Earnings call
Interarch Building Solutions Q2 FY27 earnings call: Interarch Building Solutions' residual order book was in excess of INR2,000 crores as of 31st of October
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Interarch Building Solutions' residual order book was in excess of INR2,000 crores as of 31st of October. The company is aiming for its order book to be about INR200 crores to INR220 crores a month in the next 12 months; its current order book reflects about nine months of production. Interarch Building Solutions' Andhra Pradesh Phase 1 and both Gujarat phases are operational and will ramp up quickly in the following quarters. Interarch Building Solutions' PAT was INR30.7 crores in the quarter ended September 30, 2026, compared with INR32.3 crores, mainly due to higher depreciation after capitalizing two new facilities at Gujarat and AP and lower interest income due to expenditure on capital projects. The company is choosing business from traditional and regular customers and new building types such as data center and high-rise, prioritising safe and reliable customers, better pricing and 100% variable pricing.
The numbers management gave
Results
- Interarch Building Solutions' PAT was INR30.7 crores in the quarter ended September 30, 2026, compared with INR32.3 crores, mainly due to higher depreciation after capitalizing two new facilities at Gujarat and AP and lower interest income due to expenditure on capital projects.
Show source
In terms of our financial highlights and some numbers, coming to the financial performance of this Q2 of FY27, The revenue for the quarter stood at INR505 crores, compared to INR491 crores the same quarter last year.
- Interarch Building Solutions' EBITDA margin was about 8.3% of EBITDA in Q2, compared with 8.5% in the same quarter last year.
Show source
EBITDA margin for Q2 was about 8.3%, marginally different than what it was in the last year same quarter, 8.5%.
- Interarch Building Solutions' EBITDA for the half year was INRS 1.1 crores, up from INR73.3 crores in H1 FY26, reflecting growth of 10.7%.
Show source
Revenue for the half year stood at INRYGS crores, registering a year-on-year growth of 10.7%, compared to INRS72 crores of H1 FY26.
- Interarch Building Solutions' EBITDA margin was 8.4% of EBITDA in HI FY27, and its PAT for the half year was INRS8.9 crores, compared with INR60.7 crores in H1 FY26.
Show source
EBITDA margins for HI FY27 remain stable at 8.4%, and PAT for the half year stood at INRS8.9 crores, compared to INR60.7 crores in H1 FY26, reflecting similar performance year on year, after accounting for depreciation and interest.
- Sales volume for Q2 was 41,600 metric tons.
Show source
So, the volume for Q2 was 41,600 metric tons.
- EBITDA remained 8.4% despite steel price increases over the last many months.
Show source
Despite whatever has happened, our EBITDA has remained exactly the same, 8.4%.
Show 12 more statements
Results
- Interarch Building Solutions' second-quarter results were broadly in line with the same quarter last year, Q2 of FY26.
Show source
Our second-quarter results have been broadly in line with the same quarter last year.
- Interarch Building Solutions' first-half project execution and order conversion reflected the seasonal pattern of slower execution cycles during the monsoon.
Show source
And consequently, project execution and order conversion reflect this seasonal pattern in all our results for the first half of the year.
- Interarch Building Solutions' data centres and other heavy-structure buildings had better margins and a little less risk than standard pre-engineered buildings because clients do much of the design element.
Show source
So the data centres and other things right now have a better margin than the standard pre-engineered buildings and a little less risk, because the client does a lot of the design element.
- Working capital days increased slightly because it stocked up on steel amid erratic supply chains and rising prices, opened two new plants in Gujarat and heavy structure, and those plants needed critical mass; it says there is room to improve receivables and inventory and may bring working capital nearer to its previous level as steel supply becomes more predictable.
Show source
But in the current situation, these are three or four factors which led to a slight increase in the working capital days.
- The company says expenses on newer building types and exports rise disproportionately to sales, with revenue from data center and export orders coming in later quarters; capacity, revenue and EBITDA do not move quarter to quarter, and EBITDA also reflects unusual world conditions over the last six to eight months, including oil prices and steel prices.
Show source
Arvind Nanda: See, as we get into newer kinds of buildings, into exports, see, that expense goes up disproportionately to the sales.
- Disrupted steel supplies have required Interarch Building Solutions Limited to buy more material and hold higher stocks.
Show source
So, supplies have also been disrupted, which means higher stocks for us because we have to buy more material to keep in stock because of the distuption.
Money and capital
- The company spent over INR250 crores on its capex building in the last two years, plus maybe two years and a quarter.
Show source
And we have spent over INR250 crores in the last two years, plus maybe two years and a quarter, on our capex building only.
- The company raised INR180 crores at the IPO time, of which 50% was for capex and 50% was for working capital and other items like general expenses.
Show source
This is from the IPO time, when we raised INR180 crores, out of which 50% was for capex, and 50% was for working capital and other items like general expenses.
- The company had spent INR250 crores till date on its capex building by completing its complete Andhra plant, updating all its other plants, adding a line in Kichha and a heavy structure plant in Andhra Pradesh Phase 1, and completing both phases of the Gujarat plant.
Show source
But we have actually spent INR250 crores till date already on our capex building by completing our complete Andhra plant, updating all our other plants, adding a line in Kichha and a heavy structure plant in Andhra Pradesh Phase 1, and Gujarat plant both the phases done.
- The company has completed the legal formalities required for its QIP and can launch it on 72-hour notice once Ambit determines the timing.
Show source
But we have done all the legal formalities, so we can launch at a 72-hour notice once Ambit feels that's the right time.
- The company used internal resources for its very high capex spend and working capital limits for working capital and other areas of growth and expenses it was trying to develop.
Show source
So the capex spend has been very, very high, very fast, and our interal resources have been used, and working capital limits have been used for working capital, as well as our other areas of growth that we are looking at, the other expenses that we are trying to develop.
- The initial funding planned for Interarch Building Solutions' Open Web Steel Joists systems venture was INRSO crores.
Show source
The initial funding as planned was INRSO crores for the OWSJ venture.
What it expects ahead
What management expects
- The company is aiming for its order book to be about INR200 crores to INR220 crores a month in the next 12 months; its current order book reflects about nine months of production.
Show source
So, I would say that in the next 12 months, we are aiming for our order book to be about INR200 crores to INR220 crores amonth.
- The company remains confident it can achieve revenue of INR2,150 crores by the end of the financial year, citing capacity, order book and clearances; H1 revenue was 10% up and H1 is generally less than H2 because most delivery clearances come in H2.
Show source
So, basically, our ability to execute the INR2,150 crores figure that we gave up to end of the financial year is still very much in place.
- The company expects margins to improve in the second half as higher turnover brings operating leverage without a dramatic increase in overheads, but does not expect margins to exceed its previous 9% to 9.5%.
Show source
So it should improve in the second half, definitely, but I don't think it will cross what previously we have done, 9%, 9.5%.
- The company expects better margins in '27-28 as its existing Gujarat plant and heavy structure plant reach full capacity and exports are delivered and improve.
Show source
But next year onwards, I think as the full capacity of our existing Gujarat plant, full capacity of our heavy structure plant, exports actually being delivered and improving, I think we can sce a better margin in "27-28 for sure.
- The company expects to meet INR2,150 crores to INR2,200 crores in '27.
Show source
ButI see that our expenses will also remain a little high.
- The company may incur expenses on exports before earning them back in the beginning.
Show source
In the beginning, it may be a little tight, and we may suffer from expenses because we have to spend money on all these things before we can earn it back.
Show 19 more statements
What management expects
- The company expects the effects of entering new verticals to take a year or two to appear; expenses will rise initially while turnover does not reflect them, and current overheads will cover many new orders without increasing proportionately.
Show source
It might take a year or two to see the effect.
- The company expects to improve profitability as steel prices stabilize or soften in the next few months.
Show source
So, I think there’s a lot of things happening in this country and in the world, and I think if the ultimate result of all that is that we are still on track to give what we promised six to eight months ago, and we are confident to even improve our profitability as we see steel prices will stabilize or soften in the next few months.
- The company does not expect much improvement in margins this year because of unusual events and the costs of starting its exports and heavier-structure verticals, including design engineering, travel and selling costs.
Show source
So, we don't expect any major improvement.
- Export orders will go primarily in the second and third quarter.
Show source
Arvind Nanda: See, the certain amount of exports may have been incurred in the first two quarters, but the export orders we have currently will go in the second and third quarter primarily.
- The company expects higher sales to increase its margin percentage because overheads do not increase at the same rate as turnover.
Show source
So once the sales increase, then the margin percentage automatically increases in our case, because in a lot of cases the overhead is not increasing at the same level as our turnover.
- Steel prices jumped up in October, and steel prices may affect margins again in Q3 before ideally evening out over Q4, Q1, and Q2.
Show source
So it's possible that there might be a ‘margin impact again in Q3, but that should ideally even out over Q4, Q1, and Q2.
- The company expects its variable-pricing element to keep increasing as it gets longer-term heavy-structure orders such as data centers, which are traditionally pass-through; it will not change its policy of taking orders at fixed price in the next couple of quarters and currently does not know whether steel prices will go up or down.
Show source
So our variable element will keep increasing, and I think in the next couple of quarters we are not going to vary, sort of, change our policy of taking anything at fixed price.
- Export is going to be a big vertical for Interarch Building Solutions in the coming years. Replaced by a later filing.
Show source
Export is going to be a big vertical for us in the coming years.
- The company expects better execution and throughput in the quarters ahead as the execution cycle picks up in H2. Replaced by a later filing.
Show source
This shows that our order booking across sectors has been very strong, and as the exccution cycle picks up in H2, we expect better exccution and throughput in the quarters ahead.
- The company expects execution to pick up progressively in the second half of the year. Replaced by a later filing.
Show source
In the second half of the year, we expect execution to pick up progressively.
- The company is confident of achieving better results than last year over a year, in turnover and margins. Replaced by a later filing.
Show source
So over a year, we are still quite confident of achieving better results than what we did last year, definitely in turover, but I think in margins as well.
- The company wants to become an international company and brand serving customers outside India, including in North America and Africa, where it sees a huge upsurge in demand and not so much supply available. Replaced by a later filing.
Show source
And going forward, we want to also make ourselves as an international company, international brand, servicing customers outside of India also, where we are seeing a huge upsurge in demand, with not so much supply available.
Orders
- Residual order book of INR2,000 crores includes approximately INR350 crores to INR400 crores of heavy structure orders yet to be executed, including a commercial building in Delhi and two data centers; about 15% to 20% of its order book qualifies as HSS, including a hospital, data centers, a multi-storey hotel, a commercial building and heavy process buildings for global companies in India.
Show source
So, yes, heavy structure right now, if I talk of the residual order book of INR2,000 crores, approximately about INR350 crores to INR400 crores will belong to the heavy structure, which Page 11 of 20 Interarch Building Solutions Limited November 06, 2026 is yet to be exccuted, which includes, as we said, a commercial building right in heart of Delhi, two data centers.
- Blended order book execution period is about 10 months to 11 months, with most of it scheduled for about nine months.
Show source
So that is the blended order book period, which should be about 10 months to 11 months as blended.
- Order pipeline is generally five times to six times its order throughput per month, and order throughput is about INR600 crores to INR700 crores per quarter.
Show source
So our order throughput is about INR600 crores, INR700 crores per quarter.
- About 35% of Interarch Building Solutions Limited's order book is variable-price, with steel price increases passed on to customers irrespective of when the order was booked.
Show source
So almost 35% of our order book is variable price, wherein, it is a complete pass-on irrespective of when the order was booked.
- The company is constantly bidding for data centres, and its ability to bid for larger institutional projects increases as its heavy steel structure plant expands.
Show source
We are constantly bidding for data centres.
- The company has delivered to customers on time and added to its order book despite supply disruption.
Show source
And I'm still able to deliver to my customers on time, and I'm still able to add to my order book.
- Interarch Building Solutions' residual order book was in excess of INR2,000 crores as of 31st of October. Replaced by a later filing.
What it is building and selling
Projects and capacity
- Interarch Building Solutions' Andhra Pradesh Phase 1 and both Gujarat phases are operational and will ramp up quickly in the following quarters.
Show source
On the capacity expansion, Mr. Nanda already gave you an update that our AP Phase 1 and Gujarat both phases are now operational, and they will ramp up quickly as we move forward in the following quarters.
- Interarch Building Solutions' heavy steel structure plant is currently 25,000 tons and will ultimately reach about 75,000 tons, 80,000 tons by the end of next year.
Show source
So, I think two things are very important for s for high steel: number one, this heavy steel structure plant, which ultimately will go up to about 75,000 tons, 80,000 tons by the end of next year.
- Heavy steel structure plant came into operation on 24th September, and sales from the plant will occur in the third and fourth quarter.
Show source
Heavy steel structure came into operation only on 24th September.
- The company expects to have at least 80,000 tons of capacity in '27-'28 from its Gujarat plant and heavy structure plant in Andhra; the Gujarat plant will add 40,000 tons from next year onwards, and the Andhra plant is expected to contribute approximately 35,000 tons to 40,000 tons next year as its phases are completed.
Show source
So, I would say at least 80,000 tons in '27-'28 should be in place from these two plants.
- Goal is to have usable additional capacity of 100,000 tons by March 2728, and it plans to add another 100,000 tons between '28 March and 29 June to July, with the current plan for another 100,000 tons of salable capacity in the next 14 months to 15 months.
Show source
Page 19 of 20 Interarch Building Solutions Limited November 06, 2026 So, that is the current plan, that in the next 14 months to 15 months, we should have another 100,000 tons of salable capacity in place, and beyond what was at the end of the second quarter this year, before HSS and Gujarat plant came into play, and March '28.
- The company plans to add another 100,000 tons between March-April '28 and June-July '29 to take capacity to about 400,000 tons by 29 currently.
Show source
And then we plan to add another 100,000 between March-April '28 to June-July '29 to take it up to about maybe 400,000 tons by 29 currently.
Show 16 more statements
Projects and capacity
- The company is building a hospital, a hotel, many data centers and a commercial office building in the heart of Delhi.
Show source
We are building a commercial building, an office building right in the heart of Delhi.
- The company has got data centers, hospitals, hotels and a commercial office building for the Government of India in the heart of Delhi, and recently got an airport hangar.
Show source
We have recently even got an airport hangar.
- The company is completely loaded for both heavy structure production lines it started.
Show source
Manish Garg: Absolutely, we are completely loaded for both the lines that we started.
- Interarch Building Solutions' investments in capex and manufacturing capabilities improve execution efficiencies and give it capacity to address total market requirements. Replaced by a later filing.
Show source
Collectively, the investments that we have made in our capex and manufacturing capabilities improves our execution efficiencies and give us the capacity to address the total market requirements.
Demand and pricing
- The company is choosing business from traditional and regular customers and new building types such as data center and high-rise, prioritising safe and reliable customers, better pricing and 100% variable pricing.
Show source
There's a lot of business available in the market, 5o we are choosing business which is for more reliable customers, better pricing, 100% variable pricing; though, steel prices have shown sort of a - they have been unusually moving in one direction for the last eight, nine months.
- Current policy is to take only variable-pricing orders.
Show source
But right now our policy is to take only variable pricing.
- Customer inquiries across Interarch Building Solutions' key markets remained healthy, giving the company confidence in the medium- to long-term demand outlook. Replaced by a later filing.
Show source
But despite these seasonal factors, customer inquiries across our key market remains healthy, giving us confidence in the medium to long-term demand outlook.
Segments
- The company was not focused on exports until two years ago.
Show source
It's just that our focus was not on exports till two years ago.
- The company is starting to get data centre, high-rise building and hangar projects.
Show source
We are now starting to get these buildings.
- The company was already doing a few projects in Africa and making marketing inroads into those geographies.
Show source
We are already doing a few projects there, and we are making strong marketing inroads into those kinds of geographies.
- For heavy-structure buildings, Interarch Building Solutions does not receive payment after the material leaves the factory.
Show source
Second, your payment terms are much strict, meaning you won't receive any payment after the material leaves the factory for those kinds of buildings.
- The company is entering export and heavy structure verticals because net margins are better and risk is lower; export business has no sales, collection or project management cost, and steel prices for heavy structures are completely pass-through.
Show source
So we can get export business, which has no sales cost for us, no collection cost, and no project management cost.
- Erection costs are fully pass-through to customers and vary by building type; freight costs are fully pass-through to customers and vary by location.
Show source
Arvind Nanda: Yes, Yes, these are all fully pass-through.
- The company is getting into new areas including infrastructure, data centers and commercial buildings.
Show source
And getting into new areas like infrastructure, data centers, commercial buildings.
Deals and partners
- Interarch Building Solutions' strategic collaboration with ER Steel Canada, based on the MoU announced in Q4, is advancing its steel construction solutions into the entire North American market.
Show source
Building on the MoU announced in Q4 with ER Steel Canada, we continue to advance our strategic collaboration and take our steel construction solutions to the entire North American market.
- Interarch Building Solutions' partnership with ER Steel brings together Interarch's engineering and manufacturing capabilities in India and ER Steel's deep penetration in North American markets, particularly Canada.
Show source
The partnership brings together Interarch's engineering and manufacturing capabilities in India and ER Steel's deep penetration in those North American markets, particularly Canada.
Risks, rules and outside factors
Outside factors
- Steel prices are at a record high and have not been at their current level since 2022.
Show source
Steel prices themselves are at a record high.
- The company passes through all steel prices for heavy-structure buildings, unlike pre-engineered buildings where steel prices may not always be passed through, protecting margins on heavy-structure buildings.
Show source
First, all steel prices are always passed through always, unlike pre-engincered buildings, where they may not be.
- Steel companies are delivering more material to exports, where they are probably making a better realization, disrupting supplies to Interarch Building Solutions Limited.
Show source
And then on top of that, supply is very disrupted, because these steel companies are delivering more and more material to exports where they are probably making a better realization.
- Steel prices have gone up during the monsoon period, when they invariably start coming down. Replaced by a later filing.
Show source
This time they've gone up in the monsoon period.
- Steel prices are at an all-time high in the last four years, and customers prefer variable pricing because they feel prices will only go down. Replaced by a later filing.
Show source
And variable pricing in this kind of situation, like I said, steel prices are at the all-time high in the last four years.
Rules and policy
- The government released a draft of the 2047 Steel Policy, which Manish Garg said was a boon to downstream companies like Interarch Building Solutions and anticipated steel usage to increase many notches.
Show source
The broader investment environment also looks very stable and favourable, and with the government continuing to prioritize capital expenditure as a key driver, the government has also released the draft of the 2047 Steel Policy, which is also a very big boon to the downstream like us, wherein, government is anticipating the steel usage to go up many notches.
Everything else said on the call
Other
- The company invested heavily over the last two to three years in better people, computer systems, software like SAP HANA, and engineering and project management work.
Show source
For your information, over the last two to three years, Interarch has invested heavily in better people, better computer systems, better software like SAP HANA, and, similarly, in all engineering and project management work.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Chintan Patel: Yes. So, I just want to know what is the heavy steel structure contracts capacity utilization, and how do we ramp up this facility? And what is the EBITDA per ton in heavy steel structure? Or maybe you can just guide us on a margin for a heavy steel structure? Page 7 0f20 Interarch Building Solutions Limited November 06, 2026 Arvind Nanda: Thank you.
Answer, arvind nanda
See, one thing we have to understand that heavy steel structure is not a completely separate item. Heavy steel structure basically means cach piece you can manufacture in that plant can be over five tons each, whereas in our existing pre-engineered building facilities, most pieces are less than five tons. So, a heavy-structure plant lets us build different kinds of buildings; for example, today we can do data centres and high-rise buildings. Many big industrial plants, like lithium battery plants and microchip plants, also need a substantial amount of heavy-structure pieces. Heavy structure is a piece similar to a pre-engineered building piece used in a building, but cach piece weighs over five tons, up to 20 tons o 25 tons. So there is number one, for the building that we are doing, there is no separate vertical for HSS. HSS lets us get into different building verticals.
Answer, arvind nanda
So that is one thing. So, we can now bid for data centres, etcetera. So the data centres and other things right now have a better margin than the standard pre-engineered buildings and a little less risk, because the client does a lot of the design element. These pieces carry more weight. And in these kinds of buildings, heavy-structure buildings, like data centres, high-rise buildings, hospitals and hotels, there is a clear system where two things are very important. First, all steel prices are always passed through always, unlike pre-engincered buildings, where they may not be. So, therefore, your margin is more protected when you do those kinds of buildings.
Answer, arvind nanda
Second, your payment terms are much strict, meaning you won't receive any payment after the material leaves the factory for those kinds of buildings. So, I think two things are very important for s for high steel: number one, this heavy steel structure plant, which ultimately will go up to about 75,000 tons, 80,000 tons by the end of next year. Currently, it is 25,000 tons and will allow us to bid for all these buildings. We have already got, like Manish mentioned, data centers, hospitals, hotels, a commercial office building for the Government of India in heart of Delhi. We are constantly bidding for data centres. We have recently even got an airport hangar. So our ability to bid increases; therefore, we have a new vertical of buildings we can do, and we feel that as the project gets larger and goes to these institutes, the margins are better protected.
Answer, arvind nanda
So margins are similar, but I think the net margin we will make will be higher too because our general overhead will not increase by the same amount. If our general overhead can be covered partly by the existing overhead and new overhead, we will make more net margin. So I think we - our anticipation s that we will make more margin as we get into these kinds of buildings, bigger buildings, bigger orders, bigger values, ctcetera. ‘What was the second part of your question?
Question
Chintan Patel: So basically, sir, I just want to know the overall margin improvement trajectory, as we are adding heavy structural steel and we are going to build a lot of high-margin projects such as data centres and hospitals and other projects. So, how do you see your margin improvement trajectory going forward as we embark on export orders? Page 8 0f20 Interarch Building Solutions Limited November 06, 2026 Arvind Nanda: So, in both these verticals, the primary reason we are entering both these verticals is that the net ‘margins are better; and number two, the risk is less.
Answer, arvind nanda
And these businesses will come to us because of our existing overhead infrastructure, which I think will get more leveraged. Our operational leverage will improve because the expense -- in selling an export building is not going to be substantially there for us. So we can get export business, which has no sales cost for us, no collection cost, and no project management cost. We just have to design, engincer, ‘manufacture, and supply on an LC basis. Similarly, for heavy structures, as 1 explained, margins will be better protected and higher because net margins will be higher. Because sometimes the design is not part of our thing, Even if it is, the steel price is completely pass-through, so that risk element goes away too. And on the project side also, in many cases, the project execution may be done by the client, who is normally a contractor in these cases, and it could even be done directly by the client or contractor with our erector.
Answer, arvind nanda
So, we are trying to get into these verticals to make higher margins and enter different businesses to help us grow; that is the idea. So I think we'll achieve both objectives. It might take a year or two to see the effect. So in the beginning, expenses will go up, and tumover won't reflect that. Still, we feel our current overheads will cover a lot of the orders we get rather than increasing overhead proportionately.
Question
Chintan Patel: Okay. Got it, sir. And what kind of the order pipeline we are envisaging for the coming quarters, as we already have a INR2,000 crores kind of the order book in our book. So, what new orders are we going to bid for, or what order outlook are you targeting?
Answer, arvind nanda
Arvind Nanda: See, our order book should normally reflect what we can deliver to the customer. We can't book orders which are beyond the customer's schedule. So normally, in pre-engineered buildings, including buildings like data centres and all, we have seen that they are very large orders; data centres could go from 10 months to 11 months. Most of the pre-engincered buildings are between four to eight to nine months. You don't really get many orders which go beyond that. So, my capacity and the order book must match. As my capacity goes up, I can increase my order book.
Answer, arvind nanda
So, you can sce that every quarter our order book is increasing a little bit because our capacity is going up. So, I would say that today we have 9 to 10 months of capacity in the order book. That is what it should reflect. Even if I can take more orders, I can't take them because I can't deliver. So, I would say that in the next 12 months, we should be doing INR200 crores plus business every month. That is our capacity. With Gujarat, both phases are on, and one phase has heavy structure.
Answer, arvind nanda
So, I would say that in the next 12 months, we are aiming for our order book to be about INR200 crores to INR220 crores amonth. So, the current order book already reflects about nine months of production. Page 9 0f20 Interarch Building Solutions Limited November 06, 2026 As capacity increases, the order book can grow as market business becomes available. Of course, we are trying to choose business from our traditional customers, our regular customers, new kind of building that we want to get into like data center and high-rise. But we want to deal with very safe customers. Of course, we have a choice today. There's a lot of business available in the market, 5o we are choosing business which is for more reliable customers, better pricing, 100% variable pricing; though, steel prices have shown sort of a - they have been unusually moving in one direction for the last eight, nine months.
Answer, arvind nanda
So, we want to protect ourselves from any steel price increase or decrease, wherever we can get a better margin, and where the customer is top quality, and it gives us the ability to do new kinds of buildings. Otherwise, in market there are many orders. I mean, it is not a problem to pick up orders. But it must reflect our ability to deliver. So, I would say that INR2,000 crores we will probably have to deliver latest within the next nine months. And, of course, it will pick up as we increase capacity, which we are desperately trying to increase our capacity everywhere because the market is going very fast.
Question
Chintan Patel: Okay. Got it, sir. And just typically, what kind of the margin you desire on a particular order? It could be any range for a particular order which you want to bid on. Any kind of the color you want to give on that part?
Answer, arvind nanda
Arvind Nanda: See, we feel that 10% to 12% is what we should be aiming for. Let's say we were talking about next 12 months. Ultimately, in the long term, I feel a company like ours should be caming upward of 14%, 15%. Don' forget: we do design engineering, full manufacturing of the building, and project management. So, we are actually working like three different companies and not really eaming the margin of even one good company. But competition and the steel price increases and decreases, and all these things have taken alittle bit of a toll. And I think going forward we will increase it not only by getting better margins from customers but by eaming better margins, by having better internal economies, definitely by operational leverage.
Answer, arvind nanda
As we get into more and more bigger orders, our operational leverage will go up. If our aim today is to get 10%, I think increasing the size of the business, turnover, and doing these larger orders will help us cam a better margin. So, I don't think our overheads will grow with the same level. So, camings should go up. So I would say that within two years we should reach 11% to 12%. Also, the other two verticals, like Isaid, data centers and these will kick in, exports will come to some substantial amount, even if it is INR100 crores or INR200 crores in two, three years, it will still give us some better margin. So, we aim to increase it.
Answer, arvind nanda
We are not happy at all. I mean, currently EBITDA is about 9% or something, 8.5%. I don't think that is the kind of EBITDA we deserve as a company. But yes, right now we are in a period where we have to put a lot of expense into the new verticals we are starting, and the revenue from that isn't commensurate with the expense. But I think it will clear up within, say, '27-28 at least. Page 10 of 20 Interarch Building Solutions Limited November 06, 2026 Chintan Patel: Okay.
Question
Rahul Kumar: Yes, hi. Sir, just one question on the working capital. I think this first half has actually seen an increase in these working capital days from 66 to 86. I think last time you mentioned that the share of larger orders has increased, which has resulted in this. So, is this sort of a more of a normal working capital now from onwards?
Answer, manish garg
Manish Garg: Yes, sir. I can answer that. So, the working capital actually s a function of, like you rightly said, how long that order is taking to get exccuted. So, we have the bill certification process in many orders, but all orders that we choose, we choose very carefully, our customers. So, while the order-to-cash cycle may have increased a litle bit, the payment remains safe. So that's one reason, and we are executing larger and larger orders of that kind. Second is that the last quarter has been very erratic in terms of the steel supply chains.
Answer, manish garg
So, to be able to keep delivering on time, we had to stock up a little bit on the steel inventories also, and the prices also went up. So it could be a function of that. In addition to that, we opened two new plants and made them operational, which was Gujarat, as well as the heavy structure. And as you know, each plant will have to have some critical mass for them to execute. So, while we say that there is definitely a room to improve working capital from a receivable and inventory standpoint, but as the steel situation of the supply chain improves and become more predictable, we can try and bring it somewhere near to what it used to be. But in the current situation, these are three or four factors which led to a slight increase in the working capital days.
Answer, arvind nanda
Arvind Nanda: 1 think I would just like to add that the net working capital is still in the 40 days or 42 days because we also have customer advances, which is a part of our business. So, the net current working capital, I think is in still 40, 42 days if 'm not mistaken.
Question
Rahul Kumar: Okay, thanks. And second question is on the heavy structure. So, out of this INR2,000 crores order book, would you have a share of order book from heavy structure part of the business?
Answer, manish garg
Manish Garg: Yes. So, yes, heavy structure right now, if I talk of the residual order book of INR2,000 crores, approximately about INR350 crores to INR400 crores will belong to the heavy structure, which Page 11 of 20 Interarch Building Solutions Limited November 06, 2026 is yet to be exccuted, which includes, as we said, a commercial building right in heart of Delhi, two data centers. And as Mr. Nanda also explained that it could be part of our standard pre-engincered building core competence, but the pieces which are heavier qualify to be HSS. So, in overall scheme of things, right now about 15% to 20% of our order book qualifies to be in the HSS segment, consisting of a hospital, many data centers, a multi-storey hotel, and a commercial building, and some of the very heavy process buildings that we are building for global companies in India. So, it's about in the vicinity of INR300 crores and INR3 50 crores out of our INR2,000 crores net order book right now.
Question
Rahul Kumar: Okay. So, basically, which means that we can probably utilize the two capacities, which are being commissioned right now for this heavy structure products over next...?
Answer, manish garg
Manish Garg: Absolutely, we are completely loaded for both the lines that we started. Absolutely right.
Question
Akshay Kolekar: Thank you for taking my question. Hope I am audible. So my first question is on revenue. So, we see that the Q2 revenue growth was only 2.9% year -on -year. IfI consider HI revenue, then the growth will be around 10% to 11%. And the earlier you guided for FY27 revenue will be around INR2,150 crores to INR2,200 crores. So, that indicates the average quarterly run rate is approximately INR600 crores every quarter for Q3 and Q4. Given the current H1 performance, do you remain confident in achieving FY27 revenue guidance? And what does the confidence that the business can deliver the required acceleration in H2, and INR600 crores quarterly run rate is achievable from existing ord
Answer, arvind nanda
Arvind Nanda: See, we always normally as a company take HI as a guide rather than Q1, Q2, because as we explained earlier also, that can vary. Last year Q1, I think was lower than Q2, and this year Q1 is higher than Q2, like that. So, I mean, H1, if you sce, is 10% up, and H1 is generally less than H2. That is the way, because most of the clearances we get to deliver are in the H2 part of it. So, we are very confident that the capacity exists, the order book we have and the clearances we have. So, basically, our ability to execute the INR2,150 crores figure that we gave up to end of the financial year is still very much in place. There is no change in that.
Question
Akshay Kolekar: Okay, cool. And the next question on EBITDA margin. So, in the long term, EBITDA margins you have guided around 9.5% to 10% by FY28. However, currently the margin stands around 8% t0 8.5%. So, could you just help to understand how do you achieve this target EBITDA? Page 12 of 20 Interarch Building Solutions Limited November 06, 2026 And specifically, how much improvement do you expect from operating leverage, heavy structure, or exports? And why is the margin lower this quarter? Is it because of fluctuation in steel price, freight cost, or site execution expenses impacting the margin?
Answer, arvind nanda
Arvind Nanda: See, as we get into newer kinds of buildings, into exports, see, that expense goes up disproportionately to the sales. So, as we get more into, let us say, trying to get a data center order is much more costlier for us to get it than -- because the turnover will be much less in that quarter. Turnovers will come in the later quarters. Like, we have some export orders, but the tumnover of that export order will come in the later quarters. So, as you try to build up capacity, unfortunately, capacity, revenue, and EBITDA don't work on a quarter-to-quarter basis. These are a little longer term steps that you take to build the company. So, there can be an immediate effect, but it's not worrying us because we feel that -- and don't forget, the EBITDA also takes care of the very unusual position in the last six to eight months of the world situation, oil prices, and steel prices.
Answer, arvind nanda
The way steel prices have behaved this year, we have not seen them behave like this for last four or five years. So, we have taken care of that also. We have taken substantial increases from our customers in many cases, rechanged our prices, tried to can better margin. So, despite all that, if the EBITDA margin is only 0.2% down from last year, I think the situation is very well managed, in that sense. So, we are not worried. But yes, if you look at what is happening in the world for the last 10 months, 11 months, it's been a very, very unusual and very tumultuous situation, which we have to handle on a day-to-day basis. Sometimes, the steel prices are moving up unusually, sometimes on a weekly basis.
Answer, arvind nanda
Truck prices vary because oil prices have been going up, in that sense. So, I think there’s a lot of things happening in this country and in the world, and I think if the ultimate result of all that is that we are still on track to give what we promised six to eight months ago, and we are confident to even improve our profitability as we see steel prices will stabilize or soften in the next few months. I think we have done pretty well, considering all this. Steel prices themselves are at a record high. We have not seen these steel prices since 2022, at what level they are today. Invariably they start coming down in monsoon. This time they've gone up in the monsoon period.
Answer, arvind nanda
And then on top of that, supply is very disrupted, because these steel companies are delivering more and more material to exports where they are probably making a better realization. So, supplies have also been disrupted, which means higher stocks for us because we have to buy more material to keep in stock because of the distuption. Then many times going out into the market to traders and dealers to buy because if I can't finish my building because of one size, I can't wait. And I'm still able to deliver to my customers on time, and I'm still able to add to my order book. But, yes, a few things need to get under control, Page 13 of 20 Interarch Building Solutions Limited November 06, 2026 like debtors and stock and overall management of production, productivity, and costs of production. But there are too many things happening right now, and I think we are trying to control all of them. And, in fact, I feel that if EBITDA has gone down from last year to this year from 8.5% to0 8.3%, I think we have done very well.
Question
Akshay Kolekar: Okay. It means these costs will pass on to the customer?
Answer, arvind nanda
Arvind Nanda: Yes, Yes, these are all fully pass-through. And you can imagine, if I'm doing a lithium battery plant or 'm doing a simple warchouse, erection cost will be different. If I'm doing a building in Noida or I'm doing a building in Assam, the freight cost will be different. Now that is not in my Page 14 of 20 Interarch Building Solutions Limited November 06, 2026 control. T could get all the jobs in Assam or I could get all the jobs in NCR in that quarter. It's not in my control. So, that is how you can figure out our business.
Show 4 more questions
Question
Akshay Kolekar: Yes, Yes, sure. Okay, cool. Thank you so much. That's it from my side.
Answer, arvind nanda
Arvind Nanda: 1 think this year we are not expecting much improvement, because this year, like I mentioned, these unusual events also happen, number one. But combined with unusual events, we have also started two new verticals, exports and trying to sell buildings from our heavier structure plant and trying to do different kind of building. Both these have added very heavily to our design engineering, traveling, selling cost as well. So, we don't expect any major improvement. Yes, we will do a turnover of maybe INR1,200 crores in the next six months, last two quarters. So that will of course help us. ButI see that our expenses will also remain a little high.
Answer, arvind nanda
So, it may improve. Certainly, if T have done INROS0 crores in the first two quarters, and I will do INR1,200 crores in the second two quarters, I should get a better margin because operational leverage should kick in. My overheads are not going to increase dramatically, because I'm doing a higher turnover. So it should improve in the second half, definitely, but I don't think it will cross what previously we have done, 9%, 9.5%. I don't see it crossing beyond that. But next year onwards, I think as the full capacity of our existing Gujarat plant, full capacity of our heavy structure plant, exports actually being delivered and improving, I think we can sce a better margin in "27-28 for sure. Aasim: Okay.
Answer, arvind nanda
Arvind Nanda: See, the certain amount of exports may have been incurred in the first two quarters, but the export orders we have currently will go in the second and third quarter primarily. Heavy steel structure came into operation only on 24th September. So, whatever sales happen from there will be in the third, and fourth quarter. But yes, it will increase our sales. So once the sales increase, then the margin percentage automatically increases in our case, because in a lot of cases the overhead is not increasing at the same level as our turnover. So, that is why I feel that the minuses of the first two quarters, Page 150f 20 Y, Yeas %, ¥ Rt Interarch Building Solutions Limited November 06, 2026 like steel prices, a little lower turnover compared to the two quarters, third and fourth quarter, it will help us. So, we are certainly seeing it.
Answer, arvind nanda
But sometimes too many things happen at the same year, or now we are bound by quarters, but we still try to look at it from a yearly point of view, that over a year things settle down, rather than every quarter. So over a year, we are still quite confident of achieving better results than what we did last year, definitely in turover, but I think in margins as well. Aasim: Yes. So, I guess, I get the steel price impact. I mean, that keeps fluctuating quarter-on-quarter. In fact, I think even in October, prices have jumped up. So it's possible that there might be a ‘margin impact again in Q3, but that should ideally even out over Q4, Q1, and Q2.
Answer, manish garg
Manish Garg: T think I will take all three. Okay. So, the volume for Q2 was 41,600 metric tons. That's the sale in terms of volume for Q2. Question number two was our order book and its period of execution. As we said that we have a net order book of about INR2,000 crores as on 3 1st of October, and for 75%, 70% of it is about 9 months to 10 months maximum. There are two, three orders which are a little longish, having a 12 months to 16 months execution period.
Answer, manish garg
So that is the blended order book period, which should be about 10 months to 11 months as blended. But then most of it is about nine months. In terms of our pipeline, our pipeline actually is measured in the number of inquiries and number of orders that we get as a throughput. So, it is generally about five times to six times of our order Page 16 of 20 Interarch Building Solutions Limited November 06, 2026 throughput per month. So our order throughput is about INR600 crores, INR700 crores per quarter. So multiply that by five, that's our general pipeline. And our pipeline remains actually very tightly stuffed and its very, very strong.
Question
Dhirendra Kumar: Hello, sir. Yes, so my first question is on the steel prices. So, steel has seen an inflation of about 18% to 20% Y-o-Y. So, we would have started bidding the fresh orders based on the updated steel prices. So my question is, number one, what is the price hike we have taken in the fresh orders that we are taking? And number two, what portion of our order book of INR2,000 crores is on the updated steel prices?
Answer, manish garg
Number two is what part of our order book s at current prices, at old prices. So it's actually blended, and our order book s actually a blend of three types. So, overall, two types. One is variable price orders. So almost 35% of our order book is variable price, wherein, it is a complete pass-on irrespective of when the order was booked. So, let's say if an order was booked in April and the price of steel was X, and it is coming for exccution end of September or end of November, whenever, the price at that point will prevail, and we shall be paid the increase in the price by the customer. So that's blending of about 30%, 35%.
Answer, manish garg
Next is some of our orders are at current prices. So, some of our orders have six weeks, cight weeks, 10 weeks, the supply start. And some of our orders are, yes, could be the orders coming Page 17 of 20 Interarch Building Solutions Limited November 06, 2026 for execution which were booked in maybe April, May, or June, which are coming up in exccution right now. So, it's actually a blended IN 2,000 crores order book, wherein, about 60% of our order book will be at fixed prices, which could have been booked at current, previous, and some old prices, but 40% is on variable price basis. On the same lines, I would also like to highlight that there has been increase in steel prices over last many months, and this blended approach also gets justified with our EBITDA. Despite whatever has happened, our EBITDA has remained exactly the same, 8.4%. So, that would mean that our blended order book approach and variable pricing, including dynamic pricing system has actually worked as a model very well.
Question
Dhirendra Kumar: Yes, sir. Sir, my next question would be on the fundraise. So, any update that you can give us regarding the QIP that we were planning?
Answer, arvind nanda
Arvind Nanda: So, we have done all the formalities, as required by law to do the QIP. Timing, we have left it to Ambit to decide what is the right timing. But, yes, I think since our whole expansion plans are on full speed So, I think we should do it sooner than later, but exact time I don't know. I think you will have to get in touch with Ambit. Maybe he can give you the details of Ambit and you can happily get in touch with them. But we have done all the legal formalities, so we can launch at a 72-hour notice once Ambit feels that's the right time.
Question
Dhirendra Kumar: Okay. Those are my questions. Thank you.
Answer, arvind nanda
Arvind Nanda: You see, for a company like ours, it is always preferable to take variable pricing, because steel prices are not in our control and it forms a major chunk of our cost. But we also have to go by the market situation and what kind of competition we face. So, when the prices are normally stable or cyclical in a sort of a form, which we know what will happen, something that we can foresee, then we also take very fixed pricing. But as the steel market prices become a little bit fluctuating out of normal, then we start shifting to -- and we insist with the customer, even at the cost of losing an order, that we will not do fixed pricing. So, over the last five to six months, we have been gradually moving very fast towards variable pricing. I would tell you that in the last two to three months, we have probably taken no order at Page 18 of 20 Y, YEARs ¥ 23y o Interarch Building Solutions Limited November 06, 2026 fixed price. So, the situation demands something, and then we try to act to that.
Answer, arvind nanda
But we also to take the customer and the market with us. When the fluctuation is not that much, no customer wants to get into that. And as we will get into longer term orders what we call using more of the heavy structure thing like data centers and all, they are traditionally all pass-through, so they'll all be variable. So our variable element will keep increasing, and I think in the next couple of quarters we are not going to vary, sort of, change our policy of taking anything at fixed price. We will not take, because right now we don't know where the steel prices are going, up or down. And variable pricing in this kind of situation, like I said, steel prices are at the all-time high in the last four years. Even the customer prefers a variable price, because he feels that, okay, they are all-time high, they'll only go down.
Answer, arvind nanda
But when it's only going one way, then it's a little tricky. So, that now we are taking more and more variable pricing. Let us see maybe after six months to eight months what happens, then we will see. But right now our policy is to take only variable pricing. Darshan: Okay. Thank you. And the second question, sir, is, We see in next two years we will add close to 1,25,000 tons in our capacity.
Answer, arvind nanda
Arvind Nanda: So, see, each one of our pre-engineered building plants adds about 40,000 tons to our capacity. So, Gujarat is now fully functional. So this year, of course, it will be less, but from next year onwards, that will also add 40,000 tons to our capacity. And next year I think we should also have approximately 35,000 tons to 40,000 tons from our heavy structure plant in Andhra, even though the second phase will finish by March, April, and the third phase by maybe November, December. But I think by the time they ramp up and actually the capacity starts coming out. So, I would say at least 80,000 tons in '27-'28 should be in place from these two plants. And whatever productivity improvements we can get from our existing plants, also we are working on it.
Answer, arvind nanda
So, our goal is that by end of 2728, lets say March, we should have usable capacity of additional 100,000 tons in place by then. And then we also plan to add maybe another 100,000 tons between '28 March and 29 June to July, seeing the present circumstances, if not faster, because things are moving very, very fast in the market, for us especially. Page 19 of 20 Interarch Building Solutions Limited November 06, 2026 So, that is the current plan, that in the next 14 months to 15 months, we should have another 100,000 tons of salable capacity in place, and beyond what was at the end of the second quarter this year, before HSS and Gujarat plant came into play, and March '28. And then we plan to add another 100,000 between March-April '28 to June-July '29 to take it up to about maybe 400,000 tons by 29 currently. But like I said, we are always ready to speed it up because the market is moving much faster than it has done in the past, or we are anticipating, but we are a little conservative right now. But let us see how fast it goes. Darshan: Okay.
Answer, arvind nanda
Arvind Nanda: Thank you very much, everybody, for joining us. And taking out your time on just a pre-festival timing when everybody's busy. So, thank you very much, and we look forward to your constant support, which we have got and I'm sure we will continue to get. I can only assure you that Interarch is a leading company in this. We think of the future, we think of our brand, and we think of how to give better and better solutions to our customers who currently are the world's top companies in India. And going forward, we want to also make ourselves as an international company, international brand, servicing customers outside of India also, where we are seeing a huge upsurge in demand, with not so much supply available. So, North America, Africa, etcetera., I think will do that.
Answer, arvind nanda
And getting into new areas like infrastructure, data centers, commercial buildings. So, I can assure you that as Interarch and as the management, we will be doing our level best to improve the company constantly from tumover point of view, quality point of view, from the customer quality point of view, and of course the margins, which we are ultimately all interested in. Thank you, Ambit, for hosting the call again, and thank you everybody else. Thank you very much.
Questions about this call
- When was the Interarch Building Solutions Q2 FY27 earnings call transcript filed?
- Interarch Building Solutions filed the transcript with the exchange on 11 Nov 2026. This page is built from that transcript.
- What does this page list?
- 72 statements from the transcript across 11 topics, 27 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 14 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.