VA Tech Wabag Q1 FY25 earnings call: VA Tech Wabag expects EBITDA margins to remain in the 13% to 15% band, with movement between quarters and years depending on the mix of projects

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company expects EBITDA margins to remain in the 13% to 15% band, with movement between quarters and years depending on the mix of projects. The company is planning at least 100 CBG projects over the next few years. The company has more than 125 IP rights and trademarks; VA Tech Wabag has 125+ proprietary IPRs; VA TECH WABAG LIMITED had more than 125 patents and trademarks.

The numbers management gave

Money and capital

  • The company does not intend to have any long-term debt; any debt would only cover a cash-flow mismatch.
    Show source
    We don't have and our intention is not to have any long term debt.

What it expects ahead

What management expects

  • The company expects EBITDA margins to remain in the 13% to 15% band, with movement between quarters and years depending on the mix of projects.
    Show source
    Skandaprasad S: See, we have given already a medium term outlook of 13% to 15% in terms of our EBITDA margins.
  • The company is looking for 15% to 20% top line growth.
    Show source
    We have given you the 15% to 20% top line growth we are looking at.
  • The company is looking for an order book of INR15,000 to INR16,000 crores for next year.
    Show source
    And for next year, we a re looking at INR15,000 to INR16,000 crores of order book.
  • The company wants at least 50% of its total revenue to be international and is confident it will exceed that share.
    Show source
    We w ant to be, at least 50% International of our total revenue.
  • The company expects its broad MMR to be about 25%.
    Show source
    I think about 25% would be the broad MMR.
  • The company expects preferred contracts to come in within this fiscal year, after client-side internal approvals and contract discussions.
    Show source
    And it should happen within this fiscal year.
Show 3 more statements

What management expects

  • The company expects opportunities for EP projects internationally, but says that will not be the sole factor in deciding whether to take a project.
    Show source
    When we go internationally, there is an opportunity to have EP projects more, but that will not be the only focus of determining whether or not to take a project.
  • The company expects semiconductor-related opportunities to emerge around the end of this year or early next year, as manufacturing investment is occurring.
    Show source
    So one can expect that end of this year, early next year, you can see something coming from semiconductor.
  • Hydrogen manufacturing is not yet commercially viable, but VA Tech Wabag expects it may become more economically viable in a year or a year and a half as investment goes into manufacturing electrodes, with more orders expected then.
    Show source
    But we feel that with lot of investment going into this hydrogen manufacturing of electrodes, maybe in a year, year and a half, it will become more economically viable.

What it is building and selling

Projects and capacity

  • The company is planning at least 100 CBG projects over the next few years. Replaced by a later filing.

Segments

  • The company has more than 125 IP rights and trademarks; VA Tech Wabag has 125+ proprietary IPRs; VA TECH WABAG LIMITED had more than 125 patents and trademarks.
    Show source
    We have more than 125 IP rights, trademarks.
  • Technology-challenging projects are more concentrated in desalination and water reuse, and the company expects its focus to tilt toward those areas.
    Show source
    And our technology challenging projects are more going into desal and water reuse.
  • European exposure is close to zero.
    Show source
    We are not focusing on the Europe geography; we have defocused today close to zero is our European exposure.
  • The company will remain focused on its core markets: emerging economies, India, Middle East, Africa, Southeast Asia and CIS countries. Replaced by a later filing.
    Show source
    So just to clarify, our focus will remain on our core markets, emerging economies, India, Middle East, Africa, Southeast Asia and CIS countries.

Deals and partners

  • The company has signed with Peak Ventures to jointly develop CBG projects.
    Show source
    We have signed with Peak Ventures to develop it together.

Risks, rules and outside factors

Risks and disputes

  • The company has not yet received the money under the arbitration award; the losing party's objection is still being cleared, and the company expects to receive the money once it is cleared.
    Show source
    Rajiv Mittal: Not yet.

Everything else said on the call

Group structure

  • The company Austria received about EUR8.5 million as a dividend from the Romanian subsidiary, and VA Tech Wabag Limited received EUR1.2 million as sale consideration; both amounts resulted from the divestment of the Romanian subsidiary.
    Show source
    And over and above that, we've also received a EUR1.2 million, which is a sale consideration.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Rahul Jain: I'm comparing Q1 to Q1.

    Answer, rajiv mittal

    Rajiv Mittal: Q1 to Q1, our growth if you say on a consolidated basis, it's about 13%, on standalone basis it's 7.2% and margin is 13 % EBITDA versus 11.9% . All the numbers are up and PAT is almost 31%. So I don't know where you are reading these numbers, if it's Q1 to Q1. Rahul please check your numbers.

  2. Question

    Rahul Jain: Sir, I think your India business, which is $2.6 billion, declined 22% against last year at $3.4 billion. I'm comparing those numbers.

    Answer, rajiv mittal

    Rajiv Mittal: I don't know where you're picking these numbers, Rahul. None of your numbers are correct.

  3. Question

    Rahul Jain: My second question will be, I see you have a pipeline of around INR6 ,000 crore in India and MEA region, right? So what are these orders related to? And when can we expect this to come in our order book?

    Answer, rajiv mittal

    Rajiv Mittal: See, when we say that we are confident and we use the word preferred contract or. That means this is a question where we are already a lowest bidder declared. Some places evaluations have been done. Some places still evaluation is going on and post that there is a process at the client's end to go through all the internal approvals. Then we will get into contract discussion. And it should happen within this fiscal year. Normally it takes anything between one, two, four, five months.

    Answer, rajiv mittal

    So we think even in this calendar year, we should see these orders progressively. Some of it will start in next one or two months, some of it in three to four months, and some of it in four to five months.

  4. Question

    Rahul Jain: Yes Sir, got it. VA Tech Wabag Limited August 09, 2024 Page 6 of 19 Rajiv Mittal: This is a firm pipeline.

    Answer, rajiv mittal

    It's not a normal pipeline. This is all we have bid, we are preferred bidder, we are lowest bidder. All that is a very concrete pipeline.

  5. Question

    Rahul Jain: Got it. My next question is, in the budget it was noted that government will be promoting water supply, sewage treatment and solid waste treatment projects and services in 100 large cities. So how are you looking at this opportunity and can you highlight, how can be the competitive intensity in such p lace? Because there are several other EPC players which are going for the water projects wherein they have highlighted significant opportunity in India as well as globally. How is the competition scaling up on the business side?

    Answer, rajiv mittal

    Rajiv Mittal: See Rahul, its very clear. Where there is opportunity, competition is most welcome. We have never worried about competition because we understand our strengths, we understand our technology superiority. We understand our offerings, what we give it to our customer and how do we add value. One thing is very clear, that we select our projects very carefully. Where we see, that we have a good chance, the payment security is there, cash flow is there and we have an opportunity to use our technology superiority, we select a few projects, and projects we target , generally, we are both technically and commercially very attractive. So competition?

    Answer, rajiv mittal

    Yes, will be there. Has to be there. But that does not put us in any concern. We are happy to fight the competition and win our quota of projects.

  6. Question

    Rahul Jain: Sure, sir. Next question is, are there any semiconduct or or CBG or green hydrogen projects in pipeline in the next two years? If you can highlight that also?

    Answer, rajiv mittal

    Rajiv Mittal: This is definitely, if you've seen our presentation, we put it on our website for investors and the analyst. I think, is clearly saying th at we are into this new field. You've mentioned the two, which is semiconductor which needs ultra-pure water. Compressed biogas, which is a new initiative of the government, for clean and green environment. We have been in this business already for 30 years. Now it's only question of converting that into a specification which we can directly pump into the fuel stations or the pipeline. We have to do a little bit of more cleaning up, which we are already announced a few mo nths back.

    Answer, rajiv mittal

    We have signed with Peak Ventures to develop it together. And we are willing to take these projects forward. And we are planning at least 100 projects to do it over the next few years. Same thing is with semiconductor. We have ultra-pure technologies. We have our references. We are talking to few other global leaders where we will be the technology champions in that and we will then be going after the projects.

    Answer, rajiv mittal

    Same thing we are doing for hydrogen and same thing for digitization and AI, to be included in our project. These are the four initiatives we will work over the next few years and make sure they all get integrated in our business.

  7. Question

    Thank you so much for taking my question. So my first question would be on the segmented results that you've declared on a consolidated basis. For India we can see that this quarter YoY there was a decline of 22% in revenues. Could you give some colour as to, firstly, why the India business is down? Number one. And number two is that, we can see that the export revenue has more than doubled. So, again, is there a focus shift in the company? What is going on? That's my first question.

    Answer, skandaprasad s

    Skandaprasad S: The mix of revenues between India and ROW is usually how the projects are progressing. You've seen in the last few years with the strategy shift, we have focused more on the International business. Also, over the last six to nine months in the general election phase, there has also been a lull in terms of the Indian business. The main contributors for revenue are the SIBUR project and Senegal project, as Mr. Mittal mentioned in his opening remarks. Which are completing their supply phase and moving into the installation commissioning phase. So deliveries have been happening over the last H2 as well as into Q1, and will get largely completed by Q2. So these are the revenues, which are getting a bigger share, and that's why you see that, verus first quarter of last year , in the segment results, the international revenue is better.

    Answer, skandaprasad s

    While the Indian revenue on the other side, it's a mix of projects. You will see over this year, this will slowly change because the newer projects in India, specificall y the 400 MLD desalination plant, will start picking up the deliveries starting Q4. So the manufacturing will happen over the next few quarters and the next year you will have lot of deliveries here. Of course, this mix will keep dynamic because the INR6,000 crores worth of projects where we said we are preferred bidders has a very good mix of International, large complex projects. So when they also come in, the mix is likely to swing, but I would allude you to look at us over, say, three-four year kind of period, which is what we presented during the year end. And you saw we were about 40% or more on the international business, about 30% on industrial and EP was about one-third of the EPC. So you'll have to see us over a longer period rather than merely a quarter-over-quarter because the mix of projects may change.

  8. Question

    Nidhi Shah: Got it. Also, last quarter you mentioned that the order pipeline target for this year is about INR16,000 crore. Are we still maintaining on that number? Or would we like to revise tha t number?

    Answer, skandaprasad s

    Skandaprasad S: We are expecting with the robust order pipeline and also the orders that where we have told you that we are preferred bidder, we are confident that we will be on track on this. In that range is what we are expecting it to be.

    Answer, rajiv mittal

    Rajiv Mittal: See, I just want to correct. It's not the order intake. INR16,000 crores was the order-book Nidhi Shah: Yes, my bad.

  9. Question

    The another question that I had is, that so far in Q2, have you seen any further developments on this order booking side? Have you booked anything concretely in the order booking in Q2 so far?

    Answer, rajiv mittal

    Rajiv Mittal: This is what we told you. And INR6,000 crores which is visible to us. A concrete order pipeline which should materialize over the next few months progressively. VA Tech Wabag Limited August 09, 2024 Page 8 of 19 Nidhi Shah: No, I was asking in the last one, one and a half odd month have you booked anything?

  10. Question

    I understand that you're a preferred bidder in INR6,000 crore odd projects. But have you booked anything in the last one and a half month?

    Answer, rajiv mittal

    Rajiv Mittal: So generally if we book anything, we'll make an announcement, Nidhi.

Show 20 more questions
  1. Question

    Aashish Upganlawar: Yes. Sir, wanted to understand, since the balance sheet is not published for Q1, so is there any change in the working capital cycle for us? If you could spell out how the constituents would have moved for us? Number of days, maybe?

    Answer, rajiv mittal

    Rajiv Mittal: See, I think we'll take this question, but generally, I think the business is as usual and it's the first quarter. Whatever deliveries and the work we do in the last quarter , we are in the collection phase in the first and second quarter, and you see this when we publish in a mo nth and a half. But I can tell you our Net Cash position remains positive. Which is good, which is, after many years, in the first quarter itself, we have a positive cash flow. And exact numbers you can ask us. Join one on one call and we'll give you. Otherwise in about, when we close the second quarter, we'll give you anyway the full balance sheet.

  2. Question

    Aashish Upganlawar: Okay. Sir, in the opening remarks, I think you mentioned. The aim is to double revenues and better the margins. So what the time period are we alluding to here?

    Answer, rajiv mittal

    Rajiv Mittal: No, I said the same thing, that we would do it within this decade. So in next four or five years we should achieve it. And with this kind of order backlog and order book which we have given you, I don't think it's difficult or impossible. Very much possible. And that is the reason I have made this statement.

  3. Question

    Aashish Upganlawar: Okay. If I may ask one more. Sir, our business is pretty global. So, risk management becomes most important in terms of receivables, in terms of execution of the work and stuff. So how are things shaping up because globally we are seeing lot of disturbances, plus we are very very spread over across the globe. So any comments on that will be helpful. Any risk that you see now, or is it all smooth?

    Answer, rajiv mittal

    Rajiv Mittal: We have told you before and we continue to evaluate our payment security very, very clearly before we decide to bid for the project. As we have told you, if you can see our order book, most of them have a Central Government or Federal Government guarantees. It's their projects. Like Namami Gange, Swach Bharat. AMRUT, the money is from the central government. Some other projects. Like we talk about Chennai Desal, we talked about Bangladesh, we talked about our projects in Senegal.

    Answer, rajiv mittal

    All these a re multilaterally funded. Organizations like World Bank, Asian Development Bank. JICA from Japan, KFW from Germany. These are all multilateral because we are in a social sector. These are government funds, which fund these VA Tech Wabag Limited August 09, 2024 Page 9 of 19 projects which are directly impac ting the social sector. So we always focus on those projects which give us this payment security. Some of the other clients in, say, Middle East and all, they are all government organization.

    Answer, rajiv mittal

    They are 100% owned by their local government. And some of the other projects where we see that there is LC requirement, we go to our clients and ensure that we have a LC completely backing up our payments and then only we start our project. So from a payment security, we are fully secured.

  4. Question

    Harshal Parikh: Hi. Thanks for the opportunity. Sir, our gross margins have improve d substantially this quarter on a QoQ basis as well as on a YoY basis. So what are the key reasons for the same? And is this gross margin sustainable?

    Answer, skandaprasad s

    Skandaprasad S: See, we have given already a medium term outlook of 13% to 15% in terms of our EBITDA margins. And we are in that band. This will obviously move between quarters and between years, depending on the mix of projects. But this is the band we expect to stay and with the quality of projects that we have, we are confident about this.

  5. Question

    Harshal Parikh: So the improvement in gross margin t his quarter can be linked to the higher international revenues in this quarter. Is my assumption correct?

    Answer, skandaprasad s

    Skandaprasad S: See the EP project mix, International project mix. So all of these are dynamic? Yes, it would be right to attribute it to a higher international mix.

  6. Question

    Harshal Parikh: Sir, and any update on the One City One Operator scheme? Like when will be more order or more cities will be awarded in this scheme?

    Answer, rajiv mittal

    Rajiv Mittal: I think we can say, that now we have completed almost 4.5 years of these pilot projects of Agra, Ghaziabad. There's definitely a believe that this is a way forward for most of the local bodies. We see some new projects are getting conceived which we will bid during this fiscal year. We also have recently participated in fairly large One City One Operator projects in the Middle East market. So, yes, this is some contract type. This is something which we see are getting popu lar not only in India but also internationally.

  7. Question

    Harshal Parikh: That's helpful, sir. So sir, as you said you are a preferred bidder for INR6,000 crores worth of projects, does that include any awards under this One City One Operator kind of scheme?

    Answer, rajiv mittal

    Rajiv Mittal: Not yet, but definitely includes some of our O&M. But some of the One City One Operator we have not put under this category because this is a large pro ject. Let's wait for further progress before we fancy our chances.

  8. Question

    Harshal Parikh: Sir, I have one more question, if you allow? VA Tech Wabag Limited August 09, 2024 Page 10 of 19 Rajiv Mittal: I think you can join the queue.

    Answer, rajiv mittal

    I think you have already taken many more than two. So give others chance and come back.

  9. Question

    Aejas Lakhani: Firstly, Mr. Mittal, credit to you and the team for reallocating the resources in what would have been an otherwise slow quarter in India to the International market, so that we've seen good revenue uptake. So it's credit to you and the team. Sir, my first question is that, could you just speak about how the pace of execution and revenue booking for India looks for the rest of the nine months? And also, could you quantify what has been the EP mix in revenues this quarter versus the same, maybe?

    Answer, rajiv mittal

    Rajiv Mittal: Let me answer the first one and I'll leave it to my colleagues Skanda, to answer the second one. See now is the time to pick up pace. As we said, general elections are behind us. Budget is behind us. Very soon the monsoon will be behind us. This is the best period f or execution. From September till March, best period.

    Answer, rajiv mittal

    So naturally, we always see that the pace of execution in the second half is always far, far better than in the first half. So with all these orders with us. Order pipeline is also pretty full. Enginee ring on some of the projects is more or less complete. So now we are in the phase of ordering, delivery and site work. And we definitely assume, that the pace will be far better than what we have seen till now.

  10. Question

    Aejas Lakhani: Sure sir. And sir, on the second question. The EP mix this quarter versus last quarter, same time?

    Answer, skandaprasad s

    Skandaprasad S: See, it's not a quarter-over-quarter to track, but we are well in line with our strategy. We said at least one-third of our EPC, revenues would come out of EP. And in this quarter we are much better than that because the main contributors have been the SIBUR Project, which is an EP, the Senegal Project, which is also an EP. Skandaprasad S: Okay. And Skanda, follow -up on that. The SIBUR and Senegal, you said the commissio ning and installation will take place in the second quarter, so we should see good revenue uptick from those specific projects in second quarter and onwards, right?

    Answer, skandaprasad s

    Skandaprasad S: Aejas, this is an EP project, Senegal, as well as SIBUR, where our work is engineering, procurement and we only supervise the installation commissioning. So majority of the deliveries will be completed in Q2. And after that, it is the client's work in terms of completing civils, giving us funds for supervising. So that is a small part, but large part of the revenues on these projects will be done by Q2.

  11. Question

    Kaushik Poddar: No, but you also said that you are trying to build up some tie up with some other biggies in this field or something, if I heard you correctly.

    Answer, rajiv mittal

    Rajiv Mittal: Maybe couple of INR100 crores. We don't have a huge debt. We have told you before. We don't have and our intention is not to have any long term debt. If there's some debt, it's just to cover some mismatch in cash flow. So we don't have a very high debt. Manish: And working capital also quite smooth, right?

  12. Question

    Dhimant Shah: Super. And in terms of the next two to three years in particular, because that would also mean that you achieve closer to your stated goal of 15% to 16% EBITDA margin sustainable with certain top line growth trajectory. Now, if one scans the opp ortunity size. Do you think the Middle East geography, the Indian geography or the rest of the world offers you a better landscape as far as this. So how would you spread , because you have limited man material resources to address the total size that you can handle with them. So how would you go about allocating your resources?

    Answer, rajiv mittal

    Rajiv Mittal: See, we have no target geography wise. We have given you the 15% to 20% top line growth we are looking at. 13% to 15% EBITDA we are looking at. And for next year, we a re looking at INR15,000 to INR16,000 crores of order book. And just now we said that INR6000 crores we already are preferred bidder. So these are the statements which should give enough confidence to investors like you that what we commit, we will deliver. And that's the reason we continuously give you an update on quarter -on-quarter at least, so that you can also monitor our progress compared to the guidance we have given.

  13. Question

    Dhimant Shah: But despite that, certain geographies, like last time you had mentione d. That the Middle East gives you a better flavour as far as the O&M goals as a part of the overall mix. So you could be tilting towards that side. So any colour on that, if you can.

    Answer, rajiv mittal

    Rajiv Mittal: See, that is, again, one of the stated goals, Dhimant. We w ant to be, at least 50% International of our total revenue. Which I think we are very confident we'll be better than that. We will be more and with the markets opening up, an ease of business for us where we meet all the pre- qualification, client likes our company. We think we have a great opportunity internationally also in addition to India. In those times, we'll have to judge which one gives a better revenue, better profitability, better cash flow, lower risk. Those are the projects we are going to choos e and bid for it and win those projects.

  14. Question

    Dhimant Shah: Perfect. So now, last question, if you just see Desal, ETP and STP as separate buckets. In the ensuing future, would you want to kind of spell out where the size of opportunity is bigger for you?

    Answer, rajiv mittal

    Rajiv Mittal: For us it's very clear Dhimant. We are into advanced technology. We have more than 125 IP rights, trademarks. So naturally our tilt will be more which are technologically challenging projects. And our technology challenging projects are more going into desal and water reuse. Or we call it manufactured water. Naturally, our tilt, being a technology company, will be more towards desal and water reuse.

  15. Question

    Khushbu Gandhi: Yes. Thank you, sir, for giving me the opportunity. Just one question from my side. Basically now, since we are focusing more on the European side of the projects and MEA side of countries. So are we looking over there more of EP and O&M side, are we focusing that going forward our EP, which is a ratio of one-third of EPC, would be increasing to half of EPC in next two to three years?

    Answer, skandaprasad s

    Skandaprasad S: See Khushbu, just to clarify. We are not focusing on the Europe geography; we have defocused today close to zero is our European exposure. So just to clarify, our focus will remain on our core markets, emerging economies, India, Middle East, Africa, Southeast Asia and CIS countries. That is where we will stay focused. Yes, you are right. When we go internationally, there is an opportunity to have EP projects more, but that will not be the only focus of determining whether or not to take a project. While we will be happy to take out the construction portion, if the rest of the parameters are met an EPC project is also something that we will do.

  16. Question

    Suyash Bhave: Okay, sir, I understand that for warranty, for the liquidated damages also, would it be a similar case.

    Answer, skandaprasad s

    Skandaprasad S: See, LDs are specific project cases. And when we say LD, this is typically debits from the customer, that would come. So in case there are costs which are incurred and debited to us. There may be short certification of invoices towards the end o f closure of the project. From an accounting perspective, it is booked there, but it is typically not, let's say, a failure from our side, so it should not be seen that way. Take that as part of overall direct cost. And we have taken all of this into consideration when we have guided our 13% to 15% margin range.

  17. Question

    Suyash Bhave: Okay, sir. Thank you. That makes it clear. Thank you.

    Answer, rajiv mittal

    Semiconductor is little faster because there are a lot of manufacturing investment happening. So one can expect that end of this year, early next year, you can see something coming from semiconductor. But hydrogen is sti ll in the development phase. Still, it is not commercially viable. So any investment is happening, the governments are investing just to meet their carbon reduction numbers they have agreed globally. But we feel that with lot of investment going into this hydrogen manufacturing of electrodes, maybe in a year, year and a half, it will become more economically viable. And that time we will see more orders coming in.

  18. Question

    Sriharsha KJ: First of all, thank you for giving me an opportunity. And congratulations on reporting a good set of numbers. So my first question is with regard to the Arbitration Award that was granted for one project. Has that money been received by the company?

    Answer, rajiv mittal

    Rajiv Mittal: Not yet. An Indian system is little slow. Arbi tration award came in. The opponent has their certain objection to the award, which is getting cleared up. We have to see how legal system, how quickly they can clear up. But once it is cleared up, we will receive our money. So it is still under removing the objection raised by the losing party.

  19. Question

    Sriharsha KJ: Okay. Sir, I have another question. With regard to the sale of the VA Tech Wabag Romanian company. You have also received a dividend of EUR 8.46 million being accumulated, the net worth of the subsidiary company. So you said that the total inflow from the sale of the subsidiary come to a total of EUR15.66 million being the total of the dividend and the proceeds of the sale? VA Tech Wabag Limited August 09, 2024 Page 18 of 19 Skandaprasad S: See Mr. Sriharsha, about EUR8.5 million we have received as dividend from the Romanian subsidiary to its parent, VA Tech Wabag Austria.

    Answer, skandaprasad s

    And over and above that, we've also received a EUR1.2 million, which is a sale consideration. So both of these are the result of the divestment that we have done. You are right.

  20. Question

    Siddharth Purohit: Yes.

    Answer, skandaprasad s

    Skandaprasad S: See. We will largely be around 25%. Even internationally, the tax rates are kind of converging to this level. Between India and the rest of the world, if you take Saudi Arabia, if you take African countries, where we may do through branches or subsidiaries. I think about 25% would be the broad MMR. Siddharth Purohit: Okay, sir. That's all from my side.

Questions about this call

When was the VA Tech Wabag Q1 FY25 earnings call transcript filed?
VA Tech Wabag filed the transcript with the exchange on 16 Aug 2024. This page is built from that transcript.
What does this page list?
18 statements from the transcript across 7 topics, 7 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 30 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
VA Tech Wabag Q1 FY25 concall: VA Tech Wabag expects EBITDA margins to remain in the 13% to 15% band, with movement between quarters and years depending on the mix of projects · DalalOS