Capacit'e Infraprojects Q2 FY26 earnings call

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Standalone order book stood at 11,991 crores as on September 30, 2025, with the public sector accounting for 60% and the private sector for 40% of the total order book. EBITDA guidance is between 16.5% to 17.5%, excluding other income; EBITDA was 16.8% for the first half year, and the company expects to end the financial year at the higher end of the top bracket. The company is executing a 1,120 crores project for NBCC in Delhi NCR, monitored by Supreme Court. Total income for Q2 FY26 was 650 crores, up 24% from 523 crores in Q2 FY25. Entire 11,000 crores comes from this segment alone.

The numbers management gave

Results

  • Total income for Q2 FY26 was 650 crores, up 24% from 523 crores in Q2 FY25.
    Show source
    Total income for Q2 FY26 stood at 650 crores, up by 24% as compared to 523 crores in Q2 FY25.
  • EBITDA for Q2 FY26 was 108 crores, up 14% from 95 crores in Q2 FY25, and its EBITDA margin was 16.8%, within its guided range.
    Show source
    EBITDA for Q2 FY26 came in at 108 crores, up by 14% as compared to 95 crores in Q2 FY25.
  • EBITDA for Q2 FY26 was 89 crores, up 11% from 79 crores in Q2 FY25, and its EBIT margin was 13.6%.
    Show source
    EBITDA for Q2 FY26 stood at 89 crores, up by 11% compared to 79 crores in Q2 FY25.
  • PAT for Q2 FY26 was 51 crores, up 14% from 45 crores in Q2 FY25, and its PAT margin was 7.9%.
    Show source
    PAT for Q2 FY26 stood at 51 crores, up by 14% as compared to 45 crores in Q2 FY25.
  • The company recovered 8.69 crores from Neelkanth client in Q2, reducing the amount shown as a Q1 receivable; recoveries against the remaining balance of 55 crores will continue in the coming quarters.
    Show source
    Since then, it was realized in Q2 and therefore, that amount stands reduced by 8.69 crores.
  • Outstanding with CIDCO, M HADA and Municipal Corporation of Greater Mumbai (MCGM) is only for work done against certified bills for October 2025.
    Show source
    In these three clien ts, our outstanding is only for work done as against certified bill… I repeat, certified bill, work done for the month of October 2025.
Show 24 more statements

Results

  • The current outstanding on Capacit'e Infraprojects Limited's NBCC project in Delhi NCR is 40 crores, within the company's projections.
    Show source
    The current outstanding of that project is 40 crores, which also is well within the company's projections.
  • JJ Hospital average billing is 15 crores per month, and its receivables are a total 90-day outstanding.
    Show source
    So, you can say it is a total 90-day outstanding.
  • The company is billing approximately 20-plus crores per month on the Maldives project and is open to further EXIM Bank funded projects in Maldives.
    Show source
    We are billing approximately 20-plus crores per month, and therefore, we are open to looking at further EXIM Bank funded projects in Maldives as well.
  • The company booked interest of 47 -point-odd crores in the first half year.
    Show source
    The first half year interest, what we have booked is 47 -point-odd crores.
  • Interest booked for the full financial year last year was 93 crores.
    Show source
    And the interest booked for the full financial year last year was 93 crores.
  • Auditors mention a bad-debt figure of 55 crores, against which Capacit'e Infraprojects Limited is holding properties of 200 crores.
    Show source
    Rohit Katyal: So the auditors are mentioning 55 crores a figure, against that, we are holding properties of 200 crores.
  • The company is billing in excess of 10 crores per month for phase-I of the Signature Global project.
    Show source
    Capacit'e Infraprojects Limited November 15, 2025 Rohit Katyal: We have crossed 10% here.
  • Capacit'e's asset turn, against a gross asset value of 800 crores and a net block of 425, 430 crores, stands at 5.4, compared with 2, 2.5 previously.
    Show source
    Point number two is that whatever assets we were owning, gross value of the assets, 800 crores net block is 425, 430 crores, the asset turn, which was 2, 2.5, today stands at 5.4, and maybe for the full financial year, maybe close to 6.
  • Capacit'e aims to reduce debtor levels by nearly 45-days in the current financial year, of which 22-days has already been reduced, resulting in better cash profits for the company.
    Show source
    So all these parameters, whether it is asse t turn, whether our endeavor to reduce debtor levels by nearly 45 -days in the current financial year, of which 22 -days has already been reduced, these basically result in better cash profits for the company.
  • Net Assets Turnover (Core Assets) was 5.4x for H1FY26.
    Show source
    Net asset turnover of core assets stood at 5.4x for H1 FY26.

Money and capital

  • The company has released promoter pledge shares by nearly 30% over the last 18 months and expects this number to decline significantly further in the coming quarters.
    Show source
    Over the last 18 months, we have successfully released promoter pledge shares by nearly 30% and we expect this number to decline significantly further in the coming quarters.
  • Gross debt as on September 30, 2025 was 405 crores, down from 417 crores as on 31st March 2025; gross debt-to-equity was 0.22x and net debt-to-equity was 0.11x.
    Show source
    Gross debt as on September 30, 2025 stood at 405 crores, down from 417 crores as on 31st March 2025, with gross debt-to-equity at 0.22x and net debt-to-equity at 0.11x.
  • The company has sold properties worth 31 crores and expects the money to be realized within the current quarter.
    Show source
    Against the properties, currently, we have sold out properties worth 31 crores and we expect that money to be realized within the current quarter.
  • Total assessed limits within the consortium are Rs.1,420 crores for the period starting August of this financial year till July of 2026.
    Show source
    So, the total assessed limits within the consortium are Rs.1,420 crores for the period starting August of this financial year till July of 2026.
  • Unutilized bank guarantee limits or LC limits will be close to about Rs.300 crores or thereabouts, excluding State Bank of India's project-specific limits of close to about Rs.150 crores.
    Show source
    The unutilized bank guarantee limits or LC limits will be close to about Rs.300 crores or thereabouts.
  • Fund-based total assessed limit is Rs.240 crores, and it carries a cash balance of more than Rs.65-70 crores at any given point in time.
    Show source
    Rohit Katyal: So, fund-based total assessed limit is Rs.240 crores and we continue to carry a cash balance at any given point in time of more than Rs.65-70 crores.
  • Avendus debt of 100 crores stood at 57 crores as on September, and it will repay a further 7.14 crores in the current quarter; it has no plan at the moment to prepay that debt.
    Show source
    Rohit Katyal: We had a debt of 100 crores from Avendus, stands at 57 crores as on September, we will be further repaying 7.14 crores in the current quarter , at the moment, we have no plan of prepaying that.
  • The company has sold properties worth 14 crores and will sell a further 30 crores in the current quarter.
    Show source
    Of that, we have sold properties worth 14 crores already and further 30 crores will be sold in the current quarter.
  • The company will pay an average bank interest rate of 10.3% on working capital limits from the third quarter onwards.
    Show source
    So the entire banking limits, we have received reduction in interest rates, and from third quarter onwards, we are paying an average bank interest rate … I repeat, ba nk interest rate of 10.3% on working capital limit.
  • Commissions on bank guarantees and LCs have come down by about 75 basis points per annum; the reduction will be reflected partially in the current financial year and wholly in the next financial year.
    Show source
    Our commissions in respect to bank guarantees and LCs have also come down by about 75 basis points per annum.
  • Avendus loan, its only high-cost loan, carries an interest rate of 13.8%.
    Show source
    The only high-cost loan is of Avendus, which is at 13.8%.
  • The company has already repaid nearly 45% of its Avendus loan.
    Show source
    And we have already repaid nearly 45% of that loan.
  • Punjab and Sind and Jammu and Kashmir joined Capacit'e Infraprojects Limited's consortium, and Bank of Maharashtra and PNB sanctioned increased limits; the final sanction of State Bank of India is pending, although the overall financial tie-up has been completed.
    Show source
    The final sanction of State Bank of India is pending .
  • The company may utilize additional limits from State Bank of India for project-specific incremental requirements going forward.
    Show source
    Additional limits from State Bank of India may be utilized going forward for project -specific incremental requirements.

What it expects ahead

What management expects

  • EBITDA guidance is between 16.5% to 17.5%, excluding other income; EBITDA was 16.8% for the first half year, and the company expects to end the financial year at the higher end of the top bracket.
    Show source
    We have given a guidance for the full year of EBITDA between 16.5% to 17.5%.
  • The company expects 50% of the funds for JJ Hospital to be released sometime in December of the current quarter.
    Show source
    And number two, that we expect these funds to come up to be released, 50% of that sometime in December of the current quarter.
  • The company expects to build a further 300 crores in H2 on the first six CIDCO locations.
    Show source
    We expect to build further 300 crores in H2.
  • The company will bill 720 crores in the next financial year and complete the six CIDCO locations.
    Show source
    We will be billing 720 crores in the next financial year and we will be completing the six locations.
  • The MHADA SPV expects to cross 1,000 crores plus revenue in FY27.
    Show source
    Rohit Katyal: We do believe that we should cross 1,000 crores plus revenue in FY27 at the SPV level.
  • The company is targeting 725 for Quarter 3, has done 240 crores in October already, and is targeting 850 in March, taking the target to 2,810 for the current financial year; management said it was on target and expected to achieve this, while reducing debtor levels, improving the company’s financial matrix, and reducing gross debt.
    Show source
    And in March, we are targeting 850 and that takes us to 2,810.
Show 18 more statements

What management expects

  • Initial target was 3,500 crores; it expects to cross its target quite decently in the current financial year, which could mean certain additional revenues in the next financial year.
    Show source
    So, yes, we will cross our target quite decently in the current financial year, which could mean certain additional revenues happening in the next financial year.
  • The company has reduced debtor levels by 21 -days and is on track to reduce them further by 20 , 25 days in the remaining period of the current fiscal, against a roadmap for total reduction of 60-days.
    Show source
    We have reduced that debtor level by 21 -days already and we are well on track to reduce them further by 20 , 25 days in the remaining period of the current fiscal.
  • The company would book a total interest cost, including LC discounting charges, of 41.87 or 42 crores in the second half of the year.
    Show source
    The second half of the year, we would be booking an interest cost in totality, including LC discounting charges of 41.87 or 42 crores.
  • The company will pay a finance cost on a higher utilization of 85 crores in FY27, reducing it by 9 crores on an absolute basis.
    Show source
    Going forward in FY27, we will be paying a finance cost on a higher utilization of 85 crores, thereby reducing 9 crores on absolute basis.
  • The company expects close to 150 crores or thereabouts from the Signature Global project in the current financial year.
    Show source
    That is the current status of Signature Global, and we expect close to 150 crores or thereabouts in the current financial year.
  • The company is well on track to achieve its guidance of 2,800 crores.
    Show source
    Rohit Katyal: I have already guided for 2,800 crores and that is we are well on track to achieve that.
  • Capacit'e expects its asset turn to be close to 6 for the full financial year.
    Show source
    Point number two is that whatever assets we were owning, gross value of the assets, 800 crores net block is 425, 430 crores, the asset turn, which was 2, 2.5, today stands at 5.4, and maybe for the full financial year, maybe close to 6.
  • MHADA’s SPV expects revenue to nearly double in the next financial year, with actual structure construction expected to start from January, February of the current financial year.
    Show source
    So, we should look at starting the actual construction of the structure from January, February of the current financial year, thereby giving a strong indication of nearly doubling up the revenue at the LLP, at the SPV level in the next financial year , point number one.
  • Finance cost in absolute terms will be lower than last financial year, with increased top line and higher utilization of bank guarantees.
    Show source
    So now on an absolute basis, an increased top line, higher utilization of bank guarantees, the finance cost in absolute basis will be lower than next last financial year.
  • The company expects receivables for the properties already sold within November and December.
    Show source
    Already sold off, we are expecting receivables within November and December.
  • The company says its PAT is on the higher end of the range and does not expect that to change because it is based on orders already with the company.
    Show source
    The PAT also is on the higher end of the range.
  • The company expects its results to be similar to phase-I, slightly lower. Replaced by a later filing.
    Show source
    Rohit Katyal: We should be similar to what we did in phase-I, slightly lower.

Orders

  • Standalone order book stood at 11,991 crores as on September 30, 2025, with the public sector accounting for 60% and the private sector for 40% of the total order book.
    Show source
    Order book on standalone basis stood at 11,991 crores as on September 30, 2025 , p ublic sector accounting for 60%, while private sector for 40% as a total order book.
  • The company will continue executing 35% of all handed-over MHADA projects at the subcontractor capacity level; by March of the current fiscal, April of the next fiscal, the entire MHADA project will be available to be recognized under the order book, which is currently recognized at only 35%.
    Show source
    So, you can safely conclude that by March of the current fisca l, April of the next fiscal, the entire M HADA project will be available to be recognized under the order book, which currently has been recognized at only 35%.
  • Government project execution timelines have shortened from five years to three years and now to 30 months, and Capacit'e Infraprojects Limited said its last five orders, including Uptown, NBCC, and IIT Bombay, were upward of 600, 1,000, and 1,500 crores; it is more comfortable with order sizes upward of 500 crores, except for existing private-sector clients such as Godrej, Raymond, and Oberoi.
    Show source
    And therefore, we are more comfortable in that higher bracket upward of 500 crores until and unless it is a private sector existing client, where we cannot say no for obvious reasons, because we treat a client as an account and we would like to have repeat businesses, whether it is Godrej, whether it is Raymond, whether Oberoi, any other client.
  • EPC accounts for 55% to 56% of Capacit'e Infraprojects Limited's order book, with the remaining share being BOP, which comes ideally from the private sector and certain MCGM projects.
    Show source
    Rohit Katyal: So 55% to 56% is EPC, the remaining is BOP which comes from ideally private sector and certain MCGM projects.
  • The company says 56% to 57% of its order book is EPC and 43% is BOP.
    Show source
    So yes, answering your question, 56% to 57% is EPC, 43% is BOP.
  • Year-to-date bookings had reached ₹ 3,464 crores, nearing its full-year FY26 guidance of ₹ 3,500 crores.
    Show source
    On the order front, we have already achieved Rs.3,464 crores in bookings year-to-date, thereby nearly achieving our full-year guidance with several months still to go.

What it is building and selling

Projects and capacity

  • The company is executing a 1,120 crores project for NBCC in Delhi NCR, monitored by Supreme Court.
    Show source
    So, in Delhi NCR, we are executing a 1,120 crores project for NBCC, which is monitored by Supreme Court.
  • MHADA handed over 11 additional rehab towers, taking the total handed-over rehab towers to 25 out of 34, or nearly 75%; work is in full swing on 14 towers, two have been delivered, and five will be delivered in early December 2025.
    Show source
    Work on 14 towers is in full swing, out of which two towers have been delivered and five towers will be delivered in early December 2025.
  • For MHADA’s sale residential 320-meter tall buildings, the client gave the go-ahead to commence work on all 10 towers; IOA is in place for six towers, designing is complete, and piling has started.
    Show source
    On the sale residential 320-meter tall buildings, we have received, go ahead to commence work on all the 10 towers by the client.
  • MHADA’s commercial tower received the go-ahead in the current week; designs are being prepared, the land is more or less clear, and the company expects design completion in Q4 of the current financial year for the 66-floor tower.
    Show source
    But we do expect that the designing will be completed in Q4 of the current financial year because it is a 66-floor, highly modern commercial tower.
  • The first six CIDCO locations comprise close to 2,600 crores, including price variation.
    Show source
    Coming to CIDCO, including price variation, the first six locations comprise a total of close to 2,600 crores.
  • Two CIDCO locations are being handed over on 12th of December or thereabouts, and the remaining four locations will be handed over phase-wise in FY26 -27 and FY27-28.
    Show source
    The four locations phase-wise will be handed over in FY26 -27 and FY27-28.
Show 17 more statements

Projects and capacity

  • The seventh CIDCO location is expected to be received by the company in Q4 of the current fiscal, amounting to close to 2,000 crores of executable work plus price variation computed thereon.
    Show source
    That will amount to close to 2 ,000 crores of executable work plus price variation computed thereon.
  • The company has done about 70 crores of revenue in phase-I of the Signature Global project; phase-II will start from this current month, with revenue generation expected from next month onwards.
    Show source
    And CAPEX, the status of Signature Global which was in two phases; phase-I has already started, in phase-1, we have done about 70 crores of revenue, phase-2 we will start from this current month and we hope to start generating revenues from next month onwards.
  • Capacit'e has started construction on the tallest building, arguably in the country at the moment, at 320 meters, for Mala design-build and integrated joint venture with Tata Projects.
    Show source
    Rohit Katyal: So, we have started construction on the tallest building, arguably in the country at the moment, 320 meters, that is for Mala design-build and integrated joint venture with Tata Projects.
  • The company is using aluminum formwork for new projects, especially for NBCC and the Signature Global Project.
    Show source
    But, yes, with the new projects coming in, we do look at certain aluminum formwork, which is happening especially for NBCC and for Signature Global Project.

Demand and pricing

  • The company says all projects are now being requested on an EPC basis in the government sector, where BOP tenders will hardly be seen.
    Show source
    All projects now are being requested for on EPC basis.
  • The company considers Ahluwalia a competitor in government and with certain clients in the northern region; Ahluwalia also bids for government clients that Capacit'e Infraprojects Limited works for.
    Show source
    Rohit Katyal: Yes, we do consider Ahluwalia as our competitor in government and certain clients in the northern region.
  • The company says it has not faced BL Kashyap in competition for the last three, four years.
    Show source
    So BL Kashyap, I do not think that we have faced each other in competition for the last three, four years.

Segments

  • Entire 11,000 crores comes from this segment alone.
    Show source
    Our entire 11,000 crores comes from this segment alone.
  • Capacit'e is among the few Indian building construction companies that qualify for projects upward of 700, 800 or 1,000 crores.
    Show source
    But as I explained in my earlier answers, there are a very few Indian building construction companies who qualify for projects upward of 700, 800 or 1,000 crores, and fortunately, Capacit'e is one of them who qualify.
  • The company has restricted itself to Maharashtra and central government-funded projects because of issues with state finances across India.
    Show source
    And that is why we have restricted ourselves to Maharashtra and central government -funded projects.
  • The company will not bid for state government projects that are not funded.
    Show source
    So, we will not be bidding for any state government projects which are not funded.
  • The company will work on the government side only for clients with their own sources of funds, such as MCGM, MHADA, and CIDCO, and will actively participate in central government projects funded from the budget, such as UD Ministry projects executed through clients like NBCC and other central PSUs.
    Show source
    Rohit Katyal: So, on the government side, we will only work for clients who have their own sources of funds, like MCGM, MHADA, and CIDCO, for example.
  • The company says margins tend to be higher on larger EPC projects because it can engineer them better; for example, lower steel consumption can directly impact the bottom line.
    Show source
    The margin profile obviously on the larger projects which are EPC , tends to be higher because we get an opportunity to engineer the project in a better fashion , thereby, so just giving you an example, maybe the steel consumption could go down and therefore directly impact the bottom line.
  • Capacit'e is among the top three in the country in super high-rise construction.
    Show source
    So obviously, it is a documented fact that Capacit'e is among the top three in the country as far as super high-rise is concerned.

Deals and partners

  • CIDCO, M HADA and Municipal Corporation of Greater Mumbai (MCGM) are Capacit'e Infraprojects Limited's main clients in Maharashtra, and nearly 50% of its revenues going forward will come from these three clients.
    Show source
    Rohit Katyal: So, let me first clarif y that CIDCO, M HADA and (MCGM), Municipal Corporation of Greater Mumbai, these three are the main clients of the company in the State of Maharashtra, and nearly 50% of the revenues going forward will be coming from these three clients.
  • Raymond billing is upward of 22 crores per month.
    Show source
    But yes, the largest client at the moment, Raymond, we are billing upward of 22 crores per month.
  • Projects with CIDCO are fully funded, and suitable lines of credit from State Bank of India are available to CIDCO.
    Show source
    The projects are fully funded and suitable line of credits from State Bank of India are available with CIDCO, like other clients as well.

Risks, rules and outside factors

Outside factors

  • The company faces competition for qualified skilled workmen from UAE, Middle East, and Eastern Europe, and labor availability is a continuing challenge.
    Show source
    Labor availability is a challenge right now from L&T to any other construction company, because of the depth o f qualified skilled workmen in our country and we also face competition from UAE, Middle East, as well as Eastern Europe.

Everything else said on the call

Other

  • The company has a total labor strength in excess of 12,000 and would like to have nearly 14,000 to 15,000 workmen to achieve the desired results for the next financial year.
    Show source
    The total labor strength is in excess of 12,000.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Vansh Solanki: Hello, good morning. My first question is on the auditor's report. In the audit report, the auditors are showing - Rohit Katyal: You are not audible, please.

    Answer, rohit katyal

    I cannot hear you properly. Please repeat your question through a handset.

  2. Question

    Vansh Solanki: So, my question is on the auditor 's report that in Q1, auditor 's reported long outstanding trade receivables as 63 crores, which is reduced to around Quarter 2 for 55 crores, so, it was a reduction of 9 crores. So, this reduction is due to just the normal receivable or it is in other income or recovery or something like that?

    Answer, rohit katyal

    Rohit Katyal: No, we had a recovery from Neelkanth client, which was being shown in Q1 as receivable. Since then, it was realized in Q2 and therefore, that amount stands reduced by 8.69 crores. Such recoveries against those balance 55 crores will continue in the coming quarters as well. So, it was a slow-moving asset, which has now been recovered.

  3. Question

    Vansh Solanki: So, the recovery was against the return of amount, which we have guided of 65 crores of recovery throughout the financial year '26?

    Answer, rohit katyal

    Rohit Katyal: Absolutely. That includes slow-moving assets and realization of properties, which the company had received post-COVID period against these receivables . Against the properties, currently, we have sold out properties worth 31 crores and we expect that money to be realized within the current quarter.

  4. Question

    Vansh Solanki: Okay. So, just a follow-up question on this, that if my recovery is 8.69 crores or something, but why my other income only stood at 4 crores like there is a mismatch or something like that why it is not shown in my other income?

    Answer, rohit katyal

    Rohit Katyal: It is a pending debtor, which has been recovered, not a bad debt, which has come back. If we had written this off as bad debt, then on recovery, it would have appeared under other income. Hope I have answered your question. Capacit'e Infraprojects Limited November 15, 2025 Vansh Solanki: Okay.

  5. Question

    And just another, the 65 crores recovery will come through the other income or it will also just a reduction in debtor?

    Answer, rohit katyal

    Rohit Katyal: Some part will be in other income and most of it will be under debtors or sale of assets.

  6. Question

    Vansh Solanki: Okay. Just my second question is on gross margin and EBITDA, that if I see Y oY in Quarter 2 of FY25, my GP is around 35% and as of now, it is around 31%, so, it is around 500 bps of reduction in GP and also 200 bps reduction in EBITDA. So, is this because the new accounting policy changed?

    Answer, rohit katyal

    Rohit Katyal: Whatever accountancy policies were informed, now they are uniform and there is going to be no change. We have given a guidance for the full year of EBITDA between 16.5% to 17.5%. We expect the year to end at the higher trajectory, close to 17.5%. Quarter -on-quarter in the construction company should not be compared. However, having said that, whatever guidance, whether it is top line, bottom line or the EBITDA range is being adhered to and we will continue to be adhering to in the near future as well.

  7. Question

    Vansh Solanki: Okay. Thanks. And the last question on the share of JV & Associates that we have not recovered much from the JV & Associates in H1. So, there will be more profit from JV & Associates in H2, are we looking something like that?

    Answer, rohit katyal

    Rohit Katyal: So, as I explained in the last quarter as well, this is a five, six year project and these revenues on a stabilized manner will continue to come over the next five years. However, they will pick momentum in the next financial year. I am talking about the Mara JV, alright? So, apart from that, there will be uptick from the Bhandup Hospital Project JV and that will be reflected in the Quarter 4 of the current financial year.

  8. Question

    Nirvana Laha: Hi, sir. Good morning. Thanks for the opportunity and congrats on great execution in the monsoon quarter. Sir, my first question is on the fund and non-fund-based credit limits and the utilization. If you can give the numbers? Also, I think, sir, you were about to tie up with SBI to increase your non- fund-based credit limit, if I remember correctly. So, if you can update on this aspect? Capacit'e Infraprojects Limited November 15, 2025 Rohit Katyal: Yes.

    Answer, rohit katyal

    So, the total assessed limits within the consortium are Rs.1,420 crores for the period starting August of this financial year till July of 2026. The total limits have been tied up with new banks, Punjab and Sind, Jammu and Kashmir, joining the consortium. Increase in limits sanctioned by Bank of Maharashtra, PNB. The final sanction of State Bank of India is pending . But in the interim, the entire financial tie-up has been completed. Additional limits from State Bank of India may be utilized going forward for project -specific incremental requirements. So, answering your question, the financial tie-up has been completed.

    Answer, rohit katyal

    The unutilized bank guarantee limits or LC limits will be close to about Rs.300 crores or thereabouts. This does not include the project-specific limits of State Bank of India of close to about Rs.150 crores.

  9. Question

    Nirvana Laha: Okay. And, sir, on fund-based credit limit utilization, where do we stand currently?

    Answer, rohit katyal

    Rohit Katyal: So, fund-based total assessed limit is Rs.240 crores and we continue to carry a cash balance at any given point in time of more than Rs.65-70 crores.

  10. Question

    Nirvana Laha: Okay. Got it. My next question, sir, is on the receivables and contract assets that you have. If you can give a break-up on how much is from the Maharashtra government or government-funded agencies? And also, of the unexecuted order book, what is the same split, Maharashtra government and funded agency-related break-up? The reason I ask this question is b ecause many state governments have been under pressure in terms of their budget with respect to election promises. So, a lot of investors do worry about this. So, if you can clarify this, will be a good number to know?

    Answer, rohit katyal

    Rohit Katyal: So, let me first clarif y that CIDCO, M HADA and (MCGM), Municipal Corporation of Greater Mumbai, these three are the main clients of the company in the State of Maharashtra, and nearly 50% of the revenues going forward will be coming from these three clients. In these three clien ts, our outstanding is only for work done as against certified bill… I repeat, certified bill, work done for the month of October 2025. So, that is a very convenient and comfortable position. The projects are fully funded and suitable line of credits from State Bank of India are available with CIDCO, like other clients as well. Yes, you are right. There are issues with state finances across India. And that is why we have restricted ourselves to Maharashtra and central government -funded projects.

    Answer, rohit katyal

    So, in Delhi NCR, we are executing a 1,120 crores project for NBCC, which is monitored by Supreme Court. The current outstanding of that project is 40 crores, which also is well within the company's projections. Capacit'e Infraprojects Limited November 15, 2025 Having said that, the only project we face delays is PW D of Maharashtra , JJ Hospital. The total pending receivable is close to 45 crores. However, we have been successful in making presentations to the Medical Education Department and getting funds allocated as it is a hospital project and of national importance. So, we will not be bidding for any state government projects which are not funded. It has been our policy and strategy from the very beginning.

    Answer, rohit katyal

    We have suffered enough in the COVID period. We would not like to land ourselves into another known danger of bidding and then not receiving money from the projects which are not fully funded. So, this is the state of our receivables from government. At the moment, very comfortable. And I do not see why it should not be better in the coming quarters.

Show 22 more questions
  1. Question

    Nirvana Laha: Got it. Thanks for the details. Just a couple of follow-ups on that. The JJ Hospital is how many days the receivables is overdue?

    Answer, rohit katyal

    Rohit Katyal: So, JJ Hospital average billing is 15 crores per month. So, you can say it is a total 90-day outstanding. So, something is under 30 days, something is under 60 and something above 60, number one. And number two, that we expect these funds to come up to be released, 50% of that sometime in December of the current quarter.

  2. Question

    Parvez Qazi: Hi, good morning and thanks for taking my question. So, it would be great to get an update on the status of the M HADA and CIDCO projects and how do we see execution going ahead on these projects in the second half and also FY27? Thank you.

    Answer, rohit katyal

    Rohit Katyal: So, MHADA project, we have received additional 11 towers on the rehab side, taking the total handed over towers strength to earli er 14 plus 11 , now 25. The total towers on the rehab side are 34. So, nearly 75% or thereabouts of towers have been handed over. Work on 14 towers is in full swing, out of which two towers have been delivered and five towers will be delivered in early December 2025. On the sale residential 320-meter tall buildings, we have received, go ahead to commence work on all the 10 towers by the client. IOA for six towers is in place. Designing has been completed and piling has started.

    Answer, rohit katyal

    So, we should look at starting the actual construction of the structure from January, February of the current financial year, thereby giving a strong indication of nearly doubling up the revenue at the LLP, at the SPV level in the next financial year , point number one. The commercial tower, which was the only thing pending, we have just received go ahead in the current week and now the designs are being prepared and the land also is more or less clear. But we do expect that the designing will be completed in Q4 of the current financial year because it is a 66-floor, highly modern commercial tower. This is the status of MHADA. At the subcontractor capacity level, we will continue to execute 35% of all the handed over project. So, you can safely conclude that by March of the current fisca l, April of the next fiscal, the entire M HADA project will be available to be recognized under the order book, which currently has been recognized at only 35%. Coming to CIDCO, including price variation, the first six locations comprise a total of close to 2,600 crores.

    Answer, rohit katyal

    We expect to build further 300 crores in H2. We will be billing 720 crores in the next financial year and we will be completing the six locations. Phase-wise, two locations are being handed over on 12th of December or thereabouts. That will leave us with four locations. The four locations phase-wise will be handed over in FY26 -27 and FY27-28. The seventh location is expected to be received by the company in Q4 of the current fiscal. That will amount to close to 2 ,000 crores of executable work plus price variation computed thereon.

  3. Question

    Parvez Qazi: Just one follow-up question. When you said that for the M HADA project, we expect revenues to double in FY27 at the SPV level, what would be that number in FY27?

    Answer, rohit katyal

    Rohit Katyal: We do believe that we should cross 1,000 crores plus revenue in FY27 at the SPV level.

  4. Question

    Deepak Poddar: Thank you very much for this opportunity, sir. Sir, just wanted to understand first up, are we facing any kind of labor shortage issue which we have said in the past, maybe and it is getting resolved, so, any status on the labor problem?

    Answer, rohit katyal

    Rohit Katyal: So, let us call it a challenge. The challenge is across the industry. And we are doing whatever best possible, whether it is through facilities, whether it is through very good living conditions, whether through providing hygienic food to the workmen, you call it workmen, who work under v arious subcontractors in our company. The total labor strength is in excess of 12,000. Obviously, we are short, we would love to have nearly 14,000 to 15,000 workmen to achieve the desired results for the next financial year. And the company has a separate (LRD), Labor Resource Department, who is working 24/7 to achieve these targets. Having said that, we should not keep the issue under the carpet.

    Answer, rohit katyal

    Labor availability is a challenge right now from L&T to any other construction company, because of the depth o f qualified skilled workmen in our country and we also face competition from UAE, Middle East, as well as Eastern Europe. So, yes, while this will continue to be a challenge, we will keep ourselves skilling to whatever best possible, adopt new technologies , which warrant lower deployment of workmen to achieve our targets or surpass them.

  5. Question

    Deepak Poddar: Okay. So, if I have to do back-of-the-envelope calculation at 20% growth, ideally mean execution of 2,800 crores. So, in the first half, we have done close to around 1,200 crores. So, in the second half, 1,600 crores ideally means 800 crores kind of execution per quarter. That kind of execution we have not done in the past. So, is that something which we are looking at? And what gives us confidence that we can scale up?

    Answer, rohit katyal

    Rohit Katyal: So, we never did 650 crores in a mon soon season also earlier. We are targeting 725 for Quarter 3. We have done 240 crores in October already. So, we are well on target to achieve that. And in March, we are targeting 850 and that takes us to 2,810. And therefore, as we have achieved or surpassed all of our targets in the last two financial years, there is no reason why we will not do that in the current financial year as well, while reducing the debtor levels, while improving the financial matrix of the company and also reducing the gross debt.

  6. Question

    Deepak Poddar: Okay, great. That is pretty clear. And in terms of margins, I think earlier we had said 16.5% to 17.5% including other income, but in today's call, you mentioned excluding other income. So, I am just confused, this margin is excluding or including? Capacit'e Infraprojects Limited November 15, 2025 Rohit Katyal: It is excluding other income.

    Answer, rohit katyal

    The EBITDA guidance has been given between 16.5% to 17.5%. We are at 16.8% for the first half year and we should end the financial year at the higher end of the top bracket.

  7. Question

    Deepak Poddar: And full year target is what – 4,000 to 4,500 crores?

    Answer, rohit katyal

    Rohit Katyal: So, the initial target was 3,500 crores. Obviously, we cannot not take any orders for five months. So, yes, we will cross our target quite decently in the current financial year, which could mean certain additional revenues happening in the next financial year.

  8. Question

    Rajdeep Singh: Hi, good morning. Rohit ji, firstly, congratulations on phenomenal pace of execution given the lean seasonal quarter we have due to monsoon. My question was more qualitatively, Rohit ji, other than the receivables, what are the two, three critical aspects that you have outlined in terms of choosing or selection of projects?

    Answer, rohit katyal

    Rohit Katyal: So, on the government side, we will only work for clients who have their own sources of funds, like MCGM, MHADA, and CIDCO, for example. On the other governments, we are yet waiting and watching. We will be actively participating for central government projects which have funds allocated from the budget, like the UD Ministry, and so on and so forth. And these projects are typically getting executed through clients like NBCC and other central PSUs. So that is our focus from the government perspective. The Maldives project is going on very good. We are billing approximately 20-plus crores per month, and therefore, we are open to looking at further EXIM Bank funded projects in Maldives as well.

  9. Question

    Rajdeep Singh: Sure, sure. That is helpful. And sir, is there a number in mind between the public and private, or maybe you would prefer more larger size order with larger execution timeline or smaller size order?

    Answer, rohit katyal

    Rohit Katyal: So, execution timelines are getting squeezed as we move forward. So it is not in our hand . The execution timelines being given by the government earlier five years have come down to three years and now to 30 months. So okay, technology also has improved and that gives them the comfort to squeeze the timelines. Having said that, I do believe that if you look at our last five orders, right, whether it is Uptown, whether it is NBCC, whether it is IIT Bombay, all orders are upward of 600, 1,000, 1,500 crores. So the order ticket size has already increased. And therefore, we are more comfortable in that higher bracket upward of 500 crores until and unless it is a private sector existing client, where we cannot say no for obvious reasons, because we treat a client as an account and we would like to have repeat businesses, whether it is Godrej, whether it is Raymond, whether Oberoi, any other client.

  10. Question

    Gunit Singh: Sir, the benchmark, I mean, the revenues have increased only 20%.

    Answer, rohit katyal

    Rohit Katyal: So we have given a roadmap for reduction of debtors by total 60-days. We have reduced that debtor level by 21 -days already and we are well on track to reduce them further by 20 , 25 days in the remaining period of the current fiscal.

  11. Question

    Riddhesh Gandhi: So I think a couple of quarters ago, we were talking about reducing our interest and finance cost by paying down our high cost debt. It seems to be quite high. So just wanted to understand our plans for reducing our actually blended interest rate and finance costs?

    Answer, rohit katyal

    Rohit Katyal: So if you see, the first half year interest… give me a moment, please, let me open the sheet. The first half year interest, what we have booked is 47 -point-odd crores. All right? And the interest booked for the full financial year last year was 93 crores. The second half of the year, we would be booking an interest cost in totality, including LC discounting charges of 41.87 or 42 crores. So now on an absolute basis, an increased top line, higher utilization of bank guarantees, the finance cost in absolute basis will be lower than next last financial year. Going forward in FY27, we will be paying a finance cost on a higher utilization of 85 crores, thereby reducing 9 crores on absolute basis.

  12. Question

    Riddhesh Gandhi: Yes. So have we repaid the high-cost Avendus that we were holding or still have?

    Answer, rohit katyal

    Rohit Katyal: We had a debt of 100 crores from Avendus, stands at 57 crores as on September, we will be further repaying 7.14 crores in the current quarter , at the moment, we have no plan of prepaying that. Whatever we had to prepay, that is already done. And therefore, you are seeing that on an enhanced revenue, on an absolute basis, the finance cost will be lower in the last financial year and the current financial year.

  13. Question

    Vansh Solanki: Thank you for giving me the opportunity for asking the follow-up question. My only one question is that how much total return of pool we have as of now, bad debt, that is return of which we are telling about recovery.

    Answer, rohit katyal

    Rohit Katyal: So the auditors are mentioning 55 crores a figure, against that, we are holding properties of 200 crores. So that is all written off. Now, those properties which are on the boo ks, whether as capital WIP or as assets, the company is selling that off. Of that, we have sold properties worth 14 crores already and further 30 crores will be sold in the current quarter. Already sold off, we are expecting receivables within November and December. Vansh Solanki: Okay. Thank you.

    Answer, rohit katyal

    Rohit Katyal: So the first quarter is 65 crores approximately. And CAPEX, the status of Signature Global which was in two phases; phase-I has already started, in phase-1, we have done about 70 crores of revenue, phase-2 we will start from this current month and we hope to start generating revenues from next month onwards. That is the current status of Signature Global, and we expect close to 150 crores or thereabouts in the current financial year. Vasudev: Okay. And have we started booking profits for the phase-I? Capacit'e Infraprojects Limited November 15, 2025 Rohit Katyal: We have crossed 10% here.

  14. Question

    Ujwal Lal: Hi, sir. So what would be the current mix of EPC versus BOP in our order books and what kind of difference would be in the margin profile of EPC versus non-EPC?

    Answer, rohit katyal

    Rohit Katyal: So 55% to 56% is EPC, the remaining is BOP which comes from ideally private sector and certain MCGM projects. The margin profile obviously on the larger projects which are EPC , tends to be higher because we get an opportunity to engineer the project in a better fashion , thereby, so just giving you an example, maybe the steel consumption could go down and therefore directly impact the bottom line. So yes, answering your question, 56% to 57% is EPC, 43% is BOP. However, going forward, you will see increase in government. You hardly will see any BOP tenders. All projects now are being requested for on EPC basis. On the private sector side, it is not on EPC.

  15. Question

    Ujwal Lal: Yes, that helps. Who would be our top three clients on the private sector side and what would be the monthly billing rates over there currently, if you can share this?

    Answer, rohit katyal

    Rohit Katyal: I cannot share the monthly billing rates because I do not have it in front of me. But yes, the largest clients from balance order book would be Raymond, Godrej, Uptown, then you have Signature Global and then you will taper off like M3M, Hinduja would be maybe with 150 crores, Indus, the highest and IPS Society which we are m eeting, that would be 300 crores. So it is varied. And of Capacit'e Infraprojects Limited November 15, 2025 course, Indus again is a design-build project. So very difficult to give a revenue per month on that. But yes, the largest client at the moment, Raymond, we are billing upward of 22 crores per month.

  16. Question

    Ashish Jain: Hello! Good morning. I would like to know what interes t rate you are paying presently month-on- month to financial institute?

    Answer, rohit katyal

    Rohit Katyal: Okay. So the entire banking limits, we have received reduction in interest rates, and from third quarter onwards, we are paying an average bank interest rate … I repeat, ba nk interest rate of 10.3% on working capital limit. Our commissions in respect to bank guarantees and LCs have also come down by about 75 basis points per annum. So that will get reflected partially in the current financial year and wholly in the next financial year. The only high-cost loan is of Avendus, which is at 13.8%. And we have already repaid nearly 45% of that loan. And therefore, you will see a better impact on the overall interest rate going forward quarter-on-quarter.

  17. Question

    Ashish Jain: Okay. And have you any plan to diversify construction, like water management and all other things where there are bigger margins? When we see balance sheet of other companies, we see that there are somewhere around 30% in those balance sheets.

    Answer, rohit katyal

    Our entire 11,000 crores comes from this segment alone.

  18. Question

    Rudraksh Kalra: Fair enough. If you could shed a little more light on your order book execution and realizations of the coming two quarters of this year, that would be great as well?

    Answer, rohit katyal

    Rohit Katyal: I have already guided for 2,800 crores and that is we are well on track to achieve that. I hope NGT does not spoil the show in North India because we have various parameters in India to look into. But our guidance over the last six or seven quarters h ave been met or surpassed. So I do not see any reason why we should be doing that. The PAT also is on the higher end of the range. So we do not see any reason for that to change because these are based on orders already with the company.

  19. Question

    Prateek Bhandari: Yes. Hi, sir. Thanks for the opportunity. Just wanted one clarification on the Signature Global Project. You mentioned that we have already done the phase -I and clocked about 70 crores of revenue. So when you mentioned that you expect 150 crores of revenue, is it for the phase -II or is it in entirety for both the phases?

    Answer, rohit katyal

    Rohit Katyal: So I do not have the bifurcation, sir. You can put a question. I will tell Mr. Amit Porwal from Marathon to answer this. He will have to take the details from the Mac execution team and he will provide it. I have the overall figures. So obviously, phase -I is already underway. We are billing in excess of 10 crores per month.

  20. Question

    Prateek Bhandari: Yes.

    Answer, rohit katyal

    Rohit Katyal: We should be similar to what we did in phase-I, slightly lower. But, yes, with the new projects coming in, we do look at certain aluminum formwork, which is happening especially for NBCC and for Signature Global Project. Prateek Bhandari: Okay. Thank you. That answers.

  21. Question

    Gunit Singh: Hi, sir. So I would like to understand firstly, who are our main competitors -- do we consider Ahluwalia and BL Kashyap as our competitors?

    Answer, rohit katyal

    Rohit Katyal: Yes, we do consider Ahluwalia as our competitor in government and certain clients in the northern region. I do not see them too much in Mumbai MMR in the private sector. They do bid in the government sector for the clients we work for as well. And that is about it. So BL Kashyap, I do not think that we have faced each other in competition for the last three, four years. So yes, apart from this, our elder brother L&T will always be there, Shahpoorji will be there. BG Shirke on the private sector side in the government will be there.

    Answer, rohit katyal

    Virendra in north will also be there. But as I explained in my earlier answers, there are a very few Indian building construction companies who qualify for projects upward of 700, 800 or 1,000 crores, and fortunately, Capacit'e is one of them who qualify.

  22. Question

    Gunit Singh: All right, sir, got it. So in terms of our company itself, what do you think that we do differently or the kind of projects that we take differently as compared to some larger competitors, which contributes towards healthier margins?

    Answer, rohit katyal

    Rohit Katyal: So, we have started construction on the tallest building, arguably in the country at the moment, 320 meters, that is for Mala design-build and integrated joint venture with Tata Projects. So obviously, it is a documented fact that Capacit'e is among the top three in the country as far as super high-rise is concerned. Needless to mention that it is a highly technical subject, and therefore, super high -rises will always command premium over normal 30-40 floor buildings. That is point number one. Point number two is that whatever assets we were owning, gross value of the assets, 800 crores net block is 425, 430 crores, the asset turn, which was 2, 2.5, today stands at 5.4, and maybe for the full financial year, maybe close to 6. So all these parameters, whether it is asse t turn, whether our endeavor to reduce debtor levels by nearly 45 -days in the current financial year, of which 22 -days has already been reduced, these basically result in better cash profits for the company. When I say cash profit, you have to add back depreciation.

Questions about this call

When was the Capacit'e Infraprojects Q2 FY26 earnings call transcript filed?
Capacit'e Infraprojects filed the transcript with the exchange on 17 Nov 2025. This page is built from that transcript.
What does this page list?
79 statements from the transcript across 10 topics, 61 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 32 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.