Diamond Power Infrastructure Q1 FY27 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Order book stood at INR3,688 crores, roughly $445 million, about 2 times last year’s revenue across 12 product lines, as on August 11, 2026, with over INR1,000 crores of fresh wins since April. The company is confident it will have more than 50% to 60% of next year’s targets covered by order book when it begins the next year. The company has approved two aluminum corrugation lines that will materially expand its 66 kV cable capacity and 132 kV cable capacity; adding them with a minimal capex of INR17 crores substantially opens up 66 and 132 capacity by compromising one line of 33 kV. Consolidated revenue was INR690 crores, up 129% year-on-year, and EBITDA was INR85 crores, up 172%, at a margin of 12.3%, an expansion of nearly 200 basis points, in the quarter ended 30th June 2026. The company completed a QIP placement raising INR1,640 crores, close to $195 million, achieving full minimum public shareholding compliance and welcoming marquee institutions into its register.
The numbers management gave
Results
- Consolidated revenue was INR690 crores, up 129% year-on-year, and EBITDA was INR85 crores, up 172%, at a margin of 12.3%, an expansion of nearly 200 basis points, in the quarter ended 30th June 2026.
Show source
EBITDA was INR85 crores, up 172% on a margin of 12.3%, and an expansion of nearly 200 basis points.
- Tax charge was negligible in the quarter ended 30th June 2026 because it continued to carry forward accumulated losses from the period preceding its resolution plan; the benefit will taper over time and is expected to remain for at least the next two years.
Show source
However, we have met our internal target of INR700 crores.
- Profit after tax was INR58.5 crores, up 191%, at a net margin of 8.5%, and earnings per share was INR1.11 on a face value of INR1 in the quarter ended 30th June 2026.
Show source
Profit after tax was INR58.5 crores, up 191%, at a net margin of 8.5%.
- Profit grew considerably faster than its revenue because of operating leverage, as newer and higher-value production lines matured and carried most of the load.
Show source
Our profit is growing considerably faster than our revenue.
- Auditor qualification that had been on the books stood resolved during the quarter, and the numbers were without any qualification.
Show source
More importantly, the auditor qualification which was on the books till now stands resolved and the numbers are without any qualification.
Money and capital
- The company completed a QIP placement raising INR1,640 crores, close to $195 million, achieving full minimum public shareholding compliance and welcoming marquee institutions into its register.
Show source
We completed a QIP placement raising INR1,640 crores, close to $195 million, achieving full minimum public shareholding compliance and welcoming marquee institutions into our register.
Show 1 more statement
Money and capital
- The company had net worth of negative INR922 crores as on 30th June '26 and, after QIP proceeds of INR1,614 crores, net worth was positive by INR691 crores as on today.
Show source
So whatever little legal hurdle was there got settled in May.
What it expects ahead
What management expects
- The company is confident it will have more than 50% to 60% of next year’s targets covered by order book when it begins the next year.
Show source
So we are confident that when we begin the next year, we would have got the next year targets more than 50% to 60% order book in place.
- The company is firmly on track to deliver a full-year top line in the range of INR4,300 crores to INR4,500 crores, while holding the margin profile seen in the quarter ended 30th June 2026 and not sacrificing it for volume.
Show source
On that basis, we are firmly on track to deliver a full year top line in the range of INR4,300 crores to INR4,500 crores.
- The company expects the gross margin headwind to ease as mix and utilization improve, with the impact visible in the next three quarters.
Show source
As mix and utilization both improve from here, we expect the gross margin headwind to ease and the operating leverage to compound on the top of it.
- Q1 results were earned on the balance sheet as it stood without the benefit of fresh capital; the funds are now being deployed into capacity, with the impact expected in the third and fourth quarter as new lines commission and load.
Show source
It converts into P&L as the new lines commission and load, which means it will land squarely on the third and fourth quarter.
Orders
- Order book stood at INR3,688 crores, roughly $445 million, about 2 times last year’s revenue across 12 product lines, as on August 11, 2026, with over INR1,000 crores of fresh wins since April.
Show source
As on August 11, 2026, it stood at INR3,688 crores, roughly $445 million, and about 2 times of last year’s revenue across 12 product lines, and it continues to grow with over INR1,000 crores of fresh wins since April.
- The company took orders worth INR400 crores in the last six to seven days.
Show source
I am also very happy to tell you that in the last six to seven days itself, we have taken orders worth INR400 crores.
Show 4 more statements
Orders
- The company added INR400 crores of miscellaneous orders in the last 7 days.
Show source
Other miscellaneous orders, in last 7 days itself, we have added INR400 crores.
- INR435 crores data center order sits within its INR3,688 crores order book, and roughly INR845 crores of that order book is to be executed in the next year.
Show source
Our INR435 crores data center order sits within it, and roughly INR845 crores out of this INR3,688 crores is to be executed in the next year.
- The company has around INR2,800 crores of order book to deliver before March for the current year and is adding between INR275 crores and INR325 crores of orders every month.
Show source
So for the current year, we are holding an order book of around INR2,800 crores to be delivered before March, along with the fact that we are adding between INR275 crores to INR325 crores of order every month.
- The company reported two major orders: one from Rajesh Power for disaster management and a second from the electricity board.
Show source
Therefore, you have seen that we have reported two major orders, one from Rajesh Power for disaster management, and second order coming in from the electricity board.
What it is building and selling
Projects and capacity
- The company has approved two aluminum corrugation lines that will materially expand its 66 kV cable capacity and 132 kV cable capacity; adding them with a minimal capex of INR17 crores substantially opens up 66 and 132 capacity by compromising one line of 33 kV.
Show source
It is important to understand that with the same CCV lines, by adding two more aluminum corrugation lines with a minimal capex of INR17 crores, we have opened up 66 and 132 capacity substantially by compromising one line of 33 kV and added more value-added products, so our return on investment becomes stronger.
- Two additional medium voltage cable lines are under installation and on schedule; they provide workhorse capacity for the 11 to 220 kV segment, the largest single block of its order book.
Show source
And third, our two additional medium voltage cable lines are under installation, and I am happy to tell you they are on schedule.
- At full utilization, Diamond Power Infrastructure Limited’s low voltage cable facility will add around 42,000 kilometers of capacity with revenue potential approaching INR1,880 crores.
Show source
At full utilization, it adds around 42,000 kilometers of LV capacity with revenue potential approaching INR1,880 crores.
- Commercial production from Diamond Power Infrastructure Limited’s low voltage cable project is expected from financial year ‘27-‘28, and the company will commission it before March.
Show source
Commercial production is expected from financial year ‘27-‘28.
- The company had four CCV lines and four silane-based lines operational; one installed CCV line was to be commissioned by March, one silane-based line was to be commissioned by 15th of September, and one line being ordered was to be commissioned by December 2027.
Show source
Raman K.V.: Sir, but if my understanding is right, as of March 2026, in your balance sheet, we have around long-term borrowing of INR2,400 crores.
- Sixth CCV line will require no additional civil capex, utility capex, utility costs or infrastructure costs because its existing infrastructure has scope and provision for the line.
Show source
There are no additional utility and infrastructure costs involved.
Show 3 more statements
Projects and capacity
- The company is converting its old rod mill and legacy conductor plant into a modern low voltage and control cable facility for both aluminum and copper, a brownfield upgrade with no civil construction cost.
Show source
We are converting our old rod mill and legacy conductor plant into a modern low voltage and control cable facility for both aluminum and copper, a brownfield upgrade with no civil construction cost.
- Low voltage cable facility is deliberately built for copper LV cables to suit data centers.
Show source
First, it is deliberately built for copper LV cables to suit data centers.
Deals and partners
- The company is on the forefront of getting data center orders in the country. Replaced by a later filing.
Show source
Diamond is on the forefront of getting data center orders in the country.
Risks, rules and outside factors
Outside factors
- The company said aluminum and copper prices stood firm through the quarter, and a portion of its order book was executed at prices agreed before the input moved, causing pass-through as a percentage of sales to reach it with a lag.
Show source
Raw materials, aluminum and copper both stood firm through the quarter and a portion of our order book is executed at prices agreed before this input moved, so the pass-through as per percentage of our sales reaches us with a lag.
- The company said it passes increases in metal and polymers to all its customers on a completely back-to-back basis.
Show source
We are completely back-to-back on passing the increases in metal and polymers to all our customers.
Everything else said on the call
What management stressed
- The company is moving towards a leadership position in the medium voltage and extra high voltage segment of India’s cable and conductor market. Replaced by a later filing.
Show source
Diamond Power is moving decisively towards a leadership position in the medium voltage and extra high voltage segment of India’s cable and conductor market.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Ajit Sethi: Yes. Thank you for the opportunity. Sir, with a net worth still negative and having now raised around INR1,600 crores through QIP, will this infusion be enough to make DICABS net worth positive? And if yes, by when? And out of this INR1,600 crores raised, how much is going towards clearing promoter debt legacy liability versus funding new capacity? ..... Management: Okay. So, on net worth, Pawan, why don't you share? Management: So, as on 30th June '26, our net worth is negative by INR922 crores. But after this QIP proceed from QIP, which is INR1,614 crores, our as on today, our net worth is positive by INR691 crores. Management: So yes. Now coming to the usage of the funds from
Answer, ajeet sethi
Ajeet Sethi: Great, sir. And sir, on May 2026, PMLA discharge or released INR10 billion plus of fixed assets and INR9.78 billion of the NCLT receivable. Has the company started using or monetizing this? And how much of this receivable do you realistically expect to recover in cash? Management: See, the asset was already under use since last four years because under PMLA possession was not taken. It was given to the new management. What has happened is now legally, it has got discharged and under IBC's clean fleet theory, it is basically the right of the new management to take over the assets.
Answer, ajeet sethi
So whatever little legal hurdle was there got settled in May. Coming to the receivables, there are INR957 crores of legacy receivables on the books. Post this order, we have put a special team in place, comprising of senior legal hand, one senior guy from accounts and three juniors. And we are doing a first stage evaluation on how much can be recovered. At this stage, it seems around INR300 crores can be recovered over a period of next 1 year to 18 months. And that is where we will focus and we feel we'll be able to get it.
Answer, ajeet sethi
Ajeet Sethi: Okay. And sir, regarding the audit qualification on depreciation of PPE and the company has indicated that the issue is resolved. So how should we think about the depreciation expense going forward? Management: So, the depreciation which you are seeing in the first quarter will be the depreciation going forward. Save whatever additions we are going to do pro rata the depreciation will be there in books. Page 10 of 18 Diamond Power Infrastructure Limited August 14, 2026 Ajeet Sethi: Okay.
Answer, ajeet sethi
And sir, in our previous presentation, we have indicated that our existing capacity at peak would generate around INR1,400 crores of revenue. Is the upcoming new capacity already factored into this estimate or it will be incremental to this INR14,000 crores revenue potential? Management: No, it is factored. And accordingly, we have said additions. It will be factored in.
Answer, ajeet sethi
Ajeet Sethi: Okay. And sir, just a clarification from the call before. So we expect INR7,500 crores in FY28. Have you mentioned that? Management: Yes. Yes.
Answer, ajeet sethi
And so we were expecting somewhere around 75% utilization in next three years. So, is the guidance intact? Management: So we are targeting INR1,000 crores. We are a growing company. The market is growing. We are now getting financially stronger. We have zero -- virtually zero debt on the books.
Answer, ajeet sethi
So if we see some opportunities going forward, organic, inorganic, some products doing better, three years is a long time. We are open in terms of how we can ramp up and scale up. We are always on the lookout..
Question
Raman KV: Sir, I have a couple of questions. One with respect to capex per line. Currently, how many lines are operational? One is that? And what's our capex per -- capex cost per line? And how much revenue per line on an average can we do? Management: So we have four CCV lines operational. We have four silane-based lines operational. One CCV line installed, but will be commissioned by March. One silane-based line will get commissioned by 15th of September. One line which we are ordering at present will get commissioned by December 2027. The cost of a silane-based line is between INR15 crores to INR20 crores. A cost of a CCV line is -- line cost is around INR50 crores. Again, it depends on w
Answer, raman k.v
Raman K.V.: Understood, sir. Thank you for that. My second question is with respect to our debt, what will be our peak debt going forward in 2028? Management: Yes, Yes. So, at present we have INR75 crores LC, INR5 crores CC limit from one bank. We are not utilizing it at this point of time because you are aware we have a lot of QIP funds with us. Whatever money is required to achieve the target for the current year, we will not need any borrowing.
Answer, raman k.v
Yes, we are looking at how we can get vendor financing, how we can get dealer financing, because there are two parts of the business. If we can efficiently finance, support our vendors, support our dealers, we will improve our cash flow, and in process, we will improve our margins. Next year, INR7,500 crores. We are estimating that in the current year, if we own around INR500 crores plus. For the next year, the incremental cash is already available with us. So, up to 2027, 2028, we don’t expect to have any substantial debt on the books of the company unless we get some good opportunity or we look for some other additional plans, then I cannot tell you. As of now, I think mentally, the management and the professional s here are very clear that up to March 2028, our strategy, our capacity, and our route is very clear as on date.
Answer, raman k.v
Raman K.V.: Sir, but if my understanding is right, as of March 2026, in your balance sheet, we have around long-term borrowing of INR2,400 crores. Page 14 of 18 Diamond Power Infrastructure Limited August 14, 2026 Management: So, basically, that was INR1,900 crores of bonds, 0.01% bonds payable after 30 years. These bonds are owned by the promoter. The next part was a INR400 crores unsecured loan from the promoter, which has been paid back post-QIP. There is no debt as such other than the residual value of those bonds if discounted on a net present value, they stood at INR47 crores in March 2026.
Answer, raman k.v
Raman K.V.: In 0.01% coupon rate bonds, right? Management: Yes. Payable after 30 years. This was the unsustainable debt of the company in the NCLT plan, which was converted to bonds payable after 30 years, and the bonds are now acquired by the promoter from the lenders. These are unsecured promoter-held bonds. If discounted on net present value, their value is INR47 crores.
Questions about this call
- When was the Diamond Power Infrastructure Q1 FY27 earnings call transcript filed?
- Diamond Power Infrastructure filed the transcript with the exchange on 21 Aug 2026. This page is built from that transcript.
- What does this page list?
- 29 statements from the transcript across 8 topics, 16 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 2 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.