Afcons Infrastructure Q4 FY26 earnings call

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company secured new orders worth INR 4,125 crores during FY26, excluding approximately INR 3,800 crores of variation and change orders on existing projects. The company expects to book another INR 15,000 crores of orders in the current financial year, making its total order booking guidance INR 30,000 crores for the current financial year, with about INR 15,000 crores of orders including L1 already in hand. About 25% of domestic projects were impacted. Revenue for FY26 was INR 12,322 crores, down 5.4% from INR 13,023 crores in the previous year. Gross debt was INR 3,538 crores and net debt was INR 2,653 crores; net debt to equity was around 0.49x of net worth.

The numbers management gave

Results

  • Revenue for FY26 was INR 12,322 crores, down 5.4% from INR 13,023 crores in the previous year.
    Show source
    For the year, revenue stood at INR 12,322 crores, reflecting a decline of 5.4% year-on-year.
  • FY26 EBITDA was INR 1,439 crores, with an EBITDA margin of 11.7%.
    Show source
    EBITDA was INR 1,439 crores, and despite the moderation in performance, we maintained a healthy EBITDA of 11.7%.
  • FY26 profit after tax was INR 251 crores after providing INR 76 crores for a one-time impact from implementation of the new Labor Code; excluding that impact, PAT would be INR 327 crores.
    Show source
    Profit Afcons Infrastructure Limited May 19, 2026 after tax stood at INR 251 crores, after providing INR 76 crores for a one-time impact, arising from the implementation of the new Labor Code.
  • Q4 revenue was INR 2,777 crores and EBITDA was INR 170 crores.
    Show source
    For the 4th Quarter, revenues were INR 2,777 crores, while EBITDA stood at INR 170 crores.
  • The company recorded a net loss of INR 89 crores in Q4, impacted by project-specific developments, provisions and one-time factors during the period.
    Show source
    The quarter closed with a net loss of INR 89 crores, impacted by certain project-specific developments, provisions and one-time factors during the period.
  • The company could not recognize margins in some recent projects in Q4 because they fell marginally short of the usual turnover threshold of around 10% for profit recognition.
    Show source
    So, margin could not be recognized.
Show 18 more statements

Results

  • Interest-bearing customer advances were around 40% of Afcons Infrastructure Limited’s overall customer advances for FY26, compared with around 38%-39% in March ’25; the interest-bearing share had risen from around 20% in September ’24 to around 38%-39% by March ’25.
    Show source
    Also, the interest-bearing advances for the full year FY26 which is around 40% of the overall advances from the customer, which even though in March 25 was also around say 38-39%, but then the interest on customer advances were not for the full year that 40% because it gradually moved from say around 20% in September ‘24, it moved to around 38-39% by March ‘25.
  • The company accounted for total TBM depreciation of INR 454 crores, of which normal depreciation was around INR 289 crores, or 2.33%; the remainder was accelerated depreciation.
    Show source
    On the depreciation front, we continue to account for accelerated depreciation on our TBMs of the total INR 454 crores.
  • The company recorded around 12% ROCE and around 5% ROE in FY26.
    Show source
    In FY26, we have done around 12% ROCE and ROE is around 5%, which is quite low.
  • Overseas projects were around 13% of Afcons Infrastructure Limited's overall order book, while almost 30% of turnover during the year came from the overseas market.
    Show source
    But in terms of turnover, we continue to do around 30% from the overseas market.
  • The company made provisions close to INR 160-odd crores across all projects in Q4.
    Show source
    Ramesh Jha: In Q4, across all projects, we have done a provision close to INR 160-odd crores.
  • Provision was close to INR 325 crores in FY26.
    Show source
    Ramesh Jha: FY26, the number is close to INR 325 crores.
  • The company incurred CAPEX of INR 1069 in FY26, including close to INR 700 crores in Q4; the amount was around INR 370 odd crores in December.
    Show source
    Ramesh Jha: So, in FY26, we have incurred a CAPEX of INR 1069.
  • The company is at around 143 days of networking capital and had said it was looking at around 120 odd days; it is looking for a sizable amount of stuck money to be unlocked before June, which would improve the number.
    Show source
    Because at the moment, this networking capital number of around 143 days and in last call, we had talked about that we are looking at somewhere around, say, 120 odd days.
  • Revenue growth and profitability during FY26 were meaningfully affected by slower-than-anticipated ordering activity across several segments, project-conversion delays, prolonged tender evaluations, execution disruptions, client liquidity constraints and temporary overseas project disruptions due to geopolitical developments, as well as delays from design and alignment changes.
    Show source
    Taken together, these factors had a meaningful impact on revenue growth and profitability during the year.
  • The company limited funding to some projects in Q4 to avoid overexposure to any customer amid uneven customer payments, which limited turnover in some projects.
    Show source
    This limited our turnover in some projects.
  • Q4 loss was also affected by under-recovery of fixed costs due to lower turnover and higher finance costs due to working capital lock-up.
    Show source
    In addition to this, under-recovery of fixed costs because of lower turnover, higher finance costs because of working capital lock-up were the components contributing to loss in the quarter.
  • FY26 profitability was additionally affected by a one-off exceptional item related to the Labor Code.
    Show source
    For the full year, in addition to the above factors impacting Q4 profitability, Labor Code related one-off exceptional item was another big impact.
  • Average borrowing cost improved in FY26 compared with FY25 due to lower interest rates and an improved credit rating, but average borrowings and overall interest cost increased versus the previous year.
    Show source
    But during the year, the average borrowing has gone up as compared to previous year and because of that, the overall interest cost has gone up and this has a manifestation of working capital blockages.
  • Operations were severely impacted in March as POL-related issues and logistics challenges prevented materials from being sent to project sites.
    Show source
    So, POL related stuff and logistics related stuff, so we couldn't send material to project site and this severely impacted.
  • In Q4, Afcons Infrastructure Limited moved from management-judgment provisions to a provision matrix based on receivables aging and category.
    Show source
    But this time around, rather than sticking with that individual assessment or individual basis that we used to make provision, this time we have made a matrix wherein we have moved from earlier basis, the management judgment provision, we have moved to a matrix wherein basis aging and basis category, we have made a provision matrix.
  • The company has a labor availability issue across the board, but no labor protests at its sites in India.
    Show source
    But yes, there is an availability issue of the labor part, but not protest, nothing like that.

Money and capital

  • Gross debt was INR 3,538 crores and net debt was INR 2,653 crores; net debt to equity was around 0.49x of net worth.
    Show source
    In terms of debt : Gross debt has remained in the similar range that of September and December and that stands at INR 3,538 crores and net debt is INR 2,653 crores on the net basis.
  • The company is looking at CAPEX of around INR 725 crores for FY27.
    Show source
    Ramesh Jha: So, FY27, we are looking at a CAPEX of around INR 725 crores.

What it expects ahead

What management expects

  • The company expects to book another INR 15,000 crores of orders in the current financial year, making its total order booking guidance INR 30,000 crores for the current financial year, with about INR 15,000 crores of orders including L1 already in hand.
    Show source
    Having a certainty of about INR 15,000 crores order including L1 in the current financial year, we expect to book another INR 15,000 crores of more orders, making a total order booking guidance of INR 30,000 crores for the current financial year.
  • The company expects to book INR 30,000 crores of orders this year, with visibility for the balance 15,000 crores from both domestic and international projects; some international projects are in negotiation and closure, domestic bids have been submitted and more are in the pipeline, and some of the orders may come in the current quarter.
    Show source
    Therefore, we would say there is a definite visibility in terms of balance 15,000 crores order book as well.
  • The company expects its networking capital to return to around 120 days after payments are released, with a bare minimum target of 120 days and further improvement to be assessed; it is not committing to more because of contrary news about payments.
    Show source
    So, I think, bare minimum, we can look at 120 days and from there on, we need to see improvement.
  • The company will see a sizable drop in its debt number in FY27, although debt could move up or down marginally; gross debt-to-equity is around 0.65 and net debt-to-equity is below 0.5.
    Show source
    But one thing for sure we can tell you that for this financial year FY27, we will see a sizable drop in the debt number.
  • The company guided to new order inflow of INR 30,000 crores for the year, of which it had already received INR 8,000 crores, had about INR 7,000 crores of orders at L1, and had a further INR 15,000 crores.
    Show source
    Total INR 30,000 crores is the guidance for the year.
  • The company expects a sizable liquidation of contract assets by June, in the range of INR 1000 odd crores, and expects this to be realized, with a reduction in working capital days from an elevated 143.
    Show source
    So, with that, we will see that getting realized.
Show 8 more statements

What management expects

  • The company expects tunneling operations at the Mumbai-Ahmedabad high-speed rail C2 project to commence before the end of next quarter.
    Show source
    We expect tunneling operations to commence before the end of next quarter.
  • The company expects L1 orders to convert in this quarter.
    Show source
    We expect these L1 orders to get converted in this quarter.
  • The company did not provide specific revenue growth or EBITDA margin guidance for FY27, saying it would wait for greater visibility given geopolitical uncertainty, elongated award cycles and ongoing project-related developments.
    Show source
    At this stage, considering the continued uncertainty in the geopolitical environment, elongated award cycles and ongoing project-related developments, we believe it would be prudent to wait for greater visibility before providing specific revenue growth or EBITDA margin guidance for FY27.
  • The company expects its situation to improve upon realization of locked-up assets in many projects and receipt of interest-free advances, mainly in international orders.
    Show source
    Afcons Infrastructure Limited May 19, 2026 We expect the situation to improve on realization of number of locked up assets, which we are in a very advanced stage at this point in time in many projects and also on receipt of interest free advances mainly in international order.

Orders

  • The company secured new orders worth INR 4,125 crores during FY26, excluding approximately INR 3,800 crores of variation and change orders on existing projects.
    Show source
    Coming to order inflows during the financial year, we secured new orders worth INR 4,125 crores, excluding approximately INR 3,800 crores of variation and change orders received on existing projects.
  • Bid pipeline for the next two years is close to INR 4 lakh crores across segments, with 70% domestic and 30% overseas; the company expects many large relief projects in the pipeline to convert soon.
    Show source
    It's close to INR 4 lakh crores, which we are tracking across segments, and out of that, 70% is domestic and 30% is from the overseas market.
  • INR 4 lakh crores bid pipeline includes around INR 96,000 crores from hydro and underground business, including water; around 90,000 crores from marine and industrial, distributed 50-50; around 85,000 crores from rail and road; and the remainder, around 1.3 lakh crores, from urban infrastructure, including metro, underground, elevated and elevated corridor projects.
    Show source
    So, out of that INR 4 lakh crores, around INR 96,000 crores is from the hydro and underground business, which includes our water business as well.
  • FY26 order intake was below earlier expectations largely because several large project awards were deferred and L1 positions took longer to convert into firm orders, particularly in Q4.
    Show source
    The order intake was below our earlier expectations, largely on account of the deferment of several large project awards and delays in conversion of L1 positions into firm orders, particularly in the 4th Quarter.

What it is building and selling

Projects and capacity

  • About 25% of domestic projects were impacted.
    Show source
    Maybe in domestic market, if you have to put a number around, say, 25% or so, the projects got impacted.
  • The company received the second consignment of the tunnel boring machine at the Mumbai-Ahmedabad high-speed rail C2 project site after it had been held up for several months.
    Show source
    On the Mumbai-Ahmedabad high-speed rail C2 project, the second consignment of the tunnel boring machine, which had remained held up for several months, has now been received at site.

Risks, rules and outside factors

Outside factors

  • Domestic projects have escalation formulas covering steel, cement, labor, fuel and other factors; increases are fully covered in some cases, 90% covered in some cases and more than 100% covered in others, and generally domestic contract cost increases have not caused issues except during abnormal increases such as the sudden steel-price increase in 2004-05.
    Show source
    Therefore, generally, any kind of increase in the domestic contracts, there have been no issues in terms of cost increases, except in sometimes when there's an abnormal increase, like happened in 2004-05, there was suddenly an abnormal increase in the price of steel.
  • Projects faced petroleum, oil and lubricants (POL)- and gas-related issues in project consumables and logistics challenges in Q4 after the war.
    Show source
    Also, in Q4, after the war, there were Petroleum, Oil, and Lubricants (POL) and gas-related issues in projects consumables and logistic-related challenges.
  • Gas availability was a real problem for Afcons Infrastructure Limited’s projects at remote locations in the domestic market.
    Show source
    So, availability of gas was a real problem.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Shravan Shah: Hi, Sir. Thank you. Sir, you have tried to explain various reasons why our p erformance was the worst quarter in our history, but still trying to get some more clarity there. So, when we had a call in the third quarter post the result in February, we were kind of confident that we will be able to at least 5% revenue growth for the entire full year. That means we would be doing a kind of a 19-20% kind of growth on the 4th Quarter versus now we have seen a 19% degrowth in the 4th Quarter and for full year also 5% kind of a degrowth. So, just trying to understand that even Afcons Infrastructure Limited May 19, 2026 at the middle of the quarter, we were so confident and what has go

    Answer, ramesh jha

    Ramesh Jha: That is correct. But see, usually what we have said, this was based on the last 15-20 years’ experience. What happens that in Q4, we have seen that the customers, they release all the payments up to date. This is what our experience has been for quite some time. But this year was an exception wherein we have seen that there was a slowdown in terms of payment and payments were not forthcoming. That has impacted and we had to decide a choice between growth or to preserve the liquidity and then we had not taken that aggressive call to pursue the top line growth. And then in the midst of that, the war started and then that severely impacted the supply chain management and you are aware that even this year we have done close to 30% from our overseas project, even though the order book is lower in terms of order book composition, domestic versus overseas.

    Answer, ramesh jha

    But in terms of turnover, we continue to do around 30% from the overseas market. And some of the countries where we are operating are not that bigger economies where they have got higher amount of oil reserves. So, the operations got severely impacted in the month of March. So, POL related stuff and logistics related stuff, so we couldn't send material to project site and this severely impacted. Even in domestic market also, you are aware that many of our projects are at remote locations. So, availability of gas was a real problem.

  2. Question

    Shravan Shah: Okay, got it, sir. So, now, again, we are at the middle of this quarter. So, first, obviously, I think, correct me if I am wrong, for full year FY27, we are not providing any revenue guidance. So, if that is the case, then this quarter Q1 till now and looking at whatever now the whatever the constraint, payment related issues, everything, can we see a growth in the Q1 FY27 this quarter?

    Answer, ramesh jha

    Ramesh Jha: This is where what we have conveyed is that at this point in time, because of the geopolitical situation, because the condition continues to be the same, even in domestic market, we are getting very contradicting signals. We are hearing that the energy prices are going to significantly go up. And we have not seen the payment situation improving significantly, even though some of the stuck payments we are, as I said earlier, that we are in a very advanced stage to get those payments. But at the same time, those supply chain related issues continue. So, it would not be prudent on our part to give you any guidance as such for the full year or even for the Q1.

  3. Question

    Shravan Shah: Okay, got it. So, same for even for margin also, the normal long term guidance that we have eleven percent. So, that will also we will right now will not be kind of giving any kind of guidance on that front.

    Answer, ramesh jha

    Ramesh Jha: See, we are not saying we are not giving any guidance on the margin front also, because we need to see how it actually pans out. Because many overseas places we have seen that the petrol, diesel prices have significantly gone up during the war period. In the month of March, April, the prices have gone up. Some of the places like Bangladesh, they were having elections. So, till the elections were there, the prices remained stable. But after the results, the prices had gone up. So, Afcons Infrastructure Limited May 19, 2026 we are looking at that kind of situation.

    Answer, ramesh jha

    And you are aware that in many overseas locations, our prices are fixed price contracts. So, we need to see how we are able to recover from the customer these escalated costs. So, we have in the past also explained that generally in the overseas market, we try to keep risk and contingency. But then at the same time, we are not very sure to what extent those risks and contingencies will be able to take care of the escalated costs.

  4. Question

    Shravan Shah: Lastly, sir, on the inflow front, just to get a number correct. So, after the 31st March, how much value of inflow that we have received the LOA? Obviously, we also know, if you can also specify in terms of the L1. One, what I know is a Croatia, which would be a INR 7,800 odd crore and the Vadhavan, which is INR 5,300 odd crores. So, kind of a INR 13,000 odd crore kind of, if you can specify the number would be better. So, we are saying by June, we would be getting a INR 15,000 crore LOA. That is one. And second, additionally, we will be getting a INR 15,000 crore more inflow. So, total would be a INR 30,000 crore for the entire FY27.

    Answer, ramesh jha

    Ramesh Jha: Yes. So, you are right. We have already informed to the exchanges that this Croatia order is already we have been selected as the contractor for the project. And besides that, you are aware, there are news in the social media that a couple of projects, we have been declared L1. Since we are not disclosing that to exchanges, we will not be able to give you the exact details. But you are aware there are projects where we have been, we have emerged as L1.

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: There is also an underground metro of DMRC of INR 373 crores, which we have bagged already.

    Answer, ramesh jha

    Ramesh Jha: So, in the year-end number, what we are talking about, almost 50% is having a clear visibility in place, in the first 1.5 months.

  5. Question

    Shravan Shah: Okay, got it. And the CAPEX for full year now, given the FY26, I think the TBM cost now will be shifting in the FY27. So, how one can look at the FY27 CAPEX?

    Answer, ramesh jha

    Ramesh Jha: So, FY27, we are looking at a CAPEX of around INR 725 crores.

  6. Question

    Ankita Shah: Yes, hi. Sir, I am referring to your last call that you mentioned that nearly one-third of your Q4 target is already achieved in the first 40 days. Most approval on related to project delays have been resolved. Execution pace to normalize from 4Q and 11% looks sustainable. Amid all this commentary that you gave, what is it that you did not see coming through, which impacted the balance 50 days of project execution and margins? What are the key projects that actually impacted this and you did not see it coming through?

    Answer, ramesh jha

    Ramesh Jha: So, see, let’s appreciate that Q4 always remains to be a sizable portion in any year. Now, in the month of March, we had seen a sizable drop because of, as explained earlier, because of supply Afcons Infrastructure Limited May 19, 2026 chain disruption and energy-related challenges. Many places, the vendors were asking for advance payment and then only they were committing. And they were, despite giving advance payment, many places it was not available. So, that became a major constraint. And as I explained that we have got almost one-third which comes from overseas market and some of the countries are not having those kind of energy reserve. So, that severely impacted.

    Answer, ramesh jha

    And some of the projects, even in domestic market, got impacted in the month of March. So, this is something which we had not, we were not expecting. And also, some of the projects where the Fast-track projects, we were expecting because the kind of discussion we had, because these were all private customers also, we were expecting things to ramp up, but then it did not pick up.

  7. Question

    Ankita Shah: So, do you mean to say, okay, can we read it this way that a large part of this impact has been on account of your international projects, which is 30%?

    Answer, ramesh jha

    Ramesh Jha: Large part is because of international projects. And as I explained earlier also, that the payments, see payment has to be something which makes things flow. This got stuck. This has severely constrained us to put beyond a point money by ourselves.

  8. Question

    Ankita Shah: Okay. So, how much percentage of impact is on account of domestic projects and export, I am assuming everything got impacted.

    Answer, ramesh jha

    Ramesh Jha: Export everything got impacted. Maybe in domestic market, if you have to put a number around, say, 25% or so, the projects got impacted.

  9. Question

    Ankita Shah: Okay. What do you I mean, given that the situation still remains the same, do you think this issue will continue going forward as well, at least this quarter or next six months clarity you might be having, given the kind of experience you have had over the years? What is your read through for in the near term on this?

    Answer, ramesh jha

    Ramesh Jha: This challenge continues to be so, and we have not seen a very sizable improvement in overseas market in terms of energy availability. And what we hear you might have also seen media, very prominent leaders, world leaders, they have talked about that we are looking at big disruption coming up. So, we are also not very sure how to give talk anything futuristic at this point in time, but the situation has not drastically changed. That is the reason we are holding on to the guidance, because once we see some clarity, we will be giving the guidance.

  10. Question

    Ankita Shah: Okay. Can you give me more clarity on your international projects? Where all do you have the projects and what is the nature of the work that you are doing there?

    Answer, ramesh jha

    Ramesh Jha: See, in Bangladesh, we are doing a couple of road projects, and we have got a railway project. In Maldives, we are doing one bridge connecting project. Besides that, we are doing a couple of water related project in Tanzania. We are doing a project, water related project in Benin, in Ivory Coast, and then there are various countries in Africa. Afcons Infrastructure Limited May 19, 2026 Ankita Shah: Okay.

Show 19 more questions
  1. Question

    So, what has been the issue here in these places? I mean, if you can give more clarity, is it supply chain related or local level disruption that you saw? I am unable to understand there, that thing.

    Answer, ramesh jha

    Ramesh Jha: No. Usually, what happens that in most of these projects, the material goes from domestic market India, and from Middle East. Dubai works as a hub for us. So, movement of material became a problem for these places. And usually, for our project execution, we require a lot of diesel, we require a lot of gas. So, availability of this was not there. Many places, we had to give advance, and then only they were committing delivery.

  2. Question

    Ankita Shah: Okay. So, this led to increase in the cost, and has the work stopped on the site, or you have continued the work, but you have not got the payment from the clients?

    Answer, ramesh jha

    Ramesh Jha: So, one, of course, the cost impact was not that severe, but then because of this, the operations could not move in a manner we were expecting.

  3. Question

    Jainim Jain: Thank you for the opportunity. So, we have highlighted the delay in the payment from the customer end. So, are there any concerns on any specific customer side, or are we facing issue from the government or the private clients?

    Answer, ramesh jha

    Ramesh Jha: As such, we are not saying that there is concern, but what we have seen is in some of the states, there was election, and because of that, there was no decision. The payments were certified by the customer. It was sent to the treasury, and the payments were not coming. Some of the customers, we heard that they were not deciding. Payments were certified. It was sent to their centralized finance team, and then we just heard that the payments will be released. It was not released.

    Answer, ramesh jha

    It was released actually subsequently in the month of April. So, as such, we are not saying that we are seeing any concern, and I think in the past, we have talked about the jal-jeevan mission, which continues to be in UP. They have taken a stand that wherever people are completing 100 percent, then only they will release the payment. This is contrary to the contractual condition, but this is how it has been taken up.

  4. Question

    Jainim Jain: Okay. So, basically, there was a spillover of receivables from March to this quarter, and we have seen a relief of the payments in this quarter, right?

    Answer, ramesh jha

    Ramesh Jha: Yes. It's not only limited to quarter. Actually, what we are trying to say is that the payments are getting elongated. As such, it's not that the payments are stuck. The running bills and payments are stuck, but in the manner, it used to come or we were expecting, it is not coming in that manner. Afcons Infrastructure Limited May 19, 2026 Jainim Jain: Okay.

  5. Question

    My second question is, is there any plan to bid internationally on the ME side, given that Abu Dhabi has unveiled its $55 billion worth of project pipeline?

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: We are definitely at it, and sooner than later, we will start bagging projects in the Middle East. Jainim Jain: Okay. And currently, would you give any bid pipeline number for now, for this year?

    Answer, hitesh singh

    Hitesh Singh: So, yes, sure. Our bid pipeline remains healthy for the next two years, which we track. It's close to INR 4 lakh crores, which we are tracking across segments, and out of that, 70% is domestic and 30% is from the overseas market. As MD sir just mentioned, the Middle East also looks like a big opportunity once the war gets settled. So, that area also we are looking. And there are many large relief projects in our pipeline, which we are expecting to convert soon. And basis that it gives us a confidence that this year we are giving a guidance of INR 30,000 crores for the order booking.

  6. Question

    Jainim Jain: Okay. So, do we have any bifurcation for the bid pipeline of 4 trillion?

    Answer, hitesh singh

    Hitesh Singh: Yes, I have the bifurcation as well. So, out of that INR 4 lakh crores, around INR 96,000 crores is from the hydro and underground business, which includes our water business as well. Around 90,000 crores is from the marine and industrial. It will be like 50-50 distribution. Our rail and road business will be around 85,000 crores, and remainder around 1.3 lakh crores is from the urban infrastructure business, which includes metro, underground, elevated and elevated corridor projects as well. So, that is how the distribution looks like.

  7. Question

    Parvez Qazi: Hi, good afternoon. Thanks for taking my question. So, you mentioned that in Q4, we had a sizable provision in one project. So, would it be possible to get a quantum of the total provision that is made in Q4 across all projects?

    Answer, ramesh jha

    Ramesh Jha: In Q4, across all projects, we have done a provision close to INR 160-odd crores.

  8. Question

    Parvez Qazi: ‘26.

    Answer, ramesh jha

    Ramesh Jha: FY26, the number is close to INR 325 crores. See, Parvez, I will just explain you. What we have done is, this year we have, in Q4, what we have done is we have made a ECL provisioning matrix. So, earlier, what we used to do is as per accounting standard, we used to look at some previous periods, what is the write-off and basis those averages we used to make provision. And then in some specific project where we used to think that there could be some challenge, we Afcons Infrastructure Limited May 19, 2026 used to make those specific provisions. But this time around, rather than sticking with that individual assessment or individual basis that we used to make provision, this time we have made a matrix wherein we have moved from earlier basis, the management judgment provision, we have moved to a matrix wherein basis aging and basis category, we have made a provision matrix. So, it will be automatically provision will be made, all the receivables.

    Answer, ramesh jha

    And so, there was some extra provisioning required because we had to shift to this new matrix system. There was some extra provisioning required, which we have done.

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: Also, we have done in one of the projects where we had an arbitration award where we could be taking a call as to contest or not. We thought it is prudent to provide for it. So, we had provided for that. That is also a significant amount. Plus, another of the projects where there is a cost increase in terms of our marine spreads and other things, which we thought while it could get compensated in due course of time, we thought it is upfront we will book the cost. And later on, as compensation comes, it could be plus side that time. That is how we had, as per our usual conservative accounting policies, that is something we have done up front.

  9. Question

    Parvez Qazi: So, to summarize, I mean, if one adds all these, which is extra provision due to a new policy or cost incurred in a marine project or some provision for a potential claim where we have to decide a strategy, I mean, what will be the quantum of these one-time costs in Q4 across all these categories put together?

    Answer, ramesh jha

    Ramesh Jha: I think all this put together, the quantum could be around say INR 260-265 crores.

  10. Question

    Parvez Qazi: Sure. And second question is what is the CAPEX that we incurred in Q4 and FY26?

    Answer, ramesh jha

    Ramesh Jha: So, in FY26, we have incurred a CAPEX of INR 1069. And this number was in December, this number was around INR 370 odd crores. So, in Q4, we have done close to INR 700 crores.

  11. Question

    Bhavik Shah: Hello, sir. My first question is regarding the current order book. Can you help me with the split of, say, the fixed price order book in it and the variable cost order book in it? And also in the fixed cost, how much of it is going to be impacted, say, with the margins, which may not be at our normal margins now?

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: In terms of our existing order book, nearly about 10% to 11% only is currently in the overseas segment. 13% is the overseas segment. All others are domestic segment. As you know, domestic segment, we have a pass-through mechanism and international segments, we do not have a pass- through segment. And therefore, our impact and most of these projects which we are talking about is on the closing stages. Other than the fresh order which is received in the current quarter, all others are in the final stages of closure. And therefore, we do expect a limited impact in terms of the existing cost escalation or other things.

    Answer, paramasivan srinivasan

    In the new project in the Croatia, beyond a particular level, it has a pass-through mechanism in that contract. Up to 10% additional cost we Afcons Infrastructure Limited May 19, 2026 need to absorb. Beyond that, it is a pass-through. That is something which is there in the new contract.

  12. Question

    Bhavik Shah: You told the Bangladesh Road Rail Project, the Maldives project, the Tanzania water project, the Benin project, all of these were slow moving during the quarter. Can you help us with the quantum of these projects?

    Answer, ramesh jha

    Ramesh Jha: In the overall order book, at this point in time, the overseas component is around 13%. But what I have explained earlier also that even though it is around 13% in the overall order book, but during the year turnover, almost 30% is coming from the overseas market.

  13. Question

    Shirom Kapur: Hi, sir. Thanks for the opportunity. Just had a question on your order flow visibility. So, the 30,000 crores that you are guiding for this year, what gives you that confidence on that balance 15,000 crores that you mentioned? You said visibility is in place for about 50% of this. The balance, 50%, what gives you visibility on this? Is it going to be more on the international side or domestic side? Which areas are these projects coming up in? Is the bidding already opened or is this more sort of, if you could give some more color on that balance 50%?

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: Balance 50% consists of both domestic and international. And in terms of certain international projects, we are already in the stages of negotiation and closure. So, therefore, we do expect things to happen quicker. And in domestic projects also, we have a number of bids already submitted. And there are a few more bids in the pipeline. Therefore, we would say there is a definite visibility in terms of balance 15,000 crores order book as well. We will not be surprised some more of this will come in the current quarter itself, which we are keeping our fingers crossed.

  14. Question

    And just secondly, on your working capital, right? So, of course, we have had a lot of discussion on the payments getting delayed and we have seen consequently rise in your receivable days this year. But are you seeing any – how are you seeing this panning out in FY27 in terms of your receivable days? It has gone up more than 300. Maybe in the next one, two months, you cannot give any guidance. But overall, a sense of target number that you are looking for FY27 in terms of receivable and overall working capital days.

    Answer, ramesh jha

    Ramesh Jha: See, in terms of receivable days, I have just now, during the call, I have said that on quite a few, big chunk money which is stuck and on this, we are working with various customers and we are at a very advanced stage. So, before June, we are looking at a sizable amount getting unlocked. So, that will give us some improvement in terms of the number we are looking at. Because at the moment, this networking capital number of around 143 days and in last call, we had talked about that we are looking at somewhere around, say, 120 odd days. So, with this, and to be very honest with you, these monies we were looking at getting monetized before March. That is what we were discussing. But it did not happen.

    Answer, ramesh jha

    But hopefully before June, this is going to happen because now we are on the verge of closing many of these. We know that some of the payments have already gone and they are releasing the payments. So, still, I am just taking another, say, 40 days or so. It will definitely be going to happen. So, with that happening, we will go back to around 120 days and then from there on, there are a number of stuck payments and we are not going, as I have told that in projects, we are not overexposing ourselves. So, I think, bare minimum, we can look at 120 days and from there on, we need to see improvement. But I do not want to commit at this point in time because we are hearing very contrary news about payments and all.

  15. Question

    Bhavin Modi: Thank you for the opportunity. So, my first question is, I understand that we are now doing the work in proportion to the payment that we are receiving. So, can we see debt levels to go down from here on? We are already at the pre-IPO level debt of 35 billion. So, how should we look at the debt movement going forward?

    Answer, ramesh jha

    Ramesh Jha: See, what happens that generally we have seen that in Q1, Q2, the debts go up. And I mean, even though we have said this, that from the project only we will be funding, but not all the time, all Afcons Infrastructure Limited May 19, 2026 the expenditure will be funded through the project collection. Main operations, yes, but then many a times we need to pay salaries, we need to pay rent, and those kinds of stuff, we are not hell-bent. So, there could be some marginal debt number going up and down, that is for sure. But one thing for sure we can tell you that for this financial year FY27, we will see a sizable drop in the debt number. And that's what we have stated also that debt, we have always tried to maintain it at a level which is comfortable to us and comfortable to our stakeholders. And this time it is not that this is an alarming number, on a gross debt basis also our debt-to-equity is around 0.65, on net debt basis is below 0.5, according to me it is quite a comfortable situation.

  16. Question

    Avnish Tiwari: Hi, can you explain this cost inflation passed through in the domestic projects? And the delayed payment when you are experiencing, do you think there could be a risk to the passing inflation through in these domestic projects?

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: All our domestic projects have an escalation formula. The formula could vary from customer- to-customer, but it has got an escalation formula consisting of steel, cement, labor, fuel, other factors, and all that. And based on that, whatever is the increases on in some cases, it is fully covered. Some cases, it is 90% covered. Some cases, it's more than 100% covered. So, that's a Afcons Infrastructure Limited May 19, 2026 formula. Therefore, generally, any kind of increase in the domestic contracts, there have been no issues in terms of cost increases, except in sometimes when there's an abnormal increase, like happened in 2004-05, there was suddenly an abnormal increase in the price of steel.

  17. Question

    Avnish Tiwari: Yes. The second question I had was on this minimum wage increases we are seeing, and some protests we are seeing in Northern states. Are you experiencing the cost increase as well as some degree of shortage or protest in any of your sites in India?

    Answer, hitesh singh

    Hitesh Singh: And Avnish, labor issues are across the board, so that availability we are trying to manage, how it can be managed. But yes, there is an availability issue of the labor part, but not protest, nothing like that.

  18. Question

    Ankita Shah: New order inflows, yes.

    Answer, paramasivan srinivasan

    Paramasivan Srinivasan: New order inflow, we have indicated INR 30,000 crores, out of which we have already received INR 8,000 crores and another about INR 7,000 crores were L1 and further INR 15,000 crores. Total INR 30,000 crores is the guidance for the year.

  19. Question

    Siddharth Suren: Thanks for the opportunity. So, two questions. One is on, there is this invocation of Lombard Guarantee, which you had mentioned as one of the note items. Just wanted to understand if there is any impact on the earnings for the quarter on account of that. So, that is one. And second is on the buildup of contract assets. So, you had earlier guided that there would be a liquidation, which we can see on buildup of these contract assets as the billing would be certified and so on but basis the commentary we understand that that is taking some time. So, can you still give us Afcons Infrastructure Limited May 19, 2026 some guidance as to when we can see the liquidation of the shor

    Answer, ramesh jha

    So, with that, we will see that getting realized. And also, we can look at reduction in number of working capital days, which we are looking at elevated number of 143.

Questions about this call

When was the Afcons Infrastructure Q4 FY26 earnings call transcript filed?
Afcons Infrastructure filed the transcript with the exchange on 22 May 2026. This page is built from that transcript.
What does this page list?
43 statements from the transcript across 6 topics, 27 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 29 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.