Power Mech Projects Q2 FY25 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company is targeting an order intake of around INR12,000 crores this year and had secured orders worth INR3,100 crores as of 30th September 2024, taking its total order backlog to INR58,000 crores or a little over INR58,000 crores. The company had bids for INR8,900 crores worth of projects in the pipeline, with results expected to be announced in the next 3 to 4 weeks. The company had secured all permissions for the first Kotre Basantpur Mine and expected to break ground probably in the next 3 to 4 days. The company had produced around 382 tons of coal to date while overburden removal and coal production were going on. Close to 80 gigawatts of capacity addition is planned in the power sector by 2032.
The numbers management gave
Results
- The company had produced around 382 tons of coal to date while overburden removal and coal production were going on.
Show source
OB removal and coal production is going on, and till date, we have done around 382 tons of coal production.
- Total income was INR1,035 crores in Q2 financial year 2024-25, against INR937 crores in Q2 FY '24, an increase of 12% year-on-year.
Show source
The reported total income for Q2 financial year 2024-25 is INR1,035 crores against INR937 crores in Q2 FY '24, an increase of 12% year-on-year.
- EBITDA was INR134 crores in Q2 financial year 2024-25, against INR118 crores, a growth of 13%; PAT was INR67 crores, up 31% from INR51 crores in Q2 FY '24.
Show source
EBITDA is INR134 crores as against INR118 crores as a growth of 13% and PAT is INR67 crores, which has grown by 31% compared to INR51 crores in Q2 FY '24.
- EBITDA margin increased from 12.57% in Q2 FY '24 to 12.78% in Q2 FY '25.
Show source
EBITDA margin has gone up from 12.57% in Q2 FY '24 to 12.78% in Q2 FY '25.
- PAT margin increased from 5.47% in Q2 FY '24 to 6.43% in Q2 FY '25.
Show source
PAT margin has gone up from 5.47% to 6.43%.
- Mechanical business contributed INR229 crores in quarter 2 FY '25 against INR148 crores in Q2 FY '24, showing an increase of 10% growth.
Show source
The revenue mix for the quarter 2 FY '25- Mechanical business has contributed INR229 crores against INR148 crores in Q2 FY '24, showing an increase of 10% growth.
Show 26 more statements
Results
- Civil business, including railway and water distribution, contributed INR395 crores in quarter 2 FY '25 against INR496 crores in Q2 FY '24, a decrease of 20%.
Show source
Civil business, including railway, water distribution contributed to INR395 crores against INR496 crores in Q2 FY '24, a decrease of 20%.
- O&M revenues were INR391 crores in quarter 2 FY '25 against INR272 crores in the corresponding period last year, registering growth of 44%.
Show source
O&M revenues are INR391 crores against INR272 crores in corresponding period last year, registering a growth of 44%.
- Electrical business contributed INR9 crores in quarter 2 FY '25 against INR17 crores in Q2 FY '24, a decrease of 47% year-on-year.
Show source
Electrical business, INR9 crores against INR17 crores, a decrease of 47% year-on-year.
- Mining business contributed INR12 crores in quarter 2 FY '25 against 0 in Q2 FY '24.
Show source
Mining business, INR12 crores against 0 in Q2 FY '24.
- Business distribution in quarter 2 FY '25 was 95% domestic and 5% international.
Show source
During the quarter 2 FY '25, the distribution between domestic business and international business is 95% and 5%, respectively.
- Quarter 2 FY '25 contribution was 66% from the power sector and 34% from non-power.
Show source
Contribution from the power sector remained at 66% and non-power contributed 34%.
- Total reported income was INR2,062 crores for 6 months of FY '25, against INR1,808 crores in half year FY '24, an increase of 14% year-on-year.
Show source
Similarly, the total reported income for 6 months of FY '25 stands at INR2,062 crores against INR1,808 crores in half year FY '24, an increase of 14% year -on-year.
- EBITDA was INR257 crores for 6 months of FY '25 against INR223 crores, a growth of 15%.
Show source
EBITDA is INR257 crores against INR223 crores, a growth of 15%.
- PAT was INR127 crores for 6 months of FY '25 against INR102 crores in half year 1 FY '24, a growth of 24% year-on-year.
Show source
PAT is INR127 crores against INR102 crores in half year 1 FY '24, a growth of 24% year-on-year.
- EBITDA margin increased from 12.31% in FY '24 to 12.45% in half year FY '25.
Show source
EBITDA margin has gone up from 12.31% in FY '24 to 12.45% half year FY '25.
- PAT margin increased from 5.66% in FY '24 to 6.17% in half year FY '25.
Show source
PAT margin has gone up from 5.66% to 6.17%.
- Mechanical business contributed INR331 crores for 6 months in FY '25 against INR258 crores in half year FY '24, showing an increase of 14%.
Show source
Revenue mix for 6 months- Mechanical business has contributed INR331 crores against INR258 crores in half year FY '24, showing an increase of 14%.
- Civil business, including Railway and Water Distribution, contributed INR937 crores for 6 months in FY '25 against INR989 crores in half year FY 24, a shortfall of 5%.
Show source
Civil business, including Railway, Water Distribution contributed INR937 crores against INR989 crores in half year FY 24, a shortfall of 5%.
- O&M revenues were INR732 crores for 6 months in FY '25 against INR524 crores in the corresponding previous period, registering growth of 40%; electrical business contributed INR17 crores against INR25 crores, a decrease of 32%.
Show source
O&M revenues are INR732 crores against INR524 crores in corresponding to the previous period, registering growth of 40%.Electrical business, INR17 crores against INR25 crores, a decrease of 32%.
- Mining business contributed INR26 crores for 6 months in FY '25 against 0 during the last year.
Show source
Mining business, INR26 crores against 0 during the last year.
- Business distribution during half year FY '25 was 94% domestic and 6% international.
Show source
During half year FY '25, the distribution between domestic business and international business is 94% and 6%, respectively.
- Half-year FY '25 contribution was 60% from the power sector and 40% from non-power.
Show source
Contribution from the power sector mentioned at 60% and non-power contributed 40%.
- Net current excluding cash and cash equivalents increased from 142 days in Q1 to 147 days in Q2 due to delays in certification of works and realization of receivables, mainly from the Water division, which increased the company's current assets.
Show source
So, as the financial parameters are concerned, net current excluding cash and cash equivalents have increased from 142 days in Q1 to 147 days in Q2 due to delays in certification of the works and delays in realization of receivables mainly from the Water division, resulted in increase in the current assets of the company.
- Power Mech has historically converted 35% to 40% of its opening order book into turnover.
Show source
So we have a history of converting the opening order book of 35% to 40% conversion into the turnover.
- Power Mech achieved its 30% revenue growth target from '22 to '23.
Show source
So in '23 also, we have achieved this 30% target from '22 to '23.
- The company expects to do INR50 crores in this mine.
Show source
Page 6 of 14 Power Mech Projects Limited November 13, 2024 So we are on track to doing INR50 crores in this mine.
- The company has extracted 380,000 metric tons of coal from the Kalyaneswari Tasra Mine, a SAIL mine, from February 2024 to October 2024.
Show source
And the second mine, which is named as Kalyaneswari Tasra Mine, which is a SAIL mine, we have already started extracting coal, and we have extracted 380,000 metric tons till date from February 2024 to October 2024.
Money and capital
- As on 30th September 2024, Power Mech Projects Limited's gross debt was around INR611 crores and net debt was INR64 crores.
Show source
Page 3 of 14 Power Mech Projects Limited November 13, 2024 The debt levels are in control as on 30th September 2024, the gross debt is around INR611 crores and the net debt stands at INR64 crores.
- Debt-equity ratio was 0.34x as of 30 September '24.
Show source
The debt-equity ratio as of 30 September '24 stands at 0.34x.
- The company expects an increase of around INR100 crores in capex on normal assets during the year to meet its regular revenue growth targets.
Show source
N. Aravind: To meet our regular revenue growth targets, we are increasing the capex of normal assets of around INR100 crores capex increase we are expecting during the year.
- The company plans overall capex of INR690 crores in its books for the washery setup for Tasra project over the next 2 years.
Show source
So, there is a requirement of INR690 crores overall capex plan for the washery setup for Tasra project, over a period of next 2 years' time, we will incur this INR690 crores overall capex in Power Mech books.
What it expects ahead
What management expects
- The company had bids for INR8,900 crores worth of projects in the pipeline, with results expected to be announced in the next 3 to 4 weeks.
Show source
And we have bids for INR8,900 crores worth of projects in the pipeline that we have picked for and the results of these projects are expected to be announced in the next 3 to 4 weeks.
- The company is targeting the BOP EPC space, which would represent an opportunity size of INR2.1 lakh crores for the next 4 to 5 years.
Show source
And we are also targeting the BOP EPC space would translate into an opportunity size of INR2.1 lakh crores for the next 4 to 5 years.
- The company expects to expand its order book over the next 5 years, focusing on power and infrastructure while diversifying into green energy.
Show source
Looking ahead, we expect to expand our order book in line with our growth plans over the next 5 years, focusing on our core sectors like power and infrastructure, while also diversifying into green energy.
- Power Mech estimates that future opportunities in the power sector could exceed INR30,000 crores across installation, civil, structural, mechanical and other areas, as well as non-power sectors.
Show source
So from a ballpark basis and a rough calculation of what we figured out is the opportunity size for the future is in the power sector it can go more than INR30,000 crores in various areas of the installation, civil structural, mechanical work and then other areas also in the non-power sector.
- Power Mech will pursue the Telengana EPC tender of 800mw with BHEL, which is bidding with SCCL.
Show source
Of course, Telengana EPC tender of 800mw, we will be aggressively pursuing that opportunity that has to come with the BHEL because BHEL is bidding with SCCL side, we have to see how this takes shape.
- NTPC has a mandate to complete its portion of ordering and capacity addition to meet the need of 26,000mw by '3032.
Show source
Because NTPC has got a mandate to complete their portion of the ordering and also capacity addition to meet need of 26,000mw by '3032.
Show 58 more statements
What management expects
- Management expects most of the balance tenders, except for 4,800 megawatts, to be finalized by the end of the year, with another 6 months possible.
Show source
I expect that except for 4,800 megawatts, most of the balance tenders will be finalized by end of the year, it should be, another 6 months should be possible.
- Finalizing those tenders would bring another INR20,000 crores of opportunities in the power sector segment for Power Mech.
Show source
That will bring up another INR20,000 crores of opportunities in the power sector segment itself for Power Mech .
- Around INR3,500 crores of orders will fortify in the next couple of months, or 3 months maximum.
Show source
Around INR3,500 crores of orders will fortify in the next couple of months, or 3 months maximum.
- ISCO Burnpur has an investment of INR30,000 crores for 4.5 million tons capacity, creating potential opportunities for Power Mech in civil structural and installation business.
Show source
ISCO Burnpur with the investment of INR30,000 crores for 4.5 million tons capacity and there can be opportunities in our side of the work in civil structural and installation business.
- JSPL is planning to invest INR30,000 crores in 5 million tons capacity in Oman, creating opportunities for Power Mech in the Middle East.
Show source
And there are opportunities in the Middle East also JSPL is planning to invest INR30,000 crores in the 5 million tons capacity in Oman.
- Management expects railway investments to continue for another couple of years, and expects road-sector investment of INR1.5 lakhs crores to INR2 lakh crores and more than INR2 lakh crores to INR2.5 lakh crores.
Show source
Then the balance investments will continue to flow in t he railways, we expect another couple of years approval be there with a huge investment of INR1.5 lakhs crores to INR2 lakh crores of road sector more than INR2 lakh crores to INR2.5 lakh crores.
- Power Mech's focus is to bring both mines to steady-state operations or peak rated capacity of 9 million metric tons per annum, which it expects to achieve in 2028.
Show source
So right now, our entire focus perhaps is to bring both of these mines to steady-state operations or peak rated capacity, which is 9 million metric tons per annum, and we expect to achieve this in 2028.
- Power Mech projected revenue growth of 30% in the current year based on its opening order book conversion history.
Show source
So with that basis, we projected the revenue of 30% growth in the current year.
- Power Mech initially expected the Kotre Basan tpur mine to generate around INR50 crores of revenue this year.
Show source
And this mine, initially, we expected to do around INR50 crores of revenue this year, sir.
- Power Mech initially expected the Kotre Basan tpur mine to generate around INR50 crores of revenue this year; it expects to begin extracting overburden in December first or second week after tree cutting and to start supplying the first batch of coal in January.
Show source
So even if we start supplying the first batch of coal in the month of January, if we start extracting overburden in the month of December, which we expect to do by December first or second week after the tree cutting activity is done.
- This mine is expected to reach PRC (Peak Rated Capacity) by 2028, when it will peak in revenues.
Show source
And this mine is expected to reach PRC (Peak Rated Capacity) by 2028.
- The Coal India mine’s PAT is expected to be in the range of 6% to 7% next year, because PAT will be lower until PRC is achieved and investments are required from Power Mech Projects Limited.
Show source
So it will have in the range of 6% to 7%.
- The Coal India mine’s PAT is expected to improve to 12% to 13% once PRC is achieved.
Show source
But once we achieve PRC, the PAT is going to improve significantly, substantially all the way up to 12% to 13%.
- The blended EBITDA of both mines together is expected to be around 20% to 22% when PRC is achieved.
Show source
When we achieve PRC, it will be blended EBITDA of both the mines together will be around 20% to 22%.
- The company remains confident of its order-inflow numbers, citing opportunity size; order book improved in the third and fourth quarter last year after slackness in the first 2 quarters, mainly because of the elections.
Show source
And looking at the opportunity size only, we are still confident of those numbers.
- The company is projecting receipt of another INR9,000 crores in the current year, after receiving INR3,000.
Show source
So another INR9,000 crores we are projecting current year receipt.
- Another 11,440 megawatts of tendering is in the pipeline and has to happen.
Show source
And more than that, I told you another, 11,440 megawatts tendering is in the pipeline that has to happen.
- The company expects a lot of flow on its power sector business over the next 2 to 3 years, 2 years, at least.
Show source
Therefore, over the next 2 to 3 years, 2 years, at least, there will be a lot of flow expected on the power sector business.
- The company is working to build engineering expertise over the next 5 to 10 years to take up engineering procurement and construction contracts for parts of a power plant, including BOP, and cater to a decent amount of BOPPC jobs.
Show source
So we are trying to build some engineering expertise for the next 5 to 10 years to be able to cater to decent amount of BOPPC jobs.
- The MDO order is expected to generate annual recurring revenue for the next 25 years, excluding price variation.
Show source
It's going to be an annual recurring revenue for the next 25 years, excluding the price variation.
- The MDO revenue is expected to recur for 23 years because development takes 2 years.
Show source
It's going to be for 23 years because we are in 2 years for development, yes.
- The company expects its EBITDA margin to grow by 1% to 1.5% over the next 3 to 4 years as its O&M segment increases and the MDO segment is added to its portfolio.
Show source
There is a possibility because the moment we increase our O&M segment and MDO segment added to the portfolio, there is an expectation of 1% to 1.5% growth in EBITDA margin over a period of next 3 to 4 years.
- The company did overseas O&M of around INR200 crores last year and anticipates INR235 crores to INR240 crores this year; it expects overseas O&M to grow at a rate of 30%, 35% CAGR over the next 7 to 8 years, with EBITDA margins in the range of 17% to 19% in overseas O&M.
Show source
And this year, we anticipate to do INR235 crores to INR240 crores.
- The company says revenue was INR4,200 crores last year and expects to touch INR5,000 crores or a little more in the last 2 quarters as revenue ramps up.
Show source
Therefore, the Company continues to be bullish on its growth path, INR4,200 crores last year, and we should touch upon INR5,000 crores around that or a little bit more in the last 2 quarters on how the revenues will be ramped up.
- The power-sector orders create opportunities for Power Mech in ETC business, civil works, structural work, balance-of-plant works including coal-handling facilities and commissioning, as well as O&M.
Show source
Page 4 of 14 Power Mech Projects Limited November 13, 2024 For that indirectly translates a huge opportunity base for us in terms of the ETC business, in terms of civil works, structural work, ETC works some of the balance of plants works in terms of coal handling facilities or balance of plants civil works and then the more and more sets operated and all this commissioning, then O&M opportunities also can materialize.
- Rourkela is planned for expansion investment.
Show source
And then Rourkela is also plan for expansion investment.
- The company may see more margin improvement in O&M in the half year because turnover will be higher in H2 and new O&M projects were added during Q2.
Show source
So we may get more margin improvement in the half year also.
- The company says the rate per ton realization on new installation jobs in boiler and turbine packages is better than in previous years and may bring better margins.
Show source
S. Kodandaramaiah: One more thing, the new installation job, which is coming up in the boiler and turbine packages, the realization of the rate per ton is better than the previous years.
- This mine is expected to generate revenue of INR300 crores to INR310 crores next year, depending on price variation. Replaced by a later filing.
Show source
And we'll do a revenue of INR300 crores to INR310 crores, depending on price variation.
- More O&M projects are expected this year in railways, the power sector and other infrastructure. Replaced by a later filing.
Show source
And some more O&M projects are also expected in this year in the other segments also, the railways and I told you about the power sector and then other infrastructure side.
- Bokaro is expected to come up with investments. Replaced by a later filing.
Show source
Then Bokaro also is expected to come up with investments.
- Power Mech is confident of achieving its revenue growth number during the current FY. Replaced by a later filing.
Show source
So we are confident of achieving this number during the current FY.
Orders
- The company is targeting an order intake of around INR12,000 crores this year and had secured orders worth INR3,100 crores as of 30th September 2024, taking its total order backlog to INR58,000 crores or a little over INR58,000 crores.
Show source
So this year, we are targeting an order intake of around INR12,000 crores across various sectors, namely power, non-power, civil infrastructure and water sectors and as of 30th September 2024, we have secured orders worth INR3,100 crores.
- Excluding both MDOs, Power Mech Projects Limited's unexecuted order book stood at INR18,402 crores.
Show source
And excluding both MDOs, our unexecuted order book stands at INR18,402 crores.
- Overall order backlog increased from INR17,362 crores at the beginning of the year to INR18,402 crores, an increase of nearly 6%.
Show source
The overall order backlog at the beginning of the year was INR17,362 crores, it has gone up to INR18,402 crores, upwards of nearly 6%.
- O&M order backlog increased from INR2,197 crores at the beginning of the year to INR3,326 crores, an increase of almost 51%.
Show source
With the order backlog which was on O&M, which was INR2,197 crores at the beginning of the year has gone up to INR3,326 crores, almost 51% upside.
- The company completed overall order booking of about INR3,055 crores in the first 2 quarters.
Show source
And with overall order booking done about INR3,055 crores in the first 2 quarters .
- Domestic order backlog was around 98.7%.
Show source
The domestic order backlog is around 98.7%.
- International operations accounted for 1.3% of its order backlog, mainly related to O&M jobs being pursued in the Middle East and West Africa.
Show source
The international operations of 1.3%, mainly related to lot of O&M jobs, which we are pursuing in the Middle East and also West Africa.
- Order backlog was about 68% power sector and about 32% nonpower sector.
Show source
And the power sector order backlog is about 68% and the nonpower sector is about 32%.
- In the last couple of months, Adani has ordered about 10,920 megawatts, mainly in BHEL for the main plant, and NTPC has ordered about 11,580 megawatts.
Show source
And we have seen in the last 10 months to 1 year perhaps beginning with Lara, where BHEL has taken the NTPC order and then followed with Talcher, Singrauli, then Talabira by NLC, Neyveli Lignite Corporation, then Yamunanagar by HPGCL, then a lot of orders from Adani side, totally Adani has ordered about 10,920 megawatts in the last couple of months, mainly in BHEL for the main plant,and then NTPC has ordered about 11,580 megawatts.
- The power sector ordering status has gone up to almost INR128,000 crores for BHEL.
Show source
Therefore, that shows the power sector the ordering status has gone up to almost of INR128,000 crores for the BHEL itself.
- NTPC called for bulk orders for Nabinagar, Gadarwara and Telengana, totaling 8 units, and L&T was L1.
Show source
And recently, the development is the bulk orders NTPC called for Nabinagar, Gadarwara and Telengana, so totally 8 units, that L&T was L1.
- BHEL has been confirmed to receive the Telengana project, worth around INR1,6000 crores, after matching L&T's L1 price under the tender conditions.
Show source
But as a part of the tender conditions, there was an opportunity available for BHEL to bid in one of the projects to match the L1 price that has already been confirmed now that is Telengana project, around INR1,6000 crores going to BHEL.
- Orders by Adani, HPGCL, DVC, NLC and NTPC for about 35 sets comprising 27,300 megawatts total almost INR155,000 crores, including about INR27,523 crores for L&T and INR1,28,982 cr for BHEL.
Show source
Therefore, overall ordering, which has been done by all these customers, Adani, HPGCL, DVC, NLC, NTPC for about 35 sets, comprising 27,300 megawatts comes to almost INR155,000 crores with about INR27,523 crores is for L&T, and INR1,28,982 cr to BHEL.
- Power Mech has about INR24,000 crores worth of opportunities in the power plant side, drinking water schemes and other non-power segments at the bidding stage or up for submission.
Show source
Now on the plate, we have got about INR24,000 crores worth o f various opportunities being in bidding stage and also up for submi ssion in the power plant side, in the drinking water schemes and then in various other non -power segment areas, that is why going with confiden ce what is the future for more opportunities.
- Power Mech improved its O&M order backlog by 50% from the beginning of the year to midway, which management said bodes well for topline and bottom line.
Show source
In fact, we improved order backlog of O&M by 50% at the beginning of the year to midway and this bodes well for improving the topline and more importantly for the bottom line.
- Power Mech took an O&M offer for the 3x660-megawatt Talwan di projects worth about INR951 crores under a 5 year contract; its O&M order booking this year was about INR1,860 crores.
Show source
And some of the key things that have happened is the major projects at Talwan di we have taken 3x660- megawatt, that is about INR951 crores is one of the largest O&M offers we have ever taken in the market, therefore, a 5 year contract therefore, that is why this year the overall O&M order booking about nearly INR1,860 crores,, and that speaks well for future in the growth for the profitability also.
- Power Mech has an opening order book of around INR17,362 crores without MDO business and plans order inflow of around INR12,000 crores for the current year.
Show source
N. Aravind: Sir, we have an opening order book of around INR17,362 crores without MDO business, and we have target for the current year, we are planning to order inflow of around INR12,000 crores .
- The company received an order of INR76 cr from JSPL Angul.
Show source
S. Kodandaramaiah: Yes we have received an order of INR76 cr from JSPL Angul.
- Opportunities of nearly INR4,000 crores to INR5,000 crores may arise from IISCO Burnpur construction and construction partner contracts, which are expected to follow in another 4 to 5 months.
Show source
And there can be opportunities about nearly INR4,000 crores to INR5,000 crores.
- BHEL has a total order booking of nearly INR128,000 crores in the power sector.
Show source
And then BHEL with a total order booking on the power sector itself about nearly INR128,000 crores.
- The company has executed roughly INR200 crores worth of work so far on the Udupi project.
Show source
We have done roughly around INR200 crores worth of work we have executed so far .
- The balance of Power Mech Projects Limited's FGD order book, excluding the running Udupi project, is INR4,200 crores from the Kawai, Tiroda and Mundra projects.
Show source
N. Aravind: If you keep aside the Udupi project, which is running, the balance INR4,200 crores from Kawai, Tiroda and Mundra projects.
- Order book includes INR4,200 crores of other slow-moving projects out of INR18,000 crores.
Show source
Rohit Sajja: Out of INR18,000 crores, INR4,200 crores is all these other slow-moving projects.
- The order flow on BHEL and L&T together has been about INR155,000 crores in the last 1 year.
Show source
S. Kodandaramaiah: What I have touched upon in the beginning is to be brief on that, the order flow which has come on BHEL and L&T together is about nearly INR155,000 crores in the last 1 year.
- BHEL is getting another order of INR16,000 crores from Telangana after having the opportunity to match the L1 price, even though L&T was L1 in all 3 plants.
Show source
Even though in all the 3 plants, L&T was L1 , under tender conditions BHEL is getting another order of INR16,000 crores from Telangana that is boosting up for this one.
- EPC and other tenders have been called for OPGCL in Odisha, Ukai in Gujarat, MPGCL Amarkantak, MPGCL Sarni and Singareni in Telengana.
Show source
And then there are other tenders also which have been called for this EPC and other tenders like OPGCL, Odisha then Ukai in Gujarat, then MPGCL Amarkantak, MPGCL Sarni, Singareni in Telengana that I have told you.
What it is building and selling
Projects and capacity
- The company had secured all permissions for the first Kotre Basantpur Mine and expected to break ground probably in the next 3 to 4 days.
Show source
The first Kotre Basantpur Mine we have secured all the permissions, and we are about to break ground probably in the next 3 to 4 days.
- Power Mech's 5 million metric tons per annum Kotre Basan tpur mine with Central Coal Feeds Limited was delayed by 4 months because of central elections and state elections; the company has mobilized resources and expects to start work any moment, pending the last clearance.
Show source
The first mine with Central Coal Feeds Limited, which is a 5 million metric tons per annum one, which we named as Kotre Basan tpur, there is a slight delay.
- The plan for next year is to increase this mine’s capacity to 1.5 MTPA metric tons as per the contractual agreement.
Show source
So next year's plan is to increase the capacity to 1.5 MTPA metric tons as per the contractual agreement.
- The company received environmental clearance approval for the washery in October 24.
Show source
Apart from that, we received the washery environmental clearance approval during the month of October 24.
- The company secured the Tasra mines this year.
Show source
And this year, we have secured the Tasra mines.
- The company secured forest clearance to start tree-cutting activity at the first Kotre Basantpur Mine.
Show source
We have secured the forest clearance also to start with the tree cutting activity.
Show 14 more statements
Demand and pricing
- Close to 80 gigawatts of capacity addition is planned in the power sector by 2032.
Show source
And apart from this, we are also seeing over the last 1, 1.5 years, we have been seeing a considerable amount of growth in the power sector and with close to 80 gigawatts of capacity addition planned by 2032.
- Of the close to 80 gigawatts of power-sector capacity addition planned by 2032, around 37 gigawatts had been tendered and around 43 gigawatts was yet to be tendered.
Show source
Of this, around 37 gigawatts has been tendered and around 43 gigawatts is yet to be tendered.
- The power-sector capacity addition represents a potential opportunity of INR86,000 crores for Power Mech Projects Limited in the civil and mechanical workspace, limited to construction and including boiler turbine generator areas and BOP Civil and mechanical areas.
Show source
This translates to a potential opportunity of INR86,000 crores for Power Mech in the civil and mechanical workspace and that too only the construction.
- A huge demand gap between coal-power and non-coal renewable power is expected to widen by 1930 -32, leading to grid disturbance and power outages.
Show source
And obviously, this is linked with the huge demand gap, wh ich can happen between the coal -power and also non -coal power that is the renewable power, which is expected to bring the widening of ga p by 1930 -32 leading to grid dis turbance and also power outages .
Segments
- Power Mech has a background of work on about 7,000 megawatts of thermal-sector power plants across the Middle East.
Show source
Particularly, we have got a huge HR base also in handling dozens of projects in installation, then maintenance, operation maintenance, et c. And we have got a background of work of about 7,000 megawatts of thermal sector power plants across the spectrum in the Middle East.
- The ETC business, the installation business of the main plant equipment, and civil and structural work, as well as coal handling and other balance of plant work, represent about INR30,000 crores of opportunity.
Show source
Apart from that, that itself comes on about INR30,000 crores of opportu nity.
- The company has 10 SBUs in various segments, with specialization being strengthened through engineering, procurement and experienced staff.
Show source
We have got 10 SBUs, for example, which are s in the various segments and all who are specialized in various areas, and that specialization is being strengthened in terms of engineering, procurement also with some of the staff that we have taken with a lot of experience.
- Normal installation jobs require substantial resource planning and equipment deployment. Replaced by a later filing.
Show source
But in the overall perspective, particularly in the normal installation job, there is a challenge, even though it is a routine job, but a lot of bull work is required in terms of proper resource planning equipment deployment .
Deals and partners
- L&T is to proceed with about 4,000 megawatts for Nabinagar and Gadarwara for INR27,523 crores.
Show source
And L&T to proceed with about 4,000 megawatts for Nabinagar and Gadarwara for INR27,523 crores.
- Adani has placed an order on the main plant, the BTG, for about 10,900 megawatts; the balance of plant work remains to be ordered for completion of the plants.
Show source
Apart from that, what BHEL and Adani have to do is that the Adani has only placed order on the main plant that is the BT G for about 10,900 megawatts.
- NTPC called tenders for 6,400 megawatts, including balance of plant work in the pipeline for BHEL and L&T.
Show source
But NTPC also called tenders for 6,400 megawatts, which there now almost everything in this is in the pipeline for both BHEL and L&T, this also balance of plant, they have to tender it out.
- The company is actively exploring opportunities in green hydrogen, especially SECI tenders for green hydrogen derivatives, and has tied up with a few electrolyzer manufacturers while in advanced stages of forming partnerships with them.
Show source
So this again, we have tied up with a few electrolyzer manufacturers and then we are in advanced stages of forming partnerships with them.
- The Oman investment is committed under Vulcan Steel and is to be fully invested in by JSPL. Replaced by a later filing.
Show source
Page 8 of 14 Power Mech Projects Limited November 13, 2024 JSPL, what I told about Oman is a firm investment committed under Vulcan Steel fully invested to be done by the JSPL.
- Adani has enough capabilities to do package-wise tendering for mechanical, electrical, civil and structural packages. Replaced by a later filing.
Show source
Whereas, in the case of Adani, they have got enough capabilities to do package-wise tendering in terms of various areas like mechanical, electrical and then civil packages and structural packages.
Risks, rules and outside factors
Risks and disputes
- FGD orders are slow moving because of ambiguity around the awaited Supreme Court judgment and recommendations made by some government agencies.
Show source
It is to some extent, yes, it is slow moving because of the ambiguity attached with the Supreme Court judgment waiting and also some of the recommendations made by some of the government agencies.
- The company identifies defining the overall scope of a project as a major issue from the customer side. Replaced by a later filing.
Show source
Page 11 of 14 Power Mech Projects Limited November 13, 2024 But from the customer side, the major issues are the fixing the overall scope definition of the project, that is a very big task.
Rules and policy
- NTPC has taken a firm decision to implement 58,000 megawatts of FGD implementation.
Show source
But what we can say is that like NTPC has taken a firm decision to implement 58,000 megawatts of FGD implementation.
- The government has taken advance action to ramp up coal-based plant capacity for backup baseload operation and day-night operation. Replaced by a later filing.
Show source
As a precaution, government has taken a lot of advance actions in terms of ramping up the capacity of the coal - based plants to work as a backup on baseload operation and also for day night operation.
Everything else said on the call
What management stressed
- The company is making good strides in the O&M space but says it still needs to enhance skills for thermal power plants expected to come up over the next 5 years to 10 years.
Show source
And naturally, I think O&M, we are making good strides in the O&M space, operation maintenance of power plants, but we feel there's still a lot to do in terms of skill enhancement and the kind of power plant, thermal power plants, especially that are going to come up over the next 5 years to 10 years.
- The company needs to be ready with more people for the O&M space because many people have not joined the sector in the last 10 years and there is a dearth of talent.
Show source
More than quality of skills, we need to be ready with a number of people because the last 10 years have seen a lot of people not join this sector.
- Power Mech is not looking at other mines, other MDOs, other coal blocks or mining in any other form at the moment.
Show source
And we are not looking at other mines at the moment, other MDOs or other coal blocks or mining in any other form.
- The company says that executing railway jobs requires care in engineering and supply chain, working capital management, and proper coordination of engineering, procurement and execution; customers also need to order on time, provide site access, and provide engineering and tender specifications on time.
Show source
Therefore, the challenge comes when we do with engineering, supply chain side, that is where a lot of care is required, a lot of working capital management are required, a lot of pushing around the engineering and supply, procurement and execution has to be properly interfaced.
- The company is working to increase its civil capability and engineering capability, including by enhancing teams at leadership and ground levels. Replaced by a later filing.
Show source
W e are working towards increasing capability in the civil space especially, because it's a relatively compared to what our core activities in the power sector, especially mechanical works that the company was founded on.
- The company says it is at the forefront of the O&M sector and is strengthening the organization setup on quality and people's skills. Replaced by a later filing.
Show source
And perhaps on the O&M sector, perhaps we are in the front side.
Show 4 more statements
Group structure
- The company operates its 2 MDOs under separate SPVs with separate manpower and teams; Power Mech's role is to supervise as promoter and monitor the SPVs' operations, so the MDOs have no impact on mining operations.
Show source
N. Aravind: No, these 2 MDOs we are operating under separate SPV, sir.
Other
- Power Mech's organization strength, including direct and indirect labor, has gone up by about 10% to meet new businesses in power, O&M and other areas.
Show source
In fact, the present organization strength both direct and indirect labor has gone up by about 10% to meet the new businesses, which has come not only in the power sector, but also in the O&M and other areas.
- Power plants are being put up in 3 to 4 years now, and railway jobs and road projects are also coming much faster.
Show source
Power plants are being put up in 3 to 4 years now.
- The company says around 15,000 to 16,000 people are deployed on various sites for labor.
Show source
In fact, today, the capacities what we built up in supervision, engineering people, site execution and then supply chain in terms of the labor, piece rate workers, we can say around 15,000 to 16,000 people are deployed on the various sites for the labor itself.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Omkar Chitnis: Okay. Okay. Sir, my last question is, earlier you guided a revenue growth of 25% to 30% for FY '25. What specific strategies have been implemented to achieve this target, particularly based on the current market conditions and competition, sir?
Answer, n aravind
N. Aravind: Sir, we have an opening order book of around INR17,362 crores without MDO business, and we have target for the current year, we are planning to order inflow of around INR12,000 crores . So we have a history of converting the opening order book of 35% to 40% conversion into the turnover. So with that basis, we projected the revenue of 30% growth in the current year. So in '23 also, we have achieved this 30% target from '22 to '23. So that is easily doable target. So we are confident of achieving this number during the current FY.
Answer, rohit sajja
Rohit Sajja: Yah, yes. The first mine with Central Coal Feeds Limited, which is a 5 million metric tons per annum one, which we named as Kotre Basan tpur, there is a slight delay. There was a delay of 4 months, because of central elections and now state elections. But right now, we are in a position. This week, we have mobilized our resources, and we are expecting to start our work any moment. We're just waiting for the last clearance to be obtained, which shall be obtained anytime soon. And this mine, initially, we expected to do around INR50 crores of revenue this year, sir.
Answer, rohit sajja
So even if we start supplying which is a 5 million metric tons per annum one, which we named as Kotre Basan tpur, there is a slight delay. There was a delay of 4 months, because of central elections and now state elections. But right now, we are in a position. This week, we have mobilized our resources, and we are expecting to start our work any moment. We're just waiting for the last clearance to be obtained, which shall be obtained anytime soon. And this mine, initially, we expected to do around INR50 crores of revenue this year, sir. So even if we start supplying the first batch of coal in the month of January, if we start extracting overburden in the month of December, which we expect to do by December first or second week after the tree cutting activity is done.
Answer, rohit sajja
Page 6 of 14 Power Mech Projects Limited November 13, 2024 So we are on track to doing INR50 crores in this mine. So next year's plan is to increase the capacity to 1.5 MTPA metric tons as per the contractual agreement. And we'll do a revenue of INR300 crores to INR310 crores, depending on price variation. And this mine is expected to reach PRC (Peak Rated Capacity) by 2028. So we'll peak in revenues in 2028. And the second mine, which is named as Kalyaneswari Tasra Mine, which is a SAIL mine, we have already started extracting coal, and we have extracted 380,000 metric tons till date from February 2024 to October 2024. And this trend is only going to increase going forward.
Answer, rohit sajja
In terms of washing capacity, we are running a little short because SAIL doesn't have complete offtake of this resource t hat we are able to extract. But the situation is going to improve from January, February onwards, and we were able to achieve only INR26 crores until Q2. But the next 2 quarters, there's going to be a significant increase in revenue numbers in this mine. It may touch INR150 crores to INR160 crores. And this mine again, is expected to achieve PRC, peak rated capacity) by middle of 2027, 2028. That's when our washery will also be constructed and we'll start obtaining the full mining fee.
Question
Pritesh Chheda: Okay. Can you tell us the PAT number for the Coal India mine next year at INR300 crores revenue?
Answer, rohit sajja
Rohit Sajja: Sir, initially next year, because the PAT is going to be a little less until we achieve PRC, it's more so investments that we have to pull in from our side. So it will have in the range of 6% to 7%. But once we achieve PRC, the PAT is going to improve significantly, substantially all the way up to 12% to 13%.
Question
Sandeep Dixit: It's a PAT margin, not an EBITDA margin.
Answer, rohit sajja
Rohit Sajja: EBITDA blended will be PRC. When we achieve PRC, it will be blended EBITDA of both the mines together will be around 20% to 22%.
Question
Sandeep Dixit: I think you had mentioned that in earlier calls.
Answer, n aravind
N. Aravind: Which project you're referring, sir, which order? Anant: A particular order, INR594 crores from Uttarakhand Pey Jal Nigam Limited. You disclosed it on 22nd July '24. So this seems to be a revised order. And as per my calculation, this is...
Answer, s kodandaramaiah
S. Kodandaramaiah: Yes we have received an order of INR76 cr from JSPL Angul. I think this IISCO Burnpur is taking shape. Actually, they are first focusing on the supply orders. Because supply, we had some discussions with the Russian company also. Of course, there are qualification issues are there. But the construction and the construction partner contracts will following another 4 to 5 months. And there can be opportunities about nearly INR4,000 crores to INR5,000 crores.
Answer, s kodandaramaiah
Of course, we have to see which the packages of importance to us there are. But these investments are on the firm footing. And their growth also will come up. expanding on material handling and other sites also and then we have to, of course, overall outlook is that SAIL wants to double up the capacity from 25 million tons to 50 million tons, something like that. . Page 8 of 14 Power Mech Projects Limited November 13, 2024 JSPL, what I told about Oman is a firm investment committed under Vulcan Steel fully invested to be done by the JSPL. And we can take a call based on the opportunity and also what is the type of work that will be available, which can be doable there. Of course, what I referenced having done the work in steel plant in Dolvi, Bellary and JSPL Angul and with those references, we can make a try. Pratik Shah Okay.
Answer, s kodandaramaiah
Got it, sir. My second question was for the capex for Power Mech for '25 and '26. Could you give any guidance on that?
Answer, n aravind
N. Aravind: To meet our regular revenue growth targets, we are increasing the capex of normal assets of around INR100 crores capex increase we are expecting during the year. Apart from that, we received the washery environmental clearance approval during the month of October 24. So, there is a requirement of INR690 crores overall capex plan for the washery setup for Tasra project, over a period of next 2 years' time, we will incur this INR690 crores overall capex in Power Mech books.
Question
Manthan Zaveri: So my question was regarding the order inflow. So you are guiding as of now between INR11,000 crores to INR12,000 crores of order inflow. And as of now, till date, we have received order inflows of INR3,000 crores. So what gives us confidence of achieving that in H2 or remaining 7 months of this calendar year any large orders?
Answer, s kodandaramaiah
S. Kodandaramaiah: Yes. INR24,000 crores of opportunities are on the track. It is a combination of power plant side and then the nonpower sector, in the infrastructure side, then metro side, drinking water schemes, et c.. Around INR3,500 cr are on the firm side should happen in the next 2 to 3 months. And then the other things also should come up. And actually, in the p ower sector also about the new orders should come up because all the ordering which has been done by Adani, they are making a lot of inquiries. They are interested in our partnership and all and we are working in Mahan and with the new projects coming up in Raipur, Raigarh, Mirjapur and also Kawai, all these projects will definitely come because they will take a fast er decision. And then BHEL with a total order booking on the power sector itself about nearly INR128,000 crores.
Answer, s kodandaramaiah
They also have to do a lot of fast tracking in the ordering also. Therefore, there also it's expected. Therefore, what happened in the first 2 quarters, the re was some slackness mainly because of the elections, the main elections and then the state elections and all. But the third and fourth quarter lik3 last year also similar thing happened. The order book improved in the third and fourth quarter. And looking at the opportunity size only, we are still confident of those numbers.
Question
Manthan Zaveri: Okay. And the other thing was regarding the Adani FGD orders. So are the FGD orders still slow moving? Or is there any traction reinstate?
Answer, s kodandaramaiah
S. Kodandaramaiah: No. As on today, it is going on. We all know, matter is sub judice. There are certain views expressed by different segments of the government also. Ultimately, the call has to be taken by the Supreme Court. But what we can say is that like NTPC has taken a firm decision to implement 58,000 megawatts of FGD implementation. Therefore, there is a background of that we are doing in Udupi project of INR963 crores. And that some INR300 crores of conversion should happen in this year.
Answer, s kodandaramaiah
Therefore, till anything has to come very firmly from the judicial side, we will take it that these things will stand. Page 9 of 14 Power Mech Projects Limited November 13, 2024 And I think there is a lot of sensitivity attached to this aspect of the environmental issues. Therefore, Supreme Court also will take a very measured decision on that. I think until then, we don't want to make any news, that we'll be proceeding with whatever is available. It is to some extent, yes, it is slow moving because of the ambiguity attached with the Supreme Court judgment waiting and also some of the recommendations made by some of the government agencies.
Question
Manthan Zaveri: Okay. And so of the Adani FGD order of INR6,000 crores, which was approximately INR6,000 crores, how much execution has been done?
Answer, n aravind
N. Aravind: Right now, we are operating only Udupi project, sir. We have done roughly around INR200 crores worth of work we have executed so far .
Question
Manthan Zaveri: Okay. So this order book of currently INR17,000 crores, how much will be the FGD of this component?
Answer, n aravind
N. Aravind: If you keep aside the Udupi project, which is running, the balance INR4,200 crores from Kawai, Tiroda and Mundra projects.
Answer, rohit sajja
Rohit Sajja: Out of INR18,000 crores, INR4,200 crores is all these other slow-moving projects.
Question
Manthan Zaveri: Okay. And INR14,000 crores, like if we end FY '25 at approximately INR15,000 crores or INR16,000 crores of slow moving, and we expect 30% or 40% conversion of these orders in FY '25. Is that correct?
Answer, n aravind
N. Aravind: Yes, addition of the new-year target of 11,000 addition will be there for the current year. Out of INR3,000 we received. So another INR9,000 crores we are projecting current year receipt.
Answer, s kodandaramaiah
S. Kodandaramaiah: What I have touched upon in the beginning is to be brief on that, the order flow which has come on BHEL and L&T together is about nearly INR155,000 crores in the last 1 year. And L&T to proceed with about 4,000 megawatts for Nabinagar and Gadarwara for INR27,523 crores. And BHEL also today, the news headline has come also about the Telangana job of INR16,000 crores also because they had an opportunity to match the L1 price. Even though in all the 3 plants, L&T was L1 , under tender conditions BHEL is getting another order of INR16,000 crores from Telangana that is boosting up for this one. For this there are segments of the opportunities on the ETC business that is the installation business of the main plant equip ment and then the civil and structural work. And then some of the balance of plant works in terms of where you can take coal handling and other areas and balance of plant civil work. Apart from that, that itself comes on about INR30,000 crores of opportu nity.
Answer, s kodandaramaiah
Apart from that, what BHEL and Adani have to do is that the Adani has only placed order on the main plant that is the BT G for about 10,900 megawatts. Now all these plants for facility, the completion of the main plant, they have to order the balance of plant work. There a lot of other miscellaneous work like coal handling, material handling, then ash handling, then water sys tems and all. Those will also come for tendering. And we have to see where we can fit in. But NTPC also called tenders for 6,400 megawatts, which there now almost everything in this is in the pipeline for both BHEL and L&T, this also balance of plant, they have to tender it out. That they cannot delay it.
Answer, s kodandaramaiah
That also will come as an opportunity. And more than that, I told you another, 11,440 megawatts tendering is in the pipeline that has to happen. Therefore, over the next 2 to 3 years, 2 years, at least, there will be a lot of flow expected on the power sector business. Page have to see where we can fit in. But NTPC also called tenders for 6,400 megawatts, which there now almost everything in this is in the pipeline for both BHEL and L&T, this also balance of plant, they have to tender it out. That they cannot delay it. That also will come as an opportunity.
Question
But what is about time line like when BTG is tendered out? So when is the balance of plant usually gets tendered out to you? Any time line you can...
Answer, s kodandaramaiah
S. Kodandaramaiah: Balance of plant, they should be doing it because they cannot delay it in a couple of months, it should happen because already they would have done the documentation, maybe they have to call the tenders and what the packaging they want to do it a single package or a multiple packages that has to be seen by NTPC. Whereas, in the case of Adani, they have got enough capabilities to do package-wise tendering in terms of various areas like mechanical, electrical and then civil packages and structural packages. But also they will be starting it all those areas.
Answer, rohit sajja
Rohit Sajja: Yes. Thank you. Thanks for the question. W e are working towards increasing capability in the civil space especially, because it's a relatively compared to what our core activities in the power sector, especially mechanical works that the company was founded on. So civil works is what we think we have to and we are working on it. We have been enhancing our teams, especially at the leadership level and also at the ground level, execution teams. And we are also gearing up to add more engineer ing capability within the organization.
Answer, rohit sajja
So to take up more engineering procurement and construction contracts, not an entire power plant, like Ramaiah said and I had touched upon earlier, parts of a power plant where we think we can build on our 25 years of experience. Like BOP is something that we thought we could do. So we are trying to build some engineering expertise for the next 5 to 10 years to be able to cater to decent amount of BOPPC jobs. And naturally, I think O&M, we are making good strides in the O&M space, operation maintenance of power plants, but we feel there's still a lot to do in terms of skill enhancement and the kind of power plant, thermal power plants, especially that are going to come up over the next 5 years to 10 years. So we need to be ready with numbers. More than quality of skills, we need to be ready with a number of people because the last 10 years have seen a lot of people not join this sector. There is a dearth of talent.
Show 7 more questions
Question
Sunil Kothari: And something you can talk about ju st covering your vast experience of the past and the industry, which made a lot of mistakes and get so much in a trouble. So what has changed? What precaution we are taking that w e do not make mistakes? Or we even if there is something wrong, w e can come o ut maybe a little with a little injury. Because ultimately, infrastructure and related all these things, over time, it creates a very challenging environment in terms of competition, in terms of payment, in terms of project stalling and all things. So how prepared and ready we are with our past experience that we will not make mistakes and we will take care for future?
Answer, s kodandaramaiah
S. Kodandaramaiah: I think as Rohit has said, we are a 25 -year-old company, a lot of learning has gone into the system. And perhaps on the O&M sector, perhaps we are in the front side. We are the leaders in doing the things. And we are not keeping quiet with that. We are trying to strengthen the organization setup on the quality and the skills of the people. That is where the valuation comes there. So how prepared and ready we are with our past experience that we will not make mistakes and we will take care for future?
Answer, s kodandaramaiah
S. Kodandaramaiah: I think as Rohit has said, we are a 25 -year-old company, a lot of learning has gone into the system. And perhaps on the O&M sector, perhaps we are in the front side. We are the leaders in doing the things. And we are not keeping quiet with that. We are trying to strengthen the organization setup on the quality and the skills of the people. That is where the valuation comes there. But in the overall perspective, particularly in the normal installation job, there is a challenge, even though it is a routine job, but a lot of bull work is required in terms of proper resource planning equipment deployment .
Answer, s kodandaramaiah
Our planning and pr oject management systems have to be always be on track. Of course, we have got a very robust system on that. Perhaps it is front led by Mr. Kishore Babu himself many times. He goes to the sites and sees the problem solving approach and Rohi t also is doing the same thing a nd we have got a lot of leaders in different segments. We have got 10 SBUs, for example, which are s in the various segments and all who are specialized in various areas, and that specialization is being strengthened in terms of engineering, procurement also with some of the staff that we have taken with a lot of experience. Page 11 of 14 Power Mech Projects Limited November 13, 2024 But from the customer side, the major issues are the fixing the overall scope definition of the project, that is a very big task. Particularly the standard packages of power plant, there is nothing big a challenge.
Answer, s kodandaramaiah
Ultimately, customer has to do and everybody has to do their duty into that. But we are doing things better. I don't think those days are gone where projects will take with much of delay. Power plants are being put up in 3 to 4 years now. And then even railway jobs and then road projects are also coming very faster. We are also experiencing that. We have done many of the road projects and the railway jobs.
Answer, s kodandaramaiah
They are doing 24 railway jobs. A lot of learning is there, and it is doable. Therefore, the challenge comes when we do with engineering, supply chain side, that is where a lot of care is required, a lot of working capital management are required, a lot of pushing around the engineering and supply, procurement and execution has to be properly interfaced. And the same thing goes up also in the customer side also. They have to do ordering in time. They have to get the access to site, then they have to find their engineering specifications, tender specifications in time. All these things are standard practices, which has to be followed.
Question
Tanay Rasal: Yes, sir.
Answer, s kodandaramaiah
S. Kodandaramaiah: No, I will tell you 2, 3 areas. Perhaps in the power sector, we are the peers now. I can boldly say that because of the strength we have established. In fact, today, the capacities what we built up in supervision, engineering people, site execution and then supply chain in terms of the labor, piece rate workers, we can say around 15,000 to 16,000 people are deployed on the various sites for the labor itself. That shows the strength of the organization. Perhaps very few organizations have got that capabilities. Therefore, that drives us into the front compared to the others, particularly with the private customers like Adani.
Question
Manthan Zaveri: Sir, on this MDO order, you said that INR2,100 crores will be the peak revenues in FY '28. So from FY '28 onwards, this INR2,100 crores will be recurring revenue for every year? Or is there some different calculations from FY '28? Page 12 of 14 Power Mech Projects Limited November 13, 2024 Rohit Sajja: Yes, sir.
Answer, rohit sajja
It's going to be an annual recurring revenue for the next 25 years, excluding the price variation.
Question
Manthan Zaveri: Okay. So approximately INR2,000 crores will be recurring revenue for the 25 years from these mines. And this won't be related to offtake.
Answer, rohit sajja
Rohit Sajja: It won't be for 25 years. I'm sorry. It's going to be for 23 years because we are in 2 years for development, yes.
Question
Manthan Zaveri: As our order book is gaining traction in O&M side, and you also mentioned that O&M has relatively higher margins than our other segments. So is there any scope of further improvement in margins? We have been consistent around this 11% to 12% band. So is there any further scope of improvement since our O&M order book is improving?
Answer, n aravind
N. Aravind: Yes, sir. There is a possibility because the moment we increase our O&M segment and MDO segment added to the portfolio, there is an expectation of 1% to 1.5% growth in EBITDA margin over a period of next 3 to 4 years.
Answer, rohit sajja
Rohit Sajja: And overseas is also contributing quite significantly to our O&M revenues. Last year, we did overseas O&M of around INR200 crores. And this year, we anticipate to do INR235 crores to INR240 crores. So we -- you can expect to see the same trend over the next 7 to 8 years, overseas O&M growing at a rate of 30%, 35% CAGR. And the EBITDA margins are in the range of 17% to 19% in the overseas.
Question
Manthan Zaveri: So can we expect improvement in H2 of FY '25 in EBITDA margins?
Answer, n aravind
N. Aravind: Yes, sir, because the turnover will be more in H2. So the O&M also new projects we added during Q2. So there is a chance of getting more margins in O&M side. So we may get more margin improvement in the half year also.
Answer, s kodandaramaiah
S. Kodandaramaiah: One more thing, the new installation job, which is coming up in the boiler and turbine packages, the realization of the rate per ton is better than the previous years. That can also bring some better margins.
Question
Manthan Zaveri: Okay. And sir, since we are operating these 2 large MDO orders. So in terms of capability and operational capabilities, is this somewhere hampering our bidding in other lines of business or it's not affected in terms of manpower and everything?
Answer, n aravind
N. Aravind: No, these 2 MDOs we are operating under separate SPV, sir. So there is a separate manpower, we are handled by the separate team. So Power Mech team is only supervising as a promoter. We are monitoring the operations of the SPVs. So there is no impact on the mining operations on the existing MDOs.
Answer, s kodandaramaiah
S. Kodandaramaiah: Yes. I think we have touched upon many aspects of the business growt h, the opportunity size available, the revenue growth and the EBITDA margins, it should be further st rengthened in the coming months. What we can say is that the investment climate is pretty good in the power sector, in the nonpower sector, railways, infrastructure and then other segments also. Therefore, the Company continues to be bullish on its growth path, INR4,200 crores last year, and we should touch upon INR5,000 crores around that or a little bit more in the last 2 quarters on how the revenues will be ramped up. Page 13 of 14 Power Mech Projects Limited November 13, 2024 And Rohit has given a broad spectrum of the order flow expected. And I think of the opportunities available, we should try to get whatever is possible. And then the opportunities available will be more in the coming years, the government is fully committed for more and more investments in energy sector, infrastructure sector and then so many other sectors and then steel sector also. .
Questions about this call
- When was the Power Mech Projects Q2 FY25 earnings call transcript filed?
- Power Mech Projects filed the transcript with the exchange on 18 Nov 2024. This page is built from that transcript.
- What does this page list?
- 130 statements from the transcript across 13 topics, 101 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 17 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.