Capacit'e Infraprojects Q1 FY25 earnings call: Capacit'e Infraprojects Limited's standalone order book as on 30th June 24 was INR8,828 crores
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Standalone order book as on 30th June 24 was INR8,828 crores. The company hopes to achieve an order intake target of INR3,000 crores in the current fiscal, if not more. MHADA made an additional INR1,000 crores of work front available for Capacit'e Infraprojects Limited's BDD project. The company reduced its net working capital cycle by 17 days in Q1 FY '25 over Q4 FY '24. Total additions were about INR28 crores in Q1 FY '25, including the purchase of an office at Shrikant Chambers 5th floor.
The numbers management gave
Results
- Revenue from operations in Q1 FY '25 was INR570 crores, up 32% compared with INR430 crores in Q1 FY '24, despite labour migration during elections.
Show source
Revenue from operations for Q1 FY '25 stood at INR570 crores, up by 32% as compared to INR430 crores in Q1 FY '24.
- EBITDA in Q1 FY '25 was INR116 crores, up 54% compared with INR76 crores in Q1 FY '24.
Show source
EBITDA for Q1 FY '25 stood at INR116 cror es, up by 54% as compared to INR76 crores in Q1 FY '24.
- The company executed approximately INR134 crores of work on MHADA in Q1, comprising INR100 crores of certified sales and INR34 crores of ARPU sales approval.
Show source
The company has executed in Q1 approximately INR134 crores of work.
- The company completed certified sales in excess of INR64 crores on CIDCO.
Show source
Similarly, on CIDCO front, the company has done certified sales in excess of INR64 crores.
- The company is billing INR20 crores per month at JJ Hospital.
Show source
JJ Hospital, we are billing INR20 crores per month.
- The company reduced its net working capital cycle by 17 days in Q1 FY '25 over Q4 FY '24. Replaced by a later filing.
Show 5 more statements
Money and capital
- The company expects INR60 crores to INR70 crores of cash flows from disposal of real estate assets during the remainder of the current financial year.
Show source
And we do expect about INR60 crores to INR70 crores o f cash flows coming in from there in the remainder of the current financial year.
- The company has INR250 crores of pre limits available, which it considers sufficient to take care of the next quarters.
Show source
Rohit Katyal: So we are already armed with pre limits of INR250 c rores available with us, okay?
- The company believes there will be overall availability of INR350 crores of bank guarantee limits, excluding CIDCO and MHADA, to expand its order profile and issue retention guarantees.
Show source
So we do believe that there will be overall availability of INR350 crores of bank guarantee lim its excluding CIDCO and MHADA for the company to expand its order profile and also to iss ue for retention guarantees.
- Total additions were about INR28 crores in Q1 FY '25, including the purchase of an office at Shrikant Chambers 5th floor.
Show source
The overall, the total additions to our -- was about INR28 crores in Q1, a ll right?
- The company expects to restrict total additions to about INR65 crores for the full financial year.
Show source
And we do expect to restrict this figure to about INR65 crores for the full financial year.
What it expects ahead
What management expects
- The company hopes to achieve an order intake target of INR3,000 crores in the current fiscal, if not more.
Show source
But we are back to bidding, and we do hope to achieve the target of INR3,000 crores in the current fiscal, if not more.
- The INR3,000 crores order intake target excludes work fronts opened for the BDD project of MHADA that will be added to the order book.
Show source
This INR3,000 crores is excluding the fronts open up from BDD project of MHADA and get added into the order book.
- The company expects a tax rate of 25% plus surcharge for the full year; deferred tax reversals would make the tax rate appear lower, and without reversals it would appear a little higher.
Show source
We are at 25% plus surcharge and that would be the tax rate applicable for the f ull year.
- The company believes it can reduce its net working capital cycle by a further 20 days till 31st March 2025, for an overall reduction of 37 days in the current financial year.
Show source
Now that means an overall reduction of 37 day s is what we are committed to do in the current financial year and go on improving over the next fiscal as well.
- The company believes retention and final bill payments for projects handed over and delivered will come through in quarter 2 and more so in quarter 3.
Show source
All the projects which have been handed over deliv ered, we do believe that the retention and the final bill payments will come through in quarter 2 and more so in quarter 3.
- The company expects CIDCO work to be close to INR100 crores in the current quarter and in excess of INR150 crores from next quarter onwards, further improving in quarter 4.
Show source
And we believe that in the current quarter, we sho uld be close to about INR100 crores in CIDCO.
Show 19 more statements
What management expects
- The company expects the sales tower value of each MHADA tower to be in excess of INR650 crores, starting from December onwards.
Show source
Now in MHADA project, we expect the sales tower value of each being in excess of INR650 crores, starting from December onwards.
- The company expects to build a minimum INR140 crores plus price variation in MHADA starting from December, January onwards.
Show source
So you will see that there will be an expansion and we will be in a position to build a minimum INR140 crores plus price variation starting from December, January onwards in MHADA as well.
- The company expects that 25 projects each generating in excess of INR10 crores of revenue would enable it to reach INR3,000 crores or INR3,500 crores.
Show source
So my philosophy, which we talk about earlier also Parvez, that if we have 25 projects and each project can give us excess of INR10 crores revenue, that is how we are going to do to INR3,000 crores or we are going to do INR3,500 crores.
- Historic guidance has been 11% to 12% of EBIT and PAT level of 5.5%; increased revenues are reflecting expansion in margins, which the company expects to continue for the whole year, especially in quarter 3 and quarter 4.
Show source
Now the point is our historic guidance has been at 11% to 12% of EBIT and PAT level of 5.5%, but increase in revenues are reflecting the expansion in the margins, and we do expect that to continue for the whole year, especially in quarter 3 and quarter 4.
- The company expects its whole-year guidance to be in line with what it has seen in Q1 FY '25.
Show source
But yes, we do expect the whole year guidance to be in line with what you have seen in quarter 1.
- The company has said it will grow by 25% CAGR from '23-'24 onwards for the next 4 years; 1 year has gone.
Show source
And while the guidance has not been given, we have already said that we will grow by 25% CAGR from '23-'24 onwards for the next 4 years.
- The company guided for fresh order book of INR3,000 crores apart from the MHADA project in the current financial year.
Show source
And therefore, the guidance of fresh order book at INR3,000 crores apart from MHADA project in the current financial year.
- The company does not see labor as a challenge for the current part of the remaining fiscal.
Show source
So for the current part of the remaining fiscal, I do not see that as a challenge for us.
- The company will work for private-sector clients that are agreeable to award work at its margin profile.
Show source
So the point is that whichever clients in the private sector are agreeable to award work at our margin profile, we will definitely do work for them.
Orders
- Standalone order book as on 30th June 24 was INR8,828 crores.
Show source
Our order book on a standalo ne basis as on 30th June 24, stood at INR8,828 crores.
- The sealed towers were released for Capacit'e Infraprojects Limited's BDD project, adding close to INR1,000 crores of executable order book.
Show source
Apart from th at, I also gave, during my opening remarks, that BDD project, earlier where we had received the 11 towers for rehab portion, the sealed towers also have been released, thereby adding clos e to INR1,000 crores of executable order book.
- INR1,200 crores of Capacit'e Infraprojects Limited's BDD scope was included in the order book before the additional INR1,000 crores was added.
Show source
So far, only INR1,200 crores was included in the o rder book.
- The company still has to realize close to INR3,300 to INR3,400 crores of executable order book from BDD in quarters going forward.
Show source
So, you h ave to remember that in quarters going forward, we still have to realize executable order book of close to INR3,300 to INR3,400 crores from BDD.
- The entire Thane project current order book profile is more than INR1,500 crores, of which INR700 crores has been executed.
Show source
The entire Thane project current order book profile is more than INR1,500 crores.
- The company has already got 2 orders, one in consortium with Tata Projects of INR11,700 crores and one for INR4,200 crores.
Show source
Rohit Katyal: So we have already got 2 orders, one in consortium with Tata projects of INR11,700 crores and one is for INR4,200 crores.
- Order-book conversion ratio would range between 18% to 25% in government and private sector.
Show source
Rohit Katyal: So I just mentioned the conversion ratio would rang e between 18% to 25% in government and private sector, you see it's more on invitation bas is.
- The company said there is enough opportunity for projects of INR2,000 crores month-on-month in the government sector.
Show source
And in the government side, I told you there is enough opp ortunity for projects of INR2,000 crores month-on-month basis.
- Public sector accounts for 72% and private sector for 28% of Capacit'e Infraprojects Limited's total order book.
Show source
Public sector accounts for 72% while private sector accounts for 28% of the total order book.
- The company received its fourth repeat order from Lodha for an upscale residential project in Worli in the first quarter, and work and billing have started.
Show source
In the first quarter, as I told you, we have received the fourth repeat order from Lodha for the upscale residential project in Worli.
What it is building and selling
Projects and capacity
- MHADA made an additional INR1,000 crores of work front available for Capacit'e Infraprojects Limited's BDD project.
Show source
Further, the work front for additional INR1,000 crores has been made available by MHADA for our BDD project.
- Nearly INR3,500 crores is yet to get added on the MHADA project, which is already under Capacit'e Infraprojects Limited's credit and is its scope of work.
Show source
You are aware that our scope in BDD, including escalation, is close to INR5,500 crores or thereabouts.
- The company had INR1,200 crores plus to a INR1,400 crores of order front available on MHADA.
Show source
So Parvez on MHADA front, we earlier had INR1,200 crores plus to a INR1,400 crores of order front available.
- The company had close to INR2,400 crores of land available for execution of the CIDCO project.
Show source
We ha ve close to INR2,400 crores of land available to execute the project for execution.
- The third tower of Mahalaxmi's most premium flagship project is under execution and nearing completion.
Show source
Mahalaxmi most prem ium flagship project, the third tower is under execution and nearing completion.
Deals and partners
- Lodha has been Capacit'e Infraprojects Limited's client from 2012 onwards since the company was incorporated; the company has executed and delivered 3 projects for Lodha, including Trump Tower, and the Worli project is the fourth repeat order project.
Show source
We have executed 3 projects and delivered, including the Trump Tower, and the Worli project is a high premium project, which is the fourth repeat order project.
Show 4 more statements
Deals and partners
- M3M is a new client for Capacit'e Infraprojects Limited, and the company is executing a project of INR550 crores or thereabouts in Noida for M3M.
Show source
The company is executing a project of INR550 crore s or thereabouts in Noida for them.
- The company has delivered 3 projects for Oberoi and is in line to deliver the fourth project, OGC Tower 1 and 2, by this March 25.
Show source
We are i n line to deliver the fourth project that is Capacit'e Infraprojects Limited August 16, 2024 Page 10 of 16 OGC Tower 1 and 2 by this March 25.
- The company is executing projects for DLF in Goa and has completed 2 towers for Piramal.
Show source
We are executing projects for DLF in Goa, we have completed 2 towers for Piramal.
- Raymond and M3M have not taken performance guarantees or advance guarantees from Capacit'e Infraprojects Limited.
Show source
Number two, you're aware that plants like Raymond a nd M3M have not taken any guarantees from us, neither performance guarantee, neither adv ance guarantees.
Everything else said on the call
Other
- The company is 90% manned across projects, meaning labor force, and its labor payment terms have improved from monthly (earlier a month) to every 15 day cycle, a 15-day good payment cycle, helping it retain more workforce, which resulted in some increase.
Show source
And I' d like to speak to you today, we are in 90% manned across projects, manned as the sense, the la bor force.
- The company improved labor-force payment terms from earlier a month to a 15-day good payment cycle, which resulted in some increase. Replaced by a later filing.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Mohit Kumar: Yes, understood. My second question is on the order inflow outlook, how do you think about how it has panned out in Q1? How do you think it's looking like in the balance of fiscal -- are you seeing the increasing momentum post the election more inquiry?
Answer, rohit katyal
Rohit Katyal: The big pipeline is strong across both public secto r and private sector. Of course, there were central government elections. And then as per the C VC guidelines, you do have a blackout period. But we are back to bidding, and we do hope to achieve the target of INR3,000 crores in the current fiscal, if not more. This INR3,000 crores is excluding the fronts open up from BDD project of MHADA and get added into the order book. I just mentioned in my opening remarks, that another INR1,000 crores has opened up. So effe ctively the order book should be read as INR8,800 plus, plus INR1,000 crores.
Question
My next question would be on the EBIT margins that we would be seeing for this year. How are you seeing those EBITDA margins for this year?
Answer, rohit katyal
Rohit Katyal: So, Darshil we have commented in the last financial year that once our order execution speed improves beyond INR550 crores, you will see an expansion in the margins. That's what you are actually witnessing now because there is a reduction as a percentage to turnover in the fixed cost of the company. So there is no reason why these margins plus or minus 1% should be achievable for the full year, if not better Darshil Pandya: Got it.
Question
And, sir, last call we discussed about thi s Gift City project. I would like to hear more on that from your side.
Answer, rohit katyal
Rohit Katyal: Gift City project is in full flow. We expect to com plete that by January of current financial year. We continue to bid. As we speak, we are bidding for certain more projects in Gift City area because the client and the other private sector cli ents over there find our quality far superior to what they have seen. So, yes, we do believe that Gift City will offer opportunity in the quarters to come and wherever our pricing need not be compro mised, we will be very happy to execute projects over there for both Gift and for private sector.
Question
Mukul Verma: Yes, thank you so much for the opportunity. Rohit ji, congratulations on a fantastic quarter. I have two questions. One is, are we looking to expan d to new geographies, specifically Andhra Pradesh, considering Central Government allocation t o the state for development of infrastructure? And second question is, what is the tax rate that we kind of will be put into for this year? Because I see last year we have seen a higher tax rate. These are the two questions.
Answer, rohit katyal
Rohit Katyal: Yes. So, good morning, Mukul. Let me take your tax rate question. We are at 25% plus surcharge and that would be the tax rate applicable for the f ull year. If there are reversals in deferred tax, the tax rate would appear to be that much lower and when the reversals don't come, then the tax rate would look that much little bit higher for the full year. However, at the moment, answering your question, it is 25% plus surcharge. So, your second question was?
Answer, rohit katyal
Geographical expansi on. Now, you are aware that prior to COVID, the company was present in seven cities. Now, that seven cities basically entail about 10 to 11 states for other contractors. But we are a pure urban player working in tier one cities. So, the company has enough experience of having executed projects and delivered on time with high credit quality across Chennai, Hyderabad, Bangalore, Pune, Mumbai, Goa. We have delivered more than six or seven projects in Delhi NCR and of course Mumbai MMR. So, as I speak to you today, we are already there in Mumbai.
Answer, rohit katyal
We are in Mumbai MMR. We are there already in Gujarat, Ahmedabad, Gandhinagar. W e are there in Delhi NCR, both in the private and public space. Capacit'e Infraprojects Limited August 16, 2024 Page 5 of 16 And at the moment, we are actively bidding for cer tain public sector projects like AIIMS and so on in Bangalore, Hyderabad, and for CPWD projects, apart from active bidding, which is going on in Maharashtra. So, yes, there will be an expans ion in the geographies. But that will, for at least the current financial year, be limited to wha t geographies we were servicing prior to COVID. Mukul Verma: Great.
Answer, rohit katyal
So, just to follow on. So, what is the kind of, last time I remember, you had mentioned that you take order book of close to INR3,000 crore s for this year. So, what is it that we have kind of got it in the first quarter? And is there anything to be announced in due course of time?
Answer, rohit katyal
Rohit Katyal: So, whatever has to be announced will be announced in quarter two and as we move forward. In the first quarter, as I told you, we have received the fourth repeat order from Lodha for the upscale residential project in Worli. The work has already started. The billing has started, number one. Apart from th at, I also gave, during my opening remarks, that BDD project, earlier where we had received the 11 towers for rehab portion, the sealed towers also have been released, thereby adding clos e to INR1,000 crores of executable order book. You are aware that our scope in BDD, including escalation, is close to INR5,500 crores or thereabouts. So far, only INR1,200 crores was included in the o rder book.
Answer, rohit katyal
Now, that inclusion includes another additional INR1,000 crores, taking the tota l order book of BDD to INR2,200 crores or thereabouts in our executable order book. So, you h ave to remember that in quarters going forward, we still have to realize executable order book of close to INR3,300 to INR3,400 crores from BDD. Apart from the new orders which we take. So, our g uideline is for new order intake of INR3,000 crores in the current financial year and I don't see any reason why we shouldn't achieve that.
Question
Mukul Verma: Superb, sir. Congratulations and I will join back in a queue. Thank you.
Answer, rohit katyal
Rohit Katyal: Correct. The only correction is MHADA will not happ en. It has already happened. Rikin: Okay. So, INR 1,000 crore has already happened and we are looking at a total INR 3,000 crores additional order inflow that we expect during the year. And in terms of mixed basis, the current bidding that you have, do you see a similar public versus private inflow in this INR3,000 crores? Capacit'e Infraprojects Limited August 16, 2024 Page 6 of 16 Rohit Katyal: Rikin, please try to understand.
Answer, rohit katyal
This is a very dyn amic thing. We continue to bid for good clients both in private and government sector. And a win of private sector, let's say, you will end up getting an order of INR500 crores, let's say, next month. Then suddenly that percentage will change. But ideally, we would like to maintain that somewhere between 70-75 to 25-30 levels. Simply because all the government projects now hav e become EPC. That gives us an opportunity to exercise our engineering expertise and therefore improve upon the margins.
Answer, rohit katyal
As far as the private sector is concerned, yes, we are working fo r all the top 15 developers across the geographies where we are present. So, if you talk a bout Delhi, Godrej, M3M, DLF are our existing clients. If you talk about Mumbai, you think about a good name and they are there with us as our clients. And the positive part is that we have delivered to each of these clients. It's not that the delivery will happen in future. And most of these clients, basically, we will end up getting repeat orders. Similarly, though we do n ot look at Bangalore from the private sector perspective, we, as I mentioned, we will be bidding for certain central government funded projects in Bangalore and going forward in Andhra as well.
Answer, rohit katyal
So, I do believe that there is a serious momentum just on the horizon. And I think we are not anything more than two or three months away from th ere. Where at least you would have an opportunity to choose and bid for more than INR2,000 crores per month. So, yes, answering that, this is the strategy and this is what will translate into order book of INR3,000 crores apart from MHADA. Out of this INR3,000 crores, INR250 crores from Lodha has already happened. But then, as seen in the past , the company has always surpassed its projections as far as order inflows are concerned. The only thing which the company would like to ens ure is that there is no need to go and bang our head and reduce our overall profitability in a bid to just win orders.
Answer, rohit katyal
So, this is what the strategy of the company has been. I have been repeating this for the last eight quarters. And the company is now showing results from quarter four of last financial year and has continued that momentum in the first quarter of the current financ ial year and which is expected to grow and improve upon. Rikin: So, just one follow-up on the order inflow. So, gi ven that the largest state is Maharashtra where you would see a state election, would there be any impact or slowdown you envisage for the order inflow, particularly from the public sector for that period or you don't envisage that taking place?
Answer, rohit katyal
Rohit Katyal: So yes, there will be no bidding 40 days prior to t he election dates and I do not know what election dates whether they have been announced or not. So you will have a 60-day lull in the public sector in Maharashtra. However, whatever bid s have been submitted I expect that they should materialize either way before the code of conduct is put in place. However, that is only for Maharashtra, Central PWD, Andhra Pradesh, public sector health care projects in Karnataka and the other geographies whe re we are operating, that will continue unhindered. We have to appreciate that the central government came only 60 days back. So you Capacit'e Infraprojects Limited August 16, 2024 Page 7 of 16 will see a lot of traction in the central PSUs and central government projects in the months coming going ahead. Rikin: Got it, sir.
Answer, rohit katyal
Sir, one question on the working capital front. So you did outline in the presentation the improvement that you achieved in the current qu arter. If you could outline what have been the areas that have driven this improvement and your guidance for the full year in terms of how working capital could shape up for us?
Answer, rohit katyal
Rohit Katyal: So firstly, we have collected more than INR100 crores of retention over the last 9 to 10 months period due to ample availability of bank guarantee limits. Now the company already also has access to surety bonds which all central PSUs expect in lieu of to bank guarantees. That's number one. Number two, the company has increased its revenues while maintaining the debtor levels. Which means that the number of days with respect to revenue is concerned has reduced as a percentage to the top line. Going forward, we see this trend to further strengthen. And thirdly, our old stuck monies like IGMS 50% of that has already been reali zed in the quarter 1, we believe that the balance 50% will get realized in the quarter 2.
Answer, rohit katyal
All the projects which have been handed over deliv ered, we do believe that the retention and the final bill payments will come through in quarter 2 and more so in quarter 3. And therefore, all these things are huge positive for the company. Lastly, whatever ECL and bad debts the company had taken over the last 3 years, the company is in a possession of real estate and it has given to a professional firm for disposal of these real estate assets. And we do expect about INR60 crores to INR70 crores o f cash flows coming in from there in the remainder of the current financial year. So all these put together whatever 17 days reduction you have seen that the past, I do believe that ther e are more scope for 20 days till 31st March 2025. Now that means an overall reduction of 37 day s is what we are committed to do in the current financial year and go on improving over the next fiscal as well. Rikin: Understood.
Question
Vikash Agarwal: Hi, thank you for taking my question and congratulations Mr. Katyal on a great set of numbers. And my question is as you know other questions have already been answered related to order book. And current question is related to our credit rating. So where we are now today in terms of getting that upgrade?
Answer, rohit katyal
Rohit Katyal: You'll see that we will be distributing our quarter 1 numbers along with reduction in working capital cycle and whatever bank sanction have done. At the moment, the company is totally focused on ramping up its execution to achieve the targets or surpassing those targets. So I do believe that rating will happen in due course. Howe ver, the bank limits are in place. The Capacit'e Infraprojects Limited August 16, 2024 Page 8 of 16 company is doing exceedingly well as far as the execution front is concerned. So I wouldn't like to put a time of 15-days or 20-days, but it will happen sooner than later.
Question
Parvez Qazi: So just wanted to get an update on the two big proj ects that you are doing in MHADA and CIDCO. You already said that in MHADA you'd issue som e additional work front. So for the balance, INR3,000-odd crores when do we expect that to become available to us. And also what is the kind of revenue, let's say which we did on t he MHADA project in Q1? And something similar status update about the CIDCO, what is the w ork unavailable and what is the kind of execution that you have done in Q1? And what is our expectation for FY '25?
Answer, rohit katyal
Rohit Katyal: Yes. So Parvez on MHADA front, we earlier had INR1,200 crores plus to a INR1,400 crores of order front available. The company has executed in Q1 approximately INR134 crores of work. Out of this INR100 crores is certified sales and INR34 crores is ARPU sales approval. Similarly, on CIDCO front, the company has done certified sales in excess of INR64 crores. We believe that the momentum of CIDCO will be exponential. We ha ve close to INR2,400 crores of land available to execute the project for execution.
Answer, rohit katyal
And we believe that in the current quarter, we sho uld be close to about INR100 crores in CIDCO. And from next quarter onwards, we should be in exce ss of INR150 crores in CIDCO alone, further improving in quarter 4. Now in MHADA project, we expect the sales tower value of each being in excess of INR650 crores, starting from December onwards. Once this -- and we already have received the land availability. So the piling will start. These are heavy piles. These are buildings in excess of 300 meters require serious preparatory work which have started and we should start the work by December.
Answer, rohit katyal
So you will see that there will be an expansion and we will be in a position to build a minimum INR140 crores plus price variation starting from December, January onwards in MHADA as well. But the traction is not only in these 2 projects, P arvez across our Bhandup Hospital project has seen serious traction. JJ Hospital, we are billing INR20 crores per month. So my philosophy, which we talk about earlier also Parvez, that if we have 25 projects and each project can give us excess of INR10 crores revenue, that is how we are going to do to INR3,000 crores or we are going to do INR3,500 crores. That is simply panning out now and that is what we're seeing in the execution happening.
Question
Parvez Qazi: Sure. Thanks and all the best.
Answer, rohit katyal
Rohit Katyal: Could you repeat the last part of your question, how does their profitability? Rolita: Yes -- compared to clients, like you said, you have repeat customers of Raymond, Godrej, Lodha. How does their profitability compare with each other through the projects?
Answer, rohit katyal
Rohit Katyal: So Ronita I will not be able to compare clients, my clients. I don't want to upset either any of them. We own them in high esteem, and it would not be appropriate for me to comment on their profitability. If you are talking about our profitability with respective clients, again that is ... Rolita: Yes. I'm talking about your profitability.
Answer, rohit katyal
Rohit Katyal: So that is business, madam. We cannot say the diffe rent ranges of profitability we charge from each client. In the private sector, it's more on in vitation basis and repeat order means the client is happy, willing us to pay a little bit extra for getting that performance and the quality which they are now used to from Capacite. Public sector, o bviously, as I mentioned, now the whole thing is EPC. So therefore you see bigger players competing in the space where the project sizes are INR500 crores and more. We continue to be one of them. And if you look at pan-India level in building sect or which includes hospitality, includes healthcare, includes infrastructure like stadiums, so on and so forth or super High-rise buildings from government as well.
Answer, rohit katyal
We are one of the prominent players and being EPC c ompany and competing with likes of L&T, Shapoorji, Ahluwalia. I believe that all these are mature companies. And it is not a competition which you would see in other infra segments. So it is more mature competition and thereby, which is getting reflected in the profit statements coming quarter-on-quarter basis. But if you ask me to define the profitability on the private s ector client wise, I'm sorry that will not be possible. Rolita: No worries. I would like to know who are your top c lients in the private sector and their percentage contribution to revenue?
Answer, rohit katyal
Rohit Katyal: So the top clients at the moment from an order book perspective, would start with Raymond. The entire Thane project current order book profile is more than INR1,500 crores. Of this INR700 crores has been executed. That is followed b y Godrej followed by SBUT, Saifee Burhani trust. And all these are repeat clients that has to be remembered. Apart from this, Lodha is our client from 2012 onwards since the company w as incorporated. We have executed 3 projects and delivered, including the Trump Tower, and the Worli project is a high premium project, which is the fourth repeat order project.
Answer, rohit katyal
Similarly, from growth rate, this is a fourth project. M3M is a new client for the company. The company is executing a project of INR550 crore s or thereabouts in Noida for them. So many more Oberoi, we have delivered 3 projects. We are i n line to deliver the fourth project that is Capacit'e Infraprojects Limited August 16, 2024 Page 10 of 16 OGC Tower 1 and 2 by this March 25. We are executing projects for DLF in Goa, we have completed 2 towers for Piramal. Mahalaxmi most prem ium flagship project, the third tower is under execution and nearing completion.
Answer, rohit katyal
Apart from this Prestige, we have Mr. Atul Ruia Gro up, Phoenix Mill, Phoenix Market City, Raheja as our clients, and we continue to bid for th eir new projects. So it's an ongoing process, but I must have taken names of the most reputed cli ent developers in the country. On the government side, we are working for MHADA, CIDCO the futuristic body and MCGM. We are working for a department of telecommunications thro ugh an escrow mechanism with BSNL. We are working with PWD. And this list will increas e. We have added IOCL as our esteem client and of course, Gift City. So a long list of c lients, which is only going to increase and improve further.
Answer, rohit katyal
Rohit Katyal: You have seen the margins pan out in quarter 3 and quarter 4, isn't that sufficient sir to give you a guidance for the year. Now the point is our historic guidance has been at 11% to 12% of EBIT and PAT level of 5.5%, but increase in revenues are reflecting the expansion in the margins, and we do expect that to continue for the whole year, especially in quarter 3 and quarter 4. You have to remember that quarter 2, is always marked with m onsoon stoppages. But yes, we do expect the whole year guidance to be in line with what you have seen in quarter 1.
Answer, rohit katyal
Rohit Katyal: There are two things Anupam. One thing, as I told you, there has been an expansion in revenues, expansion in revenues, anything beyond the INR550 crores. Obviously, reducing the fixed cost of the company, whether it is finance cost, whether it's staffing cost, whether it is all the indirect expenses as the company incurs. So one of the reason is that there is an expansion impact. Secondly, you will see that the cost of consumptio n of material and construction services has also following in proportion as a percentage of the top line. This is a simple reason that more revenue from the EPC project is coming into play no w. And I have always maintained that as and when this happens, you will see an expansion in margins. So even for the remainder of the current financial year, you will see serious revenu es, higher revenues coming from these EPC projects, whether it is CIDCO, MHADA whether it's MCGM hospitals, or PWD hospital.
Answer, rohit katyal
So we do see a significant improvement, which has already got reflected in quarter 4 of the last fiscal and quarter 1 of the current fiscal to continue. Capacit'e Infraprojects Limited August 16, 2024 Page 11 of 16 Now yes, there may be a certain blip in the quarte r 2 because of monsoons that cannot be ruled out. But as I told you, it will pan out, if not better, because you will see and let us put it this way, that the investors at large will be positively surprised by our growth in quarter 3 and quarter 4.
Question
Anupam Gupta: Okay. Second question is in terms of order inflows. So incrementally, what is the target and within the target, what is, let's say, how much of government orders will you want to take given that those are pretty good quality orders at least, which we are seeing right now. So what is the view there?
Answer, rohit katyal
Rohit Katyal: The private sector will be and is always on invitation. So we will pick and choose which do not negatively impact our overall EBITDA or PAT projecti ons for the year and the next 3 years. That's number one. Number two, as far as the government sector is con cerned, we will continue to work with quality of the clients like we are working for today. We ar e very eager to add CPWD and we are very eager to add those projects which the central government has funded, whether it is through PSUs or for that matter, projects, which may come up in the state of Bihar all state of Andhra Pradesh, which will be funded by JICA, guarantee for which h as been taken by the central government. JICA or ADB. So these are the projects which we would like to participate in.
Question
Anupam Gupta: Okay. Third question is, pardon me, I wasn't there in the first part of the call, but what is your guidance for revenues for '25 and '26?
Answer, rohit katyal
Rohit Katyal: So '25, we have already given a guidance of 25%. Fi rst quarter has happened and has panned out quite well. We see that, this will continue for the remaining of the financial year. So 25% minimum improvement year-on-year is given. I don't see any reason why we shouldn't exceed that substantially. And while the guidance has not been given, we have already said that we will grow by 25% CAGR from '23-'24 onwards for the next 4 years. So 1 year has gone.
Show 5 more questions
Question
Anupam Gupta: Okay. Do you see any risk to this, especially from labor because multiple avenues have highlighted labor being a very big constraint for e xecution. Do you see that as a risk for you as well?
Answer, rohit katyal
Rohit Katyal: So we have addressed a certain part of that. And I' d like to speak to you today, we are in 90% manned across projects, manned as the sense, the la bor force. And because it's monsoons and elections -- central elections behind us, West Bengal elections is not coming up this year, Bihar elections happening next year. So for the current part of the remaining fiscal, I do not see that as a challenge for us. We have improved their payment terms from earlier monthly to every 15 day cycle. So that's helping us retain more and more workforce. That's part number one.
Question
Anupam Gupta: Okay. Understand.
Answer, rohit katyal
Rohit Katyal: So we have already got 2 orders, one in consortium with Tata projects of INR11,700 crores and one is for INR4,200 crores. So it will depend on project to project, state to state. The qualification criteria is set up as per the CVC guidelines by the consultants and the client. So we have very little role to play in that.
Answer, rohit katyal
Rohit Katyal: I clarified this last quarter also to you. That we will work with our margin profile. There is no need for the company to compromise on its margin pr ofile. Given our order book and also the fact that nearly INR3,500 crores is yet to get added on MHADA project, which is already under our credit and this 3,500 is our scope of work, isn 't it? So the point is that whichever clients in the private sector are agreeable to award work at our margin profile, we will definitely do work for them. Number two, you're aware that plants like Raymond a nd M3M have not taken any guarantees from us, neither performance guarantee, neither adv ance guarantees. So we would like to push for certain contracts like of this nature where the company's financial exposure is the least exposed, and we can do -- we can have a better marg in profile.
Question
And congratulations on a very good set of numbers, sir. Sir, I have two questions , sir. In the last quarter, you have mentioned that we have in fact INR250 crores of bank guarante e limits and incremental of INR107 crores of sanctions were there in place. So I just wanted to check with that, do we acquire external bank guarantee limits for the additional INR3,500 crores of orders, which we are bidding for this financial year. If you can give some guidance on that?
Answer, rohit katyal
Rohit Katyal: So we are already armed with pre limits of INR250 c rores available with us, okay? And that is good enough to take care of the next quarters. Further, you have to remember that bank guarantee were issued and they are received back also, okay? So we do believe that there will be overall availability of INR350 crores of bank guarantee lim its excluding CIDCO and MHADA for the company to expand its order profile and also to iss ue for retention guarantees. Because as you are aware on a quarterly basis, our bank guarantee limits come back also once the advance is recovered.
Question
Vishal Mehta: Okay. And one more question, sir. Suppose if you bi d for say X crores of order. So how much do we receive out of it I mean what is the conversion ratio of the order book?
Answer, rohit katyal
Rohit Katyal: So I just mentioned the conversion ratio would rang e between 18% to 25% in government and private sector, you see it's more on invitation bas is. So we continue to bid for private sector clients on case-to-case basis, which I've already e xpanded and elaborated a lot on that. And in the government side, I told you there is enough opp ortunity for projects of INR2,000 crores month-on-month basis. And therefore, the guidance of fresh order book at INR3,000 crores apart from MHADA project in the current financial year.
Question
Parvez Qazi: Just wanted to check what is the capex that we did in Q1? And what is the target for FY '25?
Answer, rohit katyal
Rohit Katyal: So the target, Parvez, we continue to be conservati ve on the capex. The overall, the total additions to our -- was about INR28 crores in Q1, a ll right? And we do expect to restrict this figure to about INR65 crores for the full financial year. So typically, what you want you to see till 2023, INR150 crores, INR120 crores, we have bought it down substantially less in last year. And that will continue in the current financial year as well. And I just wanted to clarify, I mean if he is ther e on the line. This INR28 crores includes the purchase of office for the company at Shrikant Chambers 5th floor.
Questions about this call
- When was the Capacit'e Infraprojects Q1 FY25 earnings call transcript filed?
- Capacit'e Infraprojects filed the transcript with the exchange on 20 Aug 2024. This page is built from that transcript.
- What does this page list?
- 48 statements from the transcript across 7 topics, 33 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 15 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.