Earnings call
Diamond Power Infrastructure Q2 FY27 earnings call: Diamond Power's medium voltage cables were INR1,328 crore of its order book position, or 36%, in Q2 FY27
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Diamond Power's medium voltage cables were INR1,328 crore of its order book position, or 36%, in Q2 FY27. Diamond Power is standing by its guidance for financial year 2027 revenue of INR4,300 crores to INR4,500 crores. Diamond Power is building a single-core 3.3 kV cable plant with capacity of 1,000 kilometre a month, which will get on stream in the next 18 months, driven by demand from solar parks. Diamond Power's 3.3 kV solar cable revenue was INR39 crores in Q2 FY27, and its firm order book position for 3.3 kV solar cables was INR221 crores, with key developers including Tata Power, Solar; Diamond Power classified Tata Power, Solar as a key account in October because it expects very large order inflows from Tata Power. More than 5,000 kilometres of 33 kV tenders are coming up in Bengal.
The numbers management gave
Results
- Diamond Power's 3.3 kV solar cable revenue was INR39 crores in Q2 FY27, and its firm order book position for 3.3 kV solar cables was INR221 crores, with key developers including Tata Power, Solar; Diamond Power classified Tata Power, Solar as a key account in October because it expects very large order inflows from Tata Power.
Show source
3.3 kV solar cables were INR39 crores in Q2 and are INR221 crores on the firm order book position from key developers like Tata Power, Solar, which we have now classified as a key account in October, considering the fact that we are expecting very large order inflows from Tata Power.
- Diamond Power delivered INR240 crores of data centre cable in one single month in September, and most leading consultants in the data centre space have approved Diamond Power, making it a preferred vendor.
Show source
As I mentioned to you the last quarter, we have made a dedicated data centre team, and I can proudly tell you that most of the leading consultants in the data centre space have now approved Diamond Power., and we are now the preferred vendor considering the fact that we delivered INR240 crores of data centre cable in one single month in September.
- Diamond Power's super-clean compound has a margin of more than INR50 a kg.
Show source
Presently, we have certain data which tells us that in this compound , the margin is more than INR50 a kg.
- Diamond Power delivered INR1,722 crores in H1 FY27 and needs INR2,580 crores in H2 FY27 to meet its financial year 2027 revenue guidance.
Show source
With INR1,722 crore s delivered in H1, we have to get you INR2,580 crores in H2.
Money and capital
- Diamond Power is funding the project with INR78 crores from the GCP account of the QIP, INR100 crores from internal accruals and a small amount of debt if needed.
Show source
This project is being funded by INR78 crores from the GCP account of the QIP, and INR100 crores from internal accruals, and a small amount of debt if we feel we need to get it.
What it expects ahead
What management expects
- At Diamond Power's current volumes, captive consumption of the compound would leave additional EBITDA of INR120 crores.
Show source
And at our current volumes, this will really leave an additional EBITDA of INR120 crores when we use it on a captive consumption basis.
- Diamond Power is standing by its guidance for financial year 2027 revenue of INR4,300 crores to INR4,500 crores.
Show source
We are still standing by with that number.
Orders
- Diamond Power's medium voltage cables were INR1,328 crore of its order book position, or 36%, in Q2 FY27.
Show source
Medium voltage cables are INR1,328 crore s of our order book position, which is 36%.
- Adani Electricity placed an INR152 crore LOI on Diamond Power in Mumbai.
Show source
In Mumbai, Adani Electricity has placed a INR152 crore s LOI on us.
- PGVCL-related contractors ordered almost INR195 crores of these cables from Diamond Power in the last quarter.
Show source
Accordingly with that, we have PGVCL-related contractors who have ordered almost INR195 crores of Page 6 of 23 Diamond Power Infrastructure Limited November 04, 2026 these cables in the last quarter itself.
- Diamond Power received an INR164.5 crores EHV order for Jamnagar, and it expects good inflow on 66 kV in the next 90 days.
Show source
We received INR164.5 crores EHV order for Jamnagar, and further 66 kV tenders are in pipeline, and we are expecting a good inflow on 66 kV in the next 90 days.
Show 1 more statement
Orders
- Diamond Power's order book position was INR3,735 crores in Q2 FY27.
Show source
To sum up, a first thousand-year quarter, a half year that has already out-earned all of last year, a balance sheet that has gone from negative net worth to a positive cash flow, a INR3,735 crores order book position and a capacity enhancement program that moves up step by step, voltage class by voltage class.
What it is building and selling
Projects and capacity
- Diamond Power is building a single-core 3.3 kV cable plant with capacity of 1,000 kilometre a month, which will get on stream in the next 18 months, driven by demand from solar parks.
Show source
Demand from solar parks is strong enough that we are building a 1,000 kilometre a month single-core 3.3 kV cable plant which will get on stream in the next 18 months.
- Diamond Power's 66 kV underground program is on track.
Show source
Our 66 kV underground program is also on track.
- Diamond Power is setting up an integrated polymer complex with an INR170 crores investment in a 1.5 lakh square foot building; the land has no cost because Diamond Power already has it.
Show source
We are setting up an integrated polymer complex which is INR170 crores of investment at a in a 1.5 lakh square foot building with no land cost because the land already we have.
- Diamond Power's integrated polymer complex will have combined capacity of 84,500 tons.
Show source
The combined capacity of the project will be 84,500 tons.
- Phase 1 of Diamond Power's integrated polymer complex includes two PVC lines, two silane lines, one master-batch line and one peroxide-based line, with capacity of 66,500 tons a year.
Show source
Two PVC lines, two silane lines, one master-batch line , and one peroxide-based line with a capacity of 66,500 tons a year.
- Phase 1 of Diamond Power's integrated polymer complex will make PVC, FR, FRLS sheething compound, bedding compounds, Silane XLPE for 1.1 to 11 kV, and peroxide for 33 kV.
Show source
They will make PVC, FR, FRLS sheething compound, bedding compounds, Silane XLPE for 1.1 to 11 kV, and peroxide for 33 kV.
Show 15 more statements
Projects and capacity
- All output from Phase 1 of Diamond Power's integrated polymer complex will be captive.
Show source
All of Phase 1 output will be captive.
- Diamond Power's PVC and catalyst line was commissioned first, and the full phase is to be commissioned progressively between June and December 2027.
Show source
The PVC and catalyst line commissioned first, and the full phase is on stream to be commissioned between June and December 2027 progressively.
- Diamond Power's Phase 2 is a Swiss engineer reciprocating line using the same low-shear mixing platform that global compound makers use, making super clean peroxide XLPE insulation for 66, 132, 220 and 400 kV lines.
Show source
The same low-shear mixing platform that global compound makers use, making super clean peroxide XLPE insulation for 66, 132, 220, and 400 kV lines.
- Diamond Power's Phase 2 line will have capacity of 18,000 tons.
Show source
This is going to be 18,000 tons capacity.
- Diamond Power's project model shows a 30% post-tax IRR on a consolidated basis.
Show source
The project model shows a 30% post -tax IRR on a consolidated basis.
- Diamond Power's balancing equipment project, doubling of copper cable capacity and 5th and 6th CCV line are already running, with the CCV lines to be commissioned.
Show source
The other projects already running are the balancing equipment project, the doubling of the copper cable capacity, the 5th and 6th CCV line which is going to get commissioned.
- Diamond Power's LV cable project is to be commissioned before April 2027.
Show source
Our LV cable project, as promised, is going to be commissioned before April 2027, which will get us a very large inroad into LV cables.
- Diamond Power's single-core cable project targeting solar infrastructure is already on stream.
Show source
Additionally, the single -core cable project which targets the solar infrastructure is already on stream.
Demand and pricing
- More than 5,000 kilometres of 33 kV tenders are coming up in Bengal.
Show source
In Bengal, we have seen more than 5,000 kilometres of 33 kV tenders which are now coming up.
- Diamond Power has moved ahead of Adani in Western India and Northern India and is now focused on pan-India.
Show source
In short, Diamond Power has now moved ahead of Adani in Western India and Northern India, and now the focus is pan-India.
Segments
- Diamond Power's super-clean compound has zero impurities and nothing impure below 100 microns.
Show source
When we say Super-Clean the compound has zero impurities and there is nothing which is impure, less than 100 microns.
Deals and partners
- Diamond Power's recent 132 kV supply to Siemens India, Duttipuram Port and Indian Oil Tanking is a validation of its expansion across the market and work with sensitive industries such as ports and refineries.
Show source
Our recent 132 kV supply to Siemens India, Duttipuram Port, and Indian Oil Tanking is a validation of how we are now panning across the market and dealing with very sensitive industries like port and refineries.
- Diamond Power has a dedicated servicing team for Waaree, ACME, CleanMax and Enrich.
Show source
We have now a dedicated servicing team for Waaree, ACME, CleanMax, Enrich.
- Diamond Power has worked for the Yamuna Expressway, Mundra Port, Delhi International Airport, NTPC Vindhyachal and Reliance's bio-CNG plant at Jhajjar.
Show source
The Yamuna Expressway, Mundra Port, Delhi International Airport, NTPC Vindhyachal , the bio-CNG plant at Jhajjar for Reliance, these are some examples of the clients which we have worked on.
- Diamond Power's industrial names this quarter included AMNS, JSW, SAIL, Bukharovski and Serum Institute of India.
Show source
Our industrial names this quarter was AMNS, JSW, SAIL, Bukharovski, and Serum Institute of India.
Everything else said on the call
People and governance
- Diamond Power has a new Chief Operating Officer and a new CFO, both with industry experience.
Show source
We have a new Chief Operating Officer and a new CFO, both of whom have a fantastic industry experience.
- Diamond Power has started succession planning and created a director's office to bring its Gen Next into decision-making over the next five to seven years.
Show source
Page 9 of 23 Diamond Power Infrastructure Limited November 04, 2026 We have now started working on succession planning and a director's office has been made so that in the next five to seven years, we get our Gen Next to come on board and start being part of the decision-making process in the company.
Other
- Diamond Power's new CFO, Mr. Kundip Thakker, said cable companies do 40% of revenue in quarter 1 and 2 and 60% in quarter 3 and 4.
Show source
As my new CFO, Mr. Kundip Thakker told me yesterday, that most of the cable companies do 40% revenue in quarter 1 and 2 and 60% come in quarter 3 and 4.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Sanjaya Satapathy: Understood, understood. Thank you, sir.
Answer, aalok shah
Aalok Shah: Thank you, participants, for joining in and for this healthy discussions. On behalf of Monarch Networth, we would conclude this call. Amit, sir, you would have any concluding remarks? Or we can conclude the call? Management: No, thank you very much. I think Mr. Kundip Thakkar would like to say something. Management: Just to add to that, in case your questions are not answered or we have not been able to do that because of time constraints, you can write to us and we will get back to you one- to-one.
Questions about this call
- When was the Diamond Power Infrastructure Q2 FY27 earnings call transcript filed?
- Diamond Power Infrastructure filed the transcript with the exchange on 7 Nov 2026. This page is built from that transcript.
- What does this page list?
- 36 statements from the transcript across 10 topics, 23 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 1 question and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.