Earnings call
Highway Infrastructure Q1 FY27 earnings call: Highway Infrastructure Limited’s consolidated order book stood at approximately INR 778 crores as of June 30, 2026
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Consolidated order book stood at approximately INR 778 crores as of June 30, 2026. The company has 24 executable projects and expects to realize approximately INR 150 crores in FY27 and INR 200 crores in FY28; the work is executable over three years. The company commenced execution of the Beverly Hills project during the quarter ended 30th June, 2026, strengthening its private sector EPC portfolio and medium-term revenue visibility. Profitability during the quarter ended 30th June, 2026 was impacted by lower traffic volumes at the Moti Naroli toll project due to geopolitical developments and global trade disruptions. EPC model uses the L1 approach, with a tender worth INR 100 crores representing revenue; the revenue component is fixed and the cost component is uncertain, while its toll segment uses the H1 (higher bid) model, requiring payments to the NHAI, with uncertain revenue, fixed cost and profitability dependent on actual collections.
The numbers management gave
Results
- Profitability during the quarter ended 30th June, 2026 was impacted by lower traffic volumes at the Moti Naroli toll project due to geopolitical developments and global trade disruptions.
Show source
During the quarter, profitability was impacted by a combination of temporary factors, including lower traffic volumes at the Moti Naroli toll project due to geopolitical developments and global trade disruptions.
- Consolidated total income for Q1 FY27 was INR 304.3 crores, representing year-on-year growth of 170.6%.
Show source
Page 3 of 14 Highway Infrastructure Limited August 18, 2026 Commenting on the financials, on a consolidated basis, total income for Q1 FY27 stood at INR 304.3 crores, representing a growth of 170.6% year-on-year.
- EBITDA for the quarter ended 30th June, 2026 was INR 4.8 crores and PAT was INR 1.1 crores.
Show source
EBITDA for the quarter was INR 4.8 crores and PAT stood at INR 1.1 crores.
- Success ratio for toll is almost 25% to 30%.
Show source
Saurabh Mittal: Success ratio for toll is almost 25% to 30%.
- Ena, Moti Naroli was almost 70% larger than Kaza toll plaza, but geopolitical strains meant it did not perform as expected.
Show source
And like we mentioned Ena, Moti Naroli was almost 70% larger contract than Kaza toll plaza.
- A temporary bidding restriction from NHAI and Highway Infrastructure Limited’s voluntary surrender of a toll project where economics had been unfavorable due to the same reason contributed to short-term impacts on profitability.
Show source
A temporary bidding restriction from NHAI and the voluntary surrender of a toll project where economics had been unfavorable due to the same reason.
Show 2 more statements
Results
- Ena, Moti Naroli toll plaza was heavily impacted in Q1 by geopolitical strain and the resulting effects on logistics and factories; the impact was localized to Q1, traffic had started to grow back and businesses had resumed normal working, and the company said the impact was absorbed in Q1, hoping there would be no new development in international politics.
Show source
The Ena, Moti Naroli toll plaza that we were operating at that particular period in Q1 was heavily impacted from these two combined factors.
- EBITDA margin recently dropped because of the geopolitical situation. Replaced by a later filing.
Show source
And even so, I think there was a drop in our EBITDA margin recently because of this geopolitical situation recently.
What it expects ahead
What management expects
- The company has 24 executable projects and expects to realize approximately INR 150 crores in FY27 and INR 200 crores in FY28; the work is executable over three years.
Show source
So, in the current year, we will realize approximately INR 150 crores in FY27 and in FY28 we will do INR 200 crores.
- The company is targeting INR 850 crores turnover for FY27, including INR 700 crores from toll and the remainder from EPC.
Show source
Saurabh Mittal: For FY27, we are targeted INR 850 crores turnover, out of which INR 700 crores we are targeting for toll and rest for remaining for EPC business.
- The company expects at least INR 150 crores of EPC revenue, contributing around 40-45% of revenue over the next 15 to 16 months.
Show source
So, this will be contributing to the ballpark of around 40-45% of the revenue in the next 15 to 16 months.
- The company says that 5–10 years down the line it will be a more technology-driven infrastructure company, supported by data collection, analysis and data crunching from people and computing.
Show source
So, going forward in the future, let's say 5 -10 years down the line, you will see that we will come out as a more technology-driven infrastructure company because that is very important.
- The company expects the current weakness not to have a significant impact on full-year results because, based on past trends, it tends to hover around break-even during the first and second quarters and see rapid recovery in the third and fourth quarters.
Show source
Saurabh Mittal: Actually, this won't have a significant impact on the full-year results because, based on past trends, we tend to hover around the break-even point during the first and second quarters, while seeing a rapid recovery in the third and fourth quarters.
- The company has started to capitalize on opportunities in the eastern part of India and is focused on Tamil Nadu, keen on Andhra Pradesh and Telangana, researching entry into West Bengal, and researching entry into Assam with a team deployed on the ground.
Show source
And going forward, we see a lot of scope in the eastern part of India also, which we have started to capitalize now Tamil Nadu, we are very focused, keen on Andhra Pradesh, Telangana.
Show 14 more statements
What management expects
- The company said its EPC pipeline accumulated in the first quarter was not final, and that its major focus in Q2 was to accumulate better tenders and actively bid for quality tenders that could be executed in the very near future without a very long execution-year span; EPC business is slower in Q2 because of the monsoon season.
Show source
So, our major focus in Q2 for EPC would be to accumulate more better tenders and active bid for quality tenders that will be executed in the very near future, with not a very longer execution year span.
- The company plans to bid independently for larger tenders as its PQ increases after completion of projects in its pipeline, and is willing to collaborate with a compatible entity to bid for larger tenders.
Show source
So, as soon as our PQ increases, we will on a sole basis we want to bid for larger tenders because then we have larger opportunity, larger margins, less competition, obviously.
- The company expects renewable energy production and transmission to be a focus in the coming years, but says it will take time to realize and requires back work before it actively bids because it would be a new segment.
Show source
Riddharth Jain: So, like I mentioned in my previous calls, definitely renewable energy production and transmission is something that will be in focus in the coming years.
- The company is selectively pursuing EPC projects that offer sensible profitability and can be completed within the stated timeline, and is looking into newer departments including central departments with larger scope of work, larger contract values, better margins and less competition; MES and CPWD are among the departments it is actively considering.
Show source
So, moving forward, the departments that we have been working on, we have deployed a newer team who is actively looking into newer departments, which may include some of departments from the center, which have larger scope of work, larger contract values, better margins, and less competition.
- The company is keen to pursue larger toll contracts, citing less competition and its extensive research into toll plazas and their risks as an edge over other bidders.
Show source
And to the second part of your question, larger toll contracts are definitely something that we are very keen on.
- The company wants to participate in larger toll contracts where possible and aims to maintain a mix of small-, mid- and large-value toll contracts because larger contracts do not necessarily produce better margins.
Show source
But our visibility, our intentions for going forward would be to create a good mix of small-value contracts, mid-value contracts, and large-value contracts because in tollways it is not obvious that larger value contracts will always give you a better margin.
- The company is trying to increase its pre-qualification; once its current contracts are executed, it expects to qualify to bid for larger contracts, where margins are better and competition is less.
Show source
And yes, definitely, we are trying to increase our PQ as soon as the contracts we have in our hand will be executed, our pre -qualification will increase.
- The company is researching Andhra Pradesh and Telangana, including development, state investment and project execution timelines to assess expected traffic growth, and is researching entry into West Bengal and Assam while awaiting the right opportunity to enter a new state.
Show source
We have been researching a lot about Andhra Pradesh, Telangana, and that entire belt, that particular road belt.
- The company says the eastern belt of India offers significant opportunities and that it would be very keen to pursue opportunities there. Replaced by a later filing.
Show source
But I can say that the eastern belt of India is something that is very opportunistic and we would be very, very keen on that front.
- The company says technology will be the next forefront for executing and managing its projects, while infrastructure will remain its core business. Replaced by a later filing.
Show source
So, it is just safe to say that technology will be the next forefront on how do we execute and manage our projects while our main core business will be infrastructure.
Orders
- Consolidated order book stood at approximately INR 778 crores as of June 30, 2026.
Show source
Our consolidated order book stood at approximately INR 778 crores as of June 30, 2026, providing a healthy visibility of future execution.
- The company secured a new tollway collection contract valued at approximately INR 28.7 crores for the Kozhinjipatti toll plaza on the Dindigul-Samayanallur stretch of the NH-44 in Tamil Nadu.
Show source
We secured a new tollway collection contract valued at approximately INR 28.7 crores for the Kozhinjipatti toll plaza on the Dindigul- Samayanallur stretch of the NH-44 in Tamil Nadu.
- The company recently secured INR 120 crores in new toll projects in Tamil Nadu.
Show source
Saurabh Mittal: Recently we secured INR 120 crores new toll projects in Tamil Nadu.
- The company has INR 900 crores of work order, of which EPC is almost INR 500 crores and the rest is for the toll segment.
Show source
And so, adding this, we have INR 900 crores of work order, out of which EPC is almost INR 500 crores and the rest for toll segment.
What it is building and selling
Projects and capacity
- The company commenced execution of the Beverly Hills project during the quarter ended 30th June, 2026, strengthening its private sector EPC portfolio and medium-term revenue visibility.
Show source
A notable milestone during this quarter was the commencement of execution of Beverly Hills project, which further strengthens our private sector EPC portfolio and medium-term revenue visibility.
- Beverly Hills project is valued at approximately INR 70 crores and is expected to be executed within this year.
Show source
Value of project is INR 70 crores approx. Pratik Shah: Hello.
- The company expects the Beverly Hills project execution timeline to be approximately 15 to 16 months.
Show source
Riddharth Jain: So, we can expect a timeline of one to one and a half years, approximately considering 15 to 16 months.
Demand and pricing
- Traffic in some regions that were not very close to ports on the Western Front has resumed to normal, while traffic on the Western Front will take some time to resume to its earlier trend because a lot of factories and trade were impacted.
Show source
But on the Western Front, I still feel that substantially it will take some time to resume to what the earlier trend was because additionally a lot of factories were impacted and a lot of trade was impacted.
- The company said geopolitical strain hampered logistical movement and factories in a region connected to import and export, and the combined impacts compounded traffic on a particular road.
Show source
And gradually, so both of these impacts compounded on the traffic on that one particular road.
Segments
- EPC model uses the L1 approach, with a tender worth INR 100 crores representing revenue; the revenue component is fixed and the cost component is uncertain, while its toll segment uses the H1 (higher bid) model, requiring payments to the NHAI, with uncertain revenue, fixed cost and profitability dependent on actual collections.
Show source
Thus, these are two distinct models: in the toll projects we secure from the NHAI, the cost is fixed, and our profitability depends on the actual collections, if collections exceed the cost, we make a profit, whereas if they fall short, we incur a loss.
Show 3 more statements
Segments
- The company is entering Tamil Nadu for the first time.
Show source
This is the first time we are entering into Tamil Nadu, which was a very big achievement for us.
- The company is actively trying to increase private works to balance government and private work, and is actively bidding for tolls. Replaced by a later filing.
Show source
And in terms of private works, we are actively trying to increase our private works to create a good balance between government and private.
- The company is actively participating in infrastructure work including water, electricity, road development, urban development, building development, renewable energy production and transmission. Replaced by a later filing.
Show source
We are also actively participating.
Everything else said on the call
What management stressed
- The company is developing an internal team focused on leveraging technology to increase efficiency in its core business, reduce manpower at sites, manage multiple sites from one core location, and analyze data using AI.
Show source
So how do I accumulate all of the data at one single location and how do I then further leverage AI to analyze this data.
- The company says its understanding of regional demographics, project risks and potential problems helps it decide which EPC contracts to bid for.
Show source
And so, we know what to bid and what not to bid for.
- The company will integrate relevant technology into its verticals going forward to make its system more efficient. Replaced by a later filing.
Show source
Additionally, as I mentioned initially in my speech, a multi-vertical infrastructure company, I would also like to mention that going forward, our verticals will be well -integrated with relevant technology to leverage the same for a more efficient and runn ing system.
- The company is positioning itself as a technology-focused, technology-backed EPC company and says it has leveraged technology to increase efficiency. Replaced by a later filing.
Show source
We know when to say no. And simultaneously, we are also positioning Highway Infrastructure Limited as a technology- focused, technology-backed EPC company.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Nachiket Kale: Good morning, sir. I wanted to check how is the recovery in traffic volumes? Is it like still below normal run rate or we are at par with the usual run rate we used to see?
Answer, riddharth jain
Riddharth Jain: I think it is important to mention that the traffic in some regions has resumed to normal, the regions which were not very close to the ports on the Western Front. But on the Western Front, I still feel that substantially it will take some time to resume to what the earlier trend was because additionally a lot of factories were impacted and a lot of trade was impacted. So, I think it will take some time. But nonetheless, most ly I think general business has resumed to majorly the business should not be impacted on that front.
Question
Nachiket Kale: Okay. So, that should lead to an upward trajectory on the EBITDA margin?
Answer, riddharth jain
Riddharth Jain: Yes, I think so. And even so, I think there was a drop in our EBITDA margin recently because of this geopolitical situation recently. And so, going forward, I think, and if there are no new developments on that front, we should be good.
Question
Nachiket Kale: Okay. So, for this port-linked corridors, is there any like have you tweaked your strategy to bid for these accounts or you still see this as attractive because, is there a scope to capitalize on tough times which leads to an advantage down the line?
Answer, riddharth jain
Riddharth Jain: Definitely, I think going forward and initially since the start also, we had the strategy of diversifying into different locations or different parts of India. And that is why you must be seeing that we have been focusing a lot in the eastern, south part of India. And because these as attractive as the western front looks, it is important that we hedge our any kind of future risk by different parts of India, like I mentioned, the NH-44 corridor that we have been capitalizing recently or we intend to capitalize. This should create a balanced risk portfolio going forward.
Question
Nachiket Kale: Okay. And on the order pipeline front, what is the latest update and new order inflows, how are we progressing on that front?
Answer, saurabh mittal
Saurabh Mittal: Recently we secured INR 120 crores new toll projects in Tamil Nadu. And so, adding this, we have INR 900 crores of work order, out of which EPC is almost INR 500 crores and the rest for toll segment.
Question
Deep Shah: Thank you for the opportunity. So, I have a couple of questions. So, I want to understand what is the management doing differently compared to what they have been doing like 6 months ago?
Answer, riddharth jain
Riddharth Jain: So, as I mentioned in the later part of my speech, we have been focusing a lot on how we integrate technology, and how we leverage technology in our business. So, going forward, we are very keen on how do we develop more on technology. There are so many newer facet tenders coming up which are allied amenities such as technology, infra -technology related tenders. And simultaneously, we are also developing a good team internally to focus on that front and how do we leverage this technology to increase our efficiency on our core business as well, which is how do I reduce the manpower at the site . How do I increase efficiency in terms of how multiple sites are managed from one core location from the HO . So, I do not have to deploy multiple assets at different locations because we are doing pan-India work. So how do I accumulate all of the data at one single location and how do I then further leverage AI to analyze this data.
Answer, riddharth jain
And how do we increase that kind of, how do we decrease our error ratio in any sort. So, I think that is something that we have been very actively working on. And I think we have made some very good developments and soon, we will be able to disclose all of those developments to everybody once we are ready with it.
Question
Deep Shah: I was saying the current weakness that we experienced, will there be any impact on the full-year outlook or the expectation of the recovery will remain unchanged?
Answer, saurabh mittal
Saurabh Mittal: Actually, this won't have a significant impact on the full-year results because, based on past trends, we tend to hover around the break-even point during the first and second quarters, while seeing a rapid recovery in the third and fourth quarters.
Answer, riddharth jain
Riddharth Jain: And I think if you are talking about the geopolitical related strains, so that has been reduced and recovery should be faster enough. So, this was a time-related, it was a one, two months kind of an issue that we faced earlier. And going forward, it will become fine. I mean, we are already seeing a lot of significant growth in the traffic trends already. And you can also see it on the IHMCL website. So, naturally, we are almost near normal to what the earlier traffic was.
Question
Deep Shah: Thank you. So, just wanted to understand like how do we do the accounting treatment in toll projects and if you could just give me an example for the revenue and expenses?
Answer, saurabh mittal
Saurabh Mittal: So, we operate under two models. The first is EPC, which is based on the L1 approach; for instance, if we win a tender worth INR 100 crores, that amount represents our revenue. In the Page 5 of 14 Highway Infrastructure Limited August 18, 2026 EPC model, the revenue component is fixed, whereas the cost component is uncertain. In the toll segment, we operate on the H1 so that is higher bid, where we are required to make payments to the NHAI; consequently, the revenue component is uncertain. Thus, these are two distinct models: in the toll projects we secure from the NHAI, the cost is fixed, and our profitability depends on the actual collections, if collections exceed the cost, we make a profit, whereas if they fall short, we incur a loss.
Question
Deep Shah: Sir, mix of both if you could just share ?
Answer, riddharth jain
Riddharth Jain: So, going forward, in EPC we are constantly bidding. So, and we are also diversifying into newer departments, to say. And in terms of private works, we are actively trying to increase our private works to create a good balance between government and private. With government, this kind of portfolio will always help us going forward because it reduces the risk in any one front. If there is an issue on the government fro nt, then obviously the private segment will support and simultaneously the vice versa is valid. In terms of tolls, we are actively bidding for various tolls. This is the first time we are entering into Tamil Nadu, which was a very big achievement for us.
Answer, riddharth jain
And going forward, we see a lot of scope in the eastern part of India also, which we have started to capitalize now Tamil Nadu, we are very focused, keen on Andhra Pradesh, Telangana. Going forward, West Bengal has also shown a lot of attractive propositions and we are active , the team is actively researching more about how can we, how do we enter into this particular state because that is again a new state for us. Likely, the northeastern states, to start with Assam, is again a state that we are very keen on and the team again is already deployed and doing some research on the ground on how do we enter, how do we make it more sustainable overall. So, this is what we plan to do strategically.
Question
Rahul Verma: Good morning, sir, and thank you for taking my question. Sir, so I just have two questions. Firstly, on the order book, as I assume we have INR 507 crores of EPC order book, so I wanted to understand how much is currently under active execution and what proportion is expected to be converted into revenue during FY27?
Answer, saurabh mittal
Saurabh Mittal: Sir, we are having 24 projects in executable. So, in the current year, we will realize approximately INR 150 crores in FY27 and in FY28 we will do INR 200 crores. So, it is executable in three years.
Question
Rahul Verma: Okay, sir. Understood. So, sir, the pipeline that you mentioned, should we consider that as the broader tender pipeline that we have currently under evaluation beyond, let's say, the INR 64 crores in EPC?
Answer, riddharth jain
Riddharth Jain: Rahul. I will take up this question. We are actively bidding, so this is not the final pipeline. I mean, this is what we have already accumulated in the first quarter. And Q2 is a quarter where the EPC business is kind of slow because of the monsoon season. So, this is where we are more focused on how do we get in better tenders. So, our major focus in Q2 for EPC would be to accumulate more better tenders and active bid for quality tenders that will be executed in the very near future, with not a very longer execution year span.
Show 17 more questions
Question
Priyam Shah: Sir, good morning and thanks for the opportunity. Could you provide an update on the company's current bid-to-win ratio across the tolling and EPC segments?
Answer, saurabh mittal
Saurabh Mittal: Success ratio for toll is almost 25% to 30%.
Question
Priyam Shah: Okay. And sir, another follow -up to that, as the EPC business scales up, do you plan to pursue larger projects independently or through any strategic JV partnerships?
Answer, riddharth jain
Riddharth Jain: So, definitely, like some of the projects which are in pipeline, as soon as we complete them, our PQ will actively increase. So, as soon as our PQ increases, we will on a sole basis we want to bid for larger tenders because then we have larger opportunity, larger margins, less competition, obviously. And even for so, just to get there, we are more than happy to collaborate with any good entity in which we see a good compatibility to put up for larger tenders. So, we are all for that. Page 7 of 14 Highway Infrastructure Limited August 18, 2026 Priyam Shah: Okay.
Question
Thank you, sir. And sir, my last question is, given that EV infrastructure and renewables have been identified as a key focus area within the EPC segment, have any bids been submitted in those areas so far? And further, what is the ballpark size of the opportunity pipeline currently that you are evaluating?
Answer, riddharth jain
Riddharth Jain: So, like I mentioned in my previous calls, definitely renewable energy production and transmission is something that will be in focus in the coming years. The team and all of us are actively looking on how do we capitalize it, but it is very important to understand that it will take some time. It will take some time for us to realize and it takes a lot of back work to really, before we actively bid because this will be a new segment for us. We do not want to burn our hands into getting a new segment abruptly. So, we are actively on it. Once we have some numbers in front of us, we will be more than happy to relay to you. For any number-related questions, I would suggest that you connect with EY and we can sit on a call and I can give you a full understanding of how are we navigating through this renewable energy sector.
Question
Rohan Shah: Thank you, so much for the opportunity. So, given the current order book of around INR 778 crores and recent toll order wins, what level of revenue growth do we expect for FY27?
Answer, saurabh mittal
Saurabh Mittal: For FY27, we are targeted INR 850 crores turnover, out of which INR 700 crores we are targeting for toll and rest for remaining for EPC business.
Question
Rohan Shah: Okay. Understood. Sir, Q1 profitability was affected by temporary factors. Could you explain what will drive margin recovery from here onwards? And has the entire impact has been absorbed in Q1 or can we expect some spillover in Q2 also?
Answer, riddharth jain
Riddharth Jain: Okay. Thank you, Rohan, for this question. I think it is a very important question and I would love to address this. Like we all know, what happened recently because of geopolitical strain. So, what actually happened was because of the geopolitical strain, a lot of logistical movement, logistics movement was hampered. In turn, a lot of factories were hampered in that particular region which were correlated to import and export. And gradually, so both of these impacts compounded on the traffic on that one particular road.
Answer, riddharth jain
The Ena, Moti Naroli toll plaza that we were operating at that particular period in Q1 was heavily impacted from these two combined factors. And this was localized to Q1, because I think the trends have become near to normal. The traffic has started to grow back. The businesses have resumed to their normal working. And more so, we do not see any new progress in for the reason of this geopolitical strain. So, it was very well Page 8 of 14 Highway Infrastructure Limited August 18, 2026 absorbed in Q1, hoping that there is no new development in international politics. I hope that answers your question.
Question
Raj Patel: Yes. So, my first question is, as we look into scale the EPC business, can you just explain the strategy going forward and what kind of project sizes will HIL focus on?
Answer, riddharth jain
Riddharth Jain: Moving forward in EPC, like we have mentioned, we have been very selective in what projects we want to take up. A lot of projects, it is very important that you only choose the projects which give you sensible profitability and also will be executed within the timeline mentioned. So, moving forward, the departments that we have been working on, we have deployed a newer team who is actively looking into newer departments, which may include some of departments from the center, which have larger scope of work, larger contract values, better margins, and less competition. So, these are departments which want higher quality work and that is what we intend to do moving forward. Departments such as MES, CPWD, and relevant are where we are actively looking. We see a bright future. But again, like I mentioned, these are something that we are working on and unless and until we do not have something concrete to relay, I will say that we are working on it.
Question
Raj Patel: Okay. Thanks for the detailed answer. And my second question would be, Kaza is our currently largest toll collection project, right. So, could you just share how the project has performed so far compared to our initial expectations at the time of bidding? And does this experience give you confidence to do the similar kind of large value toll contracts going forward?
Answer, riddharth jain
Riddharth Jain: Yes, definitely. I think Kaza has been one of the projects which have outperformed our expectations, definitely. We did expect this out of Kaza toll plaza. Because we expected very good development in the Amaravati region. The local businesses and the government is very supportive in bringing investment, bringing new development, may the development be in the front of infrastructure, could it be private buildings, factories, global capacity centers, what not. Everybody knows that. So, we have been very optimistic about Kaza toll plaza.
Answer, riddharth jain
And to the second part of your question, larger toll contracts are definitely something that we are very keen on. Because there is much less competition. The risk appetite and the understanding of some toll plazas on these large scale, people outside of this industry do not understand the risks involved. Obviously, the risks are higher if you do not have complete knowledge or understanding or research about the toll plaza. Page 9 of 14 Highway Infrastructure Limited August 18, 2026 We, on the other hand, do extensive research before venturing. And so, definitely, we have an edge over the others who are from outside the industry and from the industry. There are very few people who are actively bidding for such larger contracts.
Answer, riddharth jain
So, yes going forward we want to participate in larger contracts whatsoever is possible. And like we mentioned Ena, Moti Naroli was almost 70% larger contract than Kaza toll plaza. But just because of the geopolitical strains, something that it did not go as we expected. But our visibility, our intentions for going forward would be to create a good mix of small-value contracts, mid-value contracts, and large-value contracts because in tollways it is not obvious that larger value contracts will always give you a better margin. Traffic understanding is very complicated in that front. So, we try to create a good mix of small contracts, medium contracts, and then larger contracts simultaneously.
Question
Isha Shah: Thank you for the opportunity. Sir, can you please help me understand what differentiates HIL from regional EPC players when competing for projects in the INR 50 crores to INR 250 crores range?
Answer, riddharth jain
Riddharth Jain: What makes us different, like I mentioned in the previous answers, when you say as a regional contractor, we have a very good understanding of the demographics. We have been a very old player in this industry. We know how things work. We know what kind of risk we entail. We know what kind of problems a project might face in the future. And so, we know what to bid and what not to bid for. It is very important, there are thousands of contracts out there, millions and millions of rupees contracts, but it is important to say no to the ones you know which will not work.
Answer, riddharth jain
So, we are very well acclimatized to this market and this industry. We know when to say no. And simultaneously, we are also positioning Highway Infrastructure Limited as a technology- focused, technology-backed EPC company. A lot of EPC companies may not be focusing on this front, but we are very, very keen. And like I said, there have been so many developments that the company has done, and I would love to relay it to you now, I will want to do that in a more formal way by officially, mentioning what all developments we have made. So, hopefully soon enough I will be able to do it and you will get to know how we have leveraged technology into increasing our efficiency. And I can assure you that this will be something very interesting when you get to know. Page 10 of 14 Highway Infrastructure Limited August 18, 2026 Isha Shah: Yes.
Question
Thank you, sir. One more follow-up question I have. Sir, are you seeing any shift in the competitive landscape where smaller regional contractors are finding it difficult to qualify for larger projects and also does this creates an opportunity for HIL to improve its win rate and pursue larger ticket size EPC contracts?
Answer, riddharth jain
Riddharth Jain: Definitely. We have been seeing the research tell us that a lot of other industry people want to venture into this industry. And so, they take up contracts on very thin margins and turns out a lot of projects fail, a lot of people back out, a lot of companies close. So, that has been the case for the longest time. It is nothing new. And so, a lot of people think that there is a lot of money in this infrastructure segment and the numbers are, it's all a green signal from outside. So, it has been the case for the longest time.
Answer, riddharth jain
And like I previously mentioned, we know where people burn their hands. So, we are very selective in terms of what contracts we want to bid for. And I think that is the biggest edge we have over other newer smaller players. And yes, definitely, we are trying to increase our PQ as soon as the contracts we have in our hand will be executed, our pre -qualification will increase. That will put us into the next phase into bidding for larger contracts where again margins are better, competition is less, and a better larger team gets to work on a larger project . So, I think that would be good.
Question
Pratik Shah: Thank you for the opportunity. So, my first question is that you mentioned in the opening remarks that we have recently commenced construction at Beverly Hills. So, what is the total value and expected execution timeline of this project?
Answer, saurabh mittal
Saurabh Mittal: Within this year, sir. Value of project is INR 70 crores approx. Pratik Shah: Hello.
Question
Pratik Shah: Yes, i can. And sir, what was the expected execution timeline?
Answer, riddharth jain
Riddharth Jain: So, we can expect a timeline of one to one and a half years, approximately considering 15 to 16 months.
Question
Pratik Shah: I am saying what proportion of EPC revenues could it contribute over the next 12 to 18 months? Page 11 of 14 Highway Infrastructure Limited August 18, 2026 Riddharth Jain: We are expecting at least INR 150 crores of revenue from EPC.
Answer, riddharth jain
So, this will be contributing to the ballpark of around 40-45% of the revenue in the next 15 to 16 months.
Question
Priyam Shah: Sir, thank you for the opportunity again. While the company is currently deriving a significant share of its revenue from a few key states, how is the management approaching geographic diversification as the business scales?
Answer, riddharth jain
Riddharth Jain: Thank you again for your question, Priyam. I mean, it's evident that we are not very focused on one particular state. We have ventured into Tamil Nadu for the first time. So, I think this explains how we are expanding geographically. And again, it is not about one particular state. It is about the, it takes a lot of time to analyze of what the state is going to be doing in the next couple years. And like for example, Kaza, we were very keen on Kaza.
Answer, riddharth jain
We have been researching a lot about Andhra Pradesh, Telangana, and that entire belt, that particular road belt. And so, we were actively researching, seeing how much development is happening, what kind of investments the state is bringing in, what is the timeline of execution of whatever work they are getting in. So, we could predict what kind of traffic growth we could expect on that front. So, while we are diversifying into different newer states, we are also doing well, all of these diversifications backed by extensive research. So, while like I mentioned we are keen on West Bengal and Assam also, the research is still going on and we will be waiting for the right opportunity to enter a newer state. Like I said, we only and only venture when we see the right opportunity and when our research says that it is the right time to venture.
Question
Priyam Shah: Okay. And among the states that you just mentioned, can you highlight which states would be witnessing a stronger pipeline of bidding opportunities in the coming quarters or in the coming years?
Answer, riddharth jain
Riddharth Jain: Like I said, it is all based on opportunity to opportunity, what kind of tenders are uploaded by the government in the near future. There are some newer roads that are also being completed very soon. So, it is difficult to say which one particular state wh ere we will be focusing on. But I can say that the eastern belt of India is something that is very opportunistic and we would be very, very keen on that front.
Question
Priyam Shah: Can we anticipate that the eastern belt to flow in our revenues in the coming let's say coming 6 months or 12 months down the line?
Answer, riddharth jain
Riddharth Jain: Hoping, hoping that we get the right opportunities in the right time. Page 12 of 14 Highway Infrastructure Limited August 18, 2026 Priyam Shah: Okay.
Question
And sir, this is more on our broad-based strategy that we are looking. If you can just elaborate the company's growth strategy over the next few years and how the management is envisioning the next phase of growth and what was the key drivers for the same?
Answer, riddharth jain
Riddharth Jain: Going forward, it is actually very interesting question and thank you for this question because I wanted to talk about this. India as a growing country, as a developing country, we have ample of infrastructure work, may it be water, electricity, road development, urban development, building development, or maybe newer segments such as renewable energy production, transmission, so on and so forth. And so, definitely there are multiple new companies coming up. We are also actively participating. But what should keep us ahead of others is that when there is so much opportunity, how do you decide on what is the best for us. What is the best for HIL? And how do we make sure that we get the contracts that we actually want?
Answer, riddharth jain
So, what the company has been actively doing is that nothing, so what our opinion? What the board feels is that technology is very important for us. So, how do we position ourselves as a technology-integrated infrastructure company where our focus would be on our core business such as the infrastructure development that we do, the tollway collection that we do, but how do we leverage this technology. When I say technology, technology could be a very broader umbrella, but you have to understand why I am not specifying one particular term. So technology, how do we integrate technology into , how do I better my margins? How do I better my human resource deployment? How do I better analyze on what has performed better and what could perform better in the future ?
Answer, riddharth jain
How do we predict on what is going to happen in the future? For this, we need a lot of data collection, analysis, data crunching from the human end and also from the computing end . So, going forward in the future, let's say 5 -10 years down the line, you will see that we will come out as a more technology-driven infrastructure company because that is very important. The machines are going to be the same, the way that we construct is going to be the same. But how do we manage all of this is very crucial. When you are doing infrastructure work pan-India, it is important to understand how you manage everything. How do you use these software’s. How do you use.
Answer, riddharth jain
For example, BIM it was like a newer software for India a few years back, which actually leveraged and helped a lot of bring in a lot of efficiency into building construction . Reduced the errors, reduced the time of construction, reduced actually the number of engineers that you need to execute that particular project. And that's just one example. There is actually BIM as sophisticated a software it is, it is still novice for the broader technology development already happening around the world. So, it is just safe to say that technology will be the next forefront on how do we execute and manage our projects while our main core business will be infrastructure.
Question
Priyam Shah: Sir, I am done with all my questions. Thank you, sir.
Answer, riddharth jain
Riddharth Jain: First of all, I would like to thank each and every one of you for your participation, your insightful questions, and continued interest in Highway Infrastructure. While Q1FY27 was impacted by certain temporary factors, we remain encouraged by the strength of our underlying business, improving traffic trends, healthy order book, and a strong opportunity pipeline across both EPC, tollway segment, and real estate. We have built a diversified again, I would stress more on diversified, we have built a diversified infrastructure platform with multiple growth drivers, a disciplined approach to project selection, and a clear focus on long-term value creation. As India continues to invest in its infrastructure ecosystem, we believe Highway Infrastructure is well-positioned to participate in this opportunity, deliver sustainable growth in the years ahead, and also add meaningful value to this. On behalf of the management team, I would like to thank all of our investors, customers, partners, lenders, and employees for their continued trust and support. Thank you and have a great day.
Questions about this call
- When was the Highway Infrastructure Q1 FY27 earnings call transcript filed?
- Highway Infrastructure filed the transcript with the exchange on 21 Aug 2026. This page is built from that transcript.
- What does this page list?
- 41 statements from the transcript across 7 topics, 17 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 27 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.