Garden Reach Shipbuilders & Engineers Q1 FY25 earnings call: Garden Reach Shipbuilders & Engineers Limited's order book stood at 25,231.29 crore as on 30th of June

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Order book stood at 25,231.29 crore as on 30th of June. The company expects RFPs for two Multi-purpose Vessels, with an approximate order value of around 1000-1200 crore. The first P17 Alpha Project ship had reached almost 75% physical progress of construction and was being readied for harbor and sea trials; the second ship had reached around 62% construction and the third around 50%. Portable Steel Bridges turnover increased from around 60 crore to 140 crore recently, and it had live MoUs with the Border Roads Organization, the National Highways Infrastructure Development Corporation and some State Public Works Department. Ship repair generated around 1% of Garden Reach Shipbuilders & Engineers Limited's revenue around two years back and had increased to almost 5% over the last two years.

The numbers management gave

Results

  • Portable Steel Bridges turnover increased from around 60 crore to 140 crore recently, and it had live MoUs with the Border Roads Organization, the National Highways Infrastructure Development Corporation and some State Public Works Department.
    Show source
    I'm happy to inform you that the turnover of course it is modest if you look at our overall turnover, the enhanced the turnover from around 60 crore to 140 crore recently and the tempo is being maintained and we have live MoUs with the Border Roads Organization, the National Highways Infrastructure Development Corporation and few of the State Public Works Department.
  • Revenue from operation was 1,754 crore in FY22, 2,561 crore in FY23 and 3,592 crore in FY24.
    Show source
    In FY22, our revenue from operation was 1,754 crore, in FY23 it was 2,561 crore, and in FY24 it was 3,592 crore.

What it expects ahead

What management expects

  • RFPs are likely to come from the Indian Coast Guard for six Next Generation Ocean Going Vessels and 18 Next Generation Fast Patrol Vessels.
    Show source
    In addition to this, RFPs from Indian Coast Guard are likely to come for six Next Generation Ocean Going Vessels and 18 Next Generation Fast Patrol Vessels.
  • RFPs for two multi-purpose vessels, five next generation survey vessels and 22 Water Jet FACs are expected in the first year, according to Garden Reach Shipbuilders & Engineers Limited.
    Show source
    In the first year, the RFP’s for multi-purpose vessels 2 and the next generation survey vessels 5 and 22 Water Jet FACs.
  • The company said P17 Bravo is on the Navy's prospective plan and the tender could be issued by mid of 2025, based on a very conservative estimate.
    Show source
    Now, when the project is likely to come, we very, very conservative estimate the header could be out maybe by mid of 2025.
  • The company said it will deliver growth between 25% and 30%.
    Show source
    Last time also I mentioned that we will deliver growth between 25 to 30%.
  • The company expects to maintain a PAT margin of 7.50% to 8% on a yearly basis, with marginal quarter-to-quarter fluctuations depending on project maturity.
    Show source
    The PAT margin will maintain a minimum of 7.50% to 8% on a yearly basis, we can assume there will be marginal fluctuations up or down a quarter to quarter depending upon the project maturity, but we'll maintain a PAT margin of a 7.50% to 8%.
  • The company expects RFPs for 22 Intercepted boats around 1,200 crore and 6 Next Generation Ocean Going Vessels around 2,000 crore to come out in the next one year; 22 Interceptor boats and six Next Generation OPVs are likely to come from the Coast Guard.
    Show source
    These three are likely to come from the Navy and from the Coast Guard are 22 Interceptor boats and 6 Next Generation OPVs, these are likely to come from the Coast Guard.
Show 37 more statements

What management expects

  • Expected future projects for Garden Reach Shipbuilders & Engineers Limited include Five Next Generation Survey Vessels, Twenty-one Water Jet FAC, Twelve Mine counter measure vessels, twenty-two intercept boats, P17 Bravo and the Landing Platform Dock.
    Show source
    Five Next Generation Survey Vessels, Twenty-one Water Jet FAC, Twelve Mine counter measure vessels, twenty-two intercept boats and of course, followed by the P17 Bravo and the Landing Platform Dock.
  • The company expects projects for which it signed contracts during the last three months to move as per schedule; pre-production, design and commercial activities were in progress.
    Show source
    As well as the new orders which we have for which we have signed a contract during the last three months, the pre-production activities, the design activities, commercial activities are currently in progress and we expect all these projects to move as per schedule.
  • The company expects contracts for RFPs where it has been declared L1 to be signed within the next three to six months, with contract negotiations in progress.
    Show source
    We expect these contracts to be signed within the next three to six months.
  • The company said that eight Next Generation Corvettes contracts are in prospect, with L1 taking five and L2 taking the balance; it described the probability factor as very high.
    Show source
    Plus, the NGC where we are also eagerly looking forward, there is 8 ships contracts with the L1 taking five and L2 taking so the probability factor is very very high.
  • The Navy and the Coast Guard are likely to issue RFPs over the next one to four years, according to Garden Reach Shipbuilders & Engineers Limited.
    Show source
    In addition to this, both the Navy and the Coast Guard are likely to come up with RFPs, I cannot fix a Page 8 of 17 time for that, but in my association, if you just split it into two parts, 1 short term in the next one year and 2nd is from the next one year to four years, that means a three-year period from 1st to 4th year.
  • The P17 Bravo and Mine Counter Measure Vessels (MCMV) are among the mid- to long-term opportunities over the first to fourth year, according to Garden Reach Shipbuilders & Engineers Limited.
    Show source
    Thereafter, from the first year to 4th year, the P17 Bravo, then the Mine Counter Measure Vessels (MCMV), it's a high value order, 12 vessels that are AON cost of around 32,000 crore.
  • The company expects the bid submission for the Next Generation Corvettes during this month; in the normal course, it takes around four months for the L1 to be declared, followed by another six to nine months for completion of contract in the most optimistic scenario. Garden Reach Shipbuilders & Engineers expects the Next Generation Corvette declaration in four months from the RFP and contract conclusion around six to nine months after the declaration.
    Show source
    We expect the bid submission during this month and from then in the normal course of events how the system works, it takes around four months for the L1 to be declared and from then the most optimistic scenario would be another six to nine months for completion of contract.
  • The company expects RFPs for two Multi-purpose Vessels, with an approximate order value of around 1000-1200 crore. Replaced by a later filing.
  • RFPs for 22 Interceptor boats and six Next Generation OPVs are likely to come from the Coast Guard, according to Garden Reach Shipbuilders & Engineers Limited. Replaced by a later filing.
  • The company expects the bid submission for the Next Generation Corvettes during this month; in the normal course, it takes around four months for the L1 to be declared, followed by another six to nine months for completion of contract in the most optimistic scenario. Replaced by a later filing.
  • The company intends to complete the Survey Vessel Large project in the coming one year, and a couple of Anti-Submarine Shallow Water Craft ships will be delivered this year. Replaced by a later filing.
  • The company expects the RFP for two LPDs. Replaced by a later filing.
    Show source
    In addition to that, we also expect the RFP for two LPDs.
  • The company expects the RFPs mentioned for the first-year-to-three-year bracket to come out during that period. Replaced by a later filing.
    Show source
    These are the RFP's that we expect to come out between the first year one to so that three-year bracket.

Orders

  • Order book stood at 25,231.29 crore as on 30th of June.
    Show source
    Coming to the order book position, our total order book stands at 25,231.29 crore as on 30th June 2024.
  • The company was constructing 18 warships for the Indian Navy: the P17 Alpha Project, 8 Anti-Submarine Shallow Water Crafts, 3 Survey Vessels Large and 4 Next Generation Ocean Going Patrol Vessels.
    Show source
    All these ships put together, we are constructing 18 warships for the Indian Navy.
  • The company was executing an Oceanographic Research Vessel project for the Ministry of Earth Sciences and four export projects: one ocean going tug, an advanced 1000 M3 Hopper Dredger, 3 Fast Patrol Boats and 4 Multipurpose Vessels.
    Show source
    In addition to these shipbuilding projects for the Navy, we are also executing a project for the Ministry of Earth Sciences - An Oceanographic Research Vessel and in addition, we are also executing four export projects.
  • 90% of Garden Reach Shipbuilders & Engineers Limited's order book came from the Shipbuilding segment.
    Show source
    90% of this comes from the Shipbuilding segment, the P17 Alpha, the remaining portion of the order book is 14,392 crore.
  • Anti-Submarine shallow water craft order book was approximately 4600 crore.
    Show source
    The Anti-Submarine shallow water craft of 4600 crore approximately.
  • Survey Vessel Large order book was 855 crore; the project was likely to finish within a year.
    Show source
    Survey Vessel Large 855 crore.
  • Next Generation Ocean Green Patrol Vessels order book was 3,183 crore.
    Show source
    The Next Generation Ocean Green Patrol Vessels is 3,183 crore.
  • Oceanographic Research Vessel for the Ministry of Earth Sciences had an order book of 800 crore. The oceanographic research vessel for the NCPOR, Ministry of Earth Sciences, has an order book of around ₹796 crore.
    Show source
    The Oceanographic Research Vessel for the Ministry of Earth Sciences is 800 crore.
  • Export orders for multipurpose vessels, the dredger and the ocean going tug were around 750 crore altogether.
    Show source
    The export orders i.e. the multipurpose vessels, the dredger and the ocean going tug, all put together around 750 crore.
  • The company had another order for around 200 to 230 crore worth on a Naval Surface Gun.
    Show source
    In addition to that, we also have another order for around 200 to 230 crore worth on a Naval Surface Gun.
  • Bangladesh orders together accounted for just about 1.2% of its order book, and their impact was described as insignificant.
    Show source
    The percentage of the Bangladesh orders both put together is just about 1.2%.
  • The Mine Counter Measure Vessels (MCMV) programme comprises 12 vessels with an AON cost of around 32,000 crore, according to Garden Reach Shipbuilders & Engineers Limited.
    Show source
    Thereafter, from the first year to 4th year, the P17 Bravo, then the Mine Counter Measure Vessels (MCMV), it's a high value order, 12 vessels that are AON cost of around 32,000 crore.
  • The P17A Alpha project order value was initially 19,293 crore and was enhanced to around 21,000 crore by the government considering cost fluctuations in developmental orders, including equipment being developed within India.
    Show source
    Now, that means the order value of P17 Alpha is 21,000 crore.
  • For the P17 Alpha order value of 21,000 crore, 85% is ship construction cost and 15% is for Base and Depot spares.
    Show source
    Of these, 21,000 crore, 15% of the order value comprises of Base and Depot spares i.e. 85% of this 21,000 crore is the ship construction cost and 15% is the Base and Depot spares.
  • For P-17 Alpha, around 5% of the 15% Base and Depot spares is assumed to be delivered before the ship is delivered to the Navy; the remaining around 10% is delivered over the next one or two years as per the Navy's requirement.
    Show source
    These 10% is delivered over the next one or two years, as per the Navy's requirement because some of them may not need right now.
  • The company has completed around 7,000 crore of the P-17 Alpha project order value of 21,000 crore and has around 14,392 crore left.
    Show source
    As I had mentioned, when we are discussing the other book, we are still left with around 14,392 crore.
  • Bangladesh projects represent 1.2% of order value; Garden Reach Shipbuilders & Engineers Limited said the projects are nearly two years from delivery and it does not see any impact on them, as production is taking place in India and delivery lead times are far away.
    Show source
    So, we don't see any impact on these projects.
  • The Next Generation Corvette project is valued at around 36,000 crore and is split between two shipyards, with one shipyard getting five ships and the second shipyard getting three ships; the Next Generation Corvette AON cost approved by the Defense Acquisition Council was 36,000 crore; around 22,000 crore is allocated to the L1 shipyard and around 13,500 crore for three ships to the L2 shipyard.
    Show source
    Now, as you are aware the Next Generation Corvette, I just mentioned earlier as an answer to one of the caller, the AON, that is the AON cost, which has been approved by the Defense Acquisition Council around 2 years back was 36,000 crore.
  • The company estimates the order value for two Multipurpose vessels at around 1000 to 1200 crore, five Next Generation Survey Vessels at around 3000 crore, and 22 Water Jet FACs at around 2,200 crore.
    Show source
    Now coming to the next two Multipurpose vessels, our assessment of the cost is around or likely to be around 1000 to 1200 crore, then five Next Generation Survey Vessels around 3000 crore could be the order value and 22 Water Jet FACs, the order value could to the tune of 2,200 crore.
  • The two LPDs are a high-value order around 25,000 to 30,000 crore.
    Show source
    It's around 25,000 to 30,000 crore, two weapons.
  • The Next Generation Fast Patrol Vessel project comprises 18 ships, with order values around ₹3500 to ₹4000 crore; the order value for 18 Next Generation Fast Patrol Vessels for the Coast Guard is likely to be around 4,000 crore.
    Show source
    Then for the Coast Guard, 18 Next Generation Fast Patrol Vessels, the order value is likely to be around 4,000 crore plus the P17 Bravo ships.
  • The company was declared L1 for an Acoustic Research Vessel project for the DRDO Naval Physiological and Oceanographic Laboratory, a coastal reference vessel for the Geological Survey of India, and two advanced hybrid service projects for the Government of West Bengal.
    Show source
    We have also been declared L1 for a project for the DRDO Naval Physiological and Oceanographic Laboratory for an Acoustic Research Vessel, for the Geological Survey of India to coastal reference vessel and for the Government of West Bengal, 2 projects for advanced hybrid service.
  • The Next Generation Corvette project is valued at around 36,000 crore and is split between two shipyards, with one shipyard getting five ships and the second shipyard getting three ships. Replaced by a later filing.
  • The Navy is taking 7 P17 Bravo ships, with an order value that could be around 70,000 crore. Replaced by a later filing.

What it is building and selling

Projects and capacity

  • The first P17 Alpha Project ship had reached almost 75% physical progress of construction and was being readied for harbor and sea trials; the second ship had reached around 62% construction and the third around 50%.
    Show source
    The first ship has touched almost 75% of physical progress of construction and the ship is currently being readied for harbor and sea trials.
  • The company expects to deliver the first P17 Alpha Project ship in the mid of the next calendar year and plans to deliver the last ship during the mid of the calendar year 2026.
    Show source
    Now, the first ship is expected to be delivered in the mid of the next calendar year and the last of the ship is planned to be delivered during the mid of the calendar year 2026.
  • The company delivered the first Survey Vessel Large ship in December, 2023; the second ship had completed all trials and was being readied for delivery, which the company intended during the end of this month.
    Show source
    Coming to the Survey Vessel Large Project, this is a four-ship project of which the first ship has already been delivered during the end of the last calendar year i.e. December, 2023, we delivered this ship.
  • The third Survey Vessel Large ship had reached almost 74% physical progress and was getting ready for trial, while the fourth had reached around 70% physical construction.
    Show source
    The third and Page 4 of 17 fourth ship, the third ship has reached almost 74% of physical progress and she's getting ready for trial and the fourth ship has passed around 70% of physical construction.
  • The company intends to complete the Survey Vessel Large project by delivering its balance 3 ships by the first quarter of FY26.
    Show source
    We intend completing this project that means delivery of the balance 3 ships, all the three ships by the first quarter of FY26.
  • The Anti-Submarine Shallow Water Craft project comprises 16 ships, with 8 being constructed by Garden Reach Shipbuilders & Engineers Limited and 8 by another PSU shipyard.
    Show source
    This is a 16 ship Project, 8 being constructed by GRSE and 8 by another PSU shipyard.
Show 13 more statements

Projects and capacity

  • Of Garden Reach Shipbuilders & Engineers Limited's 8 Anti-Submarine Shallow Water Craft ships, the first had undergone harbour trial, was getting ready for field trial and was expected to be delivered in another three months; it had reached around 90% physical progress of construction.
    Show source
    Of our 8 ships, the first ship has undergone the harbour trial and she is getting ready for the field trial and we expect to deliver this ship in another three months.
  • The second Anti-Submarine Shallow Water Craft ship had reached around 65% construction and the third around 55%.
    Show source
    The next ship has touched around 65%, the third shift around 55% and so on.
  • The company intends to complete its 8-ship Anti-Submarine Shallow Water Craft project by FY27.
    Show source
    As far as this project is concerned, we intend completing this project by FY27 that means delivery of all the 8 ships.
  • The company signed the Next Generation OPV contract during March last year; the first two ships had reached around 25% construction and production had started on the last two ships.
    Show source
    The progress is good and the first two ships have already touched around 25% of construction and we have already started production of the last two ships also.
  • The second P-17 Alpha ship is at around 62% construction and the third ship is at around 50%; Garden Reach Shipbuilders & Engineers Limited intends to deliver the second ship by February 2026 and the third by August or September 2026.
    Show source
    We intend delivering by February 2026 and third ship by the mid of the same year that means by on August, September 2026.
  • Garden Reach Shipbuilders & Engineers' stated shipbuilding capacity is concurrent construction of 20 platforms: 8 large and 12 small and medium.
    Show source
    Now our ship building capacity was stated, I repeat the stated ship building capacity is for concurrent construction of 20 platforms.
  • The company has initiated capacity enhancement and expects its shipbuilding capacity to increase from 20 to 24 ships by the end of this calendar year; it has 3 dedicated shipbuilding units, one of which has been completely revamped.
    Show source
    Considering that we are fully aware about the projects that are coming, we have already initiated the process of capacity enhancement and one of just for information we have 3 dedicated ship building units and one of our units has been completely revamped and by the end of this calendar year, I repeat by the end of this calendar year, our ship building capacity will enhance from 20 to 24 ships.
  • Garden Reach Shipbuilders & Engineers' shipbuilding capacity increased from 12 to 20 after a modification. Replaced by a later filing.

Segments

  • Ship repair generated around 1% of Garden Reach Shipbuilders & Engineers Limited's revenue around two years back and had increased to almost 5% over the last two years.
    Show source
    In case of ship repairs, we started in a very modest fashion around two years back and at the point of time around 1% or just about 1% of our revenue was being generated through ship repair and over the last two years we have enhanced it almost 5%.

Deals and partners

  • The company completed technical delivery of a fully electric ferry to the Government of West Bengal and expects formal takeover during the coming month; the ferry has a 150 passenger capacity, the largest within India.
    Show source
    So, we have done the technical delivery of the vessel to the Government of West Bengal and we expect the formal takeover during the coming month.
  • The company won two projects for the Government of West Bengal to construct 13 Advanced Hybrid Ferry.
    Show source
    Happy to inform you, that I had mentioned before that we had won two more projects for the Government of West Bengal for construction of 13 in number Advanced Hybrid Ferry.
  • The company concluded a contract with a European client (the German client) for four Multi-purpose Vessels, with an option to increase the quantity by another four; the total project could be for eight ships.
    Show source
    During our last interaction, I had stated that by our next meeting, that is today, I'll be able to share you the happy news of the contract which was then being negotiated, we have concluded a contract with the European client (the German client), for four multipurpose vessels.
  • The company concluded a contract with a European client (the German client) for four multipurpose vessels, with an option clause for four more vessels. Replaced by a later filing.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Amit Dixit: Yeah. Good afternoon, everyone, and thanks for the opportunity. I have 3 questions. My first question is on the order book that we have at the moment and if you can split it across the platforms that we are currently doing. That was the first question. The second one is that considering the current crisis in Bangladesh, I understand that we had two orders from Bangladesh also. So, do we expect some delay in execution or delay in payment and Bangladesh was one of the countries where in past also, we have supplied vessels. So, are we looking at a little bit of pause in ordering from that country? The third question is on next generation corvettes while you have highlighted that the

    Answer, cmde hari

    Cmde PR Hari: OK. Thank you. Thank you, Mr. Amit. Now, coming to the order book details. The order book as on 30th of June stands at 25,231.29 crore. I'll just give a breakup of this. 90% of this comes from the Shipbuilding segment, the P17 Alpha, the remaining portion of the order book is 14,392 crore.

    Answer, cmde hari

    That comes to almost 55 to 56% of the total order book. The Anti-Submarine shallow water craft of 4600 crore approximately. Survey Vessel Large 855 crore. This project is mentioned likely to finish within a year. The Next Generation Ocean Green Patrol Vessels is 3,183 crore. The Oceanographic Research Vessel for the Ministry of Earth Sciences is 800 crore. The export orders i.e. the multipurpose vessels, the dredger and the ocean going tug, all put together around 750 crore.

    Answer, cmde hari

    In addition to that, we also have another order for around 200 to 230 crore worth on a Naval Surface Gun. So, this gives you a broad breakdown of the order book. Now coming to the second point what you had mentioned about Bangladesh. See, I've given you an overall status of the order book. Order book total value is 24,250. The percentage of the Bangladesh orders both put together is just about 1.2%. So, any combination, the impact is insignificant, one.

    Answer, cmde hari

    Second, we do not see any issue unlike a normal manufacturing industry whether you place an order for a product and you get it within a day within a month within a week. Here, shipbuilding orders are long lead time activities, where depending upon the size of the platform, the delivery time project duration ranges from very very aggressive 18 months to 36 months and in some cases 60 months. We feel the current situation is a passing phase, as with every situation which has happened so far in the world, we don't see any impact on our project execution, but both the contracts have already been Page 7 of 17 concluded and right now the preparatory activities of production are enhanced. So, to answer your question in a nutshell, we don't see any impact with respect to the current situation on project execution. The Third Point you had asked about the Next Generation Corvettes. As I've mentioned, the RFP is out. We expect the bid submission during this month and from then in the normal course of events how the system works, it takes around four months for the L1 to be declared and from then the most optimistic scenario would be another six to nine months for completion of contract.

    Answer, cmde hari

    I presume I have answered all your queries you can just calculate and see where it falls with respect to the contract then. Thank you.

  2. Question

    Harshit Kapadia: Yeah, Hi. Thanks for the opportunity and good set of numbers. I think this has been your best quarter as far as Q1 is concerned. So just wanted to get your sense of how do you see this run rate of 1000 crore which you have achieved in Q1? Do you think this run rate is going to continue for the balance of the year, given that your order book has increased, that's the first question. Secondly, can you dwell a bit on the order pipeline apart from the Next Generation Corvette, any large order which you are sensing where discussions have started, maybe RFI or RFP can be launched in next two or three years? Any color would be helpful.

    Answer, cmde hari

    Cmde PR Hari: Thank you, Mr. Harshit. Thank you for your wishes regarding the Q1 results have been good and we feel that that's the good tempo for the full financial year. Now, if the figures are good, you had asked a specific question on maintaining the run rate. I had mentioned this earlier also in a lighter way. This is not a T20 match or even a one-day series. In case of shipbuilding, that's the point is I would like to it, it's like a test match at best so just we would like to maintain the run rate and considering the order book position and also the current state of projects where we are in a position for our major projects where the maturity is adequate for revenue generation, we feel will be able to maintain that tempo. That is as per our project execution strategy, I repeat and also the project current status, current maturity level and also the healthy order book that we are having.

    Answer, cmde hari

    Now, you are asking about the order pipeline. I had mentioned that we have been declared L1 among a couple of RFPs that the bid started opened recently. The contract negotiations are in progress. We expect these contracts to be signed within the next three to six months. Plus, the NGC where we are also eagerly looking forward, there is 8 ships contracts with the L1 taking five and L2 taking so the probability factor is very very high. In addition to this, both the Navy and the Coast Guard are likely to come up with RFPs, I cannot fix a Page 8 of 17 time for that, but in my association, if you just split it into two parts, 1 short term in the next one year and 2nd is from the next one year to four years, that means a three-year period from 1st to 4th year. In the first year, the RFP’s for multi-purpose vessels 2 and the next generation survey vessels 5 and 22 Water Jet FACs.

    Answer, cmde hari

    These three are likely to come from the Navy and from the Coast Guard are 22 Interceptor boats and 6 Next Generation OPVs, these are likely to come from the Coast Guard. Thereafter, from the first year to 4th year, the P17 Bravo, then the Mine Counter Measure Vessels (MCMV), it's a high value order, 12 vessels that are AON cost of around 32,000 crore. And the P-17 Bravo of course, you know it’s a high value transit. So that is the mid to long-term including the LPD, which maybe has been taking induction for the last 5 to 10 years.

  3. Question

    Harshit Kapadia: OK. Thank you. Thanks for this. I just don't, you know run rate has touched now 1,000 crore, but we're still margins are sub below 6% you know so you know any color you can give us that would be helpful. Will it be able to touch a double-digit margin if the run rate improves from here on?

    Answer, cmde hari

    Cmde PR Hari: See. I'll put a discussion. I have mentioned this and I need to reiterate that in ship building, the orders are from one on competitive bidding. The majority of our revenue comes from shipbuilding. Shipbuilding orders are won on competitive basis. We strive to maintain PAT margins of plus 7.5 to 8% and we have been maintaining these margins and we will continue maintaining these margins in future also. But you also must understand that when revenue will grow substantially in the coming years, certainly, it cannot be directly proportional to the margin increase we have to strike the balance but I can assure you from our perspective is that we will be able to maintain margins of similar kind that means 8% PAT margins in the coming quarters.

  4. Question

    Harshit Kapadia: Understood. Thank you and wish you all the best Sir.

    Answer, cmde hari

    Cmde PR Hari: Thank you. Mr. Venkatesh. I had explained about the shipbuilding cycle. So, there is a phase in ship building where the revenue recognition is right stage. So, in our position, we are exactly in that stage with respect to our max revenue generation strip i.e. the P17 Alpha. The second aspect that you brought out was that considering the execution of these projects by FY27 i.e. P17A Alpha by FY27, yes, the revenue generation will grow. Now, I will just highlight one aspect so that the we are all on the same page.

    Answer, cmde hari

    Now, when a shipbuilding order is given, the order values of the P17A Alpha project was initially 19,293 crore. After that I'm just giving an example so that you understand clearly. After that, the government enhanced the order value considering certain fluctuations from the developmental orders. Basically, some of the equipment are being developed within India. So, considering the fluctuations in cost, they enhance the order value to around 21,000 crore. Now, that means the order value of P17 Alpha is 21,000 crore. Of these, 21,000 crore, 15% of the order value comprises of Base and Depot spares i.e. 85% of this 21,000 crore is the ship construction cost and 15% is the Base and Depot spares.

    Answer, cmde hari

    Now, what are these Base and Depot spares? Base and Depot spares are spares which we order and then supply to the Navy for maintaining the ship throughout its life cycle. Some of these are required right from the first day that the ship is delivered, maybe if the defectors, or if any requirement comes so I assume or comes very, very conservative 5% of this 15% having been delivered before the ship is delivered to Navy. That leaves around 10%. These 10% is delivered over the next one or two years, as per the Navy's requirement because some of them may not need right now. In P-17 Alpha, out of this 21,000 crore, we have already completed around 7,000 crore. As I had mentioned, when we are discussing the other book, we are still left with around 14,392 crore.

    Answer, cmde hari

    Now of this 15% Base and Depot spares, if 5% we deliver at the time of when delivering of the ship still 10% would be remaining. That means around 1,500 crore out of the 14,392 crore will still remain for the next one year. Same is applicable for all the Naval Shipbuilding projects so what I'm trying to say when we deliver or complete the project with respect to delivery of ship, still a percentage given a ballpark of 10% remaining. Considering not be sending all these things when we are completing the project in FY27, there Page 10 of 17 will still be a financial year where our turnover will cross 6,000 crore it is pure arithmetic. I cannot pinpoint whether it is 5700 or 6200, but between now that is FY 25-26 and naturally FY27 also because the ship would be delivered during the year, these three years are going to be the peak years with FY26 most likely the highest in terms of revenue generation. Venkatesh: OK, Sir. Thank you very much, Sir.

  5. Question

    Kartik Bhatt: Yeah, Sir. Thanks for the opportunity. So, I missed the timeline that you mentioned for P17 Alpha 2nd and the 3rd ship.

    Answer, cmde hari

    Cmde PR Hari: Sure, the first Ship I’m sure you heard, the second ship P-17 Alpha also right now at around 62% construction and third ship around 50%. The second ship that's what you wanted to know. We intend delivering by February 2026 and third ship by the mid of the same year that means by on August, September 2026.

  6. Question

    Kartik Bhatt: OK, sure. And is there any further update on P-17 Bravo and when are we likely to have any further as to you know when it's likely to be.

    Answer, cmde hari

    Cmde PR Hari: First point is that P17 Bravo is definitely a project that is going to come because Navy wants to build more ships at the same time because they first built P-17 then now the P-17 Alpha and P-17 Bravo is very much on the anvil, from their prospective plan. Now, when the project is likely to come, we very, very conservative estimate the header could be out maybe by mid of 2025.

  7. Question

    Kartik Bhatt: Yeah, yeah. Over the next 10 months or so.

    Answer, cmde hari

    Cmde PR Hari: No, see I actually and I had actually elaborated the delivery timelines a bit earlier. You may have missed, I can just give you, I can just run you through that once again. Of these 18 platforms, which are the Naval orders which are high value orders. We intend completing the Survey Vessel Large project in the coming one year. And the Anti-Submarine Shallow Water Craft couple of ships will be delivering this year, but that apart the revenue generation will come from the P17 Alpha project, which is now at a stage where Page 11 of 17 maximum revenue generation takes place. Now, if you are asking me what will be the revenue generation during FY25, I'll just give you a background. In FY22, our revenue from operation was 1,754 crore, in FY23 it was 2,561 crore, and in FY24 it was 3,592 crore.

    Answer, cmde hari

    So, we maintain the similar trend. Last time also I mentioned that we will deliver growth between 25 to 30%.

  8. Question

    Kartik Bhatt: OK, sure. And Sir, I think regarding the Bangladesh project, I think there were couple of things that you mentioned, ocean going vessel and then few dredger. So, including all of those you're saying that the impact is less than 1% and then also it's more of a passing phase.

    Answer, cmde hari

    Cmde PR Hari: We feel it is a passing phase and the percentage of order value is just 1.2. Notwithstanding, that apart, as I mentioned right now, the preparatory activities that is once the production anyway is happening in India, we are immune to the conditions there and the lead times of delivery is far away. It is almost two years from now. So, we don't see any impact on these projects.

  9. Question

    Divyesh Shah: Sir, you have very nicely elaborated all your orders and schedules for projection. Sir, we as investors are very layman. So, my simple understanding is just now one answer to the previous question you have given a guidance of 25 to 30%. Our order book is suppose is to be precisely 25,000 crore. So, Sir, roughly in a value terms within next two years, how much value we will be executing you have every schedule in your hand. Month-wise, quarter-wise. So, how much we will complete by March 26? Combination of FY25 and FY26. So let us bifurcate into two parts of 25,000 crore. How much we will complete in first two years? Next immediate two years?

    Answer, cmde hari

    Cmde PR Hari: OK. Thank you. Now as far as the FY25 is concerned, I just give an indication to the previous call that we will be we are targeting, we're targeting around 25% of the current year. And we expect to maintain the similar tempo in the next year also. You must understand that it is due to the project as I mentioned earlier, the P17 Alpha is in a state where the revenue is coming in. So, if we are able to maintain a 25 to 30% of growth in the coming in the current year and the next year, you ourselves can assess where we'll be standing. And one more thing, when I have stated that we'll be completing the orders by FY27 i.e. for the orders which we were already executing.

    Answer, cmde hari

    We may also note that in the last few months, we have received orders, fresh orders. So naturally the fresh orders will be as per the project timelines. This Page 12 of 17 will definitely, I mean I understand the last of these projects will be in FY29. Some of that is some of the new projects, just to answer your question, yes Sir, 25 to 30% growth this year and the similar growth next year.

  10. Question

    Divyesh Shah: Sir, just to understand the maths, I am very weak in maths to understand the maths Sir, 25% of 4000 crore of last year comes to 5000 crore, roughly ± 5-10% and then above that 30% comes to 6500 crore. So, within next two years it comes down to be 11,500 crore. And remaining is and one statement you gave, the FY 26 will be the maximum value. So, I fail to understand how 25,000 crore will be executive in next 4 years?

    Answer, cmde hari

    Cmde PR Hari: We are now in FY25, the beginning of FY25. The 25,000 crore, I repeat again, the 25,000 crore comprised of earlier orders, the P17 Alpha project, the Naval projects and also the new projects that we have recently obtained. Many of these new projects will still cover. Second, to a previous call, I had explained that within the order book, a certain percentage for the Base and Depot spares of which, on a conservative basis around 10% will be provided to the customer after the ship is delivered, after the project is completed. If you remove the new orders i.e. if you remove the new orders which have recently come, the order book it will come to around 22,000- 23,000 crore. From that again you remove the 10% that at least the net will come to 20,000 crore, and of this 20,000 crore as exactly that based on my input but if you're getting a 25 to 30%, yes, around 11,500 crore will go in the coming year and the next year with just about 10,000 crore remaining in the next two years. So, it's a fair adjustment.

Show 5 more questions
  1. Question

    Divyesh Shah: Yes Sir. Very good. Excellent answer Sir. And same way, Sir, regarding the margin, I will put it into different ways, Sir. Our quarterly margins are not similar so on yearly basis, can you give a ballpark figure what should be on yearly basis our EBITDA margin should be how we can judge as a layman?

    Answer, cmde hari

    Cmde PR Hari: I will just go to the PAT margin because I always work on the PAT margin. The PAT margin will maintain a minimum of 7.50% to 8% on a yearly basis, we can assume there will be marginal fluctuations up or down a quarter to quarter depending upon the project maturity, but we'll maintain a PAT margin of a 7.50% to 8%. Thank you.

  2. Question

    Divyesh Shah: Thank you, Sir. Thank you.

    Answer, cmde hari

    Cmde PR Hari: Sure. Thank you. But you must also understand that what I'm going to indicate this based on our appreciation of and the inputs on the prospective plans of both maybe and the question. At this juncture, I'm keeping away what we are foreseeing outside the country on the commercial shipbuilding segment and for the other export activities. So, I'm just focusing on our acquisition of the Indian Navy and the Indian Coast Guard requirements. Now, as you are aware the Next Generation Corvette, I just mentioned earlier as an answer to one of the caller, the AON, that is the AON cost, which has been approved by the Defense Acquisition Council around 2 years back was 36,000 crore. This is split between two shipyards, L1 shipyard will get around 22,000 crore and the second shipyard, L2 shipyard, the three ships will get around 13,500 crore.

    Answer, cmde hari

    As I mentioned that the RFP is out, so we expect the one declaration four months from now and from then it will take around six months to nine months for the contract conclusion. Why I'm going into that many that much of details for this project because the FRP is already out. Now coming to the next two Multipurpose vessels, our assessment of the cost is around or likely to be around 1000 to 1200 crore, then five Next Generation Survey Vessels around 3000 crore could be the order value and 22 Water Jet FACs, the order value could to the tune of 2,200 crore. These three projects, we expect the RFP to come out in the next one year. This is for the Navy. So, the Coast Guard, we expect RFPs for 22 Intercepted boats around 1,200 crore. And 6 Next Generation Ocean Going Vessels around 2,000 crore, we expect these RFPs also to come out in the next one year.

    Answer, cmde hari

    Now after that, after the first year means one year to four years, we expect the RFP for 12 Mine Counter Measure Vessels. This is the High value project. This a big project the AON has already been accorded, the AON cost is around 32,000 crore. In addition to that, we also expect the RFP for two LPDs. This project has been going on for some time. This is where the Navy's wish list. It has moved up and down.

    Answer, cmde hari

    This is a high value order. It's around 25,000 to 30,000 crore, two weapons. Then for the Coast Guard, 18 Next Generation Fast Patrol Vessels, the order value is likely to be around 4,000 crore plus the P17 Bravo ships. There are 7 ships which the Navy is taking and the order value could be to the tune of around 70,000 crore. These are the RFP's that we expect to come out between the first year one to so that three-year bracket. I'm leaving out the next generation destroyers, the submarines and the indigenous aircraft carrier, if at all, as we do not have any clarity on these three projects. Does that answer your question to an extent?

    Answer, cmde hari

    Cmde PR Hari: See, we have been maintaining our 20,000 plus crore order book despite our revenue from operations. As you rightly said, it is moving up in a sharp manner for the last five, four to five years. The projects, that are on the anvil if the RFPs are out on time and if you succeed in the NGC project, yes, we'll be able to maintain all of the positions above the figure that I just taken. Gagan: And finally said, I mean, if from a capacity standpoint, you know, if you're, if you're able to wait successfully bid for some of these very large orders you know the mine counter measures, the next generation corvettes and the water jets and so on, the P 17B also. Our capacity standpoint, what do you envisage will be your requirements you know over the next three to five years. And what sort of investment will they entail?

    Answer, cmde hari

    Cmde PR Hari: A very interesting question. Yes, we are fully staffed of the current capacity and the need to enhance our capacity. Now our ship building capacity was stated, I repeat the stated ship building capacity is for concurrent construction of 20 platforms. There is 8 large and 12 small and medium. We have got up from a very modest figure of a 12 to 20 after a certain modification. Considering that we are fully aware about the projects that are coming, we have already initiated the process of capacity enhancement and one of just for information we have 3 dedicated ship building units and one of our units has been completely revamped and by the end of this calendar year, I repeat by the end of this calendar year, our ship building capacity will enhance from 20 to 24 ships. This is one part.

    Answer, cmde hari

    Second, going beyond the boundaries, physical boundaries of our shipyard, we have also taken over three dry docks long term lease spaces from the Kolkata Port Trust. We are exclusively using that facility for ship repairs because we didn't want to mix up ship repairs and ship building. In addition to that, when we had realized that concurrent construction will facilitate faster, let us say project progress, we have got to do public private partnership model. The two of the ships has been successfully implemented that so what I'm trying to say it's a three- pronged approach. One, Enhance the capacity within our physical boundaries from 20 to 24 by this calendar year and effectively utilize dry docks we have taken over, because see in case of shipbuilding, one of the major assets that we need is drydocks and building this. To utilize these drydocks which we have taken more from the Kolkata Port Trust and just to make the statement that we are also looking for other facilities wherein we can do concurrent construction in addition to the partnerships we have got with capable private players with spare capacity.

    Answer, cmde hari

    Just for information, we also have a tie up with shipyards, private shipyards on the Western front, so Page 15 of 17 should the situation come where all live partnership should the situation come where we get more export orders in a single route, executing them on the West Coast, so capacity wise we do not see a limitation now or in the coming years. Gagan: Right. Yeah. So, from a manpower perspective, I mean naval architects, welders and you know welding specialist. The current you know pipeline can is the manpower availability is adequate to meet these requirements or you feel you know they could be the competition for talent, which will lead to a cost spiral of any sort?

    Answer, cmde hari

    Cmde PR Hari: Yes, this is a very interesting question. Yes, absolutely right. There is a necessity to enhance the strength of skilled manpower such as for information, we have adopted a strategy wherein non-core jobs are outsourced, non-core means we retain the core strengthens certain activities like fabrication and complex block design activities or core commercial activities and shafting and so on. So, core strength we retain and non-core activities we outsource. But yes, the advantage of an outsourced model is that is scalable, but yes, there is a need and again we have experimented this with the P 17 Alpha project. We have experimented this with the commercial shipbuilding project that we are going to execute. The outsourced manpower for non-core activities absolutely scalable and we have got vendors working at our premises.

    Answer, cmde hari

    GRSE premises are separate geographically as Cochin, Chennai and Mumbai. So, manpower resources, human resources are not a problem. But yes, that's the point for us to make. Gagan: Thank you.

  3. Question

    Sunil Shah: Yeah. Thanks for the opportunity, Sir. I guess most of the questions have been very nicely and in detail explained. Sir, I have just one point to ask and check with you. Sir, in terms of the Government’s priority post the election mandate, which is, you know what is there in front of everybody. Has the priority taken some kind of a back seat for you know, announcing orders or Make in India stuff or, you know, is there any change pre-election and post elections if you could make us understand a little bit of that, is there any delays because earlier we were talking about the Next Generation Corvette orders or maybe you know it would fall in place by September or so. But now maybe

    Answer, cmde hari

    Thank you. It's a tricky question because I'm not a part of the Government, but I'll answer as clearly as possible. In our appreciations, there has been no letup in a pace. Since you specifically mentioned the next generation corvettes, as per the DAP from the time the AON is obtained to RFP, 30 months’ time is there and the Government has issued the tender ahead of that thirty month. It is moving very much on schedule. From our association, the Government initiative in enhancing the shipbuilding industry in India, we are eagerly waiting for the policy which the promised policy to come out soon. So, things are moving in the right direction and just to answer another question, another statement which we made as far as the Make in India efforts are concerned, 66 ships being built for the Indian Navy, 64 are being constructed by Indian shipyards and two of the shipyards, the orders were placed much earlier.

    Answer, cmde hari

    Two of the order the ships which were being constructed outside the orders were placed much earlier. In our appreciation, none of the orders for Indian Navy construction are going out of India. As far as Coast Guard is concerned, 100% of the ships being constructed for the Coast Guard are being constructed by Indian shipyards. So, in our appreciation there is no letup in pace, there is no change in policy. Things are moving as good and as fast as possible. Thank you. Yeah.

  4. Question

    Sunil Shah: Thank you, Sir. Just one point, Sir, even on the Project Bravo, which is the 70,000 crore order of which you know four and three would be the bifurcation even that could be on schedule. Just the only point I want to clarify.

    Answer, cmde hari

    Cmde PR Hari: All I can say is that there's a process involved in when you say schedule, there's a process involved in getting an approval by the Government. That's the DAP approval and thereafter the RFP issuance. That's why I had when I made an earlier comment, I had made a statement that in our appreciation during 2025. This is our appreciation. Now, the fact is that Navy want these vessels and I'm sure we'll put in our efforts to get the tender as fast as possible. Thank you.

  5. Question

    Sunil Shah: Thank you, Sir. Thank you so much.

    Answer, cmde hari

    Cmde PR Hari: Thank you, Aditya and thank you Gaurav from Concept IR for organizing this conference call. I would like to pay my sincere gratitude to all my analysts and investor friends who have taken time out of their busy schedules and listen to us today. If you have any further queries, I'd request all of you to please get in touch with us and we would be happy to address each one of your queries. Thank you once again. Wish you a very, very happy Independence Day. Jai Hind! Page 17 of 17 Moderator: Thank you.

Questions about this call

When was the Garden Reach Shipbuilders & Engineers Q1 FY25 earnings call transcript filed?
Garden Reach Shipbuilders & Engineers filed the transcript with the exchange on 22 Aug 2024. This page is built from that transcript.
What does this page list?
64 statements from the transcript across 6 topics, 50 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 15 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Garden Reach Shipbuilders & Engineers Q1 FY25 concall: Garden Reach Shipbuilders & Engineers Limited's order book stood at 25,231.29 crore as on 30th of June · DalalOS