NCC Q2 FY26 earnings call: NCC Limited's order book was INR 71,957 crores as of 30th September '25, compared to INR 7,087 crores at the end of the previous quarter

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Order book was INR 71,957 crores as of 30th September '25, compared to INR 7,087 crores at the end of the previous quarter. The company withdrew its guidance for the financial year '26 because of the challenging external business environment and elongated payment cycles, and will be able to share an update by March '26. Mumbai tunnel project and Mumbai coastal road project had obtained the required clearances, and the projects were expected to start moving after not moving in the previous 2–3 quarters. The company reported turnover of INR 4,585 crores in the second quarter of the financial year '25-'26, compared with INR5,224 crores in the corresponding quarter of the previous year. Debt stood at INR 1,852 crores at the beginning of Q2 FY '26, and net debt after cash and cash equivalents was INR 1,497 crores.

The numbers management gave

Results

  • The company reported turnover of INR 4,585 crores in the second quarter of the financial year '25-'26, compared with INR5,224 crores in the corresponding quarter of the previous year.
    Show source
    In the second Page 2of 17 NCC Limited November 07, 2025 quarter of the FY '26, the company has reported a turnover of INR 4,585 crores as against INR5,224 crores in the corresponding quarter of the previous year.
  • Consolidated EBITDA margin was 8.7% in the second quarter of the financial year '25-'26.
    Show source
    The EBITDA margin stood at 8.7% on a consol basis.
  • The company achieved cumulative turnover of INR 9,793 crores for the first half of FY '26, compared with INR 10,782 crores in the same period last year.
    Show source
    For the first half of FY '26, the company achieved a cumulative turnover of INR 9,793 crores compared to INR 10,782 crores in the same period last year.
  • Stand-alone turnover was INR 3,774 crores in Q2 of FY '26, compared with INR4,480 crores in the corresponding quarter of the previous year, a decline of 16%.
    Show source
    Turnover reported in Q2 of FY '26 is INR 3,774 crores as against turnover of INR4,480 crores in the corresponding quarter of the previous year, which was a decline of 16% at the stand-alone level.
  • Consolidated turnover for H1 of FY '26 was INR 8,204 crores, compared with INR 9,227 crores, a decline of 11%.
    Show source
    When it comes to 6 months, the turnover for Q2 for the H1 of FY '26 is INR 8,204 crores as against INR 9,227 crores, which was a decline of only 11% at the consolidated level.
  • Turnover for H1 of FY '26 was INR9,793 crores, compared with INR 10,783 crores, a decline of 9%.
    Show source
    When it comes to 6 months for the H1 of FY '26, it is INR9,793 crores as against INR 10,783 crores shows a decline of 9%.
Show 40 more statements

Results

  • Stand-alone EBITDA was 7.45% in Q2 of the financial year '25-'26, compared with 9.03% in the corresponding quarter of the previous year.
    Show source
    At the stand-alone level, we achieved EBITDA of 7.45% for Q2 as against 9.03% of the corresponding quarter of the previous year.
  • Stand-alone PBT was 3.1% and PAT was 2.68% in Q2 FY '26, compared with PBT of 4.86% and PAT of 3.58% in the corresponding quarter of the previous year.
    Show source
    PBT, we achieved 3.1% and Page 3of 17 NCC Limited November 07, 2025 PAT we achieved 2.68% in the current quarter, that is Q2 FY '26 as against PBT of 4.86% and PAT of 3.58% reported in corresponding quarter of the previous year.
  • Consolidated EBITDA was 8.66%, PBT was 4.51% and PAT was 3.37% in Q2 FY '26, compared with EBITDA of 8.52%, PBT of 4.79% and PAT of 3.12% in the corresponding quarter of the previous year.
    Show source
    At consolidated level, we achieved EBITDA of 8.66% and PBT of 4.51% and PAT of 3.37% in the current quarter as against EBITDA of 8.52%, PBT of 4.79% and PAT of 3.12% reported in the corresponding quarter of the previous year.
  • Working capital, excluding cash and margin money deposits, was INR 5,406 crores, or 33% of turnover, at the end of Q2 FY '26.
    Show source
    At the end of Q2 FY '26, it stands at INR 5,406 crores, which is 33% of the turnover.
  • Working capital stood at 110 days at the end of Q2 FY '26.
    Show source
    In terms of working capital days, it is 110 days.
  • Debtors outstanding decreased from INR 3,296 crores to INR3,277 crores by the end of Q2 FY '26, while the number of days increased from 77 to 78 days; debtors were 65 days in the corresponding quarter of the previous year.
    Show source
    Debtors outstanding at the end of Q2 has decreased from INR 3,296 crores to INR3,277 crores and the number of days increased from 77 to 78 days in the current quarter.
  • Unbilled revenue was INR 6,662 crores, 41% higher in Q2 FY '26 than INR5,937 crores at Q4 of the last year.
    Show source
    It stands at INR 6,662 crores, which is 41% up for Q2 as against INR5,937 crores at Q4 of the last year.
  • Retention money stood at INR1,993 crores for Q2 FY '26, compared with INR1,870 crores at the beginning of the year.
    Show source
    Retention money stands at INR1,993 crores for Q2 as against INR1,870 crores at the beginning of the year.
  • Mobilization advances stood at INR 2,961 crores at the end of September '25, compared with INR 2,944 crores at the end of June, a net increase of about INR 17 crores.
    Show source
    Advances stood at INR 2,961 crores as at the end of September '25 as against INR 2,944 crores as at the end of June, a net increase of about INR 17 crores.
  • ROCE was 9.82 at the end of Q2 FY '26, compared with 14.61 at end of financial year '25.
    Show source
    The ROCE stands at 9.82 as against 14.61 at end of February -- financial year '25 end.
  • Return on net worth was 9.53 at the end of Q2 FY '26, compared with 14.43 at end of financial year '25.
    Show source
    Return on net worth is 9.53 as against 14.43.
  • EPS was INR1.61 at the end of Q2 FY '26, compared with INR 2.55 for the corresponding quarter.
    Show source
    EPS stands at INR1.61 as at the end of Q2 FY '26 as against INR 2.55 for the corresponding quarter.
  • Inventory stood at INR 1,725 crores at the end of September.
    Show source
    Inventory stood at INR 1,725 crores as at end of September.
  • The company said that an extended and aggressive monsoon in the second quarter of the financial year '25-'26 impacted some projects, and delayed permissions and ROWs delayed the start of some projects that had been expected to pick up pace in the quarter.
    Show source
    Some of the permission, some of the ROWs, they have delayed the start of those projects.
  • Unprecedented rains in Q2 and elongated payment cycles were the two main reasons for NCC Limited's turnover decline.
    Show source
    These are the 2 main reasons which has caused a drop in the turnover.
  • Heavy rains in AP, Maharashtra, Karnataka and UP affected NCC Limited's project execution.
    Show source
    So considering all these things, the impact is there.
  • Heavy and unprecedented rains in other states, including Karnataka and Andhra Pradesh, reduced NCC Limited's project execution, with rains continuing beyond the season.
    Show source
    So that is the reason why there was a reduction in the execution.
  • Profit increase in the consolidated accounts came from subsidiaries Pachhwara Coal Mining and Urban, and from smart meters.
    Show source
    So the profit is coming from subsidiaries like Pachhwara Coal Mining, Urban and also on the smart meters.
  • The company said it was receiving timely payment for projects it had started executing and was billing.
    Show source
    Sanjay Pusarla: AP receivables as on date, they are very live because all the projects we started executing and whatever projects we are executing and billing, we are getting the money in time.

Money and capital

  • Debt stood at INR 1,852 crores at the beginning of Q2 FY '26, and net debt after cash and cash equivalents was INR 1,497 crores.
    Show source
    The debt at the beginning of the quarter stood at INR 1,852 crores and net debt after cash and cash equivalents is INR 1,497 crores.
  • Debt stood at INR 2,115 crores and net debt was INR 1,890 crores at the end of Q2 FY '26, compared with debt of INR1,773 crores and net debt of INR 1,624 crores at the end of Q2 FY '25.
    Show source
    At the end of quarter 2 FY '26, it stood at INR 2,115 crores and net debt of INR 1,890 crores.
  • Debt increased by INR 263 crores during Q2 FY '26.
    Show source
    There is an increase in debt by INR 263 crores.
  • Debt-equity ratio was 0.28 at the end of Q2 FY '26, compared with 0.25 at the end of Q2 FY '25 and 0.20 at the beginning of the year.
    Show source
    The debt-equity ratio stands at 0.28 at the end of Q2 FY '26 as against 0.25 at the end of Q2 FY '25.
  • Of NCC Limited's mobilized advances, 63% were interest-bearing, with average interest of around 9.17%; interest-bearing advances decreased from 79% to 63% during the half year.
    Show source
    Of these mobilized advances, 63% are interest-bearing and the average interest comes to around 9.17% and interest-bearing advances decreased from 79% to 63% during the half year.
  • The company incurred capex of INR77 crores in Q2 and cumulatively INR169 crores for the first half of '26, against budgeted capex of INR1,050 crores for regular projects.
    Show source
    We have incurred a capex of INR77 crores in Q2 and cumulatively, we incurred INR169 crores for the first half of '26 as against the budgeted capex of INR1,050 crores for the regular projects.
  • Capex was revised from INR 750 crores to INR 1,050 crores.
    Show source
    Earlier -- in the earlier call, we said the INR 750 crores is the capex , but the capex now revised to INR 1,050 crores.
  • Investments were INR 1,191 crores at the end of September.
    Show source
    The investments are INR 1,191 crores as at the end of September.
  • The company reported investments in subsidiaries of INR 1,191 crores and loans to group companies of INR 179 crores.
    Show source
    Sanjay Pusarla: Investments into subsidiaries INR 1,191 crores and loans to the group companies INR 179 crores.
  • The company said the INR 179 crores figure excluded Vizag Urban, which was INR 391 crores.
    Show source
    That number was INR 391 crores.
  • JJM outstanding receivables were almost similar to INR 1,700 crores reported last quarter; it was waiting for certifications, after which the money flow would happen.
    Show source
    Sanjay Pusarla: It is almost similar to those numbers, okay?
  • Receivables for Jal Jeevan projects were in a similar range to INR1,700 crores.
    Show source
    And as far as the receivables are concerned, it is also in the similar range as like what we said at INR1,700 crores.
  • The company said there was no overdue in its INR 1,700 crores of receivables, which remained at the same level as last time, as billing and collections continued to churn the outstanding balance.
    Show source
    Sanjay Pusarla: There is no overdue as such because last time we said INR 1,700 crores, even now also the same level.
  • The company collected about INR 600 crores from the government in Q2.
    Show source
    Sanjay Pusarla: It is about that money only, near to that.
  • The company increased its capex outlook from INR750 crores to INR1,050 crores because it received a major mining order in October that had not previously been envisaged.
    Show source
    So that is the reason we have increased the capex from INR750 crores to INR1,050 crores.
  • INR 6,800- odd crores large order required capex for the specific project, leading it to decide to increase capex.
    Show source
    So that is the reason we need to incur that capex for this specific project.
  • The company had invested INR 230 crores in smart meters in the current half year, bringing total smart meter investment to INR 300 crores.
    Show source
    The total investment that has gone into the smart meters till now is INR 300 crores.
  • The company has to make another INR280 crores of incremental investment in the smart meter projects.
    Show source
    Sanjay Pusarla: Another INR280 crores we have to make.
  • Cash and cash equivalents were INR355 crores at the end of June 2025, compared with INR789 crores at the end of March '25.
    Show source
    Cash and cash equivalents, it is INR 224 crores as on 30th September '25 and INR 355 crores as at the end of June '25.
  • Margin money deposits were INR671 crores at the end of June '25 and INR639 crores at March '25.
    Show source
    Margin money deposits, INR671 crores at the end of September and same is the number at the end of June '25 also.
  • The company said slower payments were confined to water projects and that it was otherwise okay in all other areas.
    Show source
    It was only those payments which are related to the water project.

What it expects ahead

What management expects

  • The company withdrew its guidance for the financial year '26 because of the challenging external business environment and elongated payment cycles, and will be able to share an update by March '26.
    Show source
    Due to the challenging external business environment and elongated payment cycles, we have decided to withdraw the guidance for the financial year '26 and will be able to share any update by March '26.
  • The company had withdrawn its guidance and said it was not prudent to discuss H2; it would provide an update in March '26.
    Show source
    Neerad Sharma: We have already answered that question that we have withdrawn the guidance.
  • The company said it would update on its outlook by end of March, when it expected to have more clarity, and hoped the situation would improve so it could discuss the outlook.
    Show source
    We will update you by end of March, we will have more clarity, and I hope the situation improves, then we should be in a position to talk about this.
  • The company said that elongated payment cycles, with clients unable to make stipulated payments on time, were among three factors that convinced it to revisit its guidance.
    Show source
    So these are the 3 important factors that has sort of convinced us to revisit the guidance.
  • The company withdrew its guidance and said it would revisit the figures and come back by March; the margin outcome was difficult to anticipate.
    Show source
    When we say that we have withdrawn the guidance, we have withdrawn the guidance, right?
  • The company said low turnover revenue in the first half reduced its ability to absorb fixed costs, and it may reach the lower guidance depending on turnover and improvement in Q3.
    Show source
    So depending on the turnover, depending on the situation that improvement that will happen in Q3, we may reach the lower guidance.
Show 28 more statements

What management expects

  • The company was expecting payments on Jal Jeevan projects around month end or in the first fortnight of December.
    Show source
    We are also expecting some payments to happen in this month, maybe month end or so or maybe the first week of -- first fortnight of December, we are expecting.
  • The company expected improvement in the Jal Jeevan project situation once the expected payments came in.
    Show source
    Once these things are coming, probably the improvement will be there in all these cases.
  • The company expected projects awarded in the first and second quarters to start producing revenue from Q4 onwards.
    Show source
    And those projects which have been awarded in the first and second quarters, maybe those projects will get start producing the revenue maybe in the Q4 onwards.
  • The company expects clients to continue releasing payments in the normal course of business, although a few cases may have elongated payments; projects other than those where receivables are held up have no problem receiving money, and project execution will continue.
    Show source
    And we expect that the clients also continue to release the payments, except maybe in a few cases where there may be elongated payments.
  • The company withdrew its guidance because elongated payments in a particular segment would have an impact and it was not in a position to predict what would happen in those cases in the near future.
    Show source
    That is the reason we are very optimistic that -- and we have given our withdrawal of the guidance.
  • The company said its order book was strong and that it was able to execute, and it was positive in the coming quarters. Replaced by a later filing.
    Show source
    And order book is strong, and we are able to execute, and we are positive in the coming quarters.
  • The company had received nothing in the first half and expected to receive payments in the second half. Replaced by a later filing.
    Show source
    Sanjay Pusarla: No, we have not received anything in the first half, expecting in the second half.
  • The company expected conditions to improve going forward, citing media reports that the monsoon was already retreating. Replaced by a later filing.
    Show source
    Neerad Sharma: We hope things to improve by -- on the basis of the media reports, it looks like that monsoon is already retreating and things should improve going forward.
  • The company said it would return to discuss its outlook for the future. Replaced by a later filing.
    Show source
    And for the future, we will come back to you and hopefully talk about how are we really looking at the future.

Orders

  • Order book was INR 71,957 crores as of 30th September '25, compared to INR 7,087 crores at the end of the previous quarter.
    Show source
    As of 30th September '25, our order book stands at INR 71,957 crores compared to INR 7,087 crores at the end of the previous quarter.
  • The company booked new orders worth INR6,223 crores during the second quarter of the financial year '25-'26, mainly from its Buildings, Water and Irrigation divisions.
    Show source
    During the quarter, we booked new orders worth INR6,223 crores, which is mainly from Buildings, Water and Irrigation divisions.
  • Cumulative order inflow stood at INR 9,881 crores for H1 FY '26.
    Show source
    The cumulative order inflow for H1 FY '26 stood at INR 9,881 crores.
  • Building division order book stood at INR 22,492 crores, about 31% of the total order book, as of the second quarter of the financial year '25-'26.
    Show source
    The order book in the Building division stands at INR 22,492 crores, which is about 31% of the total order book.
  • Transportation division order book was INR 17,361 crores, about 24% of the order book, as of the second quarter of the financial year '25-'26.
    Show source
    The Transportation division has an order book of INR 17,361 crores, which is about 24% of the order book.
  • Electrical division order book was INR 15,013 crores, 21% of the total order book, as of the second quarter of the financial year '25-'26.
    Show source
    The order book in the Electrical division stands at INR 15,013 crores, which is 21% of the total order book.
  • Water and Railway division held INR 7,553 crores of order book, about 10% of the total order book, as of the second quarter of the financial year '25-'26.
    Show source
    The Water and Railway division holds INR 7,553 crores, which is about 10% of the total order book.
  • Irrigation division had INR5,394 crores of order book, about 7% of the total order book, as of the second quarter of the financial year '25-'26.
    Show source
    The Irrigation division has INR5,394 crores, which is about 7% of the total order book.
  • Mining division order book stood at INR 4,137 crores, about 6% of the total order book, as of the second quarter of the financial year '25-'26.
    Show source
    The Mining division order book stands at INR 4,137 crores, which is about 6% of the total order book.
  • The company received orders worth INR 6,223 crores in Q2 of the financial year '25-'26.
    Show source
    Orders received in Q2 is INR 6,223 crores.
  • The company received cumulative orders, including orders in October, worth INR 17,420 crores in the financial year '25-'26.
    Show source
    And cumulatively, as Mr. Neerad said, we have received orders, including the orders in the month of October stands at INR 17,420 crores.
  • Order book of INR 71,957 crores comprised a stand-alone order book of INR 64,326 crores and INR 7,632 crores of subsidiaries at the end of September '25.
    Show source
    So the order book of INR 71,957 crores includes stand-alone order book of INR 64,326 crores and INR 7,632 crores of the subsidiaries.
  • The company had INR 17,420 crore of orders as of the call, and its order inflow was moving in line with its anticipation.
    Show source
    And as we speak, we already have as of today, INR 17,420 crore orders.
  • The company said orders received in March '25 may start getting executed in Q3 and Q4 after the mobilization, design clearances and work-front clearances, which generally take 5 to 6 months.
    Show source
    So now all those orders, which have come in the month of March '25 will start getting executed maybe in Q3 and Q4.
  • The company had about INR7,000 crores of Jal Jeevan projects order pending to be executed, including projects in UP and other states under the same mission.
    Show source
    We have about INR7,000 crores of order pending to be executed, okay?
  • About INR 7,000 crores of NCC Limited’s orders are water projects.
    Show source
    One thing is that about INR 7,000 crores orders, which we talked about on the water projects.
  • Order book was Rs.71,568 cr.
    Show source
    Our order book stands at INR 71,957 crores at the end of September '25.
  • The company said orders received at the fag end of the last year in March were not held back because of clearances or an NGT order, and no orders were currently hampered by those reasons.
    Show source
    At the moment, there are no orders which have been hampered because of this.
  • The company said its entire order book was executable. Replaced by a later filing.
    Show source
    Sanjay Pusarla: So the entire order book is executable, okay?

What it is building and selling

Projects and capacity

  • Mumbai tunnel project and Mumbai coastal road project had obtained the required clearances, and the projects were expected to start moving after not moving in the previous 2–3 quarters.
    Show source
    So even those projects also, which were not being moving in the last 2, 3 quarters, I think those projects also will start moving now.
  • Time period for the smart meter projects may be another 1 year to 1.5 years.
    Show source
    Sanjay Pusarla: Our time period may be another 1 year to 1.5 years.
  • The company had invested about INR 70 crores in smart meter projects.
    Show source
    In the first quarter, it was INR 70 crores.
  • Other state projects included projects in Odisha, Jharkhand and Karnataka.
    Show source
    Sanjay Pusarla: It is Odisha is there, Jharkhand is there and Karnataka is there.

Segments

  • The company had a couple of projects for private residential developers.
    Show source
    Neerad Sharma: A couple of them, a couple of projects we have for the private developers.
  • The company executes smart-meter projects as an EPC contractor, with profit captured partly at the SPV level and partly at the NCC level.
    Show source
    And the profit is captured partly at the SPV level and also at the NCC level.
Show 1 more statement

Segments

  • The company was actively looking at the private capital development space and had some projects from the private sector. Replaced by a later filing.
    Show source
    And we do have some projects from the private sector as well.

Everything else said on the call

Other

  • The value would be about INR 1,000 crores to INR 1,500 crores.
    Show source
    Neerad Sharma: The value would be about INR 1,000 crores to INR 1,500 crores.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Vaibhav Shah: Thank you. On behalf of JM Financial, I welcome everybody to Q2 FY '26 earnings conference call of NCC Limited. We have from the management, Shri R.S. Raju, Director of Projects; Shri Sanjay Pusarla, Executive Vice President, Finance and Accounts; and Shri Neerad Sharma, Head Strategy and Investor Relations. Now I hand over the call to the management for their opening remarks, followed by Q&A session. Over to you, sir.

    Answer, neerad sharma

    In the second part, our CFO will cover the financial performance for the second quarter. In the last part, we will take up your questions and clarifications. Due to the challenging external business environment and elongated payment cycles, we have decided to withdraw the guidance for the financial year '26 and will be able to share any update by March '26. As of 30th September '25, our order book stands at INR 71,957 crores compared to INR 7,087 crores at the end of the previous quarter. During the quarter, we booked new orders worth INR6,223 crores, which is mainly from Buildings, Water and Irrigation divisions. In the second Page 2of 17 NCC Limited November 07, 2025 quarter of the FY '26, the company has reported a turnover of INR 4,585 crores as against INR5,224 crores in the corresponding quarter of the previous year. The EBITDA margin stood at 8.7% on a consol basis.

    Answer, neerad sharma

    For the first half of FY '26, the company achieved a cumulative turnover of INR 9,793 crores compared to INR 10,782 crores in the same period last year. The cumulative order inflow for H1 FY '26 stood at INR 9,881 crores. Now I will break down the order book segment-wise as of second quarter. The order book in the Building division stands at INR 22,492 crores, which is about 31% of the total order book. The Transportation division has an order book of INR 17,361 crores, which is about 24% of the order book. The order book in the Electrical division stands at INR 15,013 crores, which is 21% of the total order book. The Water and Railway division holds INR 7,553 crores, which is about 10% of the total order book.

    Answer, neerad sharma

    The Irrigation division has INR5,394 crores, which is about 7% of the total order book. The Mining division order book stands at INR 4,137 crores, which is about 6% of the total order book. Now I will hand over to Mr. Sanjay Pusarla with a request to take us through the detailed financial performance of the company. Over to you.

    Answer, sanjay pusarla

    Sanjay Pusarla: Good morning, ladies and gentlemen. This is Sanjay Pusarla, CFO from NCC Limited. I'm pleased to announce the financial results of Q2 of FY '26 of NCC Limited. My announcement will be in the sequence of order book, revenue, profitability, debt movement and some of the important balance sheet items. To start with order book. Our order book stands at INR 71,957 crores at the end of September '25. You are aware the order book at the beginning of the year is INR 71,568 crores.

    Answer, sanjay pusarla

    Orders received in Q2 is INR 6,223 crores. And cumulatively, as Mr. Neerad said, we have received orders, including the orders in the month of October stands at INR 17,420 crores. So the order book of INR 71,957 crores includes stand-alone order book of INR 64,326 crores and INR 7,632 crores of the subsidiaries. Coming to the revenue. Turnover reported in Q2 of FY '26 is INR 3,774 crores as against turnover of INR4,480 crores in the corresponding quarter of the previous year, which was a decline of 16% at the stand-alone level. When it comes to 6 months, the turnover for Q2 for the H1 of FY '26 is INR 8,204 crores as against INR 9,227 crores, which was a decline of only 11% at the consolidated level. The turnover reported in Q2 FY '26 is INR 4,585 crores as against the turnover of INR5,224 crores in the corresponding quarter of the previous year, a decline of 12%.

    Answer, sanjay pusarla

    When it comes to 6 months for the H1 of FY '26, it is INR9,793 crores as against INR 10,783 crores shows a decline of 9%. Let's get into the profitability. At the stand-alone level, we achieved EBITDA of 7.45% for Q2 as against 9.03% of the corresponding quarter of the previous year. PBT, we achieved 3.1% and Page 3of 17 NCC Limited November 07, 2025 PAT we achieved 2.68% in the current quarter, that is Q2 FY '26 as against PBT of 4.86% and PAT of 3.58% reported in corresponding quarter of the previous year. At consolidated level, we achieved EBITDA of 8.66% and PBT of 4.51% and PAT of 3.37% in the current quarter as against EBITDA of 8.52%, PBT of 4.79% and PAT of 3.12% reported in the corresponding quarter of the previous year. Let's get into the debt movement. The debt at the beginning of the quarter stood at INR 1,852 crores and net debt after cash and cash equivalents is INR 1,497 crores.

    Answer, sanjay pusarla

    At the end of quarter 2 FY '26, it stood at INR 2,115 crores and net debt of INR 1,890 crores. And at the end of Q2 FY '25, the same is INR1,773 crores and net debt of INR 1,624 crores. There is an increase in debt by INR 263 crores. The debt-equity ratio stands at 0.28 at the end of Q2 FY '26 as against 0.25 at the end of Q2 FY '25. And beginning of this year, it was 0.20. So coming to the working capital, excluding cash and margin money deposits. At the end of Q2 FY '26, it stands at INR 5,406 crores, which is 33% of the turnover.

    Answer, sanjay pusarla

    In terms of working capital days, it is 110 days. Debtors outstanding at the end of Q2 has decreased from INR 3,296 crores to INR3,277 crores and the number of days increased from 77 to 78 days in the current quarter. It is 65 days for the corresponding period of the -- corresponding quarter of the previous year. Coming to unbilled revenue. It stands at INR 6,662 crores, which is 41% up for Q2 as against INR5,937 crores at Q4 of the last year. Retention money stands at INR1,993 crores for Q2 as against INR1,870 crores at the beginning of the year. Coming to the mobilization advances.

    Answer, sanjay pusarla

    Advances stood at INR 2,961 crores as at the end of September '25 as against INR 2,944 crores as at the end of June, a net increase of about INR 17 crores. Of these mobilized advances, 63% are interest-bearing and the average interest comes to around 9.17% and interest-bearing advances decreased from 79% to 63% during the half year. Cash and cash equivalents, it is INR 224 crores as on 30th September '25 and INR 355 crores as at the end of June '25. Margin money deposits, INR671 crores at the end of September and same is the number at the end of June '25 also. Coming to the capex. We have incurred a capex of INR77 crores in Q2 and cumulatively, we incurred INR169 crores for the first half of '26 as against the budgeted capex of INR1,050 crores for the regular projects. Earlier -- in the earlier call, we said the INR 750 crores is the capex , but the capex now revised to INR 1,050 crores.

    Answer, sanjay pusarla

    Coming to the investor-related ratios. The ROCE stands at 9.82 as against 14.61 at end of February -- financial year '25 end. Return on net worth is 9.53 as against 14.43. EPS stands at INR1.61 as at the end of Q2 FY '26 as against INR 2.55 for the corresponding quarter. Inventory stood at INR 1,725 crores as at end of September. The investments are INR 1,191 crores as at the end of September. With this, I conclude my results announcement.

  2. Question

    We can start the Q&A. Neerad Sharma: We can start the question-and -answer session now.

    Answer, sanjay pusarla

    Sanjay Pusarla: It is very clear, sir. Even Mr. Neerad has covered in his initial opening remarks. There is unprecedented rains that happened in the Q2. In addition to that, there were elongated payment cycle. These are the 2 main reasons which has caused a drop in the turnover. And nothing else than that. And order book is strong, and we are able to execute, and we are positive in the coming quarters.

    Answer, mohit kumar

    Mohit Kumar: Understood, sir. And are we seeing a recovery now, sir, as you're already in the midst of Q3, middle of Q3. So are you seeing a recovery some sort of which can help us post a better number compared to last year -- last year H2? Neerad Sharma : We have already shared with you, Mr. Mohit, that we will update you, give us some time. We will update you by end of March, we will have more clarity, and I hope the situation improves, then we should be in a position to talk about this.

    Answer, mohit kumar

    Mohit Kumar: Understood, sir. And sir, how is the order inflow environment? Are you seeing the weakness also percolating to the ordering environment in general? Neerad Sharma : I mean ordering, if you really see the number of orders that we have bagged as today, this continues to be healthy in line with what we had anticipated. And as we speak, we already have as of today, INR 17,420 crore orders. So I mean we -- the order inflow is moving in line with our anticipation.

  3. Question

    So broadly, if I look at the numbers, it seems that the Building and Water segment, we have seen a decent degrowth, where particularly the Building segment, which is in terms of order book, if you look at even for last 3, 4 quarters also, it is in the similar line. So not able to understand is it that there, again, we are facing major issues apart from whatever the recent projects that we have bagged in last 6 to 9 months, there obviously, it seems that the execution has not picked up. But still not able to understand why we are withdrawing the revenue guidance?

    Answer, neerad sharma

    Neerad Sharma: Yes. Let me -- I think my colleague, Mr. Pusarla, has already answered this question, but let me try to reiterate. Firstly, what we have seen is in the second quarter, we have had extended and aggressive sort of monsoon. So some of the projects got impacted. The second one is some of the projects that we had anticipated would pick up pace in this quarter has not happened. Some of the permission, some of the ROWs, they have delayed the start of those projects. The third and important reason is we have -- I have already talked about this at the very outset.

    Answer, neerad sharma

    We have noticed elongated payment cycle. The clients are not able to make the stipulated payments on time. So these are the 3 important factors that has sort of convinced us to revisit the guidance. And we believe that in the fitness of things, it is always better to communicate openly with the market. So this is what we have done.

  4. Question

    Shravan Shah: Okay. Got it. Second, in terms of the margin also, so there previously, we are looking at 9%. So already in 1H, we are 8.3%. So there still one can see the similar 8%, 8.5% in the second half or there is a possibility that we can even have a 9% in the second half EBITDA margin?

    Answer, neerad sharma

    Neerad Sharma: Mr. Shah, it is very difficult to say. When we say that we have withdrawn the guidance, we have withdrawn the guidance, right? It is very difficult to anticipate. If it was possible, I mean, we would have shared that number with you. But we will revisit all these things and come back to you by March. Sanjay Pusarla: But one thing is that we are very near to whatever lower band we have given. And it depends on how it will move in Q3, okay?

    Answer, neerad sharma

    If you see that the turnover revenue was low in the first half. And when the turnover is low, obviously, it is understood that absorbing the fixed cost will be low. So depending on the turnover, depending on the situation that improvement that will happen in Q3, we may reach the lower guidance.

  5. Question

    Shravan Shah: Got it. And on the data point on the investment -- total investment in subsidiaries and associates, if you can spell also break it into the loans to subsidiary and associates.

    Answer, sanjay pusarla

    Sanjay Pusarla: Investments into subsidiaries INR 1,191 crores and loans to the group companies INR 179 crores.

  6. Question

    Shravan Shah: Okay. So it seems there is a significant repayment on the loan front would have happened from INR452- odd crores, which was the number from March to INR 179 crores.

    Answer, sanjay pusarla

    Sanjay Pusarla: No, this is other body corporate, which is Vizag Urban, which is there. That was not part of this number what I told you. That number was INR 391 crores.

  7. Question

    Shravan Shah: Thank You.

    Answer, sanjay pusarla

    Last time we said INR28,000 proceed to work that was orders received in the month of March. That is the reason it was told that orders had to be started for execution. So same is the case even the orders which have come in March '25. Generally, what happens, you will have a mobilization period, one. Second thing, you will have a design clearances that are required to be done and also the clearances which are required to start the work at the work front. These are all the things which generally take 5 to 6 months, it will take. So now all those orders, which have come in the month of March '25 will start getting executed maybe in Q3 and Q4.

  8. Question

    Parikshit Kandpal: Okay. The second question is again the continuation of the same. So besides these INR 28,000 crores of orders of the order book, are there any orders where -- if you can quantify where the approvals like NGT or environmental issues or other approvals have not come in from the statutory bodies and we have not been able to execute. So is there any other -- any further pipeline of orders beyond the INR28,000 crores or that is included in INR 28,000 crores?

    Answer, sanjay pusarla

    Sanjay Pusarla: No, INR28,000 crores is not that it was held back because of some clearances or NGT order or other things. Those orders that have come in the month of March at the fag end of the last year. So that was the reason the execution getting happening only maybe in Q3 and Q4. And the second question, you're asking that as at the moment, are there any orders which have been stalled because of these reasons. At the moment, there are no orders which have been hampered because of this.

  9. Question

    Parikshit Kandpal: Okay. Now on the building side, sir, I mean, when we look at the other developers of the players, we have seen very strong build- out in the private sector building orders, especially on the residential side. So I just want to understand how is your thought process on the private building orders on the resi side? Are we bidding there? Are we do we have order books there? And what's the outlook on that segment beyond the government buildings, which we typically do?

    Answer, neerad sharma

    Neerad Sharma: Yes. Mr. Kandpal, we are actively looking at the private capital development space as well. And we do have some projects from the private sector as well.

  10. Question

    Parikshit Kandpal: Private residential, I'm talking about, sir. So private residential sector, I'm talking about players like...

    Answer, neerad sharma

    Neerad Sharma: A couple of them, a couple of projects we have for the private developers.

Show 12 more questions
  1. Question

    Parikshit Kandpal: Okay. And just lastly, on the JJM outstanding receivables, which was INR 1,700 crores last quarter. So what's the number now? And what would be overdue beyond 6 months here where you would have like -- should have come. So I just want to understand on the debt side, if these numbers would have come in, so what our debt would have been?

    Answer, sanjay pusarla

    Sanjay Pusarla: It is almost similar to those numbers, okay? There are -- we are waiting for some certifications from them. Once the certifications happen, the money flow also will happen. It's almost on the similar lines. Page 8of 17 NCC Limited November 07, 2025 Parikshit Kandpal: How much is overdue on this?

  2. Question

    Parikshit Kandpal: I'm saying, sir, how much of this INR 1,700 crores is overdue right now beyond 6 months, I mean, which should have come in. So I understand that last time we had INR 4,000 crores of order backlog from JJM and we were planning to execute this entirely in this year. So against that INR4,000 crores of pending, how much should have been the working capital or the debtor is outstanding? It was more generalized basis rather than being overdue right now?

    Answer, sanjay pusarla

    Sanjay Pusarla: Yes. So the order -- let me give you some picture on this Jal Jeevan projects. We have about INR7,000 crores of order pending to be executed, okay? Then that is a number that includes not only the projects of UP, the projects which are there in other states also, which are under the same mission. So INR 9,000 crores is the -- INR7,000 crores is the order book that need to be executed. And as far as the receivables are concerned, it is also in the similar range as like what we said at INR1,700 crores. It is in the similar range..

    Answer, sanjay pusarla

    We are also expecting some payments to happen in this month, maybe month end or so or maybe the first week of -- first fortnight of December, we are expecting. Once these things are coming, probably the improvement will be there in all these cases.

  3. Question

    Parikshit Kandpal: My question was, sir, out of this INR 1,700 crores, how much is overdue. I mean client -- because of the delay, the client is not paying. So the receivable collection would have passed from the deadline, which was originally supposed to happen. So how much is the overdue in this INR1,700 crores?

    Answer, sanjay pusarla

    Sanjay Pusarla: There is no overdue as such because last time we said INR 1,700 crores, even now also the same level. But we used to keep billing and we are getting money also. The money is getting churned and the outstandings will become latest. It's not the overdue.

  4. Question

    Parikshit Kandpal: So you have collected INR 600 crores in Q2 from the government?

    Answer, sanjay pusarla

    Sanjay Pusarla: It is about that money only, near to that. Page 9of 17 NCC Limited November 07, 2025 Parikshit Kandpal: Okay Understood.

  5. Question

    Ashish Shah: Yes, is it better now? Yes. So sir, what I wanted to probably understand a bit, you said that there is obviously the heavy rain impact and there is elongated payment cycles. Now you just mentioned to the previous participant question that you've done about close to INR 600 crores in JJM in the second quarter. So is that what you're primarily referring to by saying that because of elongated payment cycles, you have not been able to execute? Or are there other areas, other sectors or other projects where also you're not able to execute because of this payment cycle?

    Answer, sanjay pusarla

    Sanjay Pusarla: I think we need to give a little elaborate reply on this. So like if you see in other states, like in AP, you have got heavy rains, which are even continuing even today. In Maharashtra, you have got heavy rains. In Karnataka, you have got heavy rains, which are unprecedented, unexpected rainfall was there in this year. And UP, same thing. So considering all these things, the impact is there. It is not only the UP projects.

    Answer, sanjay pusarla

    It is also the projects which are being executed in other states because of these rains, heavy rains. If you see the rains, which were unprecedented and if you see the rains in south, like in Karnataka or in Andhra Pradesh, the rains were so heavy that it was never expected, maybe the heaviest rainfall. And even beyond the season, the rains are happening. So that is the reason why there was a reduction in the execution.

  6. Question

    Ashish Shah: Understood. On the rain part, it is understood, sir. What I'm also saying is in terms of slow payment cycles, it is obvious that Jal Jeevan is moving slower. Besides the Jal Jeevan, is there any specific thing that you want to highlight where the payments are probably slower than expected, hence, you're not able to execute as much as you would have liked?

    Answer, sanjay pusarla

    Sanjay Pusarla: No, sir. It was only those payments which are related to the water project. But otherwise, we are okay with all other areas.

  7. Question

    And the rest is primarily which other state besides UP?

    Answer, sanjay pusarla

    Sanjay Pusarla: It is Odisha is there, Jharkhand is there and Karnataka is there.

  8. Question

    Ashish Shah: Understood. The other thing, sir, is in terms of capex , we just mentioned that we've increased our capex outlook from INR 750 crores earlier to INR 1,050 crores. On what is this account, sir?

    Answer, sanjay pusarla

    Sanjay Pusarla: We have received one major order in the mining in the month of October, okay? So for that, we have not envisaged before. So that is the reason we have increased the capex from INR750 crores to INR1,050 crores.

    Answer, neerad sharma

    Neerad Sharma: Mr. Shah, it's a large order. It's a large order of INR 6,800- odd crores. So that is the reason we need to incur that capex for this specific project. So that is the reason we have decided to increase the capex.

  9. Question

    Ashish Shah: Can I continue, sir? My other thing -- this is Ashish here. So my other question is that if I look at the numbers in terms of stand-alone and consol, this time, there is about INR 50 crores incremental profit coming in consol accounts from stand-alone. Can you just broadly break it up from where is this coming? And is there any one-off there? Also, where are we capturing the value of the smart metering projects in Maharashtra? Is that getting captured in consol or in stand-alone? That's all from my side.

    Answer, sanjay pusarla

    Sanjay Pusarla: So the profit increase in -- one second. So the profit is coming from subsidiaries like Pachhwara Coal Mining, Urban and also on the smart meters. And as far as your question for smart meters are concerned, the execution is happening at NCC level as an EPC contractor. And the profit is captured partly at the SPV level and also at the NCC level.

  10. Question

    Ashish Shah: Okay Understood. Thank you.

    Answer, neerad sharma

    Neerad Sharma: The value would be about INR 1,000 crores to INR 1,500 crores. What is your second question, Mr. Qazi?

  11. Question

    Parvez Qazi: Okay. So then the related question is, I mean, of our overall order book, ultimately, the water projects are only around -- or projects where we are facing payment issues are maybe only around 10% of the order book. So if we remove that, then let's say, what are the kind of projects where work is yet to start because maybe we got them only towards March or so. In other words, what I want to ask is what is the current executable order book where work is already underway?

    Answer, sanjay pusarla

    Sanjay Pusarla: So the entire order book is executable, okay? One thing is that about INR 7,000 crores orders, which we talked about on the water projects. The second question is that some of the projects like tunnel project, which we are executing in Mumbai and also the coastal road project, which is being executed in Mumbai. These 2 are the projects where we require lots of clearances and all those clearances are now in place. So even those projects also, which were not being moving in the last 2, 3 quarters, I think those projects also will start moving now. Rest of the projects, we are able to move. There is absolutely no problem.

    Answer, sanjay pusarla

    And those projects which have been awarded in the first and second quarters, maybe those projects will get start producing the revenue maybe in the Q4 onwards.

  12. Question

    Second quarter investment in smart meters.

    Answer, sanjay pusarla

    Sanjay Pusarla: Yes, it was INR 230 crores. In the first quarter, it was INR 70 crores. The total investment what we have made so far is INR 300 crores. The INR 70 crores was up to March '25.

    Answer, sanjay pusarla

    Sanjay Pusarla: And in the current half year, we have invested INR 230 crores. The total investment that has gone into the smart meters till now is INR 300 crores.

Questions about this call

When was the NCC Q2 FY26 earnings call transcript filed?
NCC filed the transcript with the exchange on 12 Nov 2025. This page is built from that transcript.
What does this page list?
88 statements from the transcript across 7 topics, 62 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 22 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
NCC Q2 FY26 concall: NCC Limited's order book was INR 71,957 crores as of 30th September '25, compared to INR 7,087 crores at the end of the previous quarter · DalalOS