Earnings call
Power Mech Projects Q2 FY26 earnings call: Power Mech Projects Limited secured new orders worth INR1,042 crores during quarter 2 FY '26
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company secured new orders worth INR1,042 crores during quarter 2 FY '26. The company expects both ROE and ROCE to improve in the coming quarters with anticipated normalization in collections, continued strong traction in industrial power construction and ramp-up of MDO revenue from the KBP mine starting quarter 3. The company completed mobilization of heavy equipment for KBP mining, and mining operations commenced on 15th of April '25. The company reported total income of INR1,249 crores in quarter 2 FY '26, a 19% increase over INR1,046 crores in Q2 FY '25. Adani's total intake of new projects is more than 22,000 megawatts, and NTPC has taken more than 12,000 megawatts.
The numbers management gave
Results
- The company reported total income of INR1,249 crores in quarter 2 FY '26, a 19% increase over INR1,046 crores in Q2 FY '25.
Show source
For quarter 2 financial year '26, the company reported total income of INR1,249 crores, representing 19% increase over INR1,046 crores in Q2 FY '25.
- EBITDA was INR158 crores and profit after tax was INR78 crores in quarter 2 FY '26; EBITDA increased 18% from INR134 crores and profit after tax grew 12% from INR70 crores in quarter 2 FY25.
Show source
EBITDA stood at INR158 crores, up 18% from INR134 crores in the corresponding period last year, while profit after tax was INR78 crores, registering a 12% growth compared to INR70 crores in quarter 2 FY25.
- EBITDA margin was 12.7% in quarter 2 FY '26 versus 12.8% last year, marginally impacted by higher operating costs.
Show source
The EBITDA margin remained stable at 12.7% against 12.8% last year, marginally impacted by higher operating costs.
- PAT margin declined from 6.7% to 6.3% in quarter 2 FY '26, primarily on account of increased finance and depreciation costs.
Show source
The PAT margin declined from 6.7% to 6.3%, primarily on account of increased finance and depreciation costs.
- The company reported total income of INR2,554 crores in half year FY '26, a 24% increase over INR2,062 crores in half year FY '25.
Show source
For half year FY '26, the company reported a total income of INR2,554 crores, reflecting a 24% increase over INR2,062 crores in half year FY '25.
- EBITDA was INR340 crores and profit after tax was INR159 crores in half year FY '26; EBITDA was up 33% from INR257 crores, while profit after tax was comparable to INR131 crores in half year FY '25.
Show source
EBITDA stood at INR340 crores, up 33% from INR257 crores in the corresponding period last year, while profit after tax was INR159 crores comparable to INR131 crores in half year FY '25.
Show 28 more statements
Results
- EBITDA margin improved from 12.5% to 13.3% in half year FY '26, supported by exceptional revenue recognized from the Riverbed Mineral project in the previous quarter.
Show source
The EBITDA margin improved from 12.5% to 13.3%, supported by the exceptional revenue recognized from the Riverbed Mineral project in the previous quarter.
- PAT margin declined from 6.4% to 6.3% in half year FY '26, primarily due to higher finance depreciation and tax costs.
Show source
However, the PAT margin was marginally declined from 6.4% to 6.3%, primarily due to higher finance depreciation and tax costs.
- Mechanical business revenue was INR435 crores in quarter 2 FY '26, up 90% from INR229 crores in quarter 2 FY '25, driven by strong traction in industrial power construction projects.
Show source
The company's revenue mix was as follows: Mechanical business, INR435 crores, up by 90% from INR229 crores in quarter 2 FY '25, driven by strong traction in industrial power construction projects.
- Civil segment, including railways and water distribution projects, generated INR309 crores in quarter 2 FY '26, down 22% from INR395 crores in quarter 2 FY '25, impacted by extended rains in key projects and delayed bill certifications in the Water division.
Show source
Civil segment, including railways and water distribution projects, INR309 crores, down by 22% from INR395 crores in quarter 2 FY '25, impacted by extended rains in key projects and delayed bill certifications in the Water division.
- O&M revenue was INR440 crores in quarter 2 FY '26, up 12% from INR391 crores, supported by new O&M orders received during the year.
Show source
O&M, INR440 crores, up by 12% from INR391 crores, supported by new O&M orders received during the year.
- Electrical business revenue was INR22 crores in quarter 2 FY '26, up 138% from INR9 crores in quarter 2 FY '25 due to execution of railway, civil and signalling telecommunication works.
Show source
Electrical business, INR22 crores, up 138% from INR9 crores of last year quarter 2 FY '25 due to execution of railway, civil and signalling telecommunication works.
- Mining business revenue was INR31 crores in quarter 2 FY '26, up 164% from INR12 crores last year, supported by higher offtake arrangement from SAIL.
Show source
Mining business, INR31 crores, up by 164% from INR12 crores of last year, supported by higher offtake arrangement from SAIL.
- Other income was INR11 crores in quarter 2 FY '26 compared to INR10 crores in quarter 2 FY '25, due to an increase in margin money deposits with banks.
Show source
Other income of INR11 crores compared to INR10 crores in quarter 2 FY '25, due to increase in the margin money deposits with banks.
- Geographical mix for quarter 2 FY '26 was 95% domestic and 5% international; the power sector contributed 79% and the non-power sector accounted for 21%.
Show source
Page 2 of 16 Power Mech Projects Limited November 13, 2025 The geographical mix for the quarter was 95% domestic, 5% international, while power sector contribution remained at 79% with non-power sector accounting for the remaining 21%.
- Mechanical business revenue was INR658 crores in half year FY '26, up 99% from INR331 crores in half year FY '25, driven by strong traction in industrial power construction projects.
Show source
Revenue mix for 6 months, for the first half of FY '26, the company's revenue mix was as follows: Mechanical business, INR658 crores, up by 99% from INR331 crores in half year FY '25, driven by strong traction in industrial power construction projects.
- Civil segments, including railway and water distribution, generated INR890 crores in half year FY '26, down 5% from INR937 crores in half year FY '25, impacted by extended rains across key sites and delayed bill certification in the Water division.
Show source
Civil segments, including railway and water distribution, INR890 crores, down by 5% from INR937 crores half year FY '25, impacted by extended rains across key sites and delayed bill certification in the Water division.
- O&M division revenue was INR837 crores in half year FY '26, up 14% from INR732 crores in half year FY '25, supported by new order inflows during the period.
Show source
O&M division ended at INR837 crores, up 14% from INR732 crores in half year FY '25, supported by new order inflows during the period.
- Electrical business revenue was INR89 crores in half year FY '26, up 427% from INR17 crores in half year FY '25, reflecting strong execution in railway civil works and signalling and telecommunication works.
Show source
Electrical business, INR89 crores, up 427% from INR17 crores in half year FY '25, reflecting a strong execution in railway civil works and signalling and telecommunication works.
- Mining business revenue was INR57 crores in half year FY '26, up 122% from INR26 crores in half year FY '25, supported by increased offtake arrangement with SAIL.
Show source
Mining business, INR57 crores, up 122% from INR26 crores in half year FY '25, supported by increased offtake arrangement with SAIL.
- Other income was INR22 crores in half year FY '26 compared to INR19 crores in half year FY '25, primarily due to higher margin money deposits with banks.
Show source
Other income, INR22 crores compared to INR19 crores in half year FY '25, primarily due to higher margin money deposits with banks.
- Return on equity decreased from 3.4% in FY '25 to 3.37% in FY '26, primarily due to higher finance and tax costs, which impacted PAT.
Show source
The financial parameters are concerned, the company witnessed a marginal reduction in return on equity from 3.4% in FY '25 to 3.37% in FY '26, primarily due to higher finance and tax costs, which impacted PAT.
- Return on capital employed decreased from 4.73% to 4.58% in FY '26, driven by lower operating margins resulting from seasonal factors such as extended rains.
Show source
Similarly, return on capital employed decreased slightly from 4.73% to 4.58%, driven by lower operating margins resulting from the seasonal factors such as extended rains.
- Negative operating cash flow reduced from INR166 crores negative in half year FY '25 to INR63 crores negative in half year FY '26, primarily due to realization of receivables during the period.
Show source
The company's negative operating cash flow has improved, reducing from INR166 crores negative in half year FY '25 to INR63 crores negative in half year FY '26, primarily due to the realization of receivables during the period.
- Net current asset days, excluding cash and cash equivalents, increased from 128 days in FY '25 to 151 days in FY '26, primarily due to delays in certification of water works and realization of receivables; the delays resulted in higher current assets.
Show source
Net current asset days, excluding cash and cash equivalents, increased from 128 days in FY '25 to 151 days in FY '26, primarily due to delays in certification of water works and realization of receivables.
- Receivables of around INR226 crores have been pending since last 1 year because the Central Govt has made no fund allocation to the project, and work executed to the extent of INR220 crores is under certification; total outstanding receivables and uncertified bills are INR446 crores.
Show source
So total INR446 crores is the total outstanding receivable and uncertified bills.
- Receivables were around INR287 crores in March and INR 226 crore as of September.
Show source
If you look at the March, I have a receivable of around INR287 crores and where as of September it was INR 226 crore.
- Mining business was around INR84 crores last year.
Show source
N. Nani Aravind: Last year, it was around INR84 crores.
- The company is producing 50,000 to 60,000 per month at Tasra.
Show source
N. Nani Aravind: KBP Mining has just started the production.
- Execution and supply of material for two railway packages in chattisgarh covering civil, signalling and telecommunication, and overhead electrification works during the year resulted in increased revenue compared to the previous year.
Show source
Execution and supply of material during the year resulted the increase in the revenue compared to the previous year.
- During the year there was a slowdown in execution of FGD orders, but government direction accelerated progress; Adani instructed that the Udupi project, which had been moving slowly, be completed by March, and execution picked up from Q2 onwards, driving higher order execution in the power sector.
Show source
As a result, execution picked up from Q2 onwards, driving higher order execution in the power sector.
- The total value is INR960 crores; excluding INR220 crores related to water division, approximately INR700 crores pertains to regular running projects. Replaced by a later filing.
Show source
N. Nani Aravind: Total value is INR960 crores. if you exclude INR220 crores related to water division, approximately INR700 crores pertains to regular running projects.
Money and capital
- Gross debt was INR839 crores and net debt was around INR360 crores as on 30th September '25; its average debt equity ratio as on the same date was 0.37x.
Show source
As on 30th September '25, the gross debt stood at INR839 crores and the net debt is around INR360 crores.
- The company may consider approaching the market if new opportunities or investment opportunities arise. Replaced by a later filing.
Show source
If new opportunities or any investment opportunities arise, we may consider approaching the market.
What it expects ahead
What management expects
- The company expects both ROE and ROCE to improve in the coming quarters with anticipated normalization in collections, continued strong traction in industrial power construction and ramp-up of MDO revenue from the KBP mine starting quarter 3.
Show source
With the anticipated normalization in collections with continued strong traction in industrial power construction and ramp-up of MDO revenue from the KBP mine starting quarter 3, both ROE and ROCE are expected to improve in the coming quarters.
- The company anticipates a significant increase in order inflow during FY '26, particularly from the power sector across O&M, mechanical, civil construction and BOP, EPC.
Show source
During FY '26, a significant increase in order inflow is anticipated, particularly from the power sector across segments, including O&M, mechanical, civil construction and BOP, EPC.
- The company has set a revenue target of INR6,500 crores for financial year '26.
Show source
For the financial year '26, the company has set a revenue target of INR6,500 crores.
- Subject to the pace of traction in MDO business, Power Mech Projects Limited expects EBITDA margins to remain consistent with FY '25 levels and is confident of achieving approximately 25% year-on-year revenue growth.
Show source
Subject to the pace of traction in MDO business, EBITDA margins are expected to remain consistent with the FY '25 levels, and the company is confident of achieving approximately 25% year-on-year growth, revenue growth.
- Coal production at KBP mining is expected to commence in November '25.
Show source
Coal production is expected to commence in November '25.
- A substantial flow of ordering in the Power sector is expected in the next 6 months because initial order pickup was a little slow due to the engineering phase.
Show source
There is a substantial flow is expected on that in terms of the ordering in the next 6 months because the initial order pickup was a little bit slow because of the engineering phase, which is involved.
Show 42 more statements
What management expects
- The balance ordering in the main power plant itself could open an opportunity size of INR30,000 crores to INR45,000 crores in ETC, civil, structural and other miscellaneous works.
Show source
Therefore, there is a substantial balance ordering in the main power plant itself, which can open up the opportunity size, which can be between INR30,000 crores to INR45,000 crores in segments of ETC, then civil, structural and other miscellaneous works.
- The company is tracking about INR30,000 crores of ongoing opportunities in railways and targets order booking of about INR10,000 crores.
Show source
Now the new business areas, what we are focusing is particularly in the infrastructure side, railways, and then about INR30,000 crores of ongoing opportunities, we are tracking it.
- The steel-sector opportunities are expected to be about INR8,000 crores to INR10,000 crores in the next 3 to 5 months.
Show source
And that is expected about INR8,000 crores to INR10,000 crores in the next 3 to 5 months.
- Ongoing tenders of nearly INR30,000 crores to INR35,000 crores are being tracked, supporting the target of INR10,000 crores.
Show source
And as I already said, the ongoing tenders of nearly INR30,000 crores to INR35,000 crores that is on tracking.
- The company expects its O&M business to substantially go up; the opportunity is INR1,200 crores to INR1,500 crores.
Show source
As I said, INR1,200 crores to INR1,500 crores is opportunity, and we have got a huge penetration in the market and ownership there.
- The company can achieve around INR6,000 crores to INR6,200 crores from regular business in quarter 2 FY '26.
Show source
N. Nani Aravind: Around INR6,000 crores to INR6,200 crores we can achieve from the regular business, sir.
- The company expects to achieve an average EBITDA margin of around 15% to 16% as KBP ramps up production.
Show source
So, on average, we expect to achieve an average EBITDA margin of around 15% to 16%.
- The company is projecting around 25% year-on-year growth this year, with increasing volumes and addition of more MDO business in the next year, and expects growth in the range of 20% to 25%, targeting revenue in the range of around INR7,500 crores to INR8,000 crores.
Show source
We expect to maintain growth in the range of 20% to 25% targeting a revenue in the range of around INR7,500 crores to INR8,000 crores.
- INR6,500 crores estimate is linked to MDO project revenue, and it may see 1% or 2% slippage due to delays in getting new orders anticipated during the year; it most likely may touch revenue in the range of INR6,200 crores to INR6,300 crores.
Show source
So most likely, we may touch revenue in the range of INR6,200 crores to INR6,300 crores.
- The company expects to maintain the same margin level as last year; the mix of any new O&M orders and growth in MDO may probably increase margins by 0.25%, but at this stage it estimates stability at last year's level.
Show source
But at this stage, we estimate stability at the last year level.
- New investments and development in 46,000 megawatts of new plants are expected to take shape and continue over the next couple of years.
Show source
The other thing what we said was the new investments and development will come at 46,000 megawatts new plants, that has to take shape.
- The company expects to be on track to achieve ordering targets of about INR10,000 crores, having reached almost 50% by the beginning of the third quarter.
Show source
I think as projected by Aravind and also Rohit and as we discussed with the very interesting questions and all, it is reasonably assured to say that we will be on track in achieving the targets on the ordering about INR10,000 crores because we are almost near to that 50% by end of this beginning of the third quarter.
- The company expects revenue of INR2,200 crores to be reasonable and possible, noting that the third and fourth quarters usually see an upswing.
Show source
That is where the INR2,200 crores will be reasonable and will be possible.
- The company is targeting INR10,000 crores of new orders by March '26.
Show source
The company continues to actively pursue tenders and is targeting to secure INR10,000 crores in the new orders by March '26.
- The company expects a lot of flow on its power sector business over the next 2 to 3 years, 2 years, at least.
Show source
And parallelly, we are exploring opportunities in the steel sector.
- The company expects certification and clearance to further improve operating cash flow and reduce reliance on working capital limits.
Show source
This is expected to further improve the operating cash flow and reduce the reliance on the working capital limits.
- The company is actively pursuing certification and payment clearance with the client and expects significant improvement in net working capital days after certification and realization of bills in the water division.
Show source
Company is actively pursuing certification and payment clearance with the client and significant improvement in the net working capital days is expected post certification and realization of bills in the water division.
- The company expects expediting certification and recovery of bills in the Water division to further reduce net debt and the debt equity ratio in the coming quarters.
Show source
The company is focusing on expediting certification and recovery of bills in the Water division, which is expected to further reduce the net debt and the debt equity ratio in the coming quarters.
- The company anticipates stable margins, with potential upside depending on the contribution mix from O&M and mining segments.
Show source
Margins are anticipated to remain stable with potential upside depending on the contribution mix from O&M and mining segments.
- The company is interested in entering the iron ore business, drawing on its expertise in MDO business and EPC business in material handling, because iron ore demand is expected.
Show source
And that is one of the areas of interest because iron ore demand is going to be there, and we would like to see how we can enter that business and with the expertise what we have developed in the MDO business and EPC business in material handling.
- Construction, O&M and project management experience developed in the power sector will be used in the steel and mining sectors, including NMDC jobs and the mine-side facilities NMDC is going to create.
Show source
And our construction experience and O&M experience and our project management experience, what we have developed over the years in the power sector will be rightly used for the steel sector and also in the mining sector; for example, NMDC jobs and the mind side facilities, which they are going to create.
- The company hopes to bring the receivables under control by March and reduce working capital utilization.
Show source
So , we are hoping by March, we'll bring all this into the control and we'll reduce our working capital utilization with that receivable, sir.
- The company expects year-on-year growth in the bottom line from FY27 onwards as mining operations ramp up.
Show source
As these operations ramp up, we expect to see year -on-year growth in the bottom line from FY27 onwards.
- The company is taking initiatives for export jobs in O&M and maintenance. Replaced by a later filing.
Show source
And export jobs also on the O&M side and the maintenance side, certain initiatives are being taken.
- The company had some successes on the O&M side this year. Replaced by a later filing.
Show source
And the O&M side also, we had some successes in this year also.
- The company may diversify into steel, infrastructure, petroleum, and oil and gas as new plants are expected. Replaced by a later filing.
Show source
And there, we can possibly look for diversification and this experience what we have gained from it.
- The company expects to complete by March and expects this level of order execution to continue until March. Replaced by a later filing.
Show source
So we can expect this level of order execution till March.
- The company expects to continue focusing on growth in the coming couple of years in the power, steel, infrastructure, railways and other segments, alongside emerging opportunities and investments. Replaced by a later filing.
Show source
And with these-type of opportunities and investments coming up, I think, particularly in the power sector, steel sector, infrastructure side, railways and other segments, perhaps we will continue to focus for the growth in the coming couple of years.
Orders
- The company secured new orders worth INR1,042 crores during quarter 2 FY '26.
Show source
Order book status during quarter 2 FY '26, the company secured new orders worth of INR1,042 crores.
- Order backlog was approximately INR53,776 crores as of 30th September '25, with executable order excluding two MDO projects of INR14,226 crores.
Show source
As of 30th September '25, the order backlog stood at approximately INR53,776 crores with the executable order excluding two MDO projects at INR14,226 crores.
- The company received new orders worth INR2,577 crores in quarter 3 FY '26 till date, taking its total order backlog to INR56,353 crores and executable order book, excluding two MDO projects, to INR16,804 crores.
Show source
In quarter 3 FY '26 till date, the company has received new orders worth of INR2,577 crores, taking the total order backlog of INR56,353 crores with the executable order book, excluding two MDO projects increasing to INR16,804 crores.
- The company had secured orders worth INR4,889 crores as of date, achieving approximately 49% of the annual target.
Show source
As of date, the company has already secured orders worth of INR4,889 crores, achieving approximately 49% of the annual target.
- Total order book was INR14,226 crores as of 30th September: roughly INR1,700 crores from the mechanical business and power erection business, INR9,000 crores from power civil and infra civil, around INR2,700 crores from O&M, and around INR800 crores from electrical business.
Show source
N. Nani Aravind: Total INR14,226 crores as of 30th September consists of INR1,700 crores roughly from the mechanical business, power erection business; INR9,000 crores is from both power civil and infra civil; O&M of around INR2,700 crores; electrical business of around INR800 crores.
- Order book comprised INR8,300 crores from power and around INR5,900 crores from infrastructure.
Show source
So from power side, mix is INR8,300 crores is from power side and infra side is around INR5,900 crores.
- The company is projecting INR10,000 crores of order inflow this year, comprising around INR2,000 crores in erection, INR2,400 crores in civil, around INR2,600 crores in O&M, and around INR300 crores in electrical business.
Show source
N. Nani Aravind: For the order inflow this year, we are projecting INR10,000 crores.
- The company received around INR159 crores of orders under solar and other green energy projects during the year, and around INR2,550 crores in BOP EPC orders.
Show source
During the year we received around INR159 crores orders under this segment. and BOP EPC of around INR2,550 crores.
- The company is targeting around INR10,000 crores of order inflow during the year across various segments.
Show source
So we are targeting around INR10,000 crores order inflow during the year, this is a mix of various segments.
- The company had received orders worth INR4,900 crores till date and expected the balance before March. Up to September, it had received mechanical business orders of around INR49 crores, civil business orders of INR1,500 crores, O&M business orders of INR761 crores, and around INR2,550 crores of BOP EPC orders till date.
Show source
N. Nani Aravind: Till date we received orders worth of INR4,900 crores and the balance we are expecting before March.
- The company said total ordering done in the last 1.5 years, which is under execution at various stages, is roughly about 47,500 megawatts.
Show source
S. K. Ramaiah: I told you the total ordering, which has been done in the last 1.5 years, which is under execution at various stages roughly comes to about 47,500 megawatts.
- The company said 55% of this capacity will be its opportunity.
Show source
N. Nani Aravind: So sir, overall, to answer your question, in this capacity, 55% will be our opportunity.
- The initial ordering opportunity is about INR40,000 crores to INR50,000 crores, with a balance of INR40,000 crores to INR50,000 crores to come in the next couple of years.
Show source
So that is where we said that initially, we can have immediately about INR40,000 crores to INR50,000 crores and balance INR40,000 crores, INR50,000 crores, we'll come in the next couple of years.
- The balance ordering on main EPC orders already placed is for items including main plant services, balance of plant, structural work and civil works, with substantial ordering still to be done by BHEL and Adani and NTPC also needing to order.
Show source
That is substantially it is there to be ordered by BHEL, by Adani , then NTPC also has to order.
What it is building and selling
Projects and capacity
- The company completed mobilization of heavy equipment for KBP mining, and mining operations commenced on 15th of April '25.
Show source
With reference to our MDO business progress is concerned, KBP mining mobilization of heavy equipment has been completed and mining operations commenced on 15th of April '25.
- The company achieved around 6.15 lakh cubic meters of overburden removal at KBP mining until October '25, and the activity is continuing as planned.
Show source
Until October '25, the company has achieved around 6.15 lakh cubic meters of overburden removal, and the activity is continuing as planned.
- Mine approach roadworks are in progress, and it is targeting minimum coal dispatch of 1 million tons during the year with a plan to scale up operations to 1.5 million tons.
Show source
The mine approach roadworks are in progress, and the company is targeting minimum coal dispatch of 1 million tons during the year with a plan to scale up of operations to 1.5 million tons.
- Kalyaneswari Tasra project received environmental clearance for the 3.5 million tons per annum washery in October '24.
Show source
The project received environmental clearance for the 3.5 million tons per annum washery in October '24.
- Construction of the washery at Power Mech Projects Limited's Kalyaneswari Tasra project is targeted for completion by September '26.
Show source
The washery construction is targeted for completion by September '26.
- The company said the general execution cycle is 2 to 2.5 years and typically up to 3 years, while EPC projects have an execution period of around 38 months.
Show source
For EPC projects, execution period is around 38 months.
Show 51 more statements
Projects and capacity
- The company said EPC cost can be INR8 crores to INR8.5 crores, depending on the scope and whether the project has a single unit, 2 units or 3 units.
Show source
But the EPC cost can be INR8 crores to INR8.5 crores depending on the scope of pertains to the single unit, it can be more with 2 units or 3 units and slightly less.
- The company said the main plant side accounts for around 55% of the INR8 crores to INR8.5 crores EPC cost.
Show source
The main plant side, the total investment can be around 55% of this INR8 crores, INR8.5 crores.
- The company said the service portion in the main plant can be around INR1,000 crores for each plant of two units, with about INR1,000 crores of opportunity for a 1,600 megawatt plant.
Show source
That is a suppose 1,600 megawatt is there, about INR1,000 crores can be the opportunity there.
- The company said balance of plant work offers the same opportunity in service or balance of plant business, subject to qualification, and costs anywhere between INR3.5 crores to INR4 crores.
Show source
And balance of plant will be anywhere between INR3.5 crores to INR4 crores.
- The company said coal handling, material handling, civil works, structures, IDCT, cooling towers and other miscellaneous civil and structural jobs can be bid individually, and that civil work, structural work and installation services together represent 25% to 30% of the total EPC cost opportunity.
Show source
And that is also in some segments, if it is called individually, we can bid also for the coal handling and material handling and then civil , structures, then for the other miscellaneous civil works like IDCT, cooling towers and various other jobs, structural jobs, et c Therefore, we can say, including the civil work, structural work, then service portion of the installation wise, we can safely take 25% to 30% is the opportunity available out of the total EPC cost .
- At Power Mech Projects Limited's Kalyaneswari Tasra project, overburden removal and coal dispatch operations have been ongoing since January '24.
Show source
And the other mine at the Kalyaneswari Tasra project, OB removal and coal dispatch operations have been ongoing since January '24 with approximately 8.7 lakh tons of coal produced and dispatched to the existing washeries as per the SAIL’s direction.
- Water division projects have experienced delays due to slower bill certification because of non-allocation of funds; all existing projects are progressing well and remain on track except for the water division.
Show source
All existing projects are progressing well and remain on track, except for the water division, which has experienced delays due to slower bill certification due to non-allocation of funds.
- All land required for mining at Power Mech Projects Limited's KBP mine has been handed over to CCL.
Show source
All land required for mining has been handed over to CCL.
- Design consultants have been appointed for railway sidings and washery development at Power Mech Projects Limited's Kalyaneswari Tasra project.
Show source
Design consultants have been appointed for railway sidings and washery development.
- Major washery equipment design and vendor finalization at Power Mech Projects Limited's Kalyaneswari Tasra project have been completed.
Show source
And the major washery equipment design and vendor finalization have been completed.
- Equipment mobilization is in progress and civil construction works have commenced at Power Mech Projects Limited's Kalyaneswari Tasra project.
Show source
Equipment mobilization is in progress. and civil construction works have been commenced.
- SAIL’s current coal offtake remains below the plan due to limited external washery capacity; Power Mech Projects Limited is engaging with stakeholders to resolve the constraints and ramp up production in the coming months.
Show source
While SAIL’s current coal offtake remains below the plan due to the limited external washery capacity, the company is actively engaging with stakeholders to resolve these constraints and ramp up the production in the coming months.
- Coal production at KBP Mining is starting this year, and washery works at Tasra are currently in progress.
Show source
Coal production at KBP Mining is starting this year, and the washery works at Tasra are currently in progress.
Demand and pricing
- Adani's total intake of new projects is more than 22,000 megawatts, and NTPC has taken more than 12,000 megawatts.
Show source
And they also have to do substantial balance ordering of the new projects and all because Adani's total intake of the new projects, what they have taken is more than 22,000 megawatts.
- Developers ordered a total of 47,500 megawatts in the last 18 to 24 months.
Show source
Together, they contribute substantially out of the total 47,500 megawatts of ordering, which has been done in the last 18 to 24 months.
- Annual capacity addition, which had come down to 3250mw/year between 2017 to 23, is expected to go to 8,000 to 10,000 megawatts.
Show source
Another key element of this capacity addition is that the annual capacity addition, which had come down drastically 3250mw/year between 2017 to 23is going up and expected to go to 8,000 to 10,000 megawatts.
- NMDC has a planned investment of INR50,000 crores to increase iron ore capacity from 50 million tons to 100 million tons.
Show source
Then for example, NMDC, they have a planned investment of INR50,000 crores to enhance the capacity of the iron ore from 50 million tons to 100 million tons.
- Power plants are expected to run another 25, 30 years minimum, with a downward trend in emissions and decommissioning perhaps up to 2047 to 2050.
Show source
And then somewhere up to 2047 to 2050 perhaps they will be looking at a downward trend in the emissions and the decommissioning of the power plants.
- Madhya Pradesh is planning a INR60,000 crore capacity Ethylene plant.
Show source
Like Madhya Pradesh, they are planning to put a INR60,000 crore s capacity Ethylene plant.
- BHEL had capacity for 16,000 to 18,000 megawatts per year a couple of years back.
Show source
And BHEL had this wherewithal capacity to 16,000 to 18,000 megawatts per year a couple of years back.
- Of the 47,000 megawatts ordered by developers, substantial ordering remains for vendors like Adani and NTPC for new tenders.
Show source
Because as I said, the 47,000 megawatts, what has been ordered by the developers, still some substantial ordering has to be done to the various vendors like Adani and even NTPC for the new tenders, what they are going to call.
- Utility companies have a share of more than 12,000 megawatts that still has to be ordered on BHEL and L&T.
Show source
And also all the various utility companies, have got a share of more than 12,000 megawatts.
- The balance ordering for 46,000 megawatts of new developments is still to happen.
Show source
And that also has to come up with ordering done on BHEL and L&T. Then balance ordering of the development as I said, of the 46,000 megawatts new developments, which are going to happen.
- The 46,000 megawatts of new developments will be a substantial chunk of orders in the next at least 2 to 3 years, reasonably shared substantially by BHEL and to some extent by L&T.
Show source
Therefore, these 46,000 megawatts will be a substantial chunk of the order, which will come up in the next at least 2 to 3 years, which will be reasonably shared substantially by BHEL and to some extent by L&T also.
- The government’s long-term investment profile is to invest about INR10 lakh crores in the next 5 to 7 years.
Show source
S. K. Ramaiah: Because the long-term investment profile of the government is to invest about INR10 lakh crores in the next 5 to 7 years.
- Present steel capacity is 200 million tons, while last year's production was 152 million tons.
Show source
Because the present steel capacity is 200 million tons, wherein last year's production was 152 million tons.
- Steel capacity has to increase to 300 million tons by 2030, '32.
Show source
That has to go up to 300 million tons of capacity addition by 2030, '32.
- A 5 million steel plant needs about INR35,000 crores to INR45,000 crores of investment.
Show source
And as we have seen, a 5 million steel plant needs about INR35,000 crores to INR45,000 crores of investments.
- Rashmi Group is coming with an investment of about INR10,000 crores.
Show source
For example, Rashmi Group is coming with an investment of about INR10,000 crores.
- Baldota group is planning investment of about INR15,000 crores to INR20,000 crores on the mining side in Bellary.
Show source
And there is Baldota group available on the mining side in Bellary- They are also planning investment about INR15,000 crores to INR20,000 crores.
- The CEA and the Power Ministry are planning about another 45000mw, with identified customers including Adani, NTPC, Tata Power, Vedanta, SJVN Buxar, CIL, Coal India, JSW, JSPL and NLC; NTPC has expansion plans at Patratu, Meja, Obra and Darlipali, and SJVN Buxar plans to add one more unit.
Show source
S. K. Ramaiah: Planning by the CEA and the Power Ministry for about another 45000mw and even the customers also have been identified like Adani, NTPC is having plans in expansion Patratu and Meja, and then Obra, Darlipali.
- L&T is present in the domestic market unless the government takes a policy decision to import equipment from outside; management does not think that will happen.
Show source
Also L&T is there for the domestic market unless the government takes a policy decision to import the equipment from outside.
- SAIL has a clear plan for IISCO, Burnpur, followed by Bokaro and Rourkela expansions.
Show source
And all the players, for example, SAIL has got a plan, clear plan.
- SAIL is planning to invest more than INR1 lakh crores. Replaced by a later filing.
Show source
And the new investment, which is expected, is in the steel sector is opening in a big way, particularly SAIL is planning to invest more than INR1 lakh crores.
- SAIL has told about about INR1 lakh crores of investment. Replaced by a later filing.
Show source
SAIL has told about about INR1 lakh crores of investment.
- Total investment of more than INR3 lakh crores will happen because of continued economic growth, with steel linked to economic growth. Replaced by a later filing.
Show source
Therefore, the total investment of more than INR3 lakh crores and will happen because of the continued growth of the economy of course, steel is part linked with growth of the economy.
- ArcelorMittal is coming up with a plant in AP. Replaced by a later filing.
Show source
ArcelorMittal is coming up with a plant in AP.
- JSW is coming with a huge investment in Maharashtra. Replaced by a later filing.
Show source
JSW is coming with a huge investment in Maharashtra.
- BHEL's outlook will continue to have more order outlook, and BHEL will continue to drive the orders. Replaced by a later filing.
Show source
But basically, BHEL's outlook will continue to have more order outlook –and that they will continue to drive the orders .
- ArcelorMittal is coming with a greenfield plant in Andhra Pradesh, with some expansions also planned. Replaced by a later filing.
Show source
Then ArcelorMittal is coming with a greenfield plant in Andhra Pradesh and some expansions will be there.
- JSW and JSPL are planning capacity additions. Replaced by a later filing.
Show source
JSW and then JSPL both are planning capacity additions.
Segments
- The company has developed expertise in traditional ETC and O&M businesses in the power sector and in coal handling balance-of-plant and supporting packages, completing about 4, 5 contracts.
Show source
That we have done about 4, 5 contracts and we have gained that experience that should help us.
- The company is gradually completing existing transmission and distribution projects because this area is not fully aligned with its core focus; moving forward, its T&D team will handle all new railway and T&D works, and the company is pursuing new railway works under this division.
Show source
N. Nani Aravind: Yes, transmission distribution, we are gradullay completing existing projects as this area is not fully aligned with core focus.
- The company is considering data centres as an area of interest and diversification.
Show source
And another area perhaps we can look at as an interest and diversification is in data centres.
- The company sees data centres as a potential segment in which it can apply its expertise in power capacity and substations, infrastructure and civil works, and balancing facilities; refineries and steel plants are also potential areas.
Show source
Then, it needs a lot of infrastructure works and development, civil works and then other facilities, balancing facilities etc So this is a segment, which we can gainfully try to work based on the expertise what we have gained and there are other sectors also, which come up.
Deals and partners
- The company has established a presence in about 6,000 megawatts of Adani Group projects and is working on about INR2,500 crores of ongoing jobs.
Show source
And other key developers are the Adani Group, which we have substantially established the presence in many projects in about 6,000 megawatts and working in about INR2,500 crores of ongoing jobs.
- Key focus areas in the Power sector will be BHEL and L&T, EPC contractors that have taken bulk of the orders from developers NTPC, Adani Power and the generating companies.
Show source
And particularly, in the Power sector our key areas of focus will be BHEL and then L&T, which are the EPC contractors, which have taken bulk of the orders from the developers, NTPC, Adani Power and the generating companies.
- IISCO Burnpur has started issuing pretender inquiries, and Power Mech Projects Limited is participating in many opportunities.
Show source
And IISCO Burnpur has already started issuing the pretender inquiries, and we are participating in that many opportunities.
- The company is in continuous discussion with NMDC, which has started the tendering process; three BOT tenders have been notified, two in NMDC Kirandul and one in Donimalai.
Show source
NMDC has also started the tendering process. three BOT tenders are already notified, 2 in NMDC Kirandul, and 1 in Donimalai.
- The company has experience constructing steel plants at JSW Dolvi and JSW Vijayanagar and is doing some jobs in JSPL.
Show source
Therefore, we have already had experience of doing steel plant construction in JSW Dolvi and JSW Vijayanagar and ongoing, we are doing some jobs in JSPL.
- The company said Adani orders the main plant as equipment supplies, while awarding balance of plant and services jobs itself, creating an opportunity for contractors like Power Mech Projects Limited.
Show source
Therefore, that also, as an opportunity, is available for a contra ctor like us.
Risks, rules and outside factors
Risks and disputes
- The company is pursuing receivables with the client and UP government; after a recent meeting with JJM contractors headed by the UP CM, the government assured contractors that funds will be allocated, and the company is pursuing the Central Govt to release funds at the earliest.
Show source
Recently, GOVT held a meeting with all JJM contractors, headed by UP CM, and assured all contractors that the funds will be allocated and also pursuing with Central Govt to release of the funds at the earliest.
Outside factors
- Majority of contracts include price escalation clauses that are pass through, and the company is not incurring losses and is receiving the escalation amount from clients.
Show source
We are not incurring any losses and are receiving the escalation amount from the clients.
Rules and policy
- The government's plan is to add 80,000 megawatts to 1 lakh megawatts to maintain grid stability as a short-term measure of 7 to 8 years.
Show source
And this is a short-term measure of 7 to 8 years because of -the need - to maintain the grid stability, I think, we have discussed this matter many times over the grid stability, and that's why government's plan is to add 80,000 megawatts to 1 lakh megawatts.
Everything else said on the call
What management stressed
- The company will continue to prioritize high potential areas, including industrial plant operations and maintenance, railway and water infrastructure and MDO projects, to drive substantial growth and strengthen market leadership. Replaced by a later filing.
Show source
The company will continue to prioritize high potential areas, including industrial plant operations and maintenance, railway and water infrastructure and MDO projects to drive substantial growth Page 3 of 16 Power Mech Projects Limited November 13, 2025 and strengthen market leadership.
Other
- The company is actively engaging with clients to expedite certification and clearance processes and is confident of realizing outstanding dues in the coming months.
Show source
The company is actively engaging with the clients to expedite certification and clearance processes and is confident of realizing the outstanding dues in the coming months.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Mohit Kumar: Understood. Understood. So Nabinagar is pending. Nabinagar shall come up in next 1 year, so we should be able to participate, right? Correct? Is that fair understanding? Gadarwara and Nabinagar is done, I think? We are not one of the participants. And they also have a large opportunity from most of the states like most of the states, BHEL have won the tender. So how is the BHEL pipeline looking right? We have seen a lot of tenders from BHEL side. Are you only looking for a particular kind of packages or do we have the capability to do this CHP, AHP also?
Answer, s ramaiah
S. K. Ramaiah: See, we have developed expertise not only in the traditional ETC business, O&M business, in the power sector. We also developed the expertise to handle the one of the key packages in the balance of plant and the supporting packages on the coal handling also. That we have done about 4, 5 contracts and we have gained that experience that should help us. But basically, BHEL's outlook will continue to have more order outlook –and that they will continue to drive the orders . Also L&T is there for the domestic market unless the government takes a policy decision to import the equipment from outside. I don't think that will happen. And BHEL had this wherewithal capacity to 16,000 to 18,000 megawatts per year a couple of years back.
Answer, s ramaiah
And, of course, we have seen the downward trend and all those things happened. Now it has picked up. And looking at the long -term investment, at least 7 to 8 years, BHEL should be ramping up their capacities and they should be reasonably able to bid for all these things. And they will continue to be a key player. Because as I said, the 47,000 megawatts, what has been ordered by the developers, still some substantial ordering has to be done to the various vendors like Adani and even NTPC for the new tenders, what they are going to call. And also all the various utility companies, have got a share of more than 12,000 megawatts. And that also has to come up with ordering done on BHEL and L&T. Then balance ordering of the development as I said, of the 46,000 megawatts new developments, which are going to happen.
Answer, s ramaiah
Therefore, these 46,000 megawatts will be a substantial chunk of the order, which will come up in the next at least 2 to 3 years, which will be reasonably shared substantially by BHEL and to some extent by L&T also. Therefore, we should be having a long- term plan for at least executing 8,000 to 10,000 megawatts in the next 6 to 10 years.
Question
Rohit Sajja: And Mohit sir, just adding to what Ramaiah sir had said. So, the recent BOP package that we won entails us to construct a coal handling plant, ash handling plant, which is an expertise that we have developed over years. As a construction company, we are just adding engineering as an expertise. We have partnered with Tata Consultancy Engineers, TCE. And also procurement is anyway a commercial activity. And hence, our entry into this space. And also going forward, as I had said earlier, we want to participate in the state utility projects that are either planning on separating the BTG and BOP or are awarding the entire plant to an EPC player like BHEL and then we don't mind subcon
Answer, s ramaiah
S. K. Ramaiah: Because the long-term investment profile of the government is to invest about INR10 lakh crores in the next 5 to 7 years. Because the present steel capacity is 200 million tons, wherein last year's production was 152 million tons. That has to go up to 300 million tons of capacity addition by 2030, '32. And as we have seen, a 5 million steel plant needs about INR35,000 crores to INR45,000 crores of investments. And all the players, for example, SAIL has got a plan, clear plan. First, I think it is IISCO, Burnpur. Then they will have a plan for the Bokaro and then Rourkela expansions also.
Answer, s ramaiah
Then ArcelorMittal is coming with a greenfield plant in Andhra Pradesh and some expansions will be there. JSW and then JSPL both are planning capacity additions. And then there are some new players also coming up. For example, Rashmi Group is coming with an investment of about INR10,000 crores. And there is Baldota group available on the mining side in Bellary- They are also planning investment about INR15,000 crores to INR20,000 crores. Therefore, the total investment of more than INR3 lakh crores and will happen because of the continued growth of the economy of course, steel is part linked with growth of the economy. And as the economy grows, steel requirement also demand has to be there.
Answer, s ramaiah
In fact, many of the steel suppliers are also complaining that we are importing also material from outside. Therefore, we have already had experience of doing steel plant construction in JSW Dolvi and JSW Vijayanagar and ongoing, we are doing some jobs in JSPL. And our construction experience and O&M experience and our project management experience, what we have developed over the years in the power sector will be rightly used for the steel sector and also in the mining sector; for example, NMDC jobs and the mind side facilities, which they are going to create. Therefore, this is where we are quite bullish on these 2 areas.
Question
Rohit Sajja: FY27 ramp-up in both the mines, there's going to be a significant ramp-up in FY27. FY27, KTMPL, the 4 million metric tons per annum with sale, we anticipate to reach peak rated capacity. And the first mine in which we are going to do 1 million will get ramped up to 2.5 million to 3 million by FY '27, translating to a combined top line of INR550 crores to INR600 crores.
Answer, n aravind
If you look at the March, I have a receivable of around INR287 crores and where as of September it was INR 226 crore. Pritesh: So we know the figures. We know these figures. What should be done? We know the figures. We know the opportunity, incremental new inflow ?
Answer, n aravind
N. Nani Aravind: We are pursuing with the client/ UP government . Recently, GOVT held a meeting with all JJM contractors, headed by UP CM, and assured all contractors that the funds will be allocated and also pursuing with Central Govt to release of the funds at the earliest. So , we are hoping by March, we'll bring all this into the control and we'll reduce our working capital utilization with that receivable, sir. Pritesh: See, we were not active in water. We landed up taking some of these projects at the fa r end. So any review process that you implemented incrementally?
Answer, n aravind
N. Nani Aravind: There were delays in commencing the MDO projects due to external factors. Coal production at KBP Mining is starting this year, and the washery works at Tasra are currently in progress. As these operations ramp up, we expect to see year -on-year growth in the bottom line from FY27 onwards. Pritesh: Okay. And from the execution point of view, what kind of revenue execution that you see ex of mining this year in FY '26?
Answer, n aravind
N. Nani Aravind: Around INR6,000 crores to INR6,200 crores we can achieve from the regular business, sir. INR250 crores we projected from the mining business. Pritesh: And how much was mining business last year?
Answer, n aravind
N. Nani Aravind: Last year, it was around INR84 crores. Pritesh: So basically INR5,160 crores in EPC and moves to basically INR6,200 crores.
Answer, n aravind
N. Nani Aravind: Total INR14,226 crores as of 30th September consists of INR1,700 crores roughly from the mechanical business, power erection business; INR9,000 crores is from both power civil and infra civil; O&M of around INR2,700 crores; electrical business of around INR800 crores. So we have domestic of around INR14,000 crores and international order of around INR220 crores. So from power side, mix is INR8,300 crores is from power side and infra side is around INR5,900 crores.
Question
Hetali Shah: Okay, sir. And for the order inflow?
Answer, n aravind
N. Nani Aravind: For the order inflow this year, we are projecting INR10,000 crores. We are projecting erection business around INR2,000 crores; from the civil business, INR2,400 crores; O&M around INR2,600 crores; electrical business around INR300 crores. As a new initiative, we have been focusing on solar and other green energy projects. During the year we received around INR159 crores orders under this segment. and BOP EPC of around INR2,550 crores. So we are targeting around INR10,000 crores order inflow during the year, this is a mix of various segments.
Question
Hetali Shah: These orders are expected, right?
Answer, n aravind
N. Nani Aravind: Till date we received orders worth of INR4,900 crores and the balance we are expecting before March. Hetali Shah: Can you give the split of the INR4,900 crores in the segment? Page 9 of 16 Power Mech Projects Limited November 13, 2025 N. Nani Aravind: We received mechanical business of around INR49 crores, civil business of INR1,500 crores, and O&M business of INR761 crores up to September. till date, we have received around INR2,550 crores orders from the BOP EPC.
Answer, n aravind
N. Nani Aravind: Generally, execution cycle will be 2 to 2.5 years and typically up to 3 years. For EPC projects, execution period is around 38 months.
Answer, s ramaiah
S. K. Ramaiah: You are correct, INR10 crores per megawatt can be including the IDC cost. But the EPC cost can be INR8 crores to INR8.5 crores depending on the scope of pertains to the single unit, it can be more with 2 units or 3 units and slightly less. And now it is standing at greatest order BHEL has got is INR8.3 crores. The main plant side, the total investment can be around 55% of this INR8 crores, INR8.5 crores. And normally, the service portion of it, we can say it will be around something like INR1,000 crores will be coming in the main plant for each plant of two units. That is a suppose 1,600 megawatt is there, about INR1,000 crores can be the opportunity there. That is the main plant.
Answer, s ramaiah
And the balance of plant, entire same opportunity is available, whether we want to bid on the service side of the business or on the balance of plant of the business, subject to the qualification. And balance of plant will be anywhere between INR3.5 crores to INR4 crores. And that is also in some segments, if it is called individually, we can bid also for the coal handling and material handling and then civil , structures, then for the other miscellaneous civil works like IDCT, cooling towers and various other jobs, structural jobs, et c Therefore, we can say, including the civil work, structural work, then service portion of the installation wise, we can safely take 25% to 30% is the opportunity available out of the total EPC cost . Pharani : So 30% of INR8.5 crores?
Answer, s ramaiah
S. K. Ramaiah: Overall, that is the maximum. Pharani : Okay. So , 30% of INR8.5 crores. So , this will be during the project construction. And O&M comes in the operational period, right?
Answer, s ramaiah
S. K. Ramaiah: O&M it comes for commissioning that will come between 11 lakh to INR15 lakhs per megawatt per year. And then one more thing is that where BOP is there is a complete package, as I already told you, that will be the complete opportunity on 40%, 45% of INR8. crores as an opportunity for the BOP. Pharani : Right. So coming to the next question, you mentioned about 46,000 megawatts yet to be awarded in the coming year, plus about 12,000 megawatts from state utilities. So I can roughly take 40% of this overall opportunity to be our long -term opportunity, right, during construction?
Answer, s ramaiah
S. K. Ramaiah: I told you the total ordering, which has been done in the last 1.5 years, which is under execution at various stages roughly comes to about 47,500 megawatts. So , what I said was this is, you can say, mostly ordered in the EPC mode or on the main plant side. And in the case of Adani, they have taken a different route. They are ordering the main plant on the equipment supplies, whereas the balance of plant and the services job, they are awarding themselves. Therefore, that also, as an opportunity, is available for a contra ctor like us.
Answer, n aravind
N. Nani Aravind: So sir, overall, to answer your question, in this capacity, 55% will be our opportunity. Page 10 of 16 Power Mech Projects Limited November 13, 2025 Pharani: Understood. So basically, 46 plus 12 that is around 58 gigawatt.
Answer, s ramaiah
S. K. Ramaiah: Planning by the CEA and the Power Ministry for about another 45000mw and even the customers also have been identified like Adani, NTPC is having plans in expansion Patratu and Meja, and then Obra, Darlipali. Tata Power has got plans. Vedanta has got plans. Then for example, SJVN Buxar got a plan to add one more unit. CIL, Coal India wants to enter the power sector also. Then JSW and JSPL both are planning it. NLC is also planning.
Answer, s ramaiah
For all these entities either in a brownfield or a greenfield segment, they are going to put up these plans and as such about 8000 to 85000 mw that is the capacity has been arrived at it. It's a question of developing taking into account in terms of timing and execution, it is normally a development process in terms of environment clearance, land acquisition, investment tie ups to achieving the financial closure. This, we all have seen there are certain aspects in developing a projects certain things can be there in that which can take the project forward or some slowness is there. But these capacities are a must to balance the grid capacity for another 7, 8 years, it should be established. That is positively is expected to come up. Pharani: Okay, sir. My final question, since we identified the opportunity of INR3 lakh crores for this 58 gigawatts in the, say, medium to long term, what would be roughly our market share or expectation to win over this 5 to 7 years on this INR3 lakh crores of opportunity?
Answer, s ramaiah
S. K. Ramaiah: No, you can take, as I said, on the upper side, if you take about 30% on the service side, on the civil structural services side of installation. And if the balance of plant, we can take about 35% to , 45% easily. Pharani: You're talking about the market, right?
Question
Rohit Sajja: Yes, idealistic scenario, a little conservative number is what I gave you.
Answer, n aravind
N. Nani Aravind: KBP Mining has just started the production. Since, Tasra has not yet scaled up, we are operating only at limited capacity producing around 50,000 to 60,000 of tons per month. KBP just started this year and slowly, we'll ramp up the production. So, on average, we expect to achieve an average EBITDA margin of around 15% to 16%.
Question
Deepak Poddar: Okay. Understood. And secondly, I mean, you spoke about your business mix. I mean, currently, 75% is the power sector, right? So you are coming up looking at new opportunities in the steel sector. So how do you envisage even railways, you spoke about, right? So how do we envisage your business mix changing, which is 75% power and all these new sectors, how is the margin profile?
Answer, n aravind
N. Nani Aravind: So, the margin profiles are concerned, on an average, our construction segment is generating EBITDA margins of up to 10%. And the key drivers for improving overall margins will be the O&M and MDO segments once MDOs reach the peak rated capacity O&M business is delivering EBITDA margin around 15% to 16%. Page 12 of 16 Power Mech Projects Limited November 13, 2025 So business mix is concerned, the power is expected to contribute significantly over next 2 to 3 years, with an increase in power orders. And parallelly, we are exploring opportunities in the steel sector. So more or less, the margin will be expected to be steady, we will maintain at the current level.
Question
Deepak Poddar: Sure, sure. Understood. And just one last small thing from my side. So, you spoke about the guidance for this year. So anything you want to talk about for FY '27 as well given the scale up and higher margin revenue mix will increase for FY '27?
Answer, n aravind
N. Nani Aravind: So, this year, we are projecting around 25%. growth Year-on-year, with increasing volumes and addition of more MDO business in the next year. We expect to maintain growth in the range of 20% to 25% targeting a revenue in the range of around INR7,500 crores to INR8,000 crores.
Question
Deepak Poddar: At the EBITDA level. Fair enough. That’s very helpful. All the very best to you. Thank you so much.
Answer, n aravind
N Nani Aravind: Thank you, sir. Hetali: Sir, we have seen headwinds in the electrical segment for a few quarters now. So I would like to understand what is the headwind there?
Answer, n aravind
N. Nani Aravind: Last year we secured two railway packages in chattisgarh covering civil, signalling and telecommunication and overhead electrification works . Execution and supply of material during the year resulted the increase in the revenue compared to the previous year. Hetali: So are these expected to continue or is there any improvement expected in this segment?
Answer, n aravind
N. Nani Aravind: Yes, transmission distribution, we are gradullay completing existing projects as this area is not fully aligned with core focus. Moving forward, T&D team will handle all new jobs in railway & T&D works. We are pursuing new railway works under this division. Hetali: Okay, sir. Those segments will replace this one?
Question
Rohit Sajja: See, FY '26, we already won a Kusum Yojana project of 13.5 megawatts of AC capacity. Next year, we plan to enhance this to 100 megawatts of solar and around 200 to 250 megawatts of megawatt hour of battery energy storage system capacity. So those are the numbers we are looking at. This is FY '27 projection. Hetali: Okay. That was really helpful. And sir, are you projecting any cost escalations in your current projects that you're handling that can affect the margin?
Answer, n aravind
N. Nani Aravind: Majority of our contracts include the price escalation clauses, which are pass through. We are not incurring any losses and are receiving the escalation amount from the clients. Hetali: Okay. Thank you, sir.
Answer, n aravind
N. Nani Aravind: Sir, INR6,500 crores estimate is linked to the MDO project revenue. And we may see 1% or 2% slippage due to delays in getting the new orders, which we had anticipated during the year. So most likely, we may touch revenue in the range of INR6,200 crores to INR6,300 crores. Prit: And sir, would still represent an 18% growth?
Show 3 more questions
Question
Rohit Sajja: Yes, And I think 18% growth still is good enough. Prit: The other question I had was again on the margin side. So do we see a 0.25%, 0.5% bump for FY '26 over FY '25? Is that a possibility?
Answer, n aravind
N. Nani Aravind: More or less, we' expect to maintain the e same level as last year, and it depends on the mix of any new orders of O&M and growth in MDO may probably jump the margins by 0.25%. But at this stage, we estimate stability at the last year level. Prit: Understood. And do we have any plans for raising funds?
Answer, n aravind
N. Nani Aravind: At this moment, no, sir. If new opportunities or any investment opportunities arise, we may consider approaching the market. Prit: What would be our debt level at present?
Question
Rohit Sajja: And with a margin increase of not 0.5% sir, 0.25 to 0.5.
Answer, s ramaiah
S. K. Ramaiah: No, it is like this. The opportunity what has been mentioned is based on the balance ordering to be done on the main EPC orders already ordered, which is some of the items like main plant services work, balance of plant work, then structural work, civil works. That is substantially it is there to be ordered by BHEL, by Adani , then NTPC also has to order. The other thing what we said was the new investments and development will come at 46,000 megawatts new plants, that has to take shape. That will continues to be there in the next couple of years. And where the EPC orders have been placed by NTPC, Adani and utility companies in the last 6 months to 1 year. There the ordering has to be done more because they have to ramp up the ordering.
Answer, s ramaiah
So that is where we said that initially, we can have immediately about INR40,000 crores to INR50,000 crores and balance INR40,000 crores, INR50,000 crores, we'll come in the next couple of years. Vinay: So even if I take INR1 lakh crores over a period of 6, 7 years, we are looking at around INR14,000 crores per year, roughly. I mean, not in the same linear method, but is that the number? Am I getting it wrong?
Answer, n aravind
N. Nani Aravind: Yes. During the year, there was a slowdown in execution of FGD orders. And suddenly, government direction accelerated progress, and the Udupi project, which was moving slowly received instruct ion from Adani to complete this project by March. As a result, execution picked up from Q2 onwards, driving higher order execution in the power sector.
Question
Amay Sharda: Okay. So we expect this momentum to continue for the rest of the year?
Answer, n aravind
N. Nani Aravind: Yes. By before March, we will complete. So we can expect this level of order execution till March. Amay Sharda: Okay. Thank you so much. Thank you.
Answer, s ramaiah
Thanks for tour investor community and our colleagues here. I think as projected by Aravind and also Rohit and as we discussed with the very interesting questions and all, it is reasonably assured to say that we will be on track in achieving the targets on the ordering about INR10,000 crores because we are almost near to that 50% by end of this beginning of the third quarter. And with a lot more opportunities are coming up and new segments of the business, we are looking at it. On the revenue side, we have seen the third and fourth quarters are always there will be upswing will be there. That is where the INR2,200 crores will be reasonable and will be possible. And with these-type of opportunities and investments coming up, I think, particularly in the power sector, steel sector, infrastructure side, railways and other segments, perhaps we will continue to focus for the growth in the coming couple of years. And another area perhaps we can look at as an interest and diversification is in data centres.
Answer, s ramaiah
Of course, data centres development and the software part of it is different, but the hardware part of it is an interesting point because these data centres need a lot of power capacity with substations, which is our specialization. Then, it needs a lot of infrastructure works and development, civil works and then other facilities, balancing facilities etc So this is a segment, which we can gainfully try to work based on the expertise what we have gained and there are other sectors also, which come up. As I said, refineries can come up and apart from the steel plants, all those areas will be available.
Questions about this call
- When was the Power Mech Projects Q2 FY26 earnings call transcript filed?
- Power Mech Projects filed the transcript with the exchange on 20 Nov 2025. This page is built from that transcript.
- What does this page list?
- 144 statements from the transcript across 13 topics, 95 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 13 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.