Mtar Technologies Q3 FY26 earnings call: MTAR Technologies Limited's closing order book stood at INR2,394 crores as of Q3 end, including INR1,370 crores of orders received across all sectors in Q3

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

MTAR Technologies Limited's closing order book stood at INR2,394 crores as of Q3 end, including INR1,370 crores of orders received across all sectors in Q3. MTAR Technologies Limited anticipates significant growth in the civil nuclear sector starting from next fiscal year, supported by the robust order pipeline from Kaiga 5 and 6. MTAR Technologies Limited is increasing its in-house manufacturing capacity to 12,000 boxes by end of the current fiscal year and plans to scale it to 20,000 units by end of FY '27. MTAR Technologies Limited recorded revenues of INR387 crores in the Clean Energy Fuel Cell segment during the first 9 months of the fiscal year and expects to deliver revenues of INR250 crores in Q4 by end of the current fiscal year. MTAR Technologies Limited said a huge shortage exists for fuel cells and that demand over the next 5 years will be phenomenal; meeting it depends on expansion plans, execution cycles and capacity expansion.

The numbers management gave

Results

  • MTAR Technologies Limited recorded revenues of INR387 crores in the Clean Energy Fuel Cell segment during the first 9 months of the fiscal year and expects to deliver revenues of INR250 crores in Q4 by end of the current fiscal year.
    Show source
    Accordingly, the company has recorded revenues of INR387 crores in the Clean Energy Fuel Cell segment alone during the first 9 months of the fiscal year and expect to deliver revenues of INR250 crores by end of the current fiscal year in Q4.
  • MTAR Technologies Limited achieved revenues of approximately INR72 crores in the Aerospace and Defence segment for the 9 months ended FY '26 from various customers.
    Show source
    In the Aerospace and Defence segment, we achieved revenues of approximately INR72 crores for the 9 months ended FY '26 from various customers.
  • MTAR Technologies Limited generated revenues of approximately INR84 crores in the Products and Other vertical segments and expects to close the year with revenues of around INR130 crores.
    Show source
    In the Products and Other vertical segments, the company has generated revenues of approximately INR84 crores, and we expect to close the year with revenues of around INR130 crores.
  • MTAR Technologies Limited's revenue from operation was INR278 crores in Q3 FY '26 as against INR174.5 crores in Q3 FY '25, an increase of 59.3% year over year.
    Show source
    On Y-o-Y performance, Q3 Y-o-Y for this year versus last year Q3, our revenue from operation at INR278 crores in Q3 FY '26 as against INR174.5 crores in Q3 FY '25, which translates to 59.3% increase on the Y-o-Y basis.
  • MTAR Technologies Limited's EBITDA was INR64 crores in Q3 FY '26 as compared to INR33.3 crores in Q3 FY '25, an increase of 92.5% year over year.
    Show source
    EBITDA reported at INR64 crores in Q3 FY '26 as compared to INR33.3 crores in Q3 FY '25.
  • MTAR Technologies Limited's profit before tax was INR46.1 crores in Q3 FY '26 as against INR21.4 crores in Q3 FY '25, an increase of 115.2% year over year.
    Show source
    Profit before tax stands at INR46.1 crores in Q3 FY '26 as against INR21.4 crores in Q3 FY '25, 115.2% increase on Y-o-Y basis.
Show 9 more statements

Results

  • MTAR Technologies Limited's profit after tax was INR34.7 crores in Q3 FY '26 as against INR16 crores in Q3 FY '25, an increase of 117.3% year over year.
    Show source
    Profit after tax was at INR34.7 crores in Q3 FY '26 as against INR16 crores in Q3 FY '25, which is 117.3% on Y-o-Y basis.
  • MTAR Technologies Limited's working capital days were 260 days during this quarter, primarily due to higher receivables associated with increased turnover.
    Show source
    As explained earlier, the working capital days are 260 days during this quarter, primarily due to the higher receivables associated with increased turnover.
  • MTAR Technologies Limited's gross profit was 46.1% in the current quarter and 49.5% for the 9 months ended; the difference was purely due to product mix, with lower gross margins in fuel cells and higher gross margins in domestic sales.
    Show source
    It is purely on the product mix.
  • MTAR Technologies Limited did about INR18 crores and odd in aerospace export orders in the quarter, minus a INR1 crore here and there; the number is approximate.
    Show source
    Srinivas Reddy: Yes, it's about INR18 crores and odd is what we have done for the aerospace export orders for this quarter minus a INR1 crore here and there.
  • MTAR Technologies is producing around 80 to 100 parts per month in the first-article development program.
    Show source
    So, we're averaging around 80 to 100 per month to be very realistic.
  • MTAR Technologies Limited's cash flow from operations was INR22 crores negative for this year because higher revenues were sitting in receivables.
    Show source
    The cash flow from operations was INR22 crores negative for this year because of the higher revenues, which are actually sitting in receivables.
  • MTAR Technologies Limited said its EBITDA margins would not be affected by lower gross margins because domestic sales require more effort than fuel-cell sales, which involve continuous production.
    Show source
    So, our EBITDA margins will not impact because of the gross margins.
  • MTAR Technologies Limited is tightly controlling inventory positioning based on quarterly needs and supplier lead times to reduce working capital days, while inventory days have come down as dispatches increased through exports.
    Show source
    And we are trying to maintain -- the CFO is trying to maintain a very tight control on the inventories being positioned based on the needs on a quarter-on- quarter basis and the lead time by the suppliers.

Money and capital

  • MTAR Technologies Limited is looking at approximately INR50 crores to INR60 crores for 20,000 capacity, with an additional INR40 crores and odd to increase capacity from 20,000 to 30,000; infrastructure is being built for 30,000.
    Show source
    It's a rough number right now, but it's approximately between INR50 crores to INR60 crores.

What it expects ahead

What management expects

  • MTAR Technologies Limited anticipates significant growth in the civil nuclear sector starting from next fiscal year, supported by the robust order pipeline from Kaiga 5 and 6.
    Show source
    We are also anticipating significant growth in the civil nuclear sector starting from next fiscal year, supported by robust order pipeline from Kaiga 5 and 6.
  • MTAR Technologies Limited expects to grow rapidly over the next 3 years, driven by its healthy order book, favourable industrial trends and continued execution excellence.
    Show source
    Overall, the company remains confident of sustaining the growth momentum and expect to grow rapidly over the next 3 years, driven by healthy order book, favourable industrial trends and continued execution excellence.
  • MTAR Technologies Limited is targeting working capital levels of approximately 200 to 210 days in the next fiscal year, supported by initiatives to optimize receivables and pursue customer advances.
    Show source
    The company is targeting working capital levels is approximately around 200 to 210 days in the next fiscal year, supported by ongoing initiatives to optimize our receivables like we are discussing on various advance opportunities from customers.
  • MTAR Technologies Limited guided for 30% to 35% growth and revenue of INR900 crores plus for FY '26.
    Show source
    So, we'll cross about INR900 crores plus for the financial year FY '26.
  • MTAR Technologies Limited expects about 50% revenue growth in FY '27, based on about INR900 crores plus in the current financial year.
    Show source
    And FY '27, we're expecting growth of about 50% revenue growth for FY '27 based on the current growth what we have, about INR900 crores plus in the current financial year.
  • MTAR Technologies Limited was very confident it would maintain or slightly exceed its 21% plus/minus 100 bps margin guidance, and said margins would further improve in the next financial year based on the improved margins shown in this quarter.
    Show source
    And obviously, the margins, what we said 21% plus/minus 100 bps will -- we are very confident to maintain or do slightly better than that.
Show 55 more statements

What management expects

  • ADA is assessing the defence program and will probably take another 2, 3 months to shortlist the company.
    Show source
    So probably they are saying it will take another 2, 3 months for them to shortlist the company.
  • MTAR Technologies Limited is working on aerospace first articles which, once converted to volume production, could bring almost twice the current number, closer to INR40 crores or even up to INR50 crores per quarter; the company expects aerospace revenue of about INR150 crores to INR160 crores next year.
    Show source
    So overall, next year, we can look at that kind of a situation where we can do about INR150 crores to INR160 crores in aerospace itself.
  • MTAR Technologies Limited plans to work with companies like GKN and IAI, which supply to Airbus and Boeing, and is looking to establish supply of Indian parts to Boeing, Airbus and similar companies over the next 1, 1.5 years.
    Show source
    So, to get Boeing and Airbus and such companies for Indian parts, we are also looking at establishing that as well moving forward over the next 1, 1.5 years.
  • MTAR Technologies Limited is looking at aerospace revenues of at least INR350 crores to INR400 crores by the end of the third year from various such customers.
    Show source
    And moving -- by end of the third year, we're looking at revenues of at least INR350 crores to INR400 crores coming in with various of such customers.
  • MTAR Technologies Limited expects many more reactors to be established over the next 5 to 10 years and says it will play a key role by supplying key assemblies.
    Show source
    So, a lot of -- if you look at the road map for the next 5 to 10 years, a lot more reactors are going to come into place, where MTAR would play a very key role in establishing such reactors by supplying the key assemblies to the nuclear reactors that we are looking at.
  • MTAR Technologies Limited expects the majority of the opportunity from SMRs that are going to be constructed; the other reactors are an added opportunity, and the government plans to establish 700-megawatt reactors over the next 5 to 8 years.
    Show source
    Page 12 of 19 MTAR Technologies Limited January 30, 2026 Srinivas Reddy: Yes, that's an added opportunity, but a lot of the other reactors the government itself is planning to establish 700-megawatt reactors over the next 5 to 8 years.
  • MTAR Technologies Limited expects to do much more than the conservative number under discussion, and expects further ramp-up in FY '28 as additional orders come in, say, in Q4 and maybe FY '27.
    Show source
    That's a pretty conservative number for us, but we'll do much more than that.
  • MTAR Technologies Limited expects a huge nuclear operations ramp-up and phenomenal order growth over the next 2, 3 years because of new reactors and the government announcing privatization; it is comfortable with INR800 crores plus, with many more orders expected over the next 1, 2 years.
    Show source
    One is on the operations side, the ramp-up on the operations side, but the number of orders which are going to kick in over the next 2, 3 years is going to be phenomenal because of the new reactors coming in and the government announcing the privatization.
  • MTAR Technologies Limited's Weatherford infrastructure is being readied in the SEZ near the airport; part of the revenues will begin in FY '27, with full-fledged revenues from the subsequent year onwards.
    Show source
    And so those revenues -- part of those revenues will kick in, in FY '27, and then it will go in a full-fledged manner from subsequent year onwards.
  • MTAR Technologies has conservatively taken 12,000 units for next financial year.
    Show source
    So basically, it is 12,000 units is what conservatively we have taken for next financial year.
  • MTAR Technologies expects a stronger closing order book next year, but says it is too premature to comment on the details of FY '27 orders.
    Show source
    It's too premature to comment on that right now, but we'll have even more stronger order book -- closing order book next year.
  • MTAR Technologies Limited expects margins in FY '27 to improve beyond the margins seen in Q3.
    Show source
    Srinivas Reddy: Margins, we have seen in Q3, we'll have a lot more improved margins beyond that, so in FY '27.
  • MTAR Technologies Limited expects the FBR reactors to be commissioned over the next 6 months, as communicated by the relevant parties.
    Show source
    We're expecting those reactors to get commissioned over the next 6 months is what they have said.
  • MTAR Technologies Limited sees an opportunity of about INR350 crores to INR400 crores per reactor, slightly more for new reactors because it will add End Shield and Calandria assemblies.
    Show source
    So probably it should be going up to about INR350 crores to INR400 crores of opportunity per reactor.
  • MTAR Technologies Limited said its average EBITDA margin in FY '26 is about 21% and that FY '27 would be a lot higher, in a much higher range.
    Show source
    FY '26, as I said, is -- average is about 21%, but FY '27 would be a lot higher than that, right?
  • MTAR Technologies Limited is targeting around 235 working-capital days in quarter 4 under the as-is scenario; if it receives customer advances, working-capital days would be less than 200, otherwise it estimates 235 days by year-end.
    Show source
    I think our working capital will drastically reduce if we get advances, then it will be less than 200 days.
  • MTAR Technologies Limited expects inventory days to come down by another 5 to 10 days with increased turnover in Q4.
    Show source
    But with increased turnover in Q4, days will come -- further come down to, say, another 5 to 10 days, it will come down.
  • MTAR Technologies Limited's revenues from the business it can generate will be beyond INR200 crores plus once all the equipment comes in over the next 2, 3 months.
    Show source
    But the kind of revenues that we can generate will be beyond INR200 crores plus once all the equipment comes in over the next 2, 3 months.
  • MTAR Technologies Limited expects to receive further orders from the refurbishment reactors during the quarter and beginning of the next quarter.
    Show source
    In addition, we expect to receive further orders from the refurbishment reactors during the quarter and beginning of the next quarter.
  • MTAR Technologies Limited anticipates a meaningful improvement in margins over the coming quarters, supported by operating leverage and a favourable shift in product mix towards higher volume production.
    Show source
    The company also anticipates a meaningful improvement in margins over the coming quarters, supported by operating leverage and favourable shift in product mix towards higher volume production.
  • MTAR Technologies Limited's return on capital employed is expected to improve further, supported by a high asset turnover ratio in the Clean Energy segment.
    Show source
    Return on capital employed is expected to improve even further, supported by high asset turnover ratio in the Clean Energy segment.
  • MTAR Technologies Limited expects working capital days to improve substantially over the coming quarters as it optimizes inventory levels, secures customer advances and strengthens receivables management.
    Show source
    While there may be a short-term impact on working capital days, we expect this to improve substantially over the coming quarters as we continue to optimize inventory levels, secure customer advances in a big way and strengthen receivables management.
  • MTAR Technologies Limited expects significant advances from customers to enable it to reduce its working capital cycle.
    Show source
    We're also expecting significant advances from customers, which will enable us to reduce our working capital cycle.
  • MTAR Technologies Limited said its aerospace vertical would grow as it converts first articles into volume production, which it had already done for a few customers.
    Show source
    But this particular vertical is going to grow more and more in aerospace sector as and when we convert the first articles into volume production, which we have already done in the case of a few customers.
  • The domestic market for MTAR Technologies Limited's battery storage systems will take a lot more time than the company can anticipate right now.
    Show source
    For domestic, there is a market, Page 9 of 19 MTAR Technologies Limited January 30, 2026 but still, it is not -- it's going to take a lot more time than what we can anticipate right now.
  • MTAR Technologies Limited expects nuclear dispatches to happen in a big way from Q1 of next year as nuclear projects are under work in progress because of their long gestation period; the majority of orders have been executed in the Clean Energy and Aerospace segments.
    Show source
    So once that is done, the dispatches from nuclear will happen from Q1 of next year in a big way.
  • MTAR Technologies Limited says its nuclear business previously did many reactors with breaks, but it does not expect those breaks to continue.
    Show source
    But now I don't see that break happening.
  • MTAR Technologies Limited expects Weatherford volume orders to come in this quarter.
    Show source
    We're expecting the volume orders also to come in this quarter.
  • MTAR Technologies expects next year's order inflows to be much higher than this year's, but Srinivas Reddy could not quantify the number; he expects a strong order book next year, much higher than today.
    Show source
    I can't really quantify the number right now, but we'll have a pretty good strong order book next year as well, much higher than what we have today.
  • MTAR Technologies expects its margins to improve substantially next year with higher operating leverage and better revenues, while declining to comment on the exact number.
    Show source
    And obviously, with higher operating leverage and better revenues next year, our margins will substantially improve.
  • MTAR Technologies Limited expects Q4 and year-end cash flows to be better than last year through customer advances.
    Show source
    Our Q4 and year-end cash flows will be better than the last year, will be better by getting these advances, yes.
  • MTAR Technologies Limited expects EMA certifications to be closed this quarter and to proceed with regular production for future requirements as an import substitute.
    Show source
    Hopefully, this quarter, all those certifications will be closed and we'll be through with the normal regular production what they need for the future as an import substitute.
  • The clean energy fuel cells and aerospace verticals are expected to witness exponential growth in the coming years, driven by favourable demand trends and expanding market opportunities. Replaced by a later filing.
    Show source
    Both the clean energy fuel cells and aerospace verticals are expected to witness exponential growth in the coming years, driven by favourable demand trends and expanding market opportunities.
  • MTAR Technologies Limited is confident it will improve and sustain margins over the coming quarters. Replaced by a later filing.
    Show source
    In addition, we are confident that we will improve and sustained margins over the coming quarters.
  • MTAR Technologies Limited said its aerospace segment is growing as a growth engine and will grow further in the coming years. Replaced by a later filing.
    Show source
    So that's the kind of -- that segment is growing pretty well as a growth engine for MTAR, and it will move further up in the coming years.
  • MTAR Technologies Limited is almost there in terms of various certifications for the aerospace activities it is pursuing. Replaced by a later filing.
    Show source
    We are almost there in terms of various certifications.
  • MTAR Technologies Limited expects year-on-year growth to follow an exponential kind of graph based on where it is today. Replaced by a later filing.
    Show source
    So, there will be a nice exponential kind of a graph or a growth happening year-on-year basis based on where we are today.
  • MTAR Technologies Limited expects its nuclear division to be a good year-on-year growth engine moving forward. Replaced by a later filing.
    Show source
    So obviously, that's how I said this area, nuclear division also is going to -- it will be a very good growth engine for MTAR moving forward on a year-on-year basis.

Orders

  • MTAR Technologies Limited's closing order book stood at INR2,394 crores as of Q3 end, including INR1,370 crores of orders received across all sectors in Q3.
    Show source
    The closing order book as of Q3 end stood at INR2,394 crores, where INR1,370 crores of orders across all sectors are received in Q3, reflecting robust industrial tailwinds.
  • MTAR Technologies Limited received orders worth INR1,080 crores in the clean energy fuel cells vertical during the first 9 months of the fiscal year, of which approximately INR645 crores was secured in Q3.
    Show source
    In the clean energy fuel cells vertical alone, the company received orders worth INR1,080 crores during the first 9 months of the fiscal year, of which approximately INR645 crores was secured in Q3.
  • MTAR Technologies Limited's order book stood at INR2,394.90 crores by end of December.
    Show source
    And our order book stood at INR2,394.90 crores by end of December.
  • MTAR Technologies Limited expects the INR500 crores nuclear orders to be executed within the next 36 months, with some projects to be executed within a year, some in 1.5 years, some in 2 years and some within 3 years.
    Show source
    So, all this INR500 crores should be executed within the next 36 months.
  • MTAR Technologies Limited is working on a prototype for the landing gear test set up assembly referred to the AMCA program; the prototype is worth around INR4 crores, and the requirement is expected to be very large in the coming years.
    Show source
    So, the prototype is worth around INR4 crores, but the requirement would be very huge in the coming years.
  • MTAR Technologies Limited's order book in the aerospace and defence sector was around INR325 crores, including INR120 crores of MNC orders in aerospace, INR120 crores odd in space and about INR80 crores in defence.
    Show source
    So, we have the overall order book of around INR325 crores in the aerospace and defence sector.
  • MTAR Technologies Limited says that if its nuclear order book is INR800 crores by the end of the year, it needs to be executed within the next 3 years.
    Show source
    If we have order book of INR800 crores in nuclear, let's say, by end of the year, we need to anyway exclude that within the next 3 years, so.
  • Most of MTAR Technologies Limited's orders have come from Kaiga 5 and 6; refurbishment is separate, and 2, 3 nuclear reactors are expected to start or be part of the program every year.
    Show source
    So, we got most of the orders from Kaiga 5 and 6 and obviously, refurbishment is different.
  • MTAR Technologies Limited considers INR300 crores, INR500 crores of additional order book every year a fair conservative number.
    Show source
    Srinivas Reddy: That's a very fair number what we are looking at because now they're planning Mahi Banswara 4 reactor, 700 megawatts with NTPC and NPCL combination, which is called ASHVINI.
  • MTAR Technologies finalized with Andritz about INR40 crores of hydro orders to be executed every year.
    Show source
    Recently, we finalized with Andritz about INR40 crores of orders in hydro to be executed every year.
  • MTAR Technologies is looking at about INR100 crores to INR120 crores of orders it can execute next year, and says it is almost at INR100-plus crores with these customers.
    Show source
    So, we're looking at about INR100 crores to INR120 crores of orders that we can execute next year.
  • MTAR Technologies expects around INR700 crores to INR800 crores worth of orders this quarter and says it closed the order book at INR2,800 crores.
    Show source
    We're expecting around INR700 crores to INR800 crores worth of orders this quarter.
  • MTAR Technologies Limited expects a closing order book close to INR2,800 crores by the end of financial year '26, based on expected order inflows including additional orders from the clean energy segment and nuclear space.
    Show source
    And we are going to -- our forecast for the end of this financial year is INR2,800 crores.
  • MTAR Technologies Limited received its highest ever order inflows in the Clean Energy Fuel Cells and Civil Nuclear Program segments during the current fiscal year-to-date.
    Show source
    During the current fiscal year-to-date, the company has received its highest ever order inflows in the Clean Energy Fuel Cells and Civil Nuclear Program segments, underscoring the strength Page 2 of 19 MTAR Technologies Limited January 30, 2026 of our growth trajectory.
  • MTAR Technologies Limited was declared L1 for the main landing gear test setup assembly.
    Show source
    Recently, the company was declared L1 for the main landing gear test setup assembly, marking a key developmental milestone.
  • MTAR Technologies Limited said various segmental orders for the AMCA program are being released.
    Show source
    So, there are various segmental orders that we are being released.
  • MTAR Technologies Limited has enough orders on hand to handle its existing orders. Replaced by a later filing.
    Show source
    Right now, we have enough orders on hand to handle the existing orders itself.

What it is building and selling

Projects and capacity

  • MTAR Technologies Limited is increasing its in-house manufacturing capacity to 12,000 boxes by end of the current fiscal year and plans to scale it to 20,000 units by end of FY '27.
    Show source
    We are currently in the process of increasing capacity to 12,000 boxes by end of the current fiscal year and plan to further scale this to 20,000 units by end of FY '27.
  • MTAR Technologies Limited is planning to create facilities to augment capacity up to 30,000 units in the subsequent year.
    Show source
    And further, we are planning to actually create facilities to augment capacity up to 30,000 units in the subsequent year.
  • MTAR Technologies Limited is expanding capacity to 20,000 units, hopefully by end of December, based on clear visibility given by the customer.
    Show source
    And then based on a clear visibility given by the customer, we are expanding in a phased manner to 20,000 units, hopefully by end of December.
  • MTAR Technologies Limited plans to move to Phase 2 of its expansion plan to about 30,000 units in the subsequent year.
    Show source
    And then we move on to the Phase 2 of the expansion plan to about 30,000 units in the subsequent year.
  • MTAR Technologies Limited plans to phase Bloom hot-box capacity expansion, with 12,000 units ready by March end, overall capacity of 20,000 units by December end, and 30,000 units by the subsequent year; the phasing is based on the customer demand forecast.
    Show source
    And Phase 2 is about -- overall 20,000 by December end and Phase 3 to 30,000 by the subsequent year.
  • MTAR Technologies Limited was utilizing 8,000 capacity in the current quarter and planned to utilize 12,000 capacity in Q1 of next year, with that capacity to be commissioned by end of March.
    Show source
    And the subsequent quarter, that is Q1 of next year, we'll be moving up to utilizing the 12,000 capacity, which will get commissioned by end of March.
Show 30 more statements

Projects and capacity

  • MTAR Technologies Limited plans to move all Bloom operations to a new plant in the SEZ near the airport, expanding capacity to 20,000 and subsequently to 30,000 units; the facility is intended to bring operations under one roof and improve operational efficiency.
    Show source
    And beyond that, we are moving the entire facility to the SEZ near the airport for the entire Bloom operations to expand to up to 20,000 and then subsequently to 30,000 unit.
  • MTAR Technologies Limited is looking at approximately INR50 crores to INR60 crores of capex for the clean energy expansion; the infrastructure is being built for 30,000 units, while equipment installation will initially cover an additional 8,000 units and later the next phase up to 30,000.
    Show source
    So, we are looking at roughly about INR50 crores to INR60 crores of capex that might be required, it's an approximate number.
  • The Mahi Banswara 4 reactor project is planned as a 700 megawatts project with NTPC and NPCL combination and is called ASHVINI; tenders will be floated for many such projects.
    Show source
    Srinivas Reddy: That's a very fair number what we are looking at because now they're planning Mahi Banswara 4 reactor, 700 megawatts with NTPC and NPCL combination, which is called ASHVINI.
  • MTAR Technologies is positioned to deliver 12,000 units and hopes its expansion to 20,000 units will happen by December.
    Show source
    But we are -- we have positioned ourselves to deliver 12,000 units and the expansion plan to 20,000 will happen by December, hopefully.
  • MTAR Technologies Limited is expanding hotbox capacity from 8,000 to 12,000 units in its existing plants, with commissioning by March; the expansion is expected to cost approximately INR35 crores to INR40 crores.
    Show source
    Everything is on track with that.
  • MTAR Technologies Limited expects the clean energy expansion capex to be finalized in the next couple of weeks.
    Show source
    It should be finalized in the next couple of weeks.
  • MTAR Technologies Limited has infrastructure for its nuclear programs; details of the PLI scheme are not yet known, and the company expects it to be beneficial for doing more.
    Show source
    So, the PLI -- whatever the details of the scheme are not yet known, but once the union budget is done, then we'll know more details. which will be definitely beneficial to the company to do more and more.
  • MTAR Technologies Limited has planned for increased quantity of ASPs each quarter in terms of capacity, with ASP capacity also set to increase as hot-box capacity increases.
    Show source
    So, we have already planned for the increased quantity of ASPs each quarter in terms of the capacity.
  • MTAR Technologies Limited is preparing its plant for Weatherford volume production, pushing for readiness by June and expecting full-fledged commercial operations by September.
    Show source
    We are pushing it to be ready by June, but by September, we should be in a full-fledged commercial operations.
  • MTAR Technologies Limited is setting up additional capacities, with machines coming in; it is doing partial volume and partial first articles right now.
    Show source
    We are setting up additional capacities; the machines are coming in as well.

Demand and pricing

  • MTAR Technologies Limited said a huge shortage exists for fuel cells and that demand over the next 5 years will be phenomenal; meeting it depends on expansion plans, execution cycles and capacity expansion.
    Show source
    And over the next 5 years, it's going to be phenomenal.
  • MTAR Technologies Limited said that over the next 3 to 5 years, the constraint is how much it can produce, not orders.
    Show source
    It's not about orders, but it's about how much you can produce.
  • MTAR Technologies Limited said demand continues to be the same and that tariffs would hopefully come down in the future, but tariffs would not affect the company's growth momentum as currently seen.
    Show source
    And hopefully, in the future, we hope that the tariffs would come down, but that's not going to affect the company's growth momentum as we see right now, which we have clearly seen in the current quarter as well.
  • MTAR Technologies Limited expects further reactor requirements as the government has given clearance for the private sector to set up nuclear reactors.
    Show source
    And also, there is a lot of requirements which are coming in with further reactors coming in and where the government has given clearance for the private sector to set up the nuclear reactors.
  • MTAR Technologies Limited expects to retain a majority market share in these units. Replaced by a later filing.
    Show source
    Given our strong engineering capabilities, cost competitiveness and execution track record, we expect to retain a majority market share in these units withstanding previous global uncertainties.

Segments

  • MTAR Technologies Limited has commenced participation in structural assembly tenders for AMCA.
    Show source
    We are actively engaged in strategic next-generation programs, including AMCA, where we have commenced participation in structural assembly tenders.
  • MTAR Technologies Limited has completed testing of its roller screws and is waiting for the final certification papers; the defence program requires multiple certifications because the roller screws are an import substitute.
    Show source
    We're just waiting for the final papers to come in.
  • MTAR Technologies Limited is doing first articles and entering volume production with its customers simultaneously while working on a number of packages. Replaced by a later filing.
    Show source
    We enter into volume production with the customers simultaneously, working on a number of packages.

Deals and partners

  • MTAR Technologies Limited's customer entered into a $2.65 billion agreement with AEP for supply of solid oxide fuel cells.
    Show source
    In this context, we are further encouraged by the recent development wherein our customer has entered into a $2.65 billion agreement with AEP for supply of solid oxide fuel cells.
  • MTAR Technologies Limited's customer is projected to grow at an average rate of approximately 30% through 2030, driven by demand from AI-powered data centres, conventional data centres and the global clean energy transition.
    Show source
    Driven by strong demand from AI-powered data centres, conventional data centres and the global clean energy transition, our customer is projected to grow at an average rate of approximately 30% through 2030.
  • MTAR Technologies Limited's customer is expected to add 2 gigawatts of capacity by the end of CY '26 and scale this to approximately 4 gigawatts in the subsequent years.
    Show source
    As part of this expansion, the customer is expected to add 2 gigawatts of capacity by the end of CY '26 and further scale this to approximately 4 gigawatts in the subsequent years.
  • MTAR Technologies Limited's customers are adding more packages based on its performance and achievements over the last 1 year.
    Show source
    They're adding more of the packages based on our performance and achievements that we have done over the last 1 year.
  • MTAR Technologies Limited has been in the nuclear business for 40 years and supplies all core nuclear reactor components and assemblies to NPCIL, a government entity.
    Show source
    So, we are supplying all the core nuclear reactor components and assemblies to government of NPCIL.
  • MTAR Technologies Limited plans to progressively graduate to structural assembly orders with multinational customers over the coming years as it enters into volume production for the existing parks.
    Show source
    With multinational customers, we plan to progressively graduate to structural assembly orders over the coming years as we enter into volume production for the existing parks.
  • MTAR Technologies Limited recently qualified for export of ball screws with its MNC customer and has started exports of its other products, including ball screws.
    Show source
    And we're also -- we also got qualified for export of ball screws with our MNC customer recently.
  • MTAR Technologies Limited has completed the first article for Fluence, but design changes are ongoing.
    Show source
    So, we are working -- we have done the first article.
  • Fluence has not given MTAR Technologies Limited specific feedback yet, and the work remains in progress.
    Show source
    But as of today, it is still a work in progress for us.
  • MTAR Technologies Limited has completed Weatherford first articles, and they have been approved; it is waiting for volume production.
    Show source
    We have already completed the Weatherford first articles.
  • MTAR Technologies Limited has many parts and assemblies for IAI.
    Show source
    There are a lot of parts, a lot of assemblies for IAI.
  • MTAR Technologies expects the complete batch of first articles for IAI to be completed by June, July, after which IAI will look at volume production.
    Show source
    IAI, the complete batch of first articles should be done and dusted by June, July.

Risks, rules and outside factors

Outside factors

  • MTAR Technologies Limited's value-add would remain more or less the same if Bloom reduces costs through design changes or reduced BOM costs, including a possible change from Inconel to SS; the company does not see realization changing otherwise.
    Show source
    Suppose if they replace Inconel with SS or any change of materials based on the design engineers working together with MTAR, then the BOM cost comes down, then the realization, but that will not affect us because our value-add remains the same.
  • MTAR Technologies Limited is not concerned with tariffs in relation to any of its MNC customers. Replaced by a later filing.
    Show source
    Srinivas Reddy: No, we are not concerned with tariffs at all with any of our MNC customers.

Rules and policy

  • The government is likely to announce a production-linked incentives, PLI scheme valued at INR18,000 crores to INR20,000 crores for manufacturing of critical nuclear components in the upcoming union budget.
    Show source
    Furthermore, the government is likely to announce a dedicated production-linked Page 3 of 19 MTAR Technologies Limited January 30, 2026 incentives, PLI scheme valued at INR18,000 crores to INR20,000 crores for manufacturing of critical nuclear components in the upcoming union budget.
  • MTAR Technologies Limited is doing major nuclear projects for NPCIL, and the PLI would help; the company is waiting for more details on it.
    Show source
    We are doing some major projects right now for them and the PLI would help, obviously.

Everything else said on the call

What management stressed

  • MTAR Technologies Limited is working on inventory management to reduce inventories and is confident it will manage working capital and cash flow from operations through customer advance initiatives despite a short-term cash flow impact from elevated receivables.
    Show source
    And also, we actually work on inventory management to see what else we can reduce inventories l. While there has been a short-term impact on cash flows due to elevated receivables, we are confident that we are going to manage our working capital and cash flow from operations by discussing with customers on advance initiatives.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Sir, my first question is on the offtake visibility for the capacity expansion, which we are doing for Bloom, taking hot boxes from 8,000 to 20,000. Now we are talking about taking it to 30,000. So, we understand that Bloom is seeing increased acceptance of its products, but can you give some more confidence on the offtake because India is having a higher tariff rate compared to our competitors? And how should we think of market share evolving over time?

    Answer, srinivas reddy

    Srinivas Reddy: Thank you for your questions. First, I would like to emphasize on the visibility on the expansion for the Clean Energy segment. So basically, we have a capacity, as you mentioned, 8,000 units, but we are expanding to 12,000 by end of March. Everything is on track with that. And then based on a clear visibility given by the customer, we are expanding in a phased manner to 20,000 units, hopefully by end of December. And then with that, we'll have a capacity of about 20,000 units. And then we move on to the Phase 2 of the expansion plan to about 30,000 units in the subsequent year.

    Answer, srinivas reddy

    The infrastructure will be built for 30,000 units, but the equipment will be planned in such a way that it's done in 2 different phases or I would say, 3 different phases. Phase 1 is 12,000, which will be ready by March end. And Phase 2 is about -- overall 20,000 by December end and Phase 3 to 30,000 by the subsequent year. So, this is being done purely based on the kind of demand forecast what we have received from the customer, and that's how we are doing it. And as far as tariffs are concerned, as I mentioned even in my earlier call that we are not anyway concerned with being a technology company and the way we have progressed in terms of our competitiveness and various developmental programs we have done for the customer. The demand continues to be the same. And hopefully, in the future, we hope that the tariffs would come down, but that's not going to affect the company's growth momentum as we see right now, which we have clearly seen in the current quarter as well.

  2. Question

    Piyush Sevaldasani: Sir, my next question is -- yes, I think that's very clear. Sir, my next question is on the gross margins. We have seen a decline in gross margins this quarter. Could you explain why -- I think we were going through pricing negotiations with Bloom last quarter. Can you help us understand what would be the sustainable gross margins?

    Answer, gunneswara rao

    Gunneswara Rao: Yes. While this current period is -- current quarter is 46.1% gross profit, whereas 9 months ended, if you look at, it is 49.5%. It is purely on the product mix. Just because gross margin is lower, it doesn't mean that our EBITDA will affect. As we explained it many times, the gross margins in the fuel cells is lower, in case of domestic, it is higher. But however, the efforts required to make the domestic sales is more compared to the fuel cells because it is continuous production, and we were doing over the year. So, our EBITDA margins will not impact because of the gross margins.

  3. Question

    Piyush Sevaldasani: Sure. And then, sir, on the nuclear order, which we have received for INR500 crores, can you please help us understand what could be the execution cycle for this?

    Answer, srinivas reddy

    Srinivas Reddy: The INR500 crores orders should be executed within a period of -- over a period of 3 years. That's how it is done. That's the timeline that we are looking at. There are various projects out of this INR500 crores. Some will be executed within a year, some 1.5 years, some in 2 years and some projects within 3 years. So, it's a combination of all this. So, all this INR500 crores should be executed within the next 36 months.

    Answer, srinivas reddy

    Srinivas Reddy: Okay. See, the 8,000-capacity utilization, I think we are doing it in the current quarter, Renu, because it's not only about the equipment, but also ramping up, there are a lot of activities involved in the manufacturing process. So, we are fully geared up for that. And the subsequent quarter, that is Q1 of next year, we'll be moving up to utilizing the 12,000 capacity, which will get commissioned by end of March. And beyond that, we are moving the entire facility to the SEZ near the airport for the entire Bloom operations to expand to up to 20,000 and then subsequently to 30,000 unit. So that will be completely a new plant which we are trying to establish near the airport, everything under one roof so that it becomes more operationally more efficient. That's the basic plan, what we are looking at.

  4. Question

    Renu Baid: When we look -- what is the value spend capex that you're looking for this expansion? Initially, we had guided that it would be something like INR25 crores, INR30 crores for the first phase. So how are we looking at the overall capex for clean energy expansion? Page 7 of 19 MTAR Technologies Limited January 30, 2026 Srinivas Reddy: So basically, that's right.

    Answer, srinivas reddy

    For 12,000, it's about 35,000 to 40,000 whatever numbers we have given earlier. But for the -- going from 12,000 to 20,000, the infrastructure is being done for 30,000. The building, everything is being constructed for the long-term requirement of the company. But the equipment installation will be done for additional 8,000 units. And subsequently, we'll do for the next phase up to 30,000. So, we are looking at roughly about INR50 crores to INR60 crores of capex that might be required, it's an approximate number. We're still working on it.

    Answer, srinivas reddy

    It should be finalized in the next couple of weeks. So that's the approximate number what we are looking at.

  5. Question

    Renu Baid: Sure. Second, in terms of the -- you did mention that for landing gear assembly, recently L1. So, what kind of revenue opportunity we expect in the aerospace business from the customer here?

    Answer, srinivas reddy

    Srinivas Reddy: No, that's landing gear test set up assembly that's referred to the AMCA program. We are just working on the prototype. It's just the beginning of the whole program, right? So, the prototype is worth around INR4 crores, but the requirement would be very huge in the coming years. So, there are various segmental orders that we are being released. So that's just the starting point, and we'll see how it goes over the coming years. But the Aerospace segment, as I said earlier, we are doing extremely well.

    Answer, srinivas reddy

    We are doing a lot of MNC customers right now. We are growing pretty rapidly. We are still doing some first articles. We enter into volume production with the customers simultaneously, working on a number of packages. So that's the kind of -- that segment is growing pretty well as a growth engine for MTAR, and it will move further up in the coming years.

  6. Question

    Renu Baid: Got it. Sir, lastly, would you want to share what is the revised guidance for fiscal '27 and -- sorry, for fiscal '26? And any initial guidance that you would like to indicate for the next fiscal year '27?

    Answer, srinivas reddy

    Srinivas Reddy: No, the guidance would remain the same. We would -- as I said earlier that we would do 30% to 35% growth guidance for this year. So, we'll cross about INR900 crores plus for the financial year FY '26. And FY '27, we're expecting growth of about 50% revenue growth for FY '27 based on the current growth what we have, about INR900 crores plus in the current financial year. And obviously, the margins, what we said 21% plus/minus 100 bps will -- we are very confident to maintain or do slightly better than that. And the margins would further improve in the next financial year based on the kind of improved margins we have shown in this quarter.

    Answer, srinivas reddy

    The long-term contract is for 5 years, 10 years like that. But the orders what we reflect in the order book is based on the orders that they keep releasing to us on a quarter-on-quarter basis. So, we have the overall order book of around INR325 crores in the aerospace and defence sector. Specific to aerospace, we have INR120 crores of MNC orders. And then space, we have INR120 crores odd and defence about INR80 crores. So, the total is INR325 crores. But this particular vertical is going to grow more and more in aerospace sector as and when we convert the first articles into volume production, which we have already done in the case of a few customers.

    Answer, srinivas reddy

    And it's an ongoing process. They're adding more of the packages based on our performance and achievements that we have done over the last 1 year.

  7. Question

    Meet Jain: We did almost INR31 crores of revenue in this quarter for aerospace. Just want to understand, as you mentioned that the first articles has been completed and we started batch production for a few of the customers. I want to get a sense of the quantum of that?

    Answer, srinivas reddy

    Srinivas Reddy: Yes, it's about INR18 crores and odd is what we have done for the aerospace export orders for this quarter minus a INR1 crore here and there. I'm giving an approximate number.

  8. Question

    Meet Jain: Got it, sir. Apart from that, my second question is regarding the products and other segments. In terms of order book expansion, we saw almost INR137 crores of order we added in this quarter. So, as we know that during this segment, we also cater to fuel cells, we cater to nuclear power. So INR137 crores order is also linked to the strong order influence of Bloom part?

    Answer, srinivas reddy

    Srinivas Reddy: Yes. On the ASP division, yes, we also have a lot of orders coming in from that division. Apart from the other products that we do for ball screws, water lubricated bearings. And we're also -- we also got qualified for export of ball screws with our MNC customer recently. So that's something which is very positive for the company. So, we started doing exports of our other products as well in terms of ball screws right now.

    Answer, srinivas reddy

    Srinivas Reddy: No, I actually mentioned about this last time as well. So, it's taking its own time to get this going in terms of what we need to do in the battery storage systems. For domestic, there is a market, Page 9 of 19 MTAR Technologies Limited January 30, 2026 but still, it is not -- it's going to take a lot more time than what we can anticipate right now. So, let's see how it goes. That's something which we need to see as and when there's a major development, then we'll let you know about it, Bala.

    Answer, srinivas reddy

    Srinivas Reddy: We already have the infrastructure for the nuclear programs that we are doing. So, the PLI -- whatever the details of the scheme are not yet known, but once the union budget is done, then we'll know more details. which will be definitely beneficial to the company to do more and more. But we have the infrastructure to handle that already.

    Answer, srinivas reddy

    Srinivas Reddy: That's being still assessed by ADA right now, the defence program, they are assessing it. So probably they are saying it will take another 2, 3 months for them to shortlist the company. So, let's see what happens.

    Answer, srinivas reddy

    Srinivas Reddy: So, when it comes to the first question, the aerospace, what you're looking at INR18 crores, INR19 crores is just the beginning, right? We have been growing step by step in aerospace. So, part of the first articles, what we are working on, once it gets converted to volume production, we're looking at almost twice the number as what you can see right now, closer to INR40 crores or even up to INR50 crores per quarter. So overall, next year, we can look at that kind of a situation where we can do about INR150 crores to INR160 crores in aerospace itself. And as far as Fluence is concerned, we're still working on it. So, we are working -- we have done the first article. Now they are a little bit -- there are a lot of design changes.

    Answer, srinivas reddy

    They have not given us any specific feedback on that as of now. They're still working on it. But as and when something goes -- some improvements are done on that, then we'll see how it goes. But as of today, it is still a work in progress for us. Page 10 of 19 MTAR Technologies Limited January 30, 2026 Akshay J.: Sure, sir.

  9. Question

    So, if I ask a follow-up, just on the aerospace bit, commercial -- a lot of our clientele is currently defence-led aerospace globally, IAIs. I mean, GKN is definitely commercial. But what is our kind of -- are we working with Airbus, Boeing, other commercial aerospace companies that make larger planes for products because, I mean, that would really bring scalability to the business, right? I mean, could you give some thoughts on where are we on that part of the business?

    Answer, srinivas reddy

    Srinivas Reddy: So that's the plan, right? So, the plan is to work with companies like GKN and IAI, which are very good companies, who also supply to Airbus and Boeing, not that they don't supply. So, to get Boeing and Airbus and such companies for Indian parts, we are also looking at establishing that as well moving forward over the next 1, 1.5 years. So that's how we look at the aerospace vertical in a very aggressive manner in terms of building it more and more. And moving -- by end of the third year, we're looking at revenues of at least INR350 crores to INR400 crores coming in with various of such customers. So that's our vision and the road map, what we have over the next 3 years.

  10. Question

    Akshay J.: Okay. Next 3 years from now, right? Okay. Okay. And that is MNC aerospace, right?

    Answer, srinivas reddy

    Srinivas Reddy: Exactly, because there's a lot of certifications and processes that are involved. We are almost there in terms of various certifications. So, it's a matter of time that we can get into those kind of activities moving forward.

    Answer, srinivas reddy

    Srinivas Reddy: So yes, that's a good question. So, we have already planned for the increased quantity of ASPs each quarter in terms of the capacity. And as and when we increase the capacity of the hot boxes, the ASP capacities also will go up accordingly. So that's also being planned simultaneously. Balasubramanian: Okay. And how much capex we have planned for to increase to 30,000 units, sir?

    Answer, srinivas reddy

    Srinivas Reddy: I've said earlier about this. It's a rough number right now, but it's approximately between INR50 crores to INR60 crores. That's what we're looking at for 20,000 and 30,000 comes later, right? So that's probably an additional INR40 crores and odd to increase it from 12,000 to -- sorry, from 20,000 to 30,000. The infrastructure is being built for 30,000. Page 11 of 19 MTAR Technologies Limited January 30, 2026 Balasubramanian: Okay, sir. Sir, in Q2, I think some of the dispatches has been delayed nearly 4 weeks.

    Answer, srinivas reddy

    Srinivas Reddy: That's very marginal, right? I mean whatever we did -- see a lot of projects in nuclear are under work in progress because of the long gestation period. So once that is done, the dispatches from nuclear will happen from Q1 of next year in a big way. So that's how it is. But majority of the orders have been executed based on the Clean Energy segment and on the Aerospace segment as well. Balasubramanian: Okay. Because why I'm asking this question is because our inventory days came down from 282 days to 210 days in Q3.

    Answer, srinivas reddy

    Srinivas Reddy: Yes, because as the dispatches have gone up, the inventory days have also come down because of the exports that we have done. And we are trying to maintain -- the CFO is trying to maintain a very tight control on the inventories being positioned based on the needs on a quarter-on- quarter basis and the lead time by the suppliers. So, we are monitoring that very closely right now so that our working capital days also gets reduced as much as possible. Balasubramanian: Okay, sir. Sir, my last question, BOM cost is hardly less than like a single-digit percentage, which is impacted by tariffs. Whether we are completely absorbing right now or it's passed through to the customers?

    Answer, srinivas reddy

    Srinivas Reddy: No, we are not concerned with tariffs at all with any of our MNC customers.

    Answer, srinivas reddy

    Srinivas Reddy: So basically, we have been in the nuclear business for the last 40 years. So, we are supplying all the core nuclear reactor components and assemblies to government of NPCIL. We are doing some major projects right now for them and the PLI would help, obviously. We are waiting for more details on that. And also, there is a lot of requirements which are coming in with further reactors coming in and where the government has given clearance for the private sector to set up the nuclear reactors. So, a lot of -- if you look at the road map for the next 5 to 10 years, a lot more reactors are going to come into place, where MTAR would play a very key role in establishing such reactors by supplying the key assemblies to the nuclear reactors that we are looking at. Charvin: Okay.

    Answer, srinivas reddy

    Okay. So, majority of the opportunity we are expecting from the SMRs that are going to be constructed. Is it right? Page 12 of 19 MTAR Technologies Limited January 30, 2026 Srinivas Reddy: Yes, that's an added opportunity, but a lot of the other reactors the government itself is planning to establish 700-megawatt reactors over the next 5 to 8 years.

    Answer, srinivas reddy

    So, let's see how it goes. Right now, we have enough orders on hand to handle the existing orders itself.

    Answer, srinivas reddy

    Srinivas Reddy: I think very comfortably. That's a pretty conservative number for us, but we'll do much more than that. Aman: Okay. And FY '28 will be further ramp up because we'll get additional orders, say, in Q4 and maybe FY '27 or so.

    Answer, srinivas reddy

    Srinivas Reddy: Yes, exactly. So, we have to -- so it's a very simple calculation. If we have order book of INR800 crores in nuclear, let's say, by end of the year, we need to anyway exclude that within the next 3 years, so. Aman: Sure, sir. And in terms of, say, next 2, 3 years, where do you see this nuclear order book? Do you think this can grow on top of this INR800 crores or INR800 crores to INR1,000 crores is, say, a ceiling before anything newer happens?

    Answer, srinivas reddy

    Srinivas Reddy: I will not talk about the -- how much of orders, but definitely, I see a huge ramp up. One is on the operations side, the ramp-up on the operations side, but the number of orders which are going to kick in over the next 2, 3 years is going to be phenomenal because of the new reactors coming in and the government announcing the privatization. So, a lot of things are happening. So right now, we are very comfortable with this INR800 crores plus a lot more orders are going to kick in over the next 1, 2 years in any case. So, in the past, we should have -- we never had a very strong order book. We used to do a lot of reactors, but with a break. But now I don't see that break happening.

    Answer, srinivas reddy

    So, there will be a nice exponential kind of a graph or a growth happening year-on-year basis based on where we are today. Aman: Sure, sir. And just completing this part. So, we got most of the orders from Kaiga 5 and 6 and obviously, refurbishment is different. But what I see is every year, 2, 3 nuclear reactors are supposed to start or at least be part. So, is it fair to assume INR300 crores, INR500 crores additional order book every year on the conservative side?

    Answer, srinivas reddy

    Srinivas Reddy: That's a very fair number what we are looking at because now they're planning Mahi Banswara 4 reactor, 700 megawatts with NTPC and NPCL combination, which is called ASHVINI. So, a Page 13 of 19 MTAR Technologies Limited January 30, 2026 lot of such projects are coming in, the tenders will be floated. So obviously, that's how I said this area, nuclear division also is going to -- it will be a very good growth engine for MTAR moving forward on a year-on-year basis. Aman: Sure, sir. Next set of question is on, say, Weatherford and IAI. So, the First Article Inspection is taking a little longer than maybe our expectation. So, do you expect Weatherford to start scaling in FY '27 itself or maybe it is delayed to FY '28, '29?

    Answer, srinivas reddy

    Srinivas Reddy: That's a good question. We have already completed the Weatherford first articles. It's been approved already. The only thing is we are waiting for is for the volume production. Now to do the volume production, our plant is getting ready. We are pushing it to be ready by June, but by September, we should be in a full-fledged commercial operations. So, then we get into the volume production.

    Answer, srinivas reddy

    We're expecting the volume orders also to come in this quarter. So that's where we stand as far as Weatherford is concerned. It's all about doing the volume production. The infrastructure is getting ready for that in the SEZ near the airport. And so those revenues -- part of those revenues will kick in, in FY '27, and then it will go in a full-fledged manner from subsequent year onwards. Aerospace, we are not -- the first articles are not taking time. There are a lot of parts, a lot of assemblies for IAI.

    Answer, srinivas reddy

    Already one of the customers, we are already doing into volume production. And they've added a lot more packages. So, both happen simultaneously, the volume and the first articles. IAI, the complete batch of first articles should be done and dusted by June, July. So that's the timeline we're looking at. And once it is done, then they look at volume production. So, in aerospace, the requirements are very stringent, as we all know, right?

    Answer, srinivas reddy

    It's for aircrafts and all that. So, we are right on track with that as far as we are concerned. There are a lot of R&D and development program happens in first articles, which we are successfully doing it. And each month, we are doing more than close to about 100 parts per month, which is phenomenal. The average -- industry average is 300 parts per year, whereas we're doing 100 per month. So, we can't do faster than that. So, we're averaging around 80 to 100 per month to be very realistic.

    Answer, srinivas reddy

    Srinivas Reddy: No, it's not just one customer. We're working with GE, working with Andritz, Voith, a number of customers, right? Recently, we finalized with Andritz about INR40 crores of orders in hydro to be executed every year. We have done that recently. So that's purely based on our past kind of deliverables that we have given to all these customers. A lot of work has been done in that sector over the last 2 years. So [inaudible 0:46:20] is another company.

    Answer, srinivas reddy

    So, we are working with various customers. So, we're looking at about INR100 crores to INR120 crores of orders that we can execute next year. We are almost there, INR100-plus crores purely with these customers. A lot of work has been done. So, this is what I keep saying. What you don't see in the balance sheet is the kind of work MTAR has been doing on the background with various customers, developing various first articles, proving our capabilities to the customers and all that you will see the results over the next year and moving forward as well.

Questions about this call

When was the Mtar Technologies Q3 FY26 earnings call transcript filed?
Mtar Technologies filed the transcript with the exchange on 5 Feb 2026. This page is built from that transcript.
What does this page list?
117 statements from the transcript across 11 topics, 58 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 10 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.