Surface Gun in collaboration with an establishment partner and happy to inform you that we already successfully completed the acceptance trials of this Naval Surface Gun and with the success of the equipment, the gun, we expect more orders from the Navy and the Coast Guard, because both Navy and the Coast Guard have requirement of the 30 mm Guns for their medium-sized and small-sized platform, which they have in large number. So, I see a huge potential on this front. As I stated, we are expecting more orders from both the Navy and the Coast Gu ard for the 30 mm gun.

    Answer, p.r hari

    We are also exploring the feasibility of further expanding our range of Weapon- system. They are still in discussion stage. So, maybe in one of the subsequent interactions, I'll be able to give more clarity on this as we progress. But right now, we are focusing on the 30 mm Naval Surface Gun.

    Answer, surface agrawal

    Ayush Agrawal: Understood. Sir, second question is just a follow-up that, currently, there are 10 guns is what I believe and many would be in RFP stage also. So, if you can tell us a number, how many would be in the RFP stage? And going ahead, what can be our annual Naval Gun installations?

    Answer, p.r hari

    P.R. Hari: See, I will put it this way. I can give you the broad numbers. Of course, I will not be able to share the exact numbers, but I can give you a hint. But the point is what we must acknowledge is that this gun has just been developed and the acceptance the first gun has been completed just Page 8 of 14 about 4 months back. So, it is still in the stabilization phase. To answer your question with respect to, yes, we have received an RFP for 7 more guns, which are under the final negotiations for contract conclusion.

    Answer, p.r hari

    We have received an inquiry for nearly 50 guns. So, the opportunities are huge. But at this stage, 10 plus 7 plus 49 is what we have in our basket. 10 contract already signed, 7 still in liquid form. We expect the contract to be signed soon and the 49 at a very nascent stage.

  10. Question

    Ayush Agrawal: Sir, just one last question on this one. Are the older naval guns also getting replaced on the existing vessels?

    Answer, p.r hari

    P.R. Hari: I shall follow up this further. And maybe in one of the subsequent interactions, I shall let you know more on this. But as I understand, yes, there is a need to replace the vintage guns. But at this moment, since it is evident that Navy is focusing on 30 mm guns, their focus is on smaller caliber guns. But I shall definitely revert to you with further information as and when I get with respect to the other weapon systems of the process.

    Answer, p.r hari

    P.R. Hari: Could you repeat the question part once again? I am not able to hear clearly, some sort of… Yash: So, the thing is that the other shipyards have given some corporate actions like stock split or something like that. So, is there anything on the cards for our company also, sir?

    Answer, p.r hari

    P.R. Hari: Thank you, Mr. Yash. I could hear your question clearly and the intent. See, we are purely guided by DIPAM guidelines, and we are waiting for instructions from them. And as and when we get to know, our investors will be the first to know from us. At this juncture, we are waiting for further directives from DIPAM. Yash: And one more question, sir.

    Answer, p.r hari

    P.R. Hari: Okay. What I had mentioned was, one, there is a definite need for capacity adjustment. And we are doing it in two parts, not phases. One is to create brownfield facility and brownfield facility, we definitely would prefer in our home state i.e. West Bengal. And the process has already started, areas are identified, taken on charge atleast 2 of the 3 areas, and we have started the development of these areas. So that is very much in hand.

    Answer, p.r hari

    As far as the West Coast project is concerned, area has been identified. The DPR preparation is currently in progress. And this will, see any shipbuilding infrastructure, it takes a certain amount of time. It is capital intensive and time intensive. So , considering that, I would put a conservative time of about 3 to 4 years for greenfield expansion plan to fructify. As I said, right now, the DPR is under preparation. It is moving in the right direction.

    Answer, p.r hari

    And maybe in about in a year, we'll be able to put the DPR effort into action with respect to implementation. It is in the West Coast. That is the second thing. Page 9 of 14 Yash: Sure, sir. Great, sir. And I hope under your leadership, so our company will have a long way to go. Thank you, sir.

    Answer, p.r hari

    Thanks for the effort and all, you are keeping and making this company great, sir. Thanks a lot, sir.

Show 8 more questions
  1. Question

    Sunil Shah: Yes, sir. And first of all, congratulations on the first delivery of the frigate, the P-17 Alpha, that we could deliver to the country. So , big thank you from everybody and to the entire team of GRSE, congratulations on that side. Enjoyed the entire journey from the date of the order announcement till the actual delivery as an investor. Sir, just a few pointers, I just w anted to understand. When you stated during the opening remarks that the A oN is about INR 1,52,000 crores that was pertaining to the opportunity that we can look at. Is that the understanding, correct?

    Answer, p.r hari

    P.R. Hari: Thank you on your best wishes and congratulations on the delivery of this first and we assure you that even the next ship is very much on the right track for delivery ahead of schedule. Now coming to the order book on th at. See, I have stated that in addition to the pre- RFPs, which already been promulgated for which the order value is likely to be to the tune of around ₹8,700 crores. There are 7 more projects for which the DAC has already accorded AoN. These include I think, I have mentioned this already , P-17 Bravo - 7, 12 Mine Counter Mea sure Vessels, 120 FICs, 18 Interceptor Boats, Next-Generation Fast Attack Crafts - 31, LPDs - 4 and 5 NOPVs. These ships put together and the value it comes to ₹1, 52,000 crores, again with the consolidated estimate.

    Answer, p.r hari

    It could be maybe, see this is AoN cost, it could vary ₹2,000 crores, so, plus this ₹8,700 crores RFP. Now, the number, okay, I will give further elaborate to give you a little more confidence. This is only from the defense segment, domestic defense segment. In addition, I am sure you are keeping track of the news that the Ministry of Shipping has aggregated the demand, shipbuilding demand of all the non-defense PSUs like the ONGC and so on for their commercial vessels. And the number of platforms at various places are identif ied so far is 207. It is a mandate number of 207, ranging from MR tankers, LR tankers, platform support capacity, Supramax, Aframax, Panamax type of tankers vessels, so that is 207 in number. The cost, again very conservative.

    Answer, p.r hari

    It should be to the tune of ₹5,000 crores. This is the second bucket. Now, then comes another segment i.e. the export segment for commercial ships. And just as recently as today, maybe around 1 hour back, I had a European client sitting with us discussing our project i.e. a kind of pr oactive and very positive approach that the European shipbuilders, shipowners are showing towards Indian companies. Every major shipyard in India today, be it CSL, be it GSL, be it HSL you name it or MDL, they all have commercial shipbuilding orders, including us. I mentioned that we have got 12 Multi-Purpose Vessels and this segment is going to expand exponentially. So, there are three segments, one is the ₹152,000 crores plus ₹8,700 crores defence assured kitt y. Then comes the 207, which is the top, own- drive directive, the Government of India is very closely monitoring the commercial shipbuilding segment and of course, the export.

    Answer, p.r hari

    And the number of shipyards in India, all big, small, all put together are just maybe, few of them are lumpy. I will take the big shipyards; big shipyards take big orders. So, if you put all these things in the perspective, the opportunity is available for all of us. And you know how we target projects by now. So, the share that we will be buying for, arriving for will be substantial in the coming years, let's say, 1, 2, 3 years. This is in addition to the assured order, which we shipbuilding segment and of course, the export. And the number of shipyards in India, all big, small, all put together are just maybe, few of them are lumpy.

    Answer, p.r hari

    I will take the big shipyards; big shipyards take big orders. So, if you put all these things in the perspective, the opportunity is available for all of us. And you know how we target projects by now. So, the share that we will be buying for, arriving for will be substantial in the coming years, let's say, 1, 2, 3 years. This is in addition to the assured order, which we are likely to sign the contract in the next 3, 4 months for the NGC. This is where we stand today.

  2. Question

    Sunil Shah: Yes. Sir, just a little bit more on the same point. Sir, as we speak, roughly, our current order book is about ₹20,000 crores, and we are L1 for the NGC, which is ₹25,000 crores. So , by end Page 10 of 14 of the year, this financial year, FY '26, as you stated, our order book could be approximately, let's say, ₹50,000 crores. But 1 year forward from now, FY '27 year -end, once at that point in time, even the P-17 Bravo would be announced. So, is it a safe assumption that the order book of today of ₹20,000 crores maybe in th e next 15 to 18 months could be upwards of ₹75,000 crores. Is my directional assumption , correct? That's what I would like to understand. Not in number, but

    Answer, p.r hari

    P.R. Hari: Absolutely right. And they are of the same frequency. I just hope your words come true. That is exactly that we are targeting. Right now, our order book is ₹20,000 crores. As you rightly said, of course, I would like to just make a slight correction to the NGC figure, that could be to the tune of around ₹30,000 crores order.

    Answer, p.r hari

    All put together, we should end the financial year with around ₹50,000 crores. And if we get the P -17 Bravo, let's take the best-case scenario of 4 ships coming to us or the worst-case scenario of 3 ships coming to us, the order could go up exactly the way you predicted.

  3. Question

    Sunil Shah: Great, sir. Just one point here, which I wanted to understand was, we are now getting into the capacity expansion mode of Brownfield and the West Coast opportunity as well, for which the DPR is there. But the current state of affairs of shipbuilding taking up a big step forward in that direction. So, our contract with Swan Energy / Swan Defence, wherein that port is in a way, unutilized. And for us, maybe tha t could be one big thing, because we signed an MoU, but actionable on that side. Because if the orders are coming, we also have that untapped idle capacity, which we can use. So, can we speed up the growth even more biddings as because it's so much on the platform. Undoubted

    Answer, p.r hari

    P.R. Hari: Yes, it is true that we have signed the MoU with the Swan Shipyard. And we are actually waiting for the right opportunity. See, first we need to get the right kind of platform, which has to be profitable. So, and why did we go to Swan specifically, because the type of ships, which, let's say, 250 meters plus ship, we cannot build with the current capacity that we have. It is for that reason we decided to go in for an MoU with Swan and also with L&T Shipyard. So, we are in discussion with few of the shipowners, as and when the right opportunity comes in here, the time, space, cost, project timeline has to match.

    Answer, p.r hari

    It will happen, but then I cannot say at this point. We are waiting for the right opportunity. While those MoUs exist, we decided as a management strategy that we must have our own captive facility for future i.e. the reason why we are looking at the greenfield facility. So, Swan, definitely very much the MoU is very much active, but we are waiting for the right opportunity.

  4. Question

    Harshit Kapadia: Congratulations for a good set of numbers. Could you give us a breakup of the ₹20,000 crore order book across all the ship categories which you have, sir?

    Answer, p.r hari

    P.R. Hari: Sure. I will start with the P -17 Alpha project. The P -17 Alpha project, the spending remaining order balance order values around ₹9,500 crores. The Anti -Submarine Shallow Water Craft is around ₹3,075 crores. The Survey Vessel (Large) is around ₹400 crores. The Next -Generation Offshore Patrol Vessel is around ₹3,250 crores and the 30mm Naval Surface Gun is around ₹150 crores.

    Answer, p.r hari

    Rest all vessels all put together, that comes to around okay, the Ocean Research Vessel is around ₹750 crores, the Acoustic Research Ship around ₹220 crores, the West Bengal Electric Ferry, again about ₹220 crores and the Coast Research Vessels is around ₹460 crores. Page 11 of 14 The Multi-Purpose Vessels for the German plant around ₹5,400 crores and the remaining order value on the dredger is about ₹95 crores. So, all put together, ships building order book is around ₹19,856 crores. Here, what I would like to bring to your notice is that there is a point of time from our entire shipbuilding order book was catering to Naval or Coast Guard orders. There was a point of time, 100% of our order book is from shipbuilding and shipbuilding, of course, constitute almost 95% to 98% of our total order value. 100% used to come from defence platforms. But now we have reached stage of ₹19,856 crores, 83% is coming from defence and balance 17% is coming from non-defence platforms.

  5. Question

    Harshit Kapadia: Yes, sir.

    Answer, p.r hari

    P.R. Hari: I would like to put it like this. It consists of balance two ships plus the B ase and Depot spares. In one of the earlier interactions, I have mentioned that in the overall project cost, x percentage is dedicated for the B ase and D epot spares for which the customer in consultation with us decided the Ba se and D epot spares and these spares are for long- term maintenance of the ships. So, this actual project value for the next 2 ships, the one which is ready, almost ready for delivery plus the large ships plus the Base and Depot spares all put together, it comes to ₹9,400 odd crores.

  6. Question

    Divyesh Shah: Sir, congratulations for the excellent performance from last 5 years and still continuing and hope we will continue same performance in the future, sir. Sir, as per your opening statement, we are growing at about as far as revenue is concerned, about 30%. So, my rough estimate is that for and we have got a visibility of minimum next 3 years, FY'26, FY'27 and FY'28. And if I calculate by FY '28, we will be somewhere around ₹10,000 crores to ₹11,000 crores. Sir, can you please elaborate the life after FY '28, our revenue, what is our strategy after '28? Because today morning in media, you just mentioned one line that after 3 years, it will be plateau out. So, can you elaborate th

    Answer, p.r hari

    And, also to give you assurance that we have briefed of the gap, and it is only to bridge this gap that we are taking orders at plenty for smaller Page 12 of 14 and medium-sized platforms. So again, I will put it in the right perspective. FY '26, FY '27, you will see a definite upward movement, consistent upward movement, then it could plateau out for 2 years and then the spike will start again. And hopefully, as one of the earlier speakers, Mr. Yash had mentioned that we are really looking forward for the P -17 Bravo also to sustain the growth in future.

  7. Question

    Anirudh Murarka: And sir, how do we intend to use it?

    Answer, p.r hari

    P.R. Hari: See, our own funds are ₹283 crores and project funds are ₹2,874 crores, which we have parked so that the payment especially from our side is for our partners or for other requirements. That is what we are planning for the current year.

  8. Question

    Kartik Bhatt: Okay. Sure. And sir, you also mentioned in one of the earlier calls about European companies looking at India as a shipbuilding destination for commercial ship building. Is the margin profile likely to be similar to or the defen ce building is slightly better? I mean, expecting -- I mean, considering that we get more orders in this segment going forward?

    Answer, p.r hari

    But for complex vessels, which are going to convert the exploration vessels or hybrid vessels, there the margins are going to be good. But we need to have a little patience because once we need to get our name established Page 14 of 14 like Cochin Shipyard, because they have started with commercial shipbuilding business almost 30 years back, from the time they are an established one. We started the commercial shipbuilding almost 4 years back. Today, we have a name. But for us to get complex platforms with higher margins, little more patience is required. I expect another 1 year to 2 years, it should be very much there.

Questions about this call

When was the Garden Reach Shipbuilders & Engineers Q2 FY26 earnings call transcript filed?
Garden Reach Shipbuilders & Engineers filed the transcript with the exchange on 14 Nov 2025. This page is built from that transcript.
What does this page list?
65 statements from the transcript across 6 topics, 55 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 18 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Garden Reach Shipbuilders & Engineers Q2 FY26 concall: Garden Reach Shipbuilders & Engineers Limited's order book stood at ₹20,205.56 crores as on 30th September · DalalOS