Earnings call
Garden Reach Shipbuilders & Engineers Q4 FY26 earnings call: Garden Reach Shipbuilders & Engineers Limited’s current order book stands at INR 15,324.13 crore
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Current order book stands at INR 15,324.13 crore. The company completed price negotiations for the NGC contract, and had expected the contract to be signed by 31st March while contract negotiations on terms and conditions were in progress. P-17 Alpha ship has recorded about 74% physical progress of construction and is intended for delivery during the current calendar year. The company recorded revenue from operations of INR 2,119 crore in Q4 & FY 26, up 29% over the last year, and profit after tax of INR 303 crores, up 24% from INR 244 crores. The government has promulgated a revitalization package for shipbuilding worth around INR 69,725 crore; Garden Reach Shipbuilders & Engineers Limited expects the commercial shipbuilding segment to gather momentum in light of the package and demand for platforms aggregated by the Ministry of Shipping.
The numbers management gave
Results
- The company recorded revenue from operations of INR 2,119 crore in Q4 & FY 26, up 29% over the last year, and profit after tax of INR 303 crores, up 24% from INR 244 crores.
Show source
The revenue from operations recorded during the quarter was INR 2,119 crore, registering a growth of 29% over the last year and the profit after tax has moved up by 24%, from INR 244 crores to INR 303 crores.
- The company recorded revenue from operations of INR 7,002 crore in Q4 & FY 26, up 38% over the last financial year.
Show source
When we take the full financial year, I am happy to inform you that we have recorded a revenue from operations of INR 7,002 crore, registering a growth of 38% over the last financial year.
- The company recorded profit after tax of INR 748 crore in Q4 & FY 26, up 42% from INR 527 crore.
Show source
Similarly, our profit after tax has moved up from INR 527 crore to INR 748 crore, registering a growth of 42%.
- The company delivered eight warships to the Indian Navy in Q4 & FY 26; three vessels were delivered on the same day, perhaps for the first time in the history of the country.
Show source
We delivered eight warships to the Indian Navy, and interestingly, three of these vessels were delivered on the same day, and this perhaps is the first time in the history of our country.
- The company launched one warship and completed keel laying for 19 platforms in Q4 & FY 26, including 13 hybrid ferries being built for the Government of West Bengal.
Show source
We also launched one warship with a keel laying of 19 platforms.
- The company delivered 110 portable steel bridges during the last year, including 30 for export.
Show source
As you are aware, we have a daily bridges business vertical and during the last year, we delivered 110 bridges, including 30 for export.
Show 6 more statements
Results
- Bridges vertical revenue exceeded INR 200 crore for the first time in the history of that vertical during the last year.
Show source
I am also happy to inform you that the revenue from this particular vertical has touched INR 200 crore plus for the first time in the history of that vertical.
- The company recorded revenue of over INR 270 crore from exports during the last year.
Show source
Also, we have recorded a revenue of over INR 270 crore from exports.
- The company delivered three ships on the last day, and after formalizing the deliveries and handing over sales revenue, total revenue came to 7,200.
Show source
So, when all this happened and when we formalized the deliveries and handed over the sales revenue, appropriately it was realized from these ships, and the total revenue now comes to our best figures of 7,200.
- The company delivered seven naval surface guns during the last year, and four successfully completed the Sea Acceptance Trial.
Show source
Coming to the other business vertical: Seven naval surface guns were delivered during the last year, and four of these have successfully completed the Sea Acceptance Trial.
- The company delivered two ships under the P7 Alpha project, four survey vessels in the last year and the previous last two years, and four Anti-Submarine Water Craft projects.
Show source
We have delivered two of the ships and survey vessels we have delivered four of them in the last year and the previous last two years, and four of the Anti-Submarine Water Craft projects.
- The company said orders for equipment and spares for the P7 Alpha, survey vessel and Anti-Submarine Water Craft projects were placed much earlier, prices were fixed, and there was no escalation or impact, so margins were intact and had not been affected by market fluctuations.
Show source
So, the margins are intact.
What it expects ahead
What management expects
- The company completed price negotiations for the NGC contract, and had expected the contract to be signed by 31st March while contract negotiations on terms and conditions were in progress.
Show source
We were expecting the contract to be signed by 31st March because at that point of time, the contract negotiations, the terms and conditions, those aspects were in progress.
- The company does not plan revenue recognition for NGC during the current year or the next half, assuming the contract is signed in the 1st Quarter.
Show source
So, considering this aspect, in the first year, assuming, again, we are signing the contract in the 1st Quarter, we don't plan any revenue recognition during the current year, or even during the next half.
- The company had about 39 platforms under construction, and expected revenue accrual during the current financial year to be very healthy and in line with what it had seen during the last three or four years.
Show source
So, we expect that the revenue accrual during the current financial year is going to be very healthy, and in line with what we have been seeing during the last three or four years.
- GRSE expects the RFP for P-17 Bravo to come out in the current quarter.
Show source
The first part we expect the RFP for P-17 Bravo to come out in the current quarter.
- If the RFP for P-17 Bravo comes by 1st Quarter, the contract could be completed as early as end of FY27, going by the NGC trend.
Show source
So, if the RFP for the P-17 Bravo comes by 1st Quarter, then the contract could be completed as early as end of the current financial year, that is FY27, going by the NGC trend.
- Current assessment is that the NGC contract will be signed during the current quarter, that is June.
Show source
Our current assessment is that the contract will be signed during the current quarter that is June.
Show 44 more statements
What management expects
- The company expects RFPs for the Mine Countermeasure Vessel and landing platform dock projects to come out sometime during the latter half of the current financial year.
Show source
But these two, the last two projects which I mentioned are some time-off because I expect the RFPs to come out sometime during the latter half of the current financial year.
- If the NGC contract is signed during the current quarter, Garden Reach Shipbuilders & Engineers Limited expects revenue booking to happen during the latter half of FY28.
Show source
The revenue booking from NGC, if the contract is signed during the current quarter, we expect the booking to happen during the latter half of the next financial year, that is FY28.
- The company expects a very mediocre amount of NGC revenue recognition from design inputs during the latter half of FY28, leading to the ship being ready for construction.
Show source
The next part, what I mentioned to commence revenue recognition, that will be a very mediocre amount, which is coming from the design inputs, which lead to getting the ship ready for construction.
- The company expects the major chunk of NGC revenue recognition to start from FY29, when hull construction would have matured and at least some equipment comes in.
Show source
The major chunk of the revenue recognition will start from FY29, when the hull construction would have matured, and at least some part of the equipment comes in.
- The company expects to support FY28 revenue with the balance projects in hand, the NPOPV project, the first vessels, and the commercial vessels in hand.
Show source
And for the next year, that is FY28, we will pad up with the balance projects what are in hand, the NPOPV project, the f irst vessels, and the commercial vessels, what we have in hand.
- The company plans to follow its current commercial shipbuilding order with more orders, and will go for projects with higher margin and perhaps more order value.
Show source
So, when we follow thi s current order with more orders, definitely we will be going for projects with higher margin and perhaps with more order value.
- The RFPs for the other two projects could come by end of the financial year. Replaced by a later filing.
Show source
And the RFP for the other two projects could come by end of the financial year.
- The contracts for the other two projects could be completed in the next financial year. Replaced by a later filing.
Show source
And the other two projects in the next financial year.
Orders
- Current order book stands at INR 15,324.13 crore.
Show source
Our current order book stands at INR 15,324.13 crore.
- Order book comprises nine projects consisting of 39 platforms.
Show source
This order book comprises of nine projects, consisting of 39 platforms.
- The company has one ship yet to deliver under the P-70 NALSA project.
Show source
The P- 70 NALSA project, one more ship is yet to be delivered.
- Order book includes four Next-Generation Offshore Patrol Vessels, one Ocean Research Vessel, one Acoustic Research Ship, two Coastal Research Vessels, 13 Hybrid Ferries, 12 Multipurpose Vessels, and one 1,000-meter-cubed Dredger.
Show source
Four Next-Generation Offshore Patrol Vessels , one Ocean Research Vessel , one Acoustic Research Ship, two Coastal Research Vessels , 13 Hybrid Ferries , 12 Multipurpose Vessels, and 1,000-meter-cubed Dredger.
- A tender for two Multipurpose Vessel ships is out, with an expected order value of around INR 1,500 crore.
Show source
We expect the order value to be to the tune of around INR 1,500 crore, and the Next Generation Offshore Petrol Vessels for the Indian Coast Guard, five of these vessels, again, the order value is to the tune of around INR 2,000 crore, and 22 Interceptor Boats for the Indian Coast Guard again.
- The 22 Interceptor Boats for the Indian Coast Guard have a likely order value of around INR 1,000 crore.
Show source
The order value is likely to the tune of around INR 1,000 crore.
- The company expects RFPs for the 120 Fast interceptor craft project for the Indian Navy, with an order value of around INR 3,500 crore, and the 31 Follow-On Water Jet FAC project for the Indian Navy, valued at about INR 3,500 crore, to come out in the next three months.
Show source
The order value is to the tune of around INR 3,500 crore.
- The seven P-17 Bravo ships have recorded AoN, and Garden Reach Shipbuilders & Engineers Limited expects the RFP to come out in the next three months; the order value is likely around INR 70,000 crore.
Show source
We expect the RFP to come out in the next three months, and the order value is likely to the tune of around INR 70,000 crore.
- The 12 Mine Countermeasure Vessels are for the Indian Navy.
Show source
CMV project, again, for the Indian Navy.
- The AoN value for the 12 Mine Countermeasure Vessels is around INR 32,000 crore, and the four landing platform dock LPDs have a likely order value of around INR 35,000 crore.
Show source
The AoN value is around INR 32,000 crore, and four landing platform dock LPDs , the order value is likely to the tune of around INR 35,000 crore.
- The company expects the RFPs for the 120 FAC, 31 Follow-On Water Jet FAC, and seven P-17 Bravo projects to come out in the next three months; the RFPs for the Mine Countermeasure and Landing Platform Dock projects are most likely during the current financial year.
Show source
These are the projects that I have listed out, are only the projects where AoN has been accorded, and as we appreciate the first three projects, that is the 120 FAC, 31 Follow-On Water Jet FAC, and the seven P-17 Bravo, we expect the RFP to come out in the next three months, and the other two projects, the Mine Countermeasure as well, and the Landing Platform Dock , most likely during the current financial year.
- The total estimated order value of the projects listed is about 1,50,000 crore, excluding the NGC project.
Show source
And this, so the total estimated order value is to the tune of about 1,50,000 crore, excluding, of course, the NGC project.
- The cost of four Platform Support Vessels could be INR 1,200 to INR 1,500 crore.
Show source
Four Platform Support Vessels, the cost could be to the tune of INR 1,200 to INR 1,500 crore.
- Order book was INR 15,324 crores, with about 95% from shipbuilding; shipbuilding orders were around INR 14,730 crores, including INR 5,868 crores remaining for the P-17 Alpha project, INR 2,035 crores for Anti-Submarine Shellow Water Craft and INR 5,168 crores for Next Generation Offshore Patrol Vessel, while warship building orders were around INR 11,361 crores.
Show source
The order book breakup, as I mentioned, our total order book value is INR 15,324 crores, and about 95% continues to come from shipbuilding.
- Non-defense order book included the Ocean Research Vessel worth INR 749 crores, two Coastal Research Vessels worth INR 260 crores, the Acoustic Research Ship worth INR 456 crores, arctic ferries and hybrid ferries worth INR 207 crores, Multipurpose Vessels worth INR 1,345 crores, and about INR 66 crores remaining for the dredger.
Show source
Coming to the non -defense segment, the Ocean Research Vessel worth INR 749 crores, the Coastal Research Vessels , two of them we are doing, INR 260 crores, the Acoustic Research Ship, INR 456 crores, the arctic ferries, hybrid ferries, INR 207 crores, the Multipurpose Vessels, INR 1,345 crores, and the dredger, about INR 66 crores remaining.
- Non-defense segment accounted for about 22.5% of its total order book.
Show source
So, what is interesting is that in the non -defense segment, n ow we have about 22.5 % of our total order book.
- The 120 Fast Interceptor Craft project will be split between two shipyards, 80 and 40, under the likely RFP conditions.
Show source
But the other project, the 120 Fast Interceptor Craft and the P-17 Bravo, the Fast Interceptor Craft 120, it will be split between two shipyards, 80 and 40.
- The P-17 Bravo project would be split between two shipyards, four and three, like the current P-17 Alpha project.
Show source
And the second project, the P -17 Bravo, again, would be split between two shipyards, four and three, like the current P -17 Alpha project.
- The 12-ship Mine Countermeasure Vessel project would be split between two shipyards, eight and four.
Show source
The Mine Countermeasure Vessel , the 12 -ship project, would be split between two shipyards, eight and four, and the landing platform dock, two and two.
- The state order value remaining for the medium-sized Multipurpose Vessel project is around INR 1,400 to INR 1,500 crore.
Show source
Just to give you a perspective, the project what we have taken on is a multi - purpose vessel, which is a medium -sized, state ord er value remaining is around INR 1,400 to INR 1,500 crore.
- The cost per ship for an additional Anti-Submarine Shallow Water Craft project is around INR 675 crore.
Show source
If you just take any of the naval projects, be it additional Anti-Submarine Shallow Water Craft project, those ships are very small ships, but weapon-intensive ships, and the cost per ship is around INR 675 crore.
- The company said about INR 1,50,000 odd crore of RFPs are on the anvil in warship building, enough to meet the company's order book or profitability aspirations.
Show source
So, what I had stated in the beginning of this discussion that about INR 1,50,000 odd crore of RFPs which are on the anvil, so there is enough in that segment to meet the order book or profitability aspirations of the company.
- The P-17 Bravo project has seven ships and, as per the AoN accorded by the Defense Acquisition Council, will be between two shipyards: the L1 will get four ships and the L2 will get three.
Show source
The L1 will get four and the L2 will get three.
- The 12-ship project has an AoN value of around INR 32,000 crore and will be split between two shipyards, with the L1 shipyard getting eight and the L2 shipyard getting four.
Show source
The AoN value is around INR 32,000 crore.
- The LPD project has an AoN value of around INR 35,000 crore and will be two plus two.
Show source
Coming to the LPD project, the order, the AoN , as my memory goes, it's around INR 35,000 crore.
- The company said that dipping below an order book of ₹20,000 crores for the first time meant its execution rate had picked up.
Show source
Actually, I am happy that the order book has dropped below INR 20,000 crore in the last five years, it's the first time that the order book is dropping below INR 20,000 crore.
- The Next Generation Corvette is ₹33,000 crores.
Show source
That's why my first statement was that the NGC project is live and we are the L1.
- The company has four ships pending delivery under the Anti-Submarine Shallow Water Craft Project.
Show source
The Anti-Submarine Shallow Water Craft Project , we have four ships pending for delivery.
- The company is L1 for the Next Generation Corvette project; price negotiations have been completed and the company is awaiting formal signing of the contract.
Show source
The price negotiations have alread y been completed, and we are awaiting the formal signing of the contract.
- Three tenders are live: one for the Indian Navy and two for the Indian Coast Guard.
Show source
Currently, three tenders are live, one for the Indian Navy and tw o for the Indian Coast Guard.
- Four tenders are live for domestic commercial vessels aggregated by the Ministry of Shipping.
Show source
In addition, what we had been discussing earlier, the aggregated demand of the domestic requirement of commercial vessels aggregated by the Ministry of Shipping, now it has gained traction, and four tenders are live.
- The four live tenders include four MR tankers, six very large gas carriers, VLGC, and six Aframax vessels, and Garden Reach Shipbuilders & Engineers Limited will take part in these tenders.
Show source
Four MR tankers, six very large gas carriers, VLGC, and six Aframax vessels.
- The Multipurpose Vessels project has two ships and is for a single shipyard.
Show source
Coming to the smaller projects which you mentioned, the first project of Multipurpose Vessels is a single shipyard.
- The Coast Guard OPV project is for five ships and a single shipyard.
Show source
The OPV project for Coast Guard, five ships, again, a single shipyard.
- The Interceptor Boats project is for a single shipyard.
Show source
And the Interceptor Boats , again, is a single shipyard.
- The landing platform dock project would be split between two shipyards, two and two.
Show source
The Mine Countermeasure Vessel , the 12 -ship project, would be split between two shipyards, eight and four, and the landing platform dock, two and two.
What it is building and selling
Projects and capacity
- P-17 Alpha ship has recorded about 74% physical progress of construction and is intended for delivery during the current calendar year.
Show source
This ship has already recorded about 74% physical progress of construction, and we intend delivering this ship during the current calendar year.
- Under Garden Reach Shipbuilders & Engineers Limited’s eight-ship Anti-Submarine Shallow Water Craft Project, four ships have been delivered; two of the remaining ships have reached about 80% physical progress, completed basin trials, and are being prepared for Contractor Sea Trials, with delivery intended by the mid of the calendar year.
Show source
Coming to the Anti-Submarine Shallow Water Craft Project: This is an eight-ship project, and of these eight ships, four have already been delivered, and the remaining four ships, two of them have touched about 80% physical progress of construction, and their basin trials have been completed, and we are preparing them for the Contractor Sea Trials , and we intend delivering these ships by the mid of the calendar year.
- Ships 7 and 8 of Garden Reach Shipbuilders & Engineers Limited’s Anti-Submarine Shallow Water Craft Project have reached around 60% physical progress of construction and will be delivered during the current financial year, completing the project.
Show source
The last two ships, Ships 7 and 8, have touched around 60% physical progress of construction, and we will be delivering these ships during the current financial year, thereby completing this project also.
- The first ship of Garden Reach Shipbuilders & Engineers Limited’s four-ship Next-Generation Offshore Patrol Vessel project has reached the stage of launch, and its launch is planned on 20th of this month.
Show source
Coming to the Next-Generation Offshore Patrol Vessel project: This is a four-ship project, and the first of these ships have reached the stage of launch, and the launch of this vessel is planned on 20th of this month.
- The company intends to complete its Next-Generation Offshore Patrol Vessel project during Financial Year ‘29.
Show source
The progress of production, construction of the remaining three ships is also satisfactory, and we intend completing this project during Financial Year ‘29.
- The company is constructing the Ocean Research Vessel for the Ministry of Earth Sciences’ organization NCPOR -Goa; the vessel has undergone about 50% construction and is planned for launch during the current calendar year.
Show source
This ve ssel has already undergone about 50% of construction, and the ship is planned for launch during the current calendar year.
Show 12 more statements
Projects and capacity
- 13 ferries comprise six 200-PAX and seven 100-PAX ferries; the first two 100-PAX ferries are expected to be launched during May, the next one is planned for launch in the next month, and the project shall be completed by the end of the current financial year.
Show source
The Acoustic Research Ship that we are constructing for the DRDO, the ship has touched almost 20% physical progress of construction, and the 13 ferries, 6 - 200-PAX and 7 - 100-PAX ferries, they are on track, and the first two ferries of the 100-PAX are expected to be launched during May, that is this month, and the next one is planned for launch in the next month.
- The company is executing a 12-ship Multipurpose Vessel project for a German client; keel laying for three ships has been completed and the project is on track.
Show source
The keel laying, that is one of the project milestones, of three of the ships have already been completed, and the project is on track as of now.
- Current shipbuilding capacity is for construction of 28 platforms.
Show source
And just to give you the perspective, our current shipbuilding capacity is for construction of 28 platforms.
- The company intends to increase its capacity to construct ships to 32 by the end of this calendar year through ongoing modernization.
Show source
And with the ongoing expansion projects, that is the modernization projects within our premises, this capacity w ill get increased to 32 ships by the end of the calendar year.
- The company is executing a dredger project for the Government of Bangladesh, which is on track, and intends to launch the vessel during the current financial year.
Show source
And the last project that we are executing for the Government of Bangladesh, a dredger project on track, and we intend launching this vessel during the current financial year.
- The company is expanding through two Brownfield shipbuilding facilities in West Bengal and two Greenfield shipbuilding facilities, one in West Bengal and one in Gujarat.
Show source
And the projects that we have taken on for expansion is for creation of two Brownfield shipbuilding facilities in West Bengal, and two Greenfield shipbuilding facilities, one in West Bengal and one in Gujarat.
Demand and pricing
- The government has promulgated a revitalization package for shipbuilding worth around INR 69,725 crore; Garden Reach Shipbuilders & Engineers Limited expects the commercial shipbuilding segment to gather momentum in light of the package and demand for platforms aggregated by the Ministry of Shipping.
Show source
What we envisage is with the revitalization package for shipbuilding that has been promulgated by the government, which is to the tune of around INR 69,725 crore, and the demand for platforms that has already been aggregated by the Ministry of Shipping, we expect the commercial shipbuilding segment to gather momentum.
- The company said the government’s focus on warship building is evident from AoNs being accorded, RFPs being promulgated online by the Navy and Coast Guard, and RFPs being translated into contracts.
Show source
So, the government focus on warship building is there and it is evident from the fact that the AON is being accorded and the RFPs are being promulgated online by both the major end users, that is the Navy and the Coast Guard.
- The company said the commercial shipbuilding export market looks attractive, but money and margins are very much within warship building.
Show source
So, what I am trying to convey is that while the commercial ship building export market looks attractive, the money and the margins are very much within warship building.
Segments
- Around 65% of a ship's cost is equipment.
Show source
And as you are aware, around 65% of a ship's cost itself is equipment.
- For the NGC project, about 65% of the overall project cost is for equipment and systems; of that 65%, approximately 55% to 60% is accounted for by electronics, weapons, sensors and associated electronics, while around 40% to 45% comes from machinery and systems, including propulsion engines, air conditioning plants, associated machinery systems and steel.
Show source
And of this 65%, approximately about 55% to 60% is accounted by the electronics, that is the weapons, sensors, and associated electronics.
Deals and partners
- A large chunk of electronics for the NGC project comes from Bharat Electronics, a sister PSU of Garden Reach Shipbuilders & Engineers Limited.
Show source
So, a large chunk of electronics, of course, comes from our sister PSU, Bharat Electronics.
Risks, rules and outside factors
Rules and policy
- The company said the INR 18,900 crore allocated for defense shipbuilding represents a fund outflow during the particular year.
Show source
Now, when the figure of INR 18,900 crore has been allotted for defense shipbuilding, in my position, there is a fund outflow during the particular year.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Amit Dixit: Good afternoon, everyone, and thanks for the opportunity. First of all, congratulations for a very robust quarter and year, sir. Couple of questions from my side. The first one is on, if I go through the Statutory Committee of Defense reports, then something very striking that if you look at the summary of contracts that are expected to be signed over the next two years, these have gone down substantially. In the la st report, it was around INR 42,000 crores In the report released in March, it is only INR 18,900 crore approximately for warships and survey vessels, that particular category. So, in that light, just wanted to understand that how do we look at the focus o f the gover
Answer, p hari
P. R. Hari: Thank you, Amit. Now, when the figure of INR 18,900 crore has been allotted for defense shipbuilding, in my position, there is a fund outflow during the particular year. But as you are aware that government, including during the last year, perhaps even during the last two last Defense Acquisition Council, have given a green signal for multiple projects, what I had listed out earlier. So, the government focus on warship building is there and it is evident from the fact that the AON is being accorded and the RFPs are being promulgated online by both the major end users, that is the Navy and the Coast Guard. And also, the fact that these RFPs are getting translated into contracts. That's why my first statement was that the NGC project is live and we are the L1. The other value is to the tune of INR 33,000 crore only for us.
Answer, p hari
So, this figure what you have mentioned is perhaps the fund outflow that is anticipated from these projects during a particular financial year. And that depends upon the project maturity. Now, another aspect is that both the services, the Maritime Services, both the Navy and the Coast Guard have absolutely clear roadmap and stated perspective plans, which have been approved by the Government. So, to answer your question, the figures that you have stated does not reflect the intent of the Government or the progress made in this direction. Thank you.
Question
Amit Dixit: Great, sir. Very comforting. The second question that I have is, again taking a step back, it's a very macro kind of question. Considering the current warfare that is there and the TCPR of the Go vernment, where there is a lot of focus on autonomous vessels, on drones, on new age electronics. So, where do you think the traditional platforms like corvettes and destroyers stand or stack? Isn't the relevance of these traditional platforms declining? That is part one. Part two is that how GRSE is gearing itself for maybe this autonomous kind of vehicles or vessels or some kind of modern ships or the small ships that are being increasingly used in m odern warfare. So, are there some i
Answer, p hari
P. R. Hari: Thank you. You are absolutely right that there has been an increased focus on autonomous vessels. What is visible outside is the fact that the current situation has brought the focus of the Government to the fore. But otherwise, again, the Indian Navy has got and promulgated autonomous roadmap almost, which was promulgated almost three years back, even before the current situation escalated to the state where it is now. So, it is just that for us outside the realm of direct warfare, this is coming to focus. Now, even while autonomous platforms, be it subsurface, surface, or aerial, have been, are being, and will be utilized in a larger manner, larger focus, the conventional platforms would cont inue to remain because these conventional platforms, 1) they provide heavy -duty muscle in terms of armament. 2) they have huge endurance, sometimes endurance to stay more than three months at sea.
Answer, p hari
So, these conventional platforms would continue to, in my a ssociation, and as an experienced individual in this field, conventional platforms of all ranges, be it a fast patrol vessel, or be it an aircraft carrier, or be it a conventional or strategic submarine, this trust and their existence will continue to rema in. So, coming to GRSE, GRSE had ventured into the autonomous field as late as three and a half years back, and we started off in all three dimensions that I mentioned, both the subsurface, surface, and aerial. We have successfully developed both the subsurface and the surface versions, and just to inform you that one of our products has been supplied to, provided to one of the DRDO organizations. We see opportunities here, and we are an integral part, make, that is, Make-I and Make-II schemes which the G overnment has promulgated, and a few cases where the Autonomous Underwater Vessels, we are very much in the fray. And in the next year, since you asked me what can be the short term and what can be envisaged in the next five years in the short term, what we have developed, we see them gaining, let us say, more standing in the domestic market.
Answer, p hari
And in the long term, that is three to five years, we see the MAKE projects for the XL, that is Extra-Large Autonomous Underwater Vessel project to take shape, and perhaps in the next three to five years we should be able to develop and deliver this project to the customers. So, it is moving in the right direction, and as with many of the defense manufacturers of India, we have a separate business vertical on the new te chnology. So, we are focusing on the autonomous platforms, and in the next three to five years, we see the gathering for the momentum.
Question
Harshit Kapadia: Yes, hi, sir. Thanks for the opportunity, and congrats for a very good set of results. A few questions from my side. So, first, could you please give us the order book breakup which you generally give across the ship?
Answer, p hari
P. R. Hari: Sure. Thank you, Mr. Harshit. The order book breakup, as I mentioned, our total order book value is INR 15,324 crores, and about 95% continues to come from shipbuilding. So, the shipbuilding orders are to the tune of around INR 14,730 crores, and within shipbuilding, the P-17 Alpha project has about INR 5,868 crores remaining, and the Anti -Submarine Shellow Water Craft worth INR 2,035 crores, and the Next Generation Offshore P atrol Vessel INR 5,168 crores. So, the warship building orders are to the tune of around INR 11,361 crores. Coming to the non -defense segment, the Ocean Research Vessel worth INR 749 crores, the Coastal Research Vessels , two of them we are doing, INR 260 crores, the Acoustic Research Ship, INR 456 crores, the arctic ferries, hybrid ferries, INR 207 crores, the Multipurpose Vessels, INR 1,345 crores, and the dredger, about INR 66 crores remaining. So, what is interesting is that in the non -defense segment, n ow we have about 22.5 % of our total order book.
Question
Harshit Kapadia: Of course, sir, very happy, sir.
Answer, p hari
P. R. Hari: Okay, since you are happy, I am sure you are keeping track of our progress at the physical milestone. Three ships were delivered on the last day. So, the revenue recognition, the liaison with the Navy, all these aspects are going on. That is the reason why we went for a conservative figure. So, when all this happened and when we formalized the deliveries and handed over the sales revenue, appropriately it was realized from these ships, and the total revenue now comes to our best figures of 7,200. Thank you.
Question
Harshit Kapadia: Understood, sir. Sir, a follow -up question is, sir, on the NGC order, if you remember, sir, the last time when we met, you were very confident that probably we will be getting this order in, but today also you mentioned that price negotiations are going on. You are expecting the order to come soon. So, where is the hiccup, sir? Where is the delay? And by when do you think the NGC order would come? In addition to this, you also highlighted certain smaller projects like 22 water jets and other smaller-sized projects. Now, are there two winners or it will be a single winner, if you can highlight, sir?
Answer, p hari
P. R. Hari: Okay. Thank you. First thing, I would like to clarify that the price negotiations are completed. Actually, when we directed at that stage itself, the price negotiations were completed. They have been completed. We were expecting the contract to be signed by 31st March because at that point of time, the contract negotiations, the terms and conditions, those aspects were in progress. We very optimistically appreciated that it would get completed by 31st March.
Answer, p hari
Our current assessment is that the contract will be signed during the current quarter that is June. It is almost the right direction. No red flags so far. Coming to the smaller projects which you mentioned, the first project of Multipurpose Vessels is a single shipyard. There are only two ships out there. The OPV project for Coast Guard, five ships, again, a single shipyard. And the Interceptor Boats , again, is a single shipyard.
Answer, p hari
But the other project, the 120 Fast Interceptor Craft and the P-17 Bravo, the Fast Interceptor Craft 120, it will be split between two shipyards, 80 and 40. That is the likely RFP conditions. And the second project, the P -17 Bravo, again, would be split between two shipyards, four and three, like the current P -17 Alpha project. The Mine Countermeasure Vessel , the 12 -ship project, would be split between two shipyards, eight and four, and the landing platform dock, two and two. But these two, the last two projects which I mentioned are some time-off because I expect the RFPs to come out sometime during the latter half of the current financial year. I think that gives you a broad perspective of the orders in hand, including the breakup plan.
Question
Bhavya Gandhi: Yes. My first question is regarding when can we see the revenue booking for NGC starting? And in the intermittent period, you were supposed to have smaller ships where you could contribute to the revenue. So, if you can throw some light, how will the revenue numbers look like for the next two years?
Answer, p hari
P. R. Hari: Thank you. The revenue booking from NGC, if the contract is signed during the current quarter, we expect the booking to happen during the latter half of the next financial year, that is FY28. The second half of FY28, we expect the revenue generation from NGC to commence.
Question
Bhavya Gandhi: NGC, yes, NGC in particular.
Answer, p hari
P. R. Hari: Okay. Let's see. Since we have been interacting over multiple Investor and Analysts Meet, shipbuilding follows an S-curve, which means the initial phase, when the preparatory activities for construction are in progress, the revenue recognition is minimal. Then it picks up as the physical construction starts, in terms of block fabrication, the hull fabrication, where the steel and certain outfit items get into the platfo rm. Then comes the next phase, where the steeper phase, where the equipment gets lowered. And as you are aware, around 65% of a ship's cost itself is equipment. Then the outfit flattens, and the ship is moving towards the delivery, and once delivered, the balance revenue is made.
Answer, p hari
So, considering this aspect, in the first year, assuming, again, we are signing the contract in the 1st Quarter, we don't plan any revenue recognition during the current year, or even during the next half. The next part, what I mentioned to commence revenue recognition, that will be a very mediocre amount, which is coming from the design inputs, which lead to getting the ship ready for construction. The major chunk of the revenue recognition will start from FY29, when the hull construction would have matured, and at least some part of the equipment comes in. So, this is what I can say at this moment. Now, currently, as I mentioned, we have about 39 platforms under construction, and again, as what I stated during this very interaction, that a few of these vessels are in a mature state, where the production progress is very good, as per the contractual timeline . So, we expect that the revenue accrual during the current financial year is going to be very healthy, and in line with what we have been seeing during the last three or four years. And for the next year, that is FY28, we will pad up with the balance projects what are in hand, the NPOPV project, the f irst vessels, and the commercial vessels, what we have in hand.
Answer, p hari
And of course, we also expect a reasonable number of orders, which are on the anvil coming our way. So, naturally, the order book deficit currently is there, will be stemmed up by NGC1, and at least 20%-25% of the balance, what is in the kitty.
Question
Bhavya Gandhi: Thank you. Sir, can we reasonably assume that FY28 will not see dip in terms of revenue, because that's the fair understanding?
Answer, p hari
P. R. Hari: No, I did not state that. All I am telling is that by FY27, the current financial year, a couple of more projects would get completed, and the remaining projects would give us revenue during the next year FY28.
Question
Bhavya Gandhi: Okay. And, sir, during these two years, how should one look at, because you've been guiding for high -digit EBITDA margin, while NGC will be in the design phase. So, there will be some sort of de -operating leverage also, because your fixed cost will continue to remain elevated. So, if you can guide for at least ‘28-29, how the EBITDA margins will look like beyond ‘27?
Answer, p hari
P. R. Hari: In case of FY28 and ‘29, we will try and maintain similar margins. I can only say we will try and maintain similar margins, because at that point of time, the balance projects which are currently in hand, I am talking about the OPV project or the commercial research vessel projects, they will be getting completed. So, we will try and maintain similar margins during that year also. Okay. Also, in FY28 and ‘29, the NGC would start giving us revenue, perhaps maybe to the tune of around 3 %-4%-5% of the overall project cost, which is substantial. And the next year, when the construction starts again, the project will start giving revenue. And I also mentioned that what is coming from NGC in the next financial year, second half, from the balance of the projects which are on the anvil, let us take the P -17 Bravo, where there are only as of now, again, like the NGC, there are only four shipyards.
Answer, p hari
And with our kind of experience and expertise in building these vess els, we stand a very good chance of winning. And this is a very big order. So, even if we go by a conservative figure of GRSE forget L1, even if we become L2, and if the contract follows a similar pattern exactly one year from the time NGC is getting completed. The revenue recognition from 17 Bravo will commence in FY29. So, the deficit or the gap at this moment is not a grave concern. This is my observation.
Question
Sanjeev Zarbade: Yes, sir. This is Sanjeev here. Sir, my question was regarding the margins. So, we have done very good margins in FY25 and FY26, aided by the writeback of excess provisions that we would have taken on the various major platforms that we are building. So, for the future, should we kind of adjust for this writeback that we did, to really look at the sustainable margins for the future, which could be around 9% to 10%?
Answer, p hari
P. R. Hari: Sorry, Mr. Ashish, could you repeat the question, please? Somehow your voice was sounding a bit distorted. Could you please repeat the question?
Show 13 more questions
Question
Sanjeev Zarbade: Yes, sir. What I was saying was that we did 8.3% EBITDA margin in FY25 and then 11.6% in FY26. Now, if we look to maintain margins, then should we adjust for the benefit that we received from the writeback that we took in the 4th Quarter of FY25 and FY26? Is that the right way to look at how the margins will plan out for the next three - four years?
Answer, p hari
P. R. Hari: Yes, all I can say, frankly, the question was not clear purely, not because of the thing that I couldn't decipher properly. The voice is a bit dist orted, but what I understand is you are asking about the EBITDA margin trend, what will continue in the current financial year. I can assure you that the current financial year, the margins are going to be similar. That's what I understand you asked, because it's not clear.
Question
Sanjeev Zarbade: I was asking that if we adjust for the benefit that we took on account of the provision write-back in the 4th Quarter of FY25 and FY26, sustainable margins are around maybe 9.5% to 10%. So, that is the way margins should work out for the future, or we should go by the current level of around 11.5% margin that we did in FY26?
Answer, p hari
P. R. Hari: We will be able to maintain similar margins, what you said last. We will be able to maintain similar margins in the coming year, that is the current year.
Question
Raj Shah: Yes, so for the ships that have been delivered in the last two to three years, will the spare sales for those ships start reflecting in our numbers in the next two, three years, which could be a reason for margin of upward trajectory?
Answer, p hari
P. R. Hari: I will tell you this way. In the last two years, the ships which were delivered, one, of course, is the P7 Alpha project. We have delivered two of the ships and survey vessels we have delivered four of them in the last year and the previous last two years, and four of the Anti-Submarine Water Craft projects. All of these projects are high -value projects and all the orders for this equipment, the re is spares and equipment, were placed much earlier and these prices were fixed. So, we did not find any escalation coming or any impact. So, the margins are intact. They have not been affected by any of the market fluctuations.
Answer, p hari
I am not sure that that is the question which you asked because the question was not clear, but we have been able to maintain good margins on these ships, these three projects.
Question
Raj Shah: No issues. Sir, regarding this export market, do you see any new orders that you are eyeing up or any possibility of orders that will be coming in the next year or two?
Answer, p hari
P. R. Hari: Yes, definitely yes. Definitely yes because most of the European ship owners are now looking at India because of two reasons. One, their standard destination, that is China, Korea, they are jam-packed with orders. So, that is one reason. And the second reason is that they have found that the Indian pricing is affordable for them and competitive for them and so is the quality of the business. So, a few of the European clients are in dialogue with us and I am very confident that in the next year or so we should be able to conclude more contracts for commercial vessels, especially from the European market. So, we see opportunities in this.
Question
Kavish Parekh: Hi, sir. Thanks for the opportunity. While you did highlight that the order for NGC could be signed sometime in this quarter, could you also share more details on the likely vendor ecosystem for the project, including the potential key suppliers and their respective workshares?
Answer, p hari
P. R. Hari: See, yes, we are expecting the order for the contract for the NGC to be signed in the current qua rter. And for the next projects, that is the 120 FAC, 31 Waterjet FAC and the 17 Bravo projects, we expect the RFPs to come out in the next three months. Also, I had mentioned that three of the bids are currently live. So, the MPV, the bid submission has a lready taken place. And for the OPV for the Coast Guard and the interceptor boats, as I appreciate the bid submission is towards the end of this month or early next month. So, conservative time if we take for the smaller projects, from the time the bid is open, the contract would get signed within six months. And for the large project like 17 Bravo, based on our experience with NGC could take up to a year, nine months to a year.
Question
Kavish Parekh: So, sir, what I was trying to understand is, specific to the NGC program, who would be the key vendors for you for the project? And it would also be helpful if you could share the electronics content within the overall program. So, what proportion of the program value could be attributable to electronics and which major systems would this include?
Answer, p hari
P. R. Hari: You are specifically asking about the NGC project with respect to our downstream vendors. I n the NGC project, about 65% of the overall project cost is for the equipment and systems. And of this 65%, approximately about 55% to 60% is accounted by the electronics, that is the weapons, sensors, and associated electronics. And the balance, that is around 40 % to 45%, comes from the machinery and systems, that is like the propulsion engines, the air conditioning plants, and the associated machinery systems, and also the steel. So, a large chunk of electronics, of course, comes from our sister PSU, Bharat Electronics. And since the field is competitive, there are a few other Indian OEMs who are in the fray . Does that answer your question, or do you want more information?
Answer, p hari
Just for your information w e have already started discussions with several of the OEMs as part of the preparation for the project. And once the contract is signed, we will be placing the down stream orders. So, we expect the first of the downstream orders to be placed within three months of signing of the contract, and between three to six. You see here, the customer is also involved, because since it is a big project, a weapon- intensive project, the customer is also associated when the technical specifications are finalized. So, the majority of the orders will be placed between three to six months of signing of the contract.
Question
Harsh Mulchandani: Thank you for the opportunity. Sir, we have discussed that right now we are seeing good momentum. Even we have inquiries from the European companies because of our pricing advantage. So, do we have enough capacities to take large orders from them, and is there a possibility to aim for even higher margins than what we have seen in the current year, which is obviously very good, but because we are globally competitive and we have good quality also, can we position ours elves as a higher margin player also going forward from the company perspective?
Answer, p hari
P. R. Hari: Yes, the opportunities are good, and the current projects we have taken because we wanted an entry into the commercial ship building segment. So, when we follow thi s current order with more orders, definitely we will be going for projects with higher margin and perhaps with more order value. Just to give you a perspective, the project what we have taken on is a multi - purpose vessel, which is a medium -sized, state ord er value remaining is around INR 1,400 to INR 1,500 crore. If you just take any of the naval projects, be it additional Anti-Submarine Shallow Water Craft project, those ships are very small ships, but weapon-intensive ships, and the cost per ship is around INR 675 crore. So, it almost comes to around INR 5,000 to INR 5,500 crore. So, what I am trying to convey is that while the commercial ship building export market looks attractive, the money and the margins are very much within warship building. So, what I had stated in the beginning of this discussion that about INR 1,50,000 odd crore of RFPs which are on the anvil, so there is enough in that segment to meet the order book or profitability aspirations of the company.
Answer, p hari
However, the commercial ship building projects which are on the anvil, what we will be looking for is something that is definitely with good margin and projects which are attractive, like let us say hybrid platforms of large -size vessels with complex proportions which are challenging as well as attractive. To answer your question in a nutshell; yes, we will be going in for commercial ship building projects. You can see a few of them coming up in the next year or so with reasonably good margins. Otherwise, we would not go in for any projects with low margins, especially when we are concerned with commercial ship building export orders.
Question
Harsh Mulchandani: Got it. Thank you. And just one more question. I had to understand now with the commodities, prices increasing, etc., so I am assuming we would have an arrangement with the clients for cost pass-through. But I just wanted to get a sense that is there any delays in general that we see with respect to these cost pass-ons or it is these negotiations happen simultaneously on a monthly basis? How does it work on ground?
Answer, p hari
P. R. Hari: Thank you. Yes, there is a deviation or the escalation with respect to the cost of commodities there has been an impact. And so has there been an impact with respect to time. Now, coming to the cost factor, all the project s that we are currently executing, we have factored this and orders were placed much earlier. So, cost escalation with respect to the existing orders that we have for the ongoing projects. The time delays are marginal because what we have seen is that wher e minor delays with respect to steel or the industrial gas which contribute towards fabrication within the premises, yes, there is a very, very marginal insignificant impact which we are able to absorb in the overall scheme of things. For all the new contracts which we are yet to sign or where we are bidding, we will factor this aspect of uncertainty also.
Answer, p hari
In the existing contracts, just to say, all the contracts are fixed price contracts and so are our orders with our subcontractors or vendors. So, there is no impact as such.
Question
Rahil Dasani: ASW Vessels, the Anti -Submarine Warfar e Vessels , the few that we have commercialized and that are in the water as of date, I believe that without fitment of all the equipment on it, usually the Government doesn't give us the PBGS amount, which is usually 10% of the whole tender, if I am not wrong. And from what I know, we were left with the installment of the sonars on those vessels.
Answer, p hari
P. R. Hari: Okay. Since you asked a specific question, I will try and give a very clear answer. The stage payment for the naval projects as per the DAP, the Defense Acquisition Procedure, are absolutely clear. These are covered in 15 stages of payment, with the 14th stage coming at the time of delivery and the 15th stage, that's the final stage, coming after one year of warranty. And to answer your question with respect to sonar, there are two types of sonar in the ship. One is the fixed sonar, hull-founded sonar, which has already been installed, and the variable depth sonar, it is a developmental item. It's a buyer-furnished item.
Answer, p hari
So, we are not impacted by the non -availability or availability of that item. What I am trying to say, there is no financial impact with respect to the bank guarantee or PBGS, the firm's bank guarantee.
Question
Rahil Dasani: Got it. And with the upcoming NGC and the NGOPV, do they also have a similar sonar profile to the ASW, both surface as well as underwater sonar?
Answer, p hari
P. R. Hari: No, this is confidential information. You are asking me the weapon fit of a naval platform. You would like to-- Rahil Dasani: Got it.
Question
Sunil Shah: Yes, sir. Thanks for the opportunity. Sir, I missed a few points early on. And what I understand is that the P-17 Bravo is broken up between four and seven. There are other two big ticket si ze orders which you mentioned, the INR 32,000 crores and the INR 35,000 crores. I believe those order announcements could be scheduled in FY28. Sir, the order and the breakup, could you kindly just repeat it for me, please I just missed that.
Answer, p hari
P. R. Hari: Thank you, Mr. Shah. The P-17 Bravo, the total number of ships is seven. And as per the AoN accorded by the Defense Acquisition Council, this is the open- source information. The project will be between two shipyards, that is four and three. The L1 will get four and the L2 will get three. Coming to the next two projects, that is the mine countermeasure vessel project. It's a 12 -ship project.
Answer, p hari
The AoN value is around INR 32,000 crore. And it will be split between two shipyards. L1 shipyard getting eight and th e L2 shipyard getting four. Coming to the LPD project, the order, the AoN , as my memory goes, it's around INR 35,000 crore. And it will be two plus two. These are the big-ticket size order, what I mentioned.
Question
Sunil Shah: Right. Sir, thanks. Thanks for sharing this. And this could be expected by FY28. So, sir, my context is with your tenure. So, would we all hear this great news whenever it certifies from your kind self in FY28 itself? How does it work I just want to know that, sir.
Answer, p hari
P. R. Hari: The first part to answer and second part you may have to ask again. The first part we expect the RFP for P-17 Bravo to come out in the current quarter. And the RFP for the other two projects could come by end of the financial year. So, if the RFP for the P-17 Bravo comes by 1st Quarter, then the contract could be completed as early as end of the current financial year, that is FY27, going by the NGC trend. And the other two projects in the next financial year.
Question
Sunil Shah: Thanks. Thank you so much, sir. Thanks for all this.
Answer, p hari
P. R. Hari: Thank you. And thank you Concept for arranging this conference. It was an interesting session. And we had a few interesting queries during the session. And as usual, I look forward to the Investors and Analysts Meet and looking forward to interacting with you all after we announce the Results for the next Q1 FY27. Thank you.
Questions about this call
- When was the Garden Reach Shipbuilders & Engineers Q4 FY26 earnings call transcript filed?
- Garden Reach Shipbuilders & Engineers filed the transcript with the exchange on 19 May 2026. This page is built from that transcript.
- What does this page list?
- 81 statements from the transcript across 8 topics, 55 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 23 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.