Capacit'e Infraprojects Q3 FY25 earnings call: Capacit'e Infraprojects Limited was awarded new projects worth INR 1,459 crores during 9 months ending December '24

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company was awarded new projects worth INR 1,459 crores during 9 months ending December '24. The company expects to surpass its guided order book addition for FY '25. EBIT improved by nearly 200 basis points or 300 basis points over the last 12 months, and management believes that improvement will continue. The central government budget increased the allocation of PMAY housing by 14 lakh houses for the next financial year. The company expects to realize about INR115 crores to INR120 crores over the next 15 months from a total loss of INR210 crores.

The numbers management gave

Results

  • EBIT improved by nearly 200 basis points or 300 basis points over the last 12 months, and management believes that improvement will continue.
    Show source
    So, our EBIT if you see has seen nearly 200 basis po ints or 300 basis points improvement over the last 12 months.
  • Total finance cost for the current quarter was INR25.29 crores, compared with INR21.58 crores in the last quarter, and was virtually flat year-on-year; bank guarantee renewals and renewal of limits charges contributed to the quarter's cost.
    Show source
    Rohit Katyal: So the total finance cost has been for the current quarter INR25.29 crores as against the last quarter of INR21.58 crores, that means quarter-on-q uarter.
  • Depreciation for the first 9-month period was INR79 crores, compared with INR69 crores in the last financial year.
    Show source
    And it's hardly -- I mean, if you see on the first 9-month period, it is INR79 crores as compared to INR69 crores in the last financial year.
  • EBITDA was 16.74%; a one-time hit of INR12 crores for GST translated to 2.05%, and without this hit EBITDA would have been 18.74%, in line with what the company had been declaring.
    Show source
    And therefore, had this hit not been taken, your EBITDA would have been at 18.74%, which is in line with what we have been declaring.
  • The CIDCO project contributed INR190 crores in Q3 and is expected to contribute more than INR220 crores in Q4; its expected run rate next year is INR80 crores to INR85 crores per month.
    Show source
    Rohit Katyal: So Q3 contribution is INR190 crores.
  • MHADA contributed INR67.39 crores in the current quarter and is expected to contribute a similar, slightly higher amount in Q4; Capacit'e Infraprojects Limited expects approximately INR400 crores or thereabouts from MHADA for the next financial year, or approximately INR35 crores to INR36 crores per month.
    Show source
    MHADA, the total contrib ution for the current quarter is INR67.39 crores.
Show 8 more statements

Results

  • EBIT margin was close to 14.6% for 9 months.
    Show source
    Deepak: Poddar: 14.6% For 9 months EBIT margin.
  • EBIT was 12.1% for the corresponding 9 months last financial year and improved by 200 basis points.
    Show source
    And if you compare t hat with the corresponding 9 months last financial year, it was 12.1%.

Money and capital

  • The company purchased equipment of INR60 crores this year.
    Show source
    You have purchased equipment of INR60 crores this year.
  • The company expects to realize about INR115 crores to INR120 crores over the next 15 months from a total loss of INR210 crores.
    Show source
    So, we do belie ve that over the next 15 months, the company will realize about INR115 crores to INR120 crores from the total loss of INR210 crores.
  • The company has close to INR80 crores of unencumbered cash, apart from fixed deposits lying at the bank less margin for LCBG.
    Show source
    Rohit Katyal: The company is sitting with unencumbered cash of cl ose to INR80 crores, apart from the fixed deposits, which are lying at the bank less margin f or LCBG.
  • Total fund-based working-capital limits are INR190 crores, of which INR140 crores is utilized.
    Show source
    The total fund-based limits for working capital are INR190 crores.
  • Total non-fund-based limits within consortium are close to INR1,000 crores, of which close to INR700 crores is utilized; about INR260 crores of bank guarantee and LC limits are available.
    Show source
    The total non-fund-based limits are close to INR1,000 crores within consortium, and the utilization is close to INR700 crores.
  • INR67 crores is present in Capacit'e Infraprojects Limited's financial books as a recovery amount; the balance amount to be recovered will hit the bottom line.
    Show source
    INR67 crores is present.

What it expects ahead

What management expects

  • The company expects to surpass its guided order book addition for FY '25.
    Show source
    With the order book so far, we are more than confid ent of surpassing our guided order book addition for FY '25.
  • The company has internally set a target of INR4,000 crores of fresh order inflow for the next financial year and expects to close the current financial year with a minimum of INR3,000 crores of fresh order inflow, excluding whatever is added from MHADA.
    Show source
    And therefore, it should be by our conclusion that we w ill cross INR3,000 crores minimum as fresh order intake in the current financial year.
  • The company sees 25%, 30% growth year-on-year, if not more, over the next 2 to 3 years, supported by its order book and execution commitments to clients.
    Show source
    Rohit Katyal: So with the order book, which we just informed you all, and with the execution, what we need to do and commit it to clients, obviously, we see a 25%, 30% growth year-on-year, if not more.
  • The company expects working capital to reduce by about 10 days to 15 days in the current year.
    Show source
    Similarly, as we told that we should look at reduci ng about 10 days to 15 days in the current year.
  • The company maintained 18% margins over 9 months and expects to maintain them over a 12-month period.
    Show source
    It will be maintained on a 12-month period as well.
  • The company expects EBITDA, earlier guided at 17.5% upwards, to continue at that level.
    Show source
    And yes, I do firmly believe that EBITDA, which was earlier guided at 17.5% upwards, that will continue.
Show 19 more statements

What management expects

  • The company will maintain overall guidance of 17.5% plus EBITDA, approximately 18% for the full year, and will grow EBIT by at least 200 basis points over the corresponding period of the last financial year.
    Show source
    However, having said that, we have already guided that the c ompany will be maintaining the overall guidance of 17.5% plus EBITDA, which is 18% approxim ately for the full year, and it will be maintaining and growing the EBIT by at least 200 basis points over the corresponding period of the last financial year.
  • The company expects 25%, 30% growth for the next financial year, supported by CIDCO, MHADA, NBCC and private-sector projects including Godrej and Raymond.
    Show source
    So, all these factors put together, CIDCO, MHADA, NBCC, private sector, which includes Godrej, which includes other clients, including Raym ond, it clearly showcases that the 25%, 30% growth for the next financial year is given.
  • The company has guided 25% growth for the current financial year; for next year it has client commitments for at least 25% growth, which could become 30%, 32% because new orders have a shorter execution period, with year-on-year growth on a higher basis guided at a minimum of 25%.
    Show source
    Rohit Katyal: Current financial year, we have guided 25%, and ther e's no reason why we shouldn't do that.
  • Guidance was 12.5%; it had informed in Q1 or Q2 that there would be a 50-basis points improvement and has done better than that, with a stable range of 14%, 14.5%.
    Show source
    Rohit Katyal: So, our guidance was 12.5%.
  • The company guided for full-year growth above 13%.
    Show source
    Rohit Katyal: For the full year, yes, we have already guided abov e 13%.
  • The company expects net debt to fall by INR100 crores.
    Show source
    Rohit Katyal: You should see a fall of INR100 crores in net debt.
  • The company expects its absolute finance cost for the full financial year to be similar to the first 9 months of the current financial year, despite increased turnover, and a little bit lower; it expects finance cost to fall next year as cash increases.
    Show source
    On an absolute basis, you will see a similar number on an increased turnover, a little bit lower, as I Capacit'e Infraprojects Limited February 14, 2025 Page 17 of 19 mentioned in my earlier answer to a question as wel l for the full financial year. Obviously, next year, it has to fall.
  • The company expects contract assets to fall on an absolute basis in the current year and to reduce by INR200 crores over a 4-quarter period in the next financial year.
    Show source
    However, in the next financial year, we further see a reduction of INR200 crores over a 4-quarter period.
  • The company targets contract assets close to 78% by March and expects them to be below 70% by next financial year-end, if not better.
    Show source
    And by next financial year-end, we should be below 70%, if not better.
  • The company is looking for recovery of INR115 crores over the next 5, 6 quarters, but did not give a particular timeline.
    Show source
    But as I told you, that we are looking over the next 5, 6 quarters for recovery of INR115 crores.
  • The company expects its absolute finance cost to reduce on an increasing top line on a full-year basis, with finance cost also dropping as a percentage of the top line.
    Show source
    However, on the full year basis, if you -- when you will compare, you will see that on an absolute basis we would have reduced our finance cost on an increasing top line.
  • The company will record some profits once the property is registered. Replaced by a later filing.
    Show source
    Once the property is re gistered, on the contrary, you will see some profits being recorded by the company.

Orders

  • The company was awarded new projects worth INR 1,459 crores during 9 months ending December '24.
    Show source
    We have been awarded new projects worth INR 1,459 crores during 9 months ending December '25 -- December '24, sorry.
  • The company was awarded a project by NBCC worth INR1,120 crores plus GST in the current quarter, taking total fresh order intake to INR2,579 crores.
    Show source
    We had an awarded project by NBCC worth INR1,120 cror es plus GST in the current quarter, thereby taking the total fresh order intake as on d ate to INR2,579 crores.
  • The company stands as an L1 position in projects worth INR600 crores.
    Show source
    The company stands as an L1 position in projects worth INR600 crores.
  • New order inflow, excluding additions from MHADA, stands at INR2,579 crores.
    Show source
    Rohit Katyal: So in my opening remarks, I mentioned that the new order inflow, excluding additions from MHADA, stand today at INR2,579 crores.
  • The company announced an order of INR1,120 crores for the Supreme Court monitor NBCC project in Noida.
    Show source
    We have just announced an order today of INR1,120 Capacit'e Infraprojects Limited February 14, 2025 Page 5 of 19 crores for the Supreme Court monitor NBCC project in Noida.
  • Nearly 76% of Capacit'e Infraprojects Limited's projects are central government or government funded, following its order win from NBCC.
    Show source
    Rohit Katyal: With the order win of yesterday from NBCC, nearly 76% of our projects are central government or government funded, sir.
  • The MHADA project for capacity is in excess of INR5,500 crores; Capacit'e Infraprojects Limited has recognized INR2,200 crores in its order book, leaving INR3,300 crores yet to be recognized as land is made available.
    Show source
    So, to just give you a sense that MHADA project for capacity is in excess of INR5,500 crores.

What it is building and selling

Projects and capacity

  • The company will build close to INR22 crores per month on the RCC part of its Signature Global, Gurugram project, in line with the agreed timelines.
    Show source
    And obviously, with the time lines which we have ag reed to, we will have to build close to INR22 crores starting per month only on RCC part.
  • The company will start billing for its new NBCC project from April onwards.
    Show source
    We will start that billing again from April onwards.

Demand and pricing

  • The central government budget increased the allocation of PMAY housing by 14 lakh houses for the next financial year.
    Show source
    Point number two, the allocation of PMAY housing ha s been increased by 14 lakh houses for the current -- next financial year in the central g overnment budget just announced.

Segments

  • Private sector projects will have a pass-through clause.
    Show source
    So, all projects what we take will have a pass-through clause in private sector.
  • Government projects will have escalation clauses that differ from project to project, client to client, and between state government and central government.
    Show source
    In governm ent, there will be escalation clauses, which differ from project to project, client to client, d iffers between state government and central government.
  • The company will not take up any project without being substantially protected on commodity prices.
    Show source
    However, we will not take up any project without being substantially protected on the commodity prices.
Show 1 more statement

Deals and partners

  • The company booked an order worth close to INR1,100-plus crores, INR1,200 crores, and work has started at the site; the company will start recognizing revenue from March onwards and expects about INR240 crores or thereabouts in the next financial year from Signature Global, Gurugram.
    Show source
    Coming to the main question, the order which we booked was close to INR1,100-plus crores, INR1,200 crores.

Risks, rules and outside factors

Risks and disputes

  • The company stands 100% safe on the INR67 crores amount given through provision and through property available.
    Show source
    Rohit Katyal: Your company stands 100% safe on the INR67 crores a mount given through provision and through property available.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Ranodeep S.: So my second question, the data center market in In dia is experiencing a massive boom driven especially by the digital adoption and AI advancements and government, in fact, promoting data localization. Sir, with hyperscalers and enterprises aggressively expanding capacity, the demand for construction expertise in this sector is also at an all-time high. So given capacity infra's strong credential in larg e-scale infrastructure projects, what are the steps that capacity is taking to position itself as a first choice contractor for data center construction? Any specific investments in technolog y or partnerships or skill development that you would like to highlight, sir?

    Answer, rohit katyal

    Rohit Katyal: So in data centers, we have constructed about 11 da ta centers for Department of Telecommunications through BSNL. Another 2 at Udham pur and Kolkata are under construction, expected to be handed over by April. Apart from this, we have participated in a substantially large data center project, which includes the hardware part to some extent as well. And it's on EPC basis. And therefore, the designing has been done through our joint venture partners, whose name we wouldn't like to divulge at this moment in time. Go ing forward, the company definitely is looking for collaborations on the design part because we believe that there's no need to reinvent an invented wheel. And you will see capacity as a strong contender for data centers to be put up by both public and private sector in the quarters to come.

  2. Question

    Ranodeep S.: Sure, sir. Just one last bookkeeping question, sir. I think in the Q1 call, you had guided for around INR3,000 crores worth of order inflows. At the end of 9 months FY '25, we are at INR1,459 crores. Do you still maintain your guidance for INR3,000 crores, sir?

    Answer, rohit katyal

    Rohit Katyal: So in my opening remarks, I mentioned that the new order inflow, excluding additions from MHADA, stand today at INR2,579 crores. We have just announced an order today of INR1,120 Capacit'e Infraprojects Limited February 14, 2025 Page 5 of 19 crores for the Supreme Court monitor NBCC project in Noida. And that takes the order book in the current year to INR2,579 crores. Further, we are in an L1 position in projects worth INR600 crores in private sector. And therefore, it should be by our conclusion that we w ill cross INR3,000 crores minimum as fresh order intake in the current financial year. Along w ith MHADA release of land in the current financial year, we will cross INR4,000 crores. Hope to have answered your question.

    Answer, rohit katyal

    Rohit Katyal: So your question was not very clear. But if I understand, you're referring to other income. So the INR10 crores is nothing but specialized items trade d to our joint venture companies, that is the other income. And that will range between INR2 cror es to INR12 crores over the next 3 to 4 quarters going forward.

  3. Question

    Rishi Kothari: And what exactly are the specialist items? I mean, any specific explanation can you give on it?

    Answer, rohit katyal

    Rohit Katyal: Yes. So for example, hospital oxygen modular equipm ents, which are required and in which Capacite as a stand-alone is a qualified contractor. Those are the items which are traded with the joint venture companies. The joint venture companies would include Capacit'e Bhandup project, which is in joint venture with e-governance. Second ly, it could include certain revenues for goods traded with Tata Projects Limited Capacit'e JV for BDD projects.

  4. Question

    Rishi Kothari: And my other question was related to the cost of material. So I have seen that the cost of material has gone up 45% Y-o-Y. So is it purely related to the revenue scale that we have? What exactly is that mixed in the cost of material?

    Answer, rohit katyal

    Rohit Katyal: See, when you talk about cost, please don't look at M only. By M, we say material. You have to see M and M plus L, both. And the third part is L. When you total that up, you will see that the cost is 65% approximately, which is in line with wh at we have been doing over the last 4 quarters.

  5. Question

    Rishi Kothari: You're saying cost of material plus the… Rohit Katyal: I will repeat it for you.

    Answer, rohit katyal

    Cost means labor subcontra ctor charges. It includes construction expenses. It includes material. So when you total t his up, it will come to somewhere between 65% to 66%, all right? This is what the company has been maintaining. If you look at the last 4 quarters, it ranges between 66.77% to 65.5%. Capacit'e Infraprojects Limited February 14, 2025 Page 6 of 19 Rishi Kothari: Okay.

  6. Question

    And also right now, you mentioned about the one-time expense that we have incurred on the GST revenue something. So is it that we have in curred on the other expense item? Or how exactly are we accounting for it?

    Answer, rohit katyal

    Rohit Katyal: Yes, other construction expenses. So we would like to inform and I clarified during my opening remarks that this INR12 crores pertains to Bhagwati project of MCGM, where the GST when it increased from 12% to 18%, the 6% differential GST is yet to be reimbursed by the client. The legal standing on the subject is that the client ha s to pay. However, as a prudent measure, since it has been outstanding for quite some time, we have made provision for the same. But we are very confident that in the coming quarters, this will get reversed. So that is the INR12 crore expense, which you were referring to. And tha t is why you see a small impact on the EBITDA, while over the 9-month period, we have surpassed a guided target for the EBITDA.

  7. Question

    Rishi Kothari: Yes. I'm saying in terms of the next 2 to 3 years, top line, bottom line target, any growth numbers in terms of not numbers, but any percentage kind of growth?

    Answer, rohit katyal

    Rohit Katyal: So with the order book, which we just informed you all, and with the execution, what we need to do and commit it to clients, obviously, we see a 25%, 30% growth year-on-year, if not more.

  8. Question

    Shreyans Mehta: And then in terms of working capital, how is it loo king like if you can give the numbers, inventory, debtors, unbilled?

    Answer, rohit katyal

    Rohit Katyal: So there is an improved shift from WIP to debtors, which will translate into higher receivables in the current quarter. And therefore, we should see the numbers of last March, which were close to -- excuse me. Working capital, please. Close to last March on a substantially higher revenue. Similarly, as we told that we should look at reduci ng about 10 days to 15 days in the current year. We are well poised to do that. We don't see a ny hiccup in that because we hardly are working with any private sector clients where the c ertainty of payments is not there.

  9. Question

    And then one last question in terms of the new order win, will it be a pass-through in terms of raw material or it will be a fixed price contract?

    Answer, rohit katyal

    Rohit Katyal: No. We don't believe in bidding for fixed price contracts. So, all projects what we take will have a pass-through clause in private sector. In governm ent, there will be escalation clauses, which differ from project to project, client to client, d iffers between state government and central government. However, we will not take up any project without being substantially protected on the commodity prices.

  10. Question

    Rajesh Jain: Okay. But by and large, is it largely provided for or even half of it is not provided?

    Answer, rohit katyal

    Rohit Katyal: Your company stands 100% safe on the INR67 crores a mount given through provision and through property available. Once the property is re gistered, on the contrary, you will see some profits being recorded by the company.

Show 14 more questions
  1. Question

    Rajesh Jain: Great. And is there any other provision remaining for any other receivables apart from the INR67 crores?

    Answer, rohit katyal

    Rohit Katyal: No, everything has been provided for or there are properties have been received by the company. So whatever new provisions come, they come only as per the ECL policy, which you have to recognize and which is approved by the audit commit tee of the company. So those provisions will keep happening and keep getting reversed as th e company moves forward, but all the provisioning which the company was subjected to dur ing COVID year and subsequent to that, close to INR200 crores had already been done.

  2. Question

    Rajesh Jain: Okay. And sir, as of Q3, as of December 2024, what are your total receivables or as a percentage of sales, if not the absolute figure?

    Answer, rohit katyal

    Rohit Katyal: The total receivables as on Q3 '24-'25 stand at INR 500 crores which is less than 90 days and should improve by about 15 days going forward in the current quarter. Capacit'e Infraprojects Limited February 14, 2025 Page 9 of 19 Rajesh Jain: Okay.

  3. Question

    And sir, can the margin be maintained at 18% plus in Q4 and in FY '26 as a whole? Can you maintain that margin, 18% plus?

    Answer, rohit katyal

    Rohit Katyal: See, we have been guiding 18% and that we have been -- we have maintained that on a 9-month period. It will be maintained on a 12-month period as well. However, I have been requesting our investors that EBIT is the right thing to look at because EBITDA just because your interest cost goes up and therefore EBITDA goes up, it does not ma ke any logical sense for the investing community at large. That is my firm belief. So, our EBIT if you see has seen nearly 200 basis po ints or 300 basis points improvement over the last 12 months. I do believe that, that will co ntinue. And yes, I do firmly believe that EBITDA, which was earlier guided at 17.5% upwards, that will continue.

  4. Question

    Akshat Bairathi: Yes. Interest and depreciation, both.

    Answer, rohit katyal

    Rohit Katyal: So the total finance cost has been for the current quarter INR25.29 crores as against the last quarter of INR21.58 crores, that means quarter-on-q uarter. If you look at year-on-year, it's virtually flat. So obviously, this year this quarter, we have both some charges of bank guarantee renewals and certain bank charges for renewal of limits. However, on the full year basis, if you -- when you will compare, you will see that on an absolute basis we would have reduced our finance cost on an increasing top line. So, as a percentage to the top line, your cost of finance will drop. I rep eat, it will drop as a percentage to the top line. On an absolute basis also, it will drop.

  5. Question

    Akshat Bairathi: Got it, sir. And on the depreciation side?

    Answer, rohit katyal

    Rohit Katyal: The depreciation is quite similar. I mean, it is basically cyclical. You have purchased equipment of INR60 crores this year. There will be depreciation. And it's hardly -- I mean, if you see on the first 9-month period, it is INR79 crores as compared to INR69 crores in the last financial year. Capacit'e Infraprojects Limited February 14, 2025 Page 10 of 19 Akshat Bairathi: Got it, sir.

  6. Question

    And last one on the tax rate, if you can give some color. This quarter, it has dropped.

    Answer, rohit katyal

    Rohit Katyal: So let me first correct you. I do not know if INR52 crores is less profit by any means. And 16.74%, we continue to lead the market as far as EBI TDA margins are concerned. At 16.74% EBITDA, not 20%, but INR12 crores is the one-time hi t for GST. INR12 crores translates to 2.05%. And therefore, had this hit not been taken, your EBITDA would have been at 18.74%, which is in line with what we have been declaring. I reiterate that we are in a construction industry, and therefore, a 12-month period is more sensible to be compared vis-a-vis a quarter.

    Answer, rohit katyal

    Reason, a quarter is too short a period for a construction industry, which basically takes 3 to 4 months to mobilize a project. However, having said that, we have already guided that the c ompany will be maintaining the overall guidance of 17.5% plus EBITDA, which is 18% approxim ately for the full year, and it will be maintaining and growing the EBIT by at least 200 basis points over the corresponding period of the last financial year.

  7. Question

    Dhananjay Mishra: So all my questions are answered. Just wanted to know about the CIDCO project and MHADA. You said INR1,000 crores for next year from the CIDCO project itself in terms of the top line and INR400 crores from MHADA. So, what is the contribution in Q3 from both these projects? And what is the expected contribution in Q4?

    Answer, rohit katyal

    Rohit Katyal: So Q3 contribution is INR190 crores. Q4, we should be seeing more than INR220 crores coming from this project. And next year, I already told you between INR80 crores to INR85 crores will be the run rate per month. MHADA, the total contrib ution for the current quarter is INR67.39 crores. We should see a similar contribution, slightly more, in the current quarter, that is Q4. From the next financial year, we do look at approximately IN R400 crores or thereabouts for the full financial year. So that translates into approximate ly INR35 crores to INR36 crores per month.

  8. Question

    Dhananjay Mishra: So, I mean, they are not finding any stress in terms of -- I mean, a lot of launches have happened in the past and of late launches have come down. So, are they facing any challenges in terms of selling their inventory and that is -- that may imp act our future project and even the ongoing project?

    Answer, rohit katyal

    Rohit Katyal: With the order win of yesterday from NBCC, nearly 76% of our projects are central government or government funded, sir. So, there is no question of we having any impact over there. You have seen that the urbanization program announced b y the central government in the current Capacit'e Infraprojects Limited February 14, 2025 Page 12 of 19 budget itself gives us a humongous opportunity and gives a look ahead for the next 4, 5 years. And that those allocations are only going to increase. That's point number one. Point number two, the allocation of PMAY housing ha s been increased by 14 lakh houses for the current -- next financial year in the central g overnment budget just announced. Now come to the private sector.

    Answer, rohit katyal

    Rohit Katyal: So you can take that the next financial year, we ha ve internally set a target of INR4,000 crores of new fresh order inflow, all right? Current financ ial year, we will close with a minimum of INR3,000 crores fresh order inflow, excluding whate ver is added from MHADA, okay? So, to just give you a sense that MHADA project for capacity is in excess of INR5,500 crores. We have recognized only INR2,200 crores in our order book. That means that another INR3,300 crores is yet to be recognized in the order book, w hich is circulated and informed to you and everyone else, all right? As and when the land is made available, we will start recognizing it as a part of our operational order book. So answering your question, though the bid pipeline is very strong, we will aim to have INR4,000 crores of fresh order intake in the next financial year.

    Answer, rohit katyal

    Rohit Katyal: I do not have any information on their own bid pipe line, though we do keep meeting them, and they do say that they have a lot of orders, which will come up next financial year. Coming to the main question, the order which we booked was close to INR1,100-plus crores, INR1,200 crores. Capacit'e Infraprojects Limited February 14, 2025 Page 13 of 19 And the work has started at the site. We shall star t recognizing revenue from March onwards. And obviously, with the time lines which we have ag reed to, we will have to build close to INR22 crores starting per month only on RCC part. So, answering your question, we should look at about INR240 crores or thereabouts in the next financial year coming from Signature Global, Gurugram, am I right? Yes.

    Answer, rohit katyal

    Similarly, the new project from NBCC also warrant s that we start that. We will start that billing again from April onwards. And given the tim e lines, obviously, we will see serious traction in the billing of that project as well. So, all these factors put together, CIDCO, MHADA, NBCC, private sector, which includes Godrej, which includes other clients, including Raym ond, it clearly showcases that the 25%, 30% growth for the next financial year is given. And that this is what I have been always harping on, that turnovers will only happen when you have 2 0 projects, which give you INR20 crores per month. That is how a construction company will grow, not just by adding orders, which do not add revenue or the bottom line. Riken: Got it.

    Answer, rohit katyal

    Rohit Katyal: So we do expect that about INR120 crores should be realized because out of that, some properties are on registration stage, which obviously the company doesn't expect to hold those properties. It needs to be disposed, all right? So, we do belie ve that over the next 15 months, the company will realize about INR115 crores to INR120 crores from the total loss of INR210 crores.

    Answer, rohit katyal

    Rohit Katyal: The company is sitting with unencumbered cash of cl ose to INR80 crores, apart from the fixed deposits, which are lying at the bank less margin f or LCBG. The total fund-based limits for working capital are INR190 crores. Utilization is INR140 crores. The total non-fund-based limits are close to INR1,000 crores within consortium, and the utilization is close to INR700 crores. Capacit'e Infraprojects Limited February 14, 2025 Page 14 of 19 So, INR960 crores minus INR700 crores, about INR260 crores of available bank guarantee and LC limits. I think this was your question. I hope to have answered.

  9. Question

    Khushwant Pahwa: Perfect. Just one more question. I think you have d one a consolidated revenue of around INR1,678 crores in the 9 months, and you did about INR1,932 crores in the last financial year. Are you in a position to give a broad guidance for how we'll close this financial year and some broad guidance for the next financial year? I know you mentioned 25% to 30% growth for the next 2 to 3 years.

    Answer, rohit katyal

    Rohit Katyal: Current financial year, we have guided 25%, and ther e's no reason why we shouldn't do that. Next year, I have told you that we have commitments to the client for at least 25%. But the new orders that are coming in have a shorter execution period. And therefore, this 25% could become 30%, 32% as well. However, the guidance year-on-year on a higher basis will be a minimum of 25%.

    Answer, rohit katyal

    Rohit Katyal: Actually, If you look at our presentation, which has been uploaded, so you will see that our EBIT is close to 14.6%. Deepak: Poddar: 14.6% For 9 months EBIT margin.

    Answer, rohit katyal

    Rohit Katyal: And I maintain that for a construction company, it has to be seen over a 12-month period, at least a 9- to 12-month period. And if you compare t hat with the corresponding 9 months last financial year, it was 12.1%. So, I just mentioned that we have improved the EBIT by 200-basis Capacit'e Infraprojects Limited February 14, 2025 Page 16 of 19 points, and that is basically the true growth that our investors will see, thereby resulting in cash PAT, thereby resulting into a reduction. When we say that we are going to reduce our debt, it should come from the numbers that we are presenting to you. So, improvement in EBIT is a very important factor because it doesn't take into consideration depreciation and amortization. And therefore, EBIT is a more logical number to follow as far as construction companies are concerned. That's my personal view.

    Answer, rohit katyal

    Rohit Katyal: So, our guidance was 12.5%. I had already informed in Q1 or Q2 that a 50-basis points improvement would be there. We have done better than that. Let us stick to this at the moment, but don't punish us for 1% plus or minus on a quarter-on-quarter basis. Deepak: Poddar: Absolutely. But this is the stable range we can look at, right? 14%, 14.5%.

    Answer, rohit katyal

    Rohit Katyal: For the full year, yes, we have already guided abov e 13%. So, anything above that is sweetish, please let's all enjoy that. Deepak: Poddar: Absolutely. And we were also talking about debt red uction, right? I mean, so currently, you're talking about similar debt levels in this year. So how should one look at FY '26? I mean, is there any debt repayment we are planning, any interest cost reduction also?

    Answer, rohit katyal

    Rohit Katyal: When I say similar debt level, I mention gross debt . As your collection improves, your cash position improves, and therefore, your net debt lev el may fall by INR20 crores, all right? However, we have to remember that in this particula r quarter, we'll be starting 2 new projects, all right? So, there will be an infusion of our wor king capital in those projects, I think, to start with. So, therefore, I have guided that the debt level on gross will be similar. There will be some further improvement in the free cash holding of the company, which for quarter 3 was close to INR75 crores or thereabouts. And we are very hopeful to take it in excess of INR100 crores by 31st March.

    Answer, rohit katyal

    Rohit Katyal: You should see a fall of INR100 crores in net debt. Deepak: Poddar: INR100 crores fall in net debt we are talking about , so ideally absolute level interest cost also expected to fall because of -- Rohit Katyal: You can see that.

    Answer, rohit katyal

    I mean, on an absolute basis, if you look at our finance cost for the first 9 months of the current financial year as well, INR72 crores as against INR69 crores. On an absolute basis, you will see a similar number on an increased turnover, a little bit lower, as I Capacit'e Infraprojects Limited February 14, 2025 Page 17 of 19 mentioned in my earlier answer to a question as wel l for the full financial year. Obviously, next year, it has to fall. An increase in cash will result in a fall of absolute interest.

  10. Question

    Raghav Agarwal: Yes. I just wanted to touch on the contract assets. So, in September, they were at around INR1,350 crores. Just wanted to get your view on li ke how do we plan to reduce over the next 1 to 2 years on the contract assets?

    Answer, rohit katyal

    Rohit Katyal: So we do believe that the contract assets in the cu rrent year will fall on an absolute basis. However, in the next financial year, we further see a reduction of INR200 crores over a 4-quarter period.

  11. Question

    Raghav Agarwal: Understood. So, can you just throw some light on when is the contract asset added. Essentially, what is the journey of contract assets? The reason I ask this is because compared to typically other EPC players, our contract assets seem to be slightly more elevated.

    Answer, rohit katyal

    Rohit Katyal: See, so on an annualized basis, we may be at 82 days as the industry average of 72 days, but we have already guided that there will be a reduction of 4 to 5 days as a percentage of the top line. So, if you look at 7 or 8 well-performing companies, you will see an average of 72% to the top line as contract assets, which includes wage cost compensation, uncertified bills, blah, blah, blah. And to that, you add your debtors as well. That would ultimately translate into 73% to 74%. And this is true for most of the companies. Â Okay, the re may be some exceptions, but generally, 85% to 90% of the good companies will have that lev el. We have a higher level than that.

    Answer, rohit katyal

    And as I told you, that we should be close to 78% by Ma rch. At least that's what we are targeting. And by next financial year-end, we should be below 70%, if not better.

  12. Question

    Raghav Agarwal: Understood. And last question is on the recent NCLT proceedings, which you had filed on the exchanges. So, I assume that the entire claim amount of roughly INR82 crores, INR83 crores is already provisioned for as ECL. Would that understanding be fair?

    Answer, rohit katyal

    Rohit Katyal: We are well on our way towards recovery, but you see the court matters take time. And all these amounts are acknowledged debt by the clients. So, the respective clients until they are bankrupt, we do see a very strong possibility of the recovery . I cannot give a particular timeline. But as I told you, that we are looking over the next 5, 6 quarters for recovery of INR115 crores.

  13. Question

    Raghav Agarwal: Understood, sir. Just wanted to understand where is this present in our financial books, the recovery amount?

    Answer, rohit katyal

    Rohit Katyal: No, it is not present. INR67 crores is present. Tha t will come. The balance amount, which will be recovered, will hit the bottom line.

  14. Question

    Rajesh Jain: Just one, stock-related question. So now your business prospects are looking so strong over the next 2, 3 years, 25% to 30%, even with positive upsides of the reversals of the recoveries directly hitting the bottom line. Now the stock is trading at 13p, is the management at all considering of buyback through the market purchase method, or else the promoters in their individual capacity are thinking of buying from the market?

    Answer, rohit katyal

    Rohit Katyal: We haven't discussed internally because the market has fallen today for reasons only God knows. Our stock is concerned. If you look at the trailing PE -- sorry, trailing EPS over the last 4 quarters, we are close to 24. So, 24 EPS means there's a subs tantial improvement, more than 100% improvement in the company's performance. I'm sure the market will recognize it very soon. As far as promoters are concerned, your company's p romoters are all professionals like you all are. So, we started this company in 2012, and we ha ve done everything possible in our means.

    Answer, rohit katyal

    Rohit Katyal: Absolutely. We will do that. However, we are surpri sed that 16.74% is a low EBITDA, or for that matter, 8.1% PAT is a low PAT. I mean, actuall y speaking, over the last 4 quarters or 3 quarters, especially starting March of '24 and the current financial year, we have outperformed all the targets on all parameters that we have given. However, your suggestion is well taken. The IR team and our accounts team have been informed, to day after what the drabbing which we saw, we will try to be extra cautious over such matters. Deepak: Yes, sir, because in a layman, basically, if you ex clude the JV process, it seems that the profit has fallen significantly, right?

Questions about this call

When was the Capacit'e Infraprojects Q3 FY25 earnings call transcript filed?
Capacit'e Infraprojects filed the transcript with the exchange on 17 Feb 2025. This page is built from that transcript.
What does this page list?
47 statements from the transcript across 9 topics, 31 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 24 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Capacit'e Infraprojects Q3 FY25 concall: Capacit'e Infraprojects Limited was awarded new projects worth INR 1,459 crores during 9 months ending December '24 · DalalOS