Afcons Infrastructure Q2 FY26 earnings call: Afcons Infrastructure's order inflow in the first half of FY '26 was INR 1,268 crores and its pending order book was INR 32,681 crores

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Order inflow in the first half of FY '26 was INR 1,268 crores and its pending order book was INR 32,681 crores. The company expects a significant uptick in ordering activity in the second half of FY '26 after a slow first half. The company has a project pipeline of around INR 3.6 trillion spread across segments and geographies. Revenue in the first half of FY '26 was INR 6,520 crores, up 3.4% year-on-year, and EBITDA was INR 846 crores, up 6%. Gross debt in H1 was INR 3,472 crores and net debt was INR 2,714 crores; net debt-to-equity was around 0.5x of net worth.

The numbers management gave

Results

  • Revenue in the first half of FY '26 was INR 6,520 crores, up 3.4% year-on-year, and EBITDA was INR 846 crores, up 6%.
    Show source
    Let me begin with an overview of our financial performance for the quarter ending September 2025: For the first half of FY '26, our revenue was INR 6,520 crores, representing a growth of 3.4% year-on-year, while EBITDA rose 6% to INR 846 crores.
  • EBITDA margin in the first half of FY '26 was 13%, an improvement of 30 basis points.
    Show source
    EBITDA margin came in at 13%, reflecting an improvement of 30 basis points.
  • PAT in the first half of FY '26 was INR 242 crores, a 7% increase over the previous year.
    Show source
    The PAT fo r H1 stood at INR 242 crores, a 7% increase over the previous year.
  • Revenue in Q2 FY '26 was INR 3,101 crores, compared with INR 3,090 crores in Q2 of FY '25.
    Show source
    In Q2 of FY '26, we recorded a revenue of I NR 3,101 crores, marginally higher than INR 3,090 crores in Q2 of FY '25.
  • EBITDA in Q2 FY '26 was INR 401 crores, compared with INR 427 crores in Q2 of FY '25.
    Show source
    EBITDA for the quarter stood at I NR 401 crores compared to INR 427 crores in the same period last year.
  • EBITDA margin in Q2 FY '26 was 12.9%, broadly in line with last year's level.
    Show source
    The EBITDA margin for Q2 FY '26 was 12.9%, broadly in line with last year's level.
Show 14 more statements

Results

  • EBITDA margin in the first half of FY '26 rose to 13%, with near-term margin pressures due to the mix of projects under execution.
    Show source
    Despite near-term pressures on margins due to mix of projects under execution, our overall profitability for the first half improved modestly, with EBITDA margin rising to 13%, now Page 2 of 18 Afcons Infrastructure Limited November 13, 2025 turning to the industry.
  • EBITDA in the first half of FY '26 was INR 846 crores, equal to 13% and around 6% growth from the previous year's first-half EBITDA.
    Show source
    Moving on to EBITDA, for the half-year ended, we have done EBITDA of INR 846 crores, which translates in terms of percentage 13%, and there is a growth of around 6% from the previous year EBITDA number for the half year.
  • EBITDA in Q2 FY '26 was INR 401 crores, with an EBITDA percentage of 12.9%; its EBITDA calculation treats BG commission as operating expenditure and includes other income as revenue.
    Show source
    For the quarter also, we have clocked 12.9% of EBITDA percentage and in our EBITDA calculation, we considered BG commission as part of our operating expenditure.
  • Other operating income in the first half was around INR 161 crores.
    Show source
    So , for the first half, around INR 161 crores is other operating income.
  • Profit before tax in the first half was INR 333 crores, 5.1% of top line and up 2% year-on-year; for the quarter, it was INR 149 crores, 4.8% of top line.
    Show source
    In terms of profitability, the profit before tax for the half year is INR 333 crores which is 5.1% of the top line, and it shows a 2% growth Y-o -Y. And for the quarter, it is INR 149 crores, 4.8% in terms of percentage.
  • Profit after tax in the first half was INR 242 crores, 3.7% of top line and up 6.8% from the previous year; for the quarter, it was INR 105 crores, 3.4% of top line.
    Show source
    This again has grown 6.8% from the previous year and for the quarter, we have done I NR 105 crores which is 3.4%.
  • The company made a sizable provision in one project in Q2 FY '26, contributing to high other expenditure in the quarter and first half.
    Show source
    In this quarter, we have done a sizable amount of provisioning in one of the projects and that's where you will find that our other expenditure is quite high in the quarter as well as in the half year.
  • Total depreciation was around 4% of top line, of which close to 1.5% was due to accelerated depreciation.
    Show source
    The total depreciation is around 4% of the top line.
  • The company stopped work on the Jal Jeevan Mission project primarily because payment was not forthcoming and had INR 450 crores of receivables in the project.
    Show source
    We are stuck with INR 450 crores of receivables in that project.
  • The company considers arbitration interest, foreign currency exchange gain and miscellaneous incomes recurring and integral to its business, and treats them as other operating income.
    Show source
    Hence, it needs to be considered as other operating income.
  • First-half profits improved due to an upside from an arbitration award and margin improvement in some projects; material cost savings also improved margins in some projects and reflected in profit after tax.
    Show source
    Profits for the half year have improved, because we had some upside on account of arbitration award and also because of margin improvement in few projects.
  • Delays in certification of work done and release of payments in some projects increased uncertified work done and working capital requirements.
    Show source
    This has led to increase in uncertified work done, leading to jump in working capital requirements.
  • Some Indian-funded projects abroad of Afcons Infrastructure Limited saw lesser traction because the countries defaulted to India on committed repayments, leaving the projects hanging on a thin thread.
    Show source
    And so, few other projects of Indian- funded projects abroad is also seeing some lesser traction, because the countries defaulted to India on the committed repayments and other things.

Money and capital

  • Gross debt in H1 was INR 3,472 crores and net debt was INR 2,714 crores; net debt-to-equity was around 0.5x of net worth.
    Show source
    S o , debt has moved to INR 3,472 crores on a gross basis and INR 2,714 crores on net basis.

What it expects ahead

What management expects

  • The company expects a significant uptick in ordering activity in the second half of FY '26 after a slow first half.
    Show source
    The pace of ordering activity has been slow in the first half of the year, but we expect significant uptick in the second half.
  • Revenue growth for Financial Year '26 will be below its earlier guidance because of first-half headwinds, including delays in conversion of L1 orders; it estimates revenue growth to moderate to 10% plus, reduced from earlier guidance of 20% plus.
    Show source
    We had earlier expressed 20% plus, now we are reducing our guidance to 10% plus.
  • The company expects full-year EBITDA to be better than its general annual guidance of around 11%, after achieving 13% EBITDA in the first half.
    Show source
    So, we expect the number to be better than that.
  • The company is maintaining its INR 20,000 crore order flow guidance for the full year.
    Show source
    100% we are achieving a INR 20,000 crore guidance.
  • INR 3.6 lakh crore prospect pipeline includes around INR 1.6 lakh crore in Urban Infrastructure, around INR 94,000 crores in Hydro and Underground space including waterworks, and around INR 65,000 crores in Roads, including road and rail.
    Show source
    Around I NR 1.6 lakh crores is in the Urban Infrastructure .
  • INR 3.6 lakh crore prospect pipeline includes around INR 43,000 crores in Marine and Industrial; one-fourth is from the overseas market and three-fourths from the domestic market.
    Show source
    So, one-fourth is from the overseas market, 3/4th s is from the domestic market.
Show 16 more statements

What management expects

  • The company previously guided for minimum 20% growth, but some L1 orders expected to convert in the first and second quarters and to generate work in the second half of the financial year did not do so; the company also lacked visibility on payments for some projects.
    Show source
    What has changed since, some of the L1 orders which I explained to the earlier queries, that we were expecting to get it converted in the first and second quarter.
  • The company would like to maintain its earlier guidance of 15% growth for the next financial year because orders are going to bunch in the second half of the year.
    Show source
    Srinivasan Paramasivan: We would like to maintain our earlier guidance of 15% for the next financial year, because this second half of the year, orders are going to bunch.
  • The company said it was too early to give guidance on profitability metrics for the next year, but on a sustainable basis would like to achieve 15% top line growth and an 11% EBITDA number.
    Show source
    But on a sustainable basis, we would like to do 15% top line growth and 11% EBITDA number.
  • The company expects its EBITDA margin to be better than the 11% indicated at the beginning of the year, citing a 13% EBITDA margin for the half year and no bad projects or less profitable activity in the second half.
    Show source
    So, we expect our EBITDA margin to be better than what we had indicated at the beginning of the year at 11%.
  • The company expects some traction in Jal Jeevan Mission payments in the next 2 to 3 months; the Chief Minister has assured that he will clear all dues because he wants the project delivered well on time.
    Show source
    And therefo r e, we do expect some traction coming in next 2 to 3 months.
  • EBITDA guidance will remain around 11%.
    Show source
    Exact number, let us leave it at this point in time, because it would not be appropriate for me to give for the balance 6 month s. But one thing I can reassure you that we are not having any bad project or we are not having execution in the second half, which will be less profitable.
  • The company expects some L1 orders to fructify in the current quarter.
    Show source
    We do expect some of the L1 orders to fructify in the current quarter.
  • The company expects payments from customers to improve and funds to unwind as customers use their budgets toward the financial year-end; the impact of Jal Jeevan Mission is already factored in, and Afcons is not putting further money there.
    Show source
    So, we will be getting payments from the customer and things will unwind.
  • The company will achieve its full order book guidance, supported by its pipeline and ongoing tendering activities. Replaced by a later filing.
    Show source
    Suffice to say, on the back of a strong pipeline and ongoing tendering activities, we will achieve the full order book guidance.
  • The company took a cautious step based on its assessment, consciously bringing down certain turnover in some projects; this could reduce turnover but would not compromise its margin. Replaced by a later filing.
    Show source
    Therefore, we have to consciously bring down certain value of the turnover in some projects.
  • The company expects growth to continue despite a possible compromise in its percentage of growth. Replaced by a later filing.
    Show source
    While the percentage of growth could get compromised, it would still be growing.

Orders

  • Order inflow in the first half of FY '26 was INR 1,268 crores and its pending order book was INR 32,681 crores.
    Show source
    Our order inflow during the first half stood at INR 1,268 crores and our pending order book remains strong at INR 32,681 crores.
  • The company had four L1 jobs in Maharashtra: Nagpur-Gondia Expressway Package 1 at INR 2,599 crores, Nagpur-Gondia Expressway Package 2 at INR 2,849 crores, and Pune Ring Road Packages 5 and 7 together at INR 4,787 crores.
    Show source
    Nagpur -Gondia Expressway Package 2, INR 2,849 crores, Pun e Ring Road, both put together, both packages, Package 5 and Package 7 put together is INR 4,787 crores.
  • L1 project in Croatia's first road project was INR 2,406 crores, the second road project was INR 2,144 crores and the railway project was INR 6,771 crores.
    Show source
    Railway is I NR 6,771 crores.
  • The company had total L1 projects of around INR 23,000 crores.
    Show source
    With this we have total L1 projects of around INR 23,000 crores.
  • Croatia itself would be close to INR 11,500 crores to INR 12,000 crores; Afcons Infrastructure Limited is also considering INR 1,200 crores, bringing the stated total to around INR 13,500 crores, with INR 7,500 crore of fresh orders being sought.
    Show source
    So, around 13,500 crores already we are there, and remaining INR 7,500 crore fresh that we are looking at.

What it is building and selling

Projects and capacity

  • The company has a project pipeline of around INR 3.6 trillion spread across segments and geographies.
    Show source
    We have a strong project pipeline of around INR 3.6 trillion spread across segments and geographies.
  • The second consignment of tunnel boring machines for Afcons Infrastructure's C2 projects had been awaiting clearance at the port for the last 2 months, and Afcons Infrastructure was pursuing its release with the concerned authorities and ministries.
    Show source
    However, the second consignment is awaiting clearance at the port for the last 2 months, and we are actively pursuing with all the concerned authorities and ministries to secure its release at the earliest.
  • The company had completed about 15% of the Mumbai High Speed Rail Project.
    Show source
    Srinivasan Paramasivan: We have done about 15% of the project.
  • The company had completed 4.8 kilometers of NATM tunnelling on the Mumbai High Speed Rail Project, and lining work was ongoing.
    Show source
    NATM tunnelling of 4.8 kilometers is already completed.
  • The company could not take up INR 600 to INR 650 crores of Jal Jeevan Mission work because money was not forthcoming.
    Show source
    We have to do s till about INR 600 to INR 650 crores of work, which we are not able to take up.
  • The company estimates the cost of two tunnel boring machines (TBMs), including their attachments, at INR 600 to INR 700 crores; the amount depends on when the second consignment sails from China.
    Show source
    But this number is anywhere between say INR 600 to INR 700 crores for these TBMs, along with all these attachments it requires.
Show 5 more statements

Projects and capacity

  • The first consignment of tunnel boring machines for Afcons Infrastructure's C2 projects arrived from China.
    Show source
    Operationally, I am pleased to share that the first consignment of tunnel boring machines for our C2 projects have arrived from China.
  • Delays in fund flow continue to affect progress of Afcons Infrastructure's Jal Jeevan mission work, particularly in Uttar Pradesh.
    Show source
    In the Jal Jeevan mission, particularly in Uttar Pradesh, delays in fund flow continue to affect progress.
  • The company is hopeful that the second TBM consignment will sail from China this month; if it does, Afcons expects to commence execution by end March or maybe April.
    Show source
    And if it sails this month from China, I think by say, end March or maybe April, we should commence the execution.

Deals and partners

  • The client's estimated value for the Vadhvan Port bid submitted by Afcons Infrastructure Limited is INR 5,120 crores.
    Show source
    Srinivasan Paramasivan: The client's estimated value is INR 5,120 crores.
  • For the overseas project where Afcons Infrastructure is L1, contracting timelines specify 120 days from the date of bid opening, and Afcons says the timelines are already factored in.
    Show source
    120 days from the date of bid opening, all these are specified.

Risks, rules and outside factors

Risks and disputes

  • Exposure in the Jal Jeevan Mission project was around INR 450 crores; it had practically stopped work there from July onwards and had a balanced unexecuted job of roughly INR 600 to INR 650 crores.
    Show source
    Srinivasan Paramasivan: In terms of Jal Jeevan Mission, our exposure is around INR 450 crores, almost similar level.

Outside factors

  • Maharashtra projects have an escalation mechanism that starts 21 days before bid submission.
    Show source
    In fact, 21 days before submission of bid onwards, it starts.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Aditya Bhartia: Good afternoon, sir. Si r, my first question is on 2 large opportunities possibly that we are having in front of us, one being Vadhvan Port, the other one being Dubai Tunnelling Project. It would be great if you could share some details on the status of these 2 projects and how we see the timelines for these projects. Page 7 of 18 Afcons Infrastructure Limited November 13, 2025 Srinivasan Paramasivan: Vadhvan Port, we have already submitted the bid.

    Answer, srinivasan paramasivan

    Technical bid is opened yesterday. And after clarifications and other things, financial bid yet to be opened. Towards the end of the quarter or beginning of next quarter, results could be announced there. And that is as far as Vadhvan i s concerned.

  2. Question

    Aditya Bhartia: And this would be for the Breakwater, sir?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: This is for the Breakwater .

  3. Question

    Aditya Bhartia: Understood. U nderstood, sir. Sir, my second question is on Mumbai High Speed Rail Project. If you could share details on how much work has already been done and what kind of revenues and margins would we have recorded until now? Has the margin recognition started on that? Or is it likely to be starting once we move little ahead in the project?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: We have done about 15% of the project. See, substantial part of the billing schedule is on TBM tunnelling. NATM tunnelling of 4.8 kilometers is already completed. The lining work is going on. The TBM tunnelling, all of you are aware of the machine arrival related delays. The first set of consignment has come. It is not full consignment.

    Answer, srinivasan paramasivan

    The second set has to come to make it in full. After that, TBM tunnelling will start. Effectively, the profitability, the turnover will increase as we progress on the TBM tunnelling. That is where we stand. In terms of profitability, it is on expected lines. We don't expect any surprises over there.

  4. Question

    Aditya Bhartia: But so far, would we have recorded any margins from the project in 15% of the work that has been done or will margin recognition start little later?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No, margin recognition, typically, we start at 10%. And one important development on this is High Speed Railway Authority has accepted this delay of TBM arrival and other things as a force majeure condition, which is eligible for compensation to the contractor. They have officially communicated to us force majeure acceptance.

  5. Question

    Thanks for the opportunity. I just wanted to ask you about your L1. So, could you quantify what is your L1 position currently? And if you could give the breakup within Croatia between the road and the railway job as well as the other L1s like in Maharashtra? If you could give us the breakup, please.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: See, in Maharashtra L1, it continues to be the four jobs. Nagpur-Gondia Expressway P ackage 1, which is INR 2,599 crores. Nagpur -Gondia Expressway Package 2, INR 2,849 crores, Pun e Ring Road, both put together, both packages, Package 5 and Package 7 put together is INR 4,787 crores. Croatia, the first road project is INR 2,406 crores. Second is INR 2,144 crores. Railway is I NR 6,771 crores. With this we have total L1 projects of around INR 23,000 crores.

    Answer, srinivasan paramasivan

    And of this, we do expect some of the jobs to come in the current quarter. With resp ect to Mah arash tra, I th in k in th e last call also p eo p le were ask in g , th ere is so me amo u n t of uncertainty, because in some of the projects, they have just about commenced the land acquisition activity. Therefore, there is a debate within the Government, whether these projects have to go for rebid after the land acquisition is completed or whether it has to be awarded and then adequately handled, is going on. So, we have been engaging actively with the Government , but we need to see what is going to be the final decision, ok ay . That is the situation as far as the Maharashtra projects are concerned. All the other projects, we expect substantially in the current quarter, 1 o r 2 co uld slip to th e early next quarter. Some of this could happen in the current month itself.

  6. Question

    Shirom Kapur: Understood sir. Got it, sir. That is helpful. And just on your order flow guidance, are you still sticking to your INR 20,000 crore guidance for the full year or any changes to that?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: Yes. 100% we are achieving a INR 20,000 crore guidance.

  7. Question

    Shirom Kapur: Understood, sir. And just if I could ask you, last thing, your prospect pipeline you mentioned is INR 3.6 trillion. Would you be able to give us a breakup of that across segments and between Domestic and International?

    Answer, hitesh singh

    Hitesh Singh: Yes. I will just give you the breakup. So, out of this INR 3.6 lakh crores which we have talked about, as earlier trends were always there, the largest chunk lies in the Urban Infrastructure project. Around I NR 1.6 lakh crores is in the Urban Infrastructure . Fo r u s, Urban Infrastructure essentially means underground metro, elevated metro, including bridges as well. And then in Hydro and Underground space, including waterworks, around INR 94,000 crores is the project which we see. Then in the Roads business, which includes road and rail, what we call as surface transport, around INR 65,000 crores.

    Answer, hitesh singh

    And Marine and Industrial, around INR 43,000 crores. That is on the segmental breakup. Page 9 of 18 Afcons Infrastructure Limited November 13, 2025 In terms of geographical breakup, it is around 1/4ths and 3/4ths. So, one-fourth is from the overseas market, 3/4th s is from the domestic market.

  8. Question

    Mahesh Bendre: Hi, Sir. Thank you so much for the opportunity. Sir, last conference call, you mentioned that you had carried for 20%-25% kind of growth. Now, we are talking about 10% kind of growth. S o, what has changed in this last quarters, that has brought down the drastic change in the guidance?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: Yes. 20% -25%, minimum 20% is the guidance what we had given earlier. What has changed since, some of the L1 orders which I explained to the earlier queries, that we were expecting to get it converted in the first and second quarter. And some of these we were expecting the work to happen in the second half of the financial year, number one. Number 2, some of the projects, there is no visibility with respect to payment forthcoming. For example, Jal Jeevan Mission, we were slated to complete the entire project in the current financial year. We had to stop the project primarily because payment is not forthcoming.

    Answer, srinivasan paramasivan

    We are stuck with INR 450 crores of receivables in that project. And so, few other projects of Indian- funded projects abroad is also seeing some lesser traction, because the countries defaulted to India on the committed repayments and other things. Because of that, it is hanging on a thin thread. With this, there are issues with respect to this thing, not related to us with respect to the environment. Due to that, we need to take a cautious step, based on our own assessment of the situation. Therefore, we have to consciously bring down certain value of the turnover in some projects. This Jal Jeevan Mission, by now, we would have progressed very well.

    Answer, srinivasan paramasivan

    We would have completed in the current financial year. We have to do s till about INR 600 to INR 650 crores of work, which we are not able to take up. For the simple reason, money is not forthcoming. And people at all levels have been met, including CM's level and all. Therefore, that is something when the payment is going to come, all these having a lot of uncertainty, we have to take care of the interests of the company. And taking that, we have taken a call to take some of these tougher calls, which could result in reduced turnover, but it will not compromise on our margin. While the percentage of growth could get compromised, it would still be growing.

  9. Question

    Mahesh Bendre: Yes. So, whatever the revenue we could have booked in last 6 months. Is it possible, those revenues can be booked in next year, first half?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: Subject to some of the payment situation improving with some of the clients. Page 10 of 18 Afcons Infrastructure Limited November 13, 2025 Mahesh Bendre: Okay.

  10. Question

    Mahesh Bendre: Okay.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: We have demobilized some projects, giving notice to the client.

Show 10 more questions
  1. Question

    Shravan Shah: Hi, sir. So, now, let's say this year, we will be doing a 10%. So, next year onwards, previously, we used to have kind of a 15% plus, but given the 10% lower that we are doing. So, FY '27, can we look at a kind of a 20% or at current stage, there also only 10% kind of a number one can look at?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: We would like to maintain our earlier guidance of 15% for the next financial year, because this second half of the year, orders are going to bunch.

  2. Question

    Shravan Shah: Okay.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: In the second half of the financial year, orders are bunching up and the pace at which it is coming, if it comes in the current quarter, then work will start in the next financial year, initial phase installation will go. If it comes in the next quarter, then post-monsoon only it will get started. So, depending on that, our guidance of 15% would remain.

  3. Question

    Shravan Shah: Got it. So, now, just a clarification on the order inflow when we say INR 20 ,00 0 cro res. So, that obviously would be excluding the L1 that we have. So.

    Answer, maharashtra shah

    Shravan Shah: Okay. So, Croatia itself would be a kind of a close to I NR 11,500 crores to INR 12,000 crores. So, that we are considering and plus INR 1200 crores. So, around 13,500 crores already we are there, and remaining INR 7,500 crore fresh that we are looking at.

  4. Question

    And this Vadhvan Port , that the bid that we have submitted. So, this is the HAM, one that we are talking about? HAM project?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: The client's estimated value is INR 5,120 crores.

  5. Question

    Shravan Shah: Got it. And now, our guidance in terms of EBITDA margin, obviously, initially, we mentioned that it would be better. So, will it be 13% for this year and next year onwards, again, we will be having 11% kind of guidance?

    Answer, ramesh jha

    Ramesh Jha: See, as we explained that on an annual basis, the guidance we are trying to give is 11%. Because we have explained that there are many risks in projects. So, our endeavor is to of course improve and we have demonstrated that as well. For even FY '25 and even for this half year, we have done in the range of 13%. Since we have already done 13%, we expect the full year number to be better than what we had initially indicated. Exact number, let us leave it at this point in time, because it would not be appropriate for me to give for the balance 6 month s. But one thing I can reassure you that we are not having any bad project or we are not having execution in the second half, which will be less profitable. So, we are definitely going to improve from what annual guidance number we have given.

    Answer, ramesh jha

    For the next year, it will be too early to give any guidance on the profitability metrics. But on a sustainable basis, we would like to do 15% top line growth and 11% EBITDA number.

  6. Question

    Shravan Shah: Got it, got it. Lastly, on the CAPEX front, how much for this year we would be booking and a broader level next year would be how much? And also the balance sheet data point, mobilisation advance, retention money and unbilled revenue as on September. Ramesh Jha: See, on CAPEX, this year we have planned close to INR 1,100 crores and this has largely the TBM for the C2 package, which half of it has come and the second consignment is yet to start. So, once that comes, that is a sizable portion and then rest of the CAPEX, whatever we have planned is linked to the project award. So, once we get the project award, linked to that, we are going to do the CAPEX. That is for this year. I

    Answer, ramesh jha

    Ramesh Jha: See, these numbers have already been uploaded. These are part of the presentation. These numbers are already there. The unbilled revenue, and of course, these retentions, it's in the similar range what it was there. The retention number has not gone up from say the number what we were having in March or in June. Is in the similar range because some projects as we complete, we get the retention release. And the ongoing project, there is a regular recovery of retention.

    Answer, ramesh jha

    And unbilled revenue, again, it is in the similar range what it was there in the say June or March, in the similar range it is there. And the third thing you were asking was about mobilization advances. So, mobilization ad v an ces as we have not got the jobs. The jobs have not been awarded, s o we have not received those advances. On the contrary, for the ongoing jobs, whatever advances we had received earlier, recoveries are happening. So, sizable amount of mobilization advance, if we compare from say March '25 to September, the advances have come down, because of the recovery.

  7. Question

    Parvez Qazi: Hi, good afternoon, and thanks for taking my question. So, my first question is regarding our bid pipeline. You mentioned that we have a strong bid pipeline. Now, in H1, just wanted to get colour on the incremental bids, which have, let's say, got added to this bid pipeline. In which segment would we have seen new projects getting added to the bid pipeline in the last 6 months? And also, some colour on the geography, whether it's domestic or overseas, where these new projects have come, that would be great.

    Answer, hitesh singh

    Hitesh Singh: Yes, Parvez, largely the projects got added on the urban infrastructure space. There are certain projects which the Government has announced, those got added. And certain projects got added on the hydro and underground. That has been the major change. And also, as the awarding activity is going on, the tendering goes on, certain projects which were announced got dropped and new projects in the normal course of business got added. So, that's been the change why it has increased. Page 13 of 18 Afcons Infrastructure Limited November 13, 2025 And Domestic and O verseas, last time ratio was pretty much same.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: And in terms of your other question on geographies, some point of time, we had kind of practically withdrawn from the Middle East. But having got some of the clients agree to some change in the contract conditions and other things, we are reengaging in the Middle Eastern segment, where we do expect some good traction going forward.

  8. Question

    Parvez Qazi: Sure, sir. Second, what would be your view on competitive intensity in overseas projects? Do you believe there we will find lesser competition , compared to what we are se eing domestically?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: One cannot generalize the competitive intensity in the overseas situation. In different geographies, different kind of competition takes place. It depends on the client and the funding agency and the number of competitors involved. Therefore, I would not like to venture a general response to this, except saying that everywhere competitive intensity is there, we have to choose your client and also the preferred country and the client, I would put it.

  9. Question

    Parvez Qazi: Yes, are all the projects under execution or there are projects where we have received LOA, but appointed date hasn't come?

    Answer, ramesh jha

    Ramesh Jha: No, all these projects are under execution. So, there is no such project for which we have not got any appointed date or notice to proceed.

  10. Question

    Parvez Qazi: Sure. Thanks and all the best for future.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: In terms of Jal Jeevan Mission, our exposure is around INR 450 crores, almost similar level. We got some money in between, some small monies. And practically from July onwards, we have Page 14 of 18 Afcons Infrastructure Limited November 13, 2025 stopped the work over there. And just on the eve of Diwali, there was a meeting by the Chief Minister and other things. So, our exposure remains as it is. We have a balanced unexecuted job there of roughly around INR 600 to INR 650 crores. Balasubramanian: Okay, sir.

    Answer, ramesh jha

    Ramesh Jha: See, Jal Jeevan Mission, the impact anyways is already factored. And as we are not further putting money there, so what I can see is it is only going to improve from here. And also on an overall basis, usually up to H1, one needs to fund the projects. But now, since we will be approaching towards the year end, things will gradually improve, because the customers, they will have their own budgets and they need to exhaust all that during the financial year. So, we will be getting payments from the customer and things will unwind. Balasubramanian: Okay, sir. Sir, out of INR 1,100 crore CAPEX, how much CAP EX for these 2 tunnel boring machines?

    Answer, ramesh jha

    Ramesh Jha: See, exact number, we will not be able to give you. But this number is anywhere between say INR 600 to INR 700 crores for these TBMs, along with all these attachments it requires. And it is dependent on when it is sailing from China, the second consignment. And we are hopeful that maybe this month it should happen. And if it sails this month from China, I think by say, end March or maybe April, we should commence the execution. Balasubramanian: Okay, sir. Sir, if that TBM machines is getting delayed, which other projects is going to impact in the next 2 or 3 quarters?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: So, I am not clear about your question. Balasubramanian: So, what is the strategic initiatives you are going to take to reduce promoter pledging? What is the roadmap?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: On promoter pledging, we are not taking any initiative. It is with the promoter. So, it will not be appropriate for us to comment. Balasubramanian: Okay, sir. Thank you. Page 15 of 18 Afcons Infrastructure Limited November 13, 2025 Moderator: Thank you.

    Answer, bhoomika nair

    Bhoomika Nair: Yes, good afternoon, sir. So, just on this margin profile, we have seen a very strong one-edg e kind of a margin at about almost 13%, which is much higher than our guidance per se. You know, for this year, how do you see the margins moving per se, particularly in the second half? And as some of these conversions from L1 to actual time to begin work is delayed, will that impact the margins that we have quoted for some of these projects or are they escalation based, fixed price? Can you just throw some color on that?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No, with respect to margins, my CFO will respond. With respect to this thing, there is, in terms of Maharashtra projects, if you take it, there is an escalation mechanism right from the day we submitted the bid. In fact, 21 days before submission of bid onwards, it starts. Okay. With respect to the overseas project, which we are L1, there are t he contracting timelines and our timelines itself is like this. 120 days from the date of bid opening, all these are specified. Therefore, it's all factored in already.

    Answer, srinivasan paramasivan

    So, we don't expect any impact on the margins or related things. On the EBITDA guidance, Ramesh would respond.

    Answer, ramesh jha

    Ramesh Jha: So, see, Bhoomika, we have already talked about the EBITDA margin we have done for the half year, 13%. And as confirmed earlier also, we are not having any bad project as such in the second half or any less profitable activity to be executed in the second half. So, we expect our EBITDA margin to be better than what we had indicated at the beginning of the year at 11%. It should be definitely better, because half year we have already done 13%. Exact number we are not giving you, but I think we can expect that we should be doing better than what we had indicated.

    Answer, bhoomika nair

    Bhoomika Nair: Sure. And this quarter also the other income was slightly higher. Was there any arbitration or FOREX gain that was booked in this particular quarter?

    Answer, ramesh jha

    Ramesh Jha: See, FOREX gain is there in this quarter. And as you were asking about the overseas project. So, in overseas project, what happens that even though in majority of the project, we do not get any escalation, but then the exchange gain comes as an escalation measure, because on a continuous basis we are seeing that say a dollar or a euro appreciates against Indian rupees. So, we have seen in some of the project over a period of say 5, 6 years, the exchange difference itself becomes a very sizeable portion of the contract. So, likewise, things accrue. So, it is there in this quarter as well.

    Answer, bhoomika nair

    Bhoomika Nair: Okay. Okay. Got it. Got it. Understood. And so, just lastly, I know we have discussed a lot on the call in terms of the working capital rising and thereby the debt also has risen. While we will get some of these advances, when we get some of these orders, it should help in terms of reduction.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: In terms of our Jal Jeevan Mission payment, while we are not in a position to commit, Chief Minister himself has assured he will clear all the dues as he wants the project to be delivered well on time. And that is something I think the state level they are working. And therefo r e, we do expect some traction coming in next 2 to 3 months. Many of the states today, state level finances are, I would say, strained. Because of that, probably there has been some delay, I am not very sure. I am not able to comment.

Questions about this call

When was the Afcons Infrastructure Q2 FY26 earnings call transcript filed?
Afcons Infrastructure filed the transcript with the exchange on 17 Nov 2025. This page is built from that transcript.
What does this page list?
55 statements from the transcript across 8 topics, 43 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 20 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Afcons Infrastructure Q2 FY26 concall: Afcons Infrastructure's order inflow in the first half of FY '26 was INR 1,268 crores and its pending order book was INR 32,681 crores · DalalOS