Earnings call
Garden Reach Shipbuilders & Engineers Q2 FY27 earnings call: Garden Reach Shipbuilders & Engineers Limited received an order from the West Bengal tourism department for 200 passenger electric ferries
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company received an order from the West Bengal tourism department for 200 passenger electric ferries. The company expects an order value of about ₹1,000 to ₹1,100 crores for the 22 interceptor boat projects for the Indian Coast Guard. Anti-Submarine shallow water craft project is an eight-ship project, and five vessels have been delivered, including the fifth vessel on 5th of November. The company reported revenue of Rs 1,827 Cr in Q2 FY27 and Rs 3,641 Cr in H1-FY27, compared with Rs 1,677 Cr in Q2 FY26 and Rs 2,987 Cr in H1-FY26, growth of 9% and 22%, respectively. In Garden Reach Shipbuilders & Engineers Limited’s warship production cycle, maximum revenue recognition typically occurs when physical progress of construction is between 40% and 65%.
The numbers management gave
Results
- Revenue had grown at a CAGR of about 20% to 25% over the last few years while its P-17 Alpha and Anti-Submarine Shallow Water Craft projects were in their peak execution phase.
Show source
The last few years, you have seen the re venue going almost exponentially at CAGR of about 20% to 25%.
- The company reported revenue of Rs 1,827 Cr in Q2 FY27 and Rs 3,641 Cr in H1-FY27, compared with Rs 1,677 Cr in Q2 FY26 and Rs 2,987 Cr in H1-FY26, growth of 9% and 22%, respectively.
Show source
When compared year-on-year, our revenue from operations for the quarter have moved up from ₹1,677 crores to ₹1,827 crores, registering a growth of about 9% and the profit after tax going up by 12% from ₹154 crores to ₹172 crores.
- Margins on the P-17 Alpha project are good.
Show source
Now, the P-17 Alpha project is closing this year.
What it expects ahead
What management expects
- The company expects an order value of about ₹1,000 to ₹1,100 crores for the 22 interceptor boat projects for the Indian Coast Guard.
Show source
From the Indian Navy and the Coast Guard, there are four RFPs where the bids have already been submitted, 22 interceptor boat projects for the Indian Coast Guar d. We expect the order value to be to the tune of about ₹1,000 to ₹1,100 crores.
- For the 31 Follow-on Water Jet FACs for the Indian Navy, the order will be split between two shipyards, with the L1 shipyard getting 19 vessels and the L2 shipyard getting 12 vessels; Garden Reach Shipbuilders & Engineers Limited expects the order value to be about ₹15,000 crores.
Show source
As per the RFP conditions, the order will be split between two shipyards with the L1 shipyard getting 19 vessels and the L2 shipyard getting 12 vessels and we expect the order value to be to the tune of about ₹15,000 crores.
- The company says the order value for the 120 Fast Interceptor Crafts project for the Indian Navy is likely to be about ₹4,500 to ₹5,000 crores.
Show source
The order value is likely to be to the tune of about between ₹4,500 to ₹5,000 crores and six for the Next Generation Offshore Patrol Vessels for the Indian Coast Guard where the order value is expected to be to the tune of about ₹3,500 crores and all put together, the four projects that I mentioned, the order value is tantamount to about ₹25,000 crores.
- The company estimates the combined order value of the four projects it mentioned to be about ₹25,000 crores.
Show source
The order value is likely to be to the tune of about between ₹4,500 to ₹5,000 crores and six for the Next Generation Offshore Patrol Vessels for the Indian Coast Guard where the order value is expected to be to the tune of about ₹3,500 crores and all put together, the four projects that I mentioned, the order value is tantamount to about ₹25,000 crores.
- The Landing Platform Dock project has an AoN value of about ₹33,000 crores.
Show source
The Landing Platform Dock project is again a high-value project to the tune of AON value of about ₹33,000 crores.
- The company expects delivery of the first vessel under the NGC project during the latter half of calendar year 2032, with the fifth vessel to be delivered in 2035, 2036.
Show source
As per the contractual timelines, the first vessel is expected to be delivered during mid, rather, the latter half of calendar year 2032.
Show 41 more statements
What management expects
- For the NGC project, Garden Reach Shipbuilders & Engineers Limited said design finalization could be to the tune of about 7.5%-8% of the project cost, and moderate revenue recognition would commence from financial year '28.
Show source
So, this quantum could be to the tune of about 7.5%-8% of the project cost.
- The company expects the P - 17 Alpha project to be completed this financial year, during the ongoing quarter; the Anti-Submarine Shallow Water Craft project to spill over to the first quarter of FY '28; the NGOPV project to be completed by financial year '29; and the research vessel project to be completed by FY28 and '29.
Show source
Yes, two projects, that is the P - 17 Alpha project would get completed this financial year, actually this particular for the ongoing quarter.
- The company expects about 7.5% of the NGC project’s order value from revenue recognition during the pre-production phase, mostly comprising design and procurement-related activities.
Show source
Here, on a conservative basis, we expect about 7.5% of the order value.
- The company expects to recognize about 7.5% of the Next-Generation Corvette high-value project in the next financial year, following a first phase lasting about a year and a half from now.
Show source
Again, I would like to repeat that we have just started the Next-Generation Corvette high-value project, the first phase, which will be to the tune of about a year and a half from now, which means in the next financial year, we should be able to recognize about 7.5%.
- The company expects the L1 declaration for P-17 Bravo during the current financial year and, in the worst case, expects the contract to be concluded during the next financial year, towards the fourth quarter of the next financial year.
Show source
Worst case, we expect the contract to be concluded during the next financial year, towards the fourth quarter of the next financial year.
- The company has about ₹ 25,000 crores worth of orders for which RFPs and bids are already closed, and expects bid results to be announced in the next few months, starting with the interceptor boats, the water jet FACs and the OPVs.
Show source
Second, I'd also mention that about ₹ 25,000 crores worth orders, the RFP, the bids are already closed, and we expect the bid results to be announced in the next few months, starting with the interceptor boats, the water jet FACs and the OPVs.
- The company says the P-17 Bravo project, when it comes, and the NGC project will be handled to ensure concurrent construction without impacting customer expectations.
Show source
So, again, to just get back to your question, concurrent construction of P-17 Bravo, when it comes, I would not even use the term if it comes, when it comes and the NGC project would be handled by us in a manner which will not impact the customer expectations or rather will ensure concurrent construction.
- The company expects the order value for six Next Generation Offshore Patrol Vessels for the Indian Coast Guard to be about ₹3,500 crores.
Show source
The order value is likely to be to the tune of about between ₹4,500 to ₹5,000 crores and six for the Next Generation Offshore Patrol Vessels for the Indian Coast Guard where the order value is expected to be to the tune of about ₹3,500 crores and all put together, the four projects that I mentioned, the order value is tantamount to about ₹25,000 crores.
- The mine countermeasure vessel project has an AoN value of about ₹44,000 crores.
Show source
And of course, the mine countermeasure vessel project, the long-awaited project where the AON value is to the tune of about ₹44,000 crores.
- FY '27 is expected to be a peak year for Garden Reach Shipbuilders & Engineers Limited because one piece of an Alpha would have just come out and the last one will definitely come out during FY ' 27.
Show source
There will be a trough, and our peak years, as I have been reiterating in multiple interactive sessions that we had before, are FY26 and '27.
- The company expects its multipurpose vessels export project and platform supply vessels to move on to FY29.
Show source
Definitely, the multipurpose vessels export project will, and the platform supply vessels will move on to FY29.
- The company expects revenue contribution from the NGC to pick up substantially by FY29.
Show source
We expect by FY29, the revenue contribution from the NGC would pick up substantially.
- The company said the NGC is not a nomination project and its margins are adequate and akin to the profitable Anti-Submarine Shallow Water Craft project.
Show source
Yes, NGC has not been a nomination project, but all I can say is that the margins are adequate and akin to the Anti-Submarine Shallow Water Craft project, which is a profitable project.
- The company expects the NGOPV project to peak in revenue recognition during the next financial year.
Show source
But we will still have the NGOPV project, which will peak as far as its revenue recognition is concerned during the next financial year.
- The company expects the tempo of project execution to continue in the next financial year, with the Ocean Research Vessel, the Acoustic Research Ship, and the Multi-Purpose Vessel project for the German client picking up and getting fully blown in growth during that year.
Show source
So, we expect the tempo with respect to project execution to continue in the next financial year also.
- The company has procured more machines for bailey bridges and shipbuilding, and sees production throughput increasing substantially.
Show source
And we see the production throughput to increase substantially.
- The company intends to continue its partnership strategy so it does not miss orders for want of capacity, using a PPP model or partnering with another capable public sector shipyard.
Show source
To meet this strategy, we will be resorting to PPP model or even a partnership with another capable public sector shipyard.
- The company expects MSMEs receiving long-term visibility and large-size orders to enhance capacity and deliver products on time with the quality expected by the company or its end customers.
Show source
Now, having said that, what the MSMEs in turn would need to do is to ensure that if long-term visibility and large-size orders are given, they should accordingly enhance their capacity and ensure that the products are delivered on time with the quality expected by us or in turn our end customers.
- The company expects to know which shipyard is getting the chunk of these orders by the end of this financial year. Replaced by a later filing.
Show source
So, by the end of this financial year, we would be clear as to which shipyard is getting the chunk of these orders.
- The company expects about one-fourth of the chunk on a very conservative basis. Replaced by a later filing.
Show source
So, in this, on a very, very conservative basis, we expect about one-fourth of the chunk.
- All these contracts are expected to be concluded during the next financial year. Replaced by a later filing.
Show source
But all these contracts are expected to get Page 14 of 22 concluded during the next financial year.
Orders
- The company received an order from the West Bengal tourism department for 200 passenger electric ferries.
Show source
We also won an order from the West Bengal tourism department for 200 passenger electric ferries.
- Order book stood at ₹12,977.93 crores as on 30th September, and its current order book value with the Next Generation Corvette contract is about ₹44,846 crores.
Show source
Now coming to the order book, as on 30th September, our order book stood at ₹12,977.93 crores and with the Next Generation Corvette contract, the current order book value is about ₹44,846 crores.
- As of 30th September, Shipbuilding accounted for about 96% of Garden Reach Shipbuilders & Engineers Limited's orders, with the defence segment contributing 70% and the non-defence segment contributing about 29%.
Show source
When I am taking the order book position as of 30th September, Shipbuilding continues to provide about 96% of our orders with the defence segment contributing 70% and the non- defence segment contributing about 29%.
- As of 30th September, Garden Reach Shipbuilders & Engineers Limited's order book comprised 13 projects consisting of 50 platforms.
Show source
This order book comprises of 13 Page 3 of 22 projects consisting of 50 platforms.
- Order book includes two export projects: 12 Multipurpose vessels for a German client and one 1000 cubic meter Trailing hopper suction dredger for the Government of Bangladesh.
Show source
Two export projects, one for a German client, 12 Multipurpose vessels and one 1000 cubic meter Trailing hopper suction dredger for the Government of Bangladesh.
- The company is the L2 shipyard in the 11-ship Next Generation Offshore Patrol Vessel project and has been mandated to construct four vessels.
Show source
This is actually an 11 -ship project of which as the L2 shipyard, we have been mandated to cons truct four vessels.
- The company said the orders and RFPs currently closed and live in the warship building segment alone come to about ₹1,72,000 crores approximately.
Show source
So I have touched upon the financial performance of the company during the last quarter as well as the H1 current financial year, given you a glimpse of operational performance of the company during this period, touched upon the current order book position and also the status of the ongoing projects and their execution plan, given you a glimpse of what we appreciate are the opportunities available in the warship building segment because I have not touched upon anything on the commercial ship building front, on the warship building segment, which itself the orders, the RFPs currently closed and live put together alone comes to about ₹1,72,000 crores approximately.
- For a Garden Reach Shipbuilders & Engineers Limited project, base and depot spares amount to about 15% of the project cost maximum and are expected to sustain the ship after delivery; the base and depot spare outstanding in the P -17 Alpha project is about ₹1,700 crores as on date, and Garden Reach Shipbuilders & Engineers Limited will be completing the project this year.
Show source
But the ba se and depot spare outstanding in this project as on date is to the tune of about ₹1,700 crores.
- When Garden Reach Shipbuilders & Engineers Limited completes the Anti - Submarine Shallow Water Craft project, about ₹465 crore will remain, and ₹427 crores will remain for NGOPV; these amounts are about 15% of the base order value, and the company expects to deliver the base and depot spares within a year of project completion.
Show source
Similarly, the Anti - Submarine Shallow Water Craft, when we complete the project, we will still have about ₹465 crore, NGOPV ₹427 crores, and so on.
- For Garden Reach Shipbuilders & Engineers Limited projects, about 10% -12% of the project cost will still remain for execution for about a period of one year after project delivery; some spares, about 5%, may be delivered before project completion, while the balance 10% would remain after completion.
Show source
So, on an average, about 10% -12% of the project cost will still remain for execution for about a period of one year.
- The company will bid to win the P-17 Bravo project, drawing on its experience executing and completing the P-17 Alpha project successfully; in the best-case scenario GRSE would be the L1 shipyard for an order value of plus 40,000 crores, while in the worst-case scenario it could be the L2 shipyard.
Show source
The P-17 Bravo order, the best-case scenario is GRSE being the L1 shipyard where the order value would be definitely plus 40,000 crores, and the worst-case scenario, okay, it could be the L2 shipyard, but as a strategy, we will be bidding to win this project, considering experience of currently executing and completing the P-17 Alpha project successfully.
- The LPD is worth ₹33,000 crores and the MCMV is worth ₹44,000 crores.
Show source
Now, we also have two more projects in addition to P-17 Bravo, two very high-value projects, one LPD of ₹33,000 crores and the MCMV worth ₹44,000 crores.
- During the calendar year, the Navy has already closed bids for about ₹25,000 crores and RFPs are out for about ₹1,47,000 crores.
Show source
So, during the calendar year, if I had mentioned 70,000, Navy has already closed the bids for about ₹25,000 crores and about ₹1,47,000 crores worth RFPs are out.
- The seven or eight projects have a combined value of about ₹1,72,000 crores, give or take ₹ 5,000 crores, up or down, depending upon the bidding pattern.
Show source
And so, both put together, what I've just mentioned, the seven or eight projects, the value is to the tune of about ₹1,72,000 crores, give or take ₹ 5,000 crores, up or down, depending upon the bidding pattern.
- Of the 50 platforms Garden Reach Shipbuilders & Engineers Limited is executing, about 13 plus to 15 are very small business.
Show source
Of course, it is also a fact that within this 50, there are about 13 plus to 15, very, very small business.
- The company signed a contract valued at approximately ₹32,000 crore for the construction of five Next Generation Corvettes (NGCs); GRSE had emerged as the lowest bidder (L1) for the project.
Show source
In addition, the much-awaited order for the Next Generation Corvettes (NGC) was received and the contract was signed on 2nd of November and the order value of this particular contract is to the tune of plus ₹32,000 crores.
- The P-17 Bravo project is a seven-ship follow-on to the P-17 Alpha projects, with an approximate order value of around ₹70,000 crores; the L1 shipyard could get four ships and the L2 shipyard three ships, and Garden Reach Shipbuilders & Engineers Limited intended to bid with the aim of winning.
Show source
The P-17 Bravo project where the AoN value by the Defence Acquisition Council is to the tune of about ₹70,000 crores.
- Next Generation Offshore Patrol Vessel project has four ships.
Show source
There are four ships in this project.
- The company has delivered five of its eight Anti-Submarine Shallow Water Craft ships and says the six ships will be delivered within a week from today; the project is almost one year ahead of the contractual delivery schedule.
Show source
Page 17 of 22 And in this project, we are almost one year ahead of the contractual delivery schedule.
- Garden Reach Shipbuilders and Engineers Ltd. received notification awards from Oil and Natural Gas Corporation (ONGC) to construct four Platform Support Vessels and from Syama Prasad Mookerjee Port, Kolkata, for a fully electric tug.
Show source
One fully electric Tug for the Syama Prasad Mookerjee Port and four Platform Supply Vessels for ONGC.
What it is building and selling
Projects and capacity
- Anti-Submarine shallow water craft project is an eight-ship project, and five vessels have been delivered, including the fifth vessel on 5th of November.
Show source
Five of these vessels have been delivered.
- In Garden Reach Shipbuilders & Engineers Limited's Anti-Submarine shallow water craft project, the sixth vessel has reached about 99% physical progress, the seventh vessel is about 75% complete, and the eighth vessel has achieved about 63% of physical progress; the company intends to complete the project during the first half of the calendar year 2027.
Show source
The sixth vessel has touched about 99% physical progress.
- Ocean Research Vessel project for the Ministry of Earth Sciences has reached about 55% physical progress, and the ship is planned for delivery during end 2027.
Show source
We have touched about 55% of the physical progress and the ship is planned to be delivered during end 2027.
- Acoustic Research ship delivery is planned during the first half of calendar year 2028, and the vessel is almost at 40% physical progress of construction.
Show source
And here we are almost at 40% physical progress of construction.
- Coastal Research Vessel project has completed keel laying for both platforms, and the project is expected to be completed by financial year '29.
Show source
The keel laying of both the platforms has already been completed and the delivery of this vessel is planned by; this project is expected to be completed by financial year '29.
- The company has completed the technical launch of the first Coastal Research Vessel and intends to launch it during mid-2027 calendar year.
Show source
Technical launch of the first vessel has been completed and we intend launching this vessel during mid-2027 calendar year.
Show 36 more statements
Projects and capacity
- The company has laid the keel of five of the 13 ferries for the transport department of the Government of West Bengal.
Show source
And keel of five of these vessels have already been laid.
- Of the 13 ferries for the transport department of the Government of West Bengal, two 100-passenger ferries have crossed 90% physical progress of construction, and Garden Reach Shipbuilders & Engineers Limited intends to deliver them within a month or so.
Show source
The 100-passenger ferries, two of these vessels have crossed 90% physical progress of construction and we intend delivering these vessels within a month or so, the first two vessels.
- Project for the transport department of the Government of West Bengal is expected to be completed during the first half of calendar year 2027.
Show source
And the project is expected to be completed during the first half of calendar year 2027.
- Bangladesh dredger has been launched and final outfitting leading towards trials and acceptance has commenced; the company intends to deliver the vessel by April 2027.
Show source
The Page 5 of 22 Bangladesh dredger has already been launched and the final outfitting leading towards trials and acceptance has already commenced and we intend delivering this vessel by April 2027.
- The company has commenced rejuvenation of two facilities in Kolkata taken over from Syama Prasad Mookerjee port on a strategic, long-term lease; the Timber Pond expansion would cost approximately ₹100 crores and has a 130-metre dry dock and 120-metre slipway, while the Howrah facility has an investment of about ₹70 crores and would cater for medium and small-size vessels, mostly tugs and ferries.
Show source
And the first project, one in Timber Pond, that is what we call the place, the expansion would cost approximately ₹100 crores.
- Raichak project would cost about ₹2,900 crores and include a 200-meter dry dock with associated slipways and ship launch pads, able to cater for commercial ships of about 60,000 DWT.
Show source
The project cost is about ₹2,900 crores.
- The company expects the Raichak project and its plant on the west coast to take about 3.5 to 4 years for completion.
Show source
Both the major projects that is the Raichak project and the plant what we have in the west coast are expected to take about 3.5 to 4 years for completion.
- For a small project like the Interceptor Boat or the water jet FAC, there is no pre-production time and the execution clock starts straight; for a large project like P-17 Bravo, LPD or MCMV, pre-production takes one and a half years, two years.
Show source
Whereas in case of a large project like P -17 Bravo, LPD or MCMV, there's a pre-production time of one and a half years, two years.
- Concurrent-construction capacity is 28 ships today and will be 32 by next month end; this capacity includes ships in pre-launch and post-launch phases.
Show source
The capacity of 32, today 28 but by next month end 32 would comprise of ships which are in pre-launch phase and post- launch phase.
- The company has about 16 large-size and small-size dry docks, slipways, building berths and ship launch pads.
Show source
So, we have about 16 of them currently with us, a large size and small size.
- The company is undertaking a World Bank funding Hybrid Vessel project for the Government of West Bengal comprising 13 vessels: seven 100 pax passengers and 6 200 pax passengers; delivery shall commence from early 2026 and project completion is scheduled by 2027.
Show source
13 ferries, seven 100-passenger ferries and six 200-passenger ferries.
- Current shipbuilding capacity is for construction of 28 platforms.
Show source
Now, coming to our shipbuilding capacity and the expansion plan, as I have stated multiple times during the previous interactions, our current shipbuilding capacity facilitates the concurrent construction of 28 platforms and within a month, that is next month, with some of the ongoing ex pansion revitalization plans getting completed, this capacity will move up to concurrent construction of 32 platforms.
- Next Generation Corvette project is about nine years long.
Show source
It's about nine years project.
- Pre-production activities for Garden Reach Shipbuilders & Engineers Limited's Next Generation Corvette project, including design and procurement activities, have commenced.
Show source
As of now, the pre-production activities, that is the design activities as well as the procurement activities have already commenced.
- Pre-production activities for Garden Reach Shipbuilders & Engineers Limited's four platform supply vessels, including design preparation and equipment procurement, have commenced.
Show source
Similarly, for the platform supply vessels also, the pre-production activities have already commenced by way of design preparation and equipment procurement.
- Pre-production activities have commenced for Garden Reach Shipbuilders & Engineers Limited's fully electric tug ordered by the Syama Prasad Mookerjee Port Authority.
Show source
Similarly, the fully electric tug that has been ordered by the Syama Prasad Mookerjee Port Authority, the pre-production activities have commenced.
- The company is planning expansion on the west coast, with the DPR and associated partnership-related activities in progress.
Show source
In addition, we are also planning expansion on the west coast; the DPR and associated partnership-related activities are in progress.
- The company expects its two independent projects, one on the west coast and one on the east coast, to be completed in about three and a half to four years; both have board approval and are not part of the shipbuilding clusters.
Show source
They are independent projects and we expect these two, you could also ask by when they are expected to get completed, we expect them to be completed in about three and a half to four years.
- Shipbuilding clusters are planned in one or two locations in Gujarat, Maharashtra, Odissa, Andhra Pradesh and Tamil Nadu.
Show source
And as of now, there are shipbuilding clusters which are planned in Gujarat, one or two locations, Maharashtra, Odissa, and Andhra Pradesh and Tamil Nadu.
- Pre-production activities are in progress for Garden Reach Shipbuilders & Engineers Limited's project awarded by the Tourism Department. Replaced by a later filing.
Show source
Coming to the new project that was awarded by the Tourism Department, the pre-production activities are in progress.
Segments
- In Garden Reach Shipbuilders & Engineers Limited’s warship production cycle, maximum revenue recognition typically occurs when physical progress of construction is between 40% and 65%.
Show source
So, typically, in a warship production cycle, the maximum revenue recognition occurs when the physical progress of construction hovers between 40% -65%.
- Nearly 70% of Garden Reach Shipbuilders & Engineers Limited's procurement is from MSMEs.
Show source
You know, interestingly, nearly 70% of our procurement is from MSMEs, one of the highest in the segment.
- Commercial ships for export have about 40% to 45% indigenous content; the company says this content consists of yard material, including steel and outfit items procured from the local market, mostly from its industry.
Show source
Here, the indigenization content is about 40% to 45%.
- The company says indigenization for its commercial ships or non-defense platforms is limited to 60% to 65% because some projects are first ships and a few sensitive electronic equipment items will come from abroad.
Show source
For commercial ships or non -defense platforms that are getting constructed by us, the indigenization percent age could go up to about 60% to 65%.
- The three projects Garden Reach Shipbuilders & Engineers Limited completed in the last 5 years had indigenous content of plus 85%.
Show source
In the last three projects that we have completed, I am speaking about the warship building project.
- The company has commenced using Robotics in its manufacturing processes, initially in portable steel bridges, where series production is effectively using Robotics.
Show source
And we started in a reasonably modest fashion, where our Robotics was used for one of the business verticals, that is the portable steel bridges, where we have series production and effectively being utilized.
- The company has adopted collaborative robots, or Cobots, for shipbuilding that can operate on curved surfaces.
Show source
So, what we have done is we have gone ahead and adopted in line with some of the global shipyards where they use Cobots, the collaborative robots for shipbuilding purposes, where they can operate even during curved surfaces.
- The company has enhanced its use of Robotics in shipbuilding and bailey bridge fabrication within Optimus.
Show source
We are using it and we have already enhanced the usage of Robotics Page 15 of 22 in shipbuilding and of course the bailey bridge fabrication within Optimus.
- The company is a platform integrator, and the customer defines the equipment and provides specifications for systems and materials such as bull bars, composite doors and hatches.
Show source
The customer has defined the equipment.
Deals and partners
- The company won two projects for the Government of West Bengal to construct 13 Advanced Hybrid Ferry.
Show source
Two Hybrid Ferry projects, 13 Ferries, both the projects are for the Government of West Bengal, one for their transport department for 13 hybrid ferries and the second order that we recently received for two ferries for their tourism department.
- The company has successfully implemented a partnership model over the last five to six years, doing design and, in some projects, procurement, project management and quality assurance with capable shipyards; examples include the Survey Vessel Large project, anti-submarine water crafts and the foreign order from Guyana for an ocean going ferry.
Show source
So, this concept and this practice have already been successfully implemented by GRSE over the last five to six years.
- Services vendors for block fabrication, erection and outfitting are MSMEs, and the company says they have clear order book visibility.
Show source
There's clear order book visibility for them.
- The company has concluded three-to-five-year contracts to provide long-term visibility to its vendors.
Show source
We have concluded the right contracts for long-term, three to five-year contracts have been concluded.
- The company established rate contracts to aggregate demand and provide MSMEs long-term visibility instead of placing piecemeal orders, in line with ministry directions.
Show source
In line with the directions of my ministry, what we have done is to aggregate the demands and to provide long-term visibility to the MSMEs instead of giving piecemeal orders, we established rate contracts.
- For Garden Reach Shipbuilders & Engineers Limited's commercial ship order for a European client, the client specifies equipment from a particular country and vendor, and the company is bound by those contractual stipulations.
Show source
So, we are bound by those contractual stipulations.
- Demand aggregation across four shipyards is being undertaken through a process steered by the ministry, with results expected in the coming years. Replaced by a later filing.
Show source
To the extent that my ministry is steering a process where demand aggregation of the shipyards, four of us, is also being undertaken, the results will be seen in Page 19 of 22 the coming years.
Risks, rules and outside factors
Rules and policy
- Expansion plans are based on the Government of India’s Shipbuilding Revitalization Plan, which is to the tune of about ₹69,000 crores and comprises the Shipbuilding Development Scheme, Shipbuilding Financial Assistance, Interest Incentivization Policy, and Shipbreaking Credit Note.
Show source
And these expansion plans are also based on the various schemes initiated and promulg ated by the Government of India by way of the Shipbuilding Revitalization Plan, which as you are aware is to the tune of about ₹69,000 crores.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Amit Dixit: Yeah. Hi. Good evening, everyone, and thanks for the opportunity. First of all, congratulations for a good set of numbers and securing a Next -Generation Corvette order. It is indeed a very prestigious order for the company. So, two questions from my side. The first one is on NGC itself. While you have indicated that the pre-production activity will commence, just wanted to get a sense that in this nine-year period, when we are going to deliver the first vessel, and also when the revenue recognition will start for this particular project. Page 8 of 22 Commodore P. R. Hari: Thank you.
Answer, commodore hari
If you could ask your second question also, I will answer both together.
Question
Amit Dixit: Yeah, of course. The second question is essentially, if I look at the delivery schedule that you have highlighted in an elaborate manner, what I see that FY28 would be the time when the current order book, barring NGC, would be nearly exhausted. Are we going to see a phase, let us say, FY29, maybe 2030 or half of 2030, which could be a little bit lean on revenue, but rich on order book, as you are expecting several orders to be awarded, I mean, in the course of, let us say, 12, 15 months?
Answer, commodore hari
Commodore P. R. Hari: Thank you, Mr. Amit. Interesting questions. One, yes, we were waiting for the NGC order. As per the contractual, for a long time, and we are happy that finally it is fructified. As per the contractual timelines, the first vessel is expected to be delivered during mid, rather, the latter half of calendar year 2032. That is when the first vessel is expected to be delivered, and then on till 2035, 2036, where the fifth vessel will be delivered. Now, you had asked about when will the revenue start flowing in from this project.
Answer, commodore hari
In shipbuilding, as you are aware, the shipbuilding cycle forms a very peculiar revenue recognition pattern, unlike several other industries, where the first phase of a project is mostly dedicated to the preparatory activities by way of design as well as procurement. Then comes the hull fabrication with certain limited outfitting, and thereafter comes the phase where maximum equipment and systems are lowered, and then the phase of the outfitting and integration of this equipment and systems leading to trials and activities. So, typically, in a warship production cycle, the maximum revenue recognition occurs when the physical progress of construction hovers between 40% -65%. Now, this I have given a broader perspective. Now, to answer your specific question, as part of the design activities and certain information that we obtained from the major OEMs, there are imperatives to finalize the design of the ship. So, this quantum could be to the tune of about 7.5%-8% of the project cost. So, revenue recognition, of course, in a moderate way, would commence from financial year '28.
Answer, commodore hari
Page 9 of 22 Now, coming to your second question, I had given you a very detailed input on the execution plan of the ongoing projects. Yes, two projects, that is the P - 17 Alpha project would get completed this financial year, actually this particular for the ongoing quarter. The Anti-Submarine Shallow Water Craft will spill over to the first quarter of the next financial year, that is FY '28. The NGOPV project will get completed only by financial year '29. The other miscellaneous project, the research vessel project will get completed by FY28 and '29. Definitely, the multipurpose vessels export project will, and the platform supply vessels will move on to FY29. We expect by FY29, the revenue contribution from the NGC would pick up substantially.
Answer, commodore hari
Yes, this is a very natural process. There will be a trough, and our peak years, as I have been reiterating in multiple interactive sessions that we had before, are FY26 and '27. This is where we stand as of date.
Question
Dipen Vakil: Hi, sir. Thank you so much for this opportunity, and congratulations on winning the prestigious NGC contract. My first question is that I want to understand about the revenue recognition which can occur during the pre - production phase and designing phase, if any. Also, when we look at t he execution, what kind of order book is still pending post all the deliveries of a particular project are complete? Is it any ballpark number in terms of percentage as to how do we look into it? That would be my first question, sir.
Answer, commodore hari
Commodore P. R. Hari: Okay. Now, coming to the revenue contribution from the revenue recognition from the NGC project during the pre-production phase that mostly comprises of design activities and the procurement-related activities. Here, on a conservative basis, we expect about 7.5% of the order value. If you want more details of the outstanding order, I didn't get your second question. Outstanding orders, order value of each of the projects? Is that what you want to? Page 10 of 22 Dipen Vakil: That was my second question, but right now I was asking that once we deliver all the vessels, is there any order book which is still pending on your side, maybe for spares or any warranties or anything, that sort of, and what is the timeline for finishing up on those orders?
Question
That was my question.
Answer, commodore hari
Commodore P. R. Hari: Okay. That's a good question. Yes. Whenever any project is awarded to us, one, the basic value of the project is there, and certain spares, these are called base and depot spares, which works out to about 15% of the project cost maximum, are earmarked for the base and depot spares, which are expected to sustain the ship thereafter once the ship is delivered. As I mentioned, this is about 15% of the project cost. For example, we will be completing the P -17 Alpha project this year. But the ba se and depot spare outstanding in this project as on date is to the tune of about ₹1,700 crores.
Answer, commodore hari
Similarly, the Anti - Submarine Shallow Water Craft, when we complete the project, we will still have about ₹465 crore, NGOPV ₹427 crores, and so on. This works out to about 15% of the base order value. And within a year of completion of the project, we are expected to deliver these base and depot spares. I think we both are thinking about the same thing, that even after project delivery is completed, there would still be a year where this 10% -15%, because some of these spares, about 5% we may have delivered before the project is completed. The balance 10% would be remaining even after the project gets completed. So, on an average, about 10% -12% of the project cost will still remain for execution for about a period of one year. Does that answer your question?
Question
Dipen Vakil: Sir, a last small question. Since NGC was more like a competitive bidding contract, so are the margins similar to what you have been doing or slightly better, or how are the margin profiles for NGC contracts?
Answer, commodore hari
Commodore P. R. Hari: We started getting into the competition mode almost six years back, starting with the survey vessels and the Anti-Submarine Shallow Water Craft and the NGOPV project, which we won. And now the NGC. Yes, NGC has not been a nomination project, but all I can say is that the margins are adequate and akin to the Anti-Submarine Shallow Water Craft project, which is a profitable project.
Question
Milind Samit: Sir, thank you so much for taking my question. The current order book as of last quarter was to the tune of ₹13,000 crores, if I recall rightly. Now, would that be enough to take us to FY28 with the same momentum as the company has shown in the last few years? You have already guided us for FY29, where you were saying that 7% of the NGC order would slow in that year. So, do you just want to do a guidance on FY28 about the comfort we can get for this continuation of the growth?
Answer, commodore hari
Commodore P. R. Hari: Thank you. The last few years, you have seen the re venue going almost exponentially at CAGR of about 20% to 25%. During this period, the projects Page 12 of 22 that we had, the P-17 Alpha, any of the projects, the P-17 Alpha, the ASW Shallow Water Craft, they were in and are in their peak execution phase. Now, the P-17 Alpha project is closing this year. The Anti-Submarine Shallow Water Craft project will close during the first half of the next current year, perhaps during the first quarter of the next financial year. But we will still have the NGOPV project, which will peak as far as its revenue recognition is concerned during the next financial year. Again, I would like to repeat that we have just started the Next-Generation Corvette high-value project, the first phase, which will be to the tune of about a year and a half from now, which means in the next financial year, we should be able to recognize about 7.5%.
Answer, commodore hari
That is next financial year, not next financial year. Next financial year, we should be able to recognize about 7.5% of project costs. And we also have projects which are maturing, which are picking up now, but will get fully blown with respect to their growth during the next financial year, that is the Ocean Research Vessel, the Acoustic Research Ship, and the Multi-Purpose Vessel project for the German client. So, we expect the tempo with respect to project execution to continue in the next financial year also.
Question
Milind Samit: Sir, my second question is that after the recent NGC order, the next order, which would be of the same magnitude, would be P-17 Bravo orders. Now, how long do you think would that order take to fructify in terms of firmness of the orders from the points?
Answer, commodore hari
Commodore P. R. Hari: Okay, I understood your question. I would like to answer it in a slightly different fashion. I had mentioned that while the high-value order, what we are looking forward would be definitely the P-17 Bravo. So, I will first cover P- 17 Bravo and then touch upon the other projects which are where the RFPs are in progress on outsourcing level. You can look at it from an overall perspective. The P-17 Bravo order, the best-case scenario is GRSE being the L1 shipyard where the order value would be definitely plus 40,000 crores, and the worst-case scenario, okay, it could be the L2 shipyard, but as a strategy, we will be bidding to win this project, considering experience of currently executing and completing the P-17 Alpha project successfully. Now, the bid is closing in a week.
Answer, commodore hari
So, we expect the L1 declaration in another four months, Page 13 of 22 that is, during the current financial year, definitely in line with the past precedents and the current focus which Navy and the Government is providing for the shipbuilding project conversion from RFP to order. So, we expect during the current financial year, the L1 declaration and keeping a very conservative timeline of one year. Worst case, we expect the contract to be concluded during the next financial year, towards the fourth quarter of the next financial year. This is the high-value project which is currently immediately on as far as we are concern. Second, I'd also mention that about ₹ 25,000 crores worth orders, the RFP, the bids are already closed, and we expect the bid results to be announced in the next few months, starting with the interceptor boats, the water jet FACs and the OPVs. So, in this, on a very, very conservative basis, we expect about one-fourth of the chunk. That is a very, very conservative basis.
Answer, commodore hari
Now, we also have two more projects in addition to P-17 Bravo, two very high-value projects, one LPD of ₹33,000 crores and the MCMV worth ₹44,000 crores. So, this is the kind of orders that are clearly visible in defence segment alone. Now, to answer your, going back to your specific question, P-17 Bravo, the L1 declaration expected during the current financial year and the contract conclusion by the end of next financial year, most likely during Q4 FY28. Thank you.
Question
Saksham Tyagi: So, my first question is that, sir, in the previous concall, you mentioned that orders worth ₹70,000 crores were expected to be published during this calendar year. So, what's the progress on that? And also, when can we expect the execution of these orders to start?
Answer, commodore hari
Commodore P. R. Hari: Yes, I mentioned, now I realized I must have been perhaps too conservative. So, during the calendar year, if I had mentioned 70,000, Navy has already closed the bids for about ₹25,000 crores and about ₹1,47,000 crores worth RFPs are out. Now, before coming to execution, I would rather talk about when they are going to fructify. But all these contracts are expected to get Page 14 of 22 concluded during the next financial year. And then comes the execution stage, which, depending upon the size of the project, in case of a small project like Interceptor Boat or the water jet FAC, there is no pre-production time, the clock starts straight. Whereas in case of a large project like P -17 Bravo, LPD or MCMV, there's a pre-production time of one and a half years, two years. Thereafter, the actual execution would come in.
Answer, commodore hari
And so, both put together, what I've just mentioned, the seven or eight projects, the value is to the tune of about ₹1,72,000 crores, give or take ₹ 5,000 crores, up or down, depending upon the bidding pattern. And that is a substantial amount tha t is available for the Indian shipyards. And in this, our focus definitely would be on the Water Jet FACs, the interceptor boats and the P-17 Bravo ships.
Question
Saksham Tyagi: And sir, earlier you mentioned that you are focusing on maximizing the use of Robotics in your production process. So, what's the progress in that? And also, what kind of transformation can we expect in our production process due to this technology adoption?
Answer, commodore hari
Commodore P. R. Hari: Yes, very interesting question. And we have commenced the usa ge of Robotics in our manufacturing processes. And we started in a reasonably modest fashion, where our Robotics was used for one of the business verticals, that is the portable steel bridges, where we have series production and effectively being utilized. And I've seen the production throughput. We have procured more machines for bailey bridges as well as for shipbuilding. And we see the production throughput to increase substantially. Here, one point to note is that in case of shipbuilding, unlike other manufacturing processes, even one of our business verticals like bailey bridge, the surface of a ship often does not permit steady use of Robotics, except when we are fabricating panels or straight panels where state building is involved.
Answer, commodore hari
So, what we have done is we have gone ahead and adopted in line with some of the global shipyards where they use Cobots, the collaborative robots for shipbuilding purposes, where they can operate even during curved surfaces. So, to put it in a nutshell, yes, we are pleased of the necessity to adopt Robotics. We are using it and we have already enhanced the usage of Robotics Page 15 of 22 in shipbuilding and of course the bailey bridge fabrication within Optimus. Thank you.
Question
Sunil Shah: Yes, sir. Thanks. Thanks for the opportunity. Congratulations for the great service to the nation in terms of P-17 Alpha project. Thanks so much, sir. Sir, just to get some better understanding, when we say it is 32 platforms that we have, does it mean that we can construct 32 ships simultaneously or it means that the hull is constructed and the ship is launched and the work happens there and then at the same time we can still construct more ships? That is my first point to understand from you, sir.
Answer, commodore hari
Commodore P. R. Hari: Yes. Very, very interesting question. Okay, shipbuilding capacity is defined based on the assets required for infrastructure, required for ship production. These include dry docks. These include the building berths. These include the ship base or ship launch pads and also the jetties where the ships are berthed post their launch from the dry docks. So, when we say 32 ships concurrent construction means, there could be a situation where a ship is in dry dock, a ship could be in dry berth, it could be on a launch pad or it could be alongside in a jetty.
Answer, commodore hari
So, you are right. The capacity of 32, today 28 but by next month end 32 would comprise of ships which are in pre-launch phase and post- launch phase. All put together it is 32. And again, since you mentioned this topic, today I am happy to inform you that we have in India the largest number of dry docks, slipways, building berths and ship launch pads in among all the Indian shipyards. So, we have about 16 of them currently with us, a large size and small size. So, all put together and the associated jetties, the capacity is for concurrent construction including that is pre -launch and post- launch put together 32 ships, 28 today and by end of this year 32. Does that answer your question?
Show 5 more questions
Question
Sunil Shah: Yes, sir. And just to follow up for a better understanding, so now finally we have got this Next-Generation Corvette order 5 in number and we are poised for the P-17 Bravo as well. So, maybe 3 years down the line, we will have Page 16 of 22 perhaps a stage of concurrent construction of 5 of these and probably 4 of P - 17 Bravo as well in our books, let us say 3 years down the line, something like that. Would it be a possibility or we will have to make some Next-Generation Corvettes and deliver them and then start with the new ones, how would that work? Meaning a peak revenue kind of a number or a possibility on that, how would that work out?
Answer, commodore hari
Commodore P. R. Hari: Even as on date, before we come to 17 Bravo or any other project that would come along the way, even as on date, we are executing 13 projects comprising of 50 platforms. Of course, it is also a fact that within this 50, there are about 13 plus to 15, very, very small business. What we have adopted and adopted successfully as a strategy is a partnership model where we do the design and in some projects we do the procurement, we do the project management including the quality assurance where we partner capable shipyards with the competency and proven capability in building similar vessels and this model has been successfully executed for a couple of projects of ours, be it the survey vessel large project where we have partly outsourced construction of ships, the anti-submarine water crafts or the foreign order from Guyana where we built an ocean going ferry. So, this concept and this practice have already been successfully implemented by GRSE over the last five to six years. This is a strategy that we intend to continue because we would not like to miss any order for want of capacity. So, this is a strategy. To meet this strategy, we will be resorting to PPP model or even a partnership with another capable public sector shipyard.
Answer, commodore hari
These options are available. So, again, to just get back to your question, concurrent construction of P-17 Bravo, when it comes, I would not even use the term if it comes, when it comes and the NGC project would be handled by us in a manner which will not impact the customer expectations or rather will ensure concurrent construction. I will just give you an example. There is a project, it is a 16-ship project for eight anti-submarine shallow water crafts to be built by two Indian shipyards. We were actually the L2 shipyard when this bid was opened and eight ships by us and eight sh ips by another shipyard. So, in this project, we adopted a PPP model and I am happy to inform you that five of the eight ships we have already delivered and the six ships will be delivered within a week from today. Page 17 of 22 And in this project, we are almost one year ahead of the contractual delivery schedule.
Answer, commodore hari
So, these advantages which we have learned over a period of time and this strategy will be crystallized and implemented to ensure that we have capacity to take on big orders that come along the way from our ma jor customers, that is the Navy or the Coast Guard. Thank you.
Question
Sunil Shah: Sir, if I can just take one question in. Sir, it is about the cluster development, which is what the government's big ambition program is. And I believe you mentioned during the opening remarks something like Rs. 2,900 crores of investment. Was it referring to the developments in the western region? If you could make some more understanding about how would that pan out in terms of time, you mentioned three years, but in terms of capacities, etc., that would be really helpful.
Answer, commodore hari
Commodore P. R. Hari: Okay. I touched upon during my introductory talks that government has come out with a clear shipbuilding revitalization policy and one of them is shipbuilding clusters. And as of now, there are shipbuilding clusters which are planned in Gujarat, one or two locations, Maharashtra, Odissa, and Andhra Pradesh and Tamil Nadu. The projects what I have mentioned, one on the west coast and one on the east coast, where already board approval has been given, both these projects are not a part of the shipbuilding clusters. They are independent projects and we expect these two, you could also ask by when they are expected to get completed, we expect them to be completed in about three and a half to four years. Thank you.
Question
Shivam Parekh: Yeah. Hi, sir. Thanks for the opportunity. So, my first question is like orders are getting passed for the shipbuilding ancillaries with respect to bull bars, HVAC systems, composite doors, etc., as far as the comments from these managements are concerned. So, as you said in your recent remarks, we have Page 18 of 22 P-17 Bravo, LPD, NextGen Destroyers, etc., coming up. So, now with the Indian shipbuilding industry quite at a mature stage, how we are shaping up to fast-track our deliveries and what are we doing so that the MSME industries that cater to us feel safe in terms of potential revenue to build new facilities and do new investments? This was the first question. And se
Answer, commodore hari
Commodore P. R. Hari: Thank you. You know, interestingly, nearly 70% of our procurement is from MSMEs, one of the highest in the segment. Now, you're absolutely right that there will be a huge demand because we rely on MSMEs for products or for services. Most of our services vendors, be it for block fabrication, be it for erection, be it for outfitting, they're all MSMEs. Here, very, very clear order visibility is there for them. I'll come back to the production MSMEs, but first I'll just touch upon the services MSMEs. There's clear order book visibility for them.
Answer, commodore hari
We have concluded the right contracts for long-term, three to five-year contracts have been concluded. So, there is visibility. Now, coming back to what you mentioned, you touched upon opportunities where firms who manufacture bull bars, composite materials, door hatches, and so on. We are platform integrators. As shipyards, we are platform integrators. The customer has defined the equipment. They have given the specifications of the systems, the material, like for example, bull bars or composite doors or hatches.
Answer, commodore hari
The specifications are given by the customer. Now, what we have done is we have realized this bottleneck or the problem which the MSMEs are facing. In line with the directions of my ministry, what we have done is to aggregate the demands and to provide long-term visibility to the MSMEs instead of giving piecemeal orders, we established rate contracts. So, this is one initiative that we have taken to ensure that the MSMEs have clear order visibility. To the extent that my ministry is steering a process where demand aggregation of the shipyards, four of us, is also being undertaken, the results will be seen in Page 19 of 22 the coming years. So, we are pleased of the issue. Now, having said that, what the MSMEs in turn would need to do is to ensure that if long-term visibility and large-size orders are given, they should accordingly enhance their capacity and ensure that the products are delivered on time with the quality expected by us or in turn our end customers.
Answer, commodore hari
Thank you. In a nutshell, we are pleased of this. Initiatives have already been taken in terms of long-term rate contracts and further consolidation will happen and the results will be seen in the coming months and years. Thank you.
Question
Dipen Vakil: Thank you for the follow-up opportunity, sir. So, I wanted to understand a little bit about the indigenization. Since you mentioned that 70% is appropriate for MSMEs, I wanted to understand the kind of indigenization levels that we have been able to achieve. One is into warships and second is into the commercial orders that we have mainly the export orders and even some domestic orders as well. How would the indigenization have been able to improve the export content on it?
Answer, commodore hari
Commodore P. R. Hari: Okay. Indigenization, as you are fully aware, that is the focus area of our Government. In the last three projects that we have completed, I am speaking about the warship building project. Last three projects that we have completed, we have touched about 85% indigenous content. Coming to the commercial ships, here the situation is slightly different. Here, the indigenization content is about 40% to 45%. Let us take the order that we are executing.
Answer, commodore hari
We are doing it for one of the European clients and the client very clearly states that I want this equipment from this particular country, from this particular vendor. So, we are bound by those contractual stipulations. Page 20 of 22 What is left to us to make this 40% or 45% indigenous content is the yard material. Be it steel, be it the outfit items, they are all procured from the local market and most of them from our industry. Of course, steel comes from major players. So, again, to answer your questions, about 85% indigenous content on warships and about 40 % to 45% indigenous content on commercial ships for export. For commercial ships or non -defense platforms that are getting constructed by us, the indigenization percent age could go up to about 60% to 65%.
Answer, commodore hari
Why 60 % to 65% only is because some of the projects that we are executing are the first ships where a few sensitive electronic equipment will come from abroad. Does that answer your question?
Question
Dipen Vakil: Thank you. Got it, sir. That's all. Thank you so much, sir.
Answer, commodore hari
Commodore P. R. Hari: Thank you. It has been an interesting session and I thank all the participants for taking your time off and attending today's conference. And I also wish you all the very best. And also, once again, thank you for showing continued interest in the company and for engaging in this insightful Q&A session. And I thank the entire concept team for facilitating this session. I conclude today's conference with this and thank you. Jai Hind.
Questions about this call
- When was the Garden Reach Shipbuilders & Engineers Q2 FY27 earnings call transcript filed?
- Garden Reach Shipbuilders & Engineers filed the transcript with the exchange on 24 Nov 2026. This page is built from that transcript.
- What does this page list?
- 93 statements from the transcript across 7 topics, 61 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 15 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.