Earnings call
Capacit'e Infraprojects Q3 FY26 earnings call: Capacit'e Infraprojects Limited's year-to-date bookings reached INR3,909 crores, exceeding its full year guidance of INR3,500 crores
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Year-to-date bookings reached INR3,909 crores, exceeding its full year guidance of INR3,500 crores. The company expects to further accelerate execution in Q4 FY '26 after execution momentum normalized and strengthened. The company is supposed to deliver 8 towers of cluster 1 during the full financial year FY '26; one tower has 278 tenements. Consolidated total income for 9 months FY '26 was INR1,930 crores, compared with INR1,702 crores for the corresponding 9-month period FY '25. Capacit’e Infraprojects Limited has INR1,390 crores in consortium limits tie-up, apart from project-specific bank guarantee limits for CIDCO and the MHADA BDD project.
The numbers management gave
Results
- Consolidated total income for 9 months FY '26 was INR1,930 crores, compared with INR1,702 crores for the corresponding 9-month period FY '25.
Show source
Consolidated performance highlights for 9 months FY '26 Total income for 9 months FY '26 stood at INR1,930 crores as compared to INR1,702 crores for the corresponding 9-month period FY '25.
- Consolidated EBITDA for 9 months FY '26 was INR318 crores, up by 8% from INR294 crores in 9 months FY '25.
Show source
EBITDA for 9 months FY '26 stood at INR318 crores, up by 8% as compared to INR294 crores in 9 months FY '25.
- Consolidated EBITDA margin for 9 months FY '26 was 16.6%.
Show source
EBITDA margins for 9 months FY '26 stood at 16.6% within our guided range.
- Consolidated EBIT for 9 months FY '26 was INR265 crores, up by 7% from INR248 crores in 9 months FY '25.
Show source
EBIT for 9 months FY '26 stood at INR265 crores, up by 7% as compared to INR248 crores in 9 months FY '25.
- Gross debt to equity was 0.25x and its net debt to equity was 0.12x in Q3 and 9-month FY '26.
Show source
Gross debt to equity stood at 0.25x, while net debt to equity at 0.12x.
- The company had recovered INR38 crores as on date and expected the remaining INR12 crores of its internally committed INR50 crores recovery to happen before March in the current financial year.
Show source
The recovery of INR38 crores as on date, not at the end of quarter has happened.
Show 24 more statements
Results
- Auditors analyzed the labour code impact as INR40 lakh, which was provided for in the current quarter financials.
Show source
The auditors have analyzed the total impact as INR40 lakh, which has been provided for in the current quarter fi nancials.
- Capacit’e Infraprojects Limited lost 1 month and at least INR100 crores of revenue.
Show source
Rohit Katyal: We have lost 1 month, we have lost INR100 crores at least.
- Capacit’e Infraprojects Limited’s direct personnel cost is pegged at INR40 lakhs, as examined by its internal and external auditors.
Show source
The direct cost of our own personnel has been examined by our auditors, internal and external, and that i s pegged at INR40 lakhs, which is practically negligible.
- Capacit’e Infraprojects Limited’s debtors stand at close to INR980 crores.
Show source
Rohit Katyal: The debtors stand at close to INR980 crores, if I'm not wrong.
- Capacit’e Infraprojects Limited’s contract assets stand at INR1,900 crores; compared with annualized turnover of even INR2,700 crores, contract assets as a percentage of the top line are reducing year-on-year.
Show source
Rohit Katyal: So the entire contract assets stand at INR1,900 crores.
- A-rated companies have contract assets of 76% of revenue, while Capacit’e Infraprojects Limited is currently at maybe 85% and expects to breach the 80% mark by Q4 of the current financial year.
Show source
We are currently at maybe 85%, and we are sure that we will breach that 80% mark by Q4 of the current financial year itself.
- Capacit’e Infraprojects Limited’s NOI was between 165 to 170 days currently, and the company sees a reduction by a few days by March.
Show source
NOI between 165 to 170 currently, but we do see a reduction by March by a few days.
- Capacit’e Infraprojects Limited’s provisions relate to expenses to be booked over the next 5 to 6, 7 quarters for the LSTK projects it is executing, to avoid surprises in company profitability in a quarter 4 or 5 quarters from now.
Show source
Provisions are those figures for which expenses will be booked over the next, let's say, 5 to 6, 7 quarters for the LSTK projects, which we are executing so that there are no surprises on the profitability of the company going at that particular quarter going down, let's say, 4 quarters or 5 quarters from now.
- Capacit’e Infraprojects Limited’s receivables under qualification fell from INR68 crores to INR54 crores over the last 5 quarters.
Show source
If you see the number from INR68 crores has fallen to INR54 crores, all right?
- Capacit’e Infraprojects Limited collected nearly INR50 crores in the current financial year and expects another INR50 crores of recovery in the next financial year.
Show source
It is now getting reflected by collection of nearly INR50 crores in the current financial year and which will continue in the next financial year by another recovery of INR50 crores and then the subsequent year.
- Capacit’e Infraprojects Limited’s gain on properties sold in the current year was 16.39%, to be recognized only on receipt of monies.
Show source
Capacit’e Infraprojects Limited February 12, 2026 Page 13 of 18 Only for your information, the properties sold in the current year, the company's gain has been 16.39%, which will be recognized only on receipt of monies.
- Capacit’e Infraprojects Limited’s EBITDA was 16.15% and stood at 16.65% as on today; the company said its full-year consol guidance would be maintained and standalone performance would improve.
Show source
As on today, we are standing on 16.65.
- Capacit’e Infraprojects Limited lost close to INR100 crores because of the extended monsoon in October and NGT issues in November and December; the amount could be INR70 crores or INR120 crores.
Show source
Rohit Katyal: I am saying that we have lost INR100 crores, close to INR100 crores.
- Capacit’e Infraprojects Limited’s collection profile over the first 9 months improved by 30% over the corresponding period last year.
Show source
The company's collection profile over the first 9 months has improved by 30% over the corresponding period last year.
- Capacit’e Infraprojects Limited’s cash inflow for the first 9 months was INR1,800 crores.
Show source
Rohit Katyal: So cash inflow for the first 9 months stood at INR1,800 crores.
- Capacit’e Infraprojects Limited reduced its working capital cycle by 20 days on its increasing revenue.
Show source
We have reduced by 20 days on our increasing revenue.
- EBIT margin stood at 13.7% in 9M FY26.
Show source
EBIT margin for 9 months FY '26 stood at 13.7%.
- PAT margin stood at 7.7% in 9M FY26.
Show source
PAT ma rgin for 9 months FY '26 stood at 7.7%.
- Net Assets Turnover (Core Assets) stood at 5.5x for 9MFY26 vs 5.2x for FY25.
Show source
Net assets turnover of core assets stood at 5.5x on an annualized basis for the first 9 months FY '26 versus 5.2x for FY '25.
- PAT stood at ₹ 149 crores in 9M FY26.
Show source
So this order was delivered on 9th of January.
Money and capital
- Capacit’e Infraprojects Limited has INR1,390 crores in consortium limits tie-up, apart from project-specific bank guarantee limits for CIDCO and the MHADA BDD project.
Show source
So INR1,390 crores i s in the consortium limits tie -up, which we just mentioned.
- Capacit’e Infraprojects Limited had INR175 crores of fixed deposits, on which an average interest rate of 5.5%, 6% can be used to calculate other income.
Show source
Rohit Katyal: See, we have INR175 crores of fixed deposit.
- Capacit’e Infraprojects Limited’s assets held for sale totalled close to INR60 crores.
Show source
So the total assets, which we are now holding for sale is close to INR60 crores.
- Capacit’e Infraprojects Limited had sold assets for INR50 crores, collected INR38 crores, and expected to collect the balance INR12 crores by March; INR50 crores of realization had been used to reduce creditors substantially on an absolute basis.
Show source
Balance, as I told, INR50 crores has already been sold out of which INR38 crores has been collected and balance INR12 crores will be collected by March.
What it expects ahead
What management expects
- The company expects to further accelerate execution in Q4 FY '26 after execution momentum normalized and strengthened.
Show source
Execution momentum has since normalized and strengthened, and we expect to further accelerate execution in Q4 FY '26.
- The company needs to grow at 18% to 20% next financial year on an expanded order book basis, as per its commitments to its client.
Show source
Next financial year on an expanded order book basis, we definitely need to grow at 18% to 20% as per the commitments to our client.
- Standalone run rate is expected to be in excess of INR18 crores to INR20 crores plus escalation thereon per month for the next financial year.
Show source
On a standalone basis, we do believe that our run rate will be in excess of INR18 crores to INR20 crores plus escalation thereon per month for the next financial year.
- CIDCO averaged about INR45 crores of revenue per month in the last quarter and expects momentum to increase in quarter 4; CIDCO expects to achieve a minimum INR60 crores per month of revenue, including escalation, on an average monthly basis over the next financial year.
Show source
And we shou ld be able to do a minimum INR60 crores per month revenue, including escalation or thereabouts over the next financial year on an average monthly basis.
- If work on Phase 2 starts, Signature Global is expected to generate a INR30 crores type of revenue per month over the whole of the next financial year.
Show source
And if that happens, you should be able to see a INR30 crores type of revenue per month generated from Signature Global over the whole of the next financial year.
- If location 7 is handed over in quarter 1, Capacit’e Infraprojects Limited’s revenue guidance will change upwards accordingly.
Show source
If location 7 is handed over in quarter 1, the revenue guidance will change accordingly upwards.
Show 24 more statements
What management expects
- Capacit’e Infraprojects Limited plans for contract assets to be 56% of the top line over the next 8 quarters, of which 1 quarter is already completed, meaning September of '27.
Show source
So the company plans, as I told in the last quarter conference call also that over the next 8 quarters, out of which 1 quarter is already completed, which means September of '27, we would like this figure to be at 56% of the top line.
- Capacit’e Infraprojects Limited submitted guidance to clients to deliver close to 18% revenue growth in FY '27, while its internal guidance would be higher.
Show source
Rohit Katyal: So FY '27 guidance, we are submitted to our clients to deliver close to 18% increase in revenue.
- Capacit’e Infraprojects Limited would like to bring working capital days back to the historic 90 days level over the next 2 to 2.5 years and is working toward that.
Show source
However, we would like to see this again at the historic 90 days level over the next 2 to 2.5 years, and we are working behind that.
- Capacit’e Infraprojects Limited expects to remain at current borrowing levels and repay close to INR70 crores in the next financial year; it expects a meaningful reduction in net debt-to-equity.
Show source
Rohit Katyal: We will be at the current levels because -- and we see a repayment of close to INR70 crores in the next financial year, right?
- Capacit’e Infraprojects Limited expects to realize the entire receivables over the next 8 quarters; it holds assets close to INR90 crores against the receivables, which are at various forums.
Show source
We expect that over the next 8 quarters, this entire money will be realized because we are h olding assets of close to INR90 crores against these receivables, which are at various forums.
- Capacit’e Infraprojects Limited expects to realize INR25 crores in the first quarter.
Show source
And within the first quarter, the company will realize this INR25 crores.
- Capacit’e Infraprojects Limited’s EBITDA guidance is 16.5% on a consol basis; standalone guidance was always 18% plus, and the company believes standalone guidance of 17.5% to 18.5% will not be impacted in the near future.
Show source
And we do believe -- we don't see any reason why that 17.5% to 18.5% on standalone will get impacted in the near future.
- Capacit’e Infraprojects Limited set itself 8 quarters starting September '25 to reduce its overall working capital cycle.
Show source
And now the only thing is to reduce the overall working capital cycle for which we have given ourselves 8 quarters starting September '25.
- Capacit’e Infraprojects Limited expects revenue of INR105 crores or INR110 crores or thereabouts to be added from its 35% share of TCC’s top line, with TCC revenue close to INR300 crores in quarter 4 of the current fiscal.
Show source
So 35% of that would be INR105 crores or INR110 crores or thereabouts.
- Capacit’e Infraprojects Limited will achieve INR900 crores of revenue for the full quarter Q4 '26 if the expected additional revenue is added.
Show source
If that happens, we will achieve the figure what you are saying, INR900 crores of revenue for the full quarter Q4 '26.
- Capacit’e Infraprojects Limited would like to reduce its working capital cycle by 7, 8, 10 days every quarter here on.
Show source
Number two, we would like to reduce that every quarter by 7, 8, 10 days here on.
- Capacit’e Infraprojects Limited would like to bring its working capital cycle down to 90 days over 8 quarters post September '25, the level the company historically enjoyed before the issues of COVID and the held-up money started.
Show source
As I told you, our focus is that over 8 quarters post September '25, we would like to bring it down to that 90 days level, which the company historically enjoyed before the issues of COVID and the held- up money started.
- Capacit’e Infraprojects Limited’s balance sheet size would reduce by INR200 crores on the core assets as holdup receivables are normalized.
Show source
So obviously, when our holdup receivables, whether it is lying in the asset side or whether it reduces the balance sheet size by INR200 crores on the core assets, definitely, all these figures will get normalized.
- Full-year guidance remains at 16.5% to 17.5%.
Show source
For the full year, this guidance is there for the current financial year, will continue for the next financial year.
- Capacit’e Infraprojects Limited will take projects in the commercial, retail, residential, institutional, healthcare or data spaces if it gets them at fair pricing.
Show source
So if we get projects at our fair pricing, we will definitely take them, whether it's in the commercial space, retail space, residential, institutional, healthcare or data.
Orders
- Year-to-date bookings reached INR3,909 crores, exceeding its full year guidance of INR3,500 crores.
Show source
On the order front, year -to-date bookings have reached INR3,909 crores, already exceeding our full year guidance of INR3,500 crores.
- Order book stood at INR13,188 crores as on 31st December 2025.
Show source
Order book stood at INR13,188 crores as on 31st December 2025.
- Capacit’e Infraprojects Limited has built close to INR150 crores on a certified basis for NBCC, excluding GST, against a contract value of INR1,120 crores; it will have a run rate of INR16 crores to INR17 crores until it receives the full financial tie-up from the client.
Show source
Number two, we will have a run rate of INR16 crores to INR17 crores till the time the full financial tie -up from the client is received.
- Capacit’e Infraprojects Limited has identified projects worth about INR14,000 crores to focus on and expects to increase its order book by another INR500 crores to INR1,000 crores over the next 45 days.
Show source
But we do believe that over the next 45 days, we will definitely increase our order book by another INR500 crores to INR1,000 crores.
- Capacit’e Infraprojects Limited’s outstanding order book position is INR3,770 crores, of which INR2,500 crores is attributed to location number 7, promised to be given to the company in quarter 1 of the next financial year, and the balance INR1,200 crores is for the first 6 locations against which it has given revenue guidance.
Show source
So the outstanding order book position in totality is INR3,770 crores, out of which INR2,500 crores is attributed to the location number 7, which has been promised to be delivered -- given to us in quarter 1 of the next financial year.
- Capacit’e Infraprojects Limited lost an INR1,000 crore bid on commercial pricing.
Show source
We just lost INR1,000 crore bid on commercial pricing.
- Public sector accounts for 61% while private sector accounts for 39% of Capacit'e Infraprojects Limited's total order book.
Show source
Order book stood at INR13,188 crores as on 31st December 2025.
- A suitable extension for the NBCC contract is proposed, and the client will give it to Capacit’e Infraprojects Limited.
Show source
Suitable extension is proposed and the client will give us that.
- Capacit’e Infraprojects Limited has already crossed its full year guidance. Replaced by a later filing.
Show source
We have already crossed our full year guidance.
What it is building and selling
Projects and capacity
- The company is supposed to deliver 8 towers of cluster 1 during the full financial year FY '26; one tower has 278 tenements.
Show source
Rohit Katyal: During the full financial year FY '26, we are supposed to deliver 8 towers of cluster 1.
- Signature Global is grossing close to INR20 crores per month; Phase 2 has yet to be handed over, and work is expected to start in Phase 2 in March, 1 month from now.
Show source
The work is expected to start in phase -- on Phase 2 in March, 1 month from now.
- Capacit’e Infraprojects Limited delivered 11 data centers to the Department of Telecommunication for the Indian defense over the last 2 years; 2 further data centers at Udhampur and Kolkata are pending delivery, which will happen by March or April of the current calendar year.
Show source
2 further of Udhampur and Kolkata are pending to be delivered, which will happen by March or April of the current calendar year.
- Capacit’e Infraprojects Limited’s core asset additions were INR78.82 crores as on date in the current financial year, with another INR15 crores to INR20 crores expected to be added, taking the expected total to about INR100 crores to INR105 crores.
Show source
So we should be at about INR100 crores to INR105 crores of core asset addition in the current financial year.
Risks, rules and outside factors
Risks and disputes
- Capacit’e Infraprojects Limited has INR25 crores worth of assets in Bangalore, and K-RERA instructed the developer to register and hand over the property within 60 days.
Show source
Out of this INR25 crores worth of assets are in Bangalore, we have just won the K-RERA matter, whereby the honourable NCLT, Karnataka RERA has -- sorry, not NCLT, K-RERA, Karnataka RERA has instructed the developer to register and hand over the property within 60 days.
- Capacit’e Infraprojects Limited does not see any disruption happening because of the new labour code.
Show source
So we do not see any disruption as such happening because of the new labour code.
Outside factors
- Capacit’e Infraprojects Limited will charge any increase of 0.5% or 1% in contract labour costs.
Show source
And if that increases by 0.5%, 1%, it will be charged.
- Low availability of labour has led Capacit’e Infraprojects Limited to pay a serious premium to labour contractors compared with 3 years ago.
Show source
As far as the sale pricing is concerned, it is a dynamics of the availability that alre ady is very low, and we are already paying a serious premium on what used to be paid to labour contractors, let's say, 3 years ago.
- The price variation clause means there will be no material impact on Capacit’e Infraprojects Limited.
Show source
Capacit’e Infraprojects Limited February 12, 2026 Page 6 of 18 Since we are covered by the price variation clause, there will be no material impact on the company.
Rules and policy
- 50% of Capacit’e Infraprojects Limited’s subcontractors already have their own PF number and are compliant with the labor laws.
Show source
Rohit Katyal: No, not at the moment in time because 50% of our subcontractors have their own PF number already, and they are already compliant with the labor laws.
Show 2 more statements
Rules and policy
- For contractors without provident fund registration, Capacit’e Infraprojects Limited recovers 4.5% towards administration cost and payment of PF on the contractor’s basic bill.
Show source
Coming back to contract labo ur, we have a policy, those who do not have a provident fund registration, the company recovers 4.5% towards administration cost and payment of PF on the basic bill of th e contractor.
- The minimum wages on which PF is applicable increased from INR15,000 to INR20,000, but the date has yet to be notified; assuming the increase takes effect, compliance on a quantum basis will increase and will be handled by software rather than human intervention.
Show source
So assuming that, that would go to INR20,000, the compliance on a quantum basis will increase, but that again will be done by the software and not by human intervention.
Everything else said on the call
What management stressed
- Capacit’e Infraprojects Limited will sacrifice some turnover to maintain financial discipline and prudence. Replaced by a later filing.
Show source
However, we will have to sacrifice some turnover to maintain financial discipline and prudence, number one.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Diwakar Rana: So my first question is on the MHADA projects. So how many towers have we delivered in first 9 months of this financial year?
Answer, rohit katyal
Rohit Katyal: During the full financial year FY '26, we are supposed to deliver 8 towers of cluster 1. 1 tower has 278 tenements. So 8 towers will have corresponding number of tenements. Out of these two towers have been already inaugurated by the client and the remaining 5 towers will be inaugurated over the next 2 months. Capacit’e Infraprojects Limited February 12, 2026 Page 4 of 18 Diwakar Rana: And sir, for the last financial year, what was the tower delivery for last financial year 2025?
Answer, rohit katyal
Rohit Katyal: There was no delivery in the financial year '24 or '25 because the actual work on ground started only in '23. So it takes 33 to 36 months clear from the date of clear handover from the client to deliver 1 tower as per the contract conditions.
Question
Diwakar Rana: So sir, in last financial year, we reported around INR14.5 crores from JV profits. And this year, it is only INR4.68 crores. So how much will you realize in Q4 of this financial year?
Answer, rohit katyal
Rohit Katyal: So I had clarified in Q3 of FY '25 that, that was the first quarter in which the JV company recognized its profits. And therefore, when it crossed the 10% revenue threshold, it recognized INR14.67 crores, which was our share. And therefore, it was reco gnized. Thereafter, consistently, we have been declaring a profit of close to INR1.7 crores to INR2 crores on a quarter basis. For the 9-month period, it stands at INR4.73 crores. Quarter 4 will see a similar number for a quarter. However, from next financial year, on the basis of expanded revenue, the profit addition from the JV to the limit of the share of Capacit'e will go up.
Question
Diwakar Rana: Correct.
Answer, rohit katyal
Rohit Katyal: Yes. We had committed internally to recover close to INR50 crores in the current financial year. The recovery of INR38 crores as on date, not at the end of quarter has happened. And the remaining INR12 crores will happen before March. We don't see any slippage on that.
Question
Diwakar Rana: INR50 crores. And sir, what will be the revenue guidance for this year and FY '27?
Answer, rohit katyal
Rohit Katyal: We have already given the guidance. We are well on track to do that. And let's keep something for surprises. Next financial year on an expanded order book basis, we definitely need to grow at 18% to 20% as per the commitments to our client. Over the past 2 years, we have been doing that quite well. And we hope to do that over the next 2, 3 years as well.
Question
Diwakar Rana: Can you achieve 20% growth this financial year?
Answer, rohit katyal
Rohit Katyal: You see that it will depend on how much revenue will come from the JV companies. At the moment, the revenue in Q3 fell short from the JV companies. Howe ver, we are very confident that we may be able to get better revenues from the JV companies in quarter 4 to achieve that.
Question
Diwakar Rana: One last question on this labor code, sir. So do you see any exceptional loss or provisioning in the next financial year or in Q4? Capacit’e Infraprojects Limited February 12, 2026 Page 5 of 18 Rohit Katyal: So this is applicable for basic salaries below 50%.
Answer, rohit katyal
In our case, 95% and more have basic salaries above 50% up to 60%. The auditors have analyzed the total impact as INR40 lakh, which has been provided for in the current quarter fi nancials. And as such, I do not see any major impact coming over the next financial year, if any.
Answer, rohit katyal
Rohit Katyal: So the revenue increase is directly proportional to the work fronts made available by the client. As on today, as I speak to you, work on 16 towers is going on, of which 3 to wers or 2 towers have already been delivered -- 3, I guess, I'm sorry, all right. And within the quarter, the client has committed to provide a total of 20 rehab towers to work simultaneously concurrently on. Similarly, work on 3 super high-rise sale residential towers, the piling work is in full flow at the project site. Given this and the associate infra works, we are confident that at the JV level, next financial year, the revenue should be between INR60 crores to INR70 crores per month. However, unfortunately, we are not getting any part of that revenue. We will definitely recognize the profit, okay?
Answer, rohit katyal
On a standalone basis, we do believe that our run rate will be in excess of INR18 crores to INR20 crores plus escalation thereon per month for the next financial year. Vasudev: That was helpful. And on the JV level, what would be our un -executable order book right now for the MHADA project?
Answer, rohit katyal
Rohit Katyal: At the JV level, adding the price increase plus the additional area plus the increase in height of sale residential towers and increase in area of the sale commercial tower, the revised order book should be in excess of INR15,000 crores at the TCC that is a JV company level. Vasudev: Sure, sir. And can you just give some update on our progress on the CI DCO, Signature Global and NBCC projects?
Answer, rohit katyal
Rohit Katyal: CIDCO is well on track. We have averaged about INR45 crores of revenue in the last quarter on a month-to-month basis, average monthly basis. We expect the momentum to increase in quarter 4. And we shou ld be able to do a minimum INR60 crores per month revenue, including escalation or thereabouts over the next financial year on an average monthly basis. Vasudev: Sure, sir. And on Signature and NBCC, any update on that?
Answer, rohit katyal
Rohit Katyal: Yes. NBCC, we have built close to INR150 crores on certified basis. We are -- this is excluding GST. The contract value is INR1,120 crores. So therefore, we have crossed the threshold limit of 10. That's number one. Number two, we will have a run rate of INR16 crores to INR17 crores till the time the full financial tie -up from the client is received.
Answer, rohit katyal
Suitable extension is proposed and the client will give us that. Capacit’e Infraprojects Limited February 12, 2026 Page 6 of 18 Since we are covered by the price variation clause, there will be no material impact on the company. However, we will have to sacrifice some turnover to maintain financial discipline and prudence, number one. Two, Signature Global is grossing close to INR20 crores per month. We have yet to be handed over Phase 2. The work is expected to start in phase -- on Phase 2 in March, 1 month from now. And if that happens, you should be able to see a INR30 crores type of revenue per month generated from Signature Global over the whole of the next financial year.
Question
Deepak Poddar: Correct. And is it possible to quantify what would be the revenue lost because of all this reason?
Answer, rohit katyal
Rohit Katyal: We have lost 1 month, we have lost INR100 crores at least.
Question
Deepak Poddar: Okay. Understood. Yes, fair point. And then just one last thing from my side. On the pipeline, you mentioned we do have a very healthy bid pipeline. So can you -- can you quantify what would be the bid pipeline for us? And what sort of conversion we are looking at?
Answer, rohit katyal
So there are many projects. If you total up, will go in thousands of crores. Our company at the moment has ident ified projects worth about INR14,000 crores, which will be focused on. And obviously, we do not need to do anything silly to shore up our order book. We have already crossed our full year guidance. But we do believe that over the next 45 days, we will definitely increase our order book by another INR500 crores to INR1,000 crores.
Question
Deepak Poddar: INR500 crores to INR1,000 crores incremental orders we do expect. I mean that would -- I mean, that would be much higher than what we had guided earlier, I think, in terms of order inflow guidance?
Answer, rohit katyal
Rohit Katyal: Give me a second, please. So the outstanding order book position in totality is INR3,770 crores, out of which INR2,500 crores is attributed to the location number 7, which has been promised to be delivered -- given to us in quarter 1 of the next financial year. And the balance INR1,200 crores is of the first 6 locations against which we have given you the revenue guidance. If location 7 is handed over in quarter 1, the revenue guidance will change accordingly upwards.
Question
Dhananjay Mishra: And secondly, apart from opportunity in the real estate segment, do you also see opportunity in data center because like you had announced to enter into data center and we have worked with them. So do you see Capacit'e as a contender to bid data center projects Udhampur this time?
Answer, rohit katyal
Rohit Katyal: We have delivered 11 data centers to the Department of Telecommunication for the Indian defense over the last 2 years. 2 further of Udhampur and Kolkata are pending to be delivered, which will happen by March or April of the current calendar year. And therefore, we do believe that we are qualified. We just lost INR1,000 crore bid on commercial pricing. But as I told you, the company does not intend to have any negative impact on its bottom line. So if we get projects at our fair pricing, we will definitely take them, whether it's in the commercial space, retail space, residential, institutional, healthcare or data.
Show 14 more questions
Question
Dhananjay Mishra: And lastly, on this working capital limit, we had INR1,390 crores, what is the breakup between fund based and non-fund based and what is the utilization, as of right now.
Answer, rohit katyal
Rohit Katyal: I will request you to kindly send a mail to our Investor Relations. The y will promptly send you the entire details because this would be a very long answer. INR1,390 crores is in the consortium. Apart from that, we have project -specific bank guarantee limits for CIDCO and for MHADA BDD project. All right? So INR1,390 crores i s in the consortium limits tie -up, which we just mentioned. The breakup, if you just drop in a small mail, it will be shared with you.
Question
Rajesh Kumar Rathi: My question, sir, regarding the new labo ur laws. Industry sources have told me that implementation of this law can increase the contract labo ur cost by 8% to 12% because of the PF and ESI, etcetera. Do you concur with that view?
Answer, rohit katyal
Rohit Katyal: No, not at the moment in time because 50% of our subcontractors have their own PF number already, and they are already compliant with the labor laws. The direct cost of our own personnel has been examined by our auditors, internal and external, and that i s pegged at INR40 lakhs, which is practically negligible. Coming back to contract labo ur, we have a policy, those who do not have a provident fund registration, the company recovers 4.5% towards administration cost and payment of PF on the basic bill of th e contractor. This is for those who do not have it. Now the exercise is going on what exact impact that would be. And if that increases by 0.5%, 1%, it will be charged. As far as the sale pricing is concerned, it is a dynamics of the availability that alre ady is very low, and we are already paying a serious premium on what used to be paid to labour contractors, let's say, 3 years ago.
Question
Rajesh Kumar Rathi: And will it cause some kind of production slowdown disruption because of regularization of everything regarding the contract labour?
Answer, rohit katyal
So we don't see anything major. Further, the minimum wages on which PF is applicable is INR15,000, now which has increased to INR20,000, but the date has yet to be notified. So assuming that, that would go to INR20,000, the compliance on a quantum basis will increase, but that again will be done by the software and not by human intervention. So we do not see any disruption as such happening because of the new labour code.
Answer, rohit katyal
Rohit Katyal: The debtors stand at close to INR980 crores, if I'm not wrong. On an annualized basis from where you got 1x, I'm not aware. Aniket: Receivables plus contract assets?
Answer, rohit katyal
Rohit Katyal: So the entire contract assets stand at INR1,900 crores. And if you compare that with the annualized turnover of even INR2,700 crores, you will see a reduction year -on-year as a percentage of contract assets to the top line. Now if you take any A -rated company, they have contract assets of 76% to the revenue. We are currently at maybe 85%, and we are sure that we will breach that 80% mark by Q4 of the current financial year itself. So the company plans, as I told in the last quarter conference call also that over the next 8 quarters, out of which 1 quarter is already completed, which means September of '27, we would like this figure to be at 56% of the top line. Aniket: Thank you for the clarity. And additionally, can you give some clarity on the typical conversion cycle?
Answer, rohit katyal
Rohit Katyal: So FY '27 guidance, we are submitted to our clients to deliver close to 18% increase in revenue. So let us maintain at that level at the moment in time, though internally, it would be higher. Capacit’e Infraprojects Limited February 12, 2026 Page 11 of 18 Second, the working capital days as on quarter ended 30/9/25 was 1 64 days, right, excluding retention. NOI between 165 to 170 currently, but we do see a reduction by March by a few days. However, we would like to see this again at the historic 90 days level over the next 2 to 2.5 years, and we are working behind that. Aniket: And about the margin, sir?
Answer, rohit katyal
Rohit Katyal: Sir, we have already guided for 16.5% to 17.5%. For a construction company, it's never to be monitored on a quarterly basis. For the full year, this guidance is there for the current financial year, will continue for the next financial year. Aniket: And my last question about borrowings. What kind of the total level of borrowings can we expect in FY '27, sir?
Answer, rohit katyal
Rohit Katyal: We will be at the current levels because -- and we see a repayment of close to INR70 crores in the next financial year, right? So on a net debt-to-equity basis, we definitely will see meaningful reduction.
Question
Rajesh Jain: Okay. And sir, last question is, what are your typical payable days for your suppliers? Capacit’e Infraprojects Limited February 12, 2026 Page 12 of 18 Rohit Katyal: So the total creditors without provisioning, I repeat without provisioning because creditors levels include a provisional figure of INR242 crores.
Answer, rohit katyal
If you reduce that, the total creditor level for goods would stand at INR440 crores. And if you divide that by a revenue of INR2,600 crores also, you will get a 45 days creditor level average, okay? Provisions are those figures for which expenses will be booked over the next, let's say, 5 to 6, 7 quarters for the LSTK projects, which we are executing so that there are no surprises on the profitability of the company going at that particular quarter going down, let's say, 4 quarters or 5 quarters from now. On the services part, our liability would stand at about INR60 crores to INR70 crores on an absolute basis. This does not account for the INR50 crores, INR60 crores of advances given to vendors for supply of steel and concrete, cement, et cetera.
Question
Rajesh Jain: And sir, last question is on the other income. So you have -- so I believe there is a note that you are carrying some receivables at INR54 crores plus INR11 crores. I think there is some note by the auditor there. So once all those receivables are realized by you, then what is the normal steady-state trajectory of other income we can expect on a full year basis?
Answer, rohit katyal
Rohit Katyal: See, we have INR175 crores of fixed deposit. So at an average interest rate of 5.5%, 6%, you can calculate what the other income would be. Whatever assets have been capitalized, that will be appearing under capital gains what if the company is making profitability. Now coming to your question of the qualification, which continues over the last 5 quarters. If you see the number from INR68 crores has fallen to INR54 crores, all right? We expect that over the next 8 quarters, this entire money will be realized because we are h olding assets of close to INR90 crores against these receivables, which are at various forums. Out of this INR25 crores worth of assets are in Bangalore, we have just won the K-RERA matter, whereby the honourable NCLT, Karnataka RERA has -- sorry, not NCLT, K-RERA, Karnataka RERA has instructed the developer to register and hand over the property within 60 days.
Answer, rohit katyal
So this order was delivered on 9th of January. And we do hope that sense will prevail on the erring developer. And within the first quarter, the company will realize this INR25 crores. So what I used to say about 4 or 5 years ago that no commercial interest of the company will be compromised with. It is now getting reflected by collection of nearly INR50 crores in the current financial year and which will continue in the next financial year by another recovery of INR50 crores and then the subsequent year. So though it has been a long fight, the company has been troubled, but we are well on track to recover every penny that the company owns from such erring developers.
Question
Rajesh Jain: And you will be able to recover your -- all your legal costs and all your costs pertaining to the recovery?
Answer, rohit katyal
Rohit Katyal: Sir, if I -- I do not know about that. But if my legal cost is approximately INR1 crore of in a year, I definitely cannot lose INR200 crores of the company's money by not paying INR1 crore. Capacit’e Infraprojects Limited February 12, 2026 Page 13 of 18 Only for your information, the properties sold in the current year, the company's gain has been 16.39%, which will be recognized only on receipt of monies.
Question
Vaibhav Shah: And sir, lastly, what capex are we targeting for '26 and '27, both from standalone and consol side?
Answer, rohit katyal
Rohit Katyal: So '27, I can only diverge once the budget meeting is held by the Board and the figure is approved. It would be incorrect for me to answer now. But definitely, after the Board meeting on 20th of March, we can disclose and discuss with you. As far as the current financial year, the total additions as on date have been INR78.82 crores in the core assets. And we look for -- we believe that another INR15 crores to INR20 crores will get added. So we should be at about INR100 crores to INR105 crores of core asset addition in the current financial year.
Question
So you expect to maintain that run rate or that 16.5% to 17.5% guidance is fair for standalone as well?
Answer, rohit katyal
Rohit Katyal: So our guidance of 16.5% on a consol basis, standalone was always 18% plus. And we do believe -- we don't see any reason why that 17.5% to 18.5% on standalone will get impacted in the near future.
Answer, rohit katyal
Rohit Katyal: The EBITDA was 16.15%, right. As on today, we are standing on 16.65. So if you compare quarter-on-quarter, it would not give you a right picture. On a whole year basis, you will see that company is maintaining what guidance it is giving on a consol basis a nd improving on the standalone basis. And we can only say that this will continue. Comparing on quarter -to-quarter, sometimes we don't get to recognize any revenue in a particular quarter and the revenue is not recognized, the corresponding profit cannot be recognized. So all these factors cannot be explained on a quarter-to-quarter basis.
Question
Rahul Kumar: Right. Understand that. But this INR100 crore figure you mentioned for this quarter or for year as a whole actually?
Answer, rohit katyal
Rohit Katyal: I am saying that we have lost INR100 crores, close to INR100 crores. In October, we lost something because of extended monsoon. You're well aware about that. Then we have lost in November and December due to NGT issues. So my -- someone asked me a question. So I gave an approximate answer. It could be INR70 crores, it could be INR120 crores.
Question
Rahul Kumar: Got it. And I think in the quarter 2 presentation, you had mentioned that the receivables you are on track to reduce by 45 days for this year, and I think you had reduced it by 20 days in the second -- till second quarter. So I mean, where do we stand as of now? And do we continue to stand by the target which you had given?
Answer, rohit katyal
Rohit Katyal: We are doing everything possible to do that, and I see no reason why we should achieve -- we should not achieve that. The company's collection profile over the first 9 months has improved by 30% over the corresponding period last year. So not only have we reduced our creditors substantially, which I explained in one of the prior questions, we have also managed to reduce the cost of materials because of the such better payment terms. And now the only thing is to reduce the overall working capital cycle for which we have given ourselves 8 quarters starting September '25.
Question
Rahul Kumar: INR1,900 crores. This was INR1,300 crores -- INR1,400 crores?
Answer, rohit katyal
Rohit Katyal: Excuse me, sir. When I say contract assets, I'm including debtors also in that 1,900. So only contract assets will be 1,200. And so y ou have -- because contract assets for me includes everything. If you ask me what is the debtors and what is the other part of contract assets, then the overall unbilled figure lying in WIP would be close to INR1,250 crores on consol basis. On a standalone basis, it would be lower. Capacit’e Infraprojects Limited February 12, 2026 Page 16 of 18 Moderator: We have the next question from the line of Vansh Solanki from RSPN Ventures.
Answer, rohit katyal
Rohit Katyal: Sir, I just explained this in my previous answer. I repeat it. That -- there is an additional revenue, whatever consolidated revenue of INR150 crores we do on a quarterly basis, that alone is not sufficient. We believe that our 35% share of the top line in TCC should be made available to us. If that additional comes because the revenue in TCC would be close to INR300 crores in quarter 4 of the current fiscal, okay? So 35% of that would be INR105 crores or INR110 crores or thereabouts. So we are expecting that revenue to get added.
Answer, rohit katyal
If that happens, we will achieve the figure what you are saying, INR900 crores of revenue for the full quarter Q4 '26.
Question
Pratik Singhania: No, no. I'm asking you the cash flow from the -- cash flow from operations. I wanted how much is the cash flow from operation before paying any taxes?
Answer, rohit katyal
Rohit Katyal: So cash inflow for the first 9 months stood at INR1,800 crores. I can provide you for the number for quarter 3 as well, but can you please tell me the cash flow for quarter 3? But for the first 9 months, it is INR1,800 crores.
Question
Pratik Singhania: And sir, second question is with respect to these assets, the data we have. How much of these assets are such that the building and the building is completed and people are staying there? And how much is under the construction stage?
Answer, rohit katyal
Rohit Katyal: I don't have those details ready with me. But please drop a mail. We have a complete list. So the total assets, which we are now holding for sale is close to INR60 crores. Balance, as I told, INR50 crores has already been sold out of which INR38 crores has been collected and balance INR12 crores will be collected by March. So I don't have a bifurcation of what is OC, what is virtually complete, what is under construction in front of me. But what we can say is that in totality, 52 -- sorry, INR50 crores will be the realization for that, which has been used to reduce our creditors substantially on an absolute basis.
Question
Pratik Singhania: And sir, with respect to the like 2 years guidance of this entire contract assets and the working capital cycle coming down, but any near-term benchmark or milestones that you would want to Capacit’e Infraprojects Limited February 12, 2026 Page 18 of 18 place for the company that how it will translate -- transcend into, say, FY '26 and H1 FY '27 and end of FY '27 as well?
Answer, rohit katyal
Rohit Katyal: I'm sure you all are monitoring. We have reduced by 20 days on our increasing revenue. Number one. Number two, we would like to reduce that every quarter by 7, 8, 10 days here on. As I told you, our focus is that over 8 quarters post September '25, we would like to bring it down to that 90 days level, which the company historically enjoyed before the issues of COVID and the held- up money started. So obviously, when our holdup receivables, whether it is lying in the asset side or whether it reduces the balance sheet size by INR200 crores on the core assets, definitely, all these figures will get normalized. And they are already getting normalized.
Questions about this call
- When was the Capacit'e Infraprojects Q3 FY26 earnings call transcript filed?
- Capacit'e Infraprojects filed the transcript with the exchange on 16 Feb 2026. This page is built from that transcript.
- What does this page list?
- 73 statements from the transcript across 9 topics, 54 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 24 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.