Acme Solar Holdings Q4 FY26 earnings call: Acme Solar Holdings Limited recently won 1.8 gigawatts of PPAs and has around 850 megawatts of older PPAs in various stages of discussions

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company recently won 1.8 gigawatts of PPAs and has around 850 megawatts of older PPAs in various stages of discussions. Total battery target is 10 gigawatt hour, subject to material supply and geopolitical factors; the company has connectivity, financing and a supply tie available. SJVN FDRE project at Fatehgarh has short-term open access available; long-term open access is scheduled for March '27, and the project is expected to be ready by FY '27 end. Central offtakers pay in 10 days, and payment within 30 days qualifies for a cash discount; this is why the company is seeing a 15-day receivable cycle, which it says is the norm rather than a one-off. Peak power realization was around 7, 8 years even in slow years.

The numbers management gave

Results

  • The company had INR5 crores to INR6 crores of impact from real curtailment for the whole year, adjusted for pre-COD or pre-GNA curtailment.
    Show source
    Page 6 of 20 ACME Solar Holdings Limited May 08, 2026 But adjusted for that, for the whole year, we have only INR5 crores to INR6 crores of impact on the curtailment, which is the real curtailment.
  • State-connected projects in Rajasthan had INR3 crores of curtailment impact on STU for the whole year.
    Show source
    And of course, on STU, it was only INR3 crores in Rajasthan for the whole year, state connected projects.
  • INR2 crores to INR3 crores of curtailment impact on Acme Solar Holdings Limited's projects was due to maintenance by the grid operator for the whole year.
    Show source
    And the INR2 crores, INR3 crores was on the account of maintenance done by the grid operator on account of the -- on account of, you can say, the O&M which they do for that.
  • Central offtakers pay in 10 days, and payment within 30 days qualifies for a cash discount; this is why the company is seeing a 15-day receivable cycle, which it says is the norm rather than a one-off.
    Show source
    So that is why we are getting a 15 days kind of a receivable cycle today.

Money and capital

  • The company had capital advances of roughly INR323 crores.
    Show source
    Arun Chopra: Capital advances, Roughly INR323 crores.

What it expects ahead

What management expects

  • Total battery target is 10 gigawatt hour, subject to material supply and geopolitical factors; the company has connectivity, financing and a supply tie available.
    Show source
    Nikhil Dhingra: So 10 gigawatt hour is our total target.
  • Bids are expected to reach a level of 15 to 20 gigawatts.
    Show source
    So you will see bids of a level of 15 to 20 gigawatts.
  • State and central bids won with capacity next year will add 20 to 30 gigawatt.
    Show source
    Manoj Upadhyay: I would like to add here that although the bids will be won with capacity in next year this year, adding state and central will be 20 to 30 gigawatt.
  • The overall solar deployment is expected to remain 40 to 50 gigawatt, although the configuration of procurement will change.
    Show source
    So overall, if you see that the name of the -- actually configuration of the procurement will change, but deployment of solar will remain 40 to 50 gigawatt.
  • The company is targeting 1.5 gigawatts of projects and around 10 gigawatt hour of battery in this financial year; the battery target may include projects outside the 1.5 gigawatts, as the battery is being charged ahead of time.
    Show source
    Nikhil Dhingra: So we are targeting 1.5 gigawatts of projects in this financial year, right, and around 10 gigawatt hour of battery.
  • Around 8.5 gigawatt hour of the 10 gigawatt hour is expected to be commissioned on a merchant basis, and 1.5 gigawatt hour in the FDRE format; around 1,200 megawatt hour to 1,500 megawatt hour will be commissioned in the FDRE format because of the Neemuch substation.
    Show source
    So you will see around 8.5 Page 16 of 20 ACME Solar Holdings Limited May 08, 2026 gigawatt hour out of this 10 gigawatt hour would be on merchant.
Show 10 more statements

What management expects

  • Assuming a tariff arbitrage of INR6, with power sold at INR8 and purchased at INR2, the EBITDA margin will be around 75% to 80%.
    Show source
    So give or take, the margin will be around 75% to 80% EBITDA margin.
  • Battery will remain at INR9 to INR10 in the peak hour time, in Manoj Upadhyay's view.
    Show source
    So battery will remain -- my guess is battery will remain at Page 17 of 20 ACME Solar Holdings Limited May 08, 2026 INR9 to INR10 in the peak hour time.
  • As a country, around 200 to 300 gigawatt hour will be needed considering current installation and the planned installation of this year.
    Show source
    And as a country, we will need around 200 to 300 gigawatt hour considering the current installation and the planned installation of this year.
  • Peak power prices are not expected to go down for at least around 4, 5 years.
    Show source
    So we see that like Manoj ji mentioned, at least for around 4, 5 years, we don't see this going down.
  • The company expects battery installation to further reduce curtailment as more batteries are installed in Rajasthan, where most operational solar is located, and says transmission infrastructure will improve substantially.
    Show source
    Just on that, just to finish that point, as the battery installation happens, the curtailment issue will be further reduced because as more and more battery gets installed in Rajasthan.
  • The company wants to prepone battery revenue from nighttime power sales, which are allowed under the PPA construct and MNRE clarification, and expects nighttime installations to increase revenue by more than the impact of CTU timeline shifts between quarters.
    Show source
    So we will see a good jump on the revenue side because of the nighttime installations, which will more than compensate for, you can say, the CTU timelines getting shifted from one quarter to another.
  • The company plans to use connectivity associated with PPAs that may not be signed for future bids or battery-connected projects.
    Show source
    But just in case if this happens, these will be for us, our strategy will be to use them for future bids and -- or to use them for, you can say, for battery connected projects in future.
  • As more solar is added, the country's need for battery will keep going up. Replaced by a later filing.
    Show source
    But as and when we are adding more and more solar, it will keep on going up.

Orders

  • The company recently won 1.8 gigawatts of PPAs and has around 850 megawatts of older PPAs in various stages of discussions.
    Show source
    There is 1.8 gigawatts of PPAs we have won recently, and there are some which are older, you can say around 850 megawatts of older PPAs which are in various stages of discussions.
  • SECI has at least 5 gigawatts of tenders currently open, including 2 gigawatts of wind and around 1 gigawatt of PSP.
    Show source
    There are at least 5 gigawatts of tender currently open with SECI, which has -- which is 2 gigawatts of wind, around some 1 gigawatt of PSP, then there is this thermal mimic, there is CfD.

What it is building and selling

Projects and capacity

  • SJVN FDRE project at Fatehgarh has short-term open access available; long-term open access is scheduled for March '27, and the project is expected to be ready by FY '27 end.
    Show source
    So the full FDRE for SJVN, but will be ready by FY '27 end.
  • NTPC solar is ready, but its long-term open access is scheduled to be commissioned by December '26.
    Show source
    But of course, there is a long-term open access there also which is slated to be commissioned by December '26.
  • The company expects the projects discussed to be commissioned by March '27.
    Show source
    So by March '27, all this will be commissioned.
  • The company has around 2,500 megawatts of ready connectivity for selling battery power at night and is trying to transmit 10 gigawatt hour of battery during the next calendar year.
    Show source
    And, of course, so these, you can say around aggregating to around 2,500 megawatts of ready connectivity for selling battery power during night is what is ready with us from where we are trying to transmit 10 gigawatt hour of battery during the next of the calendar year.
  • The company has brought battery installation forward and is commissioning batteries at operational rather than greenfield substations; it has 2,500 megawatts of ready substations and connectivity expected to go live in the near future.
    Show source
    And we have 2,500 megawatts of ready substations and connectivity, which are going to go live in the near future.
  • The company has around 6.2 gigawatts of signed PPA under construction.
    Show source
    As far as we are concerned, we have around 6.2 gigawatts of signed PPA, which we are constructing.
Show 28 more statements

Projects and capacity

  • The company has 3.2 gigawatt of LOA converted into PPA under construction, excluding 3 operational.
    Show source
    In terms of the construction 3, if you remove the 3 operational for us, we have 3.2 gigawatt of LOA, which have converted into PPA which we are constructing.
  • The batteries are slated to run for 8,000 to 10,000 cycles over their end of life.
    Show source
    And also in terms of the end-of-life assumptions, these batteries are basically slated to run for 8,000 to 10,000 cycles, right?
  • 5 gigawatt under construction will require installation of around 17 gigawatt hour of battery.
    Show source
    But correspondingly, for other projects that we have, which are 5 gigawatt under construction, that will require installation of around 17 gigawatt hour battery.
  • The battery bids discussed are one bid out of Acme Solar Holdings Limited's overall portfolio of 8 gigawatt hour, and the company is not focusing on those bids.
    Show source
    Nikhil Dhingra: So those are the bids we have -- it's 1 bid out of the overall portfolio of 8 gigawatt hour.
  • Transmission capacity has been delayed by give and take 6 months, and Acme Solar Holdings Limited has synced its project work and capex with that delay.
    Show source
    And we have also been in sync with that, let's say, a delay of 6 months.
  • The company has no project in its pipeline on the state grid other than the battery it is installing on the Andhra Pradesh, very small 550 megawatt hour.
    Show source
    There is no project in our pipeline other than the battery we are installing on the Andhra Pradesh, very small 550 megawatt hour.
  • Around 60% of substations are on time, and the maximum delay is typically 6 months.
    Show source
    But some substations, you can say around 60% are on time.
  • In some cases, a substation delay could be more than 6 months because of an unfortunate event.
    Show source
    In some cases, because of some unfortunate event, it could be more.
  • Service-related work, transmission lines and substations are around 20%, 25% of the overall project cost and are long lead items.
    Show source
    You keep the service -related work ready, the transmission line ready, the substation ready because those are typically, you can say, 20%, 25% of the overall project cost.
  • Battery installations keep project returns in the high teens and meet customer requirements for power mix and peak power.
    Show source
    So it basically keeps the return in high teens only.
  • The company is installing batteries at most of its CTU-connected projects, and all its CTU-connected plants will have a battery available to charge with curtailed power for later use; the company will also be compensated for the curtailment.
    Show source
    All our CTU connected plant will have a battery available.
  • Pachora wind component is ready and is scheduled for commissioning a couple of quarters later.
    Show source
    And our Pachora wind component is also ready, but that is also slated for, you can say, a couple of quarters later.
  • The company is targeting commissioning of Pavagada and Anantapur during this year in line with the CTU timeline.
    Show source
    In terms of the other commissioning, we are targeting, there is Pavagada, Anantapur, which are also going to come up during this year as per the CTU timeline.
  • Battery commissioning is expected to happen early because ordered batteries are arriving every month; the company will commission solar as CTU substations are charged, with transmission lines, balance of system and equipment delivery on track to align with CTU timelines.
    Show source
    So in terms of commissioning, so the battery commissionings are going to happen early because we have ordered a battery, the battery is arriving every month.
  • The company is deferring the solar-side capex and is not installing modules at the site.
    Show source
    Nikhil Dhingra: And Dhruv, we are deferring the capex also on the solar side because it is not -- doesn't make sense to call modules at site and keep them here because what we are doing is we are deferring the solar part of capex.
  • The under-construction portfolio with signed PPAs will be commissioned by FY28.
    Show source
    But on the PPA signed, yes, so these will be commissioned by FY28.
  • The company is not building any projects on the STU; its Gujarat wind project was its only project on the state grid.
    Show source
    The Gujarat project of wind that we did was the only project we have done on the state grid.
  • Neemuch substation is on time.
    Show source
    But typically, some -- like I mentioned, our Neemuch substation is on time.
  • Where a substation delay is known, Acme Solar Holdings Limited will not call for its modules and will defer its capex.
    Show source
    We will defer our capex.
  • The company can defer sizable module capex because modules are available just in time and sufficient capacity is available in India.
    Show source
    We can defer our sizable capex of modules because modules are available just in time and there is sufficient capacity of that available in India.

Demand and pricing

  • Peak power realization was around 7, 8 years even in slow years.
    Show source
    But even in those slow years, we had a realization for peak power for around 7, 8 years.
  • The annual price has remained around INR7 to INR8 for the last few years, even when demand was low. Replaced by a later filing.
    Show source
    Nikhil Dhingra: So if you look at the history, if you look at the last few years, we have seen that the annual price remains at around INR7 to INR8 for the last few years, even when we have low demand.
  • With gas constrained, the price is slightly elevated and is likely to remain elevated. Replaced by a later filing.
    Show source
    But now that the gas is constrained, it is slightly elevated, and it is likely to be elevated.
  • Peak demand is much higher than last year. Replaced by a later filing.
    Show source
    And we are seeing some peak demand, which is much, much higher than last year.

Segments

  • Around 2 projects in Acme Solar Holdings Limited's portfolio are connected to the Rajasthan state grid; the rest of its portfolio is by and large connected to the central grid, where curtailment is compensated through the regulatory mechanism.
    Show source
    So we have, you can say, around 2 projects only out of our whole portfolio which are in Rajasthan connected to the state grid.
  • Portfolio is shifting toward 100% central as more projects become operational, and all its under-construction projects are 100% central.
    Show source
    All of our under construction projects are 100% central, where they take a cash discount.
  • Projects are connected to CTU-connected substations in Rajasthan, Gujarat, Madhya Pradesh, Andhra Pradesh and Karnataka, and the company says that once long-term open access is granted they are protected from curtailment.
    Show source
    So once the long-term open access is granted, then you are protected from curtailment on a CTU connected substation.
  • The company has consciously built its portfolio with central counterparties on CTU and has not gone aggressive on C&I because serving the actual consumer requires state projects.
    Show source
    So we don't have -- and also, that is another reason we have not gone aggressive on the C&I because they are all state projects we have to do if you want to serve the actual consumer.

Risks, rules and outside factors

Outside factors

  • Thermal power in the evening is already at INR6.5 if run at full capacity.
    Show source
    But what has also happened is that the thermal power in the evening, it is already at INR6.5 if you run at full capacity.
  • Most thermal power capacity cannot come up fast or go down, so thermal power plants operate around 60%, 70% capacity.
    Show source
    So they operate around 60%, 70% capacity.
  • Considering full capital cost, thermal power is around INR9 and INR10.
    Show source
    So considering their capital cost, full capital cost in this one, they are around INR9 and INR10.

Everything else said on the call

Other

  • The current CEA calculation indicates that around 200 gigawatt hour of battery is needed if no more solar is added.
    Show source
    Actually, right now, the current calculation of CEA is you need around 200 gigawatt hour of battery to come to this if you don't add any more solar.
  • Another 40, 50 gigawatt of FDRE and this one where the tender has happened will be added in the daytime.
    Show source
    But what is happening is also another 40, 50 gigawatt of FDRE and this one where the tender has happened, they will get added in the daytime.
  • DISCOMs give better priority to projects whose substations are scheduled to be charged in 2027 than to projects with connectivity for 2029.
    Show source
    Page 19 of 20 ACME Solar Holdings Limited May 08, 2026 So if you are somebody who has a substation getting charged in 2027, you will get a better priority from a DISCOM because customers have more visibility to your project, right?
  • As more daytime solar is added, more battery is needed in the unit. Replaced by a later filing.
    Show source
    So technically, what is happening as long as you are adding more and more daytime solar, you need a more battery in the unit.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Kartik Sharma: Understood, sir. And the future project allocation, if you could give any?

    Answer, nikhil dhingra

    Nikhil Dhingra: So all of our projects are in the CTU. So we have consciously built a portfolio with, you can say, all the central counterparties on CTU. So we don't have -- and also, that is another reason we have not gone aggressive on the C&I because they are all state projects we have to do if you want to serve the actual consumer. So in terms of the -- all our CTU connected projects with CTU connected substations, where you are regulatory protected from the customer payments are there irrespective of, you can say, the grid curtailment. So they are all on the -- you can say, various substations in Rajasthan, Gujarat, Madhya Pradesh, Andhra Pradesh, Karnataka. So once the long-term open access is granted, then you are protected from curtailment on a CTU connected substation.

  2. Question

    Kartik Sharma: Understood, sir. So just continuing on that, can I ask my second question?

    Answer, manoj upadhyay

    Manoj Upadhyay: No, just a minute, I would like to clarify.

  3. Question

    Kartik Sharma: Yes, sir.

    Answer, manoj upadhyay

    Manoj Upadhyay: My name is Manoj. Most of the CTU connected projects, we are installing the battery. So in fact, such curtailment sometimes provides you opportunity to sell the power in the peak or in the evening. So all our CTU connected plants, that's what we are focusing. All our CTU connected plant will have a battery available. So whenever that curtailment will happen, we will charge the battery, and we will use that power, right? While we will get compensated for the curtailment, but we will use the free power also to charge the battery.

    Answer, nikhil dhingra

    Nikhil Dhingra: And as the battery installation happens. Just on that, just to finish that point, as the battery installation happens, the curtailment issue will be further reduced because as more and more battery gets installed in Rajasthan. And it is by and large, happening in Rajasthan because they have the largest operational solar. So you will see that the transmission system improves a lot with the battery installation.

  4. Question

    Kartik Sharma: Understood. Understood, sir. So we highlighted that there was a sharp improvement in receivables and the DSO has come down to 14 days, which was at one point in time 180 days. So despite the significant scale up, could you help us understand whether this is largely driven by like onetime collections or is this like a structural shift that you are seeing in the portfolio Page 7 of 20 ACME Solar Holdings Limited May 08, 2026 mix when you say that it's going to be more central offtakers and how sustainable this working capital profile is going forward?

    Answer, nikhil dhingra

    Nikhil Dhingra: So see, our portfolio as it gets more operational, it is shifting towards 100% central. All of our under construction projects are 100% central, where they take a cash discount. So it essentially -- and they pay in 10 days. Basically, in 30 days, if you pay, you get a cash discount. So that is where they take a cash discount. So that is why we are getting a 15 days kind of a receivable cycle today. So which is more or less not because of one-off, it is the norm.

    Answer, ankit verma

    Ankit Verma: Yes, earlier, I think the higher receivable days you are talking about, so that pertains to very -- you can say FY '23 and before that. And I think at that point of time, like Nikhil mentioned the contribution of central offtaker was less. And there are, of course, some payment issues, especially from a couple of DISCOMs as well, especially Telangana and Andhra. Even that payment has normalized now..

  5. Question

    Kartik Sharma: See, is that the effect that we've seen in the trade receivables, which have gone down 13% year- on-year?

    Answer, manoj upadhyay

    Manoj Upadhyay: Yes. Actually that there was a regulatory reform, which was government has implemented called LPS, right? Under that LPS late payment surcharge scheme, 2, 3 states which were delayed actually because of the various regulatory issues, there were some court cases in Andhra Pradesh. All those dues are now settled and they are paying on time because this LPS scheme is very strict. They don't pay on time, you inform to the PRAPTI portal and they will get disconnected from the power. So this discipline is helping, especially for the state project. But mostly now what has happened, our projects are central projects.

    Answer, manoj upadhyay

    So central projects, technically, they are paid in just 6, 7 days because they want to take a cash discount.

  6. Question

    Aniket Mittal: Okay. And what is the capital advances number there?

    Answer, arun chopra

    Arun Chopra: Capital advances, Roughly INR323 crores.

  7. Question

    Aniket Mittal: INR323 crores. And this is pertaining to what, like?

    Answer, arun chopra

    Arun Chopra: So this advances basically given to -- for the procurement of material, which has been given to various and the material will come in over a period of time. So these advances have been given to them, maybe a partial advance, let's say, 10%, 20% advance.

    Answer, nikhil dhingra

    Nikhil Dhingra: Let's say, battery contracts, we have typically 10% advance upfront where we get a bank guarantee against it. Similarly, the turbines also we give 20% advance. So these are capital advances you need to give to supplier where they give you a BG against that.

  8. Question

    Aniket Mittal: Okay. So this largely because of battery and probably some wind.

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes. On services and domestic procurement, typically, we don't give any advance. But from an international procurement perspective and large equipment, we have to because it helps you to bind the supplier also in terms of the contract honoring and also giving him advance to purchase raw material because if you don't pay advance, he will not have money to purchase the raw material.

  9. Question

    Aniket Mittal: Okay. And when I look at the PLF number on a Y-o-Y basis, I see a 1% decline. What's the reason for that for this quarter?

    Answer, nikhil dhingra

    Nikhil Dhingra: For this quarter, Aniket, could be a function of, of course, the lower irradiation or and curtailment. These two could be the only 2 factors which would have impacted. On a Y-o-Y basis, of course, the larger capacity, it is a larger capacity. So of course, the denominator is higher. But these are the 2 only factors because it is determined by seasonality as well. So these are the factors in terms of -- we can give you a site-by-site, I think, analysis. But broadly, it is because of these factors.

  10. Question

    Aniket Mittal: Okay. In the presentation within the under construction portfolio, I also see a merchant BESS of 654 megawatt hour. Are we putting some purely on a merchant basis? What does this pertain?

    Answer, nikhil dhingra

    That has a short-term open access available right now. The long-term open access as per CTU is in March '27. So the full FDRE for SJVN, but will be ready by FY '27 end. So that's the FDRE. And the NTPC, we are ready with the solar. But of course, there is a long-term open access there also which is slated to be commissioned by December '26. And our Pachora wind component is also ready, but that is also slated for, you can say, a couple of quarters later.

    Answer, nikhil dhingra

    So by March '27, all this will be commissioned. In terms of the other commissioning, we are targeting, there is Pavagada, Anantapur, which are also going to come up during this year as per the CTU timeline. What we are trying to do is commission the batteries at our operational substations in Fatehgarh-1, which we have 1,000 megawatt. Then the Fatehgarh-1, is 1200 megawatt. Fatehgarh-2 is 1,000 megawatt where we have an STOA. In STOA, you can transmit all the battery. And then we have Bikaner 3, again, where bay is ready, so you can transmit the battery power.

    Answer, nikhil dhingra

    And, of course, so these, you can say around aggregating to around 2,500 megawatts of ready connectivity for selling battery power during night is what is ready with us from where we are trying to transmit 10 gigawatt hour of battery during the next of the calendar year. So in terms of commissioning, so the battery commissionings are going to happen early because we have ordered a battery, the battery is arriving every month. And also in parallel, as and when the CTU substations are getting charged, we will commission the solar also. In terms of preparedness, the transmission line, the balance of system, the equipment delivery, they're all on track. Page 10 of 20 ACME Solar Holdings Limited May 08, 2026 And we are trying to co-terminus with the CTU timelines of these substations. And we want to also want to prepone our revenue from the battery sales because from the power sales through night time power, which is now allowed as per the PPA construct and as per the clarification given by MNRE. So we will see a good jump on the revenue side because of the nighttime installations, which will more than compensate for, you can say, the CTU timelines getting shifted from one quarter to another.

    Answer, nikhil dhingra

    So that is the reason we have preponed the battery installation, and we are commissioning it at the operational substations and not in the greenfield substations. That is the key thing. And we have 2,500 megawatts of ready substations and connectivity, which are going to go live in the near future.

Show 7 more questions
  1. Question

    Aniket Mittal: Understood. What would be the battery total installed base, let's say, 6 months down the line and 1 year down the line?

    Answer, nikhil dhingra

    Nikhil Dhingra: So 10 gigawatt hour is our total target. And of course, it is completely dependent on a number of factors in terms of the supply of material, in terms of the connectivity. But as far as connectivity is concerned, we can do this 10 gigawatt hour because we do have the connectivity. We do have the financing available. We do have the supply tie available. But of course, in terms of the various factors which are interplay in terms of the supply of material, in terms of, you can say, geopolitical factors, those are the only uncertainties. But as far as the CTU linked is concerned and as far as the other dependencies go, it has much less external dependencies than you can say, a CTU-connected solar plant.

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. No, that's a very welcome move from CERC, which CERC has done. It's a discussion paper right now, and they will formalize it after getting comments from all. So that's a good move. In terms of how it will work is if you are not able to sign PPAs for a certain amount of LOA and the Renewable Energy Implementation Agency really clarifies that these PPAs cannot be signed. Then of course that developer is free to develop it in a merchant basis or free to use it in another LOA. As far as we are concerned, we have around 6.2 gigawatts of signed PPA, which we are constructing.

    Answer, nikhil dhingra

    In terms of the construction 3, if you remove the 3 operational for us, we have 3.2 gigawatt of LOA, which have converted into PPA which we are constructing. There is 1.8 gigawatts of PPAs we have won recently, and there are some which are older, you can say around 850 megawatts of older PPAs which are in various stages of discussions. But we are not anywhere near to that timeline where we -- the REIA will say that, right, PPA will not be signed because they are trying their best and all the agencies are trying their best to get it signed. There are various discussions at various forums to get it signed. But just in case if this happens, these will be for us, our strategy will be to use them for future bids and -- or to use them for, you can say, for battery connected projects in future. So we will use this connectivity in any case because we have a good pipeline of PPAs where there is a lot of bids which are coming which are now backed by a solid demand from states like thermal mimic, which is coming, which will require a large amount of capex and large amount of solar and battery. And there are a lot of other bids which are coming which we will use the connectivity for.

    Answer, nikhil dhingra

    So plain solar is the hardest to sell, right? But some states have a typical demand for solar because they are putting up their PSP or they are putting up their thermal is a bit, some distance away. So very few states have a plain solar demand. So in terms of the pecking order, you can say peak power selling fastest. The partial peak power is second fastest. And then the wind is selling well, but wind opportunities are very less and people are doing less wind, and the solar is selling the slowest. In terms of the bids for this year, we see that the bids will be lesser than last year, but the PPA should be faster again because they are not doing bids until the previous ones get at least Page 12 of 20 ACME Solar Holdings Limited May 08, 2026 allocated or signed in some way.

    Answer, nikhil dhingra

    So that is -- and the REIA is one. So focus will come in terms of -- there is only SECI, which will now be aggregating demand. So they'll have some sort of, you can say, aggregation power, which being a sole entity gives them in terms of the -- with the states. So they are aggregating demand for, let's say, a thermal kind of tender or peak power tender or a CfD tender, which is -- which will find takers because that is purely basis demand. They are doing wind tender, they are doing PSP tender. There are at least 5 gigawatts of tender currently open with SECI, which has -- which is 2 gigawatts of wind, around some 1 gigawatt of PSP, then there is this thermal mimic, there is CfD. So you will see bids of a level of 15 to 20 gigawatts.

    Answer, manoj upadhyay

    Manoj Upadhyay: I would like to add here that although the bids will be won with capacity in next year this year, adding state and central will be 20 to 30 gigawatt. But the overall solar or overall the capex requirement will be higher than the last year because what is going to happen in the plain vanilla solar will be INR3 crores, INR4 crores, INR4 crores per megawatt. But the current bid, which is happening, for example, mimicking the thermal power or mimicking that long hour duration storage, solar storage , they will be -- actually they will carry a very large solar behind the battery. So technically, maybe 25 to 30 gigawatt will technically mean solar of 40, 50 gigawatt. So overall, if you see that the name of the -- actually configuration of the procurement will change, but deployment of solar will remain 40 to 50 gigawatt.

    Answer, nikhil dhingra

    So that is being debated. So zero date has not yet started for us. We'll be able to update you once the zero date has started. But broadly, we are telling you the bid return when we bid it. And also in terms of the end-of-life assumptions, these batteries are basically slated to run for 8,000 to 10,000 cycles, right? So in terms of -- I think that depends on the PPA, it's a single cycle or a double cycle. I think it's a -- single cycle or double cycle.

    Answer, ankit verma

    Ankit Verma: It's a very small project in the overall portfolio because this is 550-megawatt hour. But correspondingly, for other projects that we have, which are 5 gigawatt under construction, that will require installation of around 17 gigawatt hour battery. So it's more just like the small project that you're talking about. It's more like a leasing model wherein you are not putting any generation storage, you're just storing the power, which you are getting from the DISCOM and then you are just discharging the batteries.

    Answer, nikhil dhingra

    Nikhil Dhingra: So those are the bids we have -- it's 1 bid out of the overall portfolio of 8 gigawatt hour. So we are not focusing at all on those bids. And so -- and like Ankit mentioned, the batteries which are part of the overall solar, wind and FDRE mix, the peak power mix, those will be, you can say, 99% of the capex. This is less than 1% of the capex.

  2. Question

    Dhruv Muchhal: So for example if you put an FDRE project Manoj Upadhyay: No, just I would like to add it here that even if you have installed the solar panel, if you are not connected with the battery, for example, if your FDRE -- if your LTA is not right now Page 15 of 20 ACME Solar Holdings Limited May 08, 2026 operational, most of our projects are actually connected with the Brownfield of power grid sub- station.

    Answer, manoj upadhyay

    But the day that COD timeline comes in, LTGA, LTA, grid comes in, the whole thing will get integrated into an FDRE. Nikhil Dhingra: And Dhruv, we are deferring the capex also on the solar side because it is not -- doesn't make sense to call modules at site and keep them here because what we are doing is we are deferring the solar part of capex. We are not installing the modules. We are because, of course...

  3. Question

    Dhruv Muchhal: Got it, sure. And sir, last question is, you mentioned about the commissioning target of your generation assets for this year. But if you can give the number what you're targeting to commission based on -- of generation assets based on whatever transmission visibility you have in megawatt terms?

    Answer, nikhil dhingra

    Nikhil Dhingra: So we are targeting 1.5 gigawatts of projects in this financial year, right, and around 10 gigawatt hour of battery. So this 10 gigawatt hour of battery may be for those projects which are not included in this 1.5 because for 1.5 it will be maybe 5 gigawatt hour, but we are charging the battery ahead of time.

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes. So see, other than the -- you can say around 1,200 megawatt hour to 1,500 megawatt hour, which will be commissioned on the FDRE format because of the Neemuch substation, which I mentioned earlier. Rest of it will start on the merchant basis in this financial year because the substations will get start charging in the fag end of the year only. So you will see around 8.5 Page 16 of 20 ACME Solar Holdings Limited May 08, 2026 gigawatt hour out of this 10 gigawatt hour would be on merchant. And 1.5 gigawatt hour would be in the FDRE format. In terms of the EBITDA realization, Ankit, I'll request you do it.

    Answer, ankit verma

    Ankit Verma: Yes. On the EBITDA margin, look, it's a function of at what cost you are procuring and of course at what price you are selling. But assuming a tariff arbitrage of INR6, which means selling the power at INR8, which of course more than that we are currently seeing and purchasing the power at INR2. So give or take, the margin will be around 75% to 80% EBITDA margin.

  4. Question

    Aanchal Jalan: Yes. So my question is that in the first slide for under construction portfolio, a total of 3,280 megawatt plus 12 gigawatt hour of BESS portfolio is given. So by when will this be completely commercialized, the whole under construction portfolio?

    Answer, ankit verma

    Ankit Verma: Yes. There is a second slide also, which is PPA yet to be signed. But on the PPA signed, yes, so these will be commissioned by FY28. Battery we are putting up early, like Nikhil mentioned earlier.

    Answer, manoj upadhyay

    Manoj Upadhyay: Nikhil, let me take this answer. Yes. Actually, right now, the current calculation of CEA is you need around 200 gigawatt hour of battery to come to this if you don't add any more solar. But what is happening is also another 40, 50 gigawatt of FDRE and this one where the tender has happened, they will get added in the daytime. So technically, what is happening as long as you are adding more and more daytime solar, you need a more battery in the unit. So that's a formula. Right now, that formula tells we need 200 gigawatt hour.

    Answer, manoj upadhyay

    But what has also happened is that the thermal power in the evening, it is already at INR6.5 if you run at full capacity. And most of the capacity thermal power cannot come up fast and cannot go down. So they operate around 60%, 70% capacity. So considering their capital cost, full capital cost in this one, they are around INR9 and INR10. So battery will remain -- my guess is battery will remain at Page 17 of 20 ACME Solar Holdings Limited May 08, 2026 INR9 to INR10 in the peak hour time. And as a country, we will need around 200 to 300 gigawatt hour considering the current installation and the planned installation of this year. But as and when we are adding more and more solar, it will keep on going up.

    Answer, nikhil dhingra

    Nikhil Dhingra: So if you look at the history, if you look at the last few years, we have seen that the annual price remains at around INR7 to INR8 for the last few years, even when we have low demand. In terms of the last few years, we had relatively less demand than before. But even in those slow years, we had a realization for peak power for around 7, 8 years. But now that the gas is constrained, it is slightly elevated, and it is likely to be elevated. And we are seeing some peak demand, which is much, much higher than last year. So we see that like Manoj ji mentioned, at least for around 4, 5 years, we don't see this going down.

  5. Question

    Sweta Jain: That's helpful. Secondly, sir, on -- when you mentioned that majority -- almost 80% of our projects would be on the CTU side of the business, wanted to understand the transmission and distribution angle. Are we facing lag in terms of substation connectivity at the STU level or the CTU level from an industry perspective? And how do you see the projects getting commissioned when we shift the portfolio to this 80% mark that we're looking at?

    Answer, nikhil dhingra

    So till date, they have done a wonderful job of give and take 6 months delay. They have done a wonderful job of coming up with the transmission capacity. And we have also been in sync with that, let's say, a delay of 6 months. We also try and sync our capex and sync our work along with that. As a renewable player, we can't really function without the transmission. So we have to sync up. So there has been a delay.

    Answer, nikhil dhingra

    But for a grid of this size and scale, which is the largest in the world, single grid, I think that has done a good job. So 6 month s delay is, I think, very much -- should be taken in a good light. As far as the STU is concerned, we are not building any projects on STU. The Gujarat project of wind that we did was the only project we have done on the state grid. There is no project in our pipeline other than the battery we are installing on the Andhra Pradesh, very small 550 megawatt hour. Page 18 of 20 ACME Solar Holdings Limited May 08, 2026 There is no project on the state grid. And state grid is a different organization structure.

  6. Question

    Sweta Jain: Got it. And just lastly, so our project blueprints already factor in the 6-month kind of a delay on a nominal basis?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes. So what we -- see, typically, this can't be generalized. This is on a generic overall portfolio level. But some substations, you can say around 60% are on time. The maximum delay is typically 6 months. In some cases, because of some unfortunate event, it could be more. But typically, some -- like I mentioned, our Neemuch substation is on time.

    Answer, nikhil dhingra

    Some substations are delayed. So not every substation is delayed. But wherever it is delayed and we know it from now, we will not call for our modules. We will defer our capex. What we can do about it? I can tell you what we can do about it. We can defer our sizable capex of modules because modules are available just in time and there is sufficient capacity of that available in India.

    Answer, nikhil dhingra

    So we will not call for modules because it's around 60% of a solar plant capex or sometimes more. So you don't do that. You keep the service -related work ready, the transmission line ready, the substation ready because those are typically, you can say, 20%, 25% of the overall project cost. But these are long lead items. So you do that, you don't call your modules. You keep your -- everything else ready. And that's how you defer the capex.

  7. Question

    Sweta Jain: Sir, just one last question. So there is no risk in such cases and on -- there would be no risk in terms of PPAs getting not signed or getting the DISCOMs not eager to sign the PPAs from the developer's perspective?

    Answer, nikhil dhingra

    Nikhil Dhingra: So see, that's a different question. See, in terms of the -- if you don't have a connectivity, there are 2 things on PPA signing bids, right? PPA signing when you go to a DISCOM, they look for what is the declared date of your substation, right? And they look for a declared date of substation getting charged in near term. Page 19 of 20 ACME Solar Holdings Limited May 08, 2026 So if you are somebody who has a substation getting charged in 2027, you will get a better priority from a DISCOM because customers have more visibility to your project, right? Because if there is somebody whose substation is coming up in, if the connectivity he has is for 2029, then he’ll get a second priority. He'll not get a seat at the table, right?

Questions about this call

When was the Acme Solar Holdings Q4 FY26 earnings call transcript filed?
Acme Solar Holdings filed the transcript with the exchange on 14 May 2026. This page is built from that transcript.
What does this page list?
62 statements from the transcript across 9 topics, 34 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 17 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Acme Solar Holdings Q4 FY26 concall: Acme Solar Holdings Limited recently won 1.8 gigawatts of PPAs and has around 850 megawatts of older PPAs in various stages of discussions · DalalOS