Order book stood at ₹24,221.37 crore as on 30th September, 2024, comprising 12 projects with 43 platforms, including four export projects with 10 platforms. The Next Generation Corvette (NGC) project is an 8-ship project, with the L1 shipyard getting 5 ships and the L2 shipyard 3 ships; the expected value for the L1 shipyard's 5 ships is around ₹22,500 crore. The P17 Alpha Project is a 3 ships project; all 3 ships have been launched, and the first, second and third ships have around 83%, 65% and 50% physical progress, respectively. Revenue from operations for Q2 FY 25 increased from ₹898 crore to ₹1153 crore year on year, a growth of around 28%. The company says the indigenization content of its P17 Alpha projects is around 80% to 82%.

The numbers management gave

Results

  • Revenue from operations for Q2 FY 25 increased from ₹898 crore to ₹1153 crore year on year, a growth of around 28%.
    Show source
    As I had mentioned, the results have been very encouraging and if you are doing a year-on-year comparison, our revenue from operations have gone up from ₹898 crore to ₹1153 crore i.e. registering a growth of around 28%.
  • Total income for Q2 FY 25 increased from ₹969 crore to ₹1228 crore, a growth of 27%.
    Show source
    Total income from ₹ 969 crore to ₹1228, 27% growth, the E BITDA has gone up from ₹ 120 crore to ₹145 crore , 19% growth and the profit after tax registering a growth of 21% from ₹81 crore to ₹98 crore.
  • EBITDA for Q2 FY 25 increased from ₹120 crore to ₹145 crore, a growth of 19%.
    Show source
    Total income from ₹ 969 crore to ₹1228, 27% growth, the E BITDA has gone up from ₹ 120 crore to ₹145 crore , 19% growth and the profit after tax registering a growth of 21% from ₹81 crore to ₹98 crore.
  • Profit after tax for Q2 FY 25 increased from ₹81 crore to ₹98 crore, a growth of 21%.
    Show source
    Total income from ₹ 969 crore to ₹1228, 27% growth, the E BITDA has gone up from ₹ 120 crore to ₹145 crore , 19% growth and the profit after tax registering a growth of 21% from ₹81 crore to ₹98 crore.
  • The company registered 30% revenue growth within the first half of the year.
    Show source
    Coming to revenue growth, yes, we have registered 30% growt h within the first half of the year.

What it expects ahead

What management expects

  • The Next Generation Corvette (NGC) project is an 8-ship project, with the L1 shipyard getting 5 ships and the L2 shipyard 3 ships; the expected value for the L1 shipyard's 5 ships is around ₹22,500 crore.
    Show source
    T he L1 shipyard for 5 ships expected value is around ₹22,500 crore.
  • RFPs likely to come from the Navy and the Coast Guard include 5 Next Generation Survey Vessels Large, with an approximate project value of around ₹3000 crore.
    Show source
    The RPFs which are likely to come from the Navy and the Coast Guard in the near future are for the N ext Generation Survey Vessels Large i.e. 5 ships, approximate value of the project is around ₹ 3000 crore.
  • RFPs likely to come from the Navy and the Coast Guard include 6 Next Generation Ocean going Patrol Vessels and Offshore Patrol Vessels for Indian Coast Guard, with approximate order values of around ₹2000 plus crore.
    Show source
    Next Generation Ocean going Patrol Vessels, Offshore Patrol Vessels for Indian Coast Guard for 6 ship, approximate order values around ₹2000 plus crore.
  • The 2 Multi-Purpose Vessels for the Indian Navy have an approximate order value of ₹1200 crore; Garden Reach Shipbuilders & Engineers Limited expects RFPs for two Multi-purpose Vessels, with an approximate order value of around 1000-1200 crore.
    Show source
    Next Generation Fast Patrol Vessel is a big project 18 ships in numbers and the order values around ₹ 3500 to ₹4000 crore and 2 Multi- Purpose Vessels for the Indian Navy, approximate or the value of ₹1200 crore.
  • The company expects orders from the National Highway Infrastructure Development Corporation (NHIDCL) over the next two years for 75 portable steel bridges.
    Show source
    With this M OU, we expect the orders to come in from the N HIDCL over the next two years , 75 bridges the portable steel bridges.
  • The company expects to maintain shipbuilding margins of around 7.5% to 8% in future.
    Show source
    So, we as in stating this consistently, that in shipbuilding margins , optimal margins, where satisfactory efficiencies existing around 7.5 to 8% when we are in a competitive environment and we have been maintaining this kind of margin.
Show 22 more statements

What management expects

  • If the Next Generation Corvette contract is concluded by Q3 of FY26, revenue recognition will start two years later, around 2028, when Garden Reach Shipbuilders & Engineers Limited’s current order book is expected to be exhausted.
    Show source
    If you just take the timeline, logical realistic timelines now, if the bid is going to be open by December 2024 / January 2025 and let us put a very reasonable figure about 6 months for contract negotiations and 6-8 months that means by Q3 of F Y26, when the contract is concluded, the revenue recognition will start two years from then.
  • The company expects the indigenization content for the Next Generation Corvette to be between 85% and 90% tops.
    Show source
    But the other three projects which we have again at hovers in this direction, I am not at this moment assuming any major change in the indigenization content, even in NGC, I expect it to be in our appreciation that it will be between 85 to 90% tops.
  • The best-case assumption is that the P17 Bravo RFP could come out during mid 2026 calendar year; the P-17 Bravo RFP could come out by the end of calendar year 2025; from RFP to L1 determination could take around seven months to price bid opening, followed by six months for contract signing and two years for revenue recognition, which would start in 2029 if P-17 Bravo comes through.
    Show source
    The best-case scenario, the RFP could come out , only an assumptio n that the RFP could come out during mid 2026 calendar year.
  • The company is confident of maintaining a CAGR of around 25% during the four-year period from FY23 to FY27 and expects to exceed expectations while maintaining a similar growth rate.
    Show source
    Here , I would like to make a statement which I'm only reiterating what I had mentioned during our previous interactions that we had assured us the C AGR of around 25% during the four-year period from FY23 to FY27, we are confident of maintaining that kind of CAGR and only exceed your expectations maintaining similar growth rate.
  • The company expects the export trend to continue and expects export potential to be more towards European nations that need commercial processors in large numbers.
    Show source
    So, we expect this trend to continue and the export potential to be more towards the European nations who need commercial processors and that too in large numbers.
  • The company expects to maintain current margins considering its current order book and execution strategy.
    Show source
    But , all I can say at this moment considering our current order book and the execution strategy , the current margins, we'll be able to maintain.
  • The Next Generation Fast Patrol Vessel project comprises 18 ships, with order values around ₹3500 to ₹4000 crore. Replaced by a later filing.

Orders

  • Order book stood at ₹24,221.37 crore as on 30th September, 2024, comprising 12 projects with 43 platforms, including four export projects with 10 platforms.
    Show source
    Our order boo k as on 30 th September, 2024 stands t o ₹24,221.37 crore .
  • Contract with its German client covers 8 multipurpose vessels, with a total order value of around ₹890 crore; contracts for 5 vessels have been signed, and contracts for the next 3 ships will be signed by March 25.
    Show source
    Earlier they used to go to other nations for shipbuilding requirements, but now India is sought after destination and we have orders that mentioned that we have an order for already for five Multipurpose vessels which will go up to 8 by March 25 and so do the other shipyards.
  • Shipbuilding accounted for almost 99% of Garden Reach Shipbuilders & Engineers Limited's orders, exports were around 3.17% of orders within the shipbuilding segment, and domestic orders were 96%.
    Show source
    As I narrated before, our core business is domestic w arship building and the majority of o ur orders come from domestic w arship building and now since we have made a foray into the non - defence platform also, s till, the shipbuilding segment is almost 99 % of our orders and coming to exports within the shipbuilding segment, exports come to around 3.17% as of now and the domestic i.e. the domestic values of 96%.
  • Current order book is ₹24,221.37 crore and mostly comprises shipbuilding orders, which account for 99.4%.
    Show source
    And this again as I mentioned, comprises mostly of ship building orders which comes to 99.4%.
  • The balance order remaining for the P17 Alpha project is around ₹13,927 crore.
    Show source
    Now, coming to the order book breakup project wise, the P17 A lpha - the balance order remaining is around ₹ 13,927 c rore.
  • The Anti-Submarine Shallow Water Craft project has an order book of around ₹4,331 crore.
    Show source
    The Anti- Submarine Shallow Water Craft is around ₹ 4,331 crore .
  • The Survey Vessel Large project, with two ships remaining, has an order book of around ₹729 crore.
    Show source
    The Survey Vessel Large project with the two ships were remaining around ₹729 crore, the Next Generation Offshore Patrol Vessels is ₹3,023 crore.
  • The Next Generation Offshore Patrol Vessels project has an order book of ₹3,023 crore.
    Show source
    The Survey Vessel Large project with the two ships were remaining around ₹729 crore, the Next Generation Offshore Patrol Vessels is ₹3,023 crore.
  • The multipurpose vessels have an order book of around ₹520 crore.
    Show source
    The multipurpose vessels is around ₹520 crore, 2 export projects for the Government of Bangladesh around ₹314 crore and Naval Surface Gun project around ₹255 crore.
  • The 2 export projects for the Government of Bangladesh have an order book of around ₹314 crore.
    Show source
    The multipurpose vessels is around ₹520 crore, 2 export projects for the Government of Bangladesh around ₹314 crore and Naval Surface Gun project around ₹255 crore.
  • The Naval Surface Gun project has an order book of around ₹255 crore.
    Show source
    The multipurpose vessels is around ₹520 crore, 2 export projects for the Government of Bangladesh around ₹314 crore and Naval Surface Gun project around ₹255 crore.
  • The Navy is taking 7 P17 Bravo ships, with an order value that could be around 70,000 crore; the P17 Bravo project is a 7-ship project with an overall cost of around ₹70,000 crore; the L1 shipyard could get around ₹40,000 crore worth of orders, and the second shipyard would get 3 ships at the proportionate cost.
    Show source
    It's a 7-ship project and overall cost is around ₹70,000 crore, The L1 shipyard could get ₹40,000 crore worth order around and the second shipyard, 3 ships are the proportionate cost.
  • The company says it is executing 3 projects for Bangladesh with a total order value of just about ₹300 crore, which is about 1.5% of its total order book.
    Show source
    But if you see our Page 13 of 16 overall order book and compare it with the orders in hands of Bangladesh, the total order value from Bangladesh is just about ₹300 crore, which comes to about.
  • The oceanographic research vessel for the NCPOR, Ministry of Earth Sciences, has an order book of around ₹796 crore. Replaced by a later filing.
  • The Navy is taking 7 P17 Bravo ships, with an order value that could be around 70,000 crore. Replaced by a later filing.

What it is building and selling

Projects and capacity

  • The P17 Alpha Project is a 3 ships project; all 3 ships have been launched, and the first, second and third ships have around 83%, 65% and 50% physical progress, respectively.
    Show source
    Coming to the P17 Alpha Project; a 3 ships project, all 3 ships have been launched and 1st ship has already att ained around 83 % of physical progres s, the 2nd shi p Page 3 of 16 around 65% and the third ship around 50%.
  • The company expects to deliver the first P17 Alpha Project ship in August 2025 and intends to complete the project by August 2026.
    Show source
    The first ship is expected to be delivered during the mid of next year i.e. August 2025 and we intend completing this project by August 2026.
  • The Survey Vessel Large Project is a 4-ship project; Garden Reach Shipbuilders & Engineers Limited delivered the first ship on December 4th 2023 and the second ship on 8th of October 2024.
    Show source
    Coming to the Survey Vessel Large Project, this is the 4-ship project and we have already delivered 2 ships, the first ship was delivered last year. i.e. December 4th 2023, and the second ship was delivered on 8th of October 2024.
  • The third and fourth ships of the Survey Vessel Large Project have around 78% and 72% physical progress, respectively.
    Show source
    Now the next two ships are at adva nced stages of construction with the third sh ip of the projects, having completed around 78% physical progress and the 4th ship following closely at 72% physical progress .
  • The Anti-Submarine Shallow Water Craft Project is an 8 ship project; its first ship has completed the contractor sea trial and is getting ready for delivery.
    Show source
    It is a n 8 ship project and the first of these ships have already completed the contractor sea trial and it is now getting ready for delivery.
  • The company expects to deliver the first Anti-Submarine Shallow Water Craft ship during January, 2025.
    Show source
    We expect the s hip to be delivered during January, 2025.
Show 17 more statements

Projects and capacity

  • The second and third ships of the Anti-Submarine Shallow Water Craft Project have around 83% and 70% physical progress, respectively, and Garden Reach Shipbuilders & Engineers Limited intends to complete the project by October 2026.
    Show source
    So, from then the second ship is right now at around by 83% physical progress, the third ship is around 70% and so on and we intend completing this project by October 2026.
  • The company has commenced production of all 4 Next Generation Off-shore Patrol Vessel (NGOPV) ships and recently laid the keel of 2 ships.
    Show source
    We have commenced production of all the 4 ships and the keel of 2 of these ships have been laid very recently.
  • The first 2 Next Generation Off-shore Patrol Vessel (NGOPV) ships have around 35% physical progress and the last two ships have around 25% physical progress.
    Show source
    The first 2 ships have touched around 35% physical progress and the last two ships are around 25% physical progress .
  • Delivery of the Next Generation Off-shore Patrol Vessel (NGOPV) ships will be completed by 2028.
    Show source
    The delivery of these ships will be completed by 2028.
  • Projects for the State Government, the Federal Government Research Organizations and export projects will be completed by 2028 i.e. FY29, as per its current assessment.
    Show source
    As per our current assessment, all these projects will be completed by 2028 i.e. FY29.
  • Dry docks and building blocks were around 70 percentage of utilization.
    Show source
    Now, c ome to your question regarding the utilization , right now these dry dock s and building blocks that are around the 70 percentage of utili zation and again, I would like to highlight I think I mentioned during th e last earnings call that we, our state of shipbuilding capacity was for concurrent construction of 20 platforms, 20 warships, 8 large and 12 small and medium ship.
  • The company has identified a private sector partner and is confident of achieving indigenization of hovercraft by 2027.
    Show source
    So, we have put this as a challenge and we have identified a partner, private sector partner and we are confident of achieving the indigenization of the class by 2027.
  • The company targeted shipbuilding capacity for 28 ships concurrently and is at 24 ships now.
    Show source
    What we had targeted might mean GR SE's target would be to achieve a shipbuilding capacity for the 28 ships concurrently.
  • The company expects to deliver the first P17 Alpha Project ship in the mid of the next calendar year and plans to deliver the last ship during the mid of the calendar year 2026.
    Show source
    So as per th e AP timelines, the RFP will be promulgated in the due course.
  • The company intends to deliver the third and fourth ships of the Survey Vessel Large Project by the first quarter of FY26.
    Show source
    We intend delivering both these ships by the mid of next calendar year i.e. the first quarter of FY26.
  • The company has commenced capacity enhancement and infrastructure enhancement processes for shipbuilding. Replaced by a later filing.
    Show source
    Any experience by developing green energy vessels, again, we already developed an d received more orders and capacity enhancement i.e. capability already we have , capacity enhancement and infrastru cture enhancement process already commence.

Segments

  • The company says the indigenization content of its P17 Alpha projects is around 80% to 82%.
    Show source
    Now, for the P17 Alpha projects, the major project where certain equipment are of import nature, the indigenization content is around 80 to 82%.
  • The company says that shipbuilding provides most of its revenue, and that higher ship repair revenue could increase margins because ship repair margins are much better than shipbuilding margins.
    Show source
    Yes, we have ventured into ship repairs where the margins are much better so as and when our ship repair revenue goes up, the high margins of the ship repair segment, the lower relatively lower margins of s hipbuilding and we could see an increase.

Deals and partners

  • The company signed the contract for the 5th multipurpose vessel for a European client, and intends to sign contracts for 3 more vessels by March, 2025.
    Show source
    This option clause has been exercised and the 5th vessel contract has been signed and we intend signing the contract for 3 more vessels by March, 2025.
  • The company concluded a MoU with the National Highway Infrastructure Development Corporation (NHIDCL) for its portable steel bridges in the bailey bridges segment, expanding on its existing MoUs with the Border Roads Organization.
    Show source
    Now, this MoU, we had concluded for a product of ours in the bailey bridges segment, as your aware bailey bridges is one of our that is port able steel bridges is a strong business vertical that we have and we are a market leader in this segment and we already had live MoUs with the B order Roads Organization earlier, we have expanded this to NHIDCL.
  • The German client approached shipyards directly rather than through a conventional tendering and competitive process, assessed capacity, and obtained and negotiated a cost or bid; it had approached multiple shipyards before selecting Garden Reach Shipbuilders & Engineers Limited.
    Show source
    They approach Page 14 of 16 potential shipyards directly, do a capacity assessment and when they find a particular shipyard competent and capable of u ndertaking executing their project, they take a cost or bid from us when they negotiate with us, they have a method.
  • The company was declared L1 for two Coastal Research Vessels for the Geological Survey of India, and price negotiations are in progress. Replaced by a later filing.

Risks, rules and outside factors

Risks and disputes

  • The company says there are no supply chain issues at this juncture and no impact on supply chain as of now.
    Show source
    Coming to the supply chain impact on shipbuild ing, there was a time in the post COVID phase, not definitely during the COVID phase and post COVID phase there was an issue with the supply chain, but those issues have been fully tied over and at this juncture, w e do not have any supply chain issues.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Riffat Fatma: Cost of materials. Page 5 of 16 Cmde PR Hari: Yes, definitely that cost has gone up because the cos t is directly dependent on the project maturity pace with what I'm trying to convey is that in the initial stages of the project, the material cost would be less and as the projects mature, the material cost automatically goes up.

    Answer, cmde hari

    This in turn gets translated into the value of production. Now, just to give you an example, in a conventional warship composition in terms of value, the material cost is from 65 % to 70% in the initial change of project, when the basic hull construction and the design and the comm ercial activities are in progress , the material input is very very less when the project reaches the maturity stage between 40% to 60%, that is of physical progress then the material input goes up and therefore the cost. So, it is a natural phenomenon in our shipbuilding cycle. Thank you.

  2. Question

    Riffat Fatma: OK, that answers my question. Thank you.

    Answer, cmde hari

    Cmde PR Hari: OK. Third question is on our MOU with NHA, how is it going to benefit? OK, I'll answer. Your first question; the dry docks and building birth are the key assets that any shi pbuilding industry is required and the Garden Reach shipbuilders have got adequate facilities. So, you may be aware that they've got 3 dedicated ship building units, all in Kolkata and in addition, we have also taken over a facility from the Kolkata port i.e., the Syama Prasad Mookerjee Port which comprises of three more dry do cks. So, we are good with the dry docks. Now, c ome to your question regarding the utilization , right now these dry dock s and building blocks that are around the 70 percentage of utili zation and again, I would like to highlight I think I mentioned during th e last earnings call that we, our state of shipbuilding capacity was for concurrent construction of 20 platforms, 20 warships, 8 large and 12 small and medium ship.

    Answer, cmde hari

    What we had done w as considering the orders that we currently have and also the orders on t he anvil, in addition to taking a three drydocks on long term lease from this Syama Prasad Mookerjee Port, we had also revitalized some of the existing facilities that we have. So, with this initiative, we could augment our Page 6 of 16 shipbuilding capacity from 20 to 24 and our current capacity is the construction of 24 warships concurrently i.e. 8 large and 16 medium. So, to put in a natural, our capacity utilization with respect to dry docks an d building blocks is about 70% as of now. Your second question was on the c ountry which is importing and our export potential is very high. Most of the European nation that is Germany, Netherlands and so on, they are now looking at India as a commercial sh ipbuilding hub. The results are very evident that almost all the Indian shipyards have orders from these clients. Earlier they used to go to other nations for shipbuilding requirements, but now India is sought after destination and we have orders that mentioned that we have an order for already for five Multipurpose vessels which will go up to 8 by March 25 and so do the other shipyards.

    Answer, cmde hari

    So, we expect this trend to continue and the export potential to be more towards the European nations who need commercial processors and that too in large numbers. Coming to your third question was the significance of the MOU with National highways, can I say the N ational Highway Infrastructure Development Corporation. Now, this MoU, we had concluded for a product of ours in the bailey bridges segment, as your aware bailey bridges is one of our that is port able steel bridges is a strong business vertical that we have and we are a market leader in this segment and we already had live MoUs with the B order Roads Organization earlier, we have expanded this to NHIDCL. With this M OU, we expect the orders to come in from the N HIDCL over the next two years , 75 bridges the portable steel bridges. I hope, I've addressed all your 3 queries. Karan: Yes, yes, thank you very much.

    Answer, cmde hari

    Cmde PR Hari: Sure. I will when I dig out the data regarding exports and the do mestic breakup of orders. I will first access your query on the green energy sect or. See, this is a segment that has got huge, huge potential. Now, some of the nations have mandated go green by as conditions a target as 2030. India too is moving in the right direction. Already, the Ministry of Shipping has promulgated Green Tug Transition program, the GTTP, and in addition many of the S tate Governments are going green.

    Answer, cmde hari

    When you say green, they're looking at global emission platforms and GRSE has already mad e a foray into this segment through a partially research and development funded pro ject on a fully electric f erry for the Government of West Bengal and we have successfully completed this project. We are awaiting the formal handing over of the vessel to th e Government and just for information, this is the largest in terms of passenger capacity is 150 passenger fully electric ferry for the Page 7 of 16 Government of the West Bengal. In addition, we also won an order for 13 more hybrid ferries, again from the Government of West Bengal. It's a World Bank funded project. So currently in I ndia, 2 shipya rds i.e. Cochin shipyard and GRSE has successfully completed the green energy vessels . So, this is an area where we see huge potential, and we will definitely play an active part of the Green Tug Transition program, which I'm very confident is moving in the right direction where all the ports will be mandated to use fully green tug. In addition to the GTTP , that's the green tug transition program , t he Indian Water Authority of I ndia, the IWAI , also has got requirements for green vessels for Indian water transportation.

    Answer, cmde hari

    So, this is an area where we see this potential in future. Thank you. And now , coming to your first person on the breakup of Export and domestic orders. As I narrated before, our core business is domestic w arship building and the majority of o ur orders come from domestic w arship building and now since we have made a foray into the non - defence platform also, s till, the shipbuilding segment is almost 99 % of our orders and coming to exports within the shipbuilding segment, exports come to around 3.17% as of now and the domestic i.e. the domestic values of 96%. Hiren: OK, Sir. Yeah. Thank you.

    Answer, cmde hari

    Cmde PR Hari: Coming to the order book breakup, the current order book is, as I mentioned earlier is ₹24,221.37 crore. And this again as I mentioned, comprises mostly of ship building orders which comes to 99.4%. Now, coming to the order book breakup project wise, the P17 A lpha - the balance order remaining is around ₹ 13,927 c rore. The Anti- Submarine Shallow Water Craft is around ₹ 4,331 crore . The Survey Vessel Large project with the two ships were remaining around ₹729 crore, the Next Generation Offshore Patrol Vessels is ₹3,023 crore. The oceanographic research vessel for the NCPOR, M inistry of Earth Sciences, around ₹800 crore i.e. ₹796 crore. The multipurpose vessels is around ₹520 crore, 2 export projects for the Government of Bangladesh around ₹314 crore and Naval Surface Gun project around ₹255 crore.

    Answer, cmde hari

    So, this gives you a breakup of the current order book. Your second question was on the margins. So, we as in stating this consistently, that in shipbuilding margins , optimal margins, where satisfactory efficiencies existing around 7.5 to 8% when we are in a competitive environment and we have been maintaining this kind of margin. So, we Page 8 of 16 are hopeful, we're very confident of maintaining similar margins in future too. Thank you. Harshit: Yeah, I have one more question on the N ext Generation corvette order. What is the status by Q4 , a re the t ender results expected out or there could be a delay and probably in FY26 the results would be out and second thing you mentioned on the pipeline, P17 Bravo Frigate so is that something so destroyers or will not be coming?

    Answer, cmde hari

    Is that a correct understanding because what we understand either frigates would come or destroyers would come in terms of order pipeline over next 2 -3 years. Any color on that would be helpful.

    Answer, cmde hari

    Cmde PR Hari: OK, I'll give my views on this. The Next Generation Corvette as they had brief ed before, that we have already submitted the bid. There are 4 shipyards who have built for this project and currently the technical evaluation is in progress and we expect the bid to be open by then in December or January, I mean December 2024 or as close as January 2025. What I'm trying to convey is that in our appreciation, the bid results will be declared during the current financial year itself. Of course, then the contract negotiations will happen and we expect the order to be signed only during the next financial year. Your next question was on the P17 Bravo project and the Next generation destroyer project. For the P17 Bravo project, Defence Acquisition Council (DAC) has already accorded the AON and again, what I'm trying to convey is the clock has started.

    Answer, cmde hari

    So, once the A ON has been accorded, the Navy finalize the SOTR and RFP will be promulgated. We expect the RFP to come out sometime in the calendar year 2025 that means during F Y26 we expect the RFP to come out. And coming to the next generation destroyers, yes, in our acquisition as per our assessment of the prospective plan of the Navy, Navy is need of this vessel. At this moment, we will not have any clarity as to when the project is going to fructify because they have not yet gone f or AON. So , that answers your quer ies for NGC, P17 Bravo and the N ext Generation Destroyer. Harshit: Thank you for answering all the questions and wishing you all the best.

  3. Question

    Amit Dixit: Yes, Sir. Thanks for the opportunity and congratulations for a good set of numbers. Just I have three questions from my side. So, this quarter, if you see the gross margin has declined, it is now below 30%. While I understand that qua rter on quarter, we should not look at you know, defence companies. But since this below 30%, we have not seen for a very long time and many, man y quarters. So just wanted to understand what is behind that , isn't just the execution phase or you know we expect to see gross margin at these levels only?

    Answer, cmde hari

    Cmde PR Hari: OK, if you're looking at the gross margins , during our earlier interactions also ha ve maintained that we will be providing a margin which are consistent. Consistent in Page 9 of 16 terms of, we’re looking at the perhaps margins around 8% which we are maintaining and I expect the similar trend to continue in future also, we don't see any decline nor we do not expect any steep rise . We'll be maintaining this kind of margins in future too. The margins in most of our revenue are coming from shipbuilding. Yes, we have ventured into ship repairs where the margins are much better so as and when our ship repair revenue goes up, the high margins of the ship repair segment, the lower relatively lower margins of s hipbuilding and we could see an increase. But , all I can say at this moment considering our current order book and the execution strategy , the current margins, we'll be able to maintain.

  4. Question

    Amit Dixit: OK, Sir, that's very clear. The second one is on next generation corvette, but now two parts here. The first one is that when you mentioned to Harshit’s answer that you know that you expect the contract neg otiation to go on in next financial year. Now, assuming that you know we finished the contract negotiation, then next financial year and we are ready for you know and we get the order. So, how much time will it take for us to mobilize and start recording the revenue?

    Answer, cmde hari

    Cmde PR Hari: OK, very interesting question. If you just take the timeline, logical realistic timelines now, if the bid is going to be open by December 2024 / January 2025 and let us put a very reasonable figure about 6 months for contract negotiations and 6-8 months that means by Q3 of F Y26, when the contract is concluded, the revenue recognition will start two years from then. It's gets to say that which is perfect in terms of the timeline, why perfect, it is from 20 26, if you take two years that comes to 2028 and that perhaps is the time when our current order book will get exhausted. So, time and space wise the NGC project is moving in the right direction if we get it, I’m just mentioning if we get it, 2026 make 2 years hence the revenue recognition starts and that is a time when more or less our existing order book is exhausted. That's the time for your question.

  5. Question

    Amit Dixit: Yes, Sir, certainly. And the part B of this question is that what kind, what level of indigenization are we targeting on this NGC?

    Answer, cmde hari

    Cmde PR Hari: The indigenization if you see, I'm sure you're keeping track of our company, but all the ship building companies in India, Indigenization is the focus area of the Government and almost all the ship yards have a clear mandat e to maximize the indigenous content on their ships. And as pre cedent over the last 2 -3 projects that we have completed b e it the landing craft utility project , be it the anti-submarine corvette project or something like the Fast Patrol vessel for Indian Coast Guard, the indigenization content has been hovering between 80 to 92%. Now, for the P17 Alpha projects, the major project where certain equipment are of import nature, the indigenization content is around 80 to 82%. But the other three projects which we have again at hovers in this direction, I am not at this moment assuming any major change in the indigenization content, even in NGC, I expect it to be in our appreciation that it will be between 85 to 90% tops. But there will still be an element Page 10 of 16 of import content that, maybe in the in part of the prop ulsion package or some of the consensus, so around 10% optimistic level input content and 15% at the business level.

  6. Question

    Amit Dixit: OK. That's very clear, Sir. The third question from my side is that there are some media articles suggesting that we are planning indigenous hovercraft for military operations. So just wanted to get your thoughts on this, you know and we are trying to collaborate with some private sector also that is or that media article says s o are we doing something on that trend and what kind of market we see and if so when it will translate into you know revenue or orders for us?

    Answer, cmde hari

    Cmde PR Hari: OK. As far as hovercrafts are concerned, so far hovercrafts are being used only by the Indian Coast Guard and Indian Coast Guard has two sets of hovercrafts, one which they directly imported from UK based company and second, manufactured by GRSE through collaboration. This is the past history. Now both the Coast Guard and Army , they need hovercraft. The business volumes of this venture, I will not see it very, very attractive but there is the need to indigenize hovercraft because hovercraft manufacturing technology so far is not available in India. It is with this intent that we have taken an initiative and you may be aware that there is a Department of Defence Production has key in vited sche me for encouraging startups and private se ctor to come up with the solutions towards Indigenization and new product development. So, we have put this as a challenge and we have identified a partner, private sector partner and we are confident of achieving the indigenization of the class by 2027.

    Answer, cmde hari

    Because it takes time because certain components of the technology has to be developed. So, we expect a three- year period t o develop this product and second question that you asked is what is the potential? Both the Coast Guard and the Army has dropped the requirement and if the product is indigenous, naturally the cost is going to be much lesser and the maintena nce aspects wo uld be much better handled in India. So, I expect the potential I would not say huge potential but reasonable market potential for this product sometime in the early 30s.

  7. Question

    Sunil Shah: Yeah. Thanks for the opportunity, Sir. Just need to have an understanding on the P17 Bravo project, Sir. Our P17 Alpha is going to get completed by August , 26 is what I understand from your note. Sir, what would be the timeline for this P17 Bravo to recognize the revenue for us. The way in which you explained about, you know, the Next Generation Corvette, which is 2 years after we get the order. Similarly, if we get 4 orders for P17 Bravo, how would the revenue recognition happen in terms of the timeline? If you could make me understand that piece. Page 11 of 16 Cmde PR Hari: The fact is that P17 Bravo, the AON has been already accorded recently.

    Answer, cmde hari

    So, the clock has started ticking for Navy to come up with the RFP. The best-case scenario, the RFP could come out , only an assumptio n that the RFP could come out during mid 2026 calendar year. The project , it's a big project, two shipyards will undertake this project. It's a 7-ship project and overall cost is around ₹70,000 crore, The L1 shipyard could get ₹40,000 crore worth order around and the second shipyard, 3 ships are the proportionate cost. So, if the RFP is out during t he mid-26, you keep a year from the RFP to contract signing. Best case I'm telling that means mid 2026 the contract will be signed and a s with the other project, it will take two years for the revenue recognition which should come to 2028-29.

  8. Question

    Sunil Shah: This is ok. Thanks for all this understanding that you gave me. Thank you.

    Answer, cmde hari

    Cmde PR Hari: OK. Thank you. Whatever is, yes, it's the fact that the Government is already started the process of for mulating a shipbuilding policy framework with a sole aim to bring India into the top nations in terms of shipbuilding. Yes, our ma rket share and the overall global shipbuilding scenario as a nation, it is similarly low and the intent is to enhance this and become one of the top nations. Whatever initiatives currently the Government is taking is all that is available in the o pen media , open-source information is least available. Now, our assessment is that the ship building financial assistance scheme would continue because right now the scheme is available and it is for a specific time frame . Second, there will be focused o n green initiatives with a clear intent for our transition from conventional energy driven platforms , green energy platform.

    Answer, cmde hari

    Third, there would be a focus on linking ship breaking with ship building, which means it's a very innovative scheme they're proposing , they're likely to propose is that if a ship owner breaks the ship in India, he gets a certain amou nt of credit and if he builds the next ship in India, he can avail the credit. So, such very, very innovative schemes are likely to come up as far as the ti meline is concerned. As I understand, it's one of the focus areas of the government. So anytime now, as I understand the process is at advanced stages. So anytime now maybe in the three to six months, the policy framework could come out. N ow, coming to GRSE, while our Page 12 of 16 focus has been and p rimary focus would be on Warship building, for which there is already a structured process because warship building priced on a prospective plan of both the armed forces i.e. the Navy and the Coast Guard and the budget availability. So, there's a very structured and our primary focus would remain on warship building, but considering the opportunities ava ilable in the non -defence segment, we are already, I mean we are aware that this policy framework is going to come, the Government focus will be on encouraging shipbuilding in India.

    Answer, cmde hari

    So, with that clear understanding, w e are slowly diversified and prepared ourselves into one after another ships, prepared ourselves through aiming experience in construction of commercial ships. The results are here. Any ex perience ship building like specialized research vessels again, the results are here to see. We have already got order and execution. Any experience by developing green energy vessels, again, we already developed an d received more orders and capacity enhancement i.e. capability already we have , capacity enhancement and infrastru cture enhancement process already commence. What we had targeted might mean GR SE's target would be to achieve a shipbuilding capacity for the 28 ships concurrently. We are at 24 now.

    Answer, cmde hari

    By 2025, we'll be able to achieve that. So as to your specific question, what is in store for GRSE, very much is on the anvil and we are fully geared to take on this challenge in the coming years. Thank you. Vijay: Sir. So, will there be some kind of PLI scheme for shipbuilding industry under the financial assistance program? Cmde PR Hari : As per my un derstanding, while infrastructure status may be there at this juncture, it's my understanding that there is no thought process to accord rather to provide a PLI scheme for shipbuilding. Vijay: OK.

  9. Question

    Basant Bansal: Yeah. Good evening, Sir. I have 2 -3 questions. The first one is that in your opening remarks, you said that you are working on 3 -4 proje cts for the Go vernment of Bangladesh. So, are you facing any challenge in terms of execution because of the social unrest kind of situation prevailing over there? Secondly, you are working on 24 projects as you said so, are you facing any challenge in term s of execution due to supply chain related issue or any other issue which can delay the execution part. And the third one is that in the first half you have cloc ked 30% revenue growth. So, will it be maintained for the full year for the current year as well as for the s ubsequent years?

    Answer, cmde hari

    Cmde PR Hari: OK. Thank you, Mr. Bansal. I'll address your questions one by one. You're asked about Bangladesh. Yes, we are execu ting 3 projects for Bangladesh. But if you see our Page 13 of 16 overall order book and compare it with the orders in hands of Bangladesh, the total order value from Bangladesh is just about ₹300 crore, which comes to about. 1.5% of our total order book .

    Answer, cmde hari

    So, the impact on the company is negligible. Now , coming to the impact on the project. We have an undertaking a p atrol boat projects of Bangladesh, 50% of the boats already delivered and the other three boats will be delivered by end of the year. We don't envi sage any issue with that. The other two projects again are very very small price, one is for a dredger and one is for a tug. The dredger project is moving in the right direction. That project is still in preparatory phase, so we don't see any impact and on a positive note, I feel as a nation this is just a passing phase.

    Answer, cmde hari

    It's a dip that they have once the things stabilize . I don't see any issue, especially considering the shipbuilding unlike any other manufacturing industry, the projects are long term project s o by the time the situation makes becomes normal, the project continues what he has been doing and to catch up so whatever initial teething issues Sir. So, I don't see any problems with the Bangladesh project. Coming to the supply chain impact on shipbuild ing, there was a time in the post COVID phase, not definitely during the COVID phase and post COVID phase there was an issue with the supply chain, but those issues have been fully tied over and at this juncture, w e do not have any supply chain issues. Whe n I said 24 means what I meant was that GRSE has got the capacity to construct 24 vessels concurrently within our physical boundaries. To answer your question, no impact on supply chain as of now. Coming to revenue growth, yes, we have registered 30% growt h within the first half of the year.

    Answer, cmde hari

    Here , I would like to make a statement which I'm only reiterating what I had mentioned during our previous interactions that we had assured us the C AGR of around 25% during the four-year period from FY23 to FY27, we are confident of maintaining that kind of CAGR and only exceed your expectations maintaining similar growth rate. Thank you.

  10. Question

    Kartik Bhatt: Yeah, Hi Sir. Sir, if you can throw some light on the contract that you signed with this German company, I think for multi- purpose vessels, was it a competitive bid, how many other companies are bidding , w hat is the order value and the timeline over which is to be delivered?

    Answer, cmde hari

    Cmde PR Hari: OK. Yes, this is for the or ders for our Germ an client, 8 multipurpose vessel and the initial contract when we signed about 4 months back was for ships with an option clause was for another 4 ships and we already expressed the option clause and as of now we have signed contracts for 5 of the weapons and the total order value and the next 3 ships will be signing the contracts by March 25 and the total order value for 8 ships is around ₹890 crore. And to answer your question, for foreign clients, they did not go on a conventional tende ring and competitive process. They approach Page 14 of 16 potential shipyards directly, do a capacity assessment and when they find a particular shipyard competent and capable of u ndertaking executing their project, they take a cost or bid from us when they negotiate with us, they have a method. I'm sure they would have approached multiple shipyards before coming on to GRSE and assessing our capacity. The order values around ₹890 crore.

Show 2 more questions
  1. Question

    Kartik Bhatt: OK. And Sir, I believe there is a first contract with the European company and I think in the last one also you were alluding to a lot of European nations looking at India as a destination for construction of commercial vessels. So, are we talked with the most such companies? I mean is it a sign of things to come that you’ll be p articipating in more such contracts and tenders?

    Answer, cmde hari

    Cmde PR Hari: Yes, this is the sign of things to come and more and more European clients are approaching not only as all the Indian shipyards and they are looking seriously at India as the hub for commercial shipbuilding. It is a very, very positive and good sign of things to come in future. And we will be actively pursuing more opportunities in this segment.

  2. Question

    Kartik Bhatt: That's great to hear. Thank you so much. Thank.

    Answer, cmde hari

    Cmde PR Hari: OK, I'll put it this way. In the budget , capital budget allocation, all three s ervices are given the funds based on the projections and of course the decision of t he Government. In our appreciation, the budget allocated to Indian Navy is more than adequate to meet the requirements of the ongoing projects. Neither would the drone, nor the Rafael projects, which are which have been publicized, would have any impact on the fund flow from the ongoing capital projects of the India n Navy. Coming to the future projects, once the AON is accorded, it is with the consideration that the budget is available. So, I'm even talking about be in, NGC or I'm not talking about the orde rs already in line where I have to 0 impact. I'm only speaking about the orders on the a nvil, be it NGC or be it P 17 Bravo, these considerations have already been factored while according AON and are coming out with RFP .

    Answer, cmde hari

    So, we do not see any budget constraint. And another point I'd like to highlight is that unlike an outright purchase, where you may expand the complete project valu e in one shot in case of shipbuilding, it is priced over a period of time, sometimes ranging from three Page 15 of 16 years for a small platform or a project to 5 to 10 years for a large project, some of the stuff that they used take the digital aircraft project pictures being handled by one of the other Indian shipyard as the project is almost at 12 to 13 years long. So, budget is not a constraint in my appreciation as well as the projects which we are executing or what we are likely to get in the coming years. Harshit: OK, Sir. And just one final question on the electric f erry. So, if this helps us understand Sir, there is no change in the design of our ship, you largely replace the diesel engine in the ship with an electrical engine. Is that a correct understanding and are you right now manufacturing or importing this engine?

    Answer, cmde hari

    Cmde PR Hari: OK, in case of when we say zero emission vessel , w hat we try to convey is that emissions which come from a diesel engine or a gas turbine or an erstwhile coal engine that is no longer there. While an engine is not there, the propulsion mode that is used in a very electric ferry is the batteries. The batteries drive a propulsion motor and the propulsion motor in turn drives the shaft which propels the ship. This is the basic difference. Whereas in case of a diesel engine or a gas turbine profile or a steel ship the steam engine, the diesel engine of the gas turbine drives through a gearbox the shaft, here the shaft driving is undertaken by a propulsion motor, which in turn gets power from a battery pack. The batteries are of different types. I'm sure you would not like me to get into those details, but the basic differences, the conventional proportional methods are not.

    Answer, cmde hari

    Cmde PR Hari: Please I will just request my Director Finance and CFO to answer this question. R.K. Dash: Actually, in shipbuilding, last stage of payment, receivables get delayed. In the initial period, the receivable is very fast and in the l ast moment, t here is some guarantee period because of the guarantee period, at least the last payment gets delayed by one year. So, because of that, whenever the delivery, there will be more delivery, receivable accumulation will go. So whatever disturbance you are finding, the reason is because of that. Now we have started delivering.

    Answer, cmde hari

    Cmde PR Hari: Thank you, Yashashree and there is always been a fresher, ladies and gentlemen, to interact with you and I look forward to such interactions with our citizen , an eye opener as to what you expect from us and I am very confident that to the best of our ability we have tried to clarify all your queries and looking forward to meeting you next. Thank you, Jai Hind. Thank you, Gaurav and Yashashree.

Questions about this call

When was the Garden Reach Shipbuilders & Engineers Q2 FY25 earnings call transcript filed?
Garden Reach Shipbuilders & Engineers filed the transcript with the exchange on 21 Nov 2024. This page is built from that transcript.
What does this page list?
57 statements from the transcript across 7 topics, 48 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 12 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Garden Reach Shipbuilders & Engineers Q2 FY25 concall: what the company said · DalalOS