Earnings call
Afcons Infrastructure Q2 FY25 earnings call: Afcons Infrastructure Limited’s biggest order value is about INR 5,700 crores
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Biggest order value is about INR 5,700 crores. The company is poised to maintain growth at 15%-16% CAGR over a medium to longer term. Afcons Infrastructure Limited is looking at a medium- to longer-term CAGR of 15% to 16%. The company has 16 tunnel boring machines, with four on the way. EBITDA margin was 13.8% in Q2 FY25, a record high. The company has an addressable market of around INR 3.2 lakh crores based on the large value complex projects it focuses on.
The numbers management gave
Results
- EBITDA margin moved from a sub-10% level to over 11% in FY24 over the past three years.
Show source
Our past three years, we have made substantial progress in enhancing our EBITDA margins, moving from sub-10% level to over 11% in FY24.
- The company had a CAGR of around 16% over the last 5 years, on an enhanced base.
Show source
And if you take even last 5 years, we have a CAGR of around 16% on an enhanced base.
- The company had a hit ratio of around 18% over a 20-year tenure and in excess of 22% over the last four years.
Show source
If you look at the last four years ratio, we have a hit ratio of in excess of 22%.
- The company reported top line of INR 3,090 crores in the second quarter, compared with INR 3,433 crores in Q2 FY24, and INR 6,303 crores in the half year, compared with INR 6,655 crores. Afcons Infrastructure Limited’s total income was ₹ 6,303 Cr in H1 FY25, compared to ₹ 6,655 Cr in H1 FY24, a decrease of 5.3%.
Show source
So in the second quarter, we have done INR 3,090 crores of top line as compared to INR 3,433 crores in the previous Q2 FY24.
- Top line declined around 5% in the half year, as its order book had been muted in the last 2 years due to conscious calibration because of bank limits constraint, and general elections delayed bill certifications and payments from select customers.
Show source
So there is a marginal drop in top line of around 5%.
- Half-year EBITDA margin improved by more than 200 basis points compared with the same number for the previous half year.
Show source
And this has improved by more than 200 basis points if we compare the same number of the previous half year.
Show 25 more statements
Results
- Return on capital employed was around 16.5% during the half year, generally in line with its half-year figure; management expects these numbers to return to FY24 levels as conditions improve in the second half.
Show source
So, the return on capital employed was around 16.5%, which generally is in line with the number we do it for the half year.
- Half-year turnover comprised 29% from overseas markets and 71% from the domestic market.
Show source
Ramesh Jha: So as far as the turnover for the half year is concerned, 29% was from overseas market and 71% was from the domestic market.
- The company had arbitration interest of around INR93 crores for the half year.
Show source
Ramesh Jha: So, the breakup of that other income is for the half year we have got arbitration interest of around INR93 crores.
- The company incurred around INR88 crores in bank guarantee commission for the half year ended; the continuing expenditure is integral to construction because the company must provide performance, advance payment and retention guarantees to customers.
Show source
Ramesh Jha: So, answering to your first question of bank guarantee commission, bank guarantee commission for the half year ended, we were around INR88 crores we have incurred.
- Revenue had a marginal drop year-on-year, due to a muted Order Book over the last two years, consistently calibrated because of bank guarantee constraints, delays in bill certification and payments from select customers because of the general elections, and the impact of a severe monsoon on some projects.
Show source
There is a marginal drop in revenue on a year-on- year basis.
- The company said that rationalising costs wherever possible helped improve its margin.
Show source
And so we are we are trying to rationalise our cost wherever possible and that has helped us to improve the margin.
- The company said interest on an award during the period also helped improve its margin.
Show source
Also, during this period we had award wherein we got a sizable interest and that has also helped us to improve the margin.
- The company wrote back projected losses accounted for on a project after incurring the actual expenditures.
Show source
And we have got some projected loss which we account in any project that has been written back because we have already incurred those actual expenditures.
- EBITDA margin was 13.8% in Q2 FY25, a record high. Replaced by a later filing.
- EBITDA margin improved by 200 basis points to 12.7% in H1 FY25 compared to the previous year. Replaced by a later filing.
- PAT grew by 30% year-on-year to 4.4% in Q2 FY25 and rose by 16.3% year-on-year to 3.6% in H1 FY25. Replaced by a later filing.
- The company reported quarterly EBITDA of INR 427 crores, or 13.8%, in the second quarter, compared with INR 394 crores in the same quarter of the previous year, an increase of 8.5%. Replaced by a later filing.
- The company reported quarterly profit after tax of INR 135 crores, 30% higher than in the similar quarter of the last financial year, and half-year profit after tax of INR 227 crores, 16.4% higher than in the same half year of the last financial year. Replaced by a later filing.
Money and capital
- Net worth reached INR 3,794 crores during the half year.
Show source
Our net worth has reached close to INR3,800 crores, to be very precise, INR 3,794 crores.
- Consolidated net debt was ₹ 2,640 Cr as of Sept’2024, compared to ₹ 1,789 Cr as of Mar’24. Afcons Infrastructure Limited closed September with net debt of INR 2,640 crores.
Show source
So, the net debt, we have closed September with INR 2,640 crores.
- Debt-to-equity ratio on a net debt basis was around 0.7 during the half year.
Show source
And on the net debt basis, our debt to equity was around 0.7.
- Net debt will be below INR2,000 crores, with 50% long-term debt and 50% short-term debt.
Show source
Ramesh Jha: You see as far as debt is concerned, I think at the moment, if I can give you some color we will be on a net debt basis will be sub INR2,000 crores.
- Term loans are around INR1,000 crores and are repayable over five- to eight-year periods; repayments will not be significant in this financial year.
Show source
So the repayments will not be that significant in this financial year.
- Remaining INR1,000 crores of working capital loans are continuing facilities that it avails and pays off as surpluses arise.
Show source
And the working capital loan remaining INR1,000 crores are all continuing facility which we avail and pay off as and when the surpluses arises.
- The company received INR1,223 crores after issue expenses from its IPO proceeds and used a large portion towards repayment of debt and working capital; the capex plan is earmarked for capital payment, with payments expected in November, December and January, and a small portion for general corporate purpose is earmarked for forthcoming expenditure by month end or the first week of December.
Show source
Of this, we received some after the expenses, we received some INR1,223 crores.
- Bank limit was around 6 times net worth before the IPO and is expected to be around 4.25 times net worth after the IPO.
Show source
And post this IPO, we will be somewhere around say 4.25 kind of range.
- The company had around INR20,700 crores of total bank limit, comprising INR1,800 crores of fund-based limit and INR18,900 crores of non-fund-based limit.
Show source
Ramesh Jha: So, we have around INR20,700 crores of total bank limit.
- The company expects to use around INR14,500 crores to INR15,000 crores of its non-fund-based bank limit.
Show source
We will be utilizing somewhere around say INR14,500 crores to INR15,000 crores kind of a bank limit.
- Debt increased during H1 of FY25 as limited traction with some customers and delays in bill certifications increased working capital requirements and required the company to fund project operations.
Show source
Page 7of 21 Afcons Infrastructure Limited November 25, 2024 This enhanced working capital requirement has contributed to our debt, which has increased during H1 of FY25.
- Bank limit was enhanced in FY24 and the enhanced limit is expected to take care of the company's order booking requirement for a couple of years.
Show source
So, we had a sizeable enhancement in our bank limit and that bank limit will take care of companies maybe couple of years order booking requirement.
What it expects ahead
What management expects
- The company is poised to maintain growth at 15%-16% CAGR over a medium to longer term. Afcons Infrastructure Limited is looking at a medium- to longer-term CAGR of 15% to 16%.
Show source
Paramasivan Srinivasan: And on a medium to longer term, we are looking at a CAGR of 15% to 16% which we have explained in the last 5 years.
- The company expects to move to a 70:30 ratio between domestic and overseas markets as its currently pending order book is skewed towards domestic orders.
Show source
While our current pending order book is skewed towards domestic order book, in due course of time, we are sure we will move to 70:30 ratio between domestic and overseas market.
- The company aims to maintain a book-to-bill ratio of 2.5x to 3.5x, because below 2x creates order booking pressure and above 4x creates execution pressure.
Show source
We are also looking at in the overall order book, the government's focus on in the infrastructure vertical, we are well positioned to capture the market appropriately, typically, comfortable to have between 2.5x to 3.5x book to bill ratio, primarily because we believe below 2x creates order booking pressure, above 4x creates execution pressure.
- The company expects 20% to 25% growth for 2026 from its current position, including L1.
Show source
And for 2026, we expect 20% to 25% growth comfortably from the current position.
- The company selected domestic jobs with reasonably good margins and does not expect an operating-cycle issue or margin pressure from the short-term change in the mix between domestic and overseas jobs; it expects to sustain EBITDA margins north of 11%.
Show source
And as far as EBITDA is concerned, we are looking at 11% plus.
- The company will generate positive operating cash flow for the full year, supported by expected project advances and recovery of payments that were stuck; payments from customers were improving from October onwards.
Show source
Ramesh Jha: We will be generating operating cash flow positive for the full year, because as I explained that during first half year, generally the payments are not up to date and that gets updated by the year end.
Show 14 more statements
What management expects
- The company expects reduction in finance cost to translate automatically into its net profit margin, but gave guidance only on EBITDA margin.
Show source
So, that should automatically translate into the net profit margin.
- The company is looking at a medium- to longer-term CAGR of 15% to 16%. Replaced by a later filing.
- The company is looking at EBITDA of 11% plus. Replaced by a later filing.
- The company will continue to focus on complex, large value jobs and maintain an overseas presence. Replaced by a later filing.
Show source
And going forward, also, we are looking at continuing to focus on complex, large value jobs, and continue to have overseas presence.
Orders
- Biggest order value is about INR 5,700 crores.
Show source
Page 4of 21 Afcons Infrastructure Limited November 25, 2024 Today, our biggest value of the order is about INR 5,700 crores.
- Order book was ₹34,152 crore, excluding L1 projects worth ₹10,154 crore. Afcons Infrastructure Limited’s order book stood at INR 34,152 crores as of 30th September, excluding L1 projects.
Show source
As of 30th September, our order book stands at INR 34,152 crores, excluding L1 projects.
- Order book was 80% from government clients, approximately split 50-50 between centre and state.
Show source
Currently, 80% of our order book is from government clients, is approximately split between 50-50 between centre and state.
- The company previously booked INR 17,400 crores in one of the years two or three years before, its highest-ever order book at that time.
Show source
Before that, one of the years, two, three years before, Afcons had booked INR 17,400 crores, which was the highest ever order book Afcons ever had.
- Current pending order mix is approximately 85-15 between domestic and overseas markets, after substantial domestic orders were booked that year; management would like to sustain a 30-15 mix, while the mix could be 75-25 in the short term of one or two years because of more domestic orders.
Show source
And therefore, the current pending order mix is shifted slightly about 85- 15 between domestic and overseas.
- The company has two pending L1 projects: Nagpur-Gondia Package Number 1 and Nagpur-Gondia Package 2, valued at around INR2,500 crores and INR2,800 crores, respectively.
Show source
Both are around INR2,500 crores and INR2,800 crores.
- The company has an L1 project for DRDO in Vishakhapatnam valued at around INR954 crores.
Show source
And one project we have got in Vishakhapatnam for DRDO, that is around INR954 crores.
- The company will not commence one Bangladesh road project, a job around INR600 crores, without rate revision; the government is in the process of accepting it, and the order will most likely be formally agreed to be foreclosed.
Show source
And therefore, most likely the order will be formally agreed to be foreclosed for that.
- The company is doing four projects in Bangladesh: three road projects and one railway project.
Show source
Paramasivan Srinivasan: On Bangladesh, we are doing four projects, three road projects and one railway projects.
- The company is waiting for payments from the government of Bangladesh and the government of India for its Bangladesh road jobs, which are all government of India funded jobs.
Show source
It's all government of India funded jobs.
What it is building and selling
Projects and capacity
- The company has 16 tunnel boring machines, with four on the way.
Show source
And if you look at tunnel boring missions, 16 tunnel boring missions, four are on the way.
Demand and pricing
- The company has an addressable market of around INR 3.2 lakh crores based on the large value complex projects it focuses on.
Show source
So, in terms of our total addressable market based on the kind of project we focus on, that's a large value complex project, we have an addressable market of around INR 3.2 lakh crores.
Segments
- The company re-entered overseas markets in 2005 and completed close to about 70 projects abroad over close to two decades.
Show source
2005, Afcons re-entered into overseas market and last about close to two decades, we have done close to about 70 projects abroad.
- Turnover ratio has been about 70:30 over the last several years.
Show source
Over a period of last several years, we have been having about a 70:30 ratio in terms of turnover.
- According to Engineering News Record statistics of 2023, Afcons Infrastructure Limited was the 10th largest marine player and 12th largest bridge player in the world, and the 18th largest in aqueducts and 42nd largest in overall transportation; the rankings reflect turnover outside the home country.
Show source
As per engineering news record statistics of 2023, we are the 10th largest marine player in the world, 12th largest bridge player in the world.
- The company currently subcontracts between 22% and 25% of its work and intends to move to 30% subcontracting.
Show source
We intend to move to 30% subcontracting.
Show 2 more statements
Segments
- The company has five-star export house status under the Government of India’s new policy guidelines.
Show source
We have already got a five-star export house status, and that recognizes our consistent export performance.
Deals and partners
- The Bangladesh railway project is a joint venture between Afcons and KPTL, with a 50-50 share; nearly 60% is completed and the balance is under execution.
Show source
The other one a railway project is a joint venture between Afcons and KPTL and there 50-50 is the age and there nearly about 60% is completed, I think.
Everything else said on the call
What management stressed
- The company will continue to be selective in picking orders and will say no to otherwise good orders when the commercial terms are not appropriate.
Show source
And we will continue to say no also in some of the good orders, which people consider as good order, or the thing if the commercial Page 6of 21 Afcons Infrastructure Limited November 25, 2024 terms are not appropriate to us.
Group structure
- The company was formed in 1959 as Rodio Hazarat & Company, with Rodio of Switzerland and Hazarat & Company of India joining together.
Show source
Afcons is a 65-year-old construction company having been formed in the year 1959 with the Rodio of Switzerland and the Hazarat & Company of India joining together as Rodio Hazarat & Company.
- An employee-led consortium paid off Rodio and took over Rodio Hazarat & Company in 1973, making it an employee-owned company with the Hazarat & Company stake.
Show source
That was the point when employee-led consortium paid off Rodio, took over the company and it became an employee -owned company with the Hazarat & Company stake.
- Rodio Hazarat & Company became Asia Foundation and Construction Limited in 1975-1976.
Show source
So, Rodio Hazarat & Company became Asia Foundation and Construction Limited in 1975- 1976.
- The company has incorporated an organization in Saudi and taken a local partner to manage the local environment; Afcons will have 90% ownership and the local partner 10%. Replaced by a later filing.
People and governance
- Average senior management team experience is about 23 years.
Show source
And therefore, we have a strong governance structure, and long standing senior management team, our average senior management team experience is about 23 years.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Ankur Sharma: Good afternoon. Thanks for your time. I had a couple of questions. Firstly, on the top line, which did degrow about 10% -11% in Q2, if you could help us understand the split between domestic and export growth. And secondly, within domestic, while we understand because of elections, monsoons, all the factors that you highlighted leading to this kind of a slowdown on execution, how are you seeing things kind of shape up in the second half? Are you starting to see a pickup now that monsoons are over? Are we starting to see things kind of getting back in shape and therefore second half being significantly better?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: I will answer the second part of the question. The first part of the question breakup will be given by my CFO. I am Paramasivan here. In terms of the second half of the year, we would expect for the year top line flat to normal. That is what we had indicated this thing. And considering the previous two years of calibrated order growth, we had this thing, we will have a flat growth in the top line in the current year. Page 8of 21 Afcons Infrastructure Limited November 25, 2024 While we look forward to in 20 26, while if we consider including L1, we are fully booked for our 100% of our order book is in place for 20 26.
Answer, paramasivan srinivasan
And for 2026, we expect 20% to 25% growth comfortably from the current position. As I conveyed earlier, our medium to long term CAGR, we would maintain at 15% to 16%. That is the general guidance. Ramesh, you would like to give him clarification on export and domestic turnover?
Answer, ramesh jha
Ramesh Jha: So as far as the turnover for the half year is concerned, 29% was from overseas market and 71% was from the domestic market.
Question
Ankur Sharma: So I was looking for growth rates. I understand the split between the two. I was trying to understand what was the growth rate between domestic and exports.
Answer, ramesh jha
Ramesh Jha: So see, as far as the growth is concerned, since the pending order, whatever we were having, we expect the same trend to continue in the range of say, around 30% from the overseas market and 70% from the domestic market. It is a balance year.
Question
Ankur Sharma: Okay, sir. Secondly, sir, on the order inflows, as you highlighted, we bought about INR 9,000 odd crores in the first half plus the L1. So, how much are you targeting for the full year? And also, if you could help us understand, which are the key end segments, where you're getting these orders from? Are these more domestic? Are these more exports? Some more color there? And also, what is your order pipeline? If you could give us a number, how is that looking like? If you have that with you?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: In terms of order book, including L1, you would have observed, we have in excess of INR 20,000 crores. Already, we had at the beginning of the year, we had set ourselves a target of INR 20,000 crores, which we have practically crossed for the year, if all the L1 jobs come into our kit. We have already submitted quite a few bids, and we are submitting further bids. And therefore, we expect a further order booking of not less than INR 5,000 crores. Okay. And taking that into consideration, it will be safe to assume that we may be booking an order for the whole year of INR25,000 crores, which will be the highest in the history of Afcons . Before that, one of the years, two, three years before, Afcons had booked INR 17,400 crores, which was the highest ever order book Afcons ever had.
Answer, paramasivan srinivasan
So, with this order book, not only 26 revenue visibility is in place, there is substantial revenue visibility for 27 as well with that. And in terms of this year, of the orders booked, substantial orders are from the domestic market. And therefore, the current pending order mix is shifted slightly about 85- 15 between domestic and overseas. While this is a temporary phenomenon , going forward, we would like to sustain a 30- 15, the short term one or two years, it could be 75- 25 because of more domestic orders. This is in terms of order booking pipeline, I request Mr. Hitesh Singh, our Head Of Strategy , to take you there. Hitesh Singh: Hi, Ankur. In terms of order pipeline, generally we keep a track of around next 2 years of visibility.
Answer, paramasivan srinivasan
So, in terms of our total addressable market based on the kind of project we focus on, that's a large value complex project, we have an addressable market of around INR 3.2 lakh crores. And as visible in our current pending order book, similarly the available market is the Page 9of 21 Afcons Infrastructure Limited November 25, 2024 highest in the urban infrastructure space. When I talk about urban, I am talking about underground metro, elevated metro and bridges put together. It is close to a INR1 lakh crore, that is the visibility we have, followed by surface transport, which is for us the rail and road business, which is around INR 60,000 crores. And marine and hydro, both we have around INR 50 ,000 -INR 50,000 crores each of visible order pipeline. And if we look at the overseas versus domestic, it's close to the same ratio which we generally target, around 70% of our pen order pipeline or the visible order pipeline is around 70% from the domestic part and 30% is from the overseas market. So, that's been the pipeline for us.
Question
Ankur Sharma: And just one last one, before I get back in the queue is on the operating cash flow. And then clearly, that is about INR 400 odd crores negative for the first half. And I think again, you did touch upon the reasons behind it. How do you see that for the full year? Can we expect cash flow to be positive and we generate a reasonable amount of operating cash flow for the full year? Would that be a reasonable assumption?
Answer, ramesh jha
Ramesh Jha: We will be generating operating cash flow positive for the full year, because as I explained that during first half year, generally the payments are not up to date and that gets updated by the year end. And also, for the half year ended, we have not received any sizable advance, which we generally receive. And there were recoveries happening for the earlier projects. So, that's where the numbers are negative. But I think, since we have got a number of projects, we will be getting those advances and that will help and we'll be getting the payments which were stuck. October onwards, we are seeing improvement in payments from the customers. So, we'll see a good cash flow for the full year.
Question
Sagar Tanna: Sir, despite a negative top line growth, we had a nearly 200 bps improvement in operating margins, EBITDA margins. Can you explain the reason for that? And what can be the sustainable margins for the full year and going forward?
Answer, ramesh jha
Ramesh Jha: You see as far as the margin for full year is concerned for FY24, we had clocked 11.6%. And I think what we can talk about in terms of margin is we'll - our endeavour will be to maintain 11% plus margin and coming back to your first question of the reason contributing the higher margin for the year. So, the company is focusing on operational excellence and we are trying to contain our cost wherever possible. And so we are we are trying to rationalise our cost wherever possible and that has helped us to improve the margin. Also, during this period we had award wherein we got a sizable interest and that has also helped us to improve the margin. Page 10of 21 Afcons Infrastructure Limited November 25, 2024 Sagar Tanna: So, if we exclude the interest on the arbitration award, which is mentioned in the notes of results then can we assume a normalised margin of 11%, 11.5% which we had clocked last year, is it a fair assumption?
Question
Sagar Tanna: And that is what is the sustainable margins going forward. Is that correct?
Answer, ramesh jha
Ramesh Jha: Yes. So, see what I'll say is we are into the business of construction and the margin in a quarter varies based on the nature, type and quantum of work executed. So, quarterly results may vary in different quarter and may not be indicative of the annual result and construction is full of contingencies. There could be some contingency which we may not be able to save. So, our guidance will remain that we will be clocking around 11% margin.
Question
Ashish Agarwal: Secondly, this other income this 74 crores of interest income which we got, this the cash has come in or this is on the approval basis?
Answer, ramesh jha
Ramesh Jha: So, the cash has had not come before September, but subsequent period it has come.
Question
Ashish Agarwal: Got it. And what was the forex gain, so to speak translation gain in the first half which is part of other income?
Answer, ramesh jha
Ramesh Jha: So, forex gain in this half year was not a sizable portion. It was a very minuscule amount.
Question
Ashish Agarwal: Okay, but because in the cash flows it looks like it's around INR75 crores. That's why I was trying to understand because there's a net foreign exchange difference?
Answer, ramesh jha
Ramesh Jha: In other income, there is no foreign exchange gain.
Question
Ashish Agarwal: Okay, got it. So, this INR190 crores of other income in the first half includes this INR75 crores of arbitration income and the rest will be miscellaneous income, am I right?
Answer, ramesh jha
Ramesh Jha: So, the breakup of that other income is for the half year we have got arbitration interest of around INR93 crores. And we have got some projected loss which we account in any project that has been written back because we have already incurred those actual expenditures. So, that is another aspect and then there is a balance in miscellaneous income.
Show 21 more questions
Question
Ashish Agarwal: Got it. And lastly, what is the capex plan for the second half of 2025 and if possible for F26? Page 11of 21 Afcons Infrastructure Limited November 25, 2024 Ramesh Jha: So, see for a specific number for the capex since we had for this financial year, we had planned a sizable capex related to we were buying three TBMs.
Answer, ramesh jha
Now, those three TBMs, we were expecting one of the TBMs to come before the half year which has got shifted. So the number we were looking at for the full financial year, we are looking at a reduced number for the total capex for the year.
Question
Ashish Agarwal: But if you can quantify that?
Answer, ramesh jha
Ramesh Jha: It will be difficult to put a number at the moment because we will have to see because some of the projects which we were expecting say by March or in the first quarter of June. So, all those orders got shifted. So, we will try to optimize the utilization of those equipment and as per the requirement, we will try to plan it.
Question
Ashish Agarwal: But if I have to put a number for next six quarters let us say for rest of F27 and F26, what kind of capex? Is it fair to assume it will be roughly 3% to 4% of your revenues?
Answer, ramesh jha
Ramesh Jha: Generally, we try to maintain in that range only. The capex generally is in that range only of the top line.
Question
Ashish Shah: Yes, good afternoon and thank you for the opportunity. So, first question is on the Q2 being solved, you did give some broader perspective, but a little more detail if you can share which segments and which particular type of projects were more impacted and more importantly, as we now are here almost in the end of November, how has the improvement happened or if at all it has happened?
Answer, ramesh jha
Ramesh Jha: So, specifically if I can talk about then water related projects was one segment where we have seen less of traction. Generally, there was a bill certification and payment related issues. So, we had three projects or so in that and our project like we are doing one project in Rajasthan, then couple of projects in Bihar and some other projects where we - because of monsoon related issues we saw the turnover going down.
Question
Ashish Shah: Apart from water anything significant sir which could have attributed to this slightly lower than expected performance?
Answer, ramesh jha
Ramesh Jha: So, see, as we said that generally we in first half of the year, we generally do 40% and 45%. And we are largely there in terms of top line. So, these were the projects where we had seen difficulties, water projects and some of the projects, bridges project where due to severe monsoon, we could not work.
Question
Ashish Shah: Okay.
Answer, paramasivan srinivasan
Paramasivan Srinivasan: In terms of FY25, we are looking at a flat to nominal growth and in terms of FY26, we will have 20% to 25% growth.
Question
Ashish Shah: Yes I got that.
Answer, paramasivan srinivasan
Paramasivan Srinivasan: And on a medium to longer term, we are looking at a CAGR of 15% to 16% which we have explained in the last 5 years. And as far as EBITDA is concerned, we are looking at 11% plus.
Question
Ashish Shah: Correct, sir. Also, for the L1 positions we did say that the INR10,000 odd crores number is now come down to 7,000 because maybe the LOAs have been received. So, a broad color if you can share on which are major orders in this L1 positions and by when do you think that these could be converted into firm orders?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: The first part, Hitesh, can you take them through? Management: Sure. Ashish Hitesh here. So, in terms of L1 order which are pending currently with us is two projects. One is Nagpur-Gondia Package Number 1 and Nagpur -Gondia Package 2. Both are around INR2,500 crores and INR2,800 crores. And one project we have got in Vishakhapatnam for DRDO, that is around INR954 crores.
Answer, paramasivan srinivasan
Paramasivan Srinivasan: This Bhopal metro and Vishakhapatnam, we expect in another couple of weeks by mid - December we should have it in hand before that because it has gone for institutional approval Bhopal metro. It is ADB funded job. Therefore, it has gone for ADB for approval. Here it has gone to Navy for approval. So, both of these we expect by middle of December. In terms of Nagpur-Gondia Expressway, I think once the government formation is completed, they will go ahead with the process. The timing, I am not in a position to say because there is a land acquisition related payment is to be made.
Answer, paramasivan srinivasan
After making the payment, they will release this order.
Question
Ashish Shah: Right. And maybe just one last thing what is the kind of order book which comes from Bangladesh at this point of time and how is the execution on the ground on those projects?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: On Bangladesh, we are doing four projects, three road projects and one railway projects. Out of which one road project, we had right from the beginning we have maintained the position because the order itself was given after 19 months of the submission of date. Therefore, without rate revision, we will not commence the work. So, now the government is in the process of accepting it. And therefore, most likely the order will be formally agreed to be foreclosed for that. That is a small job around INR600 crores. And Page 13of 21 Afcons Infrastructure Limited November 25, 2024 the other two jobs one job there are two road jobs.
Answer, paramasivan srinivasan
Of these two road jobs put together, will be roughly around INR600 crores, INR700 crores balance work and that is something which we will just about start. We are waiting for some payments to come from government of Bangladesh and government of India. It's all government of India funded jobs. The other one a railway project is a joint venture between Afcons and KPTL and there 50-50 is the age and there nearly about 60% is completed, I think. Hitesh, correct me. And the balance part of it is under execution. They are also giving land in bits and pieces.
Answer, paramasivan srinivasan
Therefore, it's going slow. And in terms of payment as it is an Indian funded job, we don't foresee any payment related risk.
Question
Ashish Shah: And sir what's the outstanding value of this order, the railway one for our share?
Answer, ramesh jha
Ramesh Jha: So railway job for our portion of balance will be anywhere between around INR300 crores or so.
Question
Ashish Shah: Okay.
Answer, ramesh jha
Ramesh Jha: And also to add in those contracts, since in between the work got stopped because of this unrest, contractually we are in a very strong position to get any compensation which needs to be raised. Ashish Jha: And sir in terms of outstanding receivable, is there anything sizable which is pending?
Question
Ashish Shah: All right. Thank you.
Answer, ramesh jha
Ramesh Jha: Sir just to add here in Saudi we have already incorporated an organization wherein we have taken a local partner to manage the local environment. So that company incorporation is already in place. And Afcons will be 90% ownership in that entity and 10% is the local partner. Aditya: Perfect. That's very helpful. Thank you so much.
Question
Saket Kapoor: Thank you for the opportunity. Sir, post the IPO proceeds, what are our current debt levels, debt numbers both the long term and the short term debt?
Answer, ramesh jha
Ramesh Jha: You see as far as debt is concerned, I think at the moment, if I can give you some color we will be on a net debt basis will be sub INR2,000 crores. And maybe bifurcation will be 50% will be long term debt and 50% will be short term debt in that.
Question
Saket Kapoor: Okay. Sir can you give some color on the current maturities which we have that we will be repaying by the end of this fiscal?
Answer, ramesh jha
Ramesh Jha: So see the term loans we have talked about in the range of say INR1,000 crores odd, those are all long term loans repayable over a period of anywhere between those are all 5years, 8 years kind of a loan. So the repayments will not be that significant in this financial year. I don't have the exact numbers at the moment. And the working capital loan remaining INR1,000 crores are all continuing facility which we avail and pay off as and when the surpluses arises. And those limits are always available. So we have got a very sizable bank limit which is available to us.
Question
Saket Kapoor: Okay, sir small point on the water segment. I missed your commentary on the same. Can you elaborate? What was the business environment and what portion of our order booking is towards the water segment and the scope of work for us?
Answer, ramesh jha
Ramesh Jha: So as far as water segment is concerned, what we saw that ever since the elections were announced sometime in March, April, after that there was a complete lull in terms of activity with those agencies and we had seen the bills were not getting certified and there were no payment allocation from the ministry to respective state agencies which were executing the project. So payments were not forthcoming. And after the election result, there was a change in ministry and a new regime at the helm of the affairs. They were trying to understand the whole set of things and it took a lot of time to get bills certified and paid. So that's the difficulty we were facing. And as far as… Management: And currently the pending drinking water supply projects will be around INR1,100 crores to INR1,200 crores in the pending order book.
Question
Saket Kapoor: And lastly, sir, on the IPO proceeds, we received INR1,250 crores from the IPO which towards the company and fresh issuance was to the tune of INR4000 crores. How was the proceeds bifurcated?
Answer, ramesh jha
Ramesh Jha: Yes. So, we have received - the company has received INR1,250 crores and after adjusting for the issue expenses, the proceeds have been used by company. Of this, we received some after the expenses, we received some INR1,223 crores. We have used a large portion of it towards repayment of debt and towards working capital we have already utilized. The capex plan is earmarked for the capital payment what we are having. Those are going to be utilized in due course of time because some payments are happening in November, some payment is happening in December and some in January. And we are left with a small portion of general corporate purpose which is earmarked for some of the forthcoming general corporate purpose expenditure by, say, this month end or maybe first week of December.
Answer, ramesh jha
So, we will have to look at on a composite basis, but broadly I can, I can give you a guidance that generally our margins are better in underground metro in hydro and underground, in marine and also in overseas projects, we generate a better margin, but notwithstanding that even in other sectors, since we have talked about our risk management framework and our - the company's thrust or focus on project selection metrics. So we try to identify projects where we generate a better margin. Bharani: Okay, the reason why I am asking is the trend generally we are noticing across your sphere is that margin compression is happening. It is heartening to see Afcons doing the 10% plus without other income on core EBITDA margins. However, generally when economies mature, clients get more aware of how to eke out extra money out of the EPC contractors. Generally, the contractors face margin compression. Do you see that risk playing out for generally us too, because we are one of the largest contractors in the country?
Question
Ronak Agarwal: Yes. Sir I just wanted to understand that in your finance cost there is a component of around INR150 crores of bank guarantee commission and other charges. I just wanted to understand like what is the nature of such a commission and is that something which will be – we will be occurring year-on- year or quarter-on- quarter? And the second question, sir, is on the net profit margin. So, you have given an EBITDA guidance. So, can you also just give a guidance that how your net profit margins will be on a long term basis?
Answer, ramesh jha
Ramesh Jha: So, answering to your first question of bank guarantee commission, bank guarantee commission for the half year ended, we were around INR88 crores we have incurred. And maybe you might be referring the last year's number of when we are referring INR150 crores odd. So, see, this bank guarantee commission is very much integral to construction business wherein a company is required to provide performance guarantee and advanced payment guarantee and retention guarantee to their customers. And that is a very much, a very obvious requirement for the contractor to provide. So, that expenditure will be a continuing requirement and that will be a continuing expenditure for the company. As far as the guidance on the net profit margin is concerned, so at the moment what Page 19of 21 Afcons Infrastructure Limited November 25, 2024 we are talking about is EBITDA margin only and basis that since we have talked about that, we are looking at reduction in our finance cost and all that. So, that should automatically translate into the net profit margin.
Question
Anupam Gupta: Yes. Good afternoon, sir. The first question is, you had mentioned in your remarks that your working capital constraints had limited your order inflow sort of which you saw over the last year or so. Post the IPO, what sort of resolution have you seen and what incremental improvements do you see in the constraints which were there in the last 1 year?
Answer, ramesh jha
Ramesh Jha: No. So, what constraints we were talking about in terms of bank limit which was there, but those issues were already solved prior to the IPO because in FY24 itself we had got our bank limit enhanced from the banks. So, we had a sizeable enhancement in our bank limit and that bank limit will take care of companies maybe couple of years order booking requirement. And generally banks as per the prudential norm, they sanction nine times of the net worth, the total bank limit. And today, if you look at from the network perspective before IPO, we were somewhere around 6 or so. And post this IPO, we will be somewhere around say 4.25 kind of range. So, we will have enough headroom if there is a requirement for further bank limit to go back to bank for asking for the limits. So, I hope this answers your question.
Question
Anupam Gupta: So, the things I want to quantify this, what are your fund- based and non-fund -based limits at this point of time and how much is utilized?
Answer, ramesh jha
Ramesh Jha: So, we have around INR20,700 crores of total bank limit. Of that INR1,800 crores is fund-based limit and INR18,900 is non-fu nd -based limit. In terms of utilization towards the fund-based limit maybe we will be somewhere around, say, 50%, 55% kind of utilization we will be having. And as far as non-fund -based is concerned we have got a sizable limit which is free. We will be utilizing somewhere around say INR14,500 crores to INR15,000 crores kind of a bank limit.
Question
Anupam Gupta: I understand. Okay. And the second question is you mentioned that the mix of the order book is more towards domestic at this point of time. And generally, what we understand is and you also said that overseas has higher margins and I would assume overseas would have lower operating cycle as well. So, given that the mix is more domestic at this point of time, do you expect some pressure of margins because of that and similarly, on working capital or that is not the right way to look at it? Page 20of 21 Afcons Infrastructure Limited November 25, 2024 Paramasivan Srinivasan: See, we have - while in general whatever you have stated is right.
Answer, paramasivan srinivasan
Currently, we have by and large focused on selecting the jobs in such a manner, in the domestic market also which are reasonably good margins. And also in terms of operating cycle, we don't expect much of an issue on account of this. Therefore, we don't expect on account of some change in the mix of between domestic and overseas jobs at this point which is short term I would call it. There will be change in the margin pattern. We will be in a position to sustain our margins, as informed by our CFO, North of 11% at EBITDA level.
Question
Anupam Gupta: Sure. Okay. And just one last question, if you can help. Generally, how much of your work do you subcontract annually or is it largely done yourself captively?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: We look to have about 30% of our work subcontracted. Today, we are somewhere between 22% to 25% of our work getting subcontracted. We intend to move to 30% subcontracting. We don't give back-to -back subcontract totally. Any activity -specific subcontracting , we give it which typically, less value-added jobs is the kind of work where voluminous work, where subcontractor also will be very comfortable. Those are the kind of work we try to give on subcontract basis.
Questions about this call
- When was the Afcons Infrastructure Q2 FY25 earnings call transcript filed?
- Afcons Infrastructure filed the transcript with the exchange on 28 Nov 2024. This page is built from that transcript.
- What does this page list?
- 65 statements from the transcript across 11 topics, 48 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 31 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.