Afcons Infrastructure Q1 FY26 earnings call: Afcons Infrastructure Limited's order bookings, including L1 jobs, were in excess of INR22,000 crores at the time of the call

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Order bookings, including L1 jobs, were in excess of INR22,000 crores at the time of the call. EBITDA guidance will remain around 11%. The company had completed closer to 90% of the NATM portion of tunneling on the heading part of the HSR project, and expected that portion to be completed in October 2025. Total income was INR3,419 crores in Q1 FY'26, 6.4% higher than INR3,213 crores in the previous year first quarter. Recent advances were all interest-bearing, changing the composition of total material advances to 63% interest-free and 37% interest-bearing, compared with the usual composition over the last so many years of 75% interest-free and 25% interest-bearing.

The numbers management gave

Results

  • Total income was INR3,419 crores in Q1 FY'26, 6.4% higher than INR3,213 crores in the previous year first quarter.
    Show source
    Now, coming to the specific number for the quarter, during Q1 FY'26, total income we have achieved INR3,419 crores.
  • EBITDA was INR445 crores, or 13% of the top line, in Q1 FY'26, compared with INR372 crores and an 11.6% EBITDA margin last year; the margin was 140 basis points higher.
    Show source
    Now, if we talk about specific to the margins, EBITDA margin, we have done INR445 crores which translates into 13% of the top line we have achieved.
  • Payment-related issues in UP Jal Jeevan Mission were continuing in Q1 FY'26.
    Show source
    Payment related issues in UP Jal Jeevan Mission is continuing.
  • Payment-related issues in Afcons Infrastructure Limited's MP projects were sorted in Q1 FY'26.
    Show source
    However, it stands sorted in MP projects.
  • Projects in Bangladesh started moving in a positive direction in Q1 FY'26.
    Show source
    Also, projects in Bangladesh have started moving into a positive direction.
  • Q1 period operating income included around INR49 crores, including around INR23 crores of arbitration interest and other interest accrued and around INR10 crores of miscellaneous income.
    Show source
    So for the Q1 period also, around INR49 crores is forming part of the operating income.
Show 16 more statements

Results

  • Profit before tax was INR183 crores, 5.4% of the top line, in Q1 FY'26, improving around 35% from INR135 crores and a 4.2% margin in the previous year; the improvement reflected an upside in the Calcutta metro project after an arbitration award and margin improvement in a few projects.
    Show source
    Page 5of 18 Afcons Infrastructure Limited August 08, 2025 Other margins, the profit before tax, we have done INR183 crores which is 5.4% of the top line.
  • Profit after tax was INR137 crores, 4% of the top line, in Q1 FY'26, improving by 50% from INR92 crores and a 2.9% margin in the previous year.
    Show source
    PAT margin, we have done INR137 crores in absolute number which is 4% of the top line and this has improved by 50% from the previous year wherein we had done INR92 crores absolute number and it was 2.9%.
  • Average borrowing increased by around INR366 crores in Q1 FY'26, and interest cost rose marginally as a result.
    Show source
    We have seen around INR366 crores of average borrowing has gone up in the Q1, because of this, interest cost has gone up marginally.
  • The company recorded INR139 crores of depreciation in Q1 FY'26, equal to 4.06% of turnover, with around 1.52% on account of accelerated depreciation on TBMs.
    Show source
    Now, on the depreciation front, we are continuing with the accounting for accelerated our depreciation on our TBMs, of the total INR139 crores of depreciation, which is 4.06% of the turnover, around 1.52% is on account of accelerated depreciation.
  • The amount pending from UP for the water Jal generation project had not declined from March levels and was roughly INR422 crores at the gross level; Afcons Infrastructure Limited had completed about 74% of the project.
    Show source
    It is roughly around INR422 crores at the gross level.
  • Normal trade receivables are around 40 days.
    Show source
    Now, in the receivables, we have got three categories, one normal trade receivable, which is in the range of say around 40 days, which is quite normal.

Money and capital

  • Recent advances were all interest-bearing, changing the composition of total material advances to 63% interest-free and 37% interest-bearing, compared with the usual composition over the last so many years of 75% interest-free and 25% interest-bearing.
    Show source
    That composition has changed because some of the recent advances we have received are all interest bearing, and the composition has become 63% is interest free, whereas, 37% is interest bearing.
  • The company closed Q1 FY'26 with gross borrowing of INR3,221 crores and net borrowing below INR2,500 crores.
    Show source
    So, whatever borrowing number has gone up for the Q1, we have Page 6of 18 Afcons Infrastructure Limited August 08, 2025 closed the gross borrowing was INR3,221 crores and the net borrowing was sub INR2,500.
  • Debt-to-equity was around 0.6 on gross borrowing and around 0.46 on net debt in Q1 FY'26.
    Show source
    So, on gross borrowing, the debt-to -equity was around 0.6 and on net debt it was around 0.46.
  • Net debt was below INR2,500 crores and its net debt-to-equity ratio was around 0.46.
    Show source
    Ramesh Jha: So, good evening, Vinee t. If you see the debt of the company, the net debt is sub INR2,500 crores and on net debt to equity basis, it is around 0.46 or so, which is a quite comfortable situation.
  • Over the last four or five years, Afcons Infrastructure Limited's mobilization advances were 75% interest free and 25% interest bearing; today, they are 63% interest free and 37% interest bearing.
    Show source
    Ramesh Jha: So, what I said, generally, if we see last four, five years, the bifurcation between an interest free and interest bearing used to be 75% interest free and 25% interest bearing, whereas today it is 37% is interest bearing and 63% is interest free.
  • Average bank borrowing cost is around 9%, and the interest cost on some interest-bearing advances varies from 7% to 10%.
    Show source
    Ramesh Jha: So, on our bank borrowing, the average borrowing is around 9%.
  • The company has received 50% of its arbitration receivables by way of NITI Aayog guideline, by giving a bank guarantee, although the amount is still classified as receivable.
    Show source
    And then we have got arbitration receivables, even though that gets reported in the receivable, but in 50% of the amount we have already received by way of NITI Aayog guideline, by giving bank guarantee, but still that gets classified as receivable.
  • Mobilization advances on jobs bagged last year were all interest bearing, which increased the interest-bearing proportion.
    Show source
    So of the recent job what we have bagged last year, where we have got mobilization advance, those were all having interest bearing.
  • The company was holding INR87 crores of advance. Replaced by a later filing.
    Show source
    Srinivasan Paramasivan: INR87 crores we are holding advance.
  • The company will continue investing in strategic equipment. Replaced by a later filing.
    Show source
    So, going forward also, the company will keep on investing in strategic equipment.

What it expects ahead

What management expects

  • EBITDA guidance will remain around 11%.
    Show source
    Our guidance for EBITDA will remain around 11%.
  • The company expects its tax rate to remain around 25% going forward.
    Show source
    In terms of tax, you might see that the tax rate has come back to around 25% and we could achieve this normal applicable range and we expect this to maintain at the similar range going forward as well.
  • The company hopes to return to the normal interest-free and interest-bearing advance mix it had over the last 3-4 years.
    Show source
    So hopefully going forward, we can see a situation where we go back to the normal situation what we were having for last 3-4 years.
  • The company does not expect its debt to come down significantly in the immediate term; in absolute terms, debt is not going to go significantly up or come down.
    Show source
    So, the debt in absolute terms is not going to go significantly up, but at the same time, it is not going to come down as well.
  • The company expects no challenge on the project, which is well funded by European funding, has decent payment terms and a proper interest-free mobilization advance.
    Show source
    So, we do not expect any challenge.

Orders

  • Order bookings, including L1 jobs, were in excess of INR22,000 crores at the time of the call.
    Show source
    And as things stand now, we are at, if you take all the L1 jobs plus others put together, is in excess of INR22,000 crores.
Show 6 more statements

Orders

  • Road projects are 20% higher than the estimate and its rail project is 10% higher than the estimate.
    Show source
    Srinivasan Paramasivan: I suffice to say that in one, in the road projects, we are 20% higher than estimate.
  • Pipeline includes around INR1.4 lakh crores of urban infrastructure projects, including metros, bridges and elevated corridors.
    Show source
    The largest chunk continues to be the urban infrastructure project, around INR1.4 lakh crores is from the urban infrastructure space, which includes metros, bridges, and elevated corridors as well.
  • Pipeline includes around INR80,000 crores in hydro, underground and water projects.
    Show source
    The second biggest chunk is from the hydro, underground, and water segment, which is around INR80,000 crores.
  • Surface transport pipeline, comprising its road and rail business, is around INR70,000 crores.
    Show source
    And surface transport, which is our road and rail business, around INR70,000 crores.
  • The Croatia projects Afcons Infrastructure Limited is considering are all interest free, and it is also looking at a sizable chunk of other pipeline projects in the interest-free zone.
    Show source
    Now, the order what we are looking at, like the projects we are talking about in Croatia, all are interest free.
  • Project pipeline normally covers almost two years.
    Show source
    So, that's the horizon I'll give you.

What it is building and selling

Projects and capacity

  • The company had completed closer to 90% of the NATM portion of tunneling on the heading part of the HSR project, and expected that portion to be completed in October 2025.
    Show source
    So, in October 2025, NATM portion will get completed.
  • Two Nagpur-Gondia road jobs aggregate to INR5,200 crores in value.
    Show source
    Nagpur, Gondia, two road jobs, which aggregate to INR5,200 crores value.
  • Two Pune Ring Road tunneling projects aggregate to around INR4,800 crores.
    Show source
    And Pune Ring Road, two tunneling project, which aggregate to around INR4,800 crores.
  • Two road and tunnel mixed projects in Croatia aggregate to around INR4,500 crores.
    Show source
    Then there are two road and tunnel mixed projects in Croatia, which aggregate to around INR4,500 crores.
  • The company had completed roughly one-fifth of the HSR project by the time of the call.
    Show source
    While the project progress is quite decent, we have already done roughly one-fifth of the project already.

Everything else said on the call

Other

  • The order for the project is supposed to be given within 120 days from when L1 is declared.
    Show source
    Srinivasan Paramasivan: Normally, from the time they declare L1, within 120 days, they are supposed to give the order.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Paramasivan Srinivasan: Thank you, Mr. Subramanian. Good evening, everyone. I would like to extend a warm welcome to all participants on this Q1 FY26 earnings conference call of Afcons. We value your continued interest in our journey and appreciate your engagement with us. Let me share some key updates on our performance, market outlook and project pipeline. Q1 FY26 has commenced on a positive note. We recorded a year-on- year revenue growth of 6.4% while maintaining healthy profitable margins. Based on the current trajectory and execution momentum, we are confident of achieving our annual turnover growth of 20% to 25% in this financial year. As Mr. Subramanian already explained, the global

    Answer, ramesh jha

    Ramesh Jha: Thank you, sir. Good evening everyone. Before I get into the specifics of the Q1 results, I would like to just clarify that company is into the business of construction, the margin in a quarter varies based on the nature, type and quantum of work we execute. So, quarterly results may vary in different quarters and may not be indicative of the annual results or the trend. Now, coming to the specific number for the quarter, during Q1 FY'26, total income we have achieved INR3,419 crores. This is 6.4% higher than the previous year first quarter number of INR3,213 crores. So, now we are very happy that we have got back to the positive trajectory of growth.

    Answer, ramesh jha

    G enerally, Q1 remains a little bit slow in terms of collection because most of the customers, being government entities, disburse the annual budget by March and then they devote Q1 in planning and budgeting for the next financial year. If we talk from the specific experience of FY26 Q1, then we feel the liquidity across the market needs improvement. Payment related issues in UP Jal Jeevan Mission is continuing. However, it stands sorted in MP projects. Also, projects in Bangladesh have started moving into a positive direction. Now, if we talk about specific to the margins, EBITDA margin, we have done INR445 crores which translates into 13% of the top line we have achieved. This is 140 basis points higher than what we had achieved last year where we had achieved INR372 crores absolute number and 11.6% EBITDA margin.

    Answer, ramesh jha

    On a YOY basis, the number has improved 19.6%. In EBITDA margin, in EBITDA calculation, we consider BG commission as part of our operating expenditure. So EBITDA that we are talking about is after removal of BG commission as expenditure. This also includes other income which is part of our revenue. We have in past also explained that our other income needs to be understood in the perspective of the business we are doing. Arbitration interest, foreign currency exchange gain and miscellaneous incomes are recurring in nature and very integral to the business. Hence, this needs to be considered as part of other operating income.

    Answer, ramesh jha

    So for the Q1 period also, around INR49 crores is forming part of the operating income. In that, around INR23 crores is arbitration interest and other interest we have accrued and miscellaneous income is around INR10 crores. The significant portion of the other income, I am just pointing it out. Our guidance for EBITDA will remain around 11%. Construction, as we have told, is full of contingencies. Our endeavour will be to save on those contingencies and optimise the margin. But many a times, we may not be able to save on those contingencies.

    Answer, ramesh jha

    Hence, our guidance for EBITDA will remain around 11%. Page 5of 18 Afcons Infrastructure Limited August 08, 2025 Other margins, the profit before tax, we have done INR183 crores which is 5.4% of the top line. This we have improved around 35% from the previous year wherein we had done INR135 crores and the margin was 4.2%. PAT margin, we have done INR137 crores in absolute number which is 4% of the top line and this has improved by 50% from the previous year wherein we had done INR92 crores absolute number and it was 2.9%. On profitability, we have improved on all the metrics like EBITDA, PBT, profit after tax because we had some upside in Calcutta metro project where we have got an arbitration award and also because margin improvement in few projects. We could save on some of the projects on the material cost and some of the other operational aspects and because of that the margin has improved. Specific, some of the other aspects, finance cost, in Q1 we have seen higher average borrowing during the quarter as compared to last year.

    Answer, ramesh jha

    We have seen around INR366 crores of average borrowing has gone up in the Q1, because of this, interest cost has gone up marginally. Currently, our international order booking is low where the advances are higher and all the advances are interest free in overseas market, coupled with this, new interest bearing advances we have received has also elevated the interest cost on client advances, taking the overall interest cost high. Generally, we have seen over last so many years, the composition of the total material advance we have, 75% is interest free and 25% is around interest bearing. That composition has changed because some of the recent advances we have received are all interest bearing, and the composition has become 63% is interest free, whereas, 37% is interest bearing. Now, on the depreciation front, we are continuing with the accounting for accelerated our depreciation on our TBMs, of the total INR139 crores of depreciation, which is 4.06% of the turnover, around 1.52% is on account of accelerated depreciation. In terms of tax, you might see that the tax rate has come back to around 25% and we could achieve this normal applicable range and we expect this to maintain at the similar range going forward as well.

    Answer, ramesh jha

    As far as ROCE is concerned, in Q1 we have done 15.62% and as explained, the capital infusion has increased the capital base, but operations are yet to reach to a level where we are desiring this year. So, this should reflect the proper standing on an annual basis only, of course, the ROE what we have reported is after accounting for the accelerated depreciation. During the quarter, net working capital has gone up. We are witnessing delay in certification of the work done and release of payments in some projects. This has led to an increase in uncertified work done, leading to a jump in working capital requirement. Generally, this remains the trend in Q1, but improvement what we were expecting in UP, Jal Jeevan Mission specifically has not happened. On the debt front, in Q1, payments remained relatively lower and operations had to be funded and this generally is a trend.

    Answer, ramesh jha

    So, whatever borrowing number has gone up for the Q1, we have Page 6of 18 Afcons Infrastructure Limited August 08, 2025 closed the gross borrowing was INR3,221 crores and the net borrowing was sub INR2,500. So, on gross borrowing, the debt-to -equity was around 0.6 and on net debt it was around 0.46. The incremental borrowing increase in the Q1 is in line with what we had done in last three years as well. So, it is not that this year it is significantly different. On behalf of Afcons, I thank everyone for attending this call. Now, I request moderator to open the floor for Q&A. Moderator: Thank you very much.

  2. Question

    Umesh Raut: Yeah. Hi, sir. So, my first question is on the ordering side. So, if I look at now order inflow for us during first quarter including L1, that is currently at about closer to INR21,000 crores plus, while what we have guided in the last call was order inflow of closer to INR20,000 crores to INR25,000 crores for FY26. And I think if I look at prospect pipeline as well, that is closer to now INR1.35 trillion for us. So, essentially, is there any upside in terms of order inflow guidance revision from INR25,000 crores in FY25? And second, if there is no upside, are we assuming that there is still no visibility in terms of conversion of Maharashtra state-related projects in actual sign

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No. We had guided that we will have about INR20,000 crores of order book from the current year plus L1 order that effectively translates into about INR30,000 crores for our guidance. And as things stand now, we are at, if you take all the L1 jobs plus others put together, is in excess of INR22,000 crores. So, we have no doubts as of now in our mind on any of these orders. We believe we will continue to be guarded in our guidance and we are confident of our guided numbers and beyond.

  3. Question

    Umesh Raut: Got it. And similarly, if I look at execution for the quarter, it was slower to start for FY26. And what we are guiding for 20%-25% of growth, assuming lower end of the band, it implies closer to about 25% of growth in the rest of nine months. So, are we kind of saying ramp up in existing backlog for execution? Do you think visibility around Jal Jeevan Mission collections would be improving so that the execution on water projects would be also improving? And in a way, there is no concern at all in terms of 20% growth on the top-line side for FY26?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: We have earlier call itself we had guided that substantial pickup will happen in the third and fourth quarter. And primarily because some of the fast-track orders we are receiving in the quarter, which we have received, which while the reported numbers as it is, there are significant increases in these orders are expected. All these are to be executed in short duration. Therefore, Page 7of 18 Afcons Infrastructure Limited August 08, 2025 we do expect to maintain our guidance as stated earlier. Therefore, we do not expect any execution concern as of now.

  4. Question

    Umesh Raut: Got it. And on the HSR project, where we are currently in terms of receiving TBM machines and are we assuming major uptick in execution from HSR in second half?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No. On TBM, as of now, there is uncertainty prevailing. Matter is handled at every level, at MEA, PM, railway ministry, at every level. Therefore, considering that, even if TBM starts coming, after that it has a setting of time and other things. While the project progress is quite decent, we have already done roughly one-fifth of the project already. And our NATM portion of the tunneling on the heading part of it almost 80% is already completed. In fact, closer to 90% is completed. So, in October 2025, NATM portion will get completed.

    Answer, srinivasan paramasivan

    So, the uncertainty in TBM should find its resolution hopefully in a month's time. But we are keeping our fingers crossed.

    Answer, ramesh jha

    Ramesh Jha: And just to add here, in the high-speed rail project, TBM -related tunneling is one aspect. Other than that, there are drill and blast tunneling, then we have shaft. So, all other works are going fine. Only this TBM-related tunneling is not happening. And as explained by MD, we are quite hopeful that things should materialize very shortly. And then we will be able to commence that work as well.

  5. Question

    Umesh Raut: Okay. So, in our guidance of 20% to 25% of execution growth, are we assuming material uptake from HSR? I mean, if suppose TBM machines get delayed, is there any concern around guidance for execution?

    Answer, ramesh jha

    Ramesh Jha: So, that we have already factored in. We are not looking at any concern as such. So, there will be all endeavour from our side, whatever guidance we have given. So, what happens that we have got number of projects. It is quite obvious that in some projects something may not go as planned. But at the same time, we will try to cover it up from some other project.

  6. Question

    Mohit Kumar: Hi. Good evening, sir. And thanks for the opportunity. My first question is that, have you worked in Croatia earlier? And what are the challenges in executing the orders and building a team to execute in new geographies?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: We have expressed very clearly in our earlier earnings call and all that we are looking at the markets on a continuous basis. And sooner than later, we could enter into Europe. So, this is the result of our sustained research and ground level work over a period of time. So, whatever risk, Page 8of 18 Afcons Infrastructure Limited August 08, 2025 we have evaluated and we have priced it also. Therefore, we do not foresee any major risk. And as you may be aware, we have already worked in more than 25 countries abroad quite successfully. And probably the only Indian contractor in the infrastructure space to be doing the infrastructure work in various parts of different countries.

    Answer, srinivasan paramasivan

    So, therefore, we do believe that and we are confident that we will be in a position to execute this project successfully.

  7. Question

    Mohit Kumar: When do you expect to receive the LOA and N TP for this particular project?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: Normally, from the time they declare L1, within 120 days, they are supposed to give the order.

  8. Question

    Mohit Kumar: Understood. My second question is the way that Dubai tunnel prospect, which we are pursuing in the Middle East, is there any update which you can share?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No, I think the process is going on. It is proceeding in the right direction. Beyond that, at this point of time, I think it is inappropriate to give any update.

  9. Question

    Mohit Kumar: Understood sir. My last question is what is the amount pending in UP for the water jal generation? Has it declined compared to March levels?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No, it has not declined. It is roughly around INR422 crores at the gross level. And we, of course, we hold some amount of advance of them. Therefore -- and we have already completed about 74% of the project. We are evaluating as to what is to be done. Efforts are on to realize the dues as well.

  10. Question

    Mohit Kumar: And how much advance you are holding, sir, broad number?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: INR87 crores we are holding advance.

Show 8 more questions
  1. Question

    Mohit Kumar: Understood, sir. Thank you. Thank you.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: No. Our pending order, whatever L1 is there, consists of seven orders. Two jobs, Nagpur, Gondia… Moderator: Sorry to interrupt you, sir.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: Yes. Nagpur, Gondia, two road jobs, which aggregate to INR5,200 crores value. And Pune Ring Road, two tunneling project, which aggregate to around INR4,800 crores. Then there are two road and tunnel mixed projects in Croatia, which aggregate to around INR4,500 crores. And one railway job, which is around INR6,800 crores. Everywhere, it is well bid and therefore, there is no reason for any concern.

    Answer, ramesh jha

    Ramesh Jha: And just to add, this Croatia job, we have been working for those projects for quite some time, more than one and a half years or so. So, our people were working on these projects with great details and getting into the methodology, how to procure, how to execute for quite some time. And that's where our bids are rightly priced. And the bids are far higher than the client's estimates. So, these bids are very, very nicely priced and we should see a very positive result in these projects. Balasubramanian: Okay, sir. Sir, I'm looking at FY25 numbers, like contract liability is around INR2,500 crores and contract assets, INR5,500 crores, more than two times in the FY25.

    Answer, ramesh jha

    In FY24, it's almost 1.3 times. I just want to understand, it might be the reason of delayed billing or client payment issues. And what is that status of Q1 numbers for unbilled revenue and advances side? And when we can expect to normalize these numbers?

    Answer, ramesh jha

    Ramesh Jha: No, so see, these contract assets and contract liabilities, rightly said that these are a reflection of ongoing business activity. So, if you see for a large part of time, the contract liabilities are in the similar range. When we are getting new projects, we get advances and that gets reflected in the contract liabilities. Some of the contract assets, of course, they are stuck and the company is working with various customers. One of them is Jal Jeevan Mission. So many places, we are at a very advanced stage. Even in Jal Jeevan Mission, we have tried to reach out to senior ministers and bureaucrats in the government.

    Answer, ramesh jha

    And we are working on getting those amounts settled. So at the moment, the arrangements in place are quite comfortable, but nevertheless, we'll realize these amounts and we'll have a very comfortable situation, maybe in another three, four months' time. Balasubramanian: Okay, sir. Sir, it's a common issue in the industry, labor shortages. I think various companies are facing around 20% to 30% kind of range. I just want to understand how much labor shortages we have and is there any impact on the execution of the project, especially on high -speed rail and metro projects and tunnel projects?

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: Labor shortage is a continuous issue in the Indian construction industry. We have our own ways and means of addressing it. Some projects still temporarily will have some labor shortage, but we have developed many mechanisms to see how the labor is retained. . Therefore, while there are problems, it is not a problem which is not insurmountable. It is managed. Balasubramanian: Okay, sir. Thank you.

    Answer, ramesh jha

    Ramesh Jha: So, good evening, Vinee t. If you see the debt of the company, the net debt is sub INR2,500 crores and on net debt to equity basis, it is around 0.46 or so, which is a quite comfortable situation. And the company is a growing company and we are investing a lot in strategic equipment. So, going forward also, the company will keep on investing in strategic equipment. So, immediate term, I am not foreseeing that the debt is significantly going to come down. But at the same time, let me reassure you, the debt is in a very comfortable zone and we will be able to manage with the surpluses going forward from the projects we are generating to manage the working capital requirement of the company and maybe even the capital equipment, the equipments we are going to add. So, the debt in absolute terms is not going to go significantly up, but at the same time, it is not going to come down as well. But at the same time, as I said, debt is in a very, very comfortable zone.

    Answer, ramesh jha

    Ramesh Jha: So, we are working on certain aspects of bringing down the interest cost and in that endeavor, we have done a number of commercial papers in recent past. So, those commercial papers, we have repaid some of the existing working capital lines. And of course, with these actions, we are getting the benefit of that interest arbitrage. So, we are working even on refinancing as well. Vineet Thank you so much, sir. That is helpful.

  2. Question

    Shirom Kapur: Okay. And these projects that have been, I know you spoke a little bit about it, but I just want to get more colour on the Maharashtra jobs that are in your L1. By when do you expect those orders to be converted? Because they have been sort of stuck in that L1 position since December, so, just wondering when we might get that conversion? Page 11of 18 Afcons Infrastructure Limited August 08, 2025 Srinivasan Paramasivan: It is quite a strange situation, which never happens normally.

    Answer, srinivasan paramasivan

    In Nagpur-Gondia, for example, we have been L1 since September. And in Pune-Ring Road, we are L1 since Jan. Typically, these kinds of things, as per Maharashtra government guidelines, once 70% land acquisition is completed, it can be awarded. Pune-Ring Road, it is practically 100% is acquired. And in Nagpur-Gondia, land acquisition has not reached that stage as yet. So, but today, we have no clues as to why the award of job is getting delayed. So, that is a factual statement. Therefore, when it will come?

    Answer, srinivasan paramasivan

    Anytime it can come, at least with respect to Pune- Ring Road, anytime it can come. Nagpur-Gondia, it depends on the land acquisition status, it could take some more time. That is our take. But this is something we have stated in the last earning call also. That time, one package was around 90% plus, another package was a little less. Now, it is one is 100%, another is some 99.3 or so acquisition in Pune. Therefore, we are not in a position to say, as to why it is getting delayed.

    Answer, srinivasan paramasivan

    We are hopeful that it will come very shortly.

  3. Question

    Shirom Kapur: So, in case, I mean, the delays continue, that would be a risk to achieving our order flow guidance for FY26, right? Because this would be, these orders are factored in.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: We are still confident of achieving our order book guidance. There are several other things in the pipeline.

  4. Question

    Shirom Kapur: Okay. Understood. Thank you so much.

    Answer, srinivasan paramasivan

    Srinivasan Paramasivan: I suffice to say that in one, in the road projects, we are 20% higher than estimate. And in the rail project, we are 10% higher than the estimate. And it is well funded by the European funding and payment terms are decent. We have a proper interest-free mobilization advance. It is like any other project. So, we do not expect any challenge. It is a well-bid job.

    Answer, srinivasan paramasivan

    It may not be, so it will be too premature to divulge all the details or commercial details of the project. Vasudev: Okay. Sure, sir. And so just can you give me what the capex that we did in Q1 and what we are targeting for the full year? Page 12of 18 Afcons Infrastructure Limited August 08, 2025 Ramesh Jha: So for the full year capex we have planned around INR1, 100 crores.

    Answer, ramesh jha

    Ramesh Jha: So, see, good evening. It is difficult to put a number of what percentage because there are number of projects we are executing around 64 projects or so. So putting a specific number because there are various projects which we have just commenced, like I think, you know, seven, eight projects we have just commenced, which are less than 10%. And then there are number of projects which we are on the verge of completing, maybe around out of that 64 projects, maybe around 10, 12 projects will be there, which we are going to complete this year. So that percentage varies in different projects. So putting any specific number may not reflect the right this thing. And all the projects, whatever we have got LOI, all we have commenced the execution.

  5. Question

    Shrinarayan Mishra: Yes, sir. So, my first question was again – again, it is a clarification which you highlighted earlier in your commentary. So you said that interest bearing advances, their proportion has now increased to 34% from earlier 25%. And the new orders which you are receiving on that 100% of the advances are interest bearing. Is that correct?

    Answer, ramesh jha

    Ramesh Jha: So, what I said, generally, if we see last four, five years, the bifurcation between an interest free and interest bearing used to be 75% interest free and 25% interest bearing, whereas today it is 37% is interest bearing and 63% is interest free. So of the recent job what we have bagged last year, where we have got mobilization advance, those were all having interest bearing. That is why this percentage of interest bearing has gone up. Now, the order what we are looking at, like the projects we are talking about in Croatia, all are interest free. And some of the other projects in pipeline, there also we are looking at a sizable chunk of projects in the interest free zone. So hopefully going forward, we can see a situation where we go back to the normal situation what we were having for last 3-4 years. Page 13of 18 Afcons Infrastructure Limited August 08, 2025 Shrinarayan Mishra: Okay.

  6. Question

    Shrinarayan Mishra: Okay. And sir, what will be our average cost of debt? And on the interest bearing advances, what average interest cost we are paying?

    Answer, ramesh jha

    Ramesh Jha: So, on our bank borrowing, the average borrowing is around 9%. And of course, I am not giving you the specific number, but it is around 9%. And some of the interest bearing advances, it varies from 7% to 10%.

  7. Question

    Shirom Kapur: Got it. And so, you usually give the breakup of the pipeline, you mentioned INR3.35 trillion and two-thirds domestic, but across segments, would you like to share that breakup?

    Answer, hitesh singh

    Hitesh Singh: Sure, I'll give you the breakup. So, out of that segment, as we have mentioned, normally our pipeline is well diversified and we cover projects for almost two years. So, that's the horizon I'll give you. The largest chunk continues to be the urban infrastructure project, around INR1.4 lakh crores is from the urban infrastructure space, which includes metros, bridges, and elevated corridors as well. The second biggest chunk is from the hydro, underground, and water segment, which is around INR80,000 crores. And surface transport, which is our road and rail business, around INR70,000 crores. And remaining marine is around INR46,000 crores in the pipeline.

  8. Question

    Vineet Gupta: Sir, good evening. If you could help us understand a bit on newer initiatives that you are taking apart from the existing sectors that you operate in. And second, what is typically the DSO, the debtor outstanding in terms of number of days? After completion how much -- after raising a bill, how much time does it typically take to realize the money?

    Answer, ramesh jha

    Ramesh Jha: And answering to your debtor days, see debtor days, if you see the trade receivable of the overall company, we are in the similar range. Now, in the receivables, we have got three categories, one normal trade receivable, which is in the range of say around 40 days, which is quite normal. And then we have got retention money, which gets released as per the terms of the contract. That also is in the similar range what we have for quite some time. And then we have got arbitration receivables, even though that gets reported in the receivable, but in 50% of the amount we have already received by way of NITI Aayog guideline, by giving bank guarantee, but still that gets classified as receivable. So – and that is also in the similar range what we have for quite some time. It’s not that those amounts are stuck, but something we realize, something we settle and we get it closed, but something new comes up in the category.

Questions about this call

When was the Afcons Infrastructure Q1 FY26 earnings call transcript filed?
Afcons Infrastructure filed the transcript with the exchange on 13 Aug 2025. This page is built from that transcript.
What does this page list?
40 statements from the transcript across 6 topics, 30 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 18 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.