Earnings call
Acme Solar Holdings Q2 FY26 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company won new projects aggregating to 720 megawatt capacity during the quarter, comprising a 50 megawatt FDRE project and 670 megawatt solar plus BESS, extending its under construction portfolio to around 4.5 gigawatt, including signed PPA capacity of 2.3 gigawatts. The company plans to operate approximately one gigawatt hour of battery energy storage system on merchant from Q4 FY26 onwards, which is expected to give an upside potential of annual EBITDA of around INR 170 crores, assuming a price difference of INR 5 between merchant power saving during peak hours an; Acme Solar Holdings Limited said 1 gigawatt hour of battery will give around INR170 crores of cash flow. 50 megawatt FDRE project with a private discom effectively is around a battery of around 250 megawatt hour. Operational portfolio stood at around 2,918 megawatts, capable of delivering annual steady state project level EBITDA of INR 2,025 to INR 2,075 crores and an EBITDA yield of around 14%-15%. The company said peak power tariffs of 6.5 and 6.75 can look high on a top-line basis, but require high capital, including batteries and solar to charge them.
The numbers management gave
Results
- Operational portfolio stood at around 2,918 megawatts, capable of delivering annual steady state project level EBITDA of INR 2,025 to INR 2,075 crores and an EBITDA yield of around 14%-15%.
Show source
With recent commissioning, our operational portfolio now stands at around 2,918 megawatts, capable of delivering an annual steady state project level EBITDA of INR 2,025 to INR 2,075 crores, and an EBITDA yield of around 14%-15%.
- Total revenue was INR601 crore in Q2 FY ‘26, a 104% increase year-on-year.
Show source
Moving to our financial performance now, our total revenue for the quarter stands at INR601 crore, a 104% increase year-on-year.
- EBITDA was around INR534 crores in Q2 FY ‘26, up by 108%, with a margin of 89% as against 87% last year.
Show source
So, EBITDA for the whole quarter comes in for us at around INR534 crores, again up by 108% with a margin of 89% as against 87% last year.
- PAT was INR115 crores in Q2 FY ‘26, with a PAT margin of around 19%.
Show source
PAT is at INR115 crores, with a PAT margin of around 19%.
- Net operational debt to EBITDA stood at 4.3x and net debt to net worth stood at 1.9x in Q2 FY ‘26.
Show source
Our net operational debt to EBITDA stands at 4.3x and our net debt to net worth stands at 1.9x.
- Days of sales outstanding dropped to a record low of 27 days as the proportion of central offtake increased in its operational portfolio, giving it a lot of cash flows and a new realization of its revenue.
Show source
Further, the days of sales outstanding has dropped to a record low of 27 days as the proportion of central offtake has increased in our operational portfolio, thus giving us a lot of cash flows, a new realization of our revenue.
Show 8 more statements
Results
- The company generated around 153.9 crore s units in Q2 FY ‘26, up from over 134% year-on-year.
Show source
On the operational metrics, just to wrap up, in quarter 2, we generated around 153.9 crore s units, which is up from over 134% year -on-year.
- The company said the only project impacted by the transmission-line delay is the Sikar project, because of early commissioning, and the impact will be 1.5%-2% on annual revenue; it considers early commissioning overall beneficial.
Show source
Of course, it will have an impact of 1.5%- 2% on the annual revenue, but that is in an overall sense beneficial because of early commissioning.
- Capacity utilization factor improved to 24.1% from 22.2% last year in Q2 FY ‘26, with both plant and grid availability above 99%. Replaced by a later filing.
Money and capital
- The company secured financing of around INR7,000 crores in Q2 FY ‘26 for its 680 megawatt FD RE projects from SBI and REC; buyers credit and LC mechanism will reduce costs on the ongoing rate of greenfield.
Show source
On the greenfield side, we secured financing to the tune of around INR7,000 crores this quarter for our 680 megawatt FD RE projects from SBI and REC, which will reduce our costs on the ongoing rate of greenfield because we will be taking buyers credit and LC mechanism, which is possible with the bank financing.
- 1,100 megawatt of operational projects received a rating of AA-, from ICRA and CRISIL in Q2 FY ‘26.
Show source
It is rated AA-, by both CRISIL and ICRA, which is a very significant positive for us this quarter.
- The company has a target of INR12,000 crores capex, with all capex between 75-25 and 80-20 debt equity; for INR12,000 crores, that is INR9,000 crores debt and INR3,000 crores equity, or INR2,400 crores equity and around 10,000-odd from debt on 20-80.
Show source
Page 16 of 19 ACME Solar Holdings Limited November 04, 2025 So for INR12,000 crores, it will be INR9,000 crores debt and INR3,000 crores equity.
- The company achieved an interest rate reduction of approximately 75 basis points on existing INR2,080 crores debt for its operational projects, driven by the credit rating upgrade. Replaced by a later filing.
- One of Acme Solar Holdings Limited's operational projects was refinanced with INR1,100 crores at an optimized interest rate of around 8.4%, which the company sees coming down further. Replaced by a later filing.
What it expects ahead
What management expects
- The company plans to operate approximately one gigawatt hour of battery energy storage system on merchant from Q4 FY26 onwards, which is expected to give an upside potential of annual EBITDA of around INR 170 crores, assuming a price difference of INR 5 between merchant power saving during peak hours an; Acme Solar Holdings Limited said 1 gigawatt hour of battery will give around INR170 crores of cash flow.
Show source
In addition to our earlier guidance, we plan to approximately operate one gigawatt hour of battery energy storage system on merchant from Q4 FY26 onwards, which is expected to give an upside potential of annual EBITDA of around INR 170 crores, assuming price difference of INR 5 between merchant power saving during peak hours and cost of producing the same.
- The company will always bid for projects with 14%, 15% ROCE.
Show source
So what guidance we can give you is we will always bid for projects with the 14%, 15% ROCE.
- The company anticipated that the Narela K3 connectivity line would be operational by December; after that, the ACME Sikar plant would shift to LTOA and achieve full revenue potential.
Show source
Having said that, the connectivity line is anticipated to be operational by December as per repeated assessments by CTU and of course confirmation at the highest possible level, post which the plant will shift to LTOA, long-term open access and achieve full revenue potential.
- The company expected that, because of the urgency, some of its pending PPAs would be signed earlier and some later.
Show source
So now what is happening is because of this urgency, we will see that some of them will get signed earlier and some of them will get signed later.
- The company expected a maximum delay of a quarter from signed PPA dates for connectivity allotted to its projects.
Show source
So max delay of a quarter from the signed PPA dates is what we are seeing.
- The company said 1 gigawatt hour of battery will give around INR170 crores of cash flow. Replaced by a later filing.
Show 5 more statements
Orders
- The company won new projects aggregating to 720 megawatt capacity during the quarter, comprising a 50 megawatt FDRE project and 670 megawatt solar plus BESS, extending its under construction portfolio to around 4.5 gigawatt, including signed PPA capacity of 2.3 gigawatts.
Show source
This takes our total PPA signed capacity to around 2.3 gigawatts, which we are executing.
- 220 megawatt RUMSL Morena solar park was secured at a tariff of around 2.764 per unit, entailing four hours of peak supply and two hours each in the morning and evening, while maintaining a maximum annual CUF of 35%.
Show source
Firstly, the 220 megawatt RUMSL Morena solar park, this project was secured at a competitive tariff of around 2.764 per unit, entailing four hours of peak supply, and two hours each in the morning and evening, while maintaining a maximum annual CUF of 35%.
- The company won the 450 megawatt SJVN project with peak power, involving an ongoing 2,200 megawatt hour of battery to be installed at 6.75, with peak-hour supply for 4 hours to the off-taker.
Show source
Secondly, the 450 megawatt SJVN project with peak power we won, which is an ongoing 2,200 megawatt hour of battery we will put, at 6.75, this is again a very attractive tariff.
- The company placed new orders for 2 gigawatt hour BESS with global suppliers in Q2 FY ‘26.
Show source
We have also placed new orders for 2 gigawatt hour BESS with global suppliers this quarter.
- Total BESS orders were 5.1 gigawatt hour till date, expected to get installed in a phased manner starting in Q4 FY‘26.
Show source
This takes our total BESS orders to 5.1 gigawatt hour till date, which is expected to get installed in a phased manner starting in Q4 FY‘26.
What it is building and selling
Projects and capacity
- 50 megawatt FDRE project with a private discom effectively is around a battery of around 250 megawatt hour.
Show source
It's with a private discom, a 50 megawatt FDRE, firm and dispatchable renewable energy , which effectively is around a battery of around 250 megawatt hour.
- Capex is around INR 10 crores odd per megawatt for the projects discussed.
Show source
So, in terms of the capex, around INR 10 crores odd per megawatt capex, and 550 megawatt hour of stand-alone BESS projects with NHPC, which of course is with Andhra Pradesh, and these two PPAs were signed.
- The company commissioned a pilot BESS project of 10 megawatt hour at its ISTS plant to assess effectiveness in different configurations, which will help reduce costs and increase efficiency for its FDRE BESS suited projects. ACME Solar’s 10 MWh BESS was operationalized in October 2025 on a pilot basis in Rajasthan and was designed for FDRE/Solar + BESS projects.
Show source
Page 4 of 19 ACME Solar Holdings Limited November 04, 2025 As communicated last quarter, we have successfully commissioned our pilot BESS project of 10 megawatt hour at our ISTS plant to assess the effectiveness in different configurations, which will help us reduce costs and increase efficiency for our FDRE BESS suited projects.
- The company said lower effective prices for batteries and solar, together with a shift to a solar-heavy configuration, reduced required capex, so INR12,000 crores would deliver fairly higher capacity than earlier.
Show source
So, INR12,000 crores number will get us to a fairly higher capacity as compared to the earlier.
- 450 MW of Acme Solar Holdings Limited's capacity is in advanced stages of construction.
Show source
So, our execution guidance for FY26 was to commission 450 megawatts of renewable energy capacity, and we are on track to achieve it.
- ACME Solar Holdings Limited’s under-construction BESS portfolio was 13.5 GWh.
Show source
With these new bids, our total portfolio now stands at around 7,390 megawatt, including 13.5 gigawatt hour of BESS capacity and 5,180 megawatt of PPA signed capacity.
Show 17 more statements
Projects and capacity
- ACME Solar Holdings Limited planned a 300 megawatt Sikar solar plant.
Show source
One key point to note is that because of early commissioning by a quarter and delay in commissioning of one of the connectivity lines, the Narela K3 line, the ACME Sikar project of 300 megawatt hour is currently operating under a temporary GNA / STOA, basically short-term open access.
- The company had lined up battery installations earlier as an additional mechanism to prepone revenue and increase revenue.
Show source
And as an additional mechanism to prepone our revenue, as we mentioned before, we have lined up the battery installations earlier.
- The company said it has been able to increase battery efficiency by reducing capex and generating the same sort of energy.
Show source
By efficiency, I mean reduce the capex and generate the same sort of energy.
- The company said large batteries would start coming up early next month, reducing installation time.
Show source
So, that allows us to reduce the installation time also as we get these large batteries coming up starting early next month.
- The company said tested battery configurations can reduce capex for ongoing projects where various equipment is yet to be ordered.
Show source
And also reduce the bill of material for the future projects because some of the configurations we have tested allows us to reduce the capex for our ongoing projects where we are yet to order various equipment.
- The company said the RUMSL project, where it is getting nighttime power from the customer, gives it more flexibility to try out the battery experiment.
Show source
So, I can tell you, let's say, our RUMSL project where we are getting nighttime power from the customer.
- The company tested batteries in two configurations, and both improved long-term and very short-term discharge.
Show source
We did in two configurations and both the configurations helped us to improve not only the long-term discharge, but also very short-term discharge.
- The company said higher land prices in the Delhi region and an election there raised the prices of the ROW or a land parcel on the transmission line, delaying last mile connectivity.
Show source
Page 18 of 19 ACME Solar Holdings Limited November 04, 2025 So that led to the prices of that ROW or a land parcel in the transmission line, which was falling in the Delhi region, led to delay in that.
Demand and pricing
- The company said peak power tariffs of 6.5 and 6.75 can look high on a top-line basis, but require high capital, including batteries and solar to charge them.
Show source
So I will request you to look at return on capital employed or EBITDA divided by revenue or EBITDA divided by tariff as a metric because all these PPA, let's say the peak power tariff of 6.5, 6.75 looks high on a top line perspective, but the capital requirement is also high.
- The company said it was not seeing lack of state demand for any of its PPAs.
Show source
So we are not seeing in any of our PPAs that there is no demand for it from any state.
- The company said it was not seeing any takerless PPAs because its tariffs were competitive; tariffs for its FDRE with four-hour peak power had not been beaten by any tender, and earlier PPAs were attractive because they had shorter timelines before the ISTS waiver expired, benefiting buyers.
Show source
So we are not seeing that there is no taker for, let's say, any of these PPAs because the tariffs are competitive, like we mentioned and some of them the tariffs have not fallen like in terms of the FDRE with four hour peak power, there has not been any tender which has come up, which has beaten that tariff because we have throughout the spectrum of that.
- The company said ALCM was a benefit to buyers because there was a big difference between Indian modules and the Chinese cell modules.
Show source
And also, there is a benefit of ALCM because, as you know, there is a big difference between Indian modules and the Chinese cell modules.
Deals and partners
- The company signed PPAs with Tata Power for a 50 megawatt FDRE project and 550 megawatt hour of stand-alone BESS projects with NHPC, which is with Andhra Pradesh.
Show source
So, in terms of the capex, around INR 10 crores odd per megawatt capex, and 550 megawatt hour of stand-alone BESS projects with NHPC, which of course is with Andhra Pradesh, and these two PPAs were signed.
- The company said its 10 megawatt hours each have been done using some of the suppliers it is going to work with in the future.
Show source
And these all 10 megawatt hours each have been done using some of the suppliers which we are going to work in the future.
- The company has long-term service agreements for 15 years with the vendors it has signed up for BESS.
Show source
So, in terms of the long-term agreement, like we mentioned last time, we have long-term service agreement for 15 years with the vendors we have signed up BESS for.
- The company had ongoing PPA conversations with four counterparties split equally almost, with consent letters coming or projects at board stage; it was quite advanced with a couple and not advanced with one or two.
Show source
So we have, you can say, with four counterparties split equally almost with all the four counterparties.
- The company said its BESS vendors will have on-ground people and reserves to service the systems and guarantee availability and round trip efficiency.
Show source
So, of course, we are paying them annual maintenance fee also and they will have on-ground people and they will have on-ground reserves to service, to guarantee the availability and the round trip efficiency they have told us.
Risks, rules and outside factors
Rules and policy
- The central government showed increased urgency for states to decide on signing pending PPAs, and bids had been low in the last six months because the government wanted to clear existing projects before new bids.
Show source
So, yes, there is an increased urgency from the central government to basically take a decision for the states to sign the pending PPAs.
- New bids were coming with pre-demand locked in so that PPA signing would not be extended, as the government wanted to realize connectivity utilization and avoid connectivity going unused at the earliest possible time.
Show source
And also, the new bids are now coming with a pre-demand locked in, such that the PPA signing is not extended.
- A new bid would require buyers to pay the whole ISTS charges. Replaced by a later filing.
Show source
Because if a new bid comes, they will surely have to pay the whole ISTS charges.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
And thanks for the opportunity. So, my first question is, do you see any risk of cancellation of the projects where PPA is yet to be signed? Do you see a few of the projects which are under LOA getting PPA in the next couple of months?
Answer, nikhil dhingra
Nikhil Dhingra: Right, right, Mohit. So, yes, there is an increased urgency from the central government to basically take a decision for the states to sign the pending PPAs. And that is why you see in the last six months, the bids have been low because the government wants to clear up the existing projects first before they go for new bids. And also, the new bids are now coming with a pre-demand locked in, such that the PPA signing is not extended. Because as far as government is concerned, they want to realize the connectivity utilization. They want to improve the connectivity utilization such that there is no connectivity which is not utilized in the earliest possible time. So that's a wastage of national resource.
Answer, nikhil dhingra
So as far as our signing is concerned, we have attractive tariffs across hybrid, across FDRE. And we have ongoing conversations where either the consent letter is coming or the project is at a board stage. So we have, you can say, with four counterparties split equally almost with all the four counterparties. So we are quite advanced in a couple of them. And, of course, we are not advanced in one or two of them. So now what is happening is because of this urgency, we will see that some of them will get signed earlier and some of them will get signed later. But if there is a decision taken to basically, let's say, but our tariffs are attractive.
Answer, nikhil dhingra
So we remain confident because the directive is not to do the legacy PPAs which are not finding any takers. So that sort of determination of no demand. So we are not seeing in any of our PPAs that there is no demand for it from any state. There is a demand for the state. But the procedure is a multi-legged sort of procedure at the state where first Discom and then regulatory commission approves. So we are in discussion with all the DRs, wherever we have got. And fortunately, in our cases, there is a demand from states.
Answer, nikhil dhingra
So we will, as soon as we have clarity on any of these, we have no negative confirmation from anything that they are not finding because we are personally also in touch with most of the states. So we are not seeing that there is no taker for, let's say, any of these PPAs because the tariffs are competitive, like we mentioned and some of them the tariffs have not fallen like in terms of the FDRE with four hour peak power, there has not been any tender which has come up, which has beaten that tariff because we have throughout the spectrum of that. And what makes the earlier ones slightly attractive is that they are coming up in shorter timeline where ISTS waiver is not expiring. So there is a benefit to the buyer if they buy that. Because if a new bid comes, they will surely have to pay the whole ISTS charges. And also, there is a benefit of ALCM because, as you know, there is a big difference between Indian modules and the Chinese cell modules. So these are the benefits which are appealing.
Answer, nikhil dhingra
Now, the only thing is it's up to the states to take early decisions and given that we are now picking up on the energy demand. We are hopeful Page 6 of 19 ACME Solar Holdings Limited November 04, 2025 that some of the large states will take up early decisions. So that's where we are on the PPA timeline.
Question
Mohit Kumar: Yes, understood. The second question is on the transmission issues. It seems like the transmission projects are facing a lot of issues in terms of commissioning. How do you see the risk to the under-construction project which can delay our commissioning timeline?
Answer, nikhil dhingra
Nikhil Dhingra: Sure. So we assess this every fortnight in terms of the connectivity timelines of the substations where our projects are coming up. So just to give you some examples, we like Fatehgarh substations. There are STOA available so we can evacuate power from the STOA. And you look at Neemuch, you look at Bikaner 3, they're all coming within the timeline. At max, one to three months kind of timeline delay and they are all within the PPA. Like Neemuch plant of ours, which we have signed up with Damodar Valley Corporation through NHPC.
Answer, nikhil dhingra
So that is actually coming up early because the Neemuch connectivity is operational. It depends on the choices of substation you allotted to that PPA and whether that is coming on time or not. So what we do is the PPA, which has been signed and what our best connectivity is, which are well within the timeline of that PPA. So max delay of a quarter from the signed PPA dates is what we are seeing. And as an additional mechanism to prepone our revenue, as we mentioned before, we have lined up the battery installations earlier. So that's a separate point, but that is something we are doing on top of this to increase the revenue. But connectivity-wise, from our PPA timelines, we are not seeing delay more than a quarter in the allotted connectivity.
Answer, nikhil dhingra
It is also a function of whether you have taken the liberty of allotting connectivity, which are getting delayed and using the maximum possible time allowed in the PPA or you are looking for early commissioning. And also the inventory of the connectivity available with each and every sort of player. So as far as we are concerned, we have quite a lot of connectivity coming up at various timelines in ‘26. So that gives us a lot of flexibility wherever and we have taken connectivity with flexibility, basis Land and basis bank guarantees, which allow you to allocate the connectivity across PPAs. And very little connectivity we have basis letter of award, which kind of lock you in. So that's through our allocation and connectivity inventory, we have been able to address, let's say, if there are delays, then they are allotted to later PPAs. Mohit Kumar: Understood, sir.
Answer, nikhil dhingra
Nikhil Dhingra: Sure, Bala. Thanks for inquiry. So, see, in renewable sector because the kind of bids is very dynamic. So I will request you to look at return on capital employed or EBITDA divided by revenue or EBITDA divided by tariff as a metric because all these PPA, let's say the peak power tariff of 6.5, 6.75 looks high on a top line perspective, but the capital requirement is also high. So I would not compare, I would not do a weighted average of tariffs to realize whether everybody is going up or not, because it is also because it takes a lot of batteries there, it takes a lot of solar there to charge. So the weighted average tariff is sometimes misleading, unless you adjust that for capex. And unless you adjust that for what is the component of that, because each source either generates or stores.
Answer, nikhil dhingra
So wind, as you know, sometimes generates higher CUF in certain geographies where the capex is slightly higher. The battery is storing and realizing the benefit of the peak power. So, of course, the tariff has gone up, but the configuration of PPA is also important. What are you giving there? Let's say somewhere you have a leased kind of a project where you are giving lakh per megawatt of, let's say, 2.5, 2.2 lakh odd megawatt monthly. So the market has got slightly more varied for us to do a weighted average tariff analysis. Of course, for estimating our revenue and capex, but revenue should be looked at with capex.
Answer, nikhil dhingra
So what guidance we can give you is we will always bid for projects with the 14%, 15% ROCE. That is something we really want to stick to, but tariff and revenue, I would request you to not look at it on a standalone basis. Balasubramanian: Okay, sir. Sir, on that BESS side, I think we have operational 10 megawatt hour pilot with two different container configurations. What are the key learnings regarding efficiency in terms of round-trip losses, degradation rates and operation reliability? Why I'm asking this question earlier, we have our decision to import complete BESS containers which is prioritized reliability over cost. Just want to know about the key learnings.
Answer, nikhil dhingra
Nikhil Dhingra: Right. So, see, we have a mix of technical and contractual reasons to basically prepone the battery capex like we explained the last time and before last time. So, the contractual reason is that it allows us to capture the arbitrage between the peak power prices and the solar prices prevailing. Page 8 of 19 ACME Solar Holdings Limited November 04, 2025 So, you can use solar to charge or lower rates to charge the batteries and sell it on the merchant. So, that makes a compelling business sense. And, of course, the capex is well within, much below the range we targeted when we had bid for these projects. So, that makes the commercial part of the decision about getting the batteries early.
Answer, nikhil dhingra
In terms of the technical part, we, of course, have been operating battery in the group on the Green Ammonia side for the last four or five years. But here we were trying to, let's say, work out the various combinations of the PCS, of the battery management system, of the inverters, how we can operate with a particular equipment, without a particular equipment. So, we are pleased to say that we have been able to increase the efficiency. By efficiency, I mean reduce the capex and generate the same sort of energy. And also, basically, get the reliability in terms of the round trip efficiency numbers which we have contracted and in terms of the discharge rates we have contracted and we have bought. And these all 10 megawatt hours each have been done using some of the suppliers which we are going to work in the future. So, that allows us to reduce the installation time also as we get these large batteries coming up starting early next month.
Answer, nikhil dhingra
So, it allows us to reduce the installation time, not any sort of surprises we may get in terms of the various equipments. And also reduce the bill of material for the future projects because some of the configurations we have tested allows us to reduce the capex for our ongoing projects where we are yet to order various equipment. So, it has been quite successful. And, of course, it will help us because in some projects you need to charge only batteries so you have a little more headroom. In some projects you are installing batteries where solar is already installed so it gives you less headroom. So, I can tell you, let's say, our RUMSL project where we are getting nighttime power from the customer. So, that gives us some more flexibility to try out this experiment.
Answer, nikhil dhingra
So, it is dependent on the configuration of the PPA where you can apply some of these tests we have done. So, we will apply each and when and this allows us to improve our convictions on those configurations. So, in terms of the long-term agreement, like we mentioned last time, we have long-term service agreement for 15 years with the vendors we have signed up BESS for. So, of course, we are paying them annual maintenance fee also and they will have on-ground people and they will have on-ground reserves to service, to guarantee the availability and the round trip efficiency they have told us. And, we have done the factory test in both of our vendors we have done the factory test also with the required levels of efficiency. So, before the dispatch from the third party. So, they are in the range and they are now getting logistics.
Answer, manoj upadhyay
Manoj Upadhyay: Nikhil, let me also reply. Here, my name is Manoj. Let me give you one more reply that we were testing the battery for the EMS requirement where we wanted to see that how the battery will behave in the various conditions of discharge, not only what is given in the PPA, but also in the support of if we need the battery for what is called ancillary support in the afternoon or in the morning for short time. Page 9 of 19 ACME Solar Holdings Limited November 04, 2025 So, we were testing and it was a very successful test. We did in two configurations and both the configurations helped us to improve not only the long-term discharge, but also very short-term discharge. That was the first. And, second question I think what you had is whether the round- trip efficiency is okay what we have taken in the bid.
Answer, manoj upadhyay
Fortunately, we were able to improve by 4-5% of the round-trip efficiency because of these configurational adjustments. So, what we wanted to achieve I think with these two golden containers. We call it golden containers because they come first and we do the whole installation testing. And, with that we are able to ascertain what we have bided and beyond that some of those improvements which Nikhil mentioned we could achieve it. Balasubramanian: Okay, sir. So, my next question, I think we have refinanced nearly 1,100 crores to 8.4%. So this is a fixed rate or floating rate and what is the average debt tenure and is there any significant near-term bullet repayments are there?
Answer, nikhil dhingra
Nikhil Dhingra: Right. So, all of our debts which we have refinanced is for a tenure of 20 years average because that is what we have done. And in terms of interest rates, we are effectively getting a rate of around 8% because it is linked to MCLR plus 10 basis points spread. That is the typical rate we are getting. Of course, because the rating upgrades have happened. In this project where we have reached 8.4%, it is shortly likely to be reduced to 8%. And that is the rate we are seeing in all of our refinancings for a AA asset from bank financing.
Answer, nikhil dhingra
If we go for a bond financing, we could catch maybe a better effective rate. But of course, because of the pre-payment fees and because of the short-term nature of mutual funds and financing because typically mutual fund players are only there in bonds. Insurance is currently not very highly present for the long-term, where infra-debt funds are typically fund spreading along with banks in the long-term only. So, we are able to capture them in the bank financing. So, 8% is the typical rate for all the refinances and we are hopeful that we will get all of our portfolios, whichever can be refinanced closer to that rate. And that is a significant upside for us, because -- and this is all floating to your other question. It is floating because we are able to capture the downside in the interest rate -- the down cycle in the interest rate.
Answer, nikhil dhingra
We have, of course, done one refinancing last quarter which we did with Bank of America. That was on an NCD. So, that was fixed at around 8.5% which we achieved last quarter. So, that is one fixed. So, we maintain a proportion of fixed and floating. So, some of the projects which are coming up for refinancing, we will try and see if we can get a longer term bond. Because a three-year tenure, we can do.
Answer, nikhil dhingra
But we are just going to take a decision about that in terms of the economics of it because it requires you to refinance at a shorter interval. Page 10 of 19 ACME Solar Holdings Limited November 04, 2025 In terms of the payments come up, there is no payment which is not backed by a refinancing sanction in place. So, we have refinancing sanctions in place for whatever is coming up for refinance.
Question
Ketan Jain: Yes. Sir, it is a follow-up for the first question. There was a media article saying that out of the 93-gigawatt of capacity awarded in FY ‘24 and ‘25, 42-gigawatt is still pending to be signed. PPA is pending to be signed and they are planning to cancel these awards and re-bid these awards. How do you think this will impact the industry and how does it impact our projects? Are these only solar projects which they will cancel or even the complex and FDRE projects are in the risk of getting cancelled?
Answer, nikhil dhingra
Nikhil Dhingra: Right. Right. Sir, you are right. So, basically, their target is primarily the solar projects which have been bid, and because they were bids very long back also. And like you know that the government has come up with guidelines that no project should come up without storage on a central bid and that is no longer happening, because storage is now a key part of all the upcoming bids. So in terms of the take-up at the states of these capacities, so there has been a lot of traction in the last three months to six months about the improvement in the PPA signing. Like, SECI has effectively around 6-6.5 gigawatts of PPA left and same -- and the status with the others are also kind of.
Answer, nikhil dhingra
So these 42 gigawatts may have gone down. I think if you look at some numbers, they would have gone down. And the other thing is the regime under which they have been done, that is also sometimes very, the states also like that, what plan is coming up with what timeline it allows them to give ISTS waiver or not. So these -- and if you look at it, these are significant commitments for the state. Each of these projects will have a revenue of at least $100 million or something if you look at the overall bid and maybe in some cases more than $200 million if you look at the 1.5-gigawatt bid. So significant decisions for the state. Of course, the bids were done in a quick time, and of course, the inventory clearance takes time.
Answer, nikhil dhingra
But like the mandate from the government is to -- for the states to make a decision. And of course, if there is no demand, let's say, if somebody is saying that they don't want to buy a plain solar, right? They basically have no demand for pla in solar, because if they had surplus solar in some states, they will basically - But some states still have demand. You see some of the states are not reaching renewables themselves and they have some shortage. And of course, they are looking at some bids where they call batches in their state at each substation. Page 11 of 19 ACME Solar Holdings Limited November 04, 2025 So we are quite hopeful that this will find takers. It's a matter of time.
Answer, nikhil dhingra
And of course, it's a matter of government policy whether they -- I think each REIA will take their own decision in terms of each PPA. So, it will not be a very uniform that out of 40, 20 have been cancelled or something. For a government, the decision is about not letting the connectivity go waste. So all this is coming up from the point of view of, if, let's say, somebody is sitting with an LOA. Their dates have expired for that connectivity. But still they are hanging on to that LOA, neither building the plant. So, that is a scenario government effectively wants to avoid as per my reading and that is something which you will see most likely this will converge towards.
Answer, nikhil dhingra
So not to basically -- whenever there is a dialogue going on, whenever there is a probability of something happening, I think, the time will be given. And whenever somebody is putting up a plant in anticipation and there is a fair progress towards building the plant, those will be allowed to continue and there will be -- so that's how we are thinking about it.
Question
Ketan Jain: Understood. Just in our under construction projects, these -- there are two solar projects for which I think PPA has not been signed. One is ACME Sigma Urja and ACME Omega Urja. This is 300-megawatt, one with NTPC and one with SJVN. What is the status on these projects? One of these projects is not there in the current presentation. Are these at the risk of cancellation, sir?
Answer, nikhil dhingra
Nikhil Dhingra: So, this NTPC project, I think we had updated a couple of months back that, it was done in a pooling mechanism with NTPC. I think there was -- we had announced to the stock exchanges also. So, that project, because the pooling scheme has been cancelled by Ministry of Projects. Basically, they were pooling thermal with renewable. The NTPC itself was doing that on their own plants. But I think that is under litigation with Bengal. So, that project is, of course, that is why… Ketan Jain: Understood.
Answer, nikhil dhingra
Nikhil Dhingra: That scheme itself is not there and that we had announced a couple of months back. But that is a special case. That 2.52 with SJVN, that is under consideration, because that is under consideration with some states which need that because it is the most competitive tariff in terms of the solar. Now, the decision is how they use that solar is up to states. So some of the states have shown interest. If you notice, you can basically track these all PPA things through tariff filings. So, if you look at… Ketan Jain: Right.
Question
Ketan Jain: Okay. Understood. Understood. Understood.
Answer, nikhil dhingra
Nikhil Dhingra: What -- so, you will get to know which all states have signed, which all states have got tariffs. So, if you look at this specific solar side, you look at Punjab which has recently bought a 2- gigawatt of solar, right? And they want -- that shows that they can want more. So, they are putting it up to the regulatory commission. So, because it is a multi-state process. Page 12 of 19 ACME Solar Holdings Limited November 04, 2025 So, some states have something like Punjab as a particular demand. Even in summer, they need peak power for their agricultural load.
Answer, nikhil dhingra
So, there are some states, specific states which need that power. That is why SJVN is trying, SJVN is looking at and some states have called bids like Madhya Pradesh was considering it. They have called -- and they have filed it in the tariff also. But what happens is sometimes they call their own bids. So it is a function of each state. So, I would not say this is a low probability. This can get signed.
Answer, nikhil dhingra
We have to go and it is a state-by-state situation.
Question
Ketan Jain: Understood. Just the last question, book-keeping question on capex. I think we have spent around INR1,400 crores in first half. Our target was around INR12,000 crores to INR14,000 crores. Are we on track for that at capex?
Answer, nikhil dhingra
Nikhil Dhingra: See, we have ordered batteries. Like we told you, we have ordered around 5-gigawatt hour of batteries. So, LCs have been opened. You cannot account for the capex in the balance sheet until the goods have arrived. So, it is very, very lumpy. Like the batteries arrive, you will see this capex doubling or increasing, because a battery typically around a INR1 crore or so once it is fully installed in terms of the capex. So, INR5,000 odd crores of capex will be done once we have done with this 5-gigawatt hours of batteries which are coming up in phases starting from January onwards.
Answer, nikhil dhingra
So, INR5,000 crores on batteries, you can say the modules of course are the last item to come. They are typically 50% to 60% of the overall capex now with Indian modules. So, that is also lumpy, right, because that -- like the plants which are getting commissioned in June, you will see that modules start coming in January to February there. So, modules for, you can say, around 1-gigawatt - 1.5-gigawatt which is targeted around June. So, you will see that that will again have a significant capex on them. So, INR12,000 crores may get split to June. But I think we are by and large there in terms of the capex plan and we have given orders which are in sync with the INR12,000 crores.
Answer, nikhil dhingra
The delivery timelines are on track like battery has got preponed. Like I said in the connectivity answer that a quarter of connectivity delay may be there. So, a quarter of capex delay may be also there at max.
Answer, nikhil dhingra
Nikhil Dhingra: Right. Thanks a lot for the question. So, see, non-solar connectivity is a very significant GNA amendment which has come and it is basically aimed at utilizing the connectivity which is operational but not to be utilized because of the intermittent nature of renewable and because of, let's say, 6-8 hours of operation of solar. Page 13 of 19 ACME Solar Holdings Limited November 04, 2025 So, it allows you to basically put up a plant, a pure plant which generates clean non-solar hours. So, you can put up solar there and you can put up batteries there to charge. The solar is charging that battery and you can basically discharge during any of the non-solar hours and you can also send that solar output after, let's say, even the solar you have put up to charge battery. That can also supply through that connectivity if there is a room available in that connectivity because the solar goes like a sinusoidal wave.
Answer, nikhil dhingra
So you have --that is a non-solar hour connectivity. You can use the output of that solar when you are not charging the batteries to supply through the grid through that connectivity. So, the aim is basically to use the connectivity to the maximum possible extent and that is where these guidelines really help. And also they have allowed you to charge it from the batteries from the grid. If somebody doesn't want to put solar to charge the batteries, they can draw power from the grid. They are allowed through this mechanism that has also been done in this amendment like we mentioned in the introduction. So, these are the ways in which you can use connectivity.
Question
Yogesh Patil: Thanks for taking my question, sir. As you explained the capex details for FY '26, but can you give us some funding details in terms of the data and equity portions for FY '26 capex and next year also based on your operating cash flows?
Answer, nikhil dhingra
Nikhil Dhingra: Right. So, in terms of the capex, like, we have a target of INR12,000 crores capex like we discussed. So, all of our capex is between 75-25 to 80-20 debt equity. Lately, we have been getting 80-20 and debt sanctions. But typically, historically, it has been 75-25 debt equity. Page 16 of 19 ACME Solar Holdings Limited November 04, 2025 So for INR12,000 crores, it will be INR9,000 crores debt and INR3,000 crores equity. And on 20-80, it will be basically INR2,400 crores equity and you can say around 10,000-odd from debt.
Question
Yogesh Patil: Just follow-up on that side, considering the INR12,000 crores kind of a capex in FY '26, our operating cash flows are not such as strong enough to support the INR12,000 crores kind of a cash flow. In that scenario, we will utilize our cash of INR3,000 crores which are already in the balance sheet. But for next year, from where we will get the equity portion? Because the next year also in FY '27, we are planning a INR12,000 crores to INR13,000 crores kind of a capex. And to manage that 30% or 25% of the equity to fund that capex. So, just wanted to understand on that side, if you could be a little bit elaborate on that side?
Answer, nikhil dhingra
So, if you analyze it, that is the annual cash flow we generate, right, on this side. And as you do, let's say, an 8% to 10% margin, which is on the EPC side, that will also generate some cash flows from the -- from that organic cash flow generation. Plus, of course, the debt reduction will further, the interest rate reduction will further aid into that cash flows. So, and in terms of the capex itself, right, the INR12,000 crores number will allow us to do more projects because the effective rates of the prices of the things have reduced in terms of battery, Page 17 of 19 ACME Solar Holdings Limited November 04, 2025 in terms of solar. And of course, we have shifted to solar heavy configuration like we have told you earlier. So that has also reduced the capex required to be done. So, INR12,000 crores number will get us to a fairly higher capacity as compared to the earlier.
Answer, nikhil dhingra
So, we think that in terms of the equity drawdown, because of -- and the battery, like we mentioned, 1 gigawatt hour will give us around INR170 crores of cash flow. So that is another early sort of revenue generation, which will help us improve the numbers we told you from the past profitability.
Question
Akash Mehta: Yes. Hi. I just wanted to understand on the bid curtailment front. I just want to clarify, actually, that is it only related to, I mean, is it related to demand? Is it related to the, I mean, the transmission lines not being available on time or, I mean, and what kind of capacity is exposed to such issues going ahead and in the current quarter, last quarter gone by?
Answer, nikhil dhingra
Page 18 of 19 ACME Solar Holdings Limited November 04, 2025 So that led to the prices of that ROW or a land parcel in the transmission line, which was falling in the Delhi region, led to delay in that. So it is mostly because of transmission line and the only project in which we are impacted is this Sikar project and that is because of early commissioning and we are better off doing it early commissioning than not. We do the ma th, are we better off or not, and then we are overall better off doing it early commissioning. Of course, it will have an impact of 1.5%- 2% on the annual revenue, but that is in an overall sense beneficial because of early commissioning.
Questions about this call
- When was the Acme Solar Holdings Q2 FY26 earnings call transcript filed?
- Acme Solar Holdings filed the transcript with the exchange on 10 Nov 2025. This page is built from that transcript.
- What does this page list?
- 51 statements from the transcript across 8 topics, 33 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 9 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.