Earnings call

Adani Green Energy Q2 FY26 earnings call: Adani Green Energy has LOAs for hardly 4-gigawatt that are going to be converted to PPAs

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company has LOAs for hardly 4-gigawatt that are going to be converted to PPAs. The company remains on track to achieve its targeted 50 gigawatt capacity by 2030. The company added 2.4 gigawatts of greenfield capacity in H1- FY26, equal to 74% of its total capacity addition in entire FY25. Energy sales rose 39% year-on-year to 19.6 billion units in H1 FY26. The company is currently talking of solar tariffs of $0.03 or less.

The numbers management gave

Results

  • Energy sales rose 39% year-on-year to 19.6 billion units in H1 FY26.
    Show source
    Our energy sales rose by an impressive 39% year-on-year, reaching 19.6 billion units.
  • Renewable energy capacity expanded 49% year-on-year to 16.7 gigawatts in H1 FY26.
    Show source
    Our renewable energy capacity expanded by 49% year-on-year to 16.7 gigawatts, solidifying our position as India's largest and fastest-growing pure-plate renewable energy company.
  • Revenue from power supply increased 26% year-on-year to INR6,088 crores and EBITDA grew 25% to INR5,651 crores in H1 FY26.
    Show source
    Revenue from power supply increased by 26% year-on-year to INR6,088 crores, and EBITDA grew by 25% to INR5,651 crores.
  • EBITDA margin was 92% and cash profits rose 17% year-on-year to INR3,094 crores in H1 FY26.
    Show source
    Our EBITDA margin remains best-in-class at 92%, and cash profits surge by 17% year-on-year to INR3,094 crores.
  • Average solar merchant realization was INR2.1 per unit plus INR0.35 per unit from RECs.
    Show source
    So that is another INR0.35 per unit.
  • Wind merchant realization was INR5.13 per unit plus the RECs.
    Show source
    And from wind perspective, it is INR5.13 per unit plus the RECs.
Show 9 more statements

Results

  • About 35% of Adani Green Energy's merchant capacity was wind, which helped boost overall merchant realization.
    Show source
    So from that aspect that is how the -- so on an average because we have about 35% of wind as our merchant capacity.
  • Capacity addition in H1 was more or less 74% and close to 75% of what it did last year.
    Show source
    We have been, let me again say that we did -- the company did more or less 74% and close to 75% of what it did last year.
  • Curtailment had a total impact of less than 5% on Adani Green Energy's generation in this quarter.
    Show source
    Ashish Khanna: So we have already mentioned that this total impact is actually less than 5%.
  • The average merchant price for Adani Green Energy's solar was INR2.1 per unit and for wind was INR5.13 per unit in the current six months.
    Show source
    Saurabh Shah: For the current six months, the average merchant price for solar was INR2.1 per unit, and for wind, it was INR5.13 per unit.
  • About 34% of Adani Green Energy's merchant capacities were wind merchant in the current six months.
    Show source
    And within the merchant capacity, about 34% of our capacities Page 16 of 19 Adani Green Energy Limited October 29, 2025 are wind merchant.

Money and capital

  • The company planned 5-gigawatt of capacity this year, translating into capex of about INR30,000 crores; 2.4-gigawatt had been achieved and the corresponding capex spent.
    Show source
    Saurabh Shah: So see, from capex perspective, we are the voice for 5-gigawatt of capacity this year, which will translate into a capex of about INR30,000 crores, of which 2.4-gigawatt has been achieved.
  • Net debt to run rate EBITDA was 4.4 times for operational assets and 5.1 times including under construction debt.
    Show source
    Saurabh Shah: So see from a leverage perspective, from a net debt to EBITDA, which we track on a continuous basis, net debt to run rate EBITDA, we, from an operational asset perspective, we are at 4.4 times of net debt to run rate EBITDA.
  • Overall gross block was about INR1.1 lakh crores including CWIP at the end of H1 FY ‘26.
    Show source
    Saurabh Shah: So, in terms of rupees, the overall gross block is at about INR1 lakh crores, INR1.1 lakh crores on the including the CWIP.
  • Gross block was INR94,000 crores plus CWIP of INR16,000 crores for under-construction projects at the end of H1 FY ‘26.
    Show source
    Without CWIP on a gross block, very specific basis, it is INR94,000 crores plus a CWIP of INR16,000 crores which is to be added to that in terms of under construction projects.

What it expects ahead

What management expects

  • The company remains on track to achieve its targeted 50 gigawatt capacity by 2030.
    Show source
    We remain firmly on track to achieve our targeted 50 gigawatt capacity by 2030.
  • The company expected another 2.5 gigawatt or more of evacuation in H2.
    Show source
    We do expect another 2.5 gigawatt or more than that coming in this particular H2 of further evacuation.
  • The company expected close to 17 gigawatt of capacity from Khavda over the following 9 months.
    Show source
    And in totality, if you look out another 9 months, we are expecting somewhere close to 17 gigawatt of capacity coming from Khavda itself.
  • The company expected annual capex of INR30,000 crores to INR35,000 crores for the next two years, with execution plans in a similar range or possibly higher.
    Show source
    From a perspective of next two years, the range would be in that same INR30,000 crores to INR35,000 crores of capex to be done each year.
  • The company expected net debt to run rate EBITDA to remain between 4 times and 5 times for another two years to three years because of continuing capex.
    Show source
    So from that aspect for another two years, three years, because of the kind of capex that we are continuing to do, we will be in the range between 4 times to 5 times of net debt to run rate EBITDA and continue to be there around that.
  • Net debt to run rate EBITDA was expected to start reducing drastically from ‘29 onwards as capex came online.
    Show source
    But as we get closer to ‘29 onwards, the number will drastically start to reduce because the capex would have all come on online.
Show 7 more statements

What management expects

  • The company expects overall capacity utilization to be 100-basis-point to 200-basis-point more than last year.
    Show source
    But we are definitely expecting 100-basis-point to 200-basis-point more than last year.
  • The company expected operational EBIT and run rate EBITDA to continue growing faster than debt impact.
    Show source
    And that number of operational EBIT number and the run rate EBITDA will continue to grow higher than the debt impact.
  • Khavda site will play a role in enhancing the CUF of its overall capacity because Khavda has a much better CUF of solar compared to other sites.
    Show source
    It is also coming from the fact that our site at Khavda will play a decent role in also enhancing the CUF of the overall capacity.
  • The company expected that challenges would generally be limited to a month or two at most in a quarter. Replaced by a later filing.
    Show source
    Now, with these in place, we do not foresee there will be always a challenge of a month or two at max a quarter here and there.
  • The company foresees more round the clock power and peak power coming from renewable. Replaced by a later filing.
    Show source
    And we do foresee more and more of round the clock power, our peak power type which is coming from renewable.
  • The company is on track with its strategies towards storage, whether BESS or PSP. Replaced by a later filing.
    Show source
    And like we said, we are also on track for our strategies towards the storage part, whether it is BESS or PSP.

Orders

  • The company has LOAs for hardly 4-gigawatt that are going to be converted to PPAs.
    Show source
    Conversion of the current tender, yes, we are blessed not to have many, hardly 4-gigawatt is where we have our LOAs which are going to be converted to PPAs.

What it is building and selling

Projects and capacity

  • The company added 2.4 gigawatts of greenfield capacity in H1- FY26, equal to 74% of its total capacity addition in entire FY25.
    Show source
    In H1- FY26, we set a new milestone by adding 2.4 gigawatts of greenfield capacity.
  • The company was developing a 7.1 gigawatt solar, wind, and hybrid renewable energy plant at Khavda, Gujarat, with 661 megawatt of group projects already in operation.
    Show source
    We are making steady progress in the development of the world's largest renewable energy plant at Khavda, Gujarat, with a 7.1 gigawatt solar, wind, and hybrid assets, including 661 megawatt of group projects already in operation.
  • The company said evacuation challenges were less than 5% of its total effect at the time of the call.
    Show source
    But like we said, in the current context, there has been a challenge, but that is hardly less than 5% on our total effect as we speak right now.
  • 500 megawatts of PSP at Chitravathi was about 57% completed in terms of physical progress, with an overall project cost of about INR2,600 odd crores.
    Show source
    It is about 57% odd completed in terms of physical progress.
  • Project cost was around INR5.1 crores to INR5.2 crores per megawatt.
    Show source
    Ashish Khanna: So if you look at it, Puneet it is coming at a cost of around INR5.1 crores to INR5.2 crores per megawatt.
  • Larger project of 1800 megawatts was more cost effective than the smaller project being discussed.
    Show source
    Since it's a smaller project our larger project of 1800 megawatts, they're even more cost effective on that.
Show 8 more statements

Projects and capacity

  • Rajasthan hybrid included 500 plus megawatt of wind and 600 plus megawatt of solar on 700 megawatt.
    Show source
    Raj Kumar Jain: And Puneet, just further elaborating on what Viral was saying, so we have a very intense hybrid when it comes to Rajasthan, where on the 700 megawatt we have 500 plus megawatt of wind and 600 plus megawatt of solar.
  • The company had 17-gigawatt of operating capacity and was continuously constructing 4-gigawatt to 5-gigawatt.
    Show source
    Today we are at 17- gigawatt of operating capacity, we are doing 4-gigawatt to 5-gigawatt of construction on a continuous basis.
  • The company expects around 10-gigawatt of capacities to be evacuated in Khavda by the end of this year.
    Show source
    We do expect, say in Khavda, by the end of this year, around 10-gigawatt of capacities to be evacuated.
  • The company is looking at 5 gigawatts for its project, and that is its commitment.
    Show source
    Ashish Khanna: With respect to our project, we are looking at 5 gigawatts.
  • New hybrid projects were being set up according to the requirements of their respective PPAs, without the same intensity of solar and wind as its Rajasthan hybrid.
    Show source
    The new hybrids which we are setting up are as per the requirements of the respective PPAs where such intensity of solar and wind is not there.

Demand and pricing

  • The company is currently talking of solar tariffs of $0.03 or less.
    Show source
    We are currently talking of $0.03 or less than that on a solar basis.
  • The company is seeing a shift from pure play solar and pure play wind to peak power tenders where storage plays an important role.
    Show source
    We are also seeing a shift coming from a pure play solar, pure play wind to now a peak power type of tender where the storage is playing an important role.

Deals and partners

  • The company had LOAs of more than 4 gigawatts to be converted into PPAs and around 27 gigawatts in PPAs.
    Show source
    Ashish Khanna: I think on an overall basis, as we see, today we have LOAs of more than 4 gigawatts with us to be converted into the PPAs.

Risks, rules and outside factors

Rules and policy

  • The company may import Chinese modules for bids that happened prior to somewhere early ‘21.
    Show source
    Raj Kumar Jain: So, Nikhil, the way the law of the land is, the bids which happened prior to somewhere early ‘21, we are allowed to import Chinese modules.
  • The company requires ALMM for plants commissioned after 1st April 2024 when the bids happened after early ‘21.
    Show source
    The bids which happened after that, there we have the requirement of ALMM after, if those plants are commissioned after 1st April 2024.
  • The government has introduced an ALCM requirement for projects commissioned after 1st June 2026.
    Show source
    Recently, the government has introduced the requirement for the ALCM for projects which are commissioned after 1st June 2026.
  • Merchant projects commissioned from 1st of April 2024 until 1st June of 2026 can import cells from outside India.
    Show source
    All merchant projects which we are doing from 1st of April 2024 until 1st June of 2026 would need – can import cells from outside India.
  • For projects whose bids were concluded a few months back and which are commissioned after the applicable period, Adani Green Energy needs ALCM, which means cells have to be done in India.
    Show source
    So, any merchant -- any projects for which the bids were concluded few months back and where the ALCM require -- where the -- after that period, whatever the bids are there, they – there we need to have ALCM, which means cells have to be done in India.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Anuj Upadhyay: Yes. Hi, sir, and congratulations on a good set of numbers. My first question on the capacity expansions. In the first half, we have already commissioned 2.4 gigawatt and we had guided for 5 gigawatts addition in the first – second half, which is generally considered to be a strong period. So, any probability where we can scale up our guidance for the full year? And second question is related to the evacuation challenges. If you can throw some light how those challenges are placed as of now, which again gives us a confidence of adding 5 gigawatt plus kind of a capacity?

    Answer, ashish khanna

    Ashish Khanna: Thanks, Anuj. I think we are committed to the 5 gigawatt. And I think we would like to first achieve that before saying anything else on the future capacity. There always has been challenges, which I think our team has done a phenomenal job in the first half of this year in spite of heavy rains. And in between, we also have a wall in this particular H1. And we have been on track to achieve 5 gigawatt more, 5 gigawatt in this year. And if there is anything which can be done beyond it, we will come back to you.

    Answer, ashish khanna

    But currently, we are directionally wholly committed to definitely achieve 5 gigawatt in this financial year. Regarding the challenges with respect to evacuation, I think you have to appreciate the fact that these evacuations does not come in a 250 megawatt or 750 megawatt tranches. It comes generally in a 3 gigawatt or 5 gigawatt tranches or 2.5 gigawatt tranches. So, if you map, if you time that across, then either you first wait for that evacuation to be there and then you build your asset or you build it in a time where you are more or less there when this evacuation comes and take advantage from day one of the same. In the current context, yes, there have been certain delays from the anticipation which we had and we map it very closely. We work very closely with all those who are involved besides the Page 3 of 19 Adani Green Energy Limited October 29, 2025 Government of India, but all those otherwise also who are involved in this evacuation process. All the stakeholders, we map them very closely.

    Answer, ashish khanna

    We have a great relationship with them. And we know exactly what is happening out there. And accordingly, we do time our projects too. But like we said, in the current context, there has been a challenge, but that is hardly less than 5% on our total effect as we speak right now. We do expect another 2.5 gigawatt or more than that coming in this particular H2 of further evacuation. And in totality, if you look out another 9 months, we are expecting somewhere close to 17 gigawatt of capacity coming from Khavda itself. Now, with these in place, we do not foresee there will be always a challenge of a month or two at max a quarter here and there.

    Answer, ashish khanna

    But we are committed for our particular installation, our investments and our execution capability. And then further on, we are mapping very closely. And with a few months here and there, I think we are comfortable in the way the evacuation will take place on an overall basis. Because if you look at it currently, we are focusing more on Rajasthan and Khavda. These are the two places which are where we currently are having our maximum execution of future coming in the next 1 or 2 years. And accordingly, I think we do not foresee a major challenge considering the progress which is happening on ground on this evacuation.

  2. Question

    Anuj Upadhyay: Yes, that is pretty helpful, sir. So next question is on the margin side. I believe during the quarter, the margin boosts were largely led by higher contribution from the non-PPA segment, that is your merchants, C&I and the CFD side. So my sense basically was the merchant realization was down during the quarter, but it largely has been led by higher volume of the merchant which has contributed to the EBITDA. Could you just clarify on this part, sir, how exactly the non-PPA segment has played its role in scaling up the margin here?

    Answer, ashish khanna

    Ashish Khanna: No, I do not think so. It is an element of a non-PPA segment per se. You will also realize that when you are talking about merchant, you might have taken into consideration the infirm power too. Now, this infirm power which is being currently sold as a merchant is primarily an add-on to our PPAs. Now, we are ahead of our commitments and we are selling this majority of this power ahead of and these are add-on to our overall returns because our PPAs are for 25 years once they are operationalized. So our coming ahead of the timeline is helping the organization to add more from the business case perspective and that is where you would have found that vis-a-vis the PPA, the merchant is contributing more. And I think as and when these PPAs get operationalized, they will be converted to the PPA power as then will be reflected on our balance sheet itself.

  3. Question

    Anuj Upadhyay: Okay. And lastly, sir, just can you clarify on the average realization which we got on this infirm or the merchant sales? Page 4 of 19 Adani Green Energy Limited October 29, 2025 Saurabh Shah: So the exact numbers from a solar perspective, the average merchant realization was INR2.1 per unit plus the RECs that we earn on that.

    Answer, saurabh shah

    So that is another INR0.35 per unit. And from wind perspective, it is INR5.13 per unit plus the RECs. So from that aspect that is how the -- so on an average because we have about 35% of wind as our merchant capacity. So from that aspect, that also helps the boosting the overall merchant realization.

  4. Question

    Anuj Upadhyay: Thank you, sir.

    Answer, ashish khanna

    Ashish Khanna: Again, we emphasize that the point that these are the add-ons from the point of PPAs, if you look at it. On overall business plan these are helping us to earn more by executing early.

  5. Question

    Puneet Gulati: Okay. Secondly, if you can also talk about the progress on the PSP side. How much have you spent so far there?

    Answer, ashish khanna

    Ashish Khanna: Well, on the physical progress, we are on track as we have been talking about it. We will be, I think coming out with the first PSP in the shortest time ever possible. The first one is expected to come in the coming calendar year itself and others are also on track. So we are very much on track as well as the execution of these PSPs are concerned. With respect to the exact number on the spent, if you are looking at it, I think the total.

  6. Question

    Puneet Gulati: Yes.

    Answer, saurabh shah

    Saurabh Shah: See the thing is that our first project, which is at Chitravathi of 500 megawatts of PSP, it's progressing well. It is about 57% odd completed in terms of physical progress. And as such, the overall project cost is about INR2,600 odd crores. So that's how the overall progress has been on that.

  7. Question

    Puneet Gulati: Sorry, I couldn't hear. What is the cost you said?

    Answer, saurabh shah

    Saurabh Shah: So INR2,600 crores is the overall cost of the project. And out of which physical progress has been 57%.

    Answer, ashish khanna

    Ashish Khanna: So if you look at it, Puneet it is coming at a cost of around INR5.1 crores to INR5.2 crores per megawatt. It's very cost effective that standpoint.

  8. Question

    Puneet Gulati: And will it be fair to assume you use it for merchant and there is no PPA? Page 5 of 19 Adani Green Energy Limited October 29, 2025 Ashish Khanna: No, I'm saying, I was just continuing.

    Answer, ashish khanna

    Since it's a smaller project our larger project of 1800 megawatts, they're even more cost effective on that.

  9. Question

    Puneet Gulati: Okay. And will it be fair to assume that this is largely prepared for merchant and there's no PPA at this point of time with this?

    Answer, raj jain

    Raj Kumar Jain: So, yes, today, as we stand, we have not locked it in a PPA, but we keep that flexibility with us with respect to playing this in the peak power market and extract additional revenue from there. And at the appropriate time, put that into a contract.

    Answer, ashish khanna

    Ashish Khanna: And Puneet, if you ask me on a general question, that is our strategy for all, that wherever we get an opportunity to earn a handsome return on a PPA, the assets are important to be in place. Once the opportunity comes, we will take full advantage of that particular opportunity to have the maximum return.

  10. Question

    Puneet Gulati: Understood. That's very helpful. And if you can also talk a bit about slightly lower PLF on the hybrid side, while both wind and solar have done well on year-on-year basis, hybrid has been a tad lower on year-on-year basis. How should one think about that?

    Answer, ashish khanna

    Ashish Khanna: No, I think the -- yes, but I think if you look at it in total, the wind has changed to a little extent in the current context. And I would not be -- if you see from an overall standpoint, yes, it's a few basis points less than -- but a lot of it depends on the weather content itself and where they are placed per se.

    Answer, viral raval

    Viral Raval: Just to add, Puneet, so hybrid CUF is also dependent on what kind of solar-wind combination you have. So the new projects have a specific design CUF which is lower. So it is dependent on that also, in addition to what Ashish ji has said.

Show 19 more questions
  1. Question

    Puneet Gulati: No, I am just looking at Q2 '25 versus Q2 '26. Solar is higher, wind is higher, PLF, but hybrid is down from 43 to 39.

    Answer, ashish khanna

    Ashish Khanna: It is hardly -- if you look at it, we are 39% plus on a hybrid. On that factor too, if you look at H1, right, H1 we are 39% plus, which is a very decent hybrid. A few basis points here and there in this scenario keeps on going up and down.

    Answer, raj jain

    Raj Kumar Jain: And Puneet, just further elaborating on what Viral was saying, so we have a very intense hybrid when it comes to Rajasthan, where on the 700 megawatt we have 500 plus megawatt of wind and 600 plus megawatt of solar. So that's a very intense hybrid in terms of the power which is going. That was a unique hybrid which we had set up. The new hybrids which we are setting up are as per the requirements of the respective PPAs where such intensity of solar and wind is not there. So that's where, again, it has to be more specific, seen based on the underlying mix of what hybrids which we are looking at. That's where also the difference is coming. Page 6 of 19 Adani Green Energy Limited October 29, 2025 Puneet Gulati: Understood.

  2. Question

    That's helpful. And lastly, if you can talk a bit about if you signed any new PPAs during the quarter, there were a few projects which you have won early into this year and late last year. Any progress there?

    Answer, ashish khanna

    Ashish Khanna: I think on an overall basis, as we see, today we have LOAs of more than 4 gigawatts with us to be converted into the PPAs. Other than that, around 27 gigawatts are there in the PPAs. I think we are on track. So we looked at on a more holistic basis on how we are moving towards 50 gigawatt target. And every year we have been adding on it. So I didn't get actually what number you are looking at.

  3. Question

    Puneet Gulati: No, just any new LOAs which got converted into PPA during the quarter?

    Answer, viral raval

    Viral Raval: Yes. So in this quarter, specifically, there is no such major development. But on an overall basis, we have converted a lot of LOAs into PPAs in the last six to nine months.

  4. Question

    Puneet Gulati: Correct. Understood.

    Answer, saurabh shah

    Saurabh Shah: So see, from capex perspective, we are the voice for 5-gigawatt of capacity this year, which will translate into a capex of about INR30,000 crores, of which 2.4-gigawatt has been achieved. And accordingly, the capex has been spent. From a perspective of next two years, the range would be in that same INR30,000 crores to INR35,000 crores of capex to be done each year. Because our plans would be in that similar range in terms of the execution, or maybe going a bit higher as we move forward into the next two years. So that's why the range would be between those numbers of INR30,000 crores to INR35,000 crores, which translates into $4 billion of capex sort of number in that sense.

  5. Question

    Manish Somaiya: Okay. That's super helpful. I did see the receivable days improved. And perhaps if you just kind of give us some color on what is that attributable to? Are you having delays in payments from discounts? Maybe if you can just help us understand that improvement and how sustainable is that?

    Answer, viral raval

    Viral Raval: Yes. So, Manish, if you look at the annexure on receivables that we have in the earnings presentation, you will see that our overdue receivables, which is basically any payment beyond the due date, is only four days, which is what I think is important to track. Otherwise, every DISCOM continues to pay within the due dates. So it is all on track, is what I would say.

    Answer, saurabh shah

    Saurabh Shah: And there is no change in the number of days from those perspectives. Last year or last quarter also, it was similar in that sense. Page 7 of 19 Adani Green Energy Limited October 29, 2025 Viral Raval: Yes.

    Answer, viral raval

    So sometimes what happens is when you look at the overall receivables, which you see, what happens is the not due category fluctuates a little bit, but it is not due. So what matters is what is due and then if there is a delay.

  6. Question

    Manish Somaiya: I see. Okay. No. That’s helpful.

    Answer, ashish khanna

    Ashish Khanna: I'll add on it that, we have been tracking it very closely. So it is important for us to make sure that we get our payments as they are due and not to be delayed. So there is a huge focus on realization of these payments. If there is any increment or decrement, if you are seeing on the part of our realization in terms of number of days, is also coming from the fact that our teams are very closely monitoring it. And then our realization is also getting better. So it is a continuous process and I am sure you will see continuous improvement on it, even though it is minor, but our focus is very huge on this.

  7. Question

    Manish Somaiya: Okay. No. That is super helpful. And then I was just going through the solar capacity utilization factor, which dipped sequentially. Maybe if you can just allude to why that was and then just connected to it, the delayed Khavda commissioning in 2Q, how much of that capacity has since come online in Q3? So two questions there.

    Answer, ashish khanna

    Ashish Khanna: So I think I am not sure where you are looking at this. So if you are only speaking from a Q2, yes, there is always a -- if you see the monsoon, this time has been a bit erratic. Generally, we - - it is not extended to the level it has and does not even come to that level. So there has been a weather change. But I think on an overall basis, if you look around, it is not that bad. On an H1 basis, if I look out, in the half yearly CUF of solar compared to last year, it is better than that. Of course, the weather changes impact that particular part of it.

  8. Question

    Manish Somaiya: Yes. Sure. Sure. No, and apologies for that. So just to clarify, I guess, my understanding is that there was some delayed pertaining to the Khavda commissioning in 2Q. And I was wondering if that impacted capacity in any fashion and how much of that has come online in 3Q?

    Answer, ashish khanna

    Ashish Khanna: Manish, I think, let me reiterate what we did in this particular H1. We have been, let me again say that we did -- the company did more or less 74% and close to 75% of what it did last year. So I think we are doing a great job as well as the execution is concerned. If I look around out in the whole of India, no one would have done 2.4-gigawatt in H1. And in spite of a heavy monsoon, coming close to more than 800-megawatt and close to 900- megawatt in a quarter is no small thing. Take my word on this as well as the solar and otherwise is concerned. So I think we are very proud of what the team has done here as well as the Q2 is concerned.

    Answer, ashish khanna

    There are always a scope for improvement. So we do not get the idea from where you get this idea that we have been delayed in execution of certain projects. Out of a 5-gigawatt which we have targeted this year, we are already more Page 8 of 19 Adani Green Energy Limited October 29, 2025 than 2.4-gigawatt per se. I think we are on track on an overall basis, including on Q2. Q2 has always been a difficult quarter, not only for us, but for everyone else too. And still we did a handsome job.

  9. Question

    Manish Somaiya: No. And I appreciate the answer. Again, I just wanted to get some clarification, but you have provided that. And just lastly, on leverage, if you can just help us frame leverage as we sort of go ahead, especially with all the capex needs that you have, the growth plans that you have, how should we think about leverage, not just in fiscal ‘26, but perhaps even a little bit beyond?

    Answer, saurabh shah

    Saurabh Shah: So see from a leverage perspective, from a net debt to EBITDA, which we track on a continuous basis, net debt to run rate EBITDA, we, from an operational asset perspective, we are at 4.4 times of net debt to run rate EBITDA. And including the under construction debt, we are at 5.1 times to be exact on the net debt to run rate EBITDA number. So from that aspect for another two years, three years, because of the kind of capex that we are continuing to do, we will be in the range between 4 times to 5 times of net debt to run rate EBITDA and continue to be there around that. But as we get closer to ‘29 onwards, the number will drastically start to reduce because the capex would have all come on online. See the other way of looking at this is that today, earlier we were doing 10-gigawatt or 11- gigawatt of operating capacity or 4-gigawatt to 5-gigawatt of construction. Today we are at 17- gigawatt of operating capacity, we are doing 4-gigawatt to 5-gigawatt of construction on a continuous basis. And that number of operational EBIT number and the run rate EBITDA will continue to grow higher than the debt impact.

    Answer, saurabh shah

    So from that aspect, the overall number should start continue to go on a downward trajectory and it will fall sharply from ‘29 onwards. Hope I am able to answer that.

  10. Question

    Mohit Kumar: Yes. That helps, of course. I will talk about… Ashish Khanna: So, Mohit, let me also add since we talk about curtailment and this is the second question, so I thought let us address even future questions which can come about it.

    Answer, ashish khanna

    We do expect, say in Khavda, by the end of this year, around 10-gigawatt of capacities to be evacuated. And so, that is where we have been speaking about that whatever we are adding into it, we do not, are you there?

  11. Question

    Mohit Kumar: My last question, what are the gross block at the end of H1 FY ‘26? Is it, my number is roughly INR1 trillion. Is that number right, unlike…?

    Answer, saurabh shah

    Saurabh Shah: So, in terms of rupees, the overall gross block is at about INR1 lakh crores, INR1.1 lakh crores on the including the CWIP. Without CWIP on a gross block, very specific basis, it is INR94,000 crores plus a CWIP of INR16,000 crores which is to be added to that in terms of under construction projects.

  12. Question

    Mohit Kumar: Understood, sir.

    Answer, ashish khanna

    Ashish Khanna: I think I will just give two bits before I turn it. I think the important factor, Aniket, is not tendering. It is important factor is how much of those tenders are converted into the power purchase agreement. I think that is an important factor. We are also seeing a shift coming from a pure play solar, pure play wind to now a peak power type of tender where the storage is playing an important role. And we do foresee more and more of round the clock power, our peak power type which is coming from renewable. Conversion of the current tender, yes, we are blessed not to have many, hardly 4-gigawatt is where we have our LOAs which are going to be converted to PPAs.

  13. Question

    Aniket Mittal: Got that and that is pretty helpful. Just circling back to the earlier question on grid constraints, would you be able to quantify that? So let's say had these grid constraints not occurred, how much higher would the overall generation be for us in this quarter?

    Answer, ashish khanna

    Ashish Khanna: So we have already mentioned that this total impact is actually less than 5%. And that is the impact of all this curtailment which is having on our event.

  14. Question

    Nikhil Nigania: Understood. And for the merchant solar that you have been adding for that also are Chinese modules allowed or?

    Answer, raj jain

    Raj Kumar Jain: So, Nikhil, the way the law of the land is, the bids which happened prior to somewhere early ‘21, we are allowed to import Chinese modules. So, that is where our portfolio is and we are importing there. The bids which happened after that, there we have the requirement of ALMM after, if those plants are commissioned after 1st April 2024. So, in all those cases, including Maharashtra and lot of other LOAs which we have in our hand, ALMM is the requirement. Recently, the government has introduced the requirement for the ALCM for projects which are commissioned after 1st June 2026. So, any merchant -- any projects for which the bids were concluded few months back and where the ALCM require -- where the -- after that period, whatever the bids are there, they – there we need to have ALCM, which means cells have to be done in India. All merchant projects which we are doing from 1st of April 2024 until 1st June of 2026 would need – can import cells from outside India.

  15. Question

    Understood. Got it. And the last question I had just on the infirm power side, as you said earlier, the revenues are not getting capitalized in the P&L. And similarly, I am guessing the financing cost when everything is going to the P&L as well. Management: Yes. It all goes to P&L. Nikhil Nigania: Everything goes to P&L. Perfect. Perfect. Those were my questions.

    Answer, ashish khanna

    Ashish Khanna: With respect to our project, we are looking at 5 gigawatts. That's what is our commitment.

  16. Question

    Bhavik Shah: Sure. Sure, sir. That is helpful.

    Answer, saurabh shah

    Saurabh Shah: For the current six months, the average merchant price for solar was INR2.1 per unit, and for wind, it was INR5.13 per unit. And within the merchant capacity, about 34% of our capacities Page 16 of 19 Adani Green Energy Limited October 29, 2025 are wind merchant. So, from that aspect, that is how the entire works, what we call from a merchant capacity perspective.

  17. Question

    Siddhanth K: Okay. And sir, regarding the capacity utilization, sir, like this H1, we saw that solar because of obvious prolonged monsoon, it was around 24.5%. So, and the wind was obviously higher. So, on a full year basis, how should we project this number, sir, for solar, and as well as wind on a -- like on a stable basis?

    Answer, ashish khanna

    Ashish Khanna: So, if you look out at overall basis, we should be 100-basis-point to 200-basis-point more than the last year. Because if you even compare the H1 solar of last year compared to H1 of this year, I am not going into quarter because weather cannot be determined on the way the quarter works in the calendar year. But we are definitely expecting 100-basis-point to 200-basis-point more than last year. It is also coming from the fact that our site at Khavda will play a decent role in also enhancing the CUF of the overall capacity. Since our capacities are more and more capacities are coming in Khavda, which has a much better CUF of solar compared to other sites.

  18. Question

    Siddhanth K: Okay. Okay. And so my last question is, sir, since the government has stopped doing clean Manila solar tenders, so how much of our capacity is already blocked? Is it like we should be Page 17 of 19 Adani Green Energy Limited October 29, 2025 bothered beyond the 50-gigawatt of target which we have for FY ‘30? Or do we need to consider after the first 30-gigawatts?

    Answer, ashish khanna

    So let us not discount solar that it is going to go off. We are blessed with the best of solar in this country. And if you look out, our tariffs are the best. We are currently talking of $0.03 or less than that on a solar basis. It is a great source of power, which can be utilized in multiple facets, not only for just providing the power during the daytime, but also for the storage capacity's input power.

  19. Question

    Puneet Gulati: Understood. That is very helpful. Page 18 of 19 Adani Green Energy Limited October 29, 2025 Moderator: Ladies and gentlemen, that was the last question for today.

    Answer, ashish khanna

    Ashish Khanna: I think, thank you for all of you for participating into this. I think we are in a very exciting phase. This particular quarter and in the earlier quarter too, the company has demonstrated its execution and operational skills once again, in spite of some very unprecedented challenges, which we have encountered in this particular half of the year, whether it was a war or unprecedented monsoons, which has struck. I think we are on a track for our commitment on what we have committed. And like we said, we are also on track for our strategies towards the storage part, whether it is BESS or PSP. We are well committed to execute the 50-gigawatt by 2030. And I think this particular quarter, as well as the last quarter, we are directionally and professionally absolutely right on track.

Questions about this call

When was the Adani Green Energy Q2 FY26 earnings call transcript filed?
Adani Green Energy filed the transcript with the exchange on 4 Nov 2025. This page is built from that transcript.
What does this page list?
47 statements from the transcript across 8 topics, 35 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 29 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.