The company was on track to produce around 10,000 metric ton per day this time. The company planned to commission the Numaligarh Refinery expansion in December 2025, with commissioning of select units on track. Combined oil and gas production was 1.652 million metric ton of oil equivalent in Q2 FY '26 and 3.332 MMTOE in HY FY. The company has identified more than 100 varieties of crude and will import according to which crude gives the base economics, provided there are no sanctions against a particular country; it must abide by the rules in force at the time. The company budgeted around INR7,000 crores for total capex during the current year, distributed between E&P activity and normal PPE; the budget includes around INR1,927 crores for E&P activity, around INR1,700 crores for development drilling, around INR650 crores for seismic, and INR2,284 crores for normal PPE.

The numbers management gave

Results

  • Combined oil and gas production was 1.652 million metric ton of oil equivalent in Q2 FY '26 and 3.332 MMTOE in HY FY.
    Show source
    The combined oil and gas production for Q2 FY '26 is 1.652 million metric ton of oil equivalent and for HY FY, it is 3.332 MMTOE.
  • Crude oil production was 0.848 million metric tons in Q2 FY '26, down 0.6% quarter-to-quarter and 2.58% year-to-year.
    Show source
    The crude oil production for the quarter stood at 0.848 million metric tons, a minor decrease of 0.6% on quarter-to-quarter.
  • Natural gas production was 0.804 bcm in Q2 FY '26, down 2.8% quarter-to-quarter and up 0.6% year-to-year.
    Show source
    The natural gas production for the quarter stood at 0.804 bcm at marginal decrease of minus 2.8% on quarter-to-quarter, an increase in 0.6% on a year-to-year basis.
  • The company drilled 18 new wells in Q2 FY 2026, achieving 100% of its target drilling, and drilled 32 wells in HY 2026, an increase of 28% year-to-year.
    Show source
    Oil India has drilled 18 new wells in Q2 FY 2026, achieving 100% of our target drilling and drilled 32 wells in HY 2026, an increase of 28% on year-to-year.
  • Average crude oil price realization was $68.19 per barrel during Q2, versus USD79.33 barrel in the previous quarter of the previous year.
    Show source
    Here, the average crude oil price realization during Q2 was $68.19 per barrel versus USD79.33 barrel in the previous quarter of the previous year.
  • Crude oil price realization was USD67.22 per barrel in FY '26 half year, versus USD82.09 per barrel.
    Show source
    In FY '26 half year, the crude oil price realization was USD67.22 per barrel versus USD82.09 per barrel.
Show 42 more statements

Results

  • Revenue went down nearly about 44% compared to the previous year because of an 18% reduction in crude oil price.
    Show source
    This was the major impact on our revenue because of reduction in crude oil price by 18%, our revenue has gone down at nearly about 44% as compared to the previous year.
  • Natural gas price was $6.78 per MMBTU versus $6.70 per MMBTU compared to the previous year.
    Show source
    It was $6.78 per MMBTU versus $6.70 per MMBTU.
  • Standalone revenue was INR5,456 crores in Q2 FY 2026, up around 9% quarter-to-quarter.
    Show source
    The standalone revenue for Q2 FY 2026 was INR5,456 crores, which has grown on quarter-to- quarter around 9%, which is mainly due -- quarter-to-quarter around 9%.
  • Revenue was INR10,469 crores in FY '26.
    Show source
    And FY '26, it was INR10,469 crores.
  • EBITDA margin fell to 34% from 47% in the previous quarter because of reduced revenue and well write-offs.
    Show source
    Because of reduction in revenue and well write-offs, our EBITDA margin has also gone down to 34% as compared to 47% in the previous quarter.
  • PAT was INR1,044 crores in Q2 FY 2026, reflecting 28.8% growth quarter-to-quarter.
    Show source
    The PAT for Q2 FY 2026 was INR1,044 crores, reflecting 28.8% growth on quarter-to-quarter.
  • Profit was INR1,857 crores in FY '26 HY compared with INR3,300 crores in the previous year, primarily because of lower price realization and higher provisioning of its E&P activities.
    Show source
    For half year, the profit stood at INR1,857 crores as compared to INR3,300 crores in the previous year, which is primarily because of lower price realization and higher provisioning of our E&P activities.
  • EPS was around INR6.42 per share, reflecting 28% growth quarter-to-quarter.
    Show source
    Because of lower profit, the EPS has also come down to around INR6.42 per share.
  • Material subsidiary NRL had revenue of INR6,442 crores during the quarter, up around 2.5% quarter-to-quarter and almost 24% year-to-year.
    Show source
    A brief performance of our material subsidiary, NRL, our Material subsidiary -- the revenue of our material subsidiary NRL during this quarter was INR6,442 crores, which is up by around 2.5% on quarter-to-quarter and almost 24% on a year-to-year basis.
  • NRL's refinery capacity utilization was 100% plus and distillate yield was 86% in Q2 of FY 2026.
    Show source
    The refinery achieved a capacity utilization of 100% plus and the distillate yield stood at 86% for Q2 of FY 2026.
  • NRL's gross refinery margin was USD10.56 per barrel in Q2 FY '26, up 110% from the previous quarter, and $7.73 per barrel for FY 2026 for the half year.
    Show source
    The gross refinery margin was USD10.56 per barrel for Q2 FY '26.
  • NRL's EBITDA was INR989 crores and PAT was INR725 crores for the quarter.
    Show source
    The EBITDA was INR989 crores for the quarter with PAT landing to INR725 crores.
  • NRL's EBITDA was INR1,774 crores and PAT was INR1,213 crores for FY '26 HY.
    Show source
    And for FY '26 HY EBITDA was INR1,774 crores and PAT was INR1,213 crores.
  • The company reported consolidated turnover of INR9,175 crores and PAT of INR1,640 crores for Q2 FY '26.
    Show source
    And a brief consolidated view of our company on the consolidated basis, reported a turnover of INR9,175 crores and PAT of INR1,640 crores for Q2 FY '26.
  • The company provided around INR700 crores during the first quarter for two blocks, one in Bangladesh and one in Gabon.
    Show source
    It was amounting to around INR700 crores.
  • The company provided around INR723 crores for a well drilled during the quarter in its Andaman basin in Vijayapuram-2.
    Show source
    We have also provided for that in around INR723 crores.
  • The company had higher other expenses during the quarter compared to the previous year because of the provisions for two blocks in Bangladesh and Gabon and the Vijayapuram-2 well in Andaman basin.
    Show source
    This is the only reason which we are having higher other expenses during the quarter as compared to the previous year.
  • Employee expenses were around INR60 crores higher than the previous half year because the actuarial valuation of its gratuity liability was based on an increase from INR20 lakhs to INR25 lakhs after DA crossed 50%, reaching 51.29% during the quarter.
    Show source
    Page 5 of 20 Oil India Limited November 17, 2025 So the actuarial deficit, which has been accounted during this quarter is around INR60 crores.
  • Employee benefit increase was mainly due to INR60 crores of increased actuarial valuation of gratuity expenses.
    Show source
    But the major amount because increase in employee benefit is for the increase in actuarial valuation of gratuity expenses, which is INR60 crores.
  • The company achieved production of 9,720 metric tons per day at the end of the year and 9,722 metric tons per day in September '15, equivalent pro rata to about 3.52, 3.53.
    Show source
    We achieved 9,720 metric tons per day at the end of the year also in the month of September -- September '16 -- we achieved -- September '15, we achieved 9,722 metric tons per day, which goes to -- which pro rata which goes to about 3.52, 3.53 something like that.
  • Production dropped to 8,100 metric ton per day and has since been brought back to close to 9600.
    Show source
    Because of that, the production dropped to 8,100 metric ton per day.
  • Natural flow was disturbed in around 10, 11 wells, which did not come back, but other wells and new drilling added to production.
    Show source
    So we are because what happens when our natural flow is disturbed in some of the wells around 10, 11 wells, which didn't come.
  • NRL did not take a shutdown in Q2; a marginal dip in crude availability from Oil India affected NRL, but NRL was still operating at more than 100% utilization, had accumulated crude and was receiving an imported parcel, and management expects utilization to be above 100% again this quarter.
    Show source
    There was -- as we are dependent on the crude supply from Oil India and there was a very marginal dip on the availability that also affected us.
  • NRL's 10.56 GRM had an inventory impact of only $0.44.
    Show source
    Management: Mr. Sen, actually, this 10.56has an impact of only $0.44.
  • Production went below close to 9,000 for almost 1 month within the almost 2 months before November 17, compared with production of 9,720.
    Show source
    Almost 2 months -- out of this 2 months, if we're out of these 2 months, almost 1 month, our production went below close to 9,000, which we were producing at 9,720.
  • The company provided INR723 crores for well number 2, which it considered to have no presence of hydrocarbon and treated as abandoned in its books; drilling and study of the other wells are still ongoing, and they will not be written off until absence of hydrocarbon is finally established.
    Show source
    We have provided for well number 2 for INR723 crores.
  • The company will not capitalize well number 2 in the future because it has provided for the well and concluded that there is no presence of hydrocarbon.
    Show source
    So as of now, for well number 2, you can -- we can conclude that we have provided, and this cannot be capitalized in the future.
  • The company said a temporary production slowdown owing to external factors in the Northeast region of the country drove its production dip; operations had normalized and daily production was again on its normal pace.
    Show source
    The key rationale of our production dip was driven by a temporary production slowdown owing to the external factors in the Northeast region of the country.
  • An economic block by one of the ethnic groups in the Eastern part required Oil India Limited to close wells because people could not move to work inside or outside the oil facilities.
    Show source
    But in the process, what happened is that we have to close down well because people cannot move for work inside and outside the facilities, oil facilities.
  • NRL had no maintenance-related shutdown in Q2, but took a small shutdown in Q3 for a safety-related issue in its primary unit and has completed that shutdown.
    Show source
    So there was no maintenance related shutdown in Q2 and Q3, there was a small shutdown that we had to take on safety related thing in our primary unit, but we are out of that shutdown.
  • NRL's second-quarter margins resulted in its reported GRM, inventory was not a factor, and that kind of margin continued in the third quarter.
    Show source
    So basically, the quarter 2 margins, which were available has resulted in this GRM that you have seen.
  • During H1, Oil India Limited provided for major expenditure on two blocks; it provides for well assets in the normal course of business when a well has not achieved what was planned.
    Show source
    Abhijit Das: See what happened during H1, we have provided for two of our blocks -- the major expenditure.
  • The amount for the quarter was INR723 crores. Replaced by a later filing.
    Show source
    Abhijit Majumder: No, it is INR723 crores for this quarter itself.

Money and capital

  • Board declared a dividend of INR3.50 per share during the quarter.
    Show source
    We are pleased to inform you that the Board has declared a dividend and the dividend amount is INR3.50 per share during this quarter.
  • The company budgeted around INR7,000 crores for total capex during the current year, distributed between E&P activity and normal PPE; the budget includes around INR1,927 crores for E&P activity, around INR1,700 crores for development drilling, around INR650 crores for seismic, and INR2,284 crores for normal PPE.
    Show source
    Abhijit Das: During the current year, we had budget about around INR7,000 crores of our total capex.
  • Capex spending of around INR5,561 crores includes around INR550 crores contributed as equity to its material subsidiary.
    Show source
    As of now, till date what we have been able to achieve is around INR5,561 crores has already been spent on account of our capex expenses.
  • The company had achieved around 70% to 75% of its capex budget within the last 7 months and expects to go beyond its budgeted figure.
    Show source
    So our achievement to a large extent is around 70% to 75% within this last 7 months, we are expecting to be beyond our budgeted figure.
  • The company spent INR8,000 crores on capex in '24-'25 against a budget of INR6,880 crores.
    Show source
    If I can just quote the numbers for '24-'25 against a budget of INR6,880 crores, Page 10 of 20 Oil India Limited November 17, 2025 INR6,880 crores, our spending has been INR8,000 crores.
  • Total capex utilization till date is INR5,561 crores; it budgeted INR2,284 crores for capital equipment and spent INR1,280 crores, budgeted around INR3,500 crores to INR3,600 crores for exploration and development drilling and spent INR2,200 crores, planned INR629 crores for survey and spent INR572 crores, and planned around INR100 crores or INR120 crores for overseas and spent around INR385 crores.
    Show source
    See, INR5,561 crores is our total capex utilization till date.
  • Planned investment in subsidiaries and joint ventures increased from around INR350 crores at the beginning of the year to INR1,117 crores because of the add-on of the NRL investment.
    Show source
    For subsidiaries and joint ventures, which we planned around INR350 crores in the beginning of the year, because of the add-on of the NRL investment, it is now standing at INR1,117 crores.
  • NRL had INR17,799 crores of total debt as of Q2.
    Show source
    Abhijit Das: If you see that the leveraging ratio for NRL as of now for Q2, what we have, it is INR17,799 crores of total debt has been already been taken by NRL.
  • Cash investment activity shown in the cash flow may not equal capex achieved because it includes both investment and financing activities.
    Show source
    So, the cash investment activity, which has been shown in the cash flow, that may not be the exact figure with what we have already been achieved through the capex because it is a mix of investment as well as the financing activities also.

What it expects ahead

What management expects

  • The company was on track to produce around 10,000 metric ton per day this time.
    Show source
    So what happened is that -- and we were on a track where we were going to be around 10,000 metric ton per day this time.
  • The company expects production to be around 3.5 plus this time if no such blockade happens.
    Show source
    And it is -- if no such blockade happens, then we are expecting that we'll be around 3.5 plus this time, this is beyond our hand actually.
  • NRL expects to exceed 100% utilization in Q3 and maintain more than 100% utilization for the entire year.
    Show source
    So hopefully, in Q3 also, we will exceed 100%.
  • Target for production is 3.5 to 3.55.
    Show source
    Like you asked me for a number, so I say that 3.5 to 3.55 will be my target for the production.
  • The company set a target of 3.70 MMT for oil and 3.65 for gas for '25-'26.
    Show source
    So because of that, we will have a little bit less with respect to 3.65 bcm is our target, for the gas.
  • The company is likely to exceed its budget provision this year, based on its track record of exceeding budget provisions.
    Show source
    So, the same is likely to happen this year, too.
Show 7 more statements

What management expects

  • The gas production numbers reflected are as per the ramp-up plan of the NRL new refinery, whose consumption will increase in steps rather than start on day one.
    Show source
    But the numbers that were reflected here are as per the ramp-up plan of the NRL new refinery.
  • The company targets gas production for the whole year, not half-year periods, and expects production to be higher than last year because it can ramp up gas production.
    Show source
    And we are trying to cope up and we are -- we will be having more production with respect to last year, that is for sure.
  • The company cannot increase gas production by much despite having capacity during the lean time for tea gardens, but is ready to supply other industries; production may increase further if NRL increases and the DNPL index is brought forward.
    Show source
    And hopefully, if NRL increases and if somehow, we can bring it forward, this DNPL index, then maybe we can increase further.
  • The company expects production to be the same as or a little higher than last year, not lower.
    Show source
    And I think we will be having the same production or a little bit higher production with aspect to the last year, not less.
  • The refinery's capacity ramp-up will be gradual, with serious volume expected in Q2 of next FY and rapid capacity ramp-up from June onwards, July onwards; commissioning activity will take place before then.
    Show source
    Any very serious volume will come in the Q2 of next FY.
  • The company is trying to bring production close to its expected level through optimization and changes to its strategies, but it does not say it will reach the expected level. Replaced by a later filing.
    Show source
    But we -- we are trying our level best to bring it to the level if it is not below -- not up to the expected level, but quite close to expected level.
  • The company is trying to bring in new wells every day and is working well by well with teams to bring production to its expected level. Replaced by a later filing.
    Show source
    Every day, I'm going well by well with the teams so that I can bring the production to the level which we have expected.

What it is building and selling

Projects and capacity

  • The company planned to commission the Numaligarh Refinery expansion in December 2025, with commissioning of select units on track.
    Show source
    On the downstream side, expansion of Numaligarh Refinery is gathering momentum with commissioning of select units on track, and we are well planned to get commissioned in December 2025.
  • Area 1 concessionaries declared force majeure and suspended development activities in April 2021 after degradation of the security situation in Cabo Delgado province in Mozambique.
    Show source
    In April 2021, degradation of the security situation in Cabo Delgado province in Mozambique necessitated to Area 1 concessionaries to declare force majeure and suspended the development activities.
  • The force majeure for Area 1 in Mozambique was withdrawn from November 2025.
    Show source
    We have a good news here that the force majeure has been withdrawn from November 2025.
  • The Honorable Prime Minister inaugurated the Assam bioethanol plant, a joint venture of Oil India Limited's material subsidiary, NRL, in Golaghat District of Assam on September 14, 2025.
    Show source
    The Honorable Prime Minister inaugurated the Assam bioethanol plant, a joint venture of our material subsidiary, NRL in Golaghat District of Assam on September 14, 2025.
  • India's first 2G biothanol plant uses bamboo as feedstock.
    Show source
    This is India's first 2G biothanol plant that uses bamboo as feedstock.
  • Joint venture company M/s Assam Petrochemicals Ltd commissioned its 200 TPD formalin plant in Boitamari in Bongaigaon.
    Show source
    Our 200 TPD formalin plant is commissioned in Boitamari in Bongaigaon of M/s Assam Petrochemicals Ltd our joint venture company in the Northeast.
Show 24 more statements

Projects and capacity

  • The company has completed all mechanical works on the DNPL pipeline; the next steps are obtaining PESO and PNGR PESO approvals and PNGRB authorization for expanded capacity, and hooking it up with the existing pipeline, which would require 7 days of pipeline disruption.
    Show source
    So, yes the DNPL pipeline mechanically, we have completed all the works.
  • The company plans supplementary 3D seismic to appraise the Vijayapuram 2 gas occurrence and provide tighter subsurface control for planning future wells and its exploration and exploitation strategy.
    Show source
    But our plans have to appraise the Vijayapuram 2 occurrence of gas for which we are planning supplementary 3D seismic which is going to give us tighter control of the subsurface to plan future well and define the new strategy for exploring and exploiting hydrocarbon resources from there.
  • The company has 3 plus 1 wells in line of sight in Andaman: two already drilled, a third under drilling, and one in Andaman West; the number of wells may increase depending on success and appraisal.
    Show source
    So we have in line of site 3 plus 1 well as of now, which includes the two number of wells, which have already been drilled, the third well, which is on the drilling and there is one well in the in Andaman West, but depending upon the success and the appraisal, the exploration strategy will be charted out and we will go ahead with the momentum of discovering these hydrocarbon resources and the number of wells may increase in due course of time.
  • The company plans to carry out supplementary seismic in Andaman within another 3 to 4 months to obtain numbers from the appraisal of the gas occurrence.
    Show source
    Once that is available with us, which we are planning very shortly, I think within another 3 to 4 months, we'll be carrying out the supplemental seismic in Andaman.
  • The company has completed around 95% of the DHDT plant, which is ready for pre-commissioning and has pre-commissioning underway.
    Show source
    Bhaskar Jyoti Phukan: We have already done around 95% in one of the plant called DHDT.
  • The company is hopeful that it will be in a position to commission its primary unit by end of December, after which other units will come gradually; the complex refinery may take 2 quarters to stabilize.
    Show source
    So, we are hopeful that by end of December, we should be in a position to commission our primary unit and gradually other units will come.
  • There is no plan for a shutdown before FY '27; shutdown will come in FY '27.
    Show source
    Shutdown will come in FY '27 only.
  • The company has established the occurrence of gas in an exploratory well and is conducting supplementary 3D seismic to better determine the extent of the sand bodies where hydrocarbons could be trapped.
    Show source
    And what we have established is the occurrence of gas.
  • The Andaman discovery is in shallow waters, with a water bathymetry of 300 meters.
    Show source
    The water bathymetry is 300 meters.
  • The company achieved mechanical completion of the Upgradation of Facilities of the Numaligarh–Siliguri Product Pipeline (NSPL) on 12th October 2025.
    Show source
    Page 2 of 20 Oil India Limited November 17, 2025 The midstream pipeline expansion is progressing well, and we are glad to announce you that the mechanical completion of our Numaligarh Siliguri pipeline was commissioned on 12th of October 2025.
  • Offshore exploration campaign in Andaman Basin achieved a key milestone with gas occurrence in East Andaman.
    Show source
    Additionally, our offshore exploration campaign in Andaman Basin has achieved a key milestone with gas occurrence in East Andaman.
  • The company is planning the DNPL pipeline disruption as it proceeds with PNGRB authorization.
    Show source
    So we are planning it as we proceed with PNGRB authorization.
  • Primary unit CDU VDU has pre-commissioning underway and is scheduled for pre-commissioning.
    Show source
    The primary unit CDU VDU scheduled pre-commissioning is underway.
  • The company has observed traces of hydrocarbon in the area, but it is not a discovery; further studies are needed before a discovery can be declared, and ED exploration may take up further explanation once a discovery is established.
    Show source
    What we have basically informed the community is that we have observed traces of hydrocarbon in that particular area.
  • The company has crossed the first phase of finding out whether the hydrocarbon traces constitute a discovery; capitalization would depend on other factors.
    Show source
    So that is the first phase, which we have basically just crossed.
  • The first crude intake at the refinery is likely to happen in December this year, with commissioning proceeding one unit after the other.
    Show source
    So first the crude intake is likely to happen in December itself.
  • The third well currently being drilled is a pure exploratory well, not an appraisal well.
    Show source
    It is a pure exploratory well, the third well that we are drilling right now.
  • If hydrocarbons are established in the well, Oil India Limited will take it through an appraisal phase, conduct further geoscientific analysis and then ascertain volumes before deciding on an appraisal and field development program.
    Show source
    So what we will essentially do is we'll drill this well if we establish hydrocarbons over there.
  • The discoveries are in shallow water, not deep water.
    Show source
    This belongs to still shallow water you can say?

Demand and pricing

  • Tea gardens take less gas in this month, making demand an important factor in gas production.
    Show source
    Page 13 of 20 Oil India Limited November 17, 2025 Now is the time for the tea gardens, they take less gas in this month.

Segments

  • The company has identified more than 100 varieties of crude and will import according to which crude gives the base economics, provided there are no sanctions against a particular country; it must abide by the rules in force at the time.
    Show source
    So we will import accordingly.

Deals and partners

  • The company has a service agreement with Total Energies and has leveraged its expertise in well design, planning and other engineering strategies for exploration activities; it is trying to expand the scope of services, but has not declared further engagement because it is still working on it.
    Show source
    And in this context, let me tell Page 11 of 20 Oil India Limited November 17, 2025 you that we have a service agreement with Total Energies, which is an oil and gas major, which has enormous amount of experience when it comes to deep and ultra-deepwater exploration.
  • The company is hopeful it will have some sort of engagement with Woodside Energy to partner on exploration, with the objective of building technical knowledge and expertise.
    Show source
    One of them is Woodside Energy, where we are hopeful that we'll be able to have some sort of engagement with them so that we can partner together more than the financial part, what our objective is that the technical knowledge base and expertise is what builds upon success in any exploration activity per se.
  • The company is seeking offshore discoveries in the offshore frontiers of Indian sedimentary basins through potential partnerships that build technical knowledge and expertise. Replaced by a later filing.
    Show source
    So, this is a forte and this is what we are looking for so that together, we can synergize together and lead to some good discoveries in the offshore frontiers of Indian sedimentary basins.

Risks, rules and outside factors

Risks and disputes

  • The company has provided for its Gabon and Bangladesh assets in its books of accounts; final write-off will occur only after it decides all activities for the blocks have closed and they must be wound up, and the final write-off may take place by the end of this year.
    Show source
    We have provided in our books of accounts, but the final write-off may positively or indicatively maytake this by end of this year.

Rules and policy

  • The Government of India regulated the price of crude oil by the benchmark aligned during the half year. Replaced by a later filing.
    Show source
    The price of crude oil has been regulated by the benchmark aligned by the Government of India during the half year.

Everything else said on the call

Group structure

  • The company holds 4% in Area 1 in Mozambique through its joint venture entity, BREML.
    Show source
    A brief on our international fund, Oil India holds 4% in Area 1 in Mozambique through its joint venture entity, BREML.
  • The company has thought of exiting the area in Gabon; further expenses may arise from ongoing closure efforts.
    Show source
    So whatever expenses we have incurred maybe a little more expenses would arise based on the closure efforts that are going on.
  • The company and ONGC have decided to exit from the Bangladesh block, and Oil India Limited does not anticipate any further major increase in expenditure in the Bangladesh and Gabon areas.
    Show source
    Both of us have decided to exit from that particular block.

Other

  • Sabri Hazarika asked whether the 3.65 bcm gas production target was for the full year FY '26 or the second half of '26.
    Show source
    Sabri Hazarika: Is that for the full year FY '26 or second half of ' 26, 3.65 bcm.
  • Sabri stated that the DNPL pipeline would be fully commissioned in April 2026, NRL volumes would expand by then, and Oil India Limited would supply NRL around 2 to 2.5 MSMD, and asked if that understanding was correct.
    Show source
    And then if not others, then at least we will supply to NRL around 2, 2.5 MSMD.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    So if you can help us understand what all are the one-off items here, sir?

    Answer, abhijit das

    Abhijit Das: Thank you, sir. During the quarter, as we have witnessed that there was some higher other expenses as compared to the previous year. There is only 1 minor reason of having higher expenses because and during the first quarter, what we have done, we have provided for our 2 blocks. One is in for Bangladesh and a one is for Gabon. Both these blocks we have already provided in our financial statement during the first quarter. It was amounting to around INR700 crores. And one well we have drilled during the quarter in our Andaman basin in Vijayapuram-2.

    Answer, abhijit das

    We have also provided for that in around INR723 crores. This is the only reason which we are having higher other expenses during the quarter as compared to the previous year.

  2. Question

    Gaurav Jain: On this Bangladesh and Gabon write-off, how should we be thinking about it going forward because it is now appearing in quite a few quarters?

    Answer, abhijit majumder

    Abhijit Majumder: So see, Gabon, as far as Gabon is concerned, we have thought of exiting from that area. So whatever expenses we have incurred maybe a little more expenses would arise based on the closure efforts that are going on. So apart from that, Bangladesh is also a closed chapter as far as the entire JV is concerned. We are in partnership with ONGC there. Both of us have decided to exit from that particular block. So we don't anticipate any further major increase in expenditure in each of these two areas. .

  3. Question

    Gaurav Jain: Sir, employee expenses, if you will see at INR526 crores, that is also higher than the run rate that we have been seeing a little on the higher side?

    Answer, abhijit das

    Abhijit Das: For employee expenses, what we have seen, you have witnessed that there is around INR60 crores of more expenses as compared to the previous half year. So during the our pay revision government has mandated that once your DA percentage will increase up to -- across 50%, then your gratuity amount will increase from INR20 lakhs to INR25 lakhs. So, during this quarter, we have witnessed that our DA has crossed 50%. It is 51.29% during the quarter. So as the gratuity liability of the company has already increased, we have carried out the actuarial valuation considering the liability of the employee strenghth from INR20 lakhs to INR25 lakhs. Page 5 of 20 Oil India Limited November 17, 2025 So the actuarial deficit, which has been accounted during this quarter is around INR60 crores. That is the only reason, which the employee benefit has gone up as compared to the previous half year.

    Answer, abhijit das

    Rest, normal -- marginal increase of our employee costs relating to increase your normal salary and some medical benefits. But the major amount because increase in employee benefit is for the increase in actuarial valuation of gratuity expenses, which is INR60 crores.

  4. Question

    Gaurav Jain: Yes, sir, you are audible. Yes.

    Answer, trailukya borgohain

    Trailukya Borgohain: So there are a few factors actually that affected Q1 and Q2 both Q1 mostly, what happened is that we had a little bit extra loss due to LPGs shut down, that was unwanted and we never planned it. So because of that, we had some more loss in the first quarter. And also in the second quarter what happened is that I'd like to correct one line that the production impact dropped from 9,720 metric tons. We achieved 9,720 metric tons per day at the end of the year also in the month of September -- September '16 -- we achieved -- September '15, we achieved 9,722 metric tons per day, which goes to -- which pro rata which goes to about 3.52, 3.53 something like that. So what happened is that -- and we were on a track where we were going to be around 10,000 metric ton per day this time. But what happened is that there are a few ethnic groups here, six ethnic groups. And one of the ethnic groups in the Eastern part and they -- because they want the SC Status because of -- they did the economic block, not against Oil India, but it is to the government.

    Answer, trailukya borgohain

    But in the process, what happened is that we have to close down well because people cannot move for work inside and outside the facilities, oil facilities. Because of that, the production dropped to 8,100 metric ton per day. Now we are hovering, we have brought it back to 9600 -- close to 9600. So we are because what happens when our natural flow is disturbed in some of the wells around 10, 11 wells, which didn't come. But we tried -- we have tried with other wells and also from new drilling, we have added to this amount. And the decline which we thought that it will create, but it didn't create that much, but we are again on right track. And it is -- if no such blockade happens, then we are expecting that we'll be around 3.5 plus this time, this is beyond our hand actually.

  5. Question

    Gaurav Jain: Yes.

    Answer, abhijit majumder

    Abhijit Majumder: I think Tuhin will take this question. Management: Thank you so much, sir. Good morning everyone. So, yes the DNPL pipeline mechanically, we have completed all the works. And now the next step would be to obtain PESO and PNGR PESO approvals and PNGRB authorization for the expanded capacity. And also, there is one critical step in terms of hooking it up with the existing pipeline. For that, we would need 7 days of disruption in the pipeline.

    Answer, abhijit majumder

    So we are planning it as we proceed with PNGRB authorization.

  6. Question

    Gaurav Jain: Last question, if I may squeeze in a last question on NRL, the throughput at 0.75 metric million tons was also on the lower side, if we look at quarter-on-quarter, we operated at 100% utilization. Was there any maintenance shutdown and if that is complete now?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: Yes. See. We did not take any shutdown. There was -- as we are dependent on the crude supply from Oil India and there was a very marginal dip on the availability that also affected us. But we are still more than 100% and this quarter, we have accumulated crude and then we are getting some imported parcel as well. So this quarter will be above 100% again, actually. So there was no maintenance related shutdown in Q2 and Q3, there was a small shutdown that we had to take on safety related thing in our primary unit, but we are out of that shutdown.

    Answer, bhaskar phukan

    So hopefully, in Q3 also, we will exceed 100%. So, we will maintain more than 100% for the entire year.

  7. Question

    Gaurav Jain: Thank you so much, sir. That was helpful. All the best.

    Answer, ds manral

    So Andaman exploration has been quite a success for us in the sense that we had ventured into Andaman way back in 1980s when we drill seven or eight well. So thereafter, after a long time we had again been into offshore waters because this is the thing, which is happening all around the world where the discoveries are being made. So right now, we have completed 2 number of wells, One was the number one well was Vijayapuram 1 and the second well was Vijayapuram 2, where we could see the occurrence of hydrocarbons, and the gas was even flared Now what we are exactly doing is that we moved to the third well and we are currently drilling it. But our plans have to appraise the Vijayapuram 2 occurrence of gas for which we are planning supplementary 3D seismic which is going to give us tighter control of the subsurface to plan future well and define the new strategy for exploring and exploiting hydrocarbon resources from there. And as far as the total number of wells goes.

    Answer, ds manral

    So we have in line of site 3 plus 1 well as of now, which includes the two number of wells, which have already been drilled, the third well, which is on the drilling and there is one well in the in Andaman West, but depending upon the success and the appraisal, the exploration strategy will be charted out and we will go ahead with the momentum of discovering these hydrocarbon resources and the number of wells may increase in due course of time.

  8. Question

    Probal Sen: Got it, sir. And any sort of timelines you can put on when we can get an estimate, even a contingent resource kind of a number from this region? Any assessment that your exploration team or seismic team has done at this point of time?

    Answer, ds manral

    DS Manral: As I told you in my -- as I told you that a very thorough appraisal of the occurrence of gas is required irrespective of the well, which is being drilled because each of the wells will be taken into account accordingly. So, we are planning a supplementary 3D seismic, which gives you a better image and tighter control of the subsurface. Once that is available with us, which we are planning very shortly, I think within another 3 to 4 months, we'll be carrying out the supplemental seismic in Andaman. So, this will give us those numbers which are much awaited by us as well.

  9. Question

    Probal Sen: The second question was with respect to the NRL numbers. Is it possible to share if there was any significant inventory component in the $10.6 GRMs for this quarter?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: Yes. You have the number -- you have the numbers. You can share the numbers. Yes. Management: Mr. Sen, actually, this 10.56has an impact of only $0.44. So this is very minimal.

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: So therefore, the inventory was not the factor here. Actually, we enjoyed a very good margin in the second quarter. And the good news is that, that kind of margin still continues in the quarter 3. So basically, the quarter 2 margins, which were available has resulted in this GRM that you have seen.

  10. Question

    Probal Sen: Understood sir. So, one final question about the expansion. If you can kindly just once again refresh to what's the latest timeline for physical completion and commissioning of the expanded capacity?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: We have already done around 95% in one of the plant called DHDT. So that is ready for pre- commissioning, in fact, pre-commissioning is underway. The primary unit CDU VDU scheduled pre-commissioning is underway. So, we are hopeful that by end of December, we should be in a position to commission our primary unit and gradually other units will come. But since it is a very, very complex refinery, you will understand that. I mean you have seen other refineries. So, it takes while maybe 2 quarters to stabilize.

    Answer, abhijit majumder

    Abhijit Majumder: First of all, it's not a discovery. What we have basically informed the community is that we have observed traces of hydrocarbon in that particular area. So, for it to be declared a discovery, it needs further studies and maybe ED exploration can take it up to further explain once a discovery is established, then we certainly capitalize. However, before the discovery can be declared before discovery can be declared, lots of studies need to be carried out, which we are in the process of carrying out – so ED exploration, I think that answers your query you need further clarification.

    Answer, abhijit majumder

    Abhijit Majumder: Yes, yes. That's the right understanding. And capitalization would depend on so many other factors. But everything begins with the traces of finding out discovery -- hydrocarbon. So that is the first phase, which we have basically just crossed.

    Answer, abhijit das

    Abhijit Das: During the current year, we had budget about around INR7,000 crores of our total capex. The total capex has been distributed between your E&P activity as well as your normal PPE. So out of that E&P activity, we have around INR1,927 crores of budget of development drilling around INR1,700 crores. And our seismic is around INR650 crores. If you add up these -- all these three figures, it will be around 60% of our budgeted figure of INR7,000 crores. And normal PPE, what we have budgeted for this current financial year is INR2,284 crores. As of now, till date what we have been able to achieve is around INR5,561 crores has already been spent on account of our capex expenses.

    Answer, abhijit das

    This INR5,561 crores also includes a contribution towards equity to our material subsidiary of around INR550 crores. So our achievement to a large extent is around 70% to 75% within this last 7 months, we are expecting to be beyond our budgeted figure.

    Answer, abhijit majumder

    Abhijit Majumder: Just to add on to what CGM F&A has just said, our capex year-on-year has been rising over the last few years. If I can just quote the numbers for '24-'25 against a budget of INR6,880 crores, Page 10 of 20 Oil India Limited November 17, 2025 INR6,880 crores, our spending has been INR8,000 crores. So basically. Going by our track record, we exceed the budget provision. So, the same is likely to happen this year, too.

    Answer, kirtan mehta

    Kirtan Mehta: Sure, sir. I was asking, we had sort of a softer production in the Q2 than our own expectation. Will this have any implication on the FY '26 target? Or would we be able to compensate it during the second half. Trailukya Borgohain : Definitely because if it was a small hiccup, we will not have been bothered. But this is -- this really impacted a little bit on our production because for around 2020 now -- if you look at in September '16, now today is November – November 17. Almost 2 months -- out of this 2 months, if we're out of these 2 months, almost 1 month, our production went below close to 9,000, which we were producing at 9,720.

    Answer, kirtan mehta

    Now we are bringing it up. But we are trying our level best, because we have changed our strategies also. Now I am here in field headquarters looking at both production and some other aspects also so that we can bring the production up. I'm already here last some 20 days in the field headquarters only so that we can bring the production to that level. And maybe we'll bring it to the level, but I don't say that we'll be able to go to a very -- the expected level. But we -- we are trying our level best to bring it to the level if it is not below -- not up to the expected level, but quite close to expected level. That is what our attempt is are doing optimization.

    Answer, kirtan mehta

    Every day, we are trying to bring in new wells. Every day, I'm going well by well with the teams so that I can bring the production to the level which we have expected. Yes.

    Answer, ds manral

    DS Manral: So reaching out to international oil and gas majors has been at the core of our building momentum to getting into deep and ultra-deep offshore waters. And in this context, let me tell Page 11 of 20 Oil India Limited November 17, 2025 you that we have a service agreement with Total Energies, which is an oil and gas major, which has enormous amount of experience when it comes to deep and ultra-deepwater exploration. And through this service level agreement, what we have done in the past is that we have leveraged their expertise in terms of well design, planning and other engineering strategies so that our exploration activities can come to fruition. And we are further trying to even work upon with them, engage with them to expand our scope of services. And I'm not going to declare it right now because we are still working on it over and above what we already have. Apart from this, we have been reaching out to many other national and international oil and gas majors. One of them is Woodside Energy, where we are hopeful that we'll be able to have some sort of engagement with them so that we can partner together more than the financial part, what our objective is that the technical knowledge base and expertise is what builds upon success in any exploration activity per se.

    Answer, ds manral

    So, this is a forte and this is what we are looking for so that together, we can synergize together and lead to some good discoveries in the offshore frontiers of Indian sedimentary basins. So, outreach is at the core of Oil India's activities.

    Answer, trailukya borgohain

    So 3.5 will be, but we are asking for 3.55. There is a target. Like you asked me for a number, so I say that 3.5 to 3.55 will be my target for the production.

Show 2 more questions
  1. Question

    Sarthak Tita: Got it. This was very helpful. Just one more thing. On FY '27, you mentioned in gas, 3.8 bcm right? That is significantly lower than the Q1 guidance that we had in for gas for FY '27. Considering DNPL to come up by April, which Tuhin mentioned, any other reason that we see that the weakness on the gas production outlook?

    Answer, abhijit majumder

    Abhijit Majumder: Would you like to take it? Management: Yes. So in terms of gas production capacity, we are very well prepared to ramp up gas production to much higher levels. But the numbers that were reflected here are as per the ramp-up plan of the NRL new refinery. So the NRL new refinery consumption won't start in day one. So it would stepwise, increase in steps, and that's how the number are right at here.

  2. Question

    Sarthak Tita: Got it. Thank you so much. It was very helpful.

    Answer, trailukya borgohain

    Trailukya Borgohain: Yes, yes, yes, yes. You see when there is a disruption, so it affects both oil and gas actually. So because of that, we will have a little bit less with respect to 3.65 bcm is our target, for the gas.

    Answer, sabri hazarika

    Sabri Hazarika: Is that for the full year FY '26 or second half of ' 26, 3.65 bcm.

    Answer, trailukya borgohain

    Trailukya Borgohain: This is for the whole year, for the whole year -- we don't target the half year, we don't target actually. We target for the whole year. And we are trying to cope up and we are -- we will be having more production with respect to last year, that is for sure. Because in gas, we can ramp up actually. So we can ramp up. Only thing is that the gas -- in case of gas, what happens is that the demand is the most important part. Page 13 of 20 Oil India Limited November 17, 2025 Now is the time for the tea gardens, they take less gas in this month.

    Answer, trailukya borgohain

    So even if I have the capacity, we cannot increase the gas production by that much. You understand my point. So because tea gardens this is not a plucking time. This is the lean time for the tea gardens. So other industries, when they take, we are ready to give. And hopefully, if NRL increases and if somehow, we can bring it forward, this DNPL index, then maybe we can increase further. That's all.

    Answer, trailukya borgohain

    And I think we will be having the same production or a little bit higher production with aspect to the last year, not less. Sabri: Yes, sir. And second is DNPL, I think possibly that is the main pipeline for you to raise production. So this pipeline, April 2026, it will get fully commissioned and from -- and NRL volumes will also get expanded by that same time. Is that right? And then if not others, then at least we will supply to NRL around 2, 2.5 MSMD. Is that the right understanding?

    Answer, abhijit das

    Abhijit Das: No. Is not like that. See, INR5,561 crores is our total capex utilization till date. But if we run through the figures, this is the capital equipment, which we have budgeted for INR2,284 crores, we have already spent INR1,280 crores. So, for exploration and development drilling is concerned, it was budgeted as around INR3,500 crores, INR3,600 crores. Out of that, we have already spent INR2,200 crores. For survey, which we have planned for INR629 crores, we have already spent INR572. For our overseas, what we have thought of around INR100 crores or INR120 crores, we have already spent around INR385 crores.

    Answer, abhijit das

    For subsidiaries and joint ventures, which we planned around INR350 crores in the beginning of the year, because of the add-on of the NRL investment, it is now standing at INR1,117 crores. So, the cash investment activity, which has been shown in the cash flow, that may not be the exact figure with what we have already been achieved through the capex because it is a mix of investment as well as the financing activities also. Sabri: Got it. And regarding your Andaman, I think Bangladesh and Gabon, I think we had done with the write-off? Or is there anything more pending.

    Answer, abhijit das

    Abhijit Das: We want to make it clear that based on our accounting policies, the principle which we follow as per Ind AS 106. We only write off our wells when it is fully out of question. Now is that we have provided for our Gabon, we have provided for our Bangladesh asset also in our books of accounts. Page 14 of 20 Oil India Limited November 17, 2025 But final write-off will only be taken when we will fully decide that all the activities for the particular blocks have been closed, and we have to wind up them from the fleet. We have provided in our books of accounts, but the final write-off may positively or indicatively maytake this by end of this year. And lastly, we been taken here in the first quarter itself. Sabri: Got it.

    Answer, abhijit das

    Abhijit Das: See what happened during H1, we have provided for two of our blocks -- the major expenditure. Providing for our well assets is a normal course of our business. Whenever we see that a well has not been able to achieve what we have planned for, we automatically, based on our accounting principles, we provide . Sabri: It is INR350 crores, INR360 crores for the two quarters? Or it is just one time Q2 itself INR720 crores? Just wanted to know.

    Answer, abhijit majumder

    Abhijit Majumder: No, it is INR723 crores for this quarter itself. Sabri: Okay. This quarter itself, it is INR723 crores. Okay, sir. Thank you. That's all from my side.

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: No, no. There is no plan for shutdown. Shutdown will come in FY '27 only. Pranitha: Sir, when are you expecting the first crew to take an expanded capacity?

Questions about this call

When was the Oil India Q2 FY26 earnings call transcript filed?
Oil India filed the transcript with the exchange on 21 Nov 2025. This page is built from that transcript.
What does this page list?
98 statements from the transcript across 11 topics, 62 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 12 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Oil India Q2 FY26 concall: Oil India Limited was on track to produce around 10,000 metric ton per day this time · DalalOS