Afcons Infrastructure Q2 FY27 earnings call: Afcons Infrastructure Limited secured orders worth close to INR 16,000 crore during H1, taking its total order book to INR 43,836 crore, excluding L1 orders
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company secured orders worth close to INR 16,000 crore during H1, taking its total order book to INR 43,836 crore, excluding L1 orders. The company is very confident of achieving its provided order book guidance of INR 30,000 crore and beyond. Phase-II of Mithapur–Sipara Elevated Corridor was inaugurated by the Honorable Chief Minister of Bihar during the quarter ended September 2026. EBITDA was INR 578 crore, or 10.3%, in the half year ended September 2026. The company is the eighth-largest player in marine in the world and the 12th-largest player of bridges in the world, according to Engineering News-Record U.S.A. statistics.
The numbers management gave
Results
- EBITDA was INR 578 crore, or 10.3%, in the half year ended September 2026.
Show source
On the half yearly basis, we have done INR 578 crore, which works out to be 10.3%.
- Operating income for H1 included INR 326 crores of total operating income.
Show source
So, far, in H1, we have INR 326 crores of total operating income, which we have factored.
- Profit before tax was INR 133 crore, or 2.4% of the total top line, in the half year ended September 2026, compared with INR 333 crores, or 5.1% of the PBT, last year.
Show source
For the half year, we have done INR 133 crore, which is 2.4% of the total top line, whereas last year we had done INR 333 crores at 5.1% of the PBT.
- Consolidated profit faced a higher tax percentage because 25% tax on Afcons profit was far higher than the consolidated number; some JVs pay tax in the range of 35%-36%.
Show source
As a result, consolidated profit has reduced, but 25% tax on Afcons profit, which is far higher than the consolidated number, works out to be the higher tax percentage on the consolidated profit.
- Net working capital was 147 days for the half year ended September 2026, at an elevated level because of funding to projects and lower-than-expected collection of blocked-up assets, with delays in work certification and payment releases in projects.
Show source
In terms of net working capital, the net working capital number is for the half year 147 days.
- Working capital requirement in H1 has been between INR 800 crore and INR 1,000 crore over the last four years, and this year was similar to that range and no different from the previous year; increased uncertified work led to a jump in working capital requirement.
Show source
We have seen that last, say, four years, the working capital requirement in H1 is anywhere between INR 800 crore-INR 1,000 crore, and this year also remains to be the similar situation.
Show 24 more statements
Results
- Cash flow from operations was negative in the first half of the half year ended September 2026, consistent with the annual H1 trend over the last four years, when negative cash flow was in the range of INR 800 crore to INR 1,000 crore.
Show source
If I talk about the cash flow from operations, cash flow from operations is negative in the first half, which remains to be the trend every year.
- From March 2026, Afcons Infrastructure Limited defined automatic ECL provisioning by receivable age buckets, including six months, more than six months, more than one year and more than two years, rather than basing it on past trends; this called for enhanced provisioning going forward.
Show source
From March 2026 onwards, what we have done, we have now, rather than looking at the past trend, what we have done, we have defined that any receivable which moves from, say, a six month to more than six month, then more than one year, more than two year, likewise we have bifurcated.
- The company has INR 372 crores outstanding in U.P. on JJM.
Show source
As far as outstanding is concerned, we have got INR 372 crores in U.P. outstanding.
- EBITDA margin has been in excess of 11%, 12% in normal circumstances.
Show source
And EBITDA margin in excess of 11%, 12%, I don't think most of the construction companies achieve.
- The company is receiving small payments under Jal Jeevan Mission based on a defined percentage threshold of the overall work once that work is completed.
Show source
We are receiving small payment based on certain threshold of percentage, which they have defined of the overall work once that is completed.
- EBITDA calculation includes BG commission as operating expenditure and is after removal of BG commission as an expenditure.
Show source
So, EBITDA, what we are talking about is after removal of BG commission as an expenditure.
- The company reduced manpower costs and other costs, partially offset by increases in energy, transport and logistics, finance, and provisioning costs.
Show source
But that has been partially offset by increase in energy, transport and logistics, finance, and provisioning costs.
- The company is negotiating settlement of certain arbitration receivables described as non-prime and has made a provision for the possibility of discount negotiations to realize those arbitration awards.
Show source
So, towards that, we have made a provision.
- The company made a conservative provision for an outstanding receivable at a Middle East location after negative feedback from customers and banks, and will continue to follow up on the receivable; if it is realized, some of the receivables may need to be reversed.
Show source
So, in order to, in future, we are not giving you any surprise, we thought that it would be prudent to make a provision.
- Consolidated profit decreased due to provisioning in an overseas subsidiary, based primarily on local market feedback and the geopolitical scenario in that market.
Show source
However, in the consolidation, the profit has decreased due to provisioning as just explained in one of the overseas subsidiary.
- Consolidated profit was reduced by ECL provisioning required for some closed joint venture projects.
Show source
Also in some of the closed projects which are in joint venture, we are required to make ECL provisioning, and that also takes the consolidated profit down.
- Q2 performance was lower than the corresponding period last year. Replaced by a later filing.
Show source
Let me now address the operating performance: Page 2 of 21 Afcons Infrastructure Limited November 05, 2026 Our Q2 performance was lower than the corresponding period last year.
- ECL provisioning was far higher than that of other industry players. Replaced by a later filing.
Show source
If you compare our ECL provisioning, what is appearing, we have looked at that number with other industry players, you will find that our provisioning is far higher than the others.
Money and capital
- Around 59% of Afcons Infrastructure Limited's advances are interest-free and 41% are interest-bearing.
Show source
Currently, of the total advance, currently around 59% of the advances are interest-free and 41% of the advances are interest-bearing.
- Of the advances Afcons Infrastructure Limited is looking to collect for new projects, 60% are interest-free.
Show source
Because of the advances we are looking at collecting for the new project, 60% of the advances are interest- free.
- The company made sizable CapEx payments during the first half of the half year ended September 2026.
Show source
Also, we have done sizable CapEx payment during this period.
- Gross debt was INR 4,765 crore and net debt was INR 4,050 crore in the half year ended September 2026, with net debt-to-equity at around 0.74x of net worth.
Show source
So, debt has moved to INR 4,765 crore on a gross basis, and on net basis, it is INR 4,050 crore.
- CapEx remains planned at INR 700 crores for FY '27 and around INR 650 crore for FY '28.
Show source
We are looking at for FY '27 CapEx in the range of INR 700 crores, and in FY '28 is around say INR 650 crore.
- The company expects FY '27 gross debt of around INR 3,500 crore and net debt of around INR 2,750 crore to INR 2,800 crore; those numbers remain unchanged.
Show source
And in terms of debt, we had talked about that FY '27, on gross debt basis, we will be around INR 3,500 crore.
- A significant portion of Afcons Infrastructure Limited’s March '27 debt will be term debt towards CapEx, while working capital debt will come down.
Show source
I think important point in debt one needs to understand is, we will have of the March '27 debt, a significant portion will be a term debt towards the CapEx.
- The company booked substantial orders this year, but the corresponding advances for those new orders had not come by the time Q2 financials were prepared.
Show source
This year, we have booked substantial order, but the corresponding advances of those new orders have not come yet till Q2 financials we have prepared.
- The company has a large amount of advances lined up for collection, which will significantly change its working capital scenario.
Show source
We have big amount of advances lined up for collection, and that will change the working capital scenario significantly.
- The company is maintaining a very healthy liquidity situation in its treasury. Replaced by a later filing.
Show source
We are maintaining a very healthy liquidity situation as far as company's treasury is concerned.
- Operations in H1 were funded amid continuing payment issues. Replaced by a later filing.
Show source
In terms of debt in H1, payment issues has continued and operations have been funded.
What it expects ahead
What management expects
- The company is very confident of achieving its provided order book guidance of INR 30,000 crore and beyond.
Show source
We are very confident of achieving the provided order book guidance of INR 30,000 crore and beyond.
- The company is targeting to significantly improve order booking in FY 2027 and improve its balance sheet by collecting some of its stuck receivables.
Show source
In FY 2027, we are targeting to significantly improve the order booking and improve the balance sheet by collecting some of the stuck receivables.
- The company expects the Pune Ring Road job could be awarded in Q4; the tender has been floated with a 45-day submission deadline, followed by about a month for evaluation and award, and the award will depend on who is L1.
Show source
We do expect the award of Pune Ring Road job in Q4.
- Pending pipeline for the remaining H2 is around INR 80,000 crores, spread across segments: hydro around 35%, marine around 35%, surface (road and rail) around 10%, and urban infrastructure 20%.
Show source
So, for the remaining H2, our pending pipeline, which we see is around INR 80,000 crores, and which is spread across segments.
- Total pipeline, or TAM, for FY '28 plus this quarter (around six quarters) is INR 3.6 lakh crores, spread across hydro and underground at 20%, marine and industrial at 27%, surface and surface transport at 20%, and urban infrastructure at around 32%; 65% is domestic and 35% is outside India.
Show source
For the next year, that is FY '28, and plus this quarter, which means around six quarters, the total pipeline, the total TAM for us is INR 3.6 lakh crores.
- The company expects 20% to 25% growth for 2026 from its current position, including L1.
Show source
Srinivasan Paramasivan: Next year, as we conveyed to you earlier also, we do expect about 20%-25% growth from that of current year, number one.
Show 19 more statements
What management expects
- The company expects execution in the second half to be stronger than in the first half, based on its improved execution visibility.
Show source
Based on the visibility, we expect execution in the second half to be stronger than in the first half.
- The company has held back guidance in terms of growth because of continuing uncertainty around economic activity due to war and geopolitical factors, and will reinstate guidance once broader uncertainty goes away.
Show source
Uncertainty around the economic activity because of war, geopolitical, and related stuff continues, so we have held back any guidance in terms of growth for the time being.
- Interest-free advances will help Afcons Infrastructure Limited reduce finance costs going forward.
Show source
Interest-free advances will help us in reduction in the finance cost as we move forward.
- The company expects significant improvement in net working capital or other metrics going forward, as advances on significant orders booked this year are due in the next six months and the company is working to realize stuck receivables.
Show source
Hence, we are confident that there will be significant improvement in net working capital or other metrics going forward.
- The company is likely to receive substantial advances in the next six months on jobs already secured.
Show source
However, this year we can inform you that in next six months, we are likely to receive substantial amount of advances on the already secured job.
- The company expects significant improvement in cash flow from operations in H2, leading to an overall annual correction in cash flow from operations and reductions in debt and net working capital.
Show source
So, in an overall probability, we will see a significant improvement in cash flow from operations in H2, leading to an overall annual number correction for the cash flow from operations, debt reduction, net working capital number reduction.
- The company expects second-half revenue to be higher than first-half revenue.
Show source
Srinivasan Paramasivan: Second half would be definitely higher than the first half.
- The company expects H2 to be better than H1 and is looking for a full-year correction in margins.
Show source
Now, what we are trying to say that H2, we will have a better number than what we have done in H1, and that is where we are trying to give you a confidence that for the full year, we are looking at correcting the situation as far as the margins are concerned.
- The company expects the Brahmaputra project to be awarded this year if everything goes fine, as it is L1 there.
Show source
If everything goes fine, the award for that project should also happen this year as well, considering we will be L1 there.
- The company realized a small amount of payment in U.P. in the last two, three months and does not expect a significant amount to be released going forward.
Show source
But I think going forward, the way forward we are looking at, it will not be a significant chunk getting released.
- The company does not expect its borrowing cost to exceed the run rate clocked in H1; bank guarantee costs may increase if back-project activity requires increased bank guarantee utilization.
Show source
But as far as the borrowing cost is concerned, I don't think that we are going to cross the kind of run rate we have clocked, say, in H1.
- The company is likely to receive stuck receivables targeted for this year. Replaced by a later filing.
Show source
Also, we are likely to receive stuck receivables, which we have targeted this year.
- The company is on track to achieve the budgeted number in its high-speed railway project for the current year. Replaced by a later filing.
Show source
We are on track to achieve the budgeted number in high-speed railway project for the current year.
- The company could move into a portfolio stock at some stage; the company expects this. Replaced by a later filing.
Show source
That is what we expect.
Orders
- The company secured orders worth close to INR 16,000 crore during H1, taking its total order book to INR 43,836 crore, excluding L1 orders.
Show source
This excludes L1 orders.
- Order intake for the year is close to INR 19,500 crores, excluding L1 orders.
Show source
As on date, for the year, our intake is close to INR 19,500 crores, excluding L1 orders.
- The company has an identified project pipeline of around INR 80,000 crores for Financial Year '27, with bids under evaluation and several opportunities at different stages of tendering, and remains on track towards its full-year order inflow guidance of INR 30,000 crores.
Show source
With an identified project pipeline of around INR 80,000 crores for Financial Year '27, bids under evaluation, and several opportunities at different stages of tendering, we remain on track towards our full-year order inflow guidance of INR 30,000 crores.
- The company has booked orders amounting to INR 19,437 crores till now in FY 2027, taking its pending order book to in excess of INR 47,000 crores.
Show source
Now, moving to the guidance we have talked about in FY 2027, we have booked order amounting to INR 19,437 crores till now, taking the pending order book in excess of INR 47,000 crores.
- Pending JJM order book in U.P. is around INR 474 crores; the customer expects Afcons to complete 75% before releasing payment.
Show source
The pending order book in U.P. is around INR 474 crores now, which the discussion what we had with the customer, they are expecting us to complete 75%, and then after that, they will release that payment.
What it is building and selling
Projects and capacity
- Phase-II of Mithapur–Sipara Elevated Corridor was inaugurated by the Honorable Chief Minister of Bihar during the quarter ended September 2026.
Show source
Phase-II of Mithapur–Sipara Elevated Corridor was inaugurated by the Honorable Chief Minister of Bihar during the quarter.
- Phase II of the Mithapur-Sipara Elevated Corridor was inaugurated in Bihar, reducing the expected travel time between Mithapur, Mahuli and Punpun from approximately one hour to around 15 minutes.
Show source
The corridor is expected to reduce travel time between Mithapur, Mahuli, and Punpun from approximately one hour to around 15 minutes.
- Both tunnel boring machines for Afcons Infrastructure Limited’s high-speed railway project had arrived and been put into operation in the previous quarter; the initial drive for one machine is complete and regular working has started, while the initial drive for the second is likely to be completed in November.
Show source
Number two, with respect to high-speed railway project, as in the earnings call we mentioned earlier, in the previous quarter, both the tunnel boring machines have come, and that has been put into operation.
- Land handovers at Afcons Infrastructure Limited's affected project sites are progressing, and certain approvals and clearances have moved forward. Replaced by a later filing.
Show source
Land handovers are progressing at affected sites, and certain approvals and clearances have moved forward.
Segments
- The company is the eighth-largest player in marine in the world and the 12th-largest player of bridges in the world, according to Engineering News-Record U.S.A. statistics.
Show source
As you know, Afcons is the eighth-largest player in marine in the world, 12th-largest player of bridges in the world.
Risks, rules and outside factors
Risks and disputes
- The company does not foresee any further requirement for the arbitration-award realization provision; if it realizes the amount, it may consider correcting the provision.
Show source
Even if we are able to realize this amount, there will not be, maybe we can look at correction in the provisioning.
- The company made a provision in one overseas subsidiary based on market feedback and will follow up with the customer for realization, deciding how to proceed with the provision based on progress.
Show source
And two, in one of the overseas subsidiary, based on the market feedback, we had done the provisioning.
- The company will keep some cushion for negotiation when it receives awards in newer arbitrations. Replaced by a later filing.
Show source
Srinivasan Paramasivan: Third, newer arbitrations also, when we get arbitration award, we will keep some cushion for negotiation.
Outside factors
- Geopolitical tensions in West Asia continue to affect logistics and the cost of certain inputs on some of Afcons Infrastructure Limited's projects.
Show source
Internationally, geopolitical tensions in West Asia continue to affect logistics and the cost of certain inputs on some of our projects.
- Payments to Afcons Infrastructure Limited are being stretched because executing agencies, governments and state governments do not want to borrow from banks.
Show source
We reiterate that across the spectrum, payments are being stretched for some or the other reason because the executing agencies, the government, the various state governments, or the executing Page 4 of 21 Afcons Infrastructure Limited November 05, 2026 agencies do not want to borrow from banks.
Rules and policy
- In overseas locations such as Bangladesh, tax is charged on turnover, and where no profit is made there is no provision for refund, so the tax is charged off as an expenditure.
Show source
In overseas locations like Bangladesh, the tax is charged on turnover.
Everything else said on the call
What management stressed
- The company formed a task force to review amounts stuck in about 15 projects and continuously interact with customers.
Show source
We are looking at some 15 odd project where the amounts are stuck, and that task force is on a continuous basis interacting with the customer.
- The company does not want to go overboard in funding any project and wants to maintain a healthy balance between execution and liquidity. Replaced by a later filing.
Show source
So, we do not want to go overboard in terms of funding any project, and we want to maintain a healthy balance between execution and the liquidity.
Group structure
- An Afcons Infrastructure Limited subsidiary has outstanding receivables in the Middle East, and Afcons Infrastructure Limited has set up a task force for this financial year to follow up with all customers.
Show source
Third, in Middle East, we have certain outstanding in one of the subsidiary, and for this financial year, we have set up a task force which is following up with all the customer.
Other
- Afcons was named Construction Contractor of the Year at the 16th Construction Week Awards, while several of its projects received safety awards and recognitions from domestic and international institutions during the quarter ended September 2026.
Show source
Afcons was named Construction Contractor of the Year at the 16th Construction Week Awards, while several of our projects received safety awards and recognitions from domestic and international institutions.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Aditya Bhartia: Sir, you spoke about execution pace picking up in second half. Just wanted to kind of clarify, are we looking at it on a year-on-year basis that revenue decline would be lesser, or are we speaking about in absolute terms that let's say we have done around INR 5,500 crore of revenues in first half, second half should be materially higher than that?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: Second half would be definitely higher than the first half. That much we can say for certainty.
Question
Aditya Bhartia: Also, if you could give us some indication about high-speed rail project, how is the execution going on that? What kind of revenue accretion should we be looking at it in second half as well as next year? Given that we have already gotten decent amount of orders in first half, plus we are L1 for a few contracts as well, how would you look at revenue growth from the perspective of next year?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: Next year, as we conveyed to you earlier also, we do expect about 20%-25% growth from that of current year, number one. Number two, with respect to high-speed railway project, as in the earnings call we mentioned earlier, in the previous quarter, both the tunnel boring machines have come, and that has been put into operation. As we call initial drive with respect to one tunnel boring machine is completed, regular working has started. With respect to second tunnel boring machine, initial drive is likely to get completed in the month of November. We are on track to achieve the budgeted number in high-speed railway project for the current year.
Question
Aditya Bhartia: My second question is on the ECL provisioning that we have done. Now, I could not understand what is really the change that we had put in, because from my understanding, ECL provisioning always is based on buckets, and as soon as a contract assets or a receivable moves from one bucket to another, there is provisioning that is required. What was the change that was being done this particular quarter? Page 8 of 21 Afcons Infrastructure Limited November 05, 2026 Ramesh Jha: No, what earlier the practice we were following was based on the previous experience of different buckets, whatever provision we had done in past or we had experience of any receivable going bad, basis that t
Answer, ramesh jha
From March 2026 onwards, what we have done, we have now, rather than looking at the past trend, what we have done, we have defined that any receivable which moves from, say, a six month to more than six month, then more than one year, more than two year, likewise we have bifurcated. And basis that there will be automatic provisioning rather than looking at the previous. So, this has called for an enhanced provisioning now going forward. If you compare our ECL provisioning, what is appearing, we have looked at that number with other industry players, you will find that our provisioning is far higher than the others. So, this is one change. And as I explained you that we have formed a task force in the company. We are looking at some 15 odd project where the amounts are stuck, and that task force is on a continuous basis interacting with the customer.
Answer, ramesh jha
There are many projects which is in overseas location. People are visiting, they are meeting the concerned team, and they are taking feedback how it is going to get materialized. Now, in that endeavor, in the Middle East, the feedback we got from the bankers and the overall geopolitical situation, it was not very encouraging. So, then we thought that let's make the provision at this point in time, and as things materialize, then we will see how to go about on the ECL provisioning. There will not be any surprise going forward. Rather, it could be a positive surprise. And two, we have received some three, four arbitration award, which we are on a constant basis in the same exercise we are discussing with the customer.
Answer, ramesh jha
On a suo moto basis, we have made this provision towards this. It will give us some headroom for negotiation so that we can realize the cash quickly. At the moment, we are not seeing that anybody has asked for any discount, but then from our end, we thought that it would be better we keep it so that it gives us flexibility, we can quickly conclude the deal. So, that is where we have made the provision. If we realize all that amount, there could be a reversal.
Question
Aditya Bhartia: What had really warranted this change of kind of increasing the way we are creating provisions? Because we had a one-off kind of provisioning in fourth quarter as well. Now, if we are fairly confident that we should be receiving these amounts, then why change the rate at which provisioning gets created?
Answer, ramesh jha
Ramesh Jha: Because see, the amounts are outstanding for the period of outstanding is higher, and once that outstanding receivable moves to a certain bucket, basis that bucket, we are making provision, the rate whatever is defined for that particular bucket. Page 9 of 21 Afcons Infrastructure Limited November 05, 2026 Aditya Bhartia: Just one last question.
Question
On Pune Ring Road, has there been any progress? Are we anticipating that project award in the near-term?
Answer, hitesh singh
Hitesh Singh: Pune Ring Road. Srinivasan Paramasivan: Pune Ring Road, we expect maybe Q4 it could get awarded because tender has already been floated with 45 days deadline for submission. After the submission, then it will take about a month for them to evaluate and give. We do expect the award of Pune Ring Road job in Q4. As this thing, as this fresh bid, depending on who is the L1, that will get awarded. And we are quite confident.
Question
Shravan Shah: Couple of questions. Sir, just wanted to get a clarification that for next year FY '28, when we are saying that we are looking at 20%-25% kind of a revenue growth, and even for the second half, we are saying confident that the things will improve on the execution front and obviously on the entire working capital payment, everything, and also the mobilization. So, then why not to give a guidance for the second half or maybe for the full year of FY '27? What stops us to give a guidance on the revenue and the margin for second half or maybe for full year of FY '27?
Answer, ramesh jha
Ramesh Jha: See, what we have explained is the guidance which was held back because of the geopolitical situation. There were challenges related to energy availability at many projects site. Because of that, we had held back. See, even when we speak today, we are experiencing in place like, say, Bangladesh, there is a challenge of availability of energy, and we are facing challenges in terms of the logistics for sending material to places in overseas location. So, considering that, we do not want to get into a situation where we factor something and then things go haywire. I know we are now expecting that situation should improve in terms of geopolitical situation. And once we see that the uncertainty around that is done away with, we will be resetting back the guidance.
Question
Shravan Shah: But then, sir, when we are saying FY '28, we will look at 20%-25%, but if we don't know the base, then also that also contracts that we are confident for FY '28, but we are not confident for the second half of FY, which is very immediate and one month is already passed for this quarter. So, some sense in terms of where we can look at the INR 5,300 crore revenue that we did in 1H or could it be a INR 6,000 crore, INR 6,500 crore, INR 7,000 crore, less than, higher than? Some idea on that front.
Answer, ramesh jha
Ramesh Jha: This 20%-25% number we are talking about, we are talking about that number from the full year of March 2026.
Question
Shravan Shah: Second, sir, on the margin front, so two, three things to get a clarification. What was the ECL provision for Q2? Second, my understanding is it would be around INR 86 odd crore kind of a number would be there. Even if we remove that also, then also the margin for what the second half, not as per you, but as per the reported is close to a kind of a 6.7%, which is given the similar revenue 1Q and Q2, it is significantly lower versus a 9.4% as per the reported. Still not able to understand what is impacted the margin in the second quarter. Related is now how we can look at the arbitration, whatever till now we have got, so in third and fourth quarter, how are we looking at the ar
Answer, ramesh jha
Ramesh Jha: No, see, the way we will have to look at it is, in terms of top line, when we do say around say INR 2,400 crore, INR 2,500 crore kind of a top line, at that number, that gives you a kind of break-even kind of a situation. Because the fixed cost, whatever you are incurring, that will remain fixed. Now, incrementally, over and above those numbers, say around INR 2,400 crore, INR 2,500 crore number, we start generating margin. If we look at the gross margin we are generating is around 35%, maybe say 10, 20 basis point here and there. So, we generate that 35% margin on the gross profit basis. Incrementally, every INR 100 crore, we will be generating another say INR 35 crore, and that adds to your EBITDA margin, to your profitability. Now, what we are trying to say that H2, we will have a better number than what we have done in H1, and that is where we are trying to give you a confidence that for the full year, we are looking at correcting the situation as far as the margins are concerned.
Answer, ramesh jha
Now, specifically, you are talking about the H1 number you are talking about. Maybe the difference we are having, we have explained that we include other income also as part of our operating income, and that is where we are having difference. Maybe you are looking at the number excluding the other income. If you look at the standalone Afcons profitability, that will give you a sense that the projects are generating sufficient margin, because as I explained that in one of the overseas entity, we had to make ECL provision, and that has pulled the overall profitability down.
Question
Previously, we were looking at INR 700 crore, INR 800 crore for this year and INR 600 crore, INR 650 crore for next year. How one can look at now? And in terms of the gross debt level, we were looking at kind of a INR 3,500 crore similar number.
Answer, ramesh jha
Ramesh Jha: See, t he CapEx number we have talked about for the FY '27 and '28, that number remains to be the same. It is not going to change. We are looking at for FY '27 CapEx in the range of INR 700 crores, and in FY '28 is around say INR 650 crore. That number remains to be the same. And in terms of debt, we had talked about that FY '27, on gross debt basis, we will be around INR 3,500 crore. On net debt basis, it will be around say INR 2,750 crore, INR 2,800 crore. That number will remain.
Answer, ramesh jha
I think important point in debt one needs to understand is, we will have of the March '27 debt, a significant portion will be a term debt towards the CapEx. The working capital debt will come down.
Question
Shirom Kapur: Just a couple of questions. You mentioned your order book is excluding L1 orders. So, would you be able to quantify and give us some detail on what these L1 orders are that you currently have?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: There are a couple of orders in Europe aggregating to around INR 4,000 crores.
Show 17 more questions
Question
Shirom Kapur: By when do you expect conversion of this?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: More or less, when you look at it on the INR 30,000 crore guidance, Europe, it takes a little longer time to convert into order as compared to other markets. Therefore, we have not considered this in FY '27. We do expect it in FY '28.
Question
Shirom Kapur: Second, in your last quarter, you mentioned a couple of big-ticket projects coming up, such as the Brahmaputra Tunnel and Dholera connectivity in Ahmedabad, about INR 18,000 crores, INR 19,000 crores worth of projects. Any update on these tenders, how we are positioned in these?
Answer, hitesh singh
Hitesh Singh: See, it will not be appropriate to discuss individual tenders, but as MD sir mentioned, we are fully confident that we will achieve our guidance of INR 30,000 crores. Pune Ring Road is already being discussed in the previous question. Brahmaputra, also the tenders are out. If everything goes fine, the award for that project should also happen this year as well, considering we will be L1 there. For other projects, there are certain big-ticket projects which are in the Page 12 of 21 Afcons Infrastructure Limited November 05, 2026 pipeline, and we are fairly confident, considering our strike rate and various considerations, we will achieve that target.
Question
Shirom Kapur: Just if I could ask, you have maintained your INR 30,000 crore order flow guidance for this year, but we are almost seven months in. Looking ahead to FY '28, directionally, maybe you do not have to quantify the guidance, but directionally, do you see that this INR 30,000 crores is largely a function of a lot of bunching up of orders from last year, and maybe next year the quantum could come down? Or do you expect this to continue growing in terms of order flow in FY '28- '29?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: From last year, only one job we got, INR 7,500 crores of Croatia, and all others are fresh jobs. Okay. So, it may not be appropriate to look at bunching up of orders from the previous year. As opposed to INR 7,500 crores of Croatia, we already have about INR 4,200 crores of other European jobs in the pipeline, which is marginally less, I would put it. So, for the next year order inflow guidance, we would say it will be too early to say. For the year, we will achieve first, and then we will come back to you with guidance for next year.
Answer, hitesh singh
Hitesh Singh: However, we will keep in mind our book-to-bill ratio and other risk factors. Even if there is a large availability, we will make sure that we will take the projects which we can deliver. So, all those factors will prevail.
Question
Shirom Kapur: Just lastly, you usually give a two-year prospect pipeline. You split it between your businesses and between domestic export. If you could just share those numbers.
Answer, hitesh singh
Hitesh Singh: Sure, we will do that. So, for the remaining H2, our pending pipeline, which we see is around INR 80,000 crores, and which is spread across segments. Hydro is around 35%, marine also 35%, surface, which is road and rail, is relatively less, around 10%, and urban infrastructure is 20%. For the next year, that is FY '28, and plus this quarter, which means around six quarters, the total pipeline, the total TAM for us is INR 3.6 lakh crores. Again, equally spread across segments, at 20% in hydro and underground, 27% in marine and industrial, 20% in surface and surface transport, and around 32% in urban infrastructure. In terms of geography, 65% of this pipeline is domestic and 35% is outside India.
Question
Page 13 of 21 Afcons Infrastructure Limited November 05, 2026 Ramesh Jha: No. As I explained that even this provisioning what we have done, we have explained that we are at a very advanced stage of certain arbitration award realization.
Answer, ramesh jha
We thought that let's have something in hand so that if there is a requirement to offer some discount, we will be able to offer and we can get the amounts realized. We don't foresee going forward there will be any requirement. Even if we are able to realize this amount, there will not be, maybe we can look at correction in the provisioning. And two, in one of the overseas subsidiary, based on the market feedback, we had done the provisioning. But then we will be following up with the customer for realization of that. And basis the progress, we will take call how to go about on the provisioning.
Answer, srinivasan paramasivan
Srinivasan Paramasivan: Third, newer arbitrations also, when we get arbitration award, we will keep some cushion for negotiation.
Question
Bhavik Shah: Sir, what is the receivables outstanding from these subsidiaries or projects which have been provided for in this round, like of the total receivables?
Answer, ramesh jha
Ramesh Jha: See, the total receivable, it would not be appropriate to give the number, but we have made sufficient provision, and we don't foresee that there will be any further requirement of any provisioning.
Question
Bhavik Shah: Sir, in our, say, order book, what is the proportion of, say, now the JJM order book and the JJM receivables which are outstanding?
Answer, ramesh jha
Ramesh Jha: We have explained in past that in JJM, we are doing project at two, three location, but the difficulty we are facing is in U.P. only. The pending order book in U.P. is around INR 474 crores now, which the discussion what we had with the customer, they are expecting us to complete 75%, and then after that, they will release that payment. So, going forward, we are going to execute. We will take whatever percentage we have completed to 75%, we will get the realization, and then with that money, we will try to complete. As far as outstanding is concerned, we have got INR 372 crores in U.P. outstanding. We have realized some amount of payment in last two, three months, but the amount realization is small. But I think going forward, the way forward we are looking at, it will not be a significant chunk getting released.
Answer, ramesh jha
We will have to progressively complete 75%, and against that, we will get the realization of payment.
Question
Bhavik Shah: Sir, outstanding is INR 372 crores, or we have realized INR 372 crores till now? Page 14 of 21 Afcons Infrastructure Limited November 05, 2026 Ramesh Jha: No, outstanding amount is INR 372 crores.
Answer, ramesh jha
This amount we had talked about in past, it used to be in excess of INR 400 crore, but then gradually, they have released some payment. Now, going forward, we have got a plan we have discussed with the customer. They are looking at completing certain segment, which progressively we will complete, we will cross the threshold of 75%, and once we complete, they will release the payment.
Question
Bhavik Shah: Sir, you told that some projects are seeing slowdown from the customer's end. Which are these projects and which you see will pick up execution in H2?
Answer, ramesh jha
Ramesh Jha: No, sir, see, slowdown in the sense what we have talked about, one, we have talked about that the payments are getting stretched. That we are seeing that it is across the spectrum, that kind of a trend we are seeing. In second half, the execution pace picking up, we have talked about in past that in some of the Maharashtra projects, there were certain land acquisition-related issues. There were certain design-related aspects which had to be changed. Those has already been completed, and going forward, we will be looking at Q3, Q4 faster pace of execution. Also, some of the project which is into offshore marine-related project, which generally slows down in monsoon season, we will see a pickup there.
Question
Mudit Bhandari: Sir, over the last few quarters, we have seen this in terms of various projects, like either change in scope, like you recently mentioned, in terms of either design-related or any other issues or pending clearances, either in terms of land acquisition or any other clearances. So, as we speak till now, whether the work has actually started over the projects that we are talking about since it's been some time that execution is yet to start?
Answer, ramesh jha
Ramesh Jha: No, the work was happening. In those projects, work was happening. Please understand that the project we are talking about are long stretch projects. It runs into kilometers. So, the customer had given certain land with which we had commenced the work. Certain land they had to acquire, and there were certain challenges in the acquisition, or maybe during the course on some aspect of the project, there is a change in design. So, as I explained that those aspects we have already crossed, and going forward, we will be looking at a faster execution in the entire stretch of the project.
Answer, ramesh jha
So, we were already working in those projects.
Question
Mudit Bhandari: When we say that there would be improvement in collection in the second half, till now, if you have seen any major collection being realized post-September till now, or any other in terms of interactions that you have seen that in terms of visibility of improvement of collection? Page 15 of 21 Afcons Infrastructure Limited November 05, 2026 Ramesh Jha: See, there are three aspects to it.
Answer, ramesh jha
One, what we are saying is the work done we are doing, the customers are taking time in certifying and releasing the payment. I am not saying that they are not releasing. What I am saying is they are stretching the payment. That is one. Whatever work done we are doing, we are getting it, and going forward also we will get. When we are talking about any number for the March, we have factored in this kind of a stretched payment. Two, what we are talking about is we have got certain stuck receivable which we have to receive.
Answer, ramesh jha
Say, we have completed the project, some places the retention is to be released, likewise. Those collections, we had set a target for this financial year. We had set the target for first half also. We have seen a substantial movement in first half, and in the close interaction with the customer, we are quite confident that the target we have set for this financial year, we are going to achieve that number. So, that will give us a big boost in terms of fund getting into the company from the stuck receivable. So, that will bring down the, say, receivables or contract asset, and that will also help in reduction of debt, net working capital, and that will aid to the cash flow from operation. The third aspect we are talking about is the new projects we have won now.
Answer, ramesh jha
For those projects, there is a eligibility of mobilization advance. So, till we have finalized the September accounts, we have not realized those advances. Those advances are going to get fructify in, say, Q3 and Q4. That is also going to aid the fund availability for the company, and that is how we are saying that we will see an improvement in cash flow from operations.
Question
Mudit Bhandari: Lastly, when you said that our other cost has three other things, including ECL provision, arbitration receivable provision, and one overseas subsidiary’s provision, so is it possible to quantify this amount to get the correct run rate of other cost?
Answer, ramesh jha
Ramesh Jha: See, as I explained that ECL provision, we have done because we have moved to a new ECL provisioning matrix, basis that we have done the ECL provisioning. They will not be as such, you will be able to extrapolate that ECL provisioning for the remaining period, because that was on certain specific aspect we have made that provisioning. Now, going forward, I don't think that there will be a similar ECL provisioning in, say, Q3, Q4, or maybe future period. Even on this provisioning aspect what we have done, if we see the collection is happening, then maybe we will see how do we take this ECL provisioning.
Question
Balasubramanian A: Sir, actually, tunneling turnover technically starts in November onwards. If you look at our depreciation anywhere between INR 85 crore-INR 90 crore range, but historically nearly INR 120 crore-INR 130 crore range. I think once that TBM-related tunneling activities will ramp up, whether the depreciation run rate will hit nearly INR 120 crore-INR 130 crore after quarter 3, sir? Page 16 of 21 Afcons Infrastructure Limited November 05, 2026 Ramesh Jha: Yes.
Answer, ramesh jha
You are right. The depreciation will go up. As the TBM starts operating, you will have uptick in the turnover and also the contribution, because the TBM-related tunneling, we have explained in past that it generates a higher contribution margin. You are right, the depreciation will go up, but at the same time, it will also take the top line up, and it will also contribute more margin.
Question
Balasubramanian A: Also, is there any risk on that Vadhavan Port execution side? Because the Vadhavan is restricted to geotechnical investigation and design due to land or reclamation handover delays and public agitations. What are the risks we have? Are we protected in terms of contractual or escalation clauses or equipment compensation in those sites?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: In Vadhavan Port, there are three aspects. One is our own execution. Two is approach. The approach, one project is being handled by NHAI, another project is handled by Vadhavan Port only. Both are already delayed. With respect to our work, we have already started geotechnical investigation. We have not faced any local issues so far.
Answer, srinivasan paramasivan
We have kind of engaged locals also wherever needed, all that. But the issue would remain without the approach being handed over to us, which is contractually to be handed over to us, there is going to be a challenge for a full-scale working. Clients are in discussion with us for alternative methods of doing the work, which is something currently under discussion, as this forms part of a follow-up of projects in the PRAGATI portal. There could be specific discussion around that. The alternatives are being discussed as to how to get the work going, not confining ourself only to geotechnical and design. In terms of extension of time and other areas, we don't find any issues. But the issue could come up on the execution side till the alternatives are frozen and cost related to the additional work is frozen.
Answer, srinivasan paramasivan
To that extent, the turnover could be less till that time. But we are working on the geotechnical based on which designs and all we will complete.
Question
Shravan Shah: On the finance cost, given obviously the debt has increased, excluding the bank charges, the current INR 136 odd crore kind of a quarterly run rate, will it be higher in the second half or given the way we are looking at the reduction in the working capital leading to a reduction in the gross debt, but will that impact will be in the Q4 onwards or maybe Q1 onwards, but this run rate or maybe it would be increasing the finance cost at least in the second half? Page 18 of 21 Afcons Infrastructure Limited November 05, 2026 Ramesh Jha: See, this finance cost what we are looking at, I don't think that from this kind of a run rate it is going to go up.
Answer, ramesh jha
Only thing is incrementally if we back project and if we are required to, if the bank guarantee utilization goes up, there will be increase in the bank guarantee cost. But as far as the borrowing cost is concerned, I don't think that we are going to cross the kind of run rate we have clocked, say, in H1.
Question
Yogesh Doshi: The Shapoorji Group and Afcons are known as the best EPC companies overall in the world. But if we can’t insist the payment schedule with Indian government, we should be a little choosy about taking all the projects where you feel that payment can be an issue. We should be only concentrating and focusing on projects where we see the payment cycle and promise of facilities are good enough. Instead of having INR 50,000 crore of orders, we can have INR 25,000 crore of orders for next two years. Anyway, we are doing only INR 10,000 crore, INR 12,000 crore orders. We can choose among the projects, no?
Answer, srinivasan paramasivan
Srinivasan Paramasivan: Traditionally, if you look at why Afcons is held at a premium, one, corporate governance. Second, if you look at profitability in the infrastructure segment, in normal circumstances, we have always been at the higher end of the profit spectrum. And EBITDA margin in excess of 11%, 12%, I don't think most of the construction companies achieve. You are aware of yourself. As you are an investor, you know these things. Third, there is a huge international recognition which adds to the intrinsic value, even though it may not necessarily convert into transactional value. At some stage, if some stocks have moved, like stocks, some of the other stocks have moved to a portfolio stock.
Answer, srinivasan paramasivan
At some stage, Afcons could also move into portfolio stock. That is what we expect. Therefore, taking that into consideration, I think in our assessment, Afcons would continue to be a premium segment. As you know, Afcons is the eighth-largest player in marine in the world, 12th-largest player of bridges in the world. These are not my statistics. These are Engineering News-Record U.S.A. statistics. We are the only company for 11 years in succession, we have been adjudged as the Most Admired or Most Innovative Knowledge Enterprise at India level, Asia-Pacific level, and global level.
Question
Thank you, sir. Thank you for enlightening individual shareholders with this confidence. Thank you very much.
Answer, srinivasan paramasivan
Srinivasan Paramasivan: Thank you very much. Happy Deepavali and Happy New Year to you all. As conveyed to you, we are looking at a 20%-25% growth in FY '28, and the second half will be better than first half. We stand by our guidance of INR 30,000 crore of order book, and we are looking forward to exciting times back. Thank you.
Questions about this call
- When was the Afcons Infrastructure Q2 FY27 earnings call transcript filed?
- Afcons Infrastructure filed the transcript with the exchange on 6 Nov 2026. This page is built from that transcript.
- What does this page list?
- 70 statements from the transcript across 12 topics, 33 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 27 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.