Afcons Infrastructure Q1 FY27 earnings call: Afcons Infrastructure Limited recorded order inflows of INR13,219 crores during the first quarter of '27
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company recorded order inflows of INR13,219 crores during the first quarter of '27. The company is confident of achieving its full-year order inflow guidance of INR30,000 crores, supported by a bid pipeline of approximately INR1.5 lakh crores for the remaining 9 months of financial '27 and INR3.96 lakh crores for the next 2 years across transportation, marine, hydro, underground, water, urban infrastructure, and industrial infrastructure segments. The Brahmaputra tunnel, a big-ticket project in the long-term pipeline, is around INR19,000 crores. The company reported an EBITDA margin of 9.6% in the first quarter of '27; lower revenues during the quarter primarily moderated profitability. Of Afcons Infrastructure Limited's advances, 62% were interest-free and 38% were interest-bearing in the first quarter of '27.
The numbers management gave
Results
- The company reported an EBITDA margin of 9.6% in the first quarter of '27; lower revenues during the quarter primarily moderated profitability.
Show source
Coming to profitability, we reported an EBITDA margin of 9.6% during the quarter.
- Some challenges that affected Afcons Infrastructure Limited's financial '26 continued into the first quarter of the current year.
Show source
To conclude, while some of the challenges that affected financial '26 have continued into the first quarter of the current year, we remain encouraged by the conversion of key orders and opportunities ahead.
- The company reported EBITDA of INR263 crores, or 9.6%, in the first quarter of '27, down 41% from INR445 crores, or 13%, in the previous year quarter 1.
Show source
In terms of EBITDA for the quarter, we have done INR263 crores, which is 9.6%.
- The company included around INR57 crores of other operating income in its EBITDA calculation for the Q1 period.
Show source
So, for the Q1 period, around INR57 crores is other operating income, which we have factored in EBITDA calculation.
- The company recorded profit before tax of INR51 crores in the first quarter of '27, compared with INR183 crores in the previous year Q1.
Show source
In terms of profit before tax, for this period, we have done INR51 crores of profit, which is significantly down.
- The company recorded profit after tax of INR30 crores in the first quarter of '27, compared with INR137 crores in the previous year quarter 1; lower overall turnover impacted profits.
Show source
And profit after tax is INR30 crores, which is also significantly down because we had done INR137 crores of profit after tax in the previous year quarter 1.
Show 16 more statements
Results
- The company had higher average borrowings in the first quarter of '27, which increased interest cost; new interest-bearing advances received during the last 12 to 15 months also increased interest cost on client advances.
Show source
Because of this, interest cost has gone up.
- Depreciation was INR83.52 crores, or 3.06% of turnover, in the first quarter of '27; virtually no TBM operations meant the accelerated depreciation charge was absent that quarter.
Show source
In terms of EBITDA, the depreciation is at INR83.52 crores, which is 3.06% of the turnover.
- Tax rate was almost 40% in the first quarter of '27, in part because Afcons' standalone profit was taxed at 25%, while closed projects in JVs and subsidiaries had minor administrative expenses and provisions leading to small losses in consolidated profit, amplified by lower Afcons profit.
Show source
The tax rate is working out almost 40%.
- Some JVs pay tax at a rate in the range of 35% to 36%.
Show source
Also, few JVs pay tax rate in the range of 35% to 36%.
- Historical performance generally had H1 at around 40% to 45% and H2 at around 55% to 60%.
Show source
Ramesh Jha: So, just to answer you, in past, if we see the performance of the company in generally, H1 remains to be around 40%, 45%, and H2 remains around 55% to 60%.
- The company generally makes better margins on overseas projects, with margins around 200 to 300 basis points higher in the overseas market than in the domestic market.
Show source
Ramesh Jha: So, in overseas project, we generally make better margin, and the margin -- the delta in, say, domestic versus overseas is around 200 to 300 basis points, which is higher in overseas market.
- For Afcons Infrastructure Limited in the quarter, tax arising from joint ventures was around INR4 crores to INR5 crores; the tax percentage appeared to be around 40% because profitability was low.
Show source
But the amount if you see per se is not that big number, it is around said INR4 crores to INR5 crores.
- Overseas revenue was around 16% and domestic revenue was 84% in the first quarter of '27.
Show source
So, in Q1, we are we are having overseas revenue around 16% from overseas market, domestic is 84%.
- Efforts to reduce costs on possible revenue were partially offset by increases in energy, transport, and logistics costs.
Show source
We have put lot of efforts towards reducing cost on the possible revenue, but that has been partially offset by increase in energy, transport, and logistics cost.
- Deterioration in receivables, debt, or contract assets in the first quarter of this year was not as bad as in last year Q1.
Show source
But the deterioration happened in terms of say receivables or debt number or say contract assets number in last year Q1, this year, it has not gone that bad.
- Working capital days had marginally increased from the March number.
Show source
Ramesh Jha: It has marginally increased from the March number.
Money and capital
- Of Afcons Infrastructure Limited's advances, 62% were interest-free and 38% were interest-bearing in the first quarter of '27.
Show source
Currently, 62% of our advances are interest-free and 38% of the advances are interest-bearing.
- Debt increased in the first quarter of '27 as it funded operations amid continuing payment issues and made sizable capex payments.
Show source
Also, we have done sizable capex payment this quarter, so debt has moved to a higher number.
- Debt to equity was around 0.68x of net worth on a net debt basis in the first quarter of '27.
Show source
On net debt basis, the debt to equity is around 0.68x of the net worth.
- Net debt-to-equity ratio was around 0.68 in Q1, and its numbers had slightly increased compared with the March number.
Show source
But in terms of absolute debt number, we have talked about that the debt-to-equity is around 0.68 on net debt-to-equity basis, and numbers have slightly gone up as compared to the March number.
- The company capitalized close to INR150 crores of capex in Q1, with a sizable amount in CWIP.
Show source
Ramesh Jha: So, capex in Q1, we have done close to INR150 crores capitalized, but then there is a sizable amount in CWIP.
What it expects ahead
What management expects
- The company is confident of achieving its full-year order inflow guidance of INR30,000 crores, supported by a bid pipeline of approximately INR1.5 lakh crores for the remaining 9 months of financial '27 and INR3.96 lakh crores for the next 2 years across transportation, marine, hydro, underground, water, urban infrastructure, and industrial infrastructure segments.
Show source
This is supported by our healthy bid pipeline of approximately INR1.5 lakh crores for the remaining 9 months of financial '27, and INR3.96 lakh crores for the next 2 years across transportation, marine, hydro, underground, water, urban infrastructure, and industrial infrastructure segments.
- The company expects other income to be somewhere around INR400 for the year.
Show source
So, this year also, we'll be in the range of say, for the year somewhere around INR400 or so.
- The company expects execution to significantly pick up from Q3 onwards, with a very strong H2, because the around INR16,000 crores of orders booked will take time to convert into revenue and projects in the around INR32,000 crores order book have faced slow progress, land acquisition issues, scope changes and unavailable work fronts.
Show source
As things stand, we expect the execution to significantly pick up from Q3 onwards, and so, we'll have a very strong H2, and all these orders whatever we have booked and the balance period in this year whatever orders we are going to book, we'll have a very sizable order booking in our Page 14 of 20 Afcons Infrastructure Limited August 10, 2026 hand matured for construction for the next financial year FY28.
- About 11% of Afcons Infrastructure Limited's orders are slow-moving or otherwise, and roughly 20% are in the initial phase, creating challenges in converting orders into turnover; conversion will start improving in the second half-year.
Show source
So, these are the -- when nearly about 11% of the orders are slow-moving or other thing, and another about roughly about 20% of the orders are in the initial phase, then that is why there are challenges in terms of converting it into turnover, which will start improving in the second half-year.
- The company hopes overseas revenue will return to a minimum of 30% as its order book moves to 30% from the overseas market.
Show source
So, we hope that we will go back to 30% from overseas market, that is for minimum, and then as the order book moves 30% from overseas market, revenue also will go back to 30% from the overseas market.
- The company expects the Mumbai-Ahmedabad High Speed Rail C2 project to move into its next phase of execution after reaching the planned milestone, with the TBM main tunneling drives expected to start in the coming months.
Show source
Having achieved this milestone as planned, we expect the project to move into its next phase of execution, with the TBM main tunneling drives expected to start in the coming months.
Show 18 more statements
What management expects
- The company is targeting significantly improved order booking and balance-sheet improvement in FY2027 by collecting some of its stuck receivables.
Show source
In FY2027, we are targeting to significantly improve the order booking and improve the balance sheet by collecting some of the stuck receivables.
- The company expects interest cost to go down in the coming quarter because substantial order advances have not yet come into the company, many current international orders have interest-free advances, and domestic orders have quite low interest rates.
Show source
So, we expect the interest cost to go down in the coming quarter.
- The company is directionally looking at a similar H1/H2 performance pattern in the current year, with Q3 and Q4 expected to bounce back to the levels it generated earlier.
Show source
Q3, Q4 is going to be where we'll bounce back to the levels we were generating earlier.
- The company is looking at a strong FY28 and FY29 as order booking ramps up and it targets improved financial health.
Show source
And in terms of, you know, as the order booking is ramping up, and the way we are targeting to reach in terms of financial health, we are looking at a strong FY28 and FY29.
- The company expects a sizable ramp-up in execution in FY28, as orders booked and orders to be booked during the balance period of this year mature for construction in the next financial year.
Show source
So, that's where we are looking at that FY28, we'll have a sizable ramp-up in terms of execution.
- The company expects execution to pick up better in the third and fourth quarter as right-of-way and related issues are getting resolved, with proactive involvement from the Government of Maharashtra helping resolve issues and make projects available for execution.
Show source
That is why we are saying the third and fourth quarter, it will pick up better.
- The company expects improved operational momentum and gradual strengthening of financial performance as projects move into their main execution phases. Replaced by a later filing.
Show source
As these projects progressively move into the main execution phases, we expect improved operational momentum and a gradual strengthening of our financial performance.
- Management is rigorously working to collect stuck receivables and is confident of turning things around this year. Replaced by a later filing.
Show source
However, management is rigorously working towards stuck collection, and we are confident to turn things around this year.
Orders
- The company recorded order inflows of INR13,219 crores during the first quarter of '27.
Show source
Coming to order book, I am pleased to share that we have begun financial year '27 on a positive note with a healthy order inflows of INR13,219 crores during the first quarter.
- Order book stood at INR43,290 crores at the end of the first quarter of '27.
Show source
With these orders, our order book stood at INR43,290 crores at the end of the quarter, providing strong visibility for future revenues.
- The company had booked orders of INR15,700 crores for the year to date, including orders received up to date.
Show source
As on date, our orders booked for the year stands at INR15,700 crores, including orders received up to date.
- The company had booked orders amounting to INR15,695 crores in FY27 to date, taking its pending order book above INR45,000 crores.
Show source
In FY27, we have booked order amounting to INR15,695 crores till now, taking the pending order book in excess of INR45,000 crores.
- Order inflow guidance is INR30,000 crores, and it hopes to provide better guidance as it proceeds from the current INR16,000.
Show source
And currently we are at 16,000, and we hope as we proceed, we will be in a position to guide you better, and today's guidance is INR30,000 crores.
- Of Afcons Infrastructure Limited's overall order book value, roughly 5.65% is slow-moving, Bangladesh orders constitute about 2%, and Jal Jeevan Mission orders constitute about 3%; together, roughly 11% of orders are slow-moving or otherwise.
Show source
So, these three put together, roughly around 11% is what we can categorize, or either slow-moving or otherwise.
- Order book had moved back to around 25% from the overseas market, and it expects a lot of other overseas projects.
Show source
At the moment, the order book what we have, we have moved back to around say 25% from overseas market, and there are a lot of other projects in overseas market we are expecting.
- The company had no orders pending conversion from L1 to an order.
Show source
With this, there is no order pending to be converted from L1 to that of an order.
- The Croatia railway project is the largest single order ever secured by Afcons Infrastructure Limited.
Show source
The Croatia railway project represents the largest single order ever secured by Afcons, while the Vadhvan Port project provides us with the opportunity to construct the world's second largest breakwater.
- The company has a strong pipeline in the domestic market and a good pipeline in the international market. Replaced by a later filing.
Show source
So, we have a strong pipeline in the domestic market, and similarly in the international market also, there's quite a good pipeline available to us.
What it is building and selling
Projects and capacity
- The Brahmaputra tunnel, a big-ticket project in the long-term pipeline, is around INR19,000 crores.
Show source
Paramasivan Srinivasan: Some of the big-ticket projects if you can talk about is Brahmaputra tunnel is something which is coming up, which is around INR19,000 crores.
- Dholera connectivity in Ahmedabad, a big-ticket project in the long-term pipeline, is about INR18,000 crores.
Show source
And there is Dholera connectivity in Ahmedabad, which is about INR18,000 crores.
- Elevated expressways and other projects in the long-term pipeline are in excess of all around INR4,000 crores to INR5,000 crores.
Show source
And many other projects of the sizes of elevated expressways and other things are coming in excess of all around INR4,000 crores to INR5,000 crores.
- Bridges in the long-term pipeline are in the region of between INR3,000 crores to INR5,000 crores.
Show source
There are number of bridges which are coming up, which is also in the region of between INR3,000 crores to INR5,000 crores.
- Both tunnel boring machines for Afcons Infrastructure Limited's Mumbai-Ahmedabad High Speed Rail C2 package commenced their initial tunneling drives as scheduled.
Show source
On the operations front, I am pleased to share that both tunnel boring machines for our Mumbai-Ahmedabad High Speed Rail C2 package successfully commenced their initial tunneling drives as per schedule.
- The Vadhvan Port project gives Afcons Infrastructure Limited the opportunity to construct the world's second largest breakwater.
Show source
The Croatia railway project represents the largest single order ever secured by Afcons, while the Vadhvan Port project provides us with the opportunity to construct the world's second largest breakwater.
Show 1 more statement
Projects and capacity
- The company has already started work in the water portion and will commence the land portion in the second half of the year.
Show source
And otherwise, we have already started in the water portion and other things, land portion also, we will commence in the second half of the year.
Risks, rules and outside factors
Rules and policy
- In some overseas locations such as Bangladesh, tax is charged on turnover.
Show source
Second, in some of the overseas locations like Bangladesh, tax is charged on turnover.
Everything else said on the call
Other
- The company continues to make ECL provisions under a framework approved by the Board, using guidance from professionals; it does not foresee project-specific provisioning going forward, though it makes provisions under the framework on a prudent basis.
Show source
Ramesh Jha: So, as far as ECL provisioning is concerned, we have explained last time that we have made a framework for ECL provisioning, and which was approved by the board, and which was, we had taken professional guidance from experts in this particular field, and basis that framework was devised, and basis that framework, we have started making provisioning from last year, and we continue to do the provisioning on that basis.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Aditya Bhartia: Hi, sir. In the opening remarks, we spoke about some of the execution challenges getting addressed over the next couple of quarters. Just wanted to check, are we seeing some concrete evidence of that? Are we seeing execution pace picking up across multiple projects, or at this stage, it is a bit of a hope?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: At this stage, we are definitely seeing the symptoms of it all happening, and some of the issues with respect to land-related issues are getting addressed by proactive activities undertaken by Maharashtra government. So, that would result in significant release of lands, whichever places are there. There have been regular reviews from the government, which helps in pushing the project ahead. In there are similarly in Madhya Pradesh where we have a project also where there is a compensation-related issue is getting resolved shortly. Movement has happened. So, there also, out of two projects, one project will start moving up immediately. That is what we look.
Answer, paramasivan srinivasan
Therefore, the execution-related challenges with respect to blocked-up things is more or less getting over. And with geopolitical issues becoming a little improved as compared to the last quarter, I would put it, things in terms of movement of materials, though it's a little expensive as compared to the earlier period, it would still be improved in terms of movement of materials for our overseas projects. And with these two, we do expect there are clear indications that things are moving towards positivity. Q3 and Q4, we believe, would see significant uptick. Page 7 of 20 Afcons Infrastructure Limited August 10, 2026 Aditya Bhartia: Perfect, perfect.
Question
That's great to hear, sir. Sir, my next question is on some of the large projects that we are having, like the Croatia project, the Vadhavan project. For these two projects, when should we expect work to start, and is it that the initial part would be more about designing and to that extent, there'll be lesser revenue accretion, and only over a period of time these projects should be picking up pace, if you could kind of indicate us the execution timelines around that? And a related question is on the HSR project. How should we think about that in terms of receiving payments in respect of past work that is done and execution pace from here on? Thank you so much.
Answer, paramasivan srinivasan
Paramasivan Srinivasan: With respect to Croatia, we believe the current year, there will be a minuscule expenditure as and next financial year onwards, Croatia will pick up. With respect to Vadhavan project, alternative methods are being discussed with the client, and currently, the approach road and also the reclamation-related work is yet to be completed. And you would have read in the newspaper about the agitation and all around that. So, we are working with the client proactively with the thing, but current year, it will only be a geotechnical investigation and related design-related work and initial installations that will only happen in Vadhavan. All others, there are also aggressive push from the government also to see that certain facilities or certain approaches are handed over to us so that we can start the work. So, therefore, in both the projects effectively, current year, there will be minuscule turnover. With respect to HSR, whatever turnover we have done, all these have been paid for regularly.
Answer, paramasivan srinivasan
And the tunneling- related turnover will commence from November, technically. Until that time, the initial drive will happen for about 3 months, and after that, we do expect a good turnover. As we had conveyed earlier also, tunneling carries higher level of turnover. So, therefore, as we start tunneling deeper, we will get into the turnover properly. We are in the final stages of getting the settlement with respect to force majeure done, and most likely, it will get settled in the current quarter.
Question
Shravan Shah: Hi, sir. A couple of questions. So, I was listening to your opening comments and the reply to the first participant questions. So, broadly, how So, let me break it into a 2-3 parts. So, do we see Q2 revenue be a Q-o-Q flat or a lower, and then when we are saying the H2 would be a better execution, I understand, though we are not providing a full-year guidance on the execution front, but on a directional front, even if we let's assume a 20% kind of a growth, is it possible or not? Page 8 of 20 Afcons Infrastructure Limited August 10, 2026 Even if that is possible, then for full year, the broad, rough, my calculation says we will be a kind of a flattish or maybe a 1% kind of a gr
Answer, ramesh jha
Ramesh Jha: So, see, we have already talked about that at this point in time, it doesn't make any sense to give any direction on the top line or any profitability-related guidance. So, we are not commenting on Q2 how it is going to pan out or how the year is going to pan out. But as things stand, things are moving in our, you know, whatever expectations we had, and we aspire that we should, you know, build a very strong order book in this financial year, and we should also improve the balance sheet this year by way of collecting, by way of reducing our contract assets and receivables, and by reducing our debt. So, we should be in a very strong position by end of the year in terms of order booking, in terms of financial health, and then we should ramp up the progress in the financial year '28.
Question
Shravan Shah: Yes, sir, I understand. But still, again harping on the same thing, because a directional, because when we are saying that in H2, we should see a strong execution. So, how So -- sir, my point my point, sir, listen to me, sir. My point is that, because if we will be a doing a kind of a flat, because that's what the broad, even if I take a 20% kind of a growth in the second half and maybe a flat in the Q2, that means this would be the fourth year where we will be a kind of a having a flat revenue from the what we have done in the in the FY23 from there till now. We will be having a kind of a flat growth. So, that's the, and at the same time at the PAT level, we will be drawing a
Answer, ramesh jha
Ramesh Jha: So, just to answer you, in past, if we see the performance of the company in generally, H1 remains to be around 40%, 45%, and H2 remains around 55% to 60%. Directionally, if you ask me, we are looking at a similar kind of a situation this year also. Q3, Q4 is going to be where we'll bounce back to the levels we were generating earlier. And in terms of, you know, as the order booking is ramping up, and the way we are targeting to reach in terms of financial health, we are looking at a strong FY28 and FY29.
Question
Shravan Shah: Okay, great. Sir, is it possible to share couple of balance sheet data points, because when we are saying we have mentioned that the I think the debt would have also increased, so if you can specify the particularly the gross debt and then the cash level, and also the some of the inventory, trade payable, debtor absolute numbers, and maybe mobilization advance, retention, unbilled. So, that will help us to understand how the things are either worsening or maybe at a similar level. So, that would be helpful.
Answer, ramesh jha
Ramesh Jha: See, generally, the balance sheet numbers are disclosed in H1, so maybe, you know, in September, we'll be coming out with the detailed numbers. So, you'll be able to figure out. But in terms of Q1 numbers, generally, we have seen almost say last 10-15 years, we have seen that Page 9 of 20 Afcons Infrastructure Limited August 10, 2026 Q1 numbers will be always, you know, higher than the annual number, March number. So, this is the trend. But in terms of absolute debt number, we have talked about that the debt-to-equity is around 0.68 on net debt-to-equity basis, and numbers have slightly gone up as compared to the March number. But the deterioration happened in terms of say receivables or debt number or say contract assets number in last year Q1, this year, it has not gone that bad.
Question
Shravan Shah: But, sir, unless we give the -- some directional numbers, would be difficult to kind of a quantify what we are saying. So, at least a gross debt level, what's the gross debt number and working capital days, what was in FY26 and now how much increase has happened?
Answer, ramesh jha
Ramesh Jha: It is at a elevated level as compared to a March number, but since, you know, we have the auditors have not certified the balance sheet number, it will not be prudent on our part to, you know, give those numbers.
Question
Shravan Shah: Yes, because all other companies also provide. I understand it is un-unaudited number, but at least to get a sense and how one can pencil in the numbers, unless we have any anything on that front, would be it becomes a very, very difficult to kind of a pencil in how one can look at the full year and maybe the next year. So, political sorry, sorry for that, a diplomatic answer would be a difficult to kind of a convert into the numbers. So, that's the my suggestion. Thanks.
Answer, ramesh jha
Ramesh Jha: See, you will be able to calculate these numbers. You look at the March debt number, you look at the March net worth number, and what we are saying that at this point in time, the debt to equity on a net debt basis is around 0.68, so you'll be able to calculate it. It's very simple. I'm not spelling out because, those numbers have not been audited, so it is not advisable that, we talk on a public forum these numbers. That's the limited point. You'll be able to very easily calculate.
Question
Shravan Shah: But working capital days sir we are not saying directionally also how much 10 days, 20 days increase something.
Answer, ramesh jha
Ramesh Jha: It has marginally increased from the March number.
Question
Shravan Shah: Okay, okay. Thank you, sir.
Answer, ramesh jha
Ramesh Jha: So, you are right that it's a very difficult situation where we need to manage the execution as well as we need to manage liquidity, and we are not unduly overexposing ourselves with some of the customer. So, this is, this approach, we are not approaching with all the customers. There are certain customers where we had seen that there were some challenges in those project, and in those projects only, we are taking such kind of stand like say project in Bangladesh or some water-related project. We are giving funds to the project based on the collection that project is generating. Otherwise, in excluding these projects, the payments are forthcoming. The projects' cash flows are positive. So, such projects, we are supporting with wherever there is a temporary mismatch, and if there is any requirement for the completion of the project.
Answer, ramesh jha
Balasubramanian: Okay, sir. Sir, our strategic equipment base is nearly INR4,300 crores, I think, which creates high depreciation as well as maintenance burden. If you look at last few years, our topline is anywhere between INR10,000 crores to INR13,000 crores range, but if you look at our interest cost and depreciation, it's substantially increased. Is there any thought process or strategic shifting towards asset-light model where you can like lease specialized equipments or to form a JV with equipment providers for some specific mega projects, so thereby, we can improve our ROI and ROCE profiles? So, what's your thought process on owning most of the equipments as well as moving towards leasing or renting the equipments?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: For strategic equipments only, we keep investing. We don't invest in all the equipments, number one. Number two, as we had explained in the past also, in outside of India, especially in Africa and all, the cost of rentals are very high. An equipment value is sought to be realized in 9 months' time in Africa, as opposed to some 48 months to 60 months in India. Therefore, in some of those cases also, we do invest equipments on the higher side, and we get commensurate returns as well. Third, in marine, we hold strategic advantage by having a large fleet of equipments, and that is something which helps us in some of backing up marine projects and other thing. And only thing as last couple of years, our turnover has stagnated or slightly de-grown, it creates an impression that it is on the higher side.
Answer, paramasivan srinivasan
It is not so. As we move forward, you will find that we have an asset turnover ratio also significantly improved. So, we have not invested in any assets which is not of strategic importance. Balasubramanian: Got it, sir. Thank you.
Question
Hitesh Singh: Sure. So, on the long-term pipeline, as MD sir mentioned in his speech, our long-term pipeline is close to INR4 lakh crores. In this part also, the pipeline is evenly distributed. Around 36% is from the urban infrastructure space, and surface transport will be around 20%, the hydro business will be relatively less, it's around 15%, and remainder will be marine and industrial. Abhinav: Understood. Sir, can you give some details on the urban project like which are the big-ticket projects that are coming in the near term?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: Some of the big-ticket projects if you can talk about is Brahmaputra tunnel is something which is coming up, which is around INR19,000 crores. And there is Dholera connectivity in Ahmedabad, which is about INR18,000 crores. And many other projects of the sizes of elevated expressways and other things are coming in excess of all around INR4,000 crores to INR5,000 crores. There are number of bridges which are coming up, which is also in the region of between INR3,000 crores to INR5,000 crores. So, we have a strong pipeline in the domestic market, and similarly in the international market also, there's quite a good pipeline available to us. Abhinav: Understood. Sir, my last question is on the depreciation of TBM.
Answer, ramesh jha
Ramesh Jha: So, TBM, we are accounting for as per the Companies Act prescribed rate, and we'll continue to account for those depreciations. Abhinav: Understood. Thank you, sir.
Show 19 more questions
Question
Parvez Qazi: Yes, hi. Good afternoon. Thanks for taking my question. So, couple of questions from my side. First, what was the capex that we undertook in Q1?
Answer, ramesh jha
Ramesh Jha: So, capex in Q1, we have done close to INR150 crores capitalized, but then there is a sizable amount in CWIP. Page 12 of 20 Afcons Infrastructure Limited August 10, 2026 Parvez Qazi: Possible to quantify that, or will it be same as more or less same as what it was at the end of March?
Question
Parvez Qazi: Got it. On the order intake front, we already have won about INR15,000-odd crores this year. So, for the year as a whole, fair to say somewhere around INR30,000-odd crores is something that we can look at?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: Yes, INR30,000 crores, we are very confident of booking at a minimum.
Question
Parvez Qazi: Sure. And last question to Ramesh, other income, I mean, which you mentioned about INR57- odd crores this year, now I assume forex gains, et cetera., everything is included in that. For the year as a whole, what kind of number that could be? Because I mean, it has come down. We used to have almost about INR450 to INR470-odd crores of forex gain earlier. Now, it's reduced, so what number could it be?
Answer, ramesh jha
Ramesh Jha: So, what number you are talking about in other income around INR450-INR470 crores, it used to be a combination of these factors like say arbitration interest, foreign currency gain, and the miscellaneous income and some of the other stuff also like insurance claim and other stuff. Now, for this quarter, the number is low, because we also try to close things in March wherever possible, and the activity also goes up in H2. So, this year also, we'll be in the range of say, for the year somewhere around INR400 or so.
Question
Aritra Banerjee: Yes, hi. Thanks for the opportunity. Just on the order inflow front, because we’ve already recorded such healthy order inflows, what is the upside risk that will overshoot the 30,000-order inflow target for FY27?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: I would say that first, let us achieve the INR30,000 crores, then we will see what is the upside we are in a position to make it. And currently we are at 16,000, and we hope as we proceed, we will be in a position to guide you better, and today's guidance is INR30,000 crores.
Question
Aritra Banerjee: Understood, sir. And sir, another question that I had was, the overseas projects that we have undertaken, particularly in Croatia and all. So, between domestic project and overseas project, which is likely to have a better margin profile? I understand that it's depending on the bidding and et cetera., but typically what's the margin differential between overseas and domestic projects if you could give a sense on that?
Answer, ramesh jha
Ramesh Jha: So, in overseas project, we generally make better margin, and the margin -- the delta in, say, domestic versus overseas is around 200 to 300 basis points, which is higher in overseas market. Page 13 of 20 Afcons Infrastructure Limited August 10, 2026 And whatever project we are targeting in overseas market, the margins -- specific margin, we will not be able to give you what margin we generally target, but then domestic market vis-a-vis overseas market, the margins are better in the overseas market.
Question
Vishal Periwal: Yes, sir. Thanks for the opportunity. Sir, in terms of our profit and loss account, what could be reason for decline in depreciation? Any link with the revenue that we book, or what's the reason behind that?
Answer, ramesh jha
Ramesh Jha: No, sir, depreciation, there is no link to the revenue, because generally depreciation is a time- related cost. So, the number has come down, because as I explained in the opening commentary, in this period, we did not had too much of tunneling-related activity, and we have explained in past that we used to do accelerated depreciation on the tunnel boring machine basis the running meter it used to excavate. So, this period, hardly there was any TBM-related tunneling activity. That is why the number has come down.
Question
Vishal Periwal: No. So which means it is linked with the revenue, right?
Answer, ramesh jha
Ramesh Jha: No, it is linked with the revenue only to the extent of TBM, which was not there in this quarter.
Question
Vishal Periwal: Okay, fine. And second thing is like, you know, in terms of execution, you did clarify in the previous questions, but if one has to pinpoint, like, there is -- order book is relatively young, initial stage, and execution could pick up as the quarter progresses, and that is one thought. Another is probably like, there are delays in the payment from the client, and as the clients are delaying, we are not able to pull the money, or probably like, deploy the money back in the working capital and another things which could improve execution. So, how -- which one directionally you will pinpoint, I mean, like, the reason of muted execution?
Answer, ramesh jha
Ramesh Jha: See, as we explained that the order book, whatever we have booked till now, say, around INR16,000 crores of order. These orders to convert in revenue, it will take some time. And the order what we were having in hand on, say, around INR32,000 crores, in such project, there were couple of project which were moving slow, and then in some of the other projects, there were some land acquisition related issues or there were some change in scope related stuff. So, the work fronts were not available. Because of that, there was a muted revenue in this quarter. As things stand, we expect the execution to significantly pick up from Q3 onwards, and so, we'll have a very strong H2, and all these orders whatever we have booked and the balance period in this year whatever orders we are going to book, we'll have a very sizable order booking in our Page 14 of 20 Afcons Infrastructure Limited August 10, 2026 hand matured for construction for the next financial year FY28. So, that's where we are looking at that FY28, we'll have a sizable ramp-up in terms of execution.
Question
Rahul Bhutra: Sir, cash flow from operation, is it negative for this quarter also?
Answer, ramesh jha
Ramesh Jha: Yes, so cash flow from operations generally in Q1 remains to be negative, because in past also we have explained that customers, what they try to do is, they will try to release all the payment in -- up to date payment in March quarter. And Q1, they devote their time for planning and budgeting for the next financial year. So, there is less activity in Q1 from the customer and payment also remains to be slow in Q1. So, cash flow is negative.
Question
Bhavik Shah: Yes, hi, sir. So, my question is regarding our JJM order book and receivables. Can you quantify the amount of the orders pending in order book and how much receivables we are still yet to receive?
Answer, ramesh jha
Ramesh Jha: So, in Jal Jeevan Mission, all put together, we have got INR1,221 crores of total order, in which from the UP, the balance order is INR510 crore. Madhya Pradesh is INR414 crores, and Rajasthan is INR297 crores. Amongst this, in Madhya Pradesh, we are not having any major problem, because whatever work we are executing, we are getting paid. And in Rajasthan also, payments are partly coming. Major problem is in UP where the payments, recent times, they have started making payment, because wherever we have completed the last- mile connectivity, the payments have started flowing in, but then it is not that significant corresponding to the receivable we have. So, in past also, we have explained that in UP, we were having close to INR400 crores of receivable. From there, we have received a very small fraction.
Answer, ramesh jha
So, for all practical purposes, the receivable remains to be in the similar level. Page 15 of 20 Afcons Infrastructure Limited August 10, 2026 Bhavik Shah: Understood, sir.
Question
And what will be the unbilled amount, sir?
Answer, ramesh jha
Ramesh Jha: So, this amount what we are talking about is a combination of receivable plus unbilled.
Question
Ashok Shah: Thanks for taking my question. Sir, we have very good order book position, but over the last few years, we are facing execution problem, or some different types of problem, maybe land and everything different. So, what's the problem, or how we are managing or going to increase the turnover or execution level, or what percentage of the sizable order is slow-moving? Can you explain or bifurcate it?
Answer, paramasivan srinivasan
Paramasivan Srinivasan: See, we have explained in the last quarter earnings call on some of the issues which is been factored in. If you look at of the overall order book value, roughly around 5.65% is slow-moving category, and Bangladesh orders constitute about 2%, and another about 3% constitutes Jal Jeevan Mission orders. So, these three put together, roughly around 11% is what we can categorize, or either slow-moving or otherwise. In some of the other cases, as we had explained, there have been -- initial the right of way and related issues, which is getting resolved. That is why we are saying the third and fourth quarter, it will pick up better. And with the proactive involvement of Government of Maharashtra, and there have been lot of improvements in such areas, which in the past had contributed a bit, now with the proactive involvement, things are getting resolved, and projects will be available for execution. And otherwise, we have already started in the water portion and other things, land portion also, we will commence in the second half of the year.
Answer, paramasivan srinivasan
So, with that, things will improve. So, these are the -- when nearly about 11% of the orders are slow-moving or other thing, and another about roughly about 20% of the orders are in the initial phase, then that is why there are challenges in terms of converting it into turnover, which will start improving in the second half-year.
Question
Ashok Shah: So, as stated in the call, so we do plan to reduce our debt over the years by the March. So, what is the size we are seeing to reduce our debt?
Answer, ramesh jha
Ramesh Jha: Yes, so debt, we will look at a sizable reduction, and this year, as we said that, we had to make payment for some of the capital equipment we have bought, despite all that, we see that we'll see improvement in the number what we have clocked in FY26, from that number, we will see some improvement, at least there'll be some 5% to 10% improvement from that number.
Question
Ashok Shah: Can you specify the...
Answer, ramesh jha
Ramesh Jha: Yes, we are looking at debt closing say around INR3,500 crores or so. Page 16 of 20 Afcons Infrastructure Limited August 10, 2026 Ashok Shah: So, it will be reduced by how much as a consolidated level around INR300 crores to INR400 crores?
Answer, ramesh jha
Ramesh Jha: No, so what we are talking about from FY26 debt number, we are looking at a similar number, but then this year, we will be making payment close to say around INR700 crores to INR800 crores towards capex. Despite that, we will clock the similar number on the debt front. In terms of working capital, the similar amount of improvement will be there.
Question
Ashok Shah: So, net debt will be reduced by INR700 crores, or it will be lower than that?
Answer, ramesh jha
Ramesh Jha: Net debt will be reduced -- net debt will be somewhere around INR2,700 to INR2,800 crores kind of a number.
Question
Ashok Shah: Thanks, sir. Thanks, and best wishes for current year. Thank you.
Answer, ramesh jha
Ramesh Jha: No, so it goes as a tax in whatever JV pays tax, that goes as a tax in the respective entity, and when then in consolidation, that forms part of tax. Because most of these JVs are forming part of the standalone financial itself, so it gets incorporated in standalone financials as well. Now, specifically, I was trying to explain for this quarter, because in Afcons, the profitability was low, in terms of percentage, it is appearing to be around say 40%. But the amount if you see per se is not that big number, it is around said INR4 crores to INR5 crores. Had we had maybe, say, INR150 crores to INR200 crores kind of a profit in Afcons, what we were clocking for so many quarters, these INR4 crores will not make that tax percentage a big number. Page 17 of 20 Afcons Infrastructure Limited August 10, 2026 Aritra Banerjee Okay, but in that case, tax would have also gone up, right? Like, this wouldn't be a fixed number, right?
Answer, ramesh jha
These INR4 crores that you're saying, that would have also gone up in that case. So, just wanted a bit more clarity on that?
Answer, ramesh jha
Ramesh Jha: No, so, see in Afcons, we are making so most of the entities we are making tax payment in the range of 25% or so. Just because that this quarter in some of the entities, some of the closed project’s entity, we had to incur some administrative cost, because in such entities, we are following up with customer for collections, and some other closure aspects are not closed, and in such entities, we are required to make ECL provision on the receivables. Because of that, we are looking at those entities, we are looking at a loss kind of a situation, because the projects have completed. So, all these administrative expenses, ECL provisions are coming as only cost, and because of that, the consolidated profitability is coming down, and whatever loss we are incurring in these entities because of that the tax rate is going up despite paying say 25%-26% tax only. Aritra Banerjee Got it, got it. That's clear. Thank you for answering the question.
Question
Shravan Shah: Ah, hi, sir. Thank you for the opportunity again. Sir, for capex, you said in this quarter, we have done an INR150 crores capex. But on the cash flow front, this number must be on a higher side.
Answer, ramesh jha
Ramesh Jha: Yes. Because some of the amount which was on 31st March, which was in CWIP, for that, we had to make payment in the quarter.
Question
Shravan Shah: Okay. And for finance cost, this quarter, and the ECL provision, so was there any ECL provision in this quarter, and on the finance cost, how one can look at the finance cost?
Answer, ramesh jha
Ramesh Jha: So, as far as ECL provisioning is concerned, we have explained last time that we have made a framework for ECL provisioning, and which was approved by the board, and which was, we had taken professional guidance from experts in this particular field, and basis that framework was devised, and basis that framework, we have started making provisioning from last year, and we continue to do the provisioning on that basis. No specific provision as such in any project, because we believe that any such eventuality, I mean, we do not foresee any such eventuality going forward, and whatever project-specific, provisioning we had to do last time, on a company basis, if we evaluate, let's say, last 20 year, 25 years, maybe, those were aberrations, because such instance we never had. It was maybe say at max I can say 1%, 2% kind of a possibility. So, we do not foresee going forward such kind of provisioning will be required. But then on a prudent basis, we have made a very robust provisioning mechanism and, taking guidance from professionals, and basis that, we have been making provision.
Question
Shravan Shah: Okay. And lastly, in Q1 revenue, can you can you break it down in domestic and international, what would be the share? Page 19 of 20 Afcons Infrastructure Limited August 10, 2026 Ramesh Jha: In terms of revenue from overseas market, as in March, we had shown that the overseas revenue had come to around 30%.
Answer, ramesh jha
So, in Q1, we are we are having overseas revenue around 16% from overseas market, domestic is 84%. But now the order mix is changing. At the moment, the order book what we have, we have moved back to around say 25% from overseas market, and there are a lot of other projects in overseas market we are expecting. So, we hope that we will go back to 30% from overseas market, that is for minimum, and then as the order book moves 30% from overseas market, revenue also will go back to 30% from the overseas market.
Questions about this call
- When was the Afcons Infrastructure Q1 FY27 earnings call transcript filed?
- Afcons Infrastructure filed the transcript with the exchange on 13 Aug 2026. This page is built from that transcript.
- What does this page list?
- 55 statements from the transcript across 7 topics, 32 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 29 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.