Sterling and Wilson Renewable Energy Q2 FY27 earnings call: Sterling and Wilson Renewable Energy said its order position was healthy as on 1st April 2026
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company said its order position was healthy as on 1st April 2026. The company expects recurring overheads to be around 4.5% of revenue for the current year as revenue increases, with the cost remaining the same. Gross margin was about 9.5% in the first half. The company said it is shifting strategically from the domestic market to the international market and is more skewed toward international business than the expected 70 -30 domestic, international mix for this year. Net working capital was negative INR301 crores as at 30th September 2026, compared with negative INR260 crores at the end of Q1 and negative INR329 crores in March.
The numbers management gave
Results
- Gross margin was about 9.5% in the first half.
Show source
For the first half, gross margin was about 9.5%.
- O&M gross margin was about 23% in Q2 FY '27, and it expects O&M gross margin to settle at around 20%.
Show source
O&M gross margin was about 23% this quarter, and we expect it to settle at around 20%.
- Operational EBITDA was INR56 crores, a margin of 3.7%, in Q2 FY '27, compared with INR62 crores at 3.5% in Q2 FY '26.
Show source
Page 5 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 Operational EBITDA, which is gross profit minus recurring overheads was INR56 crores, a margin of 3.7%.
- Overall turnkey wrap is more than 8%.
Show source
So, we are around -- on the overall turnkey wrap, it is more than 8%.
- International O&M margins are almost 30%, 35%, or 30% to 40% higher than domestic market margins.
Show source
And with this international being slightly better, of course, as I've told you, is almost 30%, 35%, 30% to 40% higher than the domestic market margins, right?
- O&M business grew from 11, 12 gigawatts to 18.5 gigawatts.
Show source
And that's how we have phenomenally it has grown from 11, 12 gigawatts to now 18.5 gigawatts.
Show 12 more statements
Results
- O&M business is around 5% of overall revenue and may increase to up to 10%.
Show source
Going forward, it may increase to up to 10%.
- Interest cost increased because it availed new credit lines during the current year and opened letters of credit for a longer period, with the additional period for LCR factored as interest cost; gross borrowing was on a reduction cycle and had been reduced.
Show source
So that has led to our increase in interest cost.
Money and capital
- Net working capital was negative INR301 crores as at 30th September 2026, compared with negative INR260 crores at the end of Q1 and negative INR329 crores in March.
Show source
Net working capital was negative INR301 crores as at 30th September 2026, compared with negative INR260 crores at the end of Q1 and negative INR329 crores in March.
- Receivables, including unbilled revenue, stood at INR3,005 crores in Q2 FY '27.
Show source
Receivables, including unbilled revenue stood at INR3,005 crores.
- Receivables days increased to 176 from 138 in March, and payable days increased to 164 from 135.
Show source
Receivables days increased to 176 from 138 in March and payable days increased to 164 from 135.
- The company added around INR1,800 crores of new credit lines from the banking system last year and around INR2,800 crores in the current year, around INR4,600 crores in total across the two periods.
Show source
And so basically, put together, if you see last year and current year, we have added around INR4,600 crores new credit lines from banking system.
- The company received more than INR700 crores from surety bonds, in addition to its new credit lines.
Show source
And over and above more than INR700 crores from surety bonds also we got.
- The company received 3 new sanctions from Indian banks and 1 new sanction from a South African bank for the Egypt project in the current year.
Show source
In the current year, we got 3 new sanctions from Indian banks and 1 new sanction in South Africa -- from a South African bank for Egypt project.
- Current utilization of credit lines is around 70%.
Show source
Our current utilization of the credit lines is around 70%.
- The company continues to operate with negative working capital.
Show source
We continue to operate with negative working capital.
- Credit rating is under renewal; it could not get an upgrade earlier because it took that write-off last year.
Show source
In terms of cost and credit rating, credit rating is under renewal as of now.
- The company will go back to the rating agencies for a review of its credit rating if it gets Reliance orders or other large positive news.
Show source
And the moment we'll probably have Reliance orders or any other large positive news, definitely we'll go back to the rating agencies for review of the rating.
What it expects ahead
What management expects
- The company expects recurring overheads to be around 4.5% of revenue for the current year as revenue increases, with the cost remaining the same.
Show source
It was around 5.5% and the moment revenue will increase, this cost will remain same, and we expect it to be in the range of around 4.5% for the current year.
- The company said Q3 will be better than Q2 and Q4 will be heavily loaded, although Q3 and Q4 will not each be in the same proportion of INR2,600 crores as Q1 and Q2.
Show source
So, for sure, the Q3 and Q4 will not be in the same Page 8 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 proportion of INR2,600 crores, INR2,600 respectively, but Q3 will be better than Q2 and Q4 will be heavily loaded.
- The company expects its O&M business to reach around 22, 25-gigawatt by the year-end, an increase of maybe 25% this year.
Show source
This year, I'm expecting another maybe, I mean, 25% of this -- by the year-end, I'm expecting it will go around 22, 25-gigawatt kind of things.
- O&M business is around INR200 crores and is expected to move up to INR400 crores in the beginning of next year, with a 20% margin; at INR400 crores, that would be around INR80 crores.
Show source
We'll move up to INR400 crores, right, in the beginning of next year.
- The company expects its O&M business to increase by a minimum of 10% to 15% every year, with the margin increasing to that extent.
Show source
But then you can understand that, I mean, on the business side of, let's say, INR400 crores next year, every year, if you increase minimum 10% to 15% and to that extent, the margin also will go up, right?
- The company said gross margin for a stand-alone battery project could be 10% if it involved only the balance of supply, or 8% if it included battery supply.
Show source
We expect EPC gross margin of 8% to 10%, depending on the project mix.
Show 14 more statements
What management expects
- The company maintains guidance for 15% to 20% growth over last year for the current year and gross margin of 8% to 10% for the full year.
Show source
C. K. Thakur: So Madam, so based on to our guidance, we still maintain up to 10% growth in the revenue this financial year.
- The company expects overheads as a percentage of revenue to fall and operational EBITDA margin to improve as revenue grows in the second half.
Show source
As revenue grows in second half, overheads as a percentage of revenue should fall and operational EBITDA margin should improve.
- The company said international revenue will keep on adding, while four domestic projects may take another one to two months and substantial revenue from the new PSU projects will come in Q4.
Show source
Domestic 4 projects may take some time, another maybe 1 to 2 months, but the substantial revenue from the new projects, PSU projects will come in Q4.
- The company expects good margin from the Minya project, with Q3 and Q4 of this financial year loaded because of the project; Q1 and Q2 next financial year are its completion dates.
Show source
So, I'm expecting that, I mean, good margin to come from these projects.
- The company expects an order under its framework arrangement with Adani to close soon, perhaps this month or early next month.
Show source
And we are expecting that this order as per the framework arrangement should be getting closed soon, right, maybe this month or maybe early next month, right?
- The company believes it is among Reliance's preferred EPC partners and expects a large chunk of Reliance's order to come through the company, but said it cannot commit unless the order comes to it.
Show source
But we believe we would be very -- I mean their preferred EPC partners, and we are expecting the large chunk of order to come through us.
- The company expects commencement of the Reliance project in this quarter.
Show source
But in this quarter, the commencement, of course, is expected.
- Reliance is committed to commission something this financial year, and Sterling and Wilson Renewable Energy expects the order to start coming soon; the company said things will happen this quarter for sure.
Show source
Things will happen now this quarter for sure.
- The company expects O&M to continue increasing even if its EPC business remains stable.
Show source
Because this will continuously increase and if EPC business remains stable, still O&M will continue to increase.
- The company focuses its O&M business on Africa and Saudi Arabia, and plans to expand gradually in Saudi Arabia.
Show source
So gradually, we'll expand.
- The company expects to be around the guidance it gave the market for this financial year, despite many ups and downs. Replaced by a later filing.
Show source
So, for this financial year, at least despite the fact that there are many ups and downs, but we would be around the guidance that we have given to the market.
- The company expects steady margins from its O&M business. Replaced by a later filing.
Show source
It will not be the right comparison, but it will be the steady margins coming in from this.
Orders
- The company said its order position was healthy as on 1st April 2026.
Show source
Fortunately, I will say that we had a very healthy order position as on 1st April 2026.
- Nigeria project is still on and the company is pursuing it, but it cannot commit to a timeline at this moment; the project was to be taken by the Finance Ministry, and elections are coming.
Show source
So, this was EXIM project from U.S. So, I mean, the project is still on, right?
What it is building and selling
Projects and capacity
- The company is doing two EPC projects, one in Spain and the other in Italy, and is open to European markets.
Show source
Now we are doing 2 EPC projects, basically one in Spain and other in Italy.
Demand and pricing
- Some BESS orders bagged by competitors were terminated after being priced around USD45 per kilowatt hours when battery cost was around USD75, USD80 per kilowatt hours, leaving the orders non-moving.
Show source
And therefore, I mean, the order was terminated.
Segments
- The company said it is shifting strategically from the domestic market to the international market and is more skewed toward international business than the expected 70 -30 domestic, international mix for this year.
Show source
And therefore, you could see that despite the fact that we thought that this year we will be around 70 -30 domestic, international, but we are even more.
- Turnkey projects have lower percentage margins but higher absolute profits, while balance of system projects earn better gross margins.
Show source
Turnkey projects have lower percentage margins, but higher absolute profits, while balance of system projects earn better gross margins.
- O&M contracts are manpower-intensive and cover operating and maintaining projects; obligations during the DLP are part of the EPC contract, and issues during that period affect the EPC contract rather than the O&M contract.
Show source
O&M contract is very clean, they have to only operate and maintain, and they are mostly the manpower-intensive contract.
- The company has an international division for O&M business, with a business model comprising EPC and third-party work.
Show source
Page 15 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 And your first part, yes, so as I have told you that the business model is mixed from the EPC versus third party.
Show 4 more statements
Deals and partners
- The company has a five-year framework arrangement with Adani; the first year was around 1.2 gigawatts, and an RFQ for the next 1.2 gigawatt has come to the company.
Show source
So first year was around 1.2 gigawatts and the RFQ for the next 1.2 gigawatt has already come to us day before yesterday.
- The company is bidding for international O&M business and obtained a third-party O&M business in Saudi Arabia last year.
Show source
And we have got one third-party O&M business in Saudi Arabia last year.
- O&M contract in Africa has a bonus clause under which it receives a share of profit if yield and generation improve, and it has been getting bonus from these orders year-on-year.
Show source
So, if you perform better, if the yield and generation become better, then we get also the share of that profit.
- The company has completed O&M work in Zambia, Namibia and South Africa.
Show source
So, for Africa, like you understand this market, we have done the Zambia, Namibia, South Africa.
Risks, rules and outside factors
Outside factors
- Domestic cell capacity in the module side is 35 gigawatts and may reach up to 100.
Show source
So now it is at 35 gigawatts, it may reach up to 100 by these things.
- The company said curtailment in Rajasthan and Gujarat has slowed order inflows from IPPs, and the obligation for PSU projects to install BESS systems is another factor affecting the industry.
Show source
The 2 reasons, one that I have told you in my opening remarks also that the curtailment in Rajasthan and Gujarat that have slowed down the order inflows from the IPPs and even for the PSU, the requirement of obligation of the BESS systems to be installed.
Rules and policy
- The company said BESS is now mandated to be with the domestic Indian mix, but the company does not have self-production capacity.
Show source
The BESS is now mandated to be with the domestic Indian mix kind of things, but we don't have the self- production capacity.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
We keep talking of the fact that we have a very strong order book, but the execution for whatever reason, it may not be your problem and maybe the customer is not able to get the land or whatever he's supposed to do. But it keeps getting delayed. And because of which what's happening is our profitability is getting affected. I know you've maintained your 10% top line growth for the current year, which is what you had initially said. But what is the reason for these delays? Are we going to constantly have this? And then by the end of third quarter, we say, no, now we may not be able to achieve the number because that sends projections off track, that sense our expectations off track. So, what
Answer, c thakur
C. K. Thakur: Yes. Thanks, Sameer. If you look at the UOV (Unexecuted Order Value) positions at hand at the start of the year, we had pretty robust order book in hand. Having said that, there were 3 projects, 1 large-sized project from Coal India that we announced and 2 projects from NTPC. Normally, when the projects are being announced in the Q4 or Q1, around 70% of the revenues is considered in the following years. That means your contributions from the new orders could have been much larger, right? Unfortunately, the Coal India and the 2 NTPC projects, because of the PPAs not being signed with the utilities, the final NTP did not come to us, which we expected that the execution of these projects could have been started in the, let's say, mid of the Q2.
Answer, c thakur
That's reason one. The 4 projects in international market, their NTP was supposed to come somewhere around let's say, August. For 2 projects, we were expecting the major revenue to, of course, come from Q3 and Q4 and some revenue in Q2. So those NTP also were delayed because of their financing arrangements and other things. Fortunately, one large size order which have come from Egypt Minya, they are the short gestation project and the project is moving, the NTP has come and the work has started. So , with this, historically, if you look at our performance in the last financial year also, I mean, with respect to that, we are at the right pace. So I was just telling that had these new projects been started sometime in the mid of the quarter 2, the results could have been better.
Answer, c thakur
But having seen this delay, in the Q1 results I have already given the guidance that probably Q2 will not be as promising. And it would be in the range on the Q1 only. And we are here. We are here. We are in the range of Q1 only. So going forward, the answer is yes that, I mean, the international revenue will keep on adding. Domestic 4 projects may take some time, another maybe 1 to 2 months, but the substantial revenue from the new projects, PSU projects will come in Q4.
Question
Sameer Dalal: Okay. The second question comes on costing. One thing that we have noticed is that the cost is continually moving up. Now we had talked about the fact that we can maintain our cost at the current level. And as the top line grows, the operating leverage will play out at the -- I mean, Page 7 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 this is at the central office, right, at the headquarter. But we're seeing that this is continually rising. Now where do you see it stabilizing for FY '27 and FY '28 from INR300 crores, INR320 crores that you all do? Where do you see it going over the next maybe 2 years?
Answer, ajit singh
Ajit Pratap Singh: So, I think if you see the recurring overheads, if you're talking about that, then the cost is almost flat. There is not significant movement on either side, neither lower nor higher. As a percentage of revenue, because the revenue was lower in the current quarter and in the last quarter also. So as a percentage of revenue, it looks high. It was around 5.5% and the moment revenue will increase, this cost will remain same, and we expect it to be in the range of around 4.5% for the current year.
Question
Sameer Dalal: Fair enough. But no, once you said that you are waiting for the Reliance orders. So, my question is, once the Reliance orders come in, would you need to hire a lot more people at the offices? Would that push the cost up? And of course, the question that eventually lies is by when do we expect Reliance to actually give the orders which we can start executing?
Answer, ajit singh
Ajit Pratap Singh: So, majority of the cost will be at the site, which will be part of direct cost from the Reliance orders also. There will not be any significant increase in overhead cost.
Question
Sameer Dalal: And if you can just give us a particular date then? And that's the last question I have and then.
Answer, c thakur
C. K. Thakur: No. So basically, this we discussed last time also. So, from the overhead side, I mean, the employee cost and all and the other expenditures is already part of the project cost, which will be part of the overall project cost. So, to that extent, some addition will be there at head office, but proportionately, it will not increase our burden because the revenue also will be coming. On when the project will come, I'll maintain the same status because the site readiness work is going on. And post monsoon, the work is supposed to be started. So, it is just on to the final leg of the finalization of some of the technologies on the tracking side and all. So, I'm not in a position to give you much details.
Answer, c thakur
But I can tell you that now this is almost at the fag end of the -- I mean, the planning process and the work we can see the -- I mean, some good news you will hear about soon. That's what I can tell you at this stage.
Answer, c thakur
C. K. Thakur: So Madam, so based on to our guidance, we still maintain up to 10% growth in the revenue this financial year. I've already told earlier the first -- the Q1 was a little subdued, Q2 also because of various factors, non-moving PPA adoptions, all those factors have affected new projects not to get started. But Q3 and Q4 because the international projects have all been taken off. So, I'm expecting the traction to increase more. So, for sure, the Q3 and Q4 will not be in the same Page 8 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 proportion of INR2,600 crores, INR2,600 respectively, but Q3 will be better than Q2 and Q4 will be heavily loaded. Disha: And sir, we don't see any risks to the execution, right?
Answer, c thakur
C. K. Thakur: No. So basically, we are pretty confident of our ability to execute the projects. Why it has impacted is basically some of the projects have not started. So, our team is in place. We understand everything. So, everything has been all planned. So now since the project has been launched and there is a definite timeline. So, from the international project, the revenue has to increase.
Answer, c thakur
I'm expecting the 4 stalled projects in India and few IPP projects in between that they have come, they are all on track. All the ongoing projects, all projects are on track. None of the projects are getting delayed because of our ability to not execute the projects. So, what I say that, I mean, out of the 4 projects in India and a few more projects if they come and they are at a faster track, they should be contributing towards the quarter 4. So unfortunately, this is not only with us, the entire EPC community and the whole industry, India, Indian industry in the solar sectors have been impacted because of these reasons. The 2 reasons, one that I have told you in my opening remarks also that the curtailment in Rajasthan and Gujarat that have slowed down the order inflows from the IPPs and even for the PSU, the requirement of obligation of the BESS systems to be installed. The BESS is now mandated to be with the domestic Indian mix kind of things, but we don't have the self- production capacity.
Answer, c thakur
This mismatch and understanding, people are quoting, I mean, any crazy prices few orders you must have seen, they have been all terminated, right? The contractors could not execute the job. So, the developers are also becoming very careful that, I mean, you can have the wish list for a number of things, but Indian industry does not support. So, although the pipeline, the requirement, the development plan is already in place. But on overall execution side, all these technologies and other things are taking time, which is not specific to Sterling and Wilson alone, but it is specific to the industry. Disha: And sir, for the international EPC projects, do we see a major margin differential between the domestic and the international projects? And if so, what is the differential?
Answer, c thakur
C. K. Thakur: So domestic market margin is always under pressure from the fact that in all the solar and the BESS projects, there is low entry barrier, right? So , anybody from the outside - some of the business infrastructure projects also, they feel that solar being vanilla projects, they can earn a lot of money. And without understanding the efficacies of technologies, the supply chain disruptions and all they are entering into the market, and they are quoting any price, right? And therefore, you have seen that despite the fact that, I mean, good amount of contracts have been finalized in H1, but none of the government tenders we are there because it has gone below the -- you say, from our appetite point of view, it has gone below the cost, right? And then people have taken, God knows how they are going to execute, but we have been keeping away from all such kind of decision. Page 9 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 What I said that India, this kind of entry barrier problems and all and not much opportunity in the other sectors being seen, people are coming and jumping left right? So that has impacted the margin.
Answer, c thakur
Of course, for us also, I mean, we have to sustain. Therefore, the margin that we expected, right, in the domestic market would be slowing down because you have to take a business call and you have to survive . but not to the extent that, I mean, people are doing . Then strategically, you have to move from domestic to international market. And therefore, you could see that despite the fact that we thought that this year we will be around 70 -30 domestic, international, but we are even more. We are skewed towards international. Why international margin is more? Because the market is stable.
Answer, c thakur
People understand all those things. There is healthy competition and with healthy competition and overall turnkey project in terms of percentage, even if it is slightly lower, I mean, as compared to the old Indian condition. But since it’s turnkey projects, our absolute numbers will be more than the domestic margins. So therefore, the contribution will be much more. Disha: Okay. So as the execution also scales up in the second half, can we expect for this entire year EBITDA margins to be in the range of 4%, 4.5%?
Answer, c thakur
C. K. Thakur: So, the Minya project is the project is for, let's say, around 14 months, right? And the NTP has started. So, let's say, 40% of the time to go for this financial year in the similar proportions to Q4 would be heavily loaded for the supply to commence. So, I'm expecting that, I mean, good margin to come from these projects. And Q1 and Q2 next financial year would be the completion dates. So that's the reason that I said that the Q3, Q4 of this financial because of Minya definitely would be loaded. Margin is a pretty good margin.
Answer, c thakur
So, we are around -- on the overall turnkey wrap, it is more than 8%.
Answer, c thakur
So, as you are aware that we have into the framework arrangement with Adani for 5 years. So first year was around 1.2 gigawatts and the RFQ for the next 1.2 gigawatt has already come to us day before yesterday. And we are expecting that this order as per the framework arrangement should be getting closed soon, right, maybe this month or maybe early next month, right? So that is on to the Adani side. Reliance side, it's premature to tell you that how much order will come. But we believe we would be very -- I mean their preferred EPC partners, and we are expecting the large chunk of order to come through us. But I mean, unless it comes to us, I can't commit to you, right?
Answer, c thakur
But then, yes, it's going to start soon. On the banking side, Ajit, if you can just share.
Answer, ajit singh
Ajit Pratap Singh: So on the credit line side, last year, we have added from the banking system around INR1,800 crores new credit lines. And in the current year, we have added till now around INR2,800 crores new credit lines. And so basically, put together, if you see last year and current year, we have added around INR4,600 crores new credit lines from banking system. And over and above more than INR700 crores from surety bonds also we got. So, we are sitting on a pretty good position in terms of our working capital requirement for non- fund-based limits, bankers are supporting. In the current year, we got 3 new sanctions from Indian banks and 1 new sanction in South Africa -- from a South African bank for Egypt project. So, we are pretty much on a very comfortable position in terms of our bank guarantee requirement and LC requirement.
Answer, ajit singh
Our current utilization of the credit lines is around 70%. So that gives a lot of comfort to manage bank guarantees and LCs. In terms of cost and credit rating, credit rating is under renewal as of now. But since last year, we have taken that write-off, so we could not get the credit rating upgrade earlier. And the moment we'll probably have Reliance orders or any other large positive news, definitely we'll go back to the rating agencies for review of the rating.
Question
Faisal Hawa: And sir, you did talk about the competition underbidding in most of the solar projects. So , do you see this competition now weakening and overall, their financial situation not being so good that they may not be able to -- or they may be blacklisted by many agencies, they may not be able to participate in many more contracts and overall the competitive intensity going down? Or you feel that more such players will come in now?
Answer, c thakur
C. K. Thakur: No, for sure. So we are waiting for the consolidation to happen. What is happening now, the financial qualification requirement for all such solar projects is not very stringent. Now what we see the trend getting reversed is that for all -- from all the PSU companies, the large-sized project orders that are coming, they are coming with the modules. And therefore, the project cost is in the high range. There, I'm expecting that the small players will not be competing, right? And then we will have a better opportunity to get into.
Answer, c thakur
So that would be the kind of scenario in the Q3 and Q4 - the huge pipeline that I have already told is projected. So, the consolidation for sure will happen. Page 11 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 On the existing orders that they are bagging, you must be tracking the news in the market, a few of them have been already terminated. I mean the BESS orders that they had bagged, right, at the -- I mean, say, 50% discounted price from the battery cost. I mean the battery cost was, let's say, around USD75, USD80 per kilowatt hours, their tender price was around USD45, right? And then it was a non-moving kind of orders. And therefore, I mean, the order was terminated.
Answer, c thakur
I have already told that for the green corridors, the government has taken a lot of actions on the BESS side, the cell production, if not in maybe Q3, but I mean, Q3, Q4, but Q1 of the next financial, many large players are doing. Then the domestic cell capacity in the module side, they are increasing. So now it is at 35 gigawatts, it may reach up to 100 by these things. That would be the time when I say that the price level also will get consolidated, the government policies versus the actual requirement will all be getting settled. And then that would be the healthy time where I mean you can see that the things should be in the right direction s. But till such time, because of the some of the industries paralysis, I will say, some of the policies, which are to be implemented, b ut the industry is not ready - all those things have impacted everybody. I mean a few of them which they can keep on adding , because of the IPO, they are just going for, but we are not into that race. Fortunately, I will say that we had a very healthy order position as on 1st April 2026.
Answer, c thakur
So, for this financial year, at least despite the fact that there are many ups and downs, but we would be around the guidance that we have given to the market.
Question
Faisal Hawa: So, is it now time that we forget about the Nigeria order?
Answer, c thakur
C. K. Thakur: I will not say to forget about this. But yes, it is still cold because now election is going to happen and all those kinds of things. So, I mean, the last update was that it was to be taken by the Finance Ministry, but you know how the African country work. But then the new government coming and all and the tariff war, I mean, every new day, you take the news from the honourable U.S. President, right, every country, they are all -- how they are affected. So, this was EXIM project from U.S. So, I mean, the project is still on, right? We are pursuing this. But I mean, I can't commit to the timeline at this moment for this project.
Question
Jayesh Shroff: Yes. So why has our interest and finance cost increased this quarter in spite of lower execution compared to Q1?
Answer, c thakur
So, there was no reason that I could have not gone up to the 15%. Now since in Q2 also, they have not started the projects because of the -- I mean, the NTP not coming in. So therefore, I'm not changing, maybe the support will come from the international projects, will be quite possible. But at this stage, what I say that -- I mean, since the projects they have not started, possibility that we should be able to maintain around 10% of the revenue growth.
Question
Jayesh Shroff: Okay. And this is ex Reliance, if I understand it.
Answer, ajit singh
Ajit Pratap Singh: Yes. In terms of finance cost, the cost has increased primarily for 2 reasons. As I mentioned, we have availed some new credit lines during this year. So, cost for that. And also, the LC cost, we are now opening the LC for a little longer period so that additional period for LCR is factored as interest cost. So that has led to our increase in interest cost. Although our gross borrowing, if you see that is on reduction cycle, and we have reduced our gross borrowing.
Question
Jayesh Shroff: Okay. Just one last thing. I know a lot of questions have been asked on the Reliance order. I think Mr. Thakur talked of it being very imminent. So -- and Reliance also in its last concall talked of starting the project post monsoon. So do you think that post this Jio IPO, we can see something from November onwards in terms of execution. At least will there be some execution in this quarter?
Answer, c thakur
C. K. Thakur: I don't think that the Jio IPO has any link with this. But in this quarter, the commencement, of course, is expected. So, I say that the readiness for overall technology to be integrated in these schemes is at the final end. So how the Reliance works basically. So, every single bit of decision is being taken very carefully to ensure that the ROI on the investment comes, I mean, more than the industry expectation. So, it's interesting for everybody that why it is taking time. But as per their announcement and their commitment that this financial year, they will commission something, right?
Answer, c thakur
You have seen the -- I mean, their annual general statements. So, they are committed to commission something, right? So, keeping all those things in mind, so we are also expecting the order to start coming soon. Things will happen now this quarter for sure.
Answer, c thakur
So basically, they are all basically depends on the scope. So, scope means somewhere we have the transmission line, somewhere we have the substations, somewhere we have other things. I mean then robotic clearings, semi-robotic clearings, manual cleanings, the water cleaning, all those things depend on the various -- the pricing mechanics. And with this international being slightly better, of course, as I've told you, is almost 30%, 35%, 30% to 40% higher than the domestic market margins, right? So, I mean there's no upside (cost) risk in the O&M business, right, except for sometimes there are certain obligations on the warranty and all, but they sometimes impact very minimally, not to the extent that basically the EPC business is sometimes getting impacted.
Answer, ajit singh
Ajit Pratap Singh: Gross margin generally will convert to EBITDA with very minimal change.
Question
Nilesh Doshi: So it means the labor cost is the part of the GP margin because you are considering. Okay, sir, once the EPC project is completed, O&M contract start, and we are charging extra, not it is the inclusion of the EPC cost. It is separate, and we are charging for each and every megawatt we are doing the O&M work.
Answer, c thakur
C. K. Thakur: Yes. So basically, contract is basically -- as we were trying to understand, it is, let's say, rupees per megawatt peak. The contract composition is like this, right? And then you have the BBO for the billings. So once the project is commissioned and handed over, taking over is done, certain obligation during the DLP is there, but that is part of the EPC contract. If something goes wrong, then the EPC contract is affected, not the O&M contract. O&M contract is very clean, they have to only operate and maintain, and they are mostly the manpower-intensive contract.
Answer, c thakur
C. K. Thakur: No. So the first question is, yes, we are bidding for international O&M business. And we have got one third-party O&M business in Saudi Arabia last year. We are about to close a few projects in the other geographies. I will not reveal the fact now, but yes, it is on the final stage. So, we have our international division for the O&M business as well. Page 15 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 And your first part, yes, so as I have told you that the business model is mixed from the EPC versus third party. So third-party EPCs because of our high credential in the O&M business.
Answer, c thakur
So, I have seen that here, I mean, you -- normally, you are approached by the client for the performance of the O&M team that we have and the major spreads, right? So we don't see major challenge in, I mean, grabbing the orders. And that's how we have phenomenally it has grown from 11, 12 gigawatts to now 18.5 gigawatts. This year, I'm expecting another maybe, I mean, 25% of this -- by the year-end, I'm expecting it will go around 22, 25-gigawatt kind of things. So that's how it runs.
Show 3 more questions
Question
Saurabh Srivastava: Around whatever metrics do you feel like, how this is...
Answer, c thakur
C. K. Thakur: First, what I say that this a steady business. This is a steady business, like you said that now we are at around INR200 crores. We'll move up to INR400 crores, right, in the beginning of next year. And then 20% is the margin. So, if you see that our project margins and then around INR400 crores, 20%, let's say it comes to INR80 crores, right? So, it will not be right to compare. But then you can understand that, I mean, on the business side of, let's say, INR400 crores next year, every year, if you increase minimum 10% to 15% and to that extent, the margin also will go up, right?
Answer, c thakur
But it will not be the right comparison to say that in overall margins will be what because the cost -- our -- let's say, your EPC cost is, say, INR1.5 crores per megawatt peak, whereas the O&M cost comes to be, I mean, INR100,000, INR150,000 per megawatt peak, something like depending upon the scope and all. So , it's a huge difference. It will not be the right comparison, but it will be the steady margins coming in from this.
Question
Saurabh Srivastava: And in terms of net margin -- yes, sir, please.
Answer, ajit singh
Ajit Pratap Singh: I was telling in terms of revenue mix, as of now, it's around 5% of our overall revenue. Going forward, it may increase to up to 10%. Because this will continuously increase and if EPC business remains stable, still O&M will continue to increase.
Question
Saurabh Srivastava: Got it. And sir, my last question. Sir, what sort of international geographies are we looking for the new geographies? Page 16 of 17 Sterling and Wilson Renewable Energy Limited October 16, 2026 C. K. Thakur: So, one that wherever we have the O&M project from our own EPC, for sure, that geography is our target.
Answer, c thakur
Like we have -- we started from Africa. And Africa first project is doing very good. So. the contract is also very unique. We have the bonus clause. So, if you perform better, if the yield and generation become better, then we get also the share of that profit. So year-on-year, we have been getting fantastic bonus from these orders. So, for Africa, like you understand this market, we have done the Zambia, Namibia, South Africa.
Answer, c thakur
Africa Region is our focus. Then we are now into Saudi Arabia. Saudi Arabia is a huge capacity addition being happening, you may be knowing about. So, at right times, we have entered into this market. So gradually, we'll expand. Now we are doing 2 EPC projects, basically one in Spain and other in Italy. So that means we are open to the European markets as well, right?
Answer, c thakur
And we have experience in Southeast Asia also, but primarily, the regions we are known and we have our presence, that would be the -- I mean, basically the regions for our choice.
Questions about this call
- When was the Sterling and Wilson Renewable Energy Q2 FY27 earnings call transcript filed?
- Sterling and Wilson Renewable Energy filed the transcript with the exchange on 23 Oct 2026. This page is built from that transcript.
- What does this page list?
- 51 statements from the transcript across 10 topics, 24 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 13 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.