Earnings call
Lodha Developers Q1 FY27 earnings call: Lodha Developers Limited expects land to generate INR 2,000 crores to INR 3,000 crores of sales every year for the next several years
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company expects land to generate INR 2,000 crores to INR 3,000 crores of sales every year for the next several years. The company holds about 660 acres in its data center park; it has monetized about 130 acres of the first phase of 370 acres and intends to monetize about 150 acres over the next 3 to 4 years, generating close to INR 10,000 crores of sales. The company reported revenue of INR 50 billion in Q1FY27, up 43% year-on-year. Market cap on the development business across the top six cities is just 3.5% in value terms. Lodha Development Business balances sales from existing projects and new launches, with 65% to 70% of business coming from existing projects and 30% to 35% from new launches.
The numbers management gave
Results
- The company reported revenue of INR 50 billion in Q1FY27, up 43% year-on-year.
Show source
In terms of the highlights of the performance for this quarter, revenue for the quarter was at INR 50 billion, up 43% year-on-year.
- The company reported adjusted EBITDA of INR 21.5 billion in Q1FY27, up 79%, at a margin of 43% against 34.4% a year ago.
Show source
The adjusted EBITDA was INR 21.5 billion, up 79% at a margin of 43% against 34.4% a year ago.
- The company reported PAT of INR 13.7 billion in Q1FY27, more than double the INR 6.8 billion of Q1 FY26, at a PAT margin of 26.9% against 18.6% in the equivalent quarter a year ago; it was the company's best ever quarter on revenue, EBITDA and PAT.
Show source
PAT was at INR 13.7 billion, more than double the INR 6.8 billion of Q1 FY26 at a PAT margin of 26.9% against 18.6% in the equivalent quarter a year ago, our best ever quarter on revenue, on EBITDA and on PAT.
- The company collected INR 42.1 billion in Q1FY27, up 46% Y-o-Y, converting to INR 18.9 billion of operating cash flow.
Show source
Collections for the quarter were INR 42.1 billion, up 46% Y-o-Y. That converted to INR 18.9 billion of operating cash flow.
- Overall construction cost inflation since April 2022 had run at approximately 3% per annum.
Show source
For context, our overall construction cost inflation since April 2022 has run at approximately 3% per annum.
- The value of Lodha Developers Limited's land at Palava has risen more than 15x over the last 5 years.
Show source
Overall, the value of our land at Palava has risen more than 15x over the last 5 years.
Show 14 more statements
Results
- Exit run rate for June was approximately INR3 billion, without any contribution from data centers.
Show source
On the broader annuity business, our exit run rate for June was approximately INR3 billion without any contribution from data centers.
- Almost 60% of Lodha Developers Limited's sales in Q1FY27 came from premium and luxury segments.
Show source
This quarter was no different with the lion's share of our sales of almost 60% coming from premium and luxury segments.
- Lodha's conversion number from quarter 2 from July onwards was upwards of 8%.
Show source
The other positive thing that we have seen is that the conversion number, which we are seeing, especially from quarter 2 from July onwards is in upwards of 8% and above.
- Land sales for the quarter, including the data center and some other sources of land sales, were approximately INR 1,200 crores of pre-sales; revenue recognition was about 85% to 90% of that number because certain activities at the site remained to be completed for buyers; the land sale contributed approximately INR 600 crores to PAT.
Show source
Abhishek Lodha: Pritesh, in terms of the value of land sales for this quar ter, the total, including the data center and some other sources of land sales was approximately INR 1,200 crores of pre-sales.
- Lodha Developers' embedded margins excluding land sales were around the early 30s mark in Q1FY27.
Show source
Abhishek Lodha: The embedded margins excluding the land sales for this quarter are at around the early 30s mark.
- Lodha had no new launches in this quarter and delivered business in line with its business plan, driven mainly by sustenance sales from existing business.
Show source
And despite that, we delivered a business in line with the business plan and has been driven mainly from sustenance sales coming all from the existing business.
- Lodha had one launch in Bangalore in July and was getting good initial results there.
Show source
We have one launch that has happened in the month of July in Bangalore and the kind of the first good results that we are getting there are extremely encouraging .
- Lodha's commercial for-sale product in Worli was hugely successful last year and continues to drive strong sales.
Show source
We brought in our commercial for sale product in Worli, which last year, which was hugely successful and continues to drive strong sales.
Money and capital
- The company reduced net debt by INR 4.5 billion after investments in Q1FY27, to under INR 50 billion.
Show source
After investments, we still reduced net debt by INR 4.5 billion to now under INR 50 billion.
- Net debt to equity was approximately 0.2x in Q1FY27, against its self-imposed ceiling of 0.5x.
Show source
Net debt to equity now stands at approximately 0.2x against our self-imposed ceiling of 0.5x.
- Net worth was just under INR 250 billion in Q1FY27.
Show source
Net worth is just under INR 250 billion.
- Capital allocation hierarchy is to fund opportunities with brand fit and execution capacity, targeting about 20% ROCE in DevCo and about 15% in RentCo, pay a regular dividend at 15% to 20% of PAT, then reduce debt and direct any surplus to buyback or special dividends.
Show source
Our capital allocation hierarchy is clear and publicly stated, fund opportunities where there is brand fit and execution capacity, about 20% ROCE in DevCo and about 15% in RentCo, a regular dividend at 15% to 20% of PAT, thereafter debt reduction and thereafter, any surplus towards buyback or special dividends.
- The company expects to incur INR 500 crores to INR 700-odd crores of infrastructure expense and capex for the overall 3 gigawatt it is developing, over a period.
Show source
And to that extent, yes, we would have certain expense, certain capex to be incurred, but those are in the bigger scheme of things are not too material, but yes, let's say, a number of more like INR 500 crores to INR 700-odd crores that we will incur over a period.
- Data center build is largely self-funded from land sales inside the same park and does not add to group leverage or compete with its DevCo for capital in any significant manner.
Show source
The data center build is largely self-funded from land sales inside the same park.
What it expects ahead
What management expects
- The company expects land to generate INR 2,000 crores to INR 3,000 crores of sales every year for the next several years.
Show source
Thus, overall, we expect land to be between INR 2,000 crores to INR 3,000 crores of sales every year for the next several years.
- Fiscal '27 guidance is 20% growth on last year's PAT of INR 34.3 billion, or approximately INR 41 billion of PAT; Q1 delivered 33% of that.
Show source
In terms of our guidance for fiscal '27, that is 20% growth on last year's PAT of INR 34.3 billion and hence, approximately INR 41 billion of PAT.
- The company reaffirmed its INR 240 billion pre-sales guidance for fiscal '27 and expects H1 to be 40% to 42% of the full year, with the balance of sales in H2.
Show source
In terms of the rest of the year, we reaffirm our INR 240 billion pre-sales guidance for fiscal '27, and we expect H1 to be 40% to 42% of the full year, as we had mentioned in the start of the year itself.
- Fiscal '27 launch calendar carries about 20-plus projects and phases totalling approximately INR 250 billion of GDV, including its first launch in NCR and continued growth in Bangalore and Pune.
Show source
For the full y ear, the launch calendar carries about 20-plus projects and phases totalling approximately INR 250 billion of GDV, including our first launch in NCR as well as continued growth in Bangalore and Pune.
- The company expects Q2 pre-sales to be INR 50 billion or more on the back of the planned calendar for the quarter.
Show source
In terms of the immediate outlook for Q2, we are off to a good start in July, and we expect pre-sales to be INR 50 billion or more on the back of the planned calendar for this quarter.
- The company has sold about 130 acres and expects to monetize a further 150 acres over the next 3 to 4 years at an average of about INR 600 million per acre, generating approximately INR 90 billion of further sales from Phase 1 of its land.
Show source
Of this, about 130 acres has now been sold, and we expect to monetize a further 150 acres over the next 3 to 4 years at an average of about INR 600 million per acre, generating approximately INR 90 billion of further sales just from Phase 1 of our land.
Show 22 more statements
What management expects
- The company targets over INR30 billion of annuity business by fiscal '32, 10x the June exit run rate, comprising about INR20 billion plus from data centers, INR6 billion from retail and offices, and about INR4 billion from warehousing and industrial; the estimates are based on land already acquired and development activity already progressing, and exclude further incremental land additions expected to provide upside.
Show source
The target is over INR30 billion, i.e., 10x by fiscal '32, of which about INR20 billion plus will come from data centers, INR6 billion from retail and offices and about INR4 billion from warehousing and industrial.
- The company intends for its DevCo to be net debt free within the next 2, 3 years as business development requirements taper, against an unsold GDV of approximately INR 2 trillion sufficient to support growth for the foreseeable future.
Show source
At a DevCo level, as I had mentioned earlier, of course, we intend to be effectively debt-free over the next 2 to 3 years.
- Guidance is about 20% PAT growth over the medium term, taking it beyond INR 85 billion over the next 5 years, by fiscal '31.
Show source
Our guidance of about 20% PAT growth over the medium term, taking us beyond INR 85 billion over the next 5 years, i.e., by fiscal '31.
- Return on equity was about 16% in fiscal '26 and is moving upwards and inching closer towards 20%, though it might not touch 20%.
Show source
Our return on equity, which is currently about 16% in fiscal '26, moving upwards and inching closer towards 20%, though it might not touch 20%.
- Lodha expects to achieve 40% to 42% of its pre-sales guidance in the first half and the remaining amount in the second half.
Show source
So just to sum up, in the first half, as Abhishek said that we will achieve 40% to 42% of our guidance of the pre-sales and the remaining in the second half.
- Lodha expects to enhance pricing by 5% to 7% across different micro markets over the year.
Show source
In the near term, we expect to enhance our pricing by 5% to 7% across different micro markets over the year.
- Lodha has the ability to take price growth up by at least 100 to 200 bps, which would give confidence in margins.
Show source
On the strength of our brand, we have the lever to further take the price growth up by at least 100 to 200 bps, which will straightaway give us confidence in the margins.
- Lodha expects new cities together to contribute over 30% to 45% of its pre-sales in the medium term, while MMR remains its dominant home base.
Show source
While MMR will remain a dominant home base, new cities together will start contributing over 30% to 45% of our pre-sales in the medium term, which makes our portfolio even more balanced.
- Lodha hopes to reach a 10% conversion number in the long run.
Show source
And we believe that in long run, we hope to reach the holy grail of 10%.
- Lodha's rentals are expected to grow 10x from INR 3 billion at the end of fiscal '26 to INR 30 billion at the end of fiscal '32, with contributions from data centers, retail and office, and warehousing and industrial; Lodha says the current projections have some upside potential.
Show source
So, we had suggested that our rentals would be growing by 10x from the INR 3 billion level at the end of fiscal '26 to INR 30 billion at the end of fiscal '32.
- Data center powered-shell annual rentals are expected to be a little over INR 20 million per megawatt.
Show source
Abhishek Lodha: Yes, a little over INR 20 million, yes.
- The company expects leasing for the first box within the 1 gig of power shell it intends to build to conclude in this fiscal year, and is in talks with a couple of large operators.
Show source
Abhishek Lodha: In terms of leasing, as I mentioned in my response to Abhinav and now, we expect that the leasing for the first of the boxes within that 1 gig of power shell that we intend to build will conclude in this fiscal year.
- The company expects residential demand and price points to see significant upside over the next 2 to 3 years as the bullet train comes through.
Show source
And over the next 2 to 3 years, as the bullet train comes through, we expect a significant upside in the residential demand as well as the price points.
- The company expects its LandCo to start showing from fiscal '28 that land in Palava can be used for other noncompeting uses at similar price points, about INR 500 million per acre, including back office and affordable housing.
Show source
Further, we expect that the LandCo that we are now slowly getting into shape will from fiscal '28 start showing that the land in Palava can be used for other noncompeting uses at similar price points, about INR 500 million per acre, things like back office, things like affordable housing and so on.
- Lodha Developers' margins were much higher in Q1FY27 because it completed approximately half of the land sales it expected for the year in the quarter, forward-loading those sales; the company does not expect its margins to be in the 40s for the full year and its early 30s guidance stands.
Show source
So obviously, there is outperformance this quarter where the margins are much higher, but that's got to do with the fact that we've done in this quarter approximately half of the land sales that we would expect to do in the year.
- The company said it is difficult to know what data center land power density will be in 2 years or 4 years' time because power density seems to be moving upwards.
Show source
But what it will be in 2 years or 4 years' time is very difficult to know because obviously, power density seems to be moving upwards.
- The company thinks fair market price is closer to about INR 650 million per acre and hopes to reach that level over the next 18 months.
Show source
We think fair market price is closer to about INR 650 million per acre.
- The company deliberately postponed launches out of Q1FY27 because it expected the Middle East conflict to persist through Q1 and end by the end of Q1; those launches generally make up about one third of pre-sales.
Show source
And therefore, we had deliberately postponed launches out of this quarter, and these launches generally make up about one third of pre-sales.
- Most of Lodha's new launches will happen in the second half of the year, coinciding with the festive season.
Show source
Most of the new launches will be happening in the second half of the year, coinciding with the festive season.
- Lodha has one more launch coming up in Bangalore, two in Pune, and will also enter NCR with two launches in MMR.
Show source
We have one more launch coming up in Bangalore, 2 in Pune, and we'll also be entering the NCR and 2 launch in MMR.
- The company may move from power shell to turnkey shell over time, but that is at least a couple of years out.
Show source
Over time, we might move from power shell to turnkey shell, but that's at least a couple of years out.
- Lodha remains fairly confident of delivering its guidance for the year with the right margin delivery. Replaced by a later filing.
Show source
We have built a very granular plan, which enables us to achieve the guidance and with the right margin delivery.
What it is building and selling
Projects and capacity
- The company holds about 660 acres in its data center park; it has monetized about 130 acres of the first phase of 370 acres and intends to monetize about 150 acres over the next 3 to 4 years, generating close to INR 10,000 crores of sales.
Show source
Of this, the first phase of 370 acres, we have already monetized about 130 acres, and we intend to further monetize about 150 acres over the next 3 to 4 years, which itself will generate close to INR 10,000 crores of sales.
- Balance land of approximately 300 acres provides optionality for sale or build out on its balance sheet, and it will evaluate the options in due course.
Show source
Beyond this, we have additional approximately 300 acres of optionality in our data center park.
- The company holds approximately 660 acres in its green data center park, with approximately 3 gigs of power availability at about US$0.06 to US$0.08 per unit, 5 fiber optic routes, 5 transmission lines and approval under the Maharashtra Green Integrated Data center policy.
Show source
As I had mentioned earlier, we hold approximately 660 acres of land in our green data center park with approximately 3 gigs of power availability at about US$0.06 to US$0.08 per unit, 5 fiber optic routes, 5 transmission lines and approval under the Maharashtra Green Integrated Data center policy.
- The company will use land sales to fund the build-out of about 1 gigawatt of powered shell on approximately 90 acres, which will generate over INR 20 billion of annual rental income by fiscal '32.
Show source
This will fund the build-out of about 1 gigawatt of powered shell on approximately 90 acres, which will generate over INR 20 billion of annual rental income by fiscal '32.
- The 660 acres is now part of the green data center approved by the government of Maharashtra.
Show source
Abhishek Lodha: The 660 acres is now part of the green data center, which is approved by the government of Maharashtra.
- The company has planned 0 utilization of freshwater in its green data center park, and the water it uses will be recycled water.
Show source
There is 0 planned utilization of any freshwater in our green data center park.
Show 28 more statements
Projects and capacity
- Green data center parks will have 0 usage of fresh water and will use recycled water that would otherwise be thrown into the sea.
Show source
And again, I repeat, there will be our data center park will only use recycled water, which would otherwise be thrown out into the sea and not use any freshwater.
- The company has developed more than 1,000 acres at Palava and Upper Thane for residential and related uses, and about 600 acres are earmarked for data centers.
Show source
And as you now mentioned, there is about 600 acres earmarked for data centers.
- The company has plus 1,000 acres at Palava and Upper Thane that are yet to be earmarked for any use and can be allocated to whatever use makes most sense, including based on market demand factors.
Show source
We still have significant amount of land other than what's been earmarked for these 2 in the order of plus 1,000 acres, which is yet to be earmarked for any use.
- Lodha Developers' data center land is now about 600-plus acres.
Show source
So, there are various uses of this land, including, of course, the fact that the data center is now at about 600-plus acres.
- The power density of data center land currently runs at somewhere between 11 megawatts to 15 megawatts per acre and has changed quite significantly.
Show source
The power density of land has changed quite significantly and currently runs at somewhere between 11 megawatts to 15 megawatts per acre.
- The company has good availability of recycled water from the industrial areas around where its data center park is located.
Show source
But yes, we do have good availability of recycled water from the industrial areas around where our data center park is located.
- Several data center players that bought land from Lodha Developers have completed their design and tendered their works, obtained approvals, and some have commenced physical activity at site.
Show source
Abhishek Lodha: In terms of whether work has started, yes, several of the players have completed their design and tendered their works and have obtained their approvals and some of them have commenced physical activity at site.
- The company expects physical activity on site for its own data center box to start in the course of this calendar year.
Show source
In terms of we also expect for our own box to start physical activity on site in the course of this calendar year.
- The company will have a launch in NCR in the second half of this fiscal year.
Show source
NCR, of course, we will have a launch in the second half of this fiscal year, and we'll see how that goes.
Demand and pricing
- Market cap on the development business across the top six cities is just 3.5% in value terms.
Show source
Our market cap on the development business across the top six cities is just 3.5% in value terms.
- Branded developers' contribution in the MMR market was less than 20% five years back and had moved to almost 30% by end of '25.
Show source
It was less than 20% 5 years back, and it has moved to almost 30% by end of '25.
- The contribution of branded developers in the MMR market could reach 40% to 45% by end of the decade as the weakest players with no brands keep exiting the space.
Show source
But our view is that this number could easily go to 40% to 45% by end of the decade as the weakest players with no brands keep exiting the space.
- Lodha introduced its Bangalore launch at a price point almost 30% higher than the existing price points available, and consumers accepted the product.
Show source
Even in Bangalore, where we did the new launch, we went ahead of the market curve and introduced the product at a price point, which was almost 30% higher than the existing price points available.
- Lodha's expected pricing growth of 5% to 7% is below white-collar salary growth of 9% to 10%, which keeps affordability intact and helps boost volumes.
Show source
This sort of pricing growth, which is still below the white-collar salary growth of 9% to 10%, keeps the affordability intact and helps in boosting the volumes.
- India can bring a data center from breaking ground to operational in under 3 years, compared with 4.5 to 5 years in the West, and the cost of building a power shell and turnkey shell in India is almost half that in the West.
Show source
Given India's very critical competitive advantages, primarily in terms of time because from breaking ground to getting a data center operational in India can be done in under 3 years compared to 4.5, 5 years in the West as well as in terms of cost where the cost of building power shell as well as turnkey shell in India is almost half of that in the West.
- Lodha says data-center demand is global, with operators considering locations including Virginia, Scandinavia, Johor and India; the competition is about India's ability to position itself and gain global share, not competition within India.
Show source
So therefore, from an Indian perspective, it's important to note that this is not about competition within India, but it is about how India can position itself and gain share at a global level.
- Demand for Lodha Developers' data center land is greater than the company can currently supply.
Show source
And without revealing competitive information, I can only say is that there is more demand than we can currently supply.
- In MMR, the impact of the start of the Middle East crisis has abated, and high-value sales have returned to a normalized behavioural pattern.
Show source
So , we've gone back to a normalized behavioural pattern in terms of the closure of high-value sales.
- Lodha Developers' Bangalore launch in Q1FY27 started off very well, ahead of expectations.
Show source
We had, as Prashant mentioned, the launch this quarter, and that's started off very well, ahead of our expectations.
- The company said it remains a trend setter in the luxury segment across multiple locations and not only in South Mumbai, continuing to gain market share. Replaced by a later filing.
Show source
We remain the trend setter in the luxury segment across multiple locations and not only in South Mumbai, thus continuing to gain market share on a continual basis.
Segments
- Lodha Development Business balances sales from existing projects and new launches, with 65% to 70% of business coming from existing projects and 30% to 35% from new launches.
Show source
We have always kept that balance in the range that 70% of the business, 65% to 70% coming from the existing projects and 30% to 35% coming from the new launches.
- Lodha's pre-sales are typically driven 30% to 35% by new launches.
Show source
So typically, 30% to 35%, as I said, of the pre-sales is driven by new launches.
- Lodha's mid-income portfolio, defined as homes below INR 3 crores, accounts for about 50%, with the remainder from premium and luxury segments.
Show source
Our portfolio across mid-income, premium and luxury segments are now well balanced with mid-income, which is anything below INR 3 crores, is now about 50% and remaining coming from premium and luxury segments.
- The company intends to monetize land for non-competing uses through its LandCo, including back office uses where it has surplus land like Palava.
Show source
Further through our LandCo, for shaping and coming together, we intend to monetize land for non-competing uses, for example, back office in places where we have surplus land like Palava.
- Lodha Developers' current data center strategy is to build powered shell, meaning the physical box and power enabled up to one point in the box; MEP, HVAC, rack and chip fit-out are outside its current focus because it does not believe it yet has the technical competence for them.
Show source
As we have laid out earlier, our current strategy is to move from the sale of land to in addition, building powered shell.
- The company says its powered shell solution is not provided by co-lo players or hyperscalers and that offering both land and powered shell expands the market with solutions not currently available from other solution providers.
Show source
So, I think what we are doing through our action of providing both land as well as powered shell solution is expanding the market because we are giving solutions which currently are not available from any other solution provider.
Deals and partners
- The transaction for Digital Edge India's entry into Lodha Developers Limited's Green Data Center Park at Palava was concluded at approximately INR 420 million per acre, compared with INR210 million per acre in calendar '25, almost doubling value in just less than 12 months.
Show source
The transaction was concluded at approximately INR 420 million per acre.
- Digital Edge India, a joint venture between Digital Edge Singapore and National Infrastructure and Investment Fund, entered Lodha Developers Limited's Green Data Center Park at Palava, joining AWS and STT.
Show source
The most significant development of the quarter was the entry of Digital Edge India, a joint venture between Digital Edge Singapore and National Infrastructure and Investment Fund into our Green Data Center Park at Palava, joining AWS and STT.
Risks, rules and outside factors
Outside factors
- Supply chain is about 95% domestic, so availability has not been a problem.
Show source
On the cost side, our supply chain is about 95% domestic, so availability has not been a problem.
- The company said energy-intensive input costs had risen; if the situation persisted for a full year, it would expect project construction cost to rise by 1% to 1.5%, spread across a 3 to 4 year build period and assuming no price response, with project-level EBITDA impact of 35 to 75 basis points.
Show source
If this situation persists for a full year, we would expect project construction cost to rise by between 1% to 1.5%, with spread across a 3 to 4 year build period and assuming no price response ; project level EBITDA impact of between 35 to 75 basis points.
- Lodha's portfolio across cities and categories helps it taper volatility from factors such as conflicts in Middle East and the impact of high inflation and interest rates on entry-level homebuyers.
Show source
This diversity and across the cities and categories help us taper over any volatility presented by other factors such as conflicts in Middle East or impact of high inflation and interest rates on entry-level homebuyers.
Rules and policy
- The government in India granted a tax exemption for data center operators where the usage is outside India. Replaced by a later filing.
Show source
Plus, the fact that the government in India is very proactive, both at the state levels and equally and more importantly, at the central level as we saw with the tax exemption granted for data center operators where the usage is outside India.
Everything else said on the call
Other
- The Mumbai region, or MMR as a whole, generates about 3,500 MLD of recycled water, which is generally thrown out into the sea.
Show source
I'll repeat that number, 3,500 MLD of recycled water, which is generally thrown out into the sea.
- If the 3,500 MLD of recycled water were effectively used, Mumbai could probably support upwards of 40 gigawatts of data centers.
Show source
If that 3,500 MLD was to be effectively used, Mumbai could probably support upwards of 40 gigawatts of data centers.
- The company incurs perhaps about 10% to 15% of the sales price at the current level of about INR 420 million per acre towards building out infrastructure and making land ready for construction.
Show source
In terms of value addition, as Sushil highlighted, we obviously incur a modest amount of cost, perhaps about 10% to 15% of the sales price at the current level of about INR 420 million per acre towards building out some infrastructure and making the land ready for them to start construction soon.
- Lodha Genius completed its fourth summer programme at Ashoka University and launched its first Science Circle and Summer Programme at IISER Pune, with over 400 high-potential students participating from across India.
Show source
And this quarter, we completed the fourth edition of the Lodha Genius program with over 400 students in association with IISER Pune and Ashoka University in NCR.
- The company launched the Lodha Theoretical Physics Institute, India's first privately funded institution of its kind, headed by Professor Jainendra Jain, the first physicist of Indian origin to receive the Wolf Prize.
Show source
This quarter, we launched the Lodha Theoretical Physics Institute, India's first privately funded institution of its kind, headed by Professor Jainendra Jain, the first physicist of Indian origin to receive the Wolf Prize.
- The company said assets under development were largely performing ahead of underwriting. Replaced by a later filing.
Show source
The assets that are under development are largely performing ahead of underwriting.
Show 1 more statement
Other
- Recycled water that would otherwise be thrown into the sea will become a revenue source for municipal corporations and municipal councils by being redirected for data center use as infrastructure is built out. Replaced by a later filing.
Show source
Now with the build-out of infrastructure and under the leadership of the Honorable Chief Minister and his long-term vision, a large part of this water rather than being thrown into the sea will become a revenue source for the municipal corporations and municipal councils by being redirected for usage at the data centers.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Pritesh Sheth: Got it. Contribution to PAT, INR 600 crores. Okay. And just a follow-up. So, 660 acres, everything falls under that MOU, which we have with Maharashtra government or for now, it's just 400 acres and then we can expand to 660 acres?
Answer, abhishek lodha
Abhishek Lodha: The 660 acres is now part of the green data center, which is approved by the government of Maharashtra. Pritesh Sheth: Okay. Awesome. And just on the rentals part, right? I think earlier, we had an estimate of INR 30 billion rentals coming from the power shell that we are targeting. In the presentation, now I see INR 20 billion plus kind of a number. Is it just a conservative estimate?
Answer, abhishek lodha
Abhishek Lodha: Pritesh, there may be some gap in understanding. There's been no change in our numbers. So, we had suggested that our rentals would be growing by 10x from the INR 3 billion level at the end of fiscal '26 to INR 30 billion at the end of fiscal '32. Of that, the contribution was from all the 3 verticals, i.e., data centers, retail and office and warehousing and industrial. And that same breakup continues. The current numbers are definitely, in our opinion, have some upside potential to it, but these are our current projections.
Question
Pritesh Sheth: Sure. Got it. So, for data center powered shell, it would be INR 20 million per megawatt kind of annual rentals that one should expect, right?
Answer, abhishek lodha
Abhishek Lodha: Yes, a little over INR 20 million, yes.
Answer, abhishek lodha
Abhishek Lodha: The demand environment for data centers continues to strengthen. we have to note that this is not demand which is national or regional. This is global demand. And as data center operators look to locate their sites, they will look at Virginia, they will look at Scandinavia, they will look at Johor and they will look at India. So therefore, from an Indian perspective, it's important to note that this is not about competition within India, but it is about how India can position itself and gain share at a global level. Given India's very critical competitive advantages, primarily in terms of time because from breaking ground to getting a data center operational in India can be done in under 3 years compared to 4.5, 5 years in the West as well as in terms of cost where the cost of building power shell as well as turnkey shell in India is almost half of that in the West. Plus, the fact that the government in India is very proactive, both at the state levels and equally and more importantly, at the central level as we saw with the tax exemption granted for data center operators where the usage is outside India. So, with all these factors in place, India is emerging as a strong location.
Answer, abhishek lodha
The reason for the expansion of our park, we believe that the park has created immense credibility given that 3 top operators, AWS Amazon, STT, which is Temasek and KKR subsidiary; and now Digital Edge India, which is a joint venture between Digital Edge Singapore and NIIF, which is 49% owned by the Government of India, funded by the Government of India. These are all evidences of how important this part is to the global ecosystem. We now expect to further scale up our efforts to do development of clientele in the U.S., which is where most of the demand is likely to be eventually catered and coming from and hope that we can further increase capacity. We think that in this segment, capacity attracts demand, and that's really our direction of play. And so far, that's played out reasonably well. We also are making good progress towards the leasing of the first of our boxes, which will be held on our balance sheet. And we hope that in the course of this fiscal year, that will also come to fruition.
Answer, abhishek lodha
Your last point in terms of incremental power, that's an activity which we continue to work on. And we'll, of course, update as and when those further get fructified. But I would like to conclude by stating that the positive mindset of the government and the regulators is very supportive of expanding India's data center capacity and our park in Navi Mumbai/Palava is a key part of India's budding ecosystem in data centers.
Question
Abhinav Sinha: That's very helpful, sir. Second question on Palava bit. There seem to be some uplift in sales in the current quarter and Mr. Bindal also hinting at better outcome there during the year. So, what do you see as, let's say, the launch time line of the premium inventory there? And can we see big price uplift this year or maybe that can take another odd year?
Answer, abhishek lodha
Abhishek Lodha: Abhinav, we expect that the connectivity, which is ready, physically ready will open after the monsoon. And if that happens, then of course, we expect to see that it will lead to much greater and improved connectivity to the location from Airoli as well as Mulund. This will not only unlock the higher categories within residential. And therefore, we can count on that starting to surface from the fourth quarter, though I would say meaningful impact might not be visible in the numbers till early next fiscal. But this will also start unlocking the LandCo side because as this connectivity comes through and as we know that next year on 15th August, the bullet train is going to start operations on a part of its leg, not to Palava, but on a part of its leg. And with both of those things, the LandCo, which is about selling the land that we have surplus for noncompeting uses, for example, affordable housing or back office, that will also benefit from this connectivity. So, I would say is that calendar year 2027 is when we see a significant impact.
Answer, abhishek lodha
Abhishek Lodha: This question is something which is very difficult for us to form a view on because when will the war end, what will be the nature "of the end"? And how will that impact demand? I think as I mentioned in my remarks, so far, what we see is that the impact is contained. The duration has extended beyond what we assume, but we don't yet, given the other strengths, I expect that in spite of that, we will maintain our pre-sales guidance. And let's review it once it actually ends and what that nature of the end is. Thank you.
Question
Kunal Lakhan: Just on the data center bit, when do you expect the leasing activity for the data center to commence? And what kind of demand are you forecasting in terms of like it will be like simple racks/cabinet demand or it will be more, so to speak, like hosting the servers and the end-to- end build-to-suit kind of demand. So, what kind of demand you are expecting there?
Answer, abhishek lodha
Abhishek Lodha: In terms of leasing, as I mentioned in my response to Abhinav and now, we expect that the leasing for the first of the boxes within that 1 gig of power shell that we intend to build will conclude in this fiscal year. We are in talks with a couple of large operators for that and hope that there will be good progress over the next 6 to 9 months. As we have laid out earlier, our current strategy is to move from the sale of land to in addition, building powered shell. That means that we build the physical box and enable the power up to one point in the box. The activities after that, which is the MEP and HVAC, which takes it from powered shell to turnkey shell. And thereafter, in the turnkey shell, the fit out of the racks and the chips, those are not within our purview of focus right now because we don't really believe we yet have the technical competence for that. Over time, we might move from power shell to turnkey shell, but that's at least a couple of years out.
Answer, abhishek lodha
So as of now, it's only powered shell and then the operators, the hyperscalers, the Neoclouds, the colo players, they take it further from here and then they add various layers of value. So, we are really looking at it from a very wholesale perspective at this stage. We are not in the business right now of a business model of putting in the chips and the racks, which is highly capital intensive and also at risk of technological obsolescence as well as depreciation risk. We are not in that part of the business.
Question
Kunal Lakhan: Understood. And just the last one. On the data center bit again, similar to the committed supply of, say, 3 gigawatts on the electricity side that we have from state as well as National Grid, do we also have a commitment on the water supply side, especially considering the usual pressure on water resources that we have?
Answer, abhishek lodha
Abhishek Lodha: I think it's important to understand that water consumption in data centers does not use any freshwater. There is 0 planned utilization of any freshwater in our green data center park. The reason it's referred to as a green data center park is because it will operate at amongst the highest levels of sustainable data centers anywhere in the world. And the water that will be used will be all recycled water. The Mumbai region, the MMR as a whole generates about 3,500 MLD. I'll repeat that number, 3,500 MLD of recycled water, which is generally thrown out into the sea. Now with the build-out of infrastructure and under the leadership of the Honorable Chief Minister and his long-term vision, a large part of this water rather than being thrown into the sea will become a revenue source for the municipal corporations and municipal councils by being redirected for usage at the data centers.
Answer, abhishek lodha
So again, I repeat, there is 0 usage of fresh water at any of the green data center parks, and it is about utilizing the water, which would otherwise be thrown out -- the recycled water, which would otherwise be thrown out into the sea. If that 3,500 MLD was to be effectively used, Mumbai could probably support upwards of 40 gigawatts of data centers. But obviously, that's a long, long story, and we are not aware as and when that will happen. But yes, we do have good availability of recycled water from the industrial areas around where our data center park is located. And again, I repeat, there will be our data center park will only use recycled water, which would otherwise be thrown out into the sea and not use any freshwater.
Answer, abhishek lodha
Abhishek Lodha: I think we would all agree that many of you have been tracking our company for long that 2 years ago, data center was virtually 0. Hence, what it really tells you is that our land at Palava and Upper Thane is hugely valuable because this kind of large aggregated land in touching the Navi Mumbai and Thane is hugely valuable and rare, and it can be used to put to various uses. So far, we've developed more than 1,000 acres for residential and related uses. And as you now mentioned, there is about 600 acres earmarked for data centers. We still have significant amount of land other than what's been earmarked for these 2 in the order of plus 1,000 acres, which is yet to be earmarked for any use. And therefore, can be allocated to whatever use makes most sense, including based on market demand factors and so on. Now on the residential side, as the connectivity to Airoli and Mulund concludes after the monsoon this year.
Answer, abhishek lodha
And over the next 2 to 3 years, as the bullet train comes through, we expect a significant upside in the residential demand as well as the price points. Further, we expect that the LandCo that we are now slowly getting into shape will from fiscal '28 start showing that the land in Palava can be used for other noncompeting uses at similar price points, about INR 500 million per acre, things like back office, things like affordable housing and so on. So, there are various uses of this land, including, of course, the fact that the data center is now at about 600-plus acres.
Answer, abhishek lodha
Abhishek Lodha: The embedded margins excluding the land sales for this quarter are at around the early 30s mark.
Question
Gaurav Khandelwal: Got it. So, this is still within the guidance range of 32% to 34%, which we had guided for this year?
Answer, abhishek lodha
Abhishek Lodha: That's correct. Of course, the margins for what we guided to are the margins for the company. We don't guide to margins by any segment. So obviously, there is outperformance this quarter where the margins are much higher, but that's got to do with the fact that we've done in this quarter approximately half of the land sales that we would expect to do in the year. So that sort of forward loading has moved the margins up. So, I would not change or expect that our margins will be in the 40s for the full year. Our guidance of the early 30s stands.
Question
Gaurav Khandelwal: Got it. And just a follow-up question on the land sales. Are you having any discussions? How does the pipeline for land sales look for the rest of the year?
Answer, abhishek lodha
Abhishek Lodha: I think as I mentioned, the data center piece is gathering a lot of momentum. The demand is strong. And without revealing competitive information, I can only say is that there is more demand than we can currently supply.
Answer, abhishek lodha
Abhishek Lodha: I'll defer that question to Sushil to respond to, please.
Answer, sushil modi
Sushil Kumar Modi: So basically, from a cash flow standpoint, effectively most of the sales price adjusted with the tax effectively gets to the cash flow on the net basis.
Question
Parikshit Kandpal: But do you need to incur any capex while selling this land to say, data center client? So, you have a historical land cost. And on top of it, you need to provide a minimum basic infra, some connectivity, some plug-and-play kind of infra. So typically, if you have an RFQ for, say, 100 acres or say, 1 acre, how much typical capex would go on a per acre basis to realize the INR 42 crores on that land?
Answer, sushil modi
Sushil Kumar Modi: Parikshit, yes, you are right. Obviously, when we look at the overall infrastructure, we are not looking at the infrastructure for any specific particular box. That is more for the entire 3 gigawatt as of now that we are developing. And to that extent, yes, we would have certain expense, certain capex to be incurred, but those are in the bigger scheme of things are not too material, but yes, let's say, a number of more like INR 500 crores to INR 700-odd crores that we will incur over a period.
Question
Parikshit Kandpal: Okay. Second question to Abhishek. Abhishek, you have already sold land to AWS, STT and now Digital Edge. So, has some work started there? And a related question, so when we also start building out our data center over the course of next 2, 3 years, so will we compete with these players? How will it work? Just wanted to understand that.
Answer, abhishek lodha
Abhishek Lodha: In terms of whether work has started, yes, several of the players have completed their design and tendered their works and have obtained their approvals and some of them have commenced physical activity at site. In terms of we also expect for our own box to start physical activity on site in the course of this calendar year. In terms of competing, I think it's important to note that the powered shell solution that we provide is not provided by any of the other players. So,neither the co-lo players nor the hyperscalers look at providing the solution of powered shell. So, I think what we are doing through our action of providing both land as well as powered shell solution is expanding the market because we are giving solutions which currently are not available from any other solution provider.
Question
Parikshit Kandpal: Okay. Sir, last question on the key markets on the residential side. If you can help us understand, I mean, how is Bangalore behaving? What's your initial view on NCR? Even in MMR, especially on the luxury side, have you seen any improvement on the luxury sentiment? I think last quarter, we had some fall -through sales because of the geopolitical. Have you seen the demand coming back now? Any sense on that?
Answer, abhishek lodha
Abhishek Lodha: Yes. I think in MMR, the impact of the start of the Middle East crisis that has abated. So , we've gone back to a normalized behavioural pattern in terms of the closure of high-value sales. Bangalore is shaping quite well. We had, as Prashant mentioned, the launch this quarter, and that's started off very well, ahead of our expectations. So that's shaping well. NCR, of course, we will have a launch in the second half of this fiscal year, and we'll see how that goes.
Answer, abhishek lodha
This is how things have evolved for us in Pune and Bangalore remain cautiously optimistic.
Answer, abhishek lodha
Abhishek Lodha: The answer really is evolving because technology continues to evolve quite rapidly. The power density of land has changed quite significantly and currently runs at somewhere between 11 megawatts to 15 megawatts per acre. So that's really the number right now. But what it will be in 2 years or 4 years' time is very difficult to know because obviously, power density seems to be moving upwards. Biplab: So how much power tie-up do you have currently?
Answer, abhishek lodha
Abhishek Lodha: We currently have tie-up for 3 gigawatts. Biplab: So, 3 gigawatts data center, we can build without any new tie -up that is.
Answer, abhishek lodha
Abhishek Lodha: That's correct. Biplab: Okay. And second question is on the overall competitive advantage. You and other player s are also getting aggressively into data center. So just trying to understand what is the competitive advantage for a player like you? Is it primarily access to large contiguous land parcels and tie - up to power? So, suppose if some developer hypothetically, he has both a lot of land parcel in Navi Mumbai or Delhi and also has a power tie -up.
Answer, abhishek lodha
Abhishek Lodha: Yes. So, I think the primary requirements for this business ar e land, contiguous land, power and water, recycled water. And now as the business starts moving towards, I would say, a level of growing up/maturing, it depends on the ecosystem, who's already present there, what is the infrastructure which has already bee n built out and the relationships that one has with the various capacity builders. So, it's a business where others can, of course, try to compete, but we believe that there is a clear competitive advantage that we have because we've been on this for seve ral years and have built an ecosystem as well as deep relationships in addition to, of course, the physical infrastructure that you already highlighted.
Answer, abhishek lodha
Abhishek Lodha: Kunal, I think it's important to note that the early price points that we offered were really to create the location. So, I would say that those pr ice points were below market, and that was really the cost of creating the location and establishing the ecosystem. Having now incurred that cost in the earlier transactions, we are moving more towards market price. We think fair market price is closer to about INR 650 million per acre. And we hope that over the next 18 months, we can reach that level. In terms of value addition, as Sushil highlighted, we obviously incur a modest amount of cost, perhaps about 10% to 15% of the sales price at the current level of about INR 420 million per acre towards building out some infrastructure and making the land ready for them to start construction soon. So,there is a variety of things which goes into it.
Answer, abhishek lodha
But yes, I would say is that the fair market value of the land that we have is more like INR 650 million per acre. Kunal: Got that. And then just a quick follow-up. I heard you on the commitment or the access to 3 gigawatt of power that you already have. But we also hear that data center also needs access to power for long durations. So, would you be signing up contracts with the power agencies for, let's say, a 10- to 15-year contract? Or would it be like in short burst and then there might be the risk of price increase beyond that?
Answer, abhishek lodha
Abhishek Lodha: I think the fact, Kunal, is that these are all rapidly evolving fields, and we continue to work with experts and build out our own internal capabilities around that. We also work very closely with our clients who are actually the ultimate consumers of the power. So, we will be looking at all of those, but it's not that we are the consumers. So, the consumers are the end occupiers of the spaces. So, we work closely with their strategy.
Questions about this call
- When was the Lodha Developers Q1 FY27 earnings call transcript filed?
- Lodha Developers filed the transcript with the exchange on 30 Jul 2026. This page is built from that transcript.
- What does this page list?
- 93 statements from the transcript across 10 topics, 65 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 10 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.