Skip to content

Earnings call

KPI Green Energy Q1 FY26 earnings call: KPI Green Energy Limited's orders in hand exceeded 3 GW, including capacities where LOI is awaited

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Orders in hand exceeded 3 GW, including capacities where LOI is awaited. The company expects its PAT margin to be in the range of 15% to 20%, compared with around 16%-17% today, and says it will be able to maintain that range. The company has three major IPP projects under execution: a 250 MW solar project on the AC side and 350 MW DC, a 370 MW hybrid project on the AC side and 679 MW DC, and a 150 MW standalone wind project; together they represent an execution size of Rs. 5,000 crores. The company reported total revenue of Rs. 614 crores, EBITDA of Rs. 217 crores, PBT of Rs. 149 crores, profit after tax of Rs. 111 crores, basic EPS of Rs. 5.28 and cash profit of Rs. 163 crores in the quarter ended June 30, 2025; revenue grew 75% over Rs.350 crores, EBITDA increased 64%, PBT rose 64% from Rs. 91 crores, profit after tax grew 68% compared to Rs. 66 crores, basic EPS grew 44% from Rs, 3.66, and cash profit marked 92% year-on-year growth. The company would like to issue its new green bonds at 0%, but looking at the current market would like to close the rate somewhere around 8.8%.

The numbers management gave

Results

  • The company reported total revenue of Rs. 614 crores, EBITDA of Rs. 217 crores, PBT of Rs. 149 crores, profit after tax of Rs. 111 crores, basic EPS of Rs. 5.28 and cash profit of Rs. 163 crores in the quarter ended June 30, 2025; revenue grew 75% over Rs.350 crores, EBITDA increased 64%, PBT rose 64% from Rs. 91 crores, profit after tax grew 68% compared to Rs. 66 crores, basic EPS grew 44% from Rs, 3.66, and cash profit marked 92% year-on-year growth.
    Show source
    Speaking about the key highlights of this quarter: On the financial side, if I give the synopsis of the financials, total revenue stood at Rs. 614 crores, a robust growth of 75%, over Rs.350 crores in Quarter 1 of FY'25, EBITDA rose to Rs. 217 crores, a 64% increase.
  • The company reported 60 to 70% growth on all parameters, including revenue and profitability, in the quarter ended June 30, 2025.
    Show source
    So, Garvit, if you look at this quarter also, we have done 60 to 70% of growth on all the parameters, whether it is revenue, whether it is profitability and everything.

Money and capital

  • The company would like to issue its new green bonds at 0%, but looking at the current market would like to close the rate somewhere around 8.8%.
    Show source
    I would like to get it at a 0% but most probably looking at the current market I somewhere around 8.8% or something we would like to close it.
  • The company will not exceed a 2:1 debt-to-equity ratio with the NCD and upcoming project.
    Show source
    With the NCD and upcoming project also, we will not cross 2:1.
  • KPI promoter holding is 48.70 something and will be stable for the next couple of years.
    Show source
    At present, KPI promoter is holding 48.70 something and it will be stable for next couple of years.
  • The company has not yet decided the rate for its new green bonds and will try to get a lucrative rate from the market; the entire bond is guaranteed by Garenco, a AAA entity when it comes to Indian rating.
    Show source
    So, you can understand is the second highest rating after AAA and which is one of the best rating when it comes in, so we are we have yet not decided on the rate but we will try to get the lucrative rate from the market because this entire bond is guaranteed by Garenco which is a AAA entity when it comes to Indian rating.

What it expects ahead

What management expects

  • The company expects its PAT margin to be in the range of 15% to 20%, compared with around 16%-17% today, and says it will be able to maintain that range.
    Show source
    So, accordingly, I don't see too much curtailment into the PAT margin, but it will be in the range of 15% to 20%.
  • The company says IPP and CPP margins vary by quarter because milestone-based billing of service components produces somewhat higher margins than billing of supply or material components; it expects the final PAT margin to be around 16% to 18%.
    Show source
    So, when we build the service component, at that time my margins are a little bit higher and when I build the supply component or the material component the margins, so there is depend upon the way I do the billing, my margins will keep on rotating on in some of the quarters and at the final it will be at around PAT margin of 16% to 18% kind of a margin.
  • Battery energy storage system projects are expected to have a timeline of around 1-2 years, or 18 to 24 months, depending on the different projects.
    Show source
    For these projects also timeline would be around 1-2 years kind of timeline between 18 to 24 month kind of a timeline that will be given by the depending upon different projects will have different timeline.
  • Target is for IPP to be around 25% of revenue, and it might reach 17%-18% by the end of this year.
    Show source
    Page 19 of 29 Since 1994 www.kpgroup.co Salim Yahoo: Soham: Salim Yahoo: Soham: Salim Yahoo: Soham: Moderator: Shubhankar Gupta: Salim Yahoo: KPI Green Energy Limited August 06, 2025 Sir, our target is around 25% should be the IPP share, but going forward I think by end of this year, we might move up to 17%-18% kind of.
  • Estimated EBITDA margin for IPP is around 75% to 80%.
    Show source
    Then only we will be able to tell, but roughly if I want to calculate my EBITDA for IPP would be around 75% to 80%.
  • Estimated EBITDA margin for CPP is around 20%.
    Show source
    And my EBITTDA of CPP around 20%.
Show 11 more statements

What management expects

  • The company expects revenue growth of 60% to 70%, but says CPP capacity is difficult to predict because capacity is booked as completed only after the entire project is complete.
    Show source
    So, itis very difficult to tell you that exactly how much capacity will be there, but yes if you see the revenue wise, I mean we will do 60% to 70% growth in the revenue also.
  • The company expects 60% revenue growth from the 1,700 achieved last year to '26 and another 60% growth from there to '27, given its huge pipeline.
    Show source
    So, you can count 60% of growth from there to '26 and again 60% growth from there to 27% because we have huge pipeline also.

Orders

  • Orders in hand exceeded 3 GW, including capacities where LOI is awaited.
    Show source
    Orders in hand exceeds 3 GW, including capacities where LOI is awaited.
  • CPP business had approximately 1.8 gigawatt of orders in hand, worth around Rs. 4,000 crore.
    Show source
    On the CPP side, we have approximately 1.8 gigawatt of order book, which is in the pipeline, and not the pipeline, but the orders in hand, you can say that that itself is around Rs. 4,000 crore.
  • The company has decided to bid for tenders worth around Rs. 3,000 crores to Rs. 4,000 crores for its battery energy storage system business.
    Show source
    I can tell you the tender pipeline that we have already decided to bid for, is around Rs. 3,000 crores to Rs. 4,000 crores of tenders.
  • Pipeline for solar and hybrid might go up to 4,000 to 5,000 another.
    Show source
    As I told you no, pipeline for solar and hybrid might go up to 4,000 to 5,000 another.
  • The company has a pipeline of 4,000 crores-5,000 crores at any given point of time where people are discussing and its BD team or tender team is working on it.
    Show source
    So, around 4,000-5,000 any given point of time, we have 4,000 crores-5,000 crores of pipeline where people are discussing, my BD team or tender team is working on it.
  • The company has an overall pipeline of 8,000 crores-9,000 crores between BESS and its erstwhile work on solar, wind and hybrid.
    Show source
    So, we are seeing overall between 8,000 crores-9,000 crores pipeline we have, between BESS and erstwhile work that we did on solar and wind and hybrid and so on and so forth.
  • The company has a CPP order book of 1.8 gigawatt.
    Show source
    See, as I told, the CPP capacity as on, the order book that I have in hand is 1.8 gigawatt.
  • The company received a Letter of Intent (LOI) from Gujarat Urja Vikas Nigam Limited (GUVNL) for development of a 150 MW grid-connected Wind Power Project, for 150MW grid connected Wind Power Projects, under reference no. GUVNL/RE/Wind/1034 dated July 14, 2025.
    Show source
    We received LOI, that is a letter of intent from GUVNL for our 150 MW grid connected wind project, bolstering our hybrid pipeline.
  • Pipeline is a target to participate in bids and does not represent confirmed orders.
    Show source
    So, it is not typically pipeline where we confirm it is our order confirmed, so it is a target to participate to the bid.

What it is building and selling

Projects and capacity

  • The company has three major IPP projects under execution: a 250 MW solar project on the AC side and 350 MW DC, a 370 MW hybrid project on the AC side and 679 MW DC, and a 150 MW standalone wind project; together they represent an execution size of Rs. 5,000 crores.
    Show source
    Together these projects represent a total execution size of Rs. 5,000 crores.
  • The company is targeting completion of its 250 MW pure solar and 370 MW hybrid project by September '26 in a phased manner, with part commissioning and revenue recognition expected to begin within the next few quarters.
    Show source
    We are targeting completion of the 250 MW pure solar, 370 MW hybrid project by September '26 in a phased manner.Importantly, part commissioning and revenue recognition are expected to begin within the next few quarters, leading to an early monetization and cash flow generation.
  • Installed and upcoming IPP capacity was 1.7 GW and installed and upcoming CPP capacity was 2.3 plus GW as on June 30", 2025, with a total cumulative portfolio of 4 GW.
    Show source
    The overall snapshot of the Company as on June 30", 2025, on the end of the quarter, it stands at installed and upcoming IPP capacity stands at 1.7 GW, installed and upcoming CPP capacity of 2.3 plus GW, a total cumulative portfolio of 4 GW, a land bank of 6,275 acres, along with that we have power evacuation capacity of over 3.2 GW.
  • The company had a land bank of 6,275 acres and power evacuation capacity of over 3.2 GW as on June 30", 2025.
    Show source
    The overall snapshot of the Company as on June 30", 2025, on the end of the quarter, it stands at installed and upcoming IPP capacity stands at 1.7 GW, installed and upcoming CPP capacity of 2.3 plus GW, a total cumulative portfolio of 4 GW, a land bank of 6,275 acres, along with that we have power evacuation capacity of over 3.2 GW.
  • The company has Rs. 5,000 crore projects in the IPP pipeline that are getting executed.
    Show source
    IPP, I already spoke that Rs. 5,000 crore projects are in pipeline.
  • The company is targeting September 26 to complete 1.2 gigawatt of DC capacity, described as 250-370 AC capacity.
    Show source
    So, hopefully we will complete that 1.2 gigawatt of DC capacity that is 250-370 AC capacity.
Show 4 more statements

Projects and capacity

  • The company plans to have half of the 1.2 gigawatt capacity before this financial year ends, depending on its execution run rate and seasonality.
    Show source
    So, the execution run rate can be different at different times depending upon the seasonality also, but at least we plan to have half of this capacity of 1.2 gigawatt to get before this financial.
  • The company has 3.26 gigawatt of evacuation capacity in place, with substation capacity allocated to KPI; some portion is already done.
    Show source
    The evacuation, when I talk about the evacuation, 3.26 gigawatt of evacuation in place that we have already blocked the substation where we have approval that this particular substation capacity is now allocated to KPI.

Deals and partners

  • KP Group signed three strategic MOUs with Delta Electronics India for collaboration in Battery Energy Storage Systems (BESS), Green Hydrogen and EV Charging Infrastructure, and Advanced Solar PV Inverters, to jointly develop clean energy solutions in India and select international markets.
    Show source
    We signed three strategic MOUs with Delta Electronics India, focusing on battery energy storage system, green hydrogen and EV charging infrastructure, advanced solar PV inverters.
  • Projects are backed by 25-year long-term PPA signed with GUVNL. Replaced by a later filing.

Risks, rules and outside factors

Outside factors

  • The company has panels of 1.7 gigawatt and hedges at today's rate, so it will not have a problem if rates rise.
    Show source
    So, in future if the rate goes up, we don't have a problem and if there is something from any other side, also we don't have a problem because all Indian manufacturers.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

This transcript does not separate questions and answers, so they are not listed here.

Questions about this call

When was the KPI Green Energy Q1 FY26 earnings call transcript filed?
KPI Green Energy filed the transcript with the exchange on 12 Aug 2025. This page is built from that transcript.
What does this page list?
34 statements from the transcript across 7 topics, 31 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
No. This transcript does not separate the questions from the answers, so they are not listed. The statements by topic still cover what management said.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
KPI Green Energy Q1 FY26 concall: KPI Green Energy Limited's orders in hand exceeded 3 GW, including capacities where LOI is awaited · DalalOS