Quality Power Electrical Equipments Q1 FY27 earnings call: Quality Power had USD100 million bids going on for data center opportunities, but was still struggling because delivery periods were about 12 months' time

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Quality Power had USD100 million bids going on for data center opportunities, but was still struggling because delivery periods were about 12 months' time. Quality Power had about USD60 million of BESS, meaning PCS orders, in its pipeline in Q1 FY27 and anticipated another USD40 million more in the next 12 months at least, in line with earlier guidance of at least USD80 million of business coming in. Quality Power expected the initial audits of ISO 9000, 14000 and OHSAS to take about a month before customer audits started. Mehru delivered about 18% EBITDA margin in Q1 FY27; copper and oil prices in April directly affected margins, and Mehru's revised margin guidance is around 18%, increased from the earlier guidance of above 15%. Mehru supplies 1 in 2 high voltage instrument transformers required in India.

The numbers management gave

Results

  • Quality Power's revenue increased year on year from INR37 crores to INR69 crores in Q1 FY27.
    Show source
    Year-on-year, I think Quality Power went from INR37 crores to INR69 crores.
  • Mehru's revenue increased year on year from about INR60 odd crores to about INR83 crores in Q1 FY27.
    Show source
    Mehru went on from about INR60 odd crores to about INR83 crores.
  • Endoks contributed about INR107 crores in revenue in Q1 FY27.
    Show source
    And I don't remember exactly Endoks, but Endoks contributed about INR107 crores in this revenue.
  • The company recorded a forex currency loss of INR7.5 crores in other income in Q1 FY27.
    Show source
    Bharanidharan Pandyan: I think we had a loss of INR8 crores -- INR7.5 crores, not gain.
  • Mehru delivered about 18% EBITDA margin in Q1 FY27; copper and oil prices in April directly affected margins, and Mehru's revised margin guidance is around 18%, increased from the earlier guidance of above 15%.
    Show source
    Bharanidharan Pandyan: Mehru this quarter delivered about 18%.
  • Endoks' current STATCOM, SVCs and automations product lines are normally around 25% margin; blended margins including BESS are to be assessed in Q3 after the products have shipped.
    Show source
    The current product lines where they are already present, like STATCOM, SVCs, automations, I think they are normally around 25%.
Show 11 more statements

Results

  • The factory has traditionally delivered about 25% margin over the last six quarters, and management does not expect the margin to be lower than that, while cautioning against using these figures instead of guided numbers.
    Show source
    Bharanidharan Pandyan: So, as I said, we have been traditionally doing about 25% margin in this factory.
  • The 20% EBITDA margin mentioned by Quality Power Electrical Equipments Limited is blended.
    Show source
    Bharanidharan Pandyan: Please model us at 20% or high teens EBITDA.
  • All the Indian entities increased their revenue year on year in Q1 FY27.
    Show source
    All the Indian entities increased their revenue.
  • The Turkish companies had a slight dip in revenue in Q1 FY27, primarily because it was the middle of the year and they had Eid holidays for two weeks in between.
    Show source
    The Turkish companies had a slight dip in revenue, primarily it's the middle of the year, and they had Eid holidays for two weeks in between?
  • Demand for insulators within Quality Power is slowing its growth.
    Show source
    Now, we have been finding that there's a demand for insulators internally which is slowing down our growth.
  • Quality Power's components business in Sukrut turned extremely profitable in Q1 FY27.
    Show source
    Same way is with our components business in Sukrut, which has turned extremely profitable this quarter for us.

Money and capital

  • Total debt was about INR23 crores as of last quarter at group level, including working capital at a subsidiary; the company is raising capital to close the WS acquisition and proposes INR50 crores capex at that location to enhance capacity.
    Show source
    One second, the total debt as of last quarter is I think about INR23 crores, overall at a group level, that is also working capital at some subsidiary thing.
  • Capital raise has not been quantified but will be less than INR500 crores.
    Show source
    Bharanidharan Pandyan: We have not put numbers to it, but less than INR500 crores.
  • Quality Power believes it will start the road shows from 20th of this month.
    Show source
    I believe we will start the road shows from 20th of this month.
  • Quality Power says that faster closure will make it easier to fund the business.
    Show source
    So the faster they do, it will be easier for us to be able to fund the business.
  • Quality Power may attempt raising them this month, before the AGM. Replaced by a later filing.
    Show source
    Bharanidharan Pandyan: I think we may attempt raising them this month, before the AGM.

What it expects ahead

What management expects

  • Quality Power had about USD60 million of BESS, meaning PCS orders, in its pipeline in Q1 FY27 and anticipated another USD40 million more in the next 12 months at least, in line with earlier guidance of at least USD80 million of business coming in.
    Show source
    Bharanidharan Pandyan: My current guess is that we have about USD60 million give and take of BESS, that is PCS orders, in our pipeline.
  • Mehru's margin profile is expected to stabilize in about four quarters from the date of acquisition; its margin is currently anywhere between 15% and 25% while things are not yet under control.
    Show source
    What we see at this moment is anywhere between 15% and 25% margin.
  • The company has guided to 20% revenue growth in FY27 and may consider revising the numbers at Q3; factories are yet to be fully commissioned.
    Show source
    Bharanidharan Pandyan: Darshil, I think we have guided to 20% at this moment.
  • Quality Power asked investors to stick to its 20% guidance.
    Show source
    Please stick to the 20% guidance that we have given.
  • Winwin Speciality is expected to do between INR250 crores and INR300 crores without capex, and about INR450 crores to INR500 crores with capex; the capex will add composites capability as well as porcelain capability.
    Show source
    Without a capex, I think it should be doing between INR250 crores and INR300 crores.
  • Quality Power expects to do at least INR500 crores in aluminium wire over the next two to three years, equivalent to about INR1500 crores to INR1800 crores in copper wires for its CTC business.
    Show source
    So we are building considerable capacity in the ancillary business, something like a CTC, HVDC high voltage wire, I believe over the next two, three years we should be doing at least INR500 crores in aluminium wire, which is equal to about INR1500 crores to INR1800 crores in copper wires for as a CTC business.
Show 23 more statements

What management expects

  • Quality Power will take in more orders once it is able to stabilize its factories.
    Show source
    So, once we are able to stable, we will take in more orders.
  • Quality Power was likely to get BESS to India by the end of next year and would like to start BESS in India once it had stabilized most of its business there.
    Show source
    And we are also likely to, by the end of next year, get BESS to India as again, throughout we guided two years, two years.
  • Most of the BESS orders were expected to have an execution cycle of six to nine months.
    Show source
    I think they would be in six to nine months, most of the orders.
  • Consolidation of the acquisition is expected to happen after Q4, not before, because the property is in an SEZ and requires sign-offs in Delhi.
    Show source
    Bharanidharan Pandyan: I think consolidation will happen out of Q4, not before that, primarily because this being an SEZ property, it will require a lot of secretaries to sign off in Delhi.
  • Quality Power believes the US can be catered to from India, but it would need a facility somewhere in the European peninsula for the European market, which is booming because of renewable energies.
    Show source
    So, I believe US can be catered out of India, but for the European market, which is at a different level of a boom right now because of the renewable energies, we would definitely need a facility somewhere in the European peninsula.
  • Quality Power expects to find an equilibrium between consolidating some activities and retaining freedom at factory level in the next few years.
    Show source
    I think we will find an equilibrium in the next few years.
  • It will take Taikai and Pinggao a couple of years to return to where they were six or seven years back.
    Show source
    I think it will take a couple of years for them to even come back to where they were, six, seven years back.
  • Quality Power plans to stop white labelling very soon and enter these markets itself.
    Show source
    We will stop the white labelling very soon, we will get into all these markets ourselves.
  • Quality Power will change the Vizag plant's branding to Quality Power sooner.
    Show source
    But we will be changing it to Quality Power sooner.
  • Quality Power intends to be an alternative to Hitachi from India, complementing it rather than competing with it.
    Show source
    We would like to be the alternative to Hitachi from India, not competing them but complementing them.
  • Quality Power invests in high technology and new businesses, including BESS, automation, HVDC and FACTS, where it believes free cash is generated and hopes to generate a lot of free cash.
    Show source
    Let's say BESS, automation, HVDC, FACTS, where we are building our strength, we believe this is where the free cash is being generated and we will, we hope to generate a lot of free cash.
  • Quality Power intends to participate in the race to become an electrical-sector global multinational alternative while generating free cash and avoiding mistakes.
    Show source
    But from the electrical background, globally I think there needs to be an alternative, and we intend to be a participant in that race, while generating a lot of free cash and not mak ing mistakes on the way.
  • Quality Power says software companies do not trade cheap and that it normally buys at a much lower value, so it would focus on manufacturing, its core expertise.
    Show source
    So I would focus on manufacturing which is our core expertise at this moment.
  • Quality Power expects the highest growth from the power electronics sector because of BESS, followed by high voltage power products; ancillary is technically internal consumption and is not credited as sales when billed internally under the accounting standard.
    Show source
    Bharanidharan Pandyan: I think the highest growth will come from power electronics sector because of the BESS coming in.
  • Quality Power expects power electronics to help it scale immediately in the next two to four quarters, followed by power products.
    Show source
    Power electronics would help us scale immediately in the next two, three, four quarters, and then power products would catch up.
  • Quality Power is trying to get the approvals on. Replaced by a later filing.
    Show source
    We are trying to get the approvals on.

Orders

  • Quality Power had USD100 million bids going on for data center opportunities, but was still struggling because delivery periods were about 12 months' time.
    Show source
    Apart from it, the data center opportunities are typically the, where we are seeing the USD100 million bids going on.
  • Quality Power said its order book was slated for completion in the next 15 months, give and take.
    Show source
    Bharanidharan Pandyan: This order book what we have, Rahul, this order book is slated to completion in the next 15 months, give and take.
  • Quality Power had a 4 gigawatt facility in Turkey and had almost 1 gigawatt of orders in Q1 FY27.
    Show source
    Some of the businesses like PCS can -- scaling up is much easier in the best business today, but these are as I said, we have a 4 gigawatt facility in Turkey, 1 gigawatt almost we've got an order.
  • Mehru has a lot of orders and its current facilities are expected to reach 100% capacity very soon.
    Show source
    So we do not have much of a capacity coming in from Mehru, the current facilities, I think they will reach 100% very soon.
  • Quality Power has already got a lot of orders in the Indian market, including Power Grid for 765 kV and 400 kV.
    Show source
    Page 19 of 23 Quality Power Electrical Equipments Limited August 10, 2026 At this moment, we have already got a lot of orders in the Indian market, including Power Grid for 765 kV and 400 kV.
  • Each of the factories was sitting at close to two years of order book and at the last capacities in Q1 FY27.
    Show source
    Each of the factories is sitting on more than two years of order book almost at this moment, close to two years of order book and at the last capacities.
  • Customers are writing more framework orders for Mehru rather than small order packages.
    Show source
    So the customers are writing more of framework orders now rather than small order packages.

What it is building and selling

Projects and capacity

  • Quality Power expected the initial audits of ISO 9000, 14000 and OHSAS to take about a month before customer audits started.
    Show source
    It will take us about a month.
  • Quality Power may have about 60 audits on the facility before it can take over the full volume of the existing factory; the global audits would take about six months from the day the facility opens for audits.
    Show source
    We may have about, as I referenced, about 60 audits on the facility before this can take over the full volume of the existing factory.
  • Quality Power's facility was good enough to deliver INR1,500 crores to INR1,800 crores in asset turnover, although it had not fully capitalized the full capital in the facility.
    Show source
    The asset turnover of this factory, I think we have still not fully capitalized the, put the full capital in, but I would say INR1,500 crores to INR1,800 crores I think this facility is good enough to deliver.
  • The first product to be tested will be 220 kV GIS components, with switching to 400, 765 kV planned in the next year's time.
    Show source
    I think the first product that will be testing is a 220 kV GIS components, switching on to 400, 765 kV in the next, say, one year's time.
  • Quality Power has 40 acres of land in the WS campus apart from the insulator factory.
    Show source
    Advantage of WS is that we have 40 acres of land in that campus apart from the insulator factory.
  • Quality Power is considering its facility options and expects to decide in about 6, 7 months.
    Show source
    We have about 6, 7 months' time before we bite the bullet.
Show 40 more statements

Projects and capacity

  • Quality Power has about 60 global audits lined up in its initial scope and has guided about six months.
    Show source
    Because we have at least, in our initial scope of things, we have about 60 audits lined up.
  • Commencement of the Sangli plant is subject to approvals from the bureaucrats; its Vastu Shanti pooja is on 13th and 14th of this month.
    Show source
    Bharanidharan Pandyan: So, commencement is subject to market -- what we say the approvals from the bureaucrats but as I said, our Vastu Shanti pooja is on 13th and 14th of this month.
  • The Endoks manufacturing facility is costing about $2 million, and Quality Power may spend about $1 million more.
    Show source
    As I said at this moment, the entire facility is costing us about $2 million, give and take we may spend about $1 million.
  • The Endoks manufacturing facility has scale for about $70 million to $80 million.
    Show source
    I think that factory is good enough for about at least $70 million, $80 million.
  • The Sangli plant has peak revenue potential of about 1,500 crores.
    Show source
    Bharanidharan Pandyan: As I said, about 1,500 crores, give and take.
  • The company has almost 40 acres of land on its books close to Ankara for its overseas facility.
    Show source
    We have about 40 acres of land free to do what we want in SVZ, beautiful campus.
  • Quality Power expected to be more comfortable with the new facility in about three months' time, into the next quarter, after taking it over and stabilizing it.
    Show source
    Page 6 of 23 Quality Power Electrical Equipments Limited August 10, 2026 Once, I believe in about three months' time, into the next quarter, when we are slightly comfortable once we have taken over the new facility and we have stabilized it.
  • Quality Power's machinery installation was already on, and it still had to get the building completion certificate from the authorities before it could begin trial production in the facility.
    Show source
    As soon as they give us, I think we will be able to start begin trial production in the facility.
  • Quality Power believed it would start opening up the facility maybe at Q3 this year to get in more orders once comfortable, given that some large HVDC orders had delivery timelines.
    Show source
    However, given seeing that, I think some of the large HVDC orders, we have timelines for delivery, so I believe we will start opening up, as Mr. Sarkar had said, maybe at Q3 this year to get in more orders once we are comfortable.
  • Quality Power anticipated another three months of trial run for the new product and anticipated being able to take up full production out of the facility by Q4 of this year.
    Show source
    We are anticipating by Q4 of this year is when we will be able to take up full production out of the facility.
  • Quality Power is looking at a facility in Turkey.
    Show source
    Page 12 of 23 Quality Power Electrical Equipments Limited August 10, 2026 We are overlooking at a facility in Turkey.
  • Quality Power is considering either building a facility in Turkey for European markets and serving the US from India, or developing land in Vizag to handle exports through a separate business.
    Show source
    To be able to either build a facility in Turkey for the European markets and deliver US from India and keep the rest of the world from Europe, that is one option.
  • Quality Power is interviewing candidates for its planned large green facility and is taking time over the decision rather than rushing.
    Show source
    So, we are taking our time, taking the decision rather than rushing into it.
  • Quality Power is trying to start commercial production this month, initially in small volumes, subject to obtaining authority clearances; the new facility requires customer approval before full production because the product is regulated.
    Show source
    I think we have guided this month, we are trying our level best to start commercial production this month.
  • Quality Power is prioritizing facility audits according to which project enters manufacturing first; obtaining Hitachi global approval for the Adani and Power Grid HVDC work requires about five or six audits, followed by Adani and Power Grid audits, making about eight audits before moving to the next project.
    Show source
    So that itself is about eight audits before we shift into the next project.
  • Quality Power acquired a large piece of land for expansion; only eight acres is occupied by the facility.
    Show source
    If you look at the valuation, we got a huge piece of land where we can start going and expanding it.
  • The Endoks factory is still not operational, and Quality Power will provide guidance after it ships products for a quarter or two.
    Show source
    As I said, the factory is still not operational.
  • The Chennai plant is closed down.
    Show source
    Bharanidharan Pandyan: No, the Chennai is closed down.

Demand and pricing

  • The demand for PCS in the world was very high. Replaced by a later filing.
    Show source
    The demand for PCS in the world is very high.

Segments

  • Mehru supplies 1 in 2 high voltage instrument transformers required in India.
    Show source
    They have, I think, at this moment supplying 1 in 2 high voltage instrument transformer that is required in this country.
  • WS insulators is approved in over 55 countries.
    Show source
    WS insulators is approved in over 55 countries.
  • The company makes about 12 or 13 products, and every factory has its own set of component-supply worries that changes every quarter.
    Show source
    Bharanidharan Pandyan: We are not one product, we are making about 12 or 13 products and every factory has its own set of worries.
  • Quality Power says large multinationals guiding for growth are also getting stuck because of insulator supply constraints, and it can leverage or barter their growth by supplying insulators as its product scope increases.
    Show source
    So what happens, as we increase our scope of product, we can leverage or barter their growth with the supply of insulators to them.
  • Quality Power says the insulator business helps increase throughput in its existing businesses and can be used as leverage.
    Show source
    So that A, helps us in increasing our throughput of our existing businesses, and also use it as a leverage.
  • The Vizag plant is rebranded as Winwin, and it can use the WS logo perpetually for insulators.
    Show source
    This is Vizag is rebranded as Winwin, but they have ability to use the word WS logo perpetually for insulators.
  • All approvals, type tests and credentials are inherited into the company.
    Show source
    But all the approvals, type tests, credentials, everything is inherited into the company.
  • Inavitas is mostly into grid automation and renewable energy integration software, which is not technically related to Quality Power's high voltage businesses.
    Show source
    Not related to technically this businesses of high voltage what we are operating.
  • Quality Power makes instrument transformers, is getting into grading capacitors, and is adding WS insulators and bushings for GIS to its scope.
    Show source
    So in the GIS ecosystem, we have just increased our scope again.
  • Quality Power says internal consumption in its other growing businesses is not treated as sales.
    Show source
    The other businesses we are growing in, a lot of internal consumption is not treated as sales.
  • Ancillary helps Quality Power scale its power products and power electronics businesses.
    Show source
    Ancillary helps us scale the other two businesses.

Deals and partners

  • Quality Power is in talks on about half a dozen STATCOM projects across the US, Europe and Australia, and has got a couple of STATCOMs already in the US.
    Show source
    There are about half a dozen STATCOM projects across US, Europe, Australia that we are in talks with.
  • Mehru is supplying inside the Denmark grid in Q1 FY27, and Quality Power expects to supply the Swedish grid very soon.
    Show source
    Bharanidharan Pandyan: But Europe we are already supplying inside the Denmark grid from Mehru this quarter, and we will get more from the Swedish grid very soon.
  • TVA Power Transformers was already full and supplying most of its capacities to Reliance and Adani.
    Show source
    One was TVA Power Transformers, who were already full and supplying to Reliance and Adani most of their capacities.
  • TVA Power Transformers is allowed to quote for Power Grid, but did not participate in the last tender.
    Show source
    They are allowed to quote for Power Grid, but even in the last tender they did not participate.
  • A small composite string insulator factory in Baroda is allowed to bid for HVDC contracts.
    Show source
    That company is allowed.
  • Taikai and Pinggao, with factories in Baroda and Vizag, are allowed to bid for HVDC contracts, but their factories are not operational and have been de-rated in the last seven years.
    Show source
    I think Taikai and Pinggao, one in Baroda and one in Vizag, sorry northeast in Vizag, are allowed.
  • Quality Power is already a supplier to TVA in the transformer business through Sukrut.
    Show source
    At this moment what do we supply, we are already a supplier to TVA in the transformer business through Sukrut.
  • Quality Power will supply GIS components developed with Hyosung when NEPSI or Pinggao comes to India.
    Show source
    When NEPSI or Pinggao comes in India for the GIS, we will supply the components that we have developed with Hyosung.
  • Customers from Iraq and Abu Dhabi have reached out to WS insulators because it is already approved for these high voltages.
    Show source
    Even recently, we got customers from Iraq, Abu Dhabi and all reaching out to us, because they are already approved to all these high voltages.
  • Quality Power has a right to call for software from Inavitas if required, through its directors in the group.
    Show source
    But being directors in the group, we have always a right to call for software if required.

Risks, rules and outside factors

Outside factors

  • IGBTs continued to be bottlenecks across the world for Quality Power's BESS business.
    Show source
    The bottlenecks continue to be the IGBTs across the world.
  • Quality Power estimates there are about four or five insulator manufacturers in India and another eight or nine globally, with no new vendors coming in or existing vendors expanding, and expects the grid-related insulator demand-supply mismatch to become more extreme.
    Show source
    So nobody is expanding, no new vendor is coming in, which means as the way we see the grids operate, the demand-supply mismatch of insulators are going to be even more extreme.
  • Quality Power says every business it enters or acquires will have the problem of insulators.
    Show source
    And whichever business we get into or acquire, will have the problem of insulators.
  • Quality Power has experienced a sharp increase in prices, the dollar is depreciating, and many of its orders are exports.
    Show source
    I cannot really comment the way we have been -- there's been sharp increase in prices, so the dollar is also depreciating -- a lot of appreciating and a lot of our orders are also exports.
  • Quality Power says global shortages of components and dependence on large power transformers and other equipment reaching customer sites constrain high voltage substation growth, which remains much lower globally than BESS growth; customers can take power electronics deliveries faster because those products have much less external influence.
    Show source
    So globally there is a shortage of a lot of components, so the global growth rate for a high voltage substation is still much lower compared to BESS, where there is much less of external influence on the products.
  • Bharanidharan Pandyan said CTC cables were the component-supply concern where he sat, BESS teams were concerned about IGBTs, Mehru teams about aluminium casting, and Sukrut teams about springs.
    Show source
    So at this... if you ask where I sit it is the CTC cables.
Show 1 more statement

Rules and policy

  • The government has not reduced local sourcing norms, so the Chinese companies must still buy 60% to 70% of their content domestically.
    Show source
    Also the government has not reduced any local sourcing norms, which means that they have to still buy 60%, 70% of their content domestically.

Everything else said on the call

What management stressed

  • Quality Power is considering a framework agreement with one casting vendor to combine purchasing across Mehru, WS, Sukrut and Quality Power and obtain scale and cost benefits.
    Show source
    So, if all of them are talking to four different vendors, why not have a framework agreement with one vendor to get the scale and cost?

Group structure

  • Quality Power paid about INR50 crores, INR60 crores for the business and expects to recover the amount in the next two years.
    Show source
    And the amount of money I paid for the business per se is about INR50 crores, INR60 crores.
  • Quality Power will most probably start consolidating Winwin Speciality in Q4 this year.
    Show source
    Bharanidharan Pandyan: We will start most probably consolidation Q4 this year.
  • Quality Power has absorbed the management and directors of WS Insulators into its company, and they will continue running the business with Quality Power.
    Show source
    They want it to be a process of the growth, and we have also absorbed the management and the directors into the, into our company.
  • Under the lockbox agreement, any losses until the day of the acquisition are to the owners' account.
    Show source
    For us, it's a lockbox agreement till the day of the acquisition, any losses is to the owners account.
  • Quality Power intends to use free cash it generates to buy similar complementary high technology businesses in the high voltage transmission space.
    Show source
    When we generate these free cash, we intend to again buy out similar complementary high technology businesses in the high voltage transmission space.
Show 1 more statement

Group structure

  • A couple of Endoks group directors have shareholdings in Inavitas, which is also owned by Alfa Solar, a solar company.
    Show source
    Inavitas is owned by also a company called Alfa Solar, a solar company.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Baidik Sarkar: Gentlemen, hi, good morning and congrats on a strong quarter. A couple of questions, could you break up the quantum of your Y-o-Y growth between Endoks , Mehru, and Quality? And I'm sorry, I didn't quite catch the CFO's comments on the margin pressure expected in Q3 '27, if I could, you know, request you to rehash that again, please. Thank you. Page 5 of 23 Quality Power Electrical Equipments Limited August 10, 2026 Bharanidharan Pandyan: Sir, I may not have the year-on-year of individual company, but I can give you some idea, roughly, the estimates I know.

    Answer, bharanidharan pandyan

    Year-on-year, I think Quality Power went from INR37 crores to INR69 crores. Mehru went on from about INR60 odd crores to about INR83 crores. And I don't remember exactly Endoks, but Endoks contributed about INR107 crores in this revenue. All the Indian entities increased their revenue. The Turkish companies had a slight dip in revenue, primarily it's the middle of the year, and they had Eid holidays for two weeks in between? That was your first question, sir. The second question, can you just repeat it, if you don't mind?

  2. Question

    Baidik Sarkar: Okay, that's absolutely helpful, Mr. Pandyan. And, you know, one, one last question for you from my end. You know, for Quality, what I understand is that our typical execution timeline in order book is between four to six months, right? So, you know, given that we have our plants, due for commissioning towards the later half of this fiscal, by when do you think our order book will reflect our enlarged capacities again? I understand we have been paid for a while given the capacity constraints, but, you know, by when do you think you will be in a position to move that again?

    Answer, bharanidharan pandyan

    There are about half a dozen STATCOM projects across US, Europe, Australia that we are in talks with. We have got a couple of STATCOMs already in the US. Apart from it, the data center opportunities are typically the, where we are seeing the USD100 million bids going on. That we are still struggling because the delivery periods are about 12 months' time. Page 6 of 23 Quality Power Electrical Equipments Limited August 10, 2026 Once, I believe in about three months' time, into the next quarter, when we are slightly comfortable once we have taken over the new facility and we have stabilized it. Believe me, this facility, if you come over, it's quite large. It takes you, it takes you about 600 meters from one corner to another corner walking around.

    Answer, bharanidharan pandyan

    So, once we are able to stable, we will take in more orders. Getting orders is not a worry at this moment for us. So, if like in Endoks, if we could just open up the lid and we got in, we could get in more if we are able to deliver more, the factories build operate. Each of the factories is sitting on more than two years of order book almost at this moment, close to two years of order book and at the last capacities.

  3. Question

    Baidik Sarkar: Yes, thanks for that. I'll fall back in queue. Thank you.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: So, the machinery installation is already on. I believe we are also having a Vastu Shanti pooja I think this week in the factory. We have to still get the building completion certificate from the authorities and I think the process is on. As soon as they give us, I think we will be able to start begin trial production in the facility. Obviously, the initial audits of ISO 9000, 14000, OHSAS has to be completed. It will take us about a month. And after that is when we start the customer audits in.

    Answer, bharanidharan pandyan

    We may have about, as I referenced, about 60 audits on the facility before this can take over the full volume of the existing factory. We have to schedule this one by one, these are global audits, and it will take us, I think, as we guided, about six months from the day we open up the facility for audits. These are highly regulated products and every, every customer has to come and review the facility. However, given seeing that, I think some of the large HVDC orders, we have timelines for delivery, so I believe we will start opening up, as Mr. Sarkar had said, maybe at Q3 this year to get in more orders once we are comfortable. The asset turnover of this factory, I think we have still not fully capitalized the, put the full capital in, but I would say INR1,500 crores to INR1,800 crores I think this facility is good enough to deliver.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: The machines are already on. This is a new product for us. So, we anticipate that it will take us another three months of trial run. We are anticipating by Q4 of this year is when we will be able to take up full production out of the facility. Bear in mind the machineries have come in, it will Page 7 of 23 Quality Power Electrical Equipments Limited August 10, 2026 be also installed. We have got the power, we have got everything in, getting the licenses, all the ISOs and audits will be also on the facility. But being a new product in the facility for us as a company and as a team, I think we have to give it that three to five months to a stabilization.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: This order book what we have, Rahul, this order book is slated to completion in the next 15 months, give and take. So that gives you an idea how much we can eat. That gives you a rough idea.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: I think I wouldn't commit on that, but we would try our best. We the order demand is good enough. Some of the businesses like PCS can -- scaling up is much easier in the best business today, but these are as I said, we have a 4 gigawatt facility in Turkey, 1 gigawatt almost we've got an order. We will, we will see ramping up as we start delivering products out of the facility. First we need to deliver the products out of the factory before we start committing more.

  4. Question

    Nemish Sundar: Yes, hi sir. A very good afternoon and very congratulations on a excellent set of numbers. So, just continuing on the BESS part, could you just explain it in a little more detail as to like your capacity -- current capacity that you have for BESS, broadly in volume or revenue terms as of now and the new facility that you are building at Endoks for BESS, so what could be the scalability for BESS that you are expecting from this facility, in terms of revenue or volume?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: My current guess is that we have about USD60 million give and take of BESS, that is PCS orders, in our pipeline. And we are anticipating another USD40 million more in the next 12 months at least, which is, which is in line with the guidance that we have given earlier that we see about at least USD80 million of business coming in. So at this moment our focus is to operationalize the facility and deliver more. Once we are able to deliver more, getting numbers out of BESS is not a very big problem. The demand for PCS in the world is very high. Most of the governments are still focusing on making basic battery cells and cell technologies. The power electronics, software, and the hardware part is normally missed out and there are very few players in this business.

    Answer, bharanidharan pandyan

    The bottlenecks continue to be the IGBTs across the world. Page 8 of 23 Quality Power Electrical Equipments Limited August 10, 2026 As we are able to secure supplies, we should be able to also deliver faster. And we are also likely to, by the end of next year, get BESS to India as again, throughout we guided two years, two years. I think by end of next year, once we stabilize most of our business in India, we would like to start BESS in India. The PCS for the Indian and the Asian markets.

  5. Question

    Nemish Sundar: Okay. And sir, the execution cycle of BESS would be similar to the core business, like around 12 to 15 months?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: No, these are very fast. I think they would be in six to nine months, most of the orders.

  6. Question

    Nemish Sundar: And margins would be similar to Mehru as it was initially and then you look to scale it up in the upcoming quarters? Would that be something that would be the view?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Yes, I think the margin profile would stabilize in about four quarters from the date of acquisition. You have to give us about four quarters. What we see at this moment is anywhere between 15% and 25% margin. The gap is very large because we still not have things under control. Once we have in control, we will narrow down the margin percentage.

  7. Question

    Nemish Sundar: Okay, sir. And any tentative date that you look for finalizing this acquisition? Like consolidation and everything?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: I think consolidation will happen out of Q4, not before that, primarily because this being an SEZ property, it will require a lot of secretaries to sign off in Delhi. So, it's a bureaucratic process in India, so we will have to bear with it.

  8. Question

    Darshil Jhaveri: Hello. Good evening, sir. Thank you so much for taking my question. Firstly, congratulations and a really great set of results in a challenging environment. So just wanted to know, what is the revenue guidance that we can do in FY27? Because based on the order book, I think we can have significant growth this year also, right? So could you just quantify that? Can we reach around INR1,400 crores by this, this year end?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Darshil, I think we have guided to 20% at this moment. We'll stick our guns to it. Maybe at Q3, we can look at revising, what we say, the numbers. It's very early in the quarter, a year, part of the year. I don't want to commit things I cannot honour. I would rather err in caution than be aggressive on this. We have the order book, we will build our order book more, as we speak, but, as I said, a lot of these factories are just yet to get commissioned fully.

  9. Question

    Darshil Jhaveri: Okay, fair enough. And sir, overall margin guidance, what would that be? Sir, because even, I think our Q1 is also been strong, like in an environment that's tough, right? So could you just help us with that, sir?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Please model us at 20% or high teens EBITDA. We will always try to deliver better.

  10. Question

    Naman Parmar: Yes, good afternoon, sir, and congratulations on great set of numbers. Sir, firstly I wanted to understand on the new products that the GIS and the grading capacitor used in the circuit, what's the update on that? If you can help us on that?

    Answer, bharanidharan pandyan

    Maybe in the next quarter, we will try to put some photographs of it. So, yes, I think it is on track. We should start getting some results soon about it. I think the first product that will be testing is a 220 kV GIS components, switching on to 400, 765 kV in the next, say, one year's time.

Show 14 more questions
  1. Question

    Naman Parmar: Okay, got it. Secondly, on the bookkeeping side, like how much would be the forex currency gain in the other income if you can elaborate?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: I think we had a loss of INR8 crores -- INR7.5 crores, not gain.

  2. Question

    Naman Parmar: And lastly, on the margin side, if you can help me understand what was margins for the Endoks and Mehru in the current quarter, EBITDA?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Mehru this quarter delivered about 18%. Our target was to get about 22%, 23% internally, however, with the kind of copper and oil prices that came in just in April, they had a direct impact. I believe we should be increasing the guidance of Mehru above 15% what we were earlier. I think our revised guidance for Mehru would be around 18%.

  3. Question

    Endoks?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Endoks you will have to give us some time. The current product lines where they are already present, like STATCOM, SVCs, automations, I think they are normally around 25%. With the BESS coming in, we will have to just have a look at it. The products are yet to be shipped out of the factory. I can better answer that in Q3, how the blended margins look like.

  4. Question

    Naman Parmar: Okay, got it. And lastly, like you mentioned, you are raising the capital. So if you can help us understand the raising of the fund will be for what, and current debt structure is what?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: I don't think we have much of a debt. One second, the total debt as of last quarter is I think about INR23 crores, overall at a group level, that is also working capital at some subsidiary thing. Most of the companies are sitting on cash. However, these are at subsidiary cash. We are raising capital to close the WS acquisition. We are also proposing a INR50 crores capex at that location for enhancing capacity. We have about 40 acres of land free to do what we want in SVZ, beautiful campus.

  5. Question

    Naman Parmar: Yes, so total raise would be how much?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: We have not put numbers to it, but less than INR500 crores.

  6. Question

    Ankit Jain: Good evening, sir. Congratulations for delivering very solid set of numbers. So I have 2 questions. Number 1 is, I believe that you have started marketing your Mehru's products globally. So how is the reception of the products? Are you seeing more traction from Europe or US? And if the traction is good, would we need any further capacity expansion in India itself to cater to those markets? That's number 1.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: So, for Mehru, we have got a lot of orders, but they are already full with a lot of orders. They have, I think, at this moment supplying 1 in 2 high voltage instrument transformer that is required in this country. They have been a very vital part of the entire Indian grid system. So the customers are writing more of framework orders now rather than small order packages. So we do not have much of a capacity coming in from Mehru, the current facilities, I think they will reach 100% very soon. Page 12 of 23 Quality Power Electrical Equipments Limited August 10, 2026 We are overlooking at a facility in Turkey. I was there in Turkey a couple of weeks back, looked at the site, the space we have, we had put in some photographs also of the facility.

    Answer, bharanidharan pandyan

    To be able to either build a facility in Turkey for the European markets and deliver US from India and keep the rest of the world from Europe, that is one option. Another option is to also look at the piece of land what we have in Vizag, to make it especially all the exports through one separate business. Advantage of WS is that we have 40 acres of land in that campus apart from the insulator factory. For doing whatever we want to do and build a large campus out of this facility. So these are decisions that we are looking at. We have about 6, 7 months' time before we bite the bullet.

  7. Question

    Ankit Jain: Understood, sir. And sir, second would be, in order to cater to more European markets, would we need to set up any manufacturing facility there in the US or can we fully cater to the market from India or Turkey? So is there any localization requirement that we might need to consider?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: See, most of the markets, most of the markets are inward-looking, by the way they write the policies and tender documents. So, Europeans normally prefer a European origin company rather than any other origin in the world. Americans are that way kind of open to whoever the vendor in the world, as long as the quality and the systems are in process. So, I believe US can be catered out of India, but for the European market, which is at a different level of a boom right now because of the renewable energies, we would definitely need a facility somewhere in the European peninsula. That is one of the reasons why we are also interviewing candidates, because this is putting all together a totally large green facility. So, we are taking our time, taking the decision rather than rushing into it.

  8. Question

    Ankit Jain: Understood, sir.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: But Europe we are already supplying inside the Denmark grid from Mehru this quarter, and we will get more from the Swedish grid very soon.

  9. Question

    Ankit Jain: Got it. And if I can squeeze in a very quick one. Sir, you also mentioned that you are hiring procurement across the group. So how does that help us? Will that lead to better negotiations? Can we see some margin accretion when you consolidate all the procurements? So how to see this?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: As the scale increases, we are seeing the reason why we need to start negotiating together. To give you an idea about castings, say aluminum castings, we buy about INR15 or INR20 crores in Mehru, we buy maybe at about INR250 crores of revenue in WS, we would end up buying almost INR50 crores of castings. Same way in Sukrut, they buy about INR10 crores of casting. Quality Power buys casting. So, if all of them are talking to four different vendors, why not have a framework agreement with one vendor to get the scale and cost? So, this is us going through a natural progression of being a larger company where we are finding at some points we need to start consolidating, and some points retain freedom at factory level. I think we will find an equilibrium in the next few years.

  10. Question

    Glad to hear that you are moving towards that direction. Thank you so much and best of luck.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Technically, the commercial production can start the day we get the clearance from the utility - - from the authorities, that is your pollution completion board, your factory inspector, your building completion certificate, the MIDC, all the local authorities. So, the last-minute checks and balances are being done as we speak. I think we have guided this month, we are trying our level best to start commercial production this month. Maybe in small volumes, not in very big batches. The reason why we are calling it trial is primarily because this being a regulated product, I cannot start producing everything overnight in this new facility because the customers want it only from an approved facility. And the approval of this facility is what takes time. Lovish: Got it.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: We have guided about six months. Because we have at least, in our initial scope of things, we have about 60 audits lined up. Global audits. Lovish: And would we need all of these audits in one place or can we when -- as and when we start receiving approvals, we can start ramping up production?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: So, our first focus is the orders which we are executing. Let's assume that we are executing the Adani and the Power Grid HVDC, our first focus after getting the ISOs is to get the Adani and Power Grid HVDC approvals, for that I need to first get the Hitachi global approval from the facility which is about five or six audits. Then we have an Adani audit and a Power Grid audit. So that itself is about eight audits before we shift into the next project. So, we are prioritizing the audits based on which project is coming into manufacturing first. Lovish: Understood. And sir, on the Winwin acquisition that we have done, I wanted to understand what was our rationale for this acquisition because it seems like backward integration will be only a small part of it.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Good question, Lovish. This facility will take some time of management time in getting it turned around. This is a very large factory, as big as a cement factory. Insulators are a capex heavy Page 14 of 23 Quality Power Electrical Equipments Limited August 10, 2026 business, unlike asset-light business of most engineering companies. Whether it is data centers or high voltage, low voltage, whatever we are in the business, insulators is something that we cannot live without. Let's say, if you go to any substation, the first thing you see is a brown porcelain. Now, we have been finding that there's a demand for insulators internally which is slowing down our growth.

    Answer, bharanidharan pandyan

    But also across board, every large multinational which is guiding for growth is getting stuck because of this. So what happens, as we increase our scope of product, we can leverage or barter their growth with the supply of insulators to them. A. B, globally, there are very, very few insulators people in the world. I think in India there are about four or five. Globally maybe another eight or nine people, right? So nobody is expanding, no new vendor is coming in, which means as the way we see the grids operate, the demand-supply mismatch of insulators are going to be even more extreme. And whichever business we get into or acquire, will have the problem of insulators.

    Answer, bharanidharan pandyan

    So that A, helps us in increasing our throughput of our existing businesses, and also use it as a leverage. And the amount of money I paid for the business per se is about INR50 crores, INR60 crores. If you look at the valuation, we got a huge piece of land where we can start going and expanding it. The building is free for all, only eight acres of it is the facility. So basically, the business is not very much I paid for. I think in the next two years I should be able to collect my cheque back. Lovish: Got it.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: So, as I said, we have been traditionally doing about 25% margin in this factory. Even if you see the last six quarters give and take that is what we are. Sometimes it's higher, but I don't hope it is going to be lower than that. I cannot really comment the way we have been -- there's been sharp increase in prices, so the dollar is also depreciating -- a lot of appreciating and a lot of our orders are also exports. So we will have to give it. We have always exercised caution, and my colleague Rajesh also exercised caution. So please don't build your castle based on these numbers, please build your castle based on the numbers we've guided.

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: I think we may attempt raising them this month, before the AGM. Our intention is to help my team less bureaucracy, what we say, so that we can get both the AGMs together. I believe we will start the road shows from 20th of this month. Charchit: Got you. And sir, on the Sangli ramp up, so like, till when we will -- we are targeting to commence this plant?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: So, commencement is subject to market -- what we say the approvals from the bureaucrats but as I said, our Vastu Shanti pooja is on 13th and 14th of this month. Charchit: So, we can say like from Q2, we'll start generating revenue from this plant?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: At this moment, our first focus is to get the factory in order before we start revising targets. Please stick to the 20% guidance that we have given. Charchit: Okay.

  11. Question

    Rohit Taparia: Good afternoon, sir. I had a couple of questions. First is on Endoks manufacturing facility, what is the peak revenue potential and contribution for the same in FY’28?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: So at a high technology product, we really don't invest too much. As I said at this moment, the entire facility is costing us about $2 million, give and take we may spend about $1 million. I think that factory is good enough for about at least $70 million, $80 million. That is the kind of scale it can take. Yes, that would be the guidance on that facility.

  12. Question

    Rohit Taparia: Okay. And contribution for the same, if you can provide it FY’28?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: Give us some -- you'll have to give us some time. As I said, the factory is still not operational. The civil is on. The interiors, flooring, the conveyor belts and the antistatic coating, there's a lot of, there's a power electronic facility, it needs a lot of interiors. It is on. Once we are able to ship a quarter or two with the products, we will be in a better position to give you guidance. At this moment, I will be shooting in the dark when I give you a number.

  13. Question

    Rohit Taparia: Okay, sir. And second one is that on Winwin Speciality, when you had recently acquired Winwin Speciality, and when will it start contributing to the numbers and how much will be the peak contribution without capex and with capex, as you said in the recent call?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: We will start most probably consolidation Q4 this year. Without a capex, I think it should be doing between INR250 crores and INR300 crores. With the capex, I believe it will be about INR450 crores to INR500 crores. But also the capex is just not only for porcelain it's also for composites, adding capability rather than just product volume.

  14. Question

    Rohit Taparia: Yes sir what would be the peak revenue potential for the Sangli plant?

    Answer, bharanidharan pandyan

    Bharanidharan Pandyan: As I said, about 1,500 crores, give and take.

Questions about this call

When was the Quality Power Electrical Equipments Q1 FY27 earnings call transcript filed?
Quality Power Electrical Equipments filed the transcript with the exchange on 14 Aug 2026. This page is built from that transcript.
What does this page list?
106 statements from the transcript across 12 topics, 30 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 24 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.