Capacit’e Infraprojects Limited has so far been awarded projects worth Rs. 1,500 crores, excluding BDD addition of Rs. 858 crores during the current fiscal, and is confident of achieving and surpassing its guided order book addition for FY ‘25. Capacit’e Infraprojects Limited expects strong collections in quarter three, with Rs. 200-plus crores collected in October already, after some payments shifted into October because of the elections; it expects net working capital to reduce in quarter three, with further improvement in Quarter 4, and is committed to a 100-day level by the year end. CIDCO’s execution run rate was close to Rs. 50 crores for October, and Capacit’e Infraprojects Limited expects it to reach Rs. 65 crores by December and Rs. 75 crores by January per month. Capacit’e Infraprojects Limited’s write-offs predominantly included close to Rs. 80 crores, Rs. 90 crores for the Radius Group, which had joint ventures with Sumer and DB Reality. The average project size in Delhi NCR has increased from Rs. 250 crores, Rs. 300 crores to in excess of Rs. 800,000 crores.
The numbers management gave
Results
- Capacit’e Infraprojects Limited’s write-offs predominantly included close to Rs. 80 crores, Rs. 90 crores for the Radius Group, which had joint ventures with Sumer and DB Reality.
Show source
Rohit Katyal: So, the write offs predominantly, close to Rs. 80 crores, Rs. 90 crores were for the Radius Group.
- When the earlier order book was Rs. 9,000 crores, revenue was coming from only Rs. 3,500 crores or Rs. 4,000 crores of business.
Show source
So, though the order book was Rs. 9,000 crores, the revenue was coming from only Rs. 3,500 crores or Rs. 4,000 crores business.
- The Company’s employee cost increased by Rs. 7 crores over the last quarter, primarily due to increased employee strength, new joinees and increments.
Show source
Your second question was , the employee cost has increased by Rs. 7 crores over the last quarter.
- The Company’s WIP, including work done but not billed and bills submitted, was Rs. 889 crores against a top line of close to Rs. 450 crores last financial year; at a much higher top line, WIP is Rs. 900 crores.
Show source
Rohit Katyal: So, you please if you compare, the WIP was Rs. 889 crores, which is work done, not billed, bill submitted, all that put together, was Rs. 889 crores on our top line of close to Rs. 450 crores last financial year, that is Rs. 900 crores on a much higher top line .
- The Company’s uncertified bills remained at Rs. 434 crores despite an increase in the top line.
Show source
Number two, the uncertified bills continue to be at Rs. 434 crores, even though there has been an increase in the top line .
- MHADA is contributing nearly Rs. 18 crores or Rs. 20 crores per month to the Company.
Show source
Rohit Katyal: So, MHADA, at the moment we are doing about Rs. 20 crores per month, we will continue to do that in quarter three.
Show 16 more statements
Results
- CIDCO is contributing in excess of Rs. 45 crores to Rs. 50 crores a month to the Company.
Show source
You have CIDCO which is now contributing in excess of Rs. 45 crores to Rs. 50 crores a month.
- JV is contributing in excess of Rs. 10 crores a month to the Company.
Show source
You have J V which is contributing in excess of Rs. 10 crores a month.
- The company achieved 28% year-over-year revenue growth from operations during H1FY25, alongside improvement in margins.
Show source
Our Company has commenced the year on a positive note, achieving 28% year-on-year revenue growth from operations during H1 FY ‘25 along with significant improvement in margins .
- PAT for Q1 FY25 was ₹ 53 crores, up by 180% from ₹ 19 crores in Q1 FY24.
Show source
So, coming to the fact that it's not only the last financial year, but the Company has also followed an aggressive provisioning policy subsequent to the COVID year, and we have provided for more than Rs. 180 crores of expected credit losses.
- The Company’s growth over the last three and a half or four quarters was driven by the order book becoming operational and substantial revenue from the MHADA and CIDCO orders.
Show source
So, that explains the reason why the growth you have now happening over the last three and a half or four quarters, simply because the order book is operational, and the Company is driving substantial revenue from these two big ticket size orders .
- The Company’s contract assets have stagnated even though its top line has improved significantly.
Show source
However, if you see, that amount has now stagnated even though the top line has improved significantly.
Money and capital
- Capacit’e Infraprojects Limited’s retention amount on an absolute basis has reduced to Rs. 135 crores from Rs. 170 crores last financial year, despite an increased top line over the last one year.
Show source
The retention amount over the last one year on absolute basis on increased top line has reduced to Rs. 135 crores from Rs. 170 crores last financial year.
- Capacit’e Infraprojects Limited has more than Rs. 250 crores of unutilized bank guarantee limits and does not see an issue collecting retentions or advances, which it expects to happen substantially in the current quarter given new order wins and non-fund-based limits.
Show source
The Company is sitting on more than Rs. 250 crores of unutilized bank guarantee limits, and therefore we do not see any issue of collecting our retentions or advances, which will happen substantially in the current quarter given the new order wins due to non-fund availability of non-fund-based limits.
- Capacit’e Infraprojects Limited’s collection drive, including legal action at RERA, NCLT and High Court, has resulted in the Company holding assets with a market value in excess of Rs. 200 crores against total collections of about Rs. 115 crores.
Show source
Point number two, the Company’s aggressive collection drive, which is more of legal in nature at various forums whether its RERA, whether it is at NCLT or High Court, has ensured that the Company is today holding assets in excess of Rs. 200 crores market value as against a total collection of a collection of about Rs. 115 crores.
- The Company raised close to Rs. 350 crores through preferential, QIP and infusion by the promoters.
Show source
Subsequent to that, the Company raised close to Rs. 350 crores through preferential, QIP and infusion by the promoters.
- Rs. 200 crores stuck with the private sector caused the Company’s cash flow issues.
Show source
So, I believe that the cash flow issues which you are referring to were definitely due to the Rs. 200 crores which I just mentioned a short while ago, which was stuck with the private sector .
- The Company has converted the Rs. 200 crores stuck with the private sector into real estate assets and is going for liquidation of them over the next seven to eight quarters.
Show source
Which the Company today has success successfully as converted them into real estate assets and now is going for liquidation of the same over the next Capacit’e Infraprojects Limited November 18, 2024 Page 9 of 17 seven to eight quarters.
- Liquidating the real estate assets can improve the Company’s cash flow by another Rs. 200 crores, apart from margins realized from operations.
Show source
Which means the Company can only improve the cash flow by another Rs. 200 crores, apart from whatever margins it realizes from operations.
- The total bank guarantees currently issued by the Company to clients, including consortium and project-specific guarantees for CIDCO and MHADA, are Rs. 730 crores.
Show source
Rohit Katyal: So, total bank guarantees are issued currently to the clients , so including consortium and project specific for CIDCO and MHADA, the total guarantees issued is Rs. 730 crores.
- Of Rs. 210 crores, close to Rs. 100 crores is reflected in the books, and about Rs. 90 crores is not reflected because it has already been written off.
Show source
I just explained to you, out of Rs. 210 crores what is reflecting in the books is close to Rs. 100 crores, alright.
- Gross Debt was ₹ 343 crores as on Sep 30, 2024, the same as ₹ 343 crores as at March 31, 2024; Gross Debt to Equity was 0.21x.
Show source
Gross debt stood at Rs. 343 crores as on 30th September as compared to Rs. 343 crores as on March 31st ’24, with gross debt to equity at 0.21x.
What it expects ahead
What management expects
- Capacit’e Infraprojects Limited expects strong collections in quarter three, with Rs. 200-plus crores collected in October already, after some payments shifted into October because of the elections; it expects net working capital to reduce in quarter three, with further improvement in Quarter 4, and is committed to a 100-day level by the year end.
Show source
However, now with the Capacit’e Infraprojects Limited November 18, 2024 Page 4 of 17 elections getting over by November 23rd, we see a very strong collection in quarter three happening, that is evident from the Rs. 200-plus crores collection done in October already.
- Capacit’e Infraprojects Limited’s internal net working capital targets remain at 90 days, and it is confident of achieving 100 days net working capital by the end of the current fiscal.
Show source
However, the internal targets continue to remain at 90 days, but we are very confident of achieving 100 days net working capital by the end of the current fiscal.
- Pending the NOC from State Bank of India, sales of about Rs. 17 crores have already happened; Capacit’e Infraprojects Limited expects sales close to Rs. 80 crores by March ’25, with realization in the subsequent quarter, and targets Rs. 85 crores for the current financial year.
Show source
We expect sales of close to Rs. 80 crores by March ’25, and the realization in the subsequent quarter.
- Capacit’e Infraprojects Limited continues to target Rs. 3,000 crores of order intake in FY ’25 and sees scope for improvement in actual order intake; excluding MHADA, the Company sees Rs. 3,000 crores as achievable in the current financial year.
Show source
Rohit Katyal: So, Parvez, we continue with that target of Rs. 3,000 crores, I think there is a scope of improving in actual .
- Capacit’e Infraprojects Limited expects execution as a subcontract to continue at close to Rs. 20 crores per month, increase to about Rs. 25 crores to Rs. 28 crores for Quarter 4, and exceed Rs. 100 crores per quarter from the next financial year.
Show source
However, that will increase to about Rs. 25 crores to Rs. 28 crores for Quarter 4, and it should increase significantly to cross more than Rs. 100 crores per quarter from the next financial year.
- The Company expects its uncertified bills to reduce over quarter three, Quarter 4 and subsequent quarters.
Show source
So, there was an increase earlier, then there was two quarters of stagnancy, and now yo u will see reduction over the quarter three and Quarter 4, and their subsequent quarters going forward.
Show 29 more statements
What management expects
- The Company’s target is to bring this number to approximately Rs. 900 crores over the next four to five quarters, comparable to the number being compared with.
Show source
So, the overall target is to get this number over the next four to five quarters to approximately Rs. 900 crores, which would be then comparable to the number what you are comparing with.
- The Company expects contract assets to contract in a phased manner and return to Rs. 900 crores over the next three to four quarters.
Show source
At the same time, you will have contract assets reduction or contraction in the contract assets in a phased-wise manner to bring it back to Rs. 900 crores over the next three to four quarters.
- The Company expects MHADA’s contribution to improve to Rs. 25 crores or Rs. 28 crores in Quarter 4.
Show source
We expect that to improve to Rs. 25 crores, Rs. 28 crores in Quarter 4.
- MHADA’s contribution can improve to Rs. 100 crores per quarter from next financial year, depending on the availability of new building.
Show source
And then it can improve to Rs. 100 crores from next financial year per quarter.
- Bhandup hospital will soon start contributing more than Rs. 12 crores to Rs. 15 crores per month to the Company.
Show source
You will soon have Bhandup hospital which will start contributing more than Rs. 12 crores to Rs. 15 crores per month.
- M3M was contributing close to Rs. 7 crores and is expected to contribute Rs. 15 crores from December onwards.
Show source
You have M3 M contributing close to Rs. 7 crores, but is expected to go to Rs. 15 crores from December onwards.
- Capacit’e Infraprojects Limited expects growth of 25 %, 30% on a higher base once its projects provide at least Rs. 10 crores per month.
Show source
And once that happens, only then will you see the growth of that 25 %, 30% on a higher base, and that is what exactly we are focused on.
- Rs. 3,l00 crores non-MHADA will definitely happen.
Show source
Rs. 3,l00 crores non-MHADA will definitely happen.
- When Rs. 100 crores comes in, debtors and assets held for sale will go down, the gross block will fall, and the balance not appearing in the books will positively impact profitability.
Show source
And once that Rs. 100 crores come, it will impact two things, it will impact the debtors going down and the assets held for sale, these two will go down.
- Capacit’e Infraprojects Limited will start billing for M3M from Quarter 4 of the current fiscal.
Show source
A nd M3M, as I told you, we will start billing from Quarter 4 of the current fiscal.
- The restrictions may have an impact of Rs. 15 crores, Rs. 20 crores for the quarter at best.
Show source
So, I do not see any meaningful impact, maybe Rs. 15 crores, Rs. 20 crores for the quarter at best.
- Capacit’e Infraprojects Limited's order book will continue to grow on an absolute basis, though the order book to sales ratio could be 5 or 3.5.
Show source
Rohit Katyal: It could be 5, it could be 3.5, but on a absolute basis we will only continue to grow.
- Capacit’e Infraprojects Limited anticipates further operational improvements in the second half of the year.
Show source
The back-to-back strong quarterly performance sets the tone for the second -half of the yea r wherein we anticipate further operational improvements.
- Capacit’e Infraprojects Limited does not expect PAT to be impacted by untoward provisioning from slow-moving debtors, bad debts or additional provisioning.
Show source
And therefore, we do not expect the PAT Capacit’e Infraprojects Limited November 18, 2024 Page 5 of 17 to be impacted by any untoward provisioning happening from slow moving debtors or bad debts and/or additional provisioning.
- The Company expects employee cost as a percentage of the top line for the overall year to be lower than last financial year.
Show source
And this will be on an overall year basis as a percentage lower to the top line as a percentage as opposed to last financial year.
- The Company expects to start booking its share of profit from the LLP from next financial year, and expects it to be substantial.
Show source
However, we will book our share of profit which hopefully should start from next financial year and should be substantial.
- At the LLP level, Tata projects and Capacit’e are putting all efforts to get the entire portfolio of project execution in hand, which they are quite hopeful will happen by quarter two of next fiscal year.
Show source
And we are quite hopeful that by quarter two of next fiscal year that should be happening.
- Capacit’e Infraprojects Limited expects execution to grow in Q3; elections do not affect execution of existing projects but affect government inflow of orders in the state where elections are happening, and management sees no reason for elections to affect the Company's top line or continued growth.
Show source
So, I do not see any reason for elections having any impact whatsoever on the top line of the Company, the growth will continue.
- Capacit’e Infraprojects Limited expects complete realization within seven to eight quarters. Replaced by a later filing.
Show source
You will see the complete realization hopefully within seven to eight quarters.
- The Company is more than confident in achieving the targets it has laid out. Replaced by a later filing.
Show source
So, the summary of all this is that we are more than confident in achieving whatever targets we have lined out.
Orders
- Capacit’e Infraprojects Limited has so far been awarded projects worth Rs. 1,500 crores, excluding BDD addition of Rs. 858 crores during the current fiscal, and is confident of achieving and surpassing its guided order book addition for FY ‘25.
Show source
We have so far been awarded projects worth Rs. 1,500 crores, excluding BDD addition of Rs. 858 crores during the current fiscal and are confident of achieving and surpassing our guided order book addition for FY ‘25.
- Capacit’e Infraprojects Limited’s standalone order book stood at Rs. 9,203 crores as on September 30th, ’24.
Show source
Order book on a standalone basis stood at Rs. 9,203 crores as on September 30th, ’24.
- Public sector accounts were 73% of Capacit’e Infraprojects Limited’s total order book, while private sector accounts were 27% of the total order book, as on September 30th, ’24.
Show source
Public sector accounts were 73% while private sector accounts were 27% of the total order book.
- The current order book gives the Company an opportunity to bag seven or eight projects, each with minimum revenue of Rs. 10 crores per month per project.
Show source
Point number three, the Rs. 8,000 crores order book was spread across maybe 50 projects, and now this Rs. 10,000 crores is spread about maybe 2 2, 23 projects, thereby giving the Company an opportunity to ba g another seven or eight projects , having the minimum revenue of Rs. 10 crores per month per project .
- MHADA is close to Rs. 2,300 crores, with more than Rs. 1,400 crores, Rs. 1,500 crores yet to execute.
Show source
But MHADA is close to Rs. 2,300 crores now, all right, and we yet have to execute more than I think Rs. 1,400 crores, Rs. 1,500 crores out of that.
- The Rs. 1,200 crore order received from Signatureglobal is part of the Rs. 1,500 crores year-to-date order inflow, and Capacit’e Infraprojects Limited is targeting another Rs. 1,500 crores over the next five months in the current fiscal.
Show source
Rohit Katyal: No, it is a part of the Rs. 1,500 crores year-to-date order inflow, and we are targeting another Rs. 1,500 crores over the next five months in the current fiscal.
- Capacit’e Infraprojects Limited continues to bid for both the private sector and government sector, and its last major order has happened from the private sector, slightly tilting or improving the balance of its order book in favor of the private sector.
Show source
Our last major order has happened from the private sector.
- The Company is hopeful that MHADA’s traction will translate into executable order book.
Show source
However, given the traction, we are quite hopeful that this is going to translate into executable order book.
- The MHADA amount will be added as locations to start construction are received, and Capacit’e Infraprojects Limited will inform investors in that quarter. Replaced by a later filing.
Show source
MHADA, as and when we get the locations to start the construction , that will be added automatically , and we will inform you in that quarter.
What it is building and selling
Projects and capacity
- CIDCO’s execution run rate was close to Rs. 50 crores for October, and Capacit’e Infraprojects Limited expects it to reach Rs. 65 crores by December and Rs. 75 crores by January per month.
Show source
So, the execution run rate for October for CIDCO was close to Rs. 50 crores, we expect that to go to Rs. 65 crores by December and Rs. 75 crores by January per month .
- CIDCO has total land available worth Rs. 2,400 crores across six locations, with about Rs. 1,500 crores still to be billed on a certified mechanism across those locations by March of ’26.
Show source
T he total land available is Rs. 2,400 crores across six locations, which means that we have to still bill about Rs. 1,500 crores on certified mechanism on these six locations, which has to happen by March of ‘26 in totality.
- For MHADA, Capacit’e Infraprojects Limited has received land for five sale-component towers close to 90 stories in height or 305 meters, and has 14 rehab-portion towers of 40 stories; it expects another eight towers to be released by December of the current quarter, that is quarter three.
Show source
As concerning MHADA, we have received land for five towers of sale component which are close to 90 stories in height or 305 meters.
- MHADA was non-operational at the time of the earlier order book, but is operational now.
Show source
However, in that order book MHADA was non-operational at that moment in time which is operational now.
- CIDCO was non-operational for one and a half years.
Show source
CIDCO for one and a half years was non-operational.
- M3M is going on in Noida, where there are no restrictions on construction, although there is a restriction on some vehicles and sand; Capacit’e Infraprojects Limited does not buy sand and will ensure its concrete manufacturers have sufficient quantity.
Show source
There is restriction on the sand, but we do not buy sand so we will have to ensure that our concrete manufacturers have sufficient quantity to negat e that impact.
Show 3 more statements
Demand and pricing
- The average project size in Delhi NCR has increased from Rs. 250 crores, Rs. 300 crores to in excess of Rs. 800,000 crores.
Show source
So, earlier the average size used to be Rs. 250 crores, Rs. 300 crores which has now suddenly shot up to in excess of Rs. 800,000 crores.
Segments
- Capacit’e Infraprojects Limited is actively looking at Hyderabad and bidding for projects there, identifying it as its fourth geography.
Show source
We are actively looking at Hyderabad and bidding in projects for over there, that's the fourth geography.
Deals and partners
- For the Signatureglobal project, Capacit’e Infraprojects Limited will do only shell and core works for the residential tower, non-tower and retail area, and the scope will remain the same as the previous project.
Show source
And we will be doing only shell and core works for the residential tower, non-tower and the retail area.
Risks, rules and outside factors
Outside factors
- Capacit’e Infraprojects Limited has full pass through of raw material price increases in private-sector projects; government projects have price variation, or escalation, clauses covering increases in material or labor costs.
Show source
In the government sector, all projects have price variation clauses, which is commonly known as escalation clauses , w hich cover up for price increases , alright, whether it is material or labor.
Everything else said on the call
What management stressed
- Capacit’e Infraprojects Limited aims to have no project in its portfolio that provides less than Rs. 10 crores per month.
Show source
So, all the p rojects, basically the idea of taking limited projects is that we do not want to have any project in the portfolio which gives less than Rs. 10 crores per month.
- Capacit’e Infraprojects Limited follows a policy of taking orders in a particular financial year and targeting execution in the next financial year at a level similar to that year's order intake; for example, an order target of Rs. 3,000 crore s in FY ’25 would have a similar execution target in the next financial year.
Show source
L et's say if the order target is Rs. 3,000 crore s in FY ’25, then the target for execution is similar to the order intake in the next financial year.
- Capacit’e Infraprojects Limited aims to take orders that offer an opportunity to bill at least Rs. 10 crores per month, because a lower amount does not provide a conducive risk reward ratio.
Show source
And obviously, as I just told the earlier gentleman who asked, our policy is that whatever orders we take, we should have an o pportunity to bill at least Rs. 10 crores per month, otherwise the risk reward ratio is not very conducive for the Company.
Group structure
- The Company owns 35% of the LLP and does not consolidate revenue at the LLP level, but consolidates revenue from other projects.
Show source
Rohit Katyal: Obviously, we are not consolidating the revenue at the LLP level, because we own 35% of that , other projects consolidate that.
- At the end of the project, the Company will be entitled to book its share of subcontract, close to Rs. 5,000 crores, and its 35% project profit at the LLP level, the joint venture level.
Show source
Rohit Katyal: I would like to reiterate that we will be entitled to book our share of subcontract, which will be at the end of the project close to Rs. 5,000 crores, and we will be entitled for our 35% project profit at the LLP level, that is the joint venture level.
People and governance
- The Company has a permanent workforce of more than 1,800 staff, 80% from engineering and 20% from support commercial, and more than 1,400 technicians to support its 25% year-on-year revenue growth guidance.
Show source
However, to sum u p, we do believe that the current traction of improvement in revenues, bottom line , and today the Company has a permanent workforce of more than 1 ,800 strong staff, 80% from the engineering background, 20% from support commercial , and more than 1 ,400 techn icians to support the revenue guidance of 25% growth year-on-year.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Nirvana Laha: Sir, congrats on another great quarter. Sir my question is a little strategic in nature. So, if I look at your execution history from FY ‘18 to FY ‘24, obviously earlier you used to be 80%, 90% private order book and now you are about 75% government order book. Sir, you have explained that you do the design part in government projects, and you are able to earn 200 bps higher margin in these projects. But sir, if I look at the working capital, it used to be less than 100 days pre-COVID, now it is touching 200 days. So, as a return on capital levels , sir, we are either at the same level or maybe even lower, plus there are liquidity risks of non-fund-based limits etc. So, I know
Answer, rohit katyal
Rohit Katyal: Yes, good question. So, the point is that you have to look at the whole year performance to come at any conclusion as far as the working capital is concerned . If you look at Quarter 1, there was basically a reduction in the net working ca pital by 13 days . This quarter, some of our payments got shifted into October because of the elections which were going on . However, now with the Capacit’e Infraprojects Limited November 18, 2024 Page 4 of 17 elections getting over by November 23rd, we see a very strong collection in quarter three happening, that is evident from the Rs. 200-plus crores collection done in October already. And therefore, you will see a reduction in net working capital in quarter three, with further improvement in Quarter 4. We stand committed to that 100-day level by the year end, this I have repeated earlier also.
Answer, rohit katyal
However, the internal targets continue to remain at 90 days, but we are very confident of achieving 100 days net working capital by the end of the current fiscal. And that will only improve going forward. You see, you mentioned COVID, and COVID taught us that overdependence of anyone, whether private or public, is not warranted. It is very dynamic in nature. We continue to bid for both the private sector and government sector. Our last major order has happened from the private sector. Again, therefore, tilting or improving the balance of order book slightly in favor on private sector.
Answer, rohit katyal
So, there is nothing called 50:50. We will continue to bid for projects in both private and public. Quality of client continues to be the most important parameter while taking an order book. And third, liquidity issues cannot arise. The retention amount over the last one year on absolute basis on increased top line has reduced to Rs. 135 crores from Rs. 170 crores last financial year. The Company is sitting on more than Rs. 250 crores of unutilized bank guarantee limits, and therefore we do not see any issue of collecting our retentions or advances, which will happen substantially in the current quarter given the new order wins due to non-fund availability of non-fund-based limits. I hope to have covered all your points.
Question
Nirvana Laha: Thanks a lot for the detailed answer. Sir, on the Signatureglobal order, first of all, congratulations on bagging such a large order. When can we see the execution start and how do you see it ramping up?
Answer, rohit katyal
Rohit Katyal: So, the execution of this order will start in Quarter 4 of the current fiscal. And given the completion period, it should peak at about Rs. 25 crores to Rs. 30 crores per month. This order is in two phases, phase one will start from 1st Quarter and Phase-II may start from the 2nd Quarter of the next fiscal. For the first part, I stand corrected, 4th Quarter and the 1st Quarter. Nirvana Laha: Sir, if I look at your FY ‘24 Annual Report, we had taken Rs. 112 crore receivable write -off. I assume this was to do with clients which faced difficulties during COVID. If you can call that out please, because I am not aware of the history which client and what projects are they pertaining to.
Answer, rohit katyal
And if there are any other receivables on our books currently which are at risk of such a write- off. I understand that you have already taken possession of some assets which you intend to sell. So, if you can just give some idea about all these aspects, what is happening to the assets held for sale, plus how much more receivables can be expected to flip to us taking possession of such assets and the write-off happened from which client? Thank you.
Answer, rohit katyal
Rohit Katyal: So, the write offs predominantly, close to Rs. 80 crores, Rs. 90 crores were for the Radius Group. Because Radius was in joint venture somewhere with Sumer, somewhere with DB Reality and elsewhere. So, coming to the fact that it's not only the last financial year, but the Company has also followed an aggressive provisioning policy subsequent to the COVID year, and we have provided for more than Rs. 180 crores of expected credit losses. Which means that we are not left with any surprises which I reaffirmed in the last quarter as well. And therefore, we do not expect the PAT Capacit’e Infraprojects Limited November 18, 2024 Page 5 of 17 to be impacted by any untoward provisioning happening from slow moving debtors or bad debts and/or additional provisioning. That's point number one. Point number two, the Company’s aggressive collection drive, which is more of legal in nature at various forums whether its RERA, whether it is at NCLT or High Court, has ensured that the Company is today holding assets in excess of Rs. 200 crores market value as against a total collection of a collection of about Rs. 115 crores.
Answer, rohit katyal
We expect this realization from fixed assets over and above our collection normal targets from our debt ors to happen over the next seven quarters to eight quarters. Now, what will this mean? This will mean that about Rs. 100 crores of debtors or debt levels will fall in the balance sheet. Number two, the bottom line will strengthen by close to Rs. 80 crores, Rs. 85 crores. And number three, the gross debt of the Company will fall apart from whatever it falls from the operational profits by about Rs. 200 crores from these collections. Hope I have explained.
Question
Nirvana Laha: Sir, great to hear. Last question sir, has the sale already started or which quarter do you anticipate this sale starting from?
Answer, rohit katyal
Rohit Katyal: We are waiting for the N OC from State Bank of India . Pending the NOC, sales of about Rs. 17 crores have already happened. We expect sales of close to Rs. 80 crores by March ’25, and the realization in the subsequent quarter. But as I told you, plea se do not hold me responsible, these are internal targets. You will see the complete realization hopefully within seven to eight quarters. But Rs. 85 crores is the target for the current financial year.
Question
Nirvana Laha: Thank you so much, sir. Congrats on the great execution and hope you have a great day. Thank you.
Answer, rohit katyal
Rohit Katyal: There is no impairment, madam. There is a policy of expected credit loss which every Company follows. And that is exactly this expected credit loss or what we know known as ECL is a policy which is approved by the auditors and also by the audit committee of the Company. A nd the Company follows that policy, which means that there is a certain provisioning on the working capital that is work in process, there is certain provisioning on the retention and there is certain provisioning on the debtors. So, this is a normal thing. Again, if you look at the other expenses, the total expenses have to be looked into and as a percentage because the revenue of quarter two is lesser than Quarter 1 obviously because of the monsoons, there we lost 22 days. You will have to look at the full year where we believe that the provision will improve as a percentage to top line basically on all expenditure parameters.
Answer, rohit katyal
Further, when you are looking at provisioning, you also have to look at other income where the provisioning happens. So, when you take the net of it, it's a much improved positioning. Capacit’e Infraprojects Limited November 18, 2024 Page 6 of 17 Aditi: And I have a few other questions. So, one is, the cash on hand essentially that has dipped in the first half, so is there anything to read into that?
Answer, rohit katyal
Rohit Katyal: Madam, you please see that there is a temporary increase in the debtors where the amount sitting in WIP is moving towards certified bills. That collection has just shifted by 10 days coming into quarter three of the current financial year. So, the cash position will be back to what it was by the end of Q3, nothing to read into that. Aditi: And the EBIT margin has been really great in the first half , so is that sustainable , or do we see some moderation going forward?
Answer, rohit katyal
Rohit Katyal: No, with the current order book superimposed, we do believe that this will continue at least for the next four quarters, until unless there is something untoward which happens to the industry which we do not expect. Aditi: And sir last question, there was this data center project that you were bidding for around Rs. 700 crews, so any updates on that?
Answer, rohit katyal
Rohit Katyal: Let the elections get over, madam. We believe that at the moment all the orders from government in the Maharashtra state are status quo. So, once the elections are over we will then pursue for that. At the moment, at least for the current month, we will be targeting only the private sector. And the private sector negotiations are on and we should be waiting for some good information.
Question
Parvez Qazi: Sir my first question is regarding the order intake. I believe you have given a guidance about Rs. 3,000 crores of order intake in FY ’25, so does this still stand or you want to revise that number?
Answer, rohit katyal
Rohit Katyal: So, Parvez, we continue with that target of Rs. 3,000 crores, I think there is a scope of improving in actual . But you have seen that we have been very choosy in picking up the orders because anything which we do today will have an impact whether positive or negative two years down the line. So, we are very, very particular. Not to forget that MHADA has to still add about Rs. 3,000 crores to Rs. 4, 000 crores of order booked to the overall order book of the Company. So, the Company will be cautious in picking up orders . B ut excluding MHADA, Rs. 3,000 crores is something which we definitely see as happening in the current financial year.
Question
Parvez Qazi: And for our two big projects, which is MHADA and CIDCO, would be great to get a status of the projects in terms of what is the work front available as of now and what is the execution run rate now and where do we expect to see it going ahead?
Answer, rohit katyal
Rohit Katyal: Yes. So, the execution run rate for October for CIDCO was close to Rs. 50 crores, we expect that to go to Rs. 65 crores by December and Rs. 75 crores by January per month . T he total land available is Rs. 2,400 crores across six locations, which means that we have to still bill about Rs. 1,500 crores on certified mechanism on these six locations, which has to happen by March of ‘26 in totality. The seventh location is identified. However, once it is received, it shall be promptly Capacit’e Infraprojects Limited November 18, 2024 Page 7 of 17 informed to you. As concerning MHADA, we have received land for five towers of sale component which are close to 90 stories in height or 305 meters. Apart from that, we have 14 towers on the rehab portion of 40 stories, and we expect another eight towers to be released by December of the current quarter , t hat is quarter three.
Answer, rohit katyal
So, we do believe that the execution will continue for Capacit’e as a subcontract as close to Rs. 20 crores per month. However, that will increase to about Rs. 25 crores to Rs. 28 crores for Quarter 4, and it should increase significantly to cross more than Rs. 100 crores per quarter from the next financial year.
Question
Rajesh Jain: Sir, I have three questions. Sir, I have recently started tracking your Company and I was going through some of the very old calls of 2018 and ’19, much before pre-COVID just after your listing. I understand that today you have an order book of approximately around Rs. 10,000 crores and you have guided for 25% growth for the next two, three years. But back then also, in 2018 and ‘19, even much before COVID, you had an order book of Rs. 8000 crores and you had guided for the same, 25% growth for two, three years. But what actually panned out was only one year of growth and then subsequent degrowth. So, what has changed ? I mean , in the current scenario how confident you are that
Answer, rohit katyal
Rohit Katyal: Good question. So, you have to first track the Company from 2013 till 2019-‘20 which has seen a compounded annual growth of excess of 35%, 40%. So, the first jolt was in the COVID years, and Capacit’e Infraprojects Limited November 18, 2024 Page 8 of 17 thereafter there was recovery, but not to the extent to match with March 2020 , alright? That's number one. Number two, the order book was Rs. 8,000 crores or more. However, in that order book MHADA was non-operational at that moment in time which is operational now. CIDCO for one and a half years was non-operational.
Answer, rohit katyal
So, though the order book was Rs. 9,000 crores, the revenue was coming from only Rs. 3,500 crores or Rs. 4,000 crores business. So, that explains the reason why the growth you have now happening over the last three and a half or four quarters, simply because the order book is operational, and the Company is driving substantial revenue from these two big ticket size orders . Point number three, the Rs. 8,000 crores order book was spread across maybe 50 projects, and now this Rs. 10,000 crores is spread about maybe 2 2, 23 projects, thereby giving the Company an opportunity to ba g another seven or eight projects , having the minimum revenue of Rs. 10 crores per month per project . And therefore, then taking it to the growth projections what we have given you. So, the summary of all this is that we are more than confident in achieving whatever targets we have lined out.
Question
Rajesh Jain: Sir, just two more questions , again, one related to the history and then one related to accounting norms. So, in the past what I came to know from my circle is that you had a lot of issues related to delayed payments of salaries and delayed execution of projects, even those which were operational. I mean, I do not know how much of that is true, so I just wanted to hear from you how much of that is true. And whether any of that project delays or salary delays issues persist today , or is there any risk of that coming back?
Answer, rohit katyal
Rohit Katyal: There are too many questions . Number one, whatever the Company did, also during the difficult times it worked within the cash flows which were received per quarter. Subsequent to that, the Company raised close to Rs. 350 crores through preferential, QIP and infusion by the promoters. So, therefore, any cash fl ow issues, whoever has told, is a matter of maybe long past . And any which ways the Company has, along with its amazing team, confronted it very, very well. So, I do not know who has given you this feedback, which I can only call he arsay. However, to sum u p, we do believe that the current traction of improvement in revenues, bottom line , and today the Company has a permanent workforce of more than 1 ,800 strong staff, 80% from the engineering background, 20% from support commercial , and more than 1 ,400 techn icians to support the revenue guidance of 25% growth year-on-year.
Answer, rohit katyal
So, I believe that the cash flow issues which you are referring to were definitely due to the Rs. 200 crores which I just mentioned a short while ago, which was stuck with the private sector . Which the Company today has success successfully as converted them into real estate assets and now is going for liquidation of the same over the next Capacit’e Infraprojects Limited November 18, 2024 Page 9 of 17 seven to eight quarters. Which means the Company can only improve the cash flow by another Rs. 200 crores, apart from whatever margins it realizes from operations.
Question
Rajesh Jain: Sir, that's very reassuring. And my last question is on accounting norms in your business. Because you are a contractor who executes projects for the other builders, for the real estate companies. As far as those real estate companies goes like Godrej or DLF or other housing companies, their pre- sales number flow to revenue as per the accounting norms after project completi on and after OC is received, as per my understanding. So, in your business is there any accounting norms for the revenue to flow to books based on certain percentage of completion method? And if yes, then can you elaborate on that, just for my understanding?
Answer, rohit katyal
Rohit Katyal: Yes. So, slow down will happen during elections from an order inflow perspective on the public sector side pertaining to the state where the elections are happening. So, if th e elections are happening now in Maharashtra, there is a code of conduct in place. And obviously, during code of conduct which only ceases after the elections are fully over, there will not be any new orders which could flow from the government to any Company, that's number one. Your second question was , the employee cost has increased by Rs. 7 crores over the last quarter. This is primarily due to increase in employee strength, new joinees which I meant to say , and obviously the increments which have happened. And this will be on an overall year basis as a percentage lower to the top line as a percentage as opposed to last financial year.
Question
Akshat Mehta: Yes.
Answer, rohit katyal
Rohit Katyal: So, total bank guarantees are issued currently to the clients , so including consortium and project specific for CIDCO and MHADA, the total guarantees issued is Rs. 730 crores.
Show 17 more questions
Question
Akshat Mehta: So, my question was that our unbilled revenue, or the revenue that we have for certification , that has been increasing quite a lot over the last couple of years. So, any specific reason that we are seeing that increase in number? And what could it be going in the future?
Answer, rohit katyal
Rohit Katyal: So, you please if you compare, the WIP was Rs. 889 crores, which is work done, not billed, bill submitted, all that put together, was Rs. 889 crores on our top line of close to Rs. 450 crores last financial year, that is Rs. 900 crores on a much higher top line . Number two, the uncertified bills continue to be at Rs. 434 crores, even though there has been an increase in the top line . And this overall stagnancy will now show reductions. So, there was an increase earlier, then there was two quarters of stagnancy, and now yo u will see reduction over the quarter three and Quarter 4, and their subsequent quarters going forward. So, the overall target is to get this number over the next four to five quarters to approximately Rs. 900 crores, which would be then comparable to the number what you are comparing with.
Question
Akshat Mehta: So, we want to get back to two years back what the number was?
Answer, rohit katyal
Rohit Katyal: Absolutely, because there is no reason we have started the POC method about three years ago. There was a temporary increase in that. And I will not say that it was not a big increase, yes, it was a substantially big increase. However, if you see, that amount has now stagnated even though the top line has improved significantly. Going forward, the top line is bound to increase. At the same time, you will have contract assets reduction or contraction in the contract assets in a phased-wise manner to bring it back to Rs. 900 crores over the next three to four quarters.
Question
Dhananjay Mishra: And can you repeat the MHADA monthly run rate as of now, I didn't hear.
Answer, rohit katyal
Rohit Katyal: So, MHADA, at the moment we are doing about Rs. 20 crores per month, we will continue to do that in quarter three. We expect that to improve to Rs. 25 crores, Rs. 28 crores in Quarter 4. And then it can improve to Rs. 100 crores from next financial year per quarter. It all depends on the availability of new building. However, given the traction, we are quite hopeful that this is going to translate into executable order book.
Question
Dhananjay Mishra: And this is our share?
Answer, rohit katyal
Rohit Katyal: Obviously, we are not consolidating the revenue at the LLP level, because we own 35% of that , other projects consolidate that. However, we will book our share of profit which hopefully should start from next financial year and should be substantial.
Question
Dhananjay Mishra: So, we will only take profit from both projects as a JV profit?
Answer, rohit katyal
Rohit Katyal: I would like to reiterate that we will be entitled to book our share of subcontract, which will be at the end of the project close to Rs. 5,000 crores, and we will be entitled for our 35% project profit at the LLP level, that is the joint venture level. So, these are the two things which the Company will recognize.
Question
Dhananjay Mishra: And lastly, can you give major orders apart from CIDCO which are contributing to our revenue as of now?
Answer, rohit katyal
Rohit Katyal: All. So, Raymond is contributing Rs. 20 crores per month. MHADA is contributing nearly Rs. 18 crores, Rs. 20 crores per month. You have CIDCO which is now contributing in excess of Rs. 45 crores to Rs. 50 crores a month. You have J V which is contributing in excess of Rs. 10 crores a month. You have Bhagwati Hospital, which is contributing more than Rs. 10 crores per month. You will soon have Bhandup hospital which will start contributing more than Rs. 12 crores to Rs. 15 crores per month.
Answer, rohit katyal
You have M3 M contributing close to Rs. 7 crores, but is expected to go to Rs. 15 crores from December onwards. So, all the p rojects, basically the idea of taking limited projects is that we do not want to have any project in the portfolio which gives less than Rs. 10 crores per month. And once that happens, only then will you see the growth of that 25 %, 30% on a higher base, and that is what exactly we are focused on. Capacit’e Infraprojects Limited November 18, 2024 Page 13 of 17 Moderator: Thank you.
Question
Anupam Gupta: And you said by the end of this year, so another Rs. 1,500 crores from non-MHADA and possibly another Rs. 3,000 crore of MHADA orders will get increased?
Answer, rohit katyal
Rohit Katyal: No, I would like to correct you. Rs. 3,l00 crores non-MHADA will definitely happen. MHADA, as and when we get the locations to start the construction , that will be added automatically , and we will inform you in that quarter. But MHADA is close to Rs. 2,300 crores now, all right, and we yet have to execute more than I think Rs. 1,400 crores, Rs. 1,500 crores out of that. So, that is substantial for the next two years. However, at the LLP level, both Tata projects and Capacit’e are putting all efforts to get the entire portfolio of the project execution in hand . And we are quite hopeful that by quarter two of next fiscal year that should be happening.
Question
Anupam Gupta: And all of that in your balance sheet is currently reflected in other long term assets, right?
Answer, rohit katyal
Rohit Katyal: No, about Rs. 90 crores not reflecting only, that's already been written off. I just explained to you, out of Rs. 210 crores what is reflecting in the books is close to Rs. 100 crores, alright. And once that Rs. 100 crores come, it will impact two things, it will impact the debtors going down and the assets held for sale, these two will go down. So, one is, the asset will fall , the gross block. The second thing is that your debtors will fall. Third thing is that balance, which is not appearing in the books, will hit your profitability positively.
Question
Anupam Gupta: And just one last question , in your order book what book portion of projects are currently under execution and NCR, which will see impact, let's say, over the next two months at least?
Answer, rohit katyal
Rohit Katyal: So, we have M3M which is going on in Noida, so far there are no restrictions, but you can never guess. So, there are no restrictions on construction, there is restriction on some vehicles which has come in, at the moment. There is restriction on the sand, but we do not buy sand so we will have to ensure that our concrete manufacturers have sufficient quantity to negat e that impact. A nd M3M, as I told you, we will start billing from Quarter 4 of the current fiscal. So, I do not see any meaningful impact, maybe Rs. 15 crores, Rs. 20 crores for the quarter at best.
Question
Anupam Gupta: Employee availability.
Answer, rohit katyal
Rohit Katyal: Availability. Oh, that's always a challenge to get good people. So, that will continue till the time we do business, isn't it, Anupam? I mean, the point is that ’s there across industry, that’s nothing specific to us. The challenge is to retain workmen . And we are among the first few companies in the building construction industry we have adopted the 15-day payment cycle successfully over the last months, which has made a significant improvement in we being able to retain labor contractors, and we hope that that will continue. So, you have to do things which are innovative in nature to ensure that the labor avail ability, especially the trained labor availability, does not become a challenge, therefore an impediment to your growth.
Question
Jayesh Gandhi: So, first of all, congratulations on good numbers. My question is on order book position. If I look at your order book to sales ratio in the last three, four years, it is it is coming off. And currently, I mean, FY ‘24 it shows as 4.7. I am guessing even on September if you take, probably it would be at the similar level. So, is it our conscious decision to do that or are we choosy for margins or is there a competitive pressure or can you just throw some light on that?
Answer, rohit katyal
Rohit Katyal: Sir, if you see our order book, it is in line with our competition and the industry. Earlier there were times where the order book was 6x, but the execution period was five years. Today, if the execution period on average is coming down, then your order book cannot increase abnormally, because you need to execute the order book as well. So, our policy is that we need to take orders in a particular financial year . L et's say if the order target is Rs. 3,000 crore s in FY ’25, then the target for execution is similar to the order intake in the next financial year. So, that is the policy which we follow. And obviously, as I just told the earlier gentleman who asked, our policy is that whatever orders we take, we should have an o pportunity to bill at least Rs. 10 crores per month, otherwise the risk reward ratio is not very conducive for the Company.
Question
Jayesh Gandhi: Then can I conclude by saying that we will be somewhere between 4.5 only in future as well?
Answer, rohit katyal
Rohit Katyal: It could be 5, it could be 3.5, but on a absolute basis we will only continue to grow.
Question
Khadija Mantri: Sir, I have two questions. One is, in Q3 do we expect the execution to be impacted because of election? Or we will have a good growth on Y-o-Y basis as well?
Answer, rohit katyal
Rohit Katyal: Please expect execution to grow. Elections have no impact on execution of existing projects. They only have an impact on government inflow of orders of the state where the elections are happening. So, I do not see any reason for elections having any impact whatsoever on the top line of the Company, the growth will continue.
Question
Khadija Mantri: And sir, the next question is , this Rs. 1,200 crore s order that we have received from Signatureglobal, it is part of the Rs. 1,500 crores order inflow that we have talked about till year- to-date or is it over and above that?
Answer, rohit katyal
Rohit Katyal: No, it is a part of the Rs. 1,500 crores year-to-date order inflow, and we are targeting another Rs. 1,500 crores over the next five months in the current fiscal.
Question
Khadija Mantri: Sir, in this project will the scope of the work for us remain the same as the previous project, or is it something different that we would be doing in this project?
Answer, rohit katyal
Rohit Katyal: No, all private sector projects, whether we do , L&T does, more often than not we try to do only shell and core. And we will be doing only shell and core works for the residential tower, non-tower and the retail area. So, the scope will remain the same. But yes, as you are seeing that the sizes of the projects, especially in Delhi NCR area are increasing manifold. So, earlier the average size used to be Rs. 250 crores, Rs. 300 crores which has now suddenly shot up to in excess of Rs. 800,000 crores. Apart from that size difference, we do not see any other scope change as of now.
Question
Amit Agicha: Thank you for the opportunity and congratulations to the whole team for a good set of quarter numbers. My question was with respect to like, are there any plans to diversify into new geographies or segments beyond the current quarter?
Answer, rohit katyal
Rohit Katyal: Sir, we before COVID were in seven top cities of the country. Again, we have increased over the last one and a half year back we are in Mumbai. We will be in Pune whenever the opportunity comes, but yes, we are there. We are in Mumbai MMR, which is conside red as one geography. We are in Delhi NCR which is considered as a second geography. We are in Gandhinagar, Gujarat which is the third geography. We are actively looking at Hyderabad and bidding in projects for over there, that's the fourth geography.
Question
Rajesh Jain: Thanks for the follow up. I just want to understand on the raw material pricing, if the raw material prices increase then will you have to absorb the entire cost or some of it is passed through in your contracts?
Answer, rohit katyal
Rohit Katyal: In private sector it is full pass through. In the government sector, all projects have price variation clauses, which is commonly known as escalation clauses , w hich cover up for price increases , alright, whether it is material or labor. So, this is the protection which any contractor keeps when bidding for government projects and /or private sector projects. So, answering your question that we have adequate cover for the increase in prices, if the prices decrease obviously the client will take away that decrease. So, as I have repeated in the past, our orders are non-speculative in nature.
Questions about this call
- When was the Capacit'e Infraprojects Q2 FY25 earnings call transcript filed?
- Capacit'e Infraprojects filed the transcript with the exchange on 21 Nov 2024. This page is built from that transcript.
- What does this page list?
- 73 statements from the transcript across 12 topics, 54 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 27 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.