Rail Vikas Nigam Q4 FY26 earnings call

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Stand-alone order inflow was INR 4,644 crores during the quarter ended January to March 2026 and INR 5,875 crores for the full financial year 2025-26. The company expects revenue to rise around 15-20% in 2026-27 and expects margins to increase and be much better than this year. The BharatNet project, awarded by Bharat Sanchar Nigam Limited, is a INR 13,236 crore initiative to provide high speed broadband connectivity in rural and remote areas through 8,206 kilometers of OFC infrastructure. Stand-alone turnover increased by 47.6% QoQ from quarter three financial year ’26 to quarter four of financial year ‘26, and grew 4.78% from quarter four of ‘25 to quarter four of ’26 and 0.72% YoY, reflecting healthy execution momentum and improved project activity during the quarter. The company paid an interim dividend of INR 208 crores and the board extended a final dividend of INR 148.03 crores, subject to approval of shareholders.

The numbers management gave

Results

  • Stand-alone turnover increased by 47.6% QoQ from quarter three financial year ’26 to quarter four of financial year ‘26, and grew 4.78% from quarter four of ‘25 to quarter four of ’26 and 0.72% YoY, reflecting healthy execution momentum and improved project activity during the quarter.
    Show source
    The company reported a strong growth in revenue during Q4 financial year 2025-26 with the stand-alone turnover increasing by 47.6% QoQ, if I compare it to quarter three financial year ’26 to quarter four of financial year ‘26.
  • Consolidated turnover grew by 42.94% from quarter three to quarter four, 4.8% from quarter four ’25 to ‘26, and 2.45% year-over-year.
    Show source
    On a consolidated basis as well, turnover grew by 42.94% quarter three to quarter four, 4.8% quarter four ’25, ‘26 and 2.45% year-over-year, demonstrating sustained business expansion and strong order execution capabilities.
  • Standalone EBITDA declined by 16.88% from quarter three to quarter four, 33.55% from quarter four to quarter four ’25 to ’26, and 26.74% YoY; EBITDA margin reduced from 10.36% in quarter three to 5.83% in quarter four FY26.
    Show source
    Standalone EBITDA declined by 16.88% if I compare quarter three to quarter four; 33.55% quarter four to quarter four ’25 to ’26; and 26.74% YoY, while EBITDA margin reduced from 10.36% in quarter three to 5.83% in quarter four FY26.
  • PAT declined by 19.66% QoQ, 43.14% quarter four to quarter four compared to FY25-26, and 32% YoY, indicating margin pressure and increased cost burden during execution.
    Show source
    Similarly, PAT declined by 19.66% QoQ and 43.14% quarter four to quarter four compared to FY25-26, and 32% YoY, indicating margin pressure and increased cost burden during execution.
  • Building works of RVNL and the company contributed 31.40% to total revenue from operation, an increase of 129.50% from the previous year.
    Show source
    I want to brief that building works of this RVNL and the company have contributed 31.40% to the total revenue from operation, so showing an increase of 129.50% from the previous year.
  • RVNL's JVs and subsidiaries contributed INR 399.86 crore to consolidated revenue and INR 64.23 crore to PAT in Q4 FY26.
    Show source
    Performance of our JVs and subsidiaries remained encouraging, contributing INR 399.86 crore to consolidated revenue and INR 64.23 crore to PAT.
Show 4 more statements

Results

  • RVNL received dividend income of INR 43.45 crore from JVs and subsidiaries during Q4 FY26 and INR 47.88 crore for the full year, contributing positively to consolidated profitability.
    Show source
    Additional dividend income received from JVs and subsidiaries stood at INR 43.45 crore during Q4 and INR 47.88 crore for the full year, which contributed positively to the company's consolidated profitability.
  • Execution from bidding works increased by almost 129%, from INR 2,737 crore in financial year ’24, ’25 to INR 6,283 crores in financial year ’25, ‘26.
    Show source
    In financial year ’25, ‘26, it has increased by almost 129%, which was INR 2,737 crore in the financial year ’24, ’25, which has increased to INR 6,283 crores in the financial year ’25, ‘26.
  • EBITDA decline was mainly driven by a few onerous contracts and reconciliation adjustment relating to joint ventures.
    Show source
    The decline in the above parameter is mainly driven by a few onerous contracts and reconciliation adjustment relating to joint ventures.

Money and capital

  • The company paid an interim dividend of INR 208 crores and the board extended a final dividend of INR 148.03 crores, subject to approval of shareholders.
    Show source
    I want to inform that the company has paid an interim dividend of INR 208 crores, and board has also extended a final dividend of INR 148.03 crores, subject to approval of shareholders.

What it expects ahead

What management expects

  • The company expects revenue to rise around 15-20% in 2026-27 and expects margins to increase and be much better than this year.
    Show source
    We are definitely expecting a good rise in our revenue, which will be around, say, 15-20%.
  • The company targets at least 5-10% profit from each bidding work.
    Show source
    We have kind of positioned ourselves like that, that we should get at least 5-10% profit from each works of bidding.
  • RVNL expects good revenue and profit margin this year from the BharatNet project as execution progresses across project locations.
    Show source
    Project execution momentum has improved significantly, and work is now progressing at a good pace across project locations, and we are expecting good revenue and profit margin in this year.
  • The company expects execution from bidding works to increase tremendously in the coming years.
    Show source
    So, the order book inflow and the execution matches, but in the coming years, the execution from the bidding works will increase tremendously because as you've seen in the last year, as compared to financial year ’24, ‘25.
  • The company expects the first quarter to be slightly challenging but is hopeful of achieving the targets and having good revenue, profit and margins. Replaced by a later filing.
    Show source
    But you know the quarter -- the first quarter will be slightly challenging for us, but we are hopeful to achieve the targets and have a good revenue and good profit, good margins.

Orders

  • Stand-alone order inflow was INR 4,644 crores during the quarter ended January to March 2026 and INR 5,875 crores for the full financial year 2025-26.
    Show source
    During the quarter ended January to March 2026, the stand-alone order inflow stood at INR 4,644 crores, while for the full financial year 2025-26, standalone order inflows were INR 5,875 crores.
Show 7 more statements

Orders

  • The company secured works amounting to INR 1,201 crores with joint ventures.
    Show source
    2 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 With joint ventures, we have also secured works amounting to INR 1,201 crores.
  • Total order book stood at INR 99,262 crore as on March 31, 2026.
    Show source
    So as on March 31, 2026, the company's total order book stood at an impressive INR 99,262 crore.
  • Order book comprised railways at INR 57,000 crores, signaling at INR 14,900 crores, port, roads, highways at INR 10,400 crores, metros at INR 9,900 crores, power and transmission works of about INR 4,000 crores, and hydro and irrigation projects at INR 2,000 crores.
    Show source
    The order book is primarily driven by railways with INR 57,000 crores followed by signaling at INR 14,900 crores; port, roads, highways at INR 10,400 crores; and metros at INR 9,900 crores, and we have works of power and transmission of about INR 4,000 crores and hydro and irrigation project at INR 2,000 crores.
  • The company said its nomination and bidding breakup was almost 50%, 50-50 each; it described 45,000 works as bidding and INR 45 crores as nomination basis.
    Show source
    Presently, 45,000 works of bidding and INR 45 crores are on nomination basis.
  • The company said almost 30,000 railway works are going on in its pipeline.
    Show source
    So now our business strategy is that we should focus on railway works which we already have in pipeline, which is almost 30,000 works are going on.
  • The company recently received one railway bidding work of INR 400 crores for its JVs.
    Show source
    Saleem Ahmad 7 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 JV, we have got one work in recently from railways, which is a bidding work of INR 400 crores right now.
  • Order book from bidding works was around INR 6,000 crore, while execution from bidding works was around INR 6,300 crore, during the last financial year.
    Show source
    Saleem Ahmad Actually, if you see the order book, which we have reviewed it during the last financial year was around INR 6,000 crore, and the execution from the bidding works also stand around INR 6,300 crore.

What it is building and selling

Projects and capacity

  • The BharatNet project, awarded by Bharat Sanchar Nigam Limited, is a INR 13,236 crore initiative to provide high speed broadband connectivity in rural and remote areas through 8,206 kilometers of OFC infrastructure.
    Show source
    One is BharatNet project, which has been awarded by Bharat Sanchar Nigam Limited, is a INR 13,236 crore initiative to provide high speed broadband connectivity in rural and remote areas through 8,206 kilometers of OFC infrastructure.
  • RVNL has achieved 15.01 physical progress on the BharatNet project till date.
    Show source
    Till date, RVNL has achieved 15.01 physical progress.
  • The Rishikesh Karnaprayag Rail project in Uttarakhand is being developed at a cost of INR 37,000 crore; the 125-kilometer project has achieved 74% overall progress, with around 96% tunnel excavation complete.
    Show source
    Being developed at a cost of INR 37,000 crore, the 125-kilometer project has achieved 74% overall progress, with around 96% tunnel excavation complete.
  • The Vande Bharat sleeper train set is a INR 14,400 crore project with 35 years maintenance arrangement being executed by RVNL's SPV Kinet Railway Solutions.
    Show source
    Another important project is Vande Bharat sleeper train set, a INR 14,400 crore project with 35 years maintenance arrangement being executed by our SPV Kinet Railway Solutions.
  • The first prototype training set for the Vande Bharat sleeper train set is targeted for launch in December 2026.
    Show source
    We are hopeful that first prototype training set is targeted for launch in December 2026.
  • RVNL's Rishikesh-Karnaprayag Rail Project is targeted for completion by December 2029; it will improve access to the Himalayan region, support the Char Dham pilgrimage corridor, strengthen border connectivity, boost tourism and local economies, and reduce travel time in the region.
    Show source
    Target for completion by December 2029, the project will improve access to the Himalayan region.
Show 1 more statement

Deals and partners

  • The company is talking to other PSUs and government for management works on PMC basis and has got works from NMDC and the Visakhapatnam Port Trust.
    Show source
    We have got works from NMDC, the Visakhapatnam Port Trust, and other, and we are focusing that we should get more works on PMC.

Risks, rules and outside factors

Outside factors

  • The company gets price variation in most contracts to control market fluctuations; some contracts are fixed and some are dynamic.
    Show source
    Some are fixed contracts, some are dynamic also, but in most of the contracts we get the price variation, which controls the fluctuation of the market.

Everything else said on the call

What management stressed

  • The company is using latest technologies, a pay model with 5G functions that tracks financial and planned progress against actual progress, drones for site inspection, and software dashboards to monitor performance.
    Show source
    We are using a pay model, which give us the 5G functions, which gives the progress, financial progress, and planned progress versus the actual progress.
  • The company is not bidding very aggressively for bidding works. Replaced by a later filing.
    Show source
    But this time we are not bidding very aggressively for the bidding works.

Other

  • The company achieved an MoU rating of very good for the year 2024-25 from Department of Public Enterprises.
    Show source
    As a result of which, the company has achieved an MoU rating of very good for the year 2024-25 from Department of Public Enterprises.
  • The company will implement the stakeholder’s proposed solution and put it on its website. Replaced by a later filing.
    Show source
    This is a very good solution, and we will definitely implement it and put it on our website, so that every stakeholder can go through it.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Abhishek K Leekha : Nestle Wealth LLP 1 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 Moderator Good afternoon, ladies and gentlemen.

    Answer, saleem ahmad

    Saleem Ahmad Good afternoon, everyone. Thank you for joining us today for earnings call of RVNL for this quarter and year ended 31st March, 2026. As all of you know, RVNL’s portfolio comprises primarily of infrastructure focused businesses, which stands across rail infrastructure, metros, roads and highways, transmission and port harbors. Although this year has been challenging for the company, RVNL has remained focused on sustaining its operational performance and ensuring timely execution of key projects. Despite market and sectoral headwinds, we continue to maintain a strong order book, and are actively working towards improving efficiency and expanding business opportunities. With continued government emphasis on relevant perceptual development, we remain confident about the long-term growth prospects of the company. As a result of which, the company has achieved an MoU rating of very good for the year 2024-25 from Department of Public Enterprises.

    Answer, saleem ahmad

    I'm pleased to share that our order book continues to remain strong and diversified, providing healthy multiyear execution visibility for the company. During the quarter ended January to March 2026, the stand-alone order inflow stood at INR 4,644 crores, while for the full financial year 2025-26, standalone order inflows were INR 5,875 crores. 2 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 With joint ventures, we have also secured works amounting to INR 1,201 crores.

    Answer, earnings conference

    So as on March 31, 2026, the company's total order book stood at an impressive INR 99,262 crore. The order book is primarily driven by railways with INR 57,000 crores followed by signaling at INR 14,900 crores; port, roads, highways at INR 10,400 crores; and metros at INR 9,900 crores, and we have works of power and transmission of about INR 4,000 crores and hydro and irrigation project at INR 2,000 crores. Growth and movement in the order book was supported by new railway and multi sector infrastructure works awarded to RVNL. Stunning execution leading to revenue recognition and our disciplined margin focused selective bidding strategy. This strong and well-balanced order book positions the company competently for sustained growth in the coming years. The company reported a strong growth in revenue during Q4 financial year 2025-26 with the stand-alone turnover increasing by 47.6% QoQ, if I compare it to quarter three financial year ’26 to quarter four of financial year ‘26. We have a growth of 4.78% when compared to quarter four of ‘25 to quarter four of ’26, and 0.72% YoY growth, reflecting healthy execution momentum and improved project activity during the quarter.

    Answer, earnings conference

    On a consolidated basis as well, turnover grew by 42.94% quarter three to quarter four, 4.8% quarter four ’25, ‘26 and 2.45% year-over-year, demonstrating sustained business expansion and strong order execution capabilities. However, despite the robust increase in revenue, profitability remained under pressure during the quarter. Standalone EBITDA declined by 16.88% if I compare quarter three to quarter four; 33.55% quarter four to quarter four ’25 to ’26; and 26.74% YoY, while EBITDA margin reduced from 10.36% in quarter three to 5.83% in quarter four FY26. Similarly, PAT declined by 19.66% QoQ and 43.14% quarter four to quarter four compared to FY25-26, and 32% YoY, indicating margin pressure and increased cost burden during execution. On a consolidated basis, the EBITDA impact witnessed declines despite higher turnover. The decline in the above parameter is mainly driven by a few onerous contracts and reconciliation adjustment relating to joint ventures. Overall, the results indicate strong revenue visibility and execution growth for the company.

    Answer, earnings conference

    However, pressure on margins and profitability remains a key area of concern, which may require close monitoring in the coming quarters. I want to brief that building works of this RVNL and the company have contributed 31.40% to the total revenue from operation, so showing an increase of 129.50% from the previous year. I want to inform that the company has paid an interim dividend of INR 208 crores, and board has also extended a final dividend of INR 148.03 crores, subject to approval of shareholders. 3 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 I want to highlight the progress of the major projects undertaken by Rail Vikas Nigam Limited.

    Answer, earnings conference

    One is BharatNet project, which has been awarded by Bharat Sanchar Nigam Limited, is a INR 13,236 crore initiative to provide high speed broadband connectivity in rural and remote areas through 8,206 kilometers of OFC infrastructure. Till date, RVNL has achieved 15.01 physical progress. Project execution momentum has improved significantly, and work is now progressing at a good pace across project locations, and we are expecting good revenue and profit margin in this year. Another important project is Rishikesh Karnaprayag Rail project, which is of a national importance in Uttarakhand. Being developed at a cost of INR 37,000 crore, the 125-kilometer project has achieved 74% overall progress, with around 96% tunnel excavation complete. Target for completion by December 2029, the project will improve access to the Himalayan region. Another important project is Vande Bharat sleeper train set, a INR 14,400 crore project with 35 years maintenance arrangement being executed by our SPV Kinet Railway Solutions.

    Answer, earnings conference

    We are hopeful that first prototype training set is targeted for launch in December 2026. SPV has also received the Bronze Air Design Award 2026 in Italy for excellence in mobility and transportation design. Performance of our JVs and subsidiaries remained encouraging, contributing INR 399.86 crore to consolidated revenue and INR 64.23 crore to PAT. Additional dividend income received from JVs and subsidiaries stood at INR 43.45 crore during Q4 and INR 47.88 crore for the full year, which contributed positively to the company's consolidated profitability. I also brief that the employee productivity showed improvement, which has increased from INR 21.23 crore to INR 22.46 crore. This growth reflects enhanced operational efficiency and better utilization of human resources. RVNL continues to demonstrate disciplined execution and stable operational performance, supported by a strong and diversified order book.

    Answer, earnings conference

    We remain focused on efficient project delivery, margin discipline, and conversion of healthy L1 and LOA in pipeline. We are also actively encouraging opportunities in diversified infrastructure and emerging business areas. With sustained progress in key national infrastructure projects, the company is well positioned for long term sustainable growth and value creation. Thank you for your continued trust and support. So, we are open for the question and answer. Thank you.

    Answer, earnings conference

    Wait for a moment as the question queue assembles. The first question comes from the line of Vishal Periwal from PL Capital. Please go ahead.

  2. Question

    Vishal Periwal Yes sir, thanks for the opportunity. Sir, on the margins, though you did clarify it is coming from one of the JV work that we are doing. So, is it fair to say, is the work has concluded and probably we'll have a better margins from quarter one of FY27, or do you think probably the base of 4%, 4.5% EBITDA margin is a new base for us?

    Answer, saleem ahmad

    Saleem Ahmad PAT looks lower in this quarter, but if we adjust for the onerous contract of INR 54 crores, and we have paid municipal taxes on new building, and we have readjusted after reconciliation of our SPV amounting to INR 35 crores. So, you will see that the PAT is slightly better than the last year than the last quarter. So definitely, now the adjustment for the onerous contract has been done, and we are hopeful that we will definitely improve our margins in the first quarter of ’27 year. Thank you.

  3. Question

    Vishal Periwal Okay. Yes, thanks for the clarification. Maybe one last question from me is, I think we have seen an increase in the receivables in financial year ‘26 numbers, and that has led to lower cash and lower other income. So, is it coming from a big segment or probably anything, any color that can be provided?

    Answer, saleem ahmad

    Saleem Ahmad Cash flow is a challenge, because we are working for Ministry of Railways, and we have to get money from Ministry of Railways. If you see that our INR 3,400 crores were recoverable from MoR, which we could not get within this year, but we have received now in April. So that was the reason for cash flow negative share.

  4. Question

    Abhishek K Leekha Okay, thank you. And what kind of top line growth that can be expected in 2026-27, and how should we take the margin outlook from current? Because what I understand from last con call was you mentioned that 2026-27 as far as execution would be better off and also margins would be comparatively on the brighter side.

    Answer, saleem ahmad

    Saleem Ahmad Yes. We are definitely expecting a good rise in our revenue, which will be around, say, 15-20%. And even the margins will definitely increase. That I want to assure you. And it will be much better than this year.

  5. Question

    Abhishek K Leekha Should we expect it, like from the current quarter itself, June quarter onwards? Like the top line growth and followed by the margin growth to be start seeing? 6 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 Saleem Ahmad Yeah, definitely, QoQ, year wise, definitely there will be improvement.

    Answer, saleem ahmad

    But you know the quarter -- the first quarter will be slightly challenging for us, but we are hopeful to achieve the targets and have a good revenue and good profit, good margins.

  6. Question

    Vishal Periwal Yes, sir. Thanks for the follow-up. Sir, in terms of our order book of INR 99,000 crores odd, what is the breakout in nomination and competitive bidding now?

    Answer, saleem ahmad

    Saleem Ahmad If you see our breakup for nomination and bidding is almost 50%, 50-50 each. Presently, 45,000 works of bidding and INR 45 crores are on nomination basis. So now our business strategy is that we should focus on railway works which we already have in pipeline, which is almost 30,000 works are going on. In addition, we are talking to other PSUs and government for management works on PMC basis. We have got works from NMDC, the Visakhapatnam Port Trust, and other, and we are focusing that we should get more works on PMC. And third line will be -- vertical will be from the bidding works. But this time we are not bidding very aggressively for the bidding works.

    Answer, saleem ahmad

    We have kind of positioned ourselves like that, that we should get at least 5-10% profit from each works of bidding. So that is our target and our strategy.

  7. Question

    Vishal Periwal Sure, sir. And in terms of our order inflow, though you did clarify stand alone and, this is FY26 and quarter four. For the JVs can you also share what is the inflows in quarter four and FY26?

    Answer, saleem ahmad

    Saleem Ahmad 7 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 JV, we have got one work in recently from railways, which is a bidding work of INR 400 crores right now.

    Answer, earnings conference

    And we are expecting that we should get more work in future, definitely.

  8. Question

    Vishal Periwal Okay. So sir, I think if I look at our order inflow, including JVs, everything, is it to the tune of maybe like INR 7,000 odd crore for this year? And we have done execution of INR 20,000 odd crore in terms of revenue. And our order book has seen increase. So is there a large part of this change is coming from the scope change or any anything that you can share on this?

    Answer, saleem ahmad

    Saleem Ahmad Actually, if you see the order book, which we have reviewed it during the last financial year was around INR 6,000 crore, and the execution from the bidding works also stand around INR 6,300 crore. So, the order book inflow and the execution matches, but in the coming years, the execution from the bidding works will increase tremendously because as you've seen in the last year, as compared to financial year ’24, ‘25. In financial year ’25, ‘26, it has increased by almost 129%, which was INR 2,737 crore in the financial year ’24, ’25, which has increased to INR 6,283 crores in the financial year ’25, ‘26. So, our order book is healthy, and we hope that with increased execution also, the order book will be able to give us a good handsome revenue.

  9. Question

    Vishal Periwal Maybe one last question.

    Answer, saleem ahmad

    Saleem Ahmad And the change of [indiscernible 00:22:23] -- many projects is there, especially in macro projects and other projects, which we are excluding. Even gold projects, we got change of scope as per the requirement of the site and clients decor.

  10. Question

    Vishal Periwal In terms of -- I think a lot of cost inflation that we are seeing in terms of the commodity prices and other things. I understand nomination order, which is almost INR 45,000 odd crores, the things are passed through. But in competitive bidding, is it a fixed price contract or there are escalations? Can you share anything on that – this one?

    Answer, earnings conference

    Some are fixed contracts, some are dynamic also, but in most of the contracts we get the price variation, which controls the fluctuation of the market. But definitely, challenges will be there, yeah.

Show 3 more questions
  1. Question

    Abhishek K Leekha Yes, sir. Thank you for the follow-up question. I just want to have the understanding on what steps the company is taking, so that fast track execution can be cleared on priority, in terms of like automation or steps that that are being taken, which helps the company to enhance the execution capability.

    Answer, saleem ahmad

    Saleem Ahmad 9 Rail Vikas Nigam Limited Q4 FY26 Earnings Conference Call 26.05.2026 You know, the main challenge that we have seen for us is faster execution.

    Answer, earnings conference

    Then only we can have good revenue and good margins. So, our whole team is focusing on it. We are using latest technologies. We are using a pay model, which give us the 5G functions, which gives the progress, financial progress, and planned progress versus the actual progress. We are using drones for the site in inspection, and we are using many kind of softwares with pure dashboards and give us the performance on -- all on our dashboard. So many things are being done at every level, from the supervisory to the top management, and our focus is for the faster execution of the work and timely execution of the work.

  2. Question

    Abhishek K Leekha Can we have a presentation, kind of wherein will you give the points or the areas which the company is doing a lot of exciting work and good work. So that we also understand what exactly the company is doing in terms of execution readiness and how well that can be put in use or has been -- or you might be using it, so that it gets communicated well amongst the stakeholders.

    Answer, saleem ahmad

    Saleem Ahmad Thank you. This is a very good solution, and we will definitely implement it and put it on our website, so that every stakeholder can go through it. And if they have some suggestion, we will be happy to incorporate those.

  3. Question

    Abhishek K Leekha Thank you for that. And if that can be in a presentation, in a quarterly or a yearly kind of a thing, that would be great also, because a lot of questions can be put to on basis of that. And one more thing, has RVNL been approved together or upgrade corridors specifically for the defense logistics? Because in this war scenario, railways can be -- also be used as a defense logistics. So, anything specifically that can be done by RVNL in that line?

    Answer, saleem ahmad

    Saleem Ahmad Yeah, definitely, we are doing, but we will not be able to explain here. There will be many strategic projects in pipeline.

Questions about this call

When was the Rail Vikas Nigam Q4 FY26 earnings call transcript filed?
Rail Vikas Nigam filed the transcript with the exchange on 2 Jun 2026. This page is built from that transcript.
What does this page list?
35 statements from the transcript across 9 topics, 27 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 13 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.