NCC Q2 FY27 earnings call: NCC Limited said the major Jal Jeevan order backlog in U.P. will be substantially completed by March 2027
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The transcript names the quarter but not the year. The year is worked out from the date it was filed.
The company said the major Jal Jeevan order backlog in U.P. will be substantially completed by March 2027. The company retained its FY27 guidance of 8%-10% growth after working through estimates for various projects; mining division and several other projects provided revenues and numbers needed for growth in H1. The company has completed installation of almost 51% of its smart meters, with 49% outstanding. Inventory stood at INR1,742 crores at the end of September, INR1,815 crores at the end of June, and INR1,787 crores at the end of March '26. The company incurred capex of INR83 crores in the second quarter and INR253 crores in the first six months of the current financial year, against a budget of INR500 crores for the financial year '27.
The numbers management gave
Results
- EPS was INR2.60 at the end of the second quarter, compared with INR1.62 in the relevant quarter of the previous year.
Show source
The EPS stands at INR2.60 at the end of Q2, as against INR1.62 of the relevant quarter of the previous year.
- Inventory stood at INR1,742 crores at the end of September, INR1,815 crores at the end of June, and INR1,787 crores at the end of March '26.
Show source
Inventory stands at INR1,742 crores as at the end of September, INR1,815 crores end of June, and INR1,787 crores at the end of March ' 26.
- Vizag receivable was INR270 crores at the end of September '26, almost INR270 crores at the end of June, and INR291 crores at the end of March.
Show source
Coming to the Vizag receivable status, at the end of September ' 26, it is INR270 crores; at the end of June, it is almost at INR270 crores; at the end of March, it was INR291 crores.
- Outstanding across all JJM projects it handles in various states was INR2,246 crores as on date.
Show source
Sanjay Pusarla: As on date, INR2,246 crores, including all the JJM projects handled by us across various states.
- Trade receivables were INR344 crores, and its unbilled revenue was INR2,009 crores.
Show source
Sanjay Pusarla: If you ask me to give you only the trade receivables, it has come down to INR344 crores .
- The company receives realization for work it is executing in AP between 30-40 days.
Show source
Between 30- 40 days, we are getting realization.
Show 17 more statements
Results
- The company received about INR1,720 crores in JJM payments in the first half of the current financial year.
Show source
Sanjay Pusarla: In the first half, we received about INR1,720 crores .
- Payment cycles with government clients range between 50-60 days from the date of certification.
Show source
Generally, in the government clients, the payment cycles ranges between 50-60 days from the date of certification.
- Depreciation cost increases quarter to quarter in absolute terms based on new orders and capex already undertaken or to be undertaken in the remaining quarters, while depreciation is 1.48% and that percentage is maintainable.
Show source
1.48% is given.
- Mining project is standalone, and its depreciation is included in the 1.48%.
Show source
RS Raju: No, here mining is inclusive of this 1.48.
- The company recognizes unbilled revenue under Ind AS 115 for amounts spent and obligations completed but not billed because of certification, and adds that amount as contract revenue.
Show source
Unbilled revenue as per the standard Ind AS 115, what we need to do is that whatever money we have spent and we have completed our obligation and not billed because of the certification, that amount whatever is there need to be recognized in unbilled revenue.
- Finance cost percentage will be around 9.21%.
Show source
Sanjay Pusarla: The percentage will be around 9.21 finance cost.
- The company said its payment cycle was improving in general, and payments from the Jal Jeevan Mission were also improving and coming in a regular manner.
Show source
Sanjay Pusarla: In general, we have seen the payment cycle is improving.
- For NCC's BharatNet projects, the lead time from execution to billing and realization is a little longer.
Show source
Especially in the BharatNet projects, the lead time for conversion from billing, from execution to billing and realization is little longer.
- TBM and mining project depreciation will come under standalone.
Show source
Both will come under the standalone only.
- Unbilled revenue is progressively realizing. Replaced by a later filing.
Show source
The unbilled revenue is progressively realizing.
Money and capital
- The company incurred capex of INR83 crores in the second quarter and INR253 crores in the first six months of the current financial year, against a budget of INR500 crores for the financial year '27.
Show source
We have incurred a capex of INR83 crores in the Q2 FY27 and INR253 crores in the first six months, as against the budget of INR500 crores for the financial year ' 27.
- Investments stood at INR867 crores at the end of September, the same as at the end of March '26.
Show source
The number is INR867 crores end of September, and the same is the case end of March '26 also.
- Loans to group companies were INR306 crores at the end of September, INR290 crores at the end of June, and INR295 crores at the end of March 2026.
Show source
Loans to group companies, INR306 crores at the end of September, and INR290 crores at the end of June, and INR295 crores at the end of March 2026.
- Retention money increased by about INR150 crores quarter-on-quarter; it may reduce if the company obtains contracts allowing retention money to be replaced with bank guarantees, and retention money is returned when contracts complete the DLP period. Some contracts allow replacing 50% of retention money with a bank guarantee on contract completion; the amount depends on contract terms, contract mix and present situations.
Show source
If you see on quarter-on -quarter, there is about INR150 crore s, there is an increase in the retention money.
- Capex in the first six months was INR253 crores, excluding TBM; the TBM investment was made last year, when it was capital work in progress, and was capitalized this year.
Show source
It is INR 253 crores in the first six months.
- Overall capex is INR500 crores, of which INR253 crores has been spent in the first half, and it will probably spend the balance INR250 crores in the second half.
Show source
Sanjay Pusarla: Second half capex is overall capex is INR500 crores and INR253 crores we have already spent in the first half.
- The company accounts for the smart meters financial asset as other financial liabilities in its consolidated accounts because the smart meters are a HAM project.
Show source
Because smart meters is a HAM project, it has to be accounted under the financial liability.
What it expects ahead
What management expects
- The company retained its FY27 guidance of 8%-10% growth after working through estimates for various projects; mining division and several other projects provided revenues and numbers needed for growth in H1.
Show source
But still we have two quarters to go, and whenever we share a number with investors, we do a thorough working for various projects, and then depending on that estimation only, we have Page 6of 17 NCC Limited November 06, 202 6 shared the guidance for you, that is 8%-10% growth for FY27, and we have decided to retain that guidance.
- The company expects to complete recovery of the INR270 crores outstanding from the Vizag land sale by end of the quarter four.
Show source
Sanjay Pusarla: We expect by end of the quarter four, we will be able to complete this.
- The company does not expect the same problems or tightness in government payment releases, because governments including AP and other places are coming up with the JJM scheme.
Show source
Sanjay Pusarla: Yes, we do not expect the same kind of problems or same kind of tightness will be there in release of payments by the government.
- The company capitalized and put the TBM machine to use in September, and depreciation is expected to increase in the third and fourth quarters as depreciation on the TBM and capital-intensive mining project comes into play.
Show source
Definitely, the depreciation is going to go up in the third quarter and fourth quarter.
- The company will take new JJM projects if it gets an opportunity. Replaced by a later filing.
Show source
If we get an opportunity, then we will take it.
- The company expects to maintain a similar level of unbilled revenue in the days to come. Replaced by a later filing.
Show source
But we expect that we maintain maybe a similar type of unbilled revenue in the days to come.
Show 7 more statements
Orders
- The company said the major Jal Jeevan order backlog in U.P. will be substantially completed by March 2027.
Show source
The major Jal Jeevan order backlog, which is there in U.P., will get substantially completed by March 2027 itself.
- AP order book is INR14,500 crores.
Show source
INR14,500 crores is the order book for the AP.
- JJM order book is INR5,413 crores.
Show source
Sanjay Pusarla: INR5,413 crores.
- Order inflow is about INR11,108 crores, including projects bagged in October, about 50% of its INR22,000 crores-INR25,000 crores order inflow guidance.
Show source
Neerad Sharma: See, you are absolutely right that we have shared the order inflow guidance, a band, INR22,000 crores-INR25,000 crore s. If we take into account the projects that we have bagged in the month of October, the total inflow is about INR11,108 crores, which is about 50% of the lower band.
- Value of the Ken-Betwa contract to be executed is INR3,389 crores.
Show source
It was INR3,389 crores, which is the value per the NCC to be executed.
- Order inflow guidance is INR22,000 crores to INR25,000 crores for FY '26.
Show source
We retain that guidance, and hopefully, we will achieve that number.
- The company was the first to bag a project awarded for the Ken-Betwa project.
Show source
Neerad Sharma: Mr. Kapoor, I think Ken-Betwa, we are the first ones to bag the first ever project that was awarded for the Ken-Betwa part.
What it is building and selling
Projects and capacity
- The company has completed installation of almost 51% of its smart meters, with 49% outstanding.
Show source
Sanjay Pusarla: Yes, it is almost like 51% we have completed installation, and 49% is outstanding.
- The company has executed almost 11% of the total BharatNet contract in both MP and Uttarakhand.
Show source
Sanjay Pusarla: We have done almost like 11% of the total contract we have executed in both MP and Uttarakhand.
- The company has spent about INR1,000 crores on BharatNet work and has started billing.
Show source
We have almost spent about INR1,000 crores on its work, and we have started billing now.
- The company is making reasonable progress on the Ken-Betwa sites; the land acquisition issue or demonstration mentioned was at a place 30, 40 km away from its project site.
Show source
Neerad Sharma: No, we are making reasonable progress on the Ken-Betwa sites.
- The company expects to substantially complete the INR3,200 crores balance in its legacy Jal Jeevan projects by March 2027; its current Jal Jeevan projects are about INR2,128 crores, are progressing, and payments are progressively coming in.
Show source
If you ask me, the legacy part of the Jal Jeevan, if you see that, it is INR3,200 crores is the balance which is there available in the legacy Jal Jeevan projects, which we are expecting to substantially complete by March 2027.
Risks, rules and outside factors
Risks and disputes
- The company has invested INR107 crores in an investment property project in Hyderabad that is midway; the project was stopped, the developer is in difficulty, and RERA canceled or put the project on hold.
Show source
Sanjay Pusarla: This INR107 crores investment relates to a project in Hyderabad.
- Investment in the Hyderabad project is completely secured, with no problem in recoverability, but the time to resolve the issue is uncertain because it is before the NCLT.
Show source
Definitely, the amount of investment is completely secured.
Outside factors
- The company said that almost all of its present contracts have 5% retention money, while some contracts in the electrical division where it has lost have retention money as high as 20%; Mumbai CC roads contracts also have very high retention money, explaining why retention money appears high compared with the previous period.
Show source
In the present context, what is happening, almost all the contracts have a retention money, 5% of retention money, and some of the contracts in electrical division where we have lost, the retention money is as high as 20%.
- 81% of NCC's contracts have escalation clauses, which majorly offset price increases through the available price variation clauses.
Show source
Sanjay Pusarla: 81% of our contracts have got the escalation clauses.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Vaibhav Shah: Thank you, Rayo. On behalf of JM Financial, I welcome everybody to Q2 FY27 earnings conference call of NCC Limited. We have from the management today Shri R.S. Raju, Director of Projects; Shri Sanjay Pusarla, Executive Vice President, Finance and Accounts; and Shri Neerad Sharma, Head Strategy and Investor Relations. Now I hand over the call to the management for their opening remarks, post which we can begin Q&A session. Over to you, sir.
Answer, neerad sharma
Neerad Sharma: Thank you very much, Vaibhav. Good morning, everyone. This is Neerad. It gives me great pleasure to welcome you all to NCC's earnings call for the second quarter and the first half of the current financial year. At the very outset, I would like to thank each of you for joining this interactive session and for your continued interest and trust in NCC. I have with me my colleagues, Mr. R.S. Raju, Director Projects; and our CFO, Mr. Sanjay Pusarla.
Answer, neerad sharma
Yesterday, we have announced our unaudited financial results for the second quarter and the first half of the -- for the half year ended 30th September '26, which have been uploaded on our website and shared with the stock exchanges. We trust you have had the opportunity to review the financial statements and the investor presentation. Before we begin, I would like to draw your attention to a brief disclaimer with a request to study a detailed version from our investor presentation. This presentation may contain forward- looking statements concerning NCC's future business prospects and profitability, which are subject to several risks and uncertainties. The actual results could materially differ from those indicated in such forward-looking statements. End of the disclaimer. This interaction is broadly divided into three parts.
Answer, neerad sharma
In the first part, I will present a brief overview of the business environment, operational highlights, and our progress against our FY27 guidance. In the second part, our CFO will cover the detailed financial performance for the second quarter and the first half of the current financial year. In the third and last part, we will take up your questions. As you are aware, we have been continuously exploring new areas to expand our offerings to remain relevant to the emerging infrastructure opportunities, particularly in technology-enabled infrastructure and allied sector. We have already entered in new areas such as smart meters and tunneling using TBMs in the recent past. Page 2of 17 NCC Limited November 06, 202 6 As part of our medium-term plan to pursue emerging business opportunities, our Board has approved a few modifications in the Memorandum of Association to enlarge the scope of activities to be undertaken by the company. The second quarter is seasonally impacted by the monsoon, which generally slows down activity at project sites.
Answer, neerad sharma
Despite this, execution across our project portfolio remained steady, and we have recorded the highest ever second quarter revenue in NCC's history on a consol basis. Project progress across the sector continues to be influenced by fund allocation, client approvals, land availability, utility shifting, and billing milestones. Our teams have remained focused on mitigating these through disciplined project execution and close engagement with our clients. Our underlying business fundamentals remain robust, supported by a diversified order book across seven business divisions and an established and proven project management framework. As of 30th September 2026, our order book stands at INR80,167 crores, which is 11% higher than a year ago. During the quarter, we have booked new orders worth INR4,838 crores, mainly from our buildings and water and railway divisions. Our order book is about 3.5 times trailing 12-month revenue, giving healthy multi -year revenue visibility.
Answer, sanjay pusarla
Sanjay Pusarla: Yes, thank you. So, I will start from the capex. I think at that point of time, the disturbance came again. We have incurred a capex of INR83 crores in the Q2 FY27 and INR253 crores in the first six months, as against the budget of INR500 crores for the financial year ' 27. The EPS stands at INR2.60 at the end of Q2, as against INR1.62 of the relevant quarter of the previous year. Inventory stands at INR1,742 crores as at the end of September, INR1,815 crores end of June, and INR1,787 crores at the end of March ' 26. Coming to the investments, there is no change in the investment.
Answer, sanjay pusarla
The number is INR867 crores end of September, and the same is the case end of March '26 also. Loans to group companies, INR306 crores at the end of September, and INR290 crores at the end of June, and INR295 crores at the end of March 2026. Coming to the Vizag receivable status, at the end of September ' 26, it is INR270 crores; at the end of June, it is almost at INR270 crores; at the end of March, it was INR291 crores. With this, I will be ending my presentation on the financial statement. Now it is open for the question-and -answer session. Thank you.
Question
Shravan Shah: Good morning, sir.
Answer, neerad sharma
Neerad Sharma: Mr. Shah, the guidance that we had shared with you has been for the whole year, that is FY27 . We are pleased to share with you the fact that things have worked very well for us in the H1. The mining division, several other projects have given us the revenues, the numbers that we really needed for the growth, and we have shared very good set of numbers that we have already called out. But still we have two quarters to go, and whenever we share a number with investors, we do a thorough working for various projects, and then depending on that estimation only, we have Page 6of 17 NCC Limited November 06, 202 6 shared the guidance for you, that is 8%-10% growth for FY27, and we have decided to retain that guidance.
Question
Shravan Shah: Yes. Sir, just in terms of one more aspect, I was just looking at in terms of the retention money for us. For last three quarters, this number has the INR2,500- odd crores currently, which is there, 13.3% of the revenue is there, which used to be a kind of 8.5% one and a half year before. If I have to translate in terms of the numbers, it is kind of INR950,000 crores of a revenue. If we release this kind of a money and on a 9% interest, it translates to INR85, 90- odd crores, which is a 10% of the PAT. Just trying to understand, are we making any effort or attempt to kind of reduce this retention money as a percentage of revenue? Because it is significant, INR1,000-odd crores w
Answer, sanjay pusarla
Sanjay Pusarla: Yes. This is Sanjay here. The retention money you are talking 1.5 year back, at that point of time, we have got contracts of about INR20,000 crores where there is no retention money at all. In the present context, what is happening, almost all the contracts have a retention money, 5% of retention money, and some of the contracts in electrical division where we have lost, the retention money is as high as 20%. Some of the contracts which we received in Mumbai for the CC roads, the retention money is also very high. That is the reason the retention money, when you compare to the previous period, it appears to be high. But this is the retention money which we are having it.
Answer, sanjay pusarla
If you see on quarter-on -quarter, there is about INR150 crore s, there is an increase in the retention money. Going forward, maybe if you get a contract where you can replace retention money with the bank guarantees, definitely there will be reduction in that. Otherwise, whatever contract that will be completing the DLP period, you will be getting back your retention money. Some of the contracts have a clause where the contract completion, you can replace the retention money with a bank guarantee for 50%. It depends on the contract, it depends on the composition mix of the contracts and the present situations. This retention money will be there. It will continue to be there.
Question
Parvez Qazi: Hi. Good afternoon and thanks for taking my question. Two questions from my side. First, we have seen a pretty decent improvement in our payment cycle, especially over the last six-odd months. Will this be largely due to the UP JJM projects or, I mean, in general, we have seen improvement in payment cycle across them?
Answer, sanjay pusarla
Sanjay Pusarla: In general, we have seen the payment cycle is improving. As you said, even the payment from the Jal Jeevan Mission is also improving. They are coming in a regular manner.
Question
Parvez Qazi: What would be the outstanding in UP JJM projects now?
Answer, sanjay pusarla
Sanjay Pusarla: As on date, INR2,246 crores, including all the JJM projects handled by us across various states.
Question
Parvez Qazi: I think, if I remember correctly, it was about INR2,700-INR800 last quarter. So there has been a substantial reduction in this quarter.
Answer, sanjay pusarla
Sanjay Pusarla: If you ask me to give you only the trade receivables, it has come down to INR344 crores . In the case of unbilled revenue, it was INR2,009 crores.
Question
Parvez Qazi: Sure. There has been a decent reduction there. The second question is on the capex. You mentioned, I think, H1 capex at about INR153- odd crores. Now, I am assuming this is only at the standalone level. Overall capex, including TBM, is INR388 crores. Is that number correct?
Answer, sanjay pusarla
Sanjay Pusarla: Yes. It is not 153. It is INR 253 crores in the first six months. TBM, whatever we have invested, it was invested in the last year itself. It was there as a capital work in progress in the last year. This year, it has been capitalized. It is excluding that.
Question
Vaibhav Shah: And we plan to execute this by next year end?
Answer, sanjay pusarla
Sanjay Pusarla: It is like this. In this INR5,142 crores, there are some new projects which have come from Jal Jeevan, in other states. The major Jal Jeevan order backlog, which is there in U.P., will get substantially completed by March 2027 itself.
Question
Vaibhav Shah: And sir, we are open to take new projects in JJM?
Answer, sanjay pusarla
Sanjay Pusarla: Yes, definitely. If we get an opportunity, then we will take it.
Question
Vaibhav Shah: Despite the payments being an issue for quite some time in last couple of years, we are still open?
Answer, sanjay pusarla
Sanjay Pusarla: Yes, we do not expect the same kind of problems or same kind of tightness will be there in release of payments by the government. Because now the governments are coming up, like in AP, they are coming up, and some other places also they are coming up with the JJM scheme.
Show 20 more questions
Question
Vaibhav Shah: Okay, got it. Secondly, on the Vizag land sale, you mentioned that INR270 crores is outstanding. So by when do we expect to recover it?
Answer, sanjay pusarla
Sanjay Pusarla: We expect by end of the quarter four, we will be able to complete this.
Question
Vaibhav Shah: Okay. Lastly on the smart meter thing, what is the outstanding order backlog right now for smart meter?
Answer, sanjay pusarla
Sanjay Pusarla: Yes, it is almost like 51% we have completed installation, and 49% is outstanding.
Question
Vishal Periwal: That's good to hear, sir. And then maybe one bookkeeping. I think unbilled revenue, it has come down on a quarter basis this quarter, but last two, three years we have seen an increase. So I think broadly you mentioned 2,000 is coming from JJM. Is it possible to get what exactly is this stickiness or probably anything color that can be provided regarding unbilled revenue, sir?
Answer, sanjay pusarla
There is no sticky unbilled revenue. The unbilled revenue is progressively realizing. But we expect that we maintain maybe a similar type of unbilled revenue in the days to come. Page 10of 17 NCC Limited November 06, 202 6 Vishal Periwal: Okay.
Question
And maybe if I can just ask one last question. What is the outstanding in BharatNet for us in terms of order book, and probably what kind of execution we have done quarterly this quarter for BharatNet?
Answer, sanjay pusarla
Sanjay Pusarla: We have done almost like 11% of the total contract we have executed in both MP and Uttarakhand. We have almost spent about INR1,000 crores on its work, and we have started billing now. The unbilled revenue, as I said, that is also there. Especially in the BharatNet projects, the lead time for conversion from billing, from execution to billing and realization is little longer.
Question
Hrishali Shah: Yes. Thank you for the opportunity. I wanted to ask more on smart meter end. I would want to understand what kind of payment cycle are we seeing there? Is there any working capital challenges we are facing on that side?
Answer, sanjay pusarla
Sanjay Pusarla: No, we do not see any working capital challenges in the smart meters execution. Smart meters, when we are executing, the payment will be in two phases. One is earlier, first on installation of the smart meters, we get some amount of payment, and the balance amount we will get over 83 months after the installation. Management: 93.
Question
Hrishali Shah: Okay. Second question is on AP Capital City. What kind of receivables is outstanding right now, and what order book are we looking at on that front?
Answer, sanjay pusarla
Sanjay Pusarla: But as far as the receivables are concerned, we are not facing any challenge. Whatever work we are executing, we are getting realization. Between 30- 40 days, we are getting realization. So that is not a problem. When it comes to the order book, I just give you what is the amount of order book. INR14,500 crores is the order book for the AP. Page 11of 17 NCC Limited November 06, 202 6 Hrishali Shah: Okay.
Question
Parth Thakkar: Yes, sir. What would be our JJM payment in the first half?
Answer, sanjay pusarla
Sanjay Pusarla: In the first half, we received about INR1,720 crores .
Question
Parth Thakkar: Okay. My last question, do we see any impact of higher raw material prices on our margins?
Answer, sanjay pusarla
Sanjay Pusarla: 81% of our contracts have got the escalation clauses. Any increase in the prices will majorly offset from the price variation clauses that are available.
Question
Shravan Jain: Thanks for the opportunity. My question is that since 60% of your clients are PSUs, could you explain your billing process, the average collection period, and whether any retention amount is withheld from the payments?
Answer, sanjay pusarla
Sanjay Pusarla: As per the contract, retention monies are from 5%-10%, and each of the running bill, when they are processed, they will hold the retention money, and that money will be released only after completion of the contract partially, and balance they will release it after completion of the DLP period. Generally, in the government clients, the payment cycles ranges between 50-60 days from the date of certification.
Question
Pankaj Kumar: Yes, thanks for taking my question, and congrats on good set of numbers. Sir, on the JJM project, what is the total outstanding order book as of now?
Answer, sanjay pusarla
Sanjay Pusarla: INR5,413 crores. Page 12of 17 NCC Limited November 06, 202 6 Pankaj Kumar: Earlier, we indicated that we will try to complete large part of this order backlog in the current financial year.
Question
Pankaj Kumar: Okay. Since we have already received around INR11,000 crores of orders, and we have guided for INR22,000 crores-INR25,000 crore s of inflows, can we assume, because normally H2 we get the larger part of the orders, are we on track to exceed our guidance or may achieve upper end of the guidance? If you can comment on the new order inflows guidance.
Answer, neerad sharma
Neerad Sharma: See, you are absolutely right that we have shared the order inflow guidance, a band, INR22,000 crores-INR25,000 crore s. If we take into account the projects that we have bagged in the month of October, the total inflow is about INR11,108 crores, which is about 50% of the lower band. This itself gives us the confidence that we are on our way to achieve the band of the order inflow guidance that we have shared with the street. We retain that guidance, and hopefully, we will achieve that number.
Question
Pankaj Kumar: Ken-Betwa project. I mean, there were some issues earlier regarding land acquisition from there. Any update on river linking project?
Answer, neerad sharma
Neerad Sharma: No, we are making reasonable progress on the Ken-Betwa sites. The land acquisition issue or demonstration that you are alluding to was at a place that was at a distance of 30, 40 km away from our project site. We are happy to share with you that we are making reasonable progress on this project.
Question
Shravan Shah: In terms of the depreciation, how it will inch up from this quarter INR73-odd crore s, as it inched up by INR3 crores-INR 4 crores on Q-o -Q business. So, will it keep on inching up, or will it be a sizable increase in third and fourth quarter?
Answer, sanjay pusarla
Sanjay Pusarla: It is like this. The TBM machine was capitalized and put to use in the month of September. From September, that means second quarter of this year. Definitely, the depreciation is going to go up in the third quarter and fourth quarter. Besides the TBM, we also have got the mining project where we are executing, where it is a capital intensive. There also the depreciation will come into play. Hence, the depreciation is going to inch up in the subsequent quarters.
Answer, rs raju
RS Raju: Hello. The point here to be noted is, in absolute terms, the depreciation cost increases quarter- to-quarter, basing on the new orders, basing on the new capex already taken place, and also the capex take place in the rest of the quarters. However, in terms of percentage, the same reading is maintainable. 1.48% is given. That is maintainable.
Question
Shravan Shah: Okay. But this TBM and mining one, will that depreciation be a part of standalone or will it be a part of the consol?
Answer, rs raju
RS Raju: No, here mining is inclusive of this 1.48. The mining project is in a standalone project.
Answer, sanjay pusarla
Sanjay Pusarla: Even TBM also is a standalone. Both will come under the standalone only.
Question
Saket Kapoor: Yes, good. Yes , sir. Good afternoon, sir. Thank you firstly, sir, for updating the investor presentation, especially the smart meter part of the story. We have been given more information, just to add to it, sir, if going ahead, even for the Jal Jeevan part, which has been a sticky issue, I think so now resolution on the way, if you could further give us the understanding pertaining to the questions that are being asked. That will also suffice lot of questions in terms of the legacy part, the execution, receivables, the new addition, then the execution of the same. That would give us some more understanding how we are moving ahead, firstly. So sir, firstly, do you have the bre
Answer, sanjay pusarla
I think it's very good to hear from you that we have improved our presentation on smart meters. Jal Jeevan is like a standalone project. Once the projects are getting executed, it will be over. The legacy issue is what the Jal Jeevan we were facing, I think they are coming to an end. If you ask me, the legacy part of the Jal Jeevan, if you see that, it is INR3,200 crores is the balance which is there available in the legacy Jal Jeevan projects, which we are expecting to substantially complete by March 2027. The current projects is about INR2,128 crores, where we are making good progress and the payments are also progressively coming now.
Question
Saket Kapoor: Yes, it's a big project, I think, some few billion dollars. How much are we?
Answer, neerad sharma
Neerad Sharma: Mr. Kapoor, I think Ken-Betwa, we are the first ones to bag the first ever project that was awarded for the Ken-Betwa part.
Question
Saket Kapoor: What is the value? Anyway, we can take it offline also. Now, sir, for the financial question, firstly, sir, investment property under construction, this value of INR108 crores, what does it signify? Going ahead, how will this number shape up? Secondly, sir, if you could explain to us, what is the nature of unbilled revenue and how it impacts our finances? The numbers which we report, I think so in the presentation also about March, then June, and then September. Its significance and how is this going to trend? These two questions, sir.
Answer, sanjay pusarla
Sanjay Pusarla: This INR107 crores investment relates to a project in Hyderabad. We have invested in that project, and the project is in midway. It was stopped, and the developer is in a little problem. There was an issue with the RERA also. RERA has canceled the project or kept the project on hold. We are also taking up with RERA along with other people who are there in the project. We expect that this problem will get resolved over a period of time.
Answer, sanjay pusarla
We are not very sure that how much time it will take, because it is a judicial matter before the NCLT. That is the reason Page 15of 17 NCC Limited November 06, 202 6 we are not sure that how much time it will take. Definitely, the amount of investment is completely secured. There is no problem in recoverability of this investment. Second one is on the Ken-Betwa. You were asking what is the value of the contract. It was INR3,389 crores, which is the value per the NCC to be executed.
Answer, sanjay pusarla
You are asking unbilled revenue. Unbilled revenue as per the standard Ind AS 115, what we need to do is that whatever money we have spent and we have completed our obligation and not billed because of the certification, that amount whatever is there need to be recognized in unbilled revenue. That is the reason unbilled revenue will come into the place and it will be added as a contract revenue for us.
Question
Saket Kapoor: Okay. Lastly, sir, what is this other financial liability of INR8,163 crores, which goes into the consolidated accounts under the current liability?
Answer, sanjay pusarla
Sanjay Pusarla: That is the financial asset of the smart meters. Because smart meters is a HAM project, it has to be accounted under the financial liability. Whatever that money is there, that is accounted under the other financial liabilities. Financial liability. Yes .
Question
Saket Kapoor: Lastly to the CWIP also, sir. I joined the queue after this that our current work in progress closing balance is INR92 crores . What do we attribute this amount to? For the second half, what is the capex that we have outlined?
Answer, sanjay pusarla
Sanjay Pusarla: Second half capex is overall capex is INR500 crores and INR253 crores we have already spent in the first half. Probably the balance INR 250 crores we will be spending in the second half.
Question
Saket Kapoor: I will take it offline. Sir, for this quarter, our subcontractor work bills have gone up, if we take the number on June. How are these numbers comparable? Also on the finance cost, that is also moving inching up on an every quarter basis. So what should we look at this number as a run rate or a percentage of sales, sir, going ahead?
Answer, sanjay pusarla
Sanjay Pusarla: The percentage will be around 9.21 finance cost.
Questions about this call
- When was the NCC Q2 FY27 earnings call transcript filed?
- NCC filed the transcript with the exchange on 10 Nov 2026. This page is built from that transcript.
- What does this page list?
- 45 statements from the transcript across 7 topics, 29 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 30 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.