Earnings call
NCC Q4 FY25 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Order book was INR71,568 crores, its FY '25 order bookings were INR 32,888 crores, about 50% more than the upper band of its guidance, standalone revenue increased by 5%, and its EBITDA margin was 9.1%, in line with the guidance shared with the Street. For FY '26, NCC Limited gave guidance for order inflow of INR 22,000 crores to INR 25,000 crores, revenue growth of 10%, and an EBITDA margin between 9% to 9.25%; it said its prospective pipeline was about INR 2.55 lakh crores. The company said that about 20% of households remained to be provided with portable water connections under the Jal Jeevan Mission. Standalone turnover in Q4 was INR5,376 crores, against INR5,446 crores in the previous year. Debt at the beginning of the year was INR 1,005 crores and net debt after cash and cash equivalent was INR 517 crores; at the end of quarter 4, debt was INR 1,484 crores and net debt was INR 710 crores, compared with debt of INR 2,415 crores and net debt of INR 2,344 crores at the end of quarter 3.
The numbers management gave
Results
- Standalone turnover in Q4 was INR5,376 crores, against INR5,446 crores in the previous year.
Show source
Turnover reported in Q4 is INR5,376 crores as against turnover of INR5,446 crores in the previous year.
- Standalone turnover during the 12 months was INR 19,205 crores, against INR 18,314 crores in the previous 12 months.
Show source
During the 12 months, turnover is INR 19,205 crores as against INR 18,314 crores, which is reported in the previous 12 months.
- Standalone turnover in Q4 was INR 6,131 crores, against INR6,485 crores in the previous year.
Show source
Turnover reported in Q4 is INR 6,131 crores against the turnover of INR6,485 crores in the previous year.
- Standalone turnover during the 12 months was INR 22,199 crores, against INR 20,845 crores, showing growth of around 7%.
Show source
During the 12 months, the turnover is INR 22,199 crores as against INR 20,845 crores, showing a growth of around 7%.
- Standalone EBITDA margin in Q4 was 9.21%, against 9.36% in the corresponding quarter of the previous year.
Show source
We achieved EBITDA margin of 9.21% for Q4 as against 9.36% of the corresponding quarter of the previous year.
- Standalone EBITDA for the 12 months of the financial year '25 was 9.09%, against 9% in the 12 months of the previous year.
Show source
And for the 12 months of the financial year '25, we achieved EBITDA of 9.09% as against 9% in 12 months of the previous year.
Show 32 more statements
Results
- Standalone PBT was 6.2% and PAT was 3.94% in Q4, against PBT of 6.29% and PAT of 3.41% in the corresponding period.
Show source
PBT, we achieved 6.2% and PAT we achieved 3.94% in the current quarter, that is Q4 as against PBT of 6.29% and PAT of 3.41% of the corresponding period.
- Consolidated EBITDA was 9.7%, PBT was 5.95% and PAT was 4.28% in Q4, against EBITDA of 8.49%, PBT of 5.97% and PAT of 3.66%.
Show source
We achieved EBITDA of 9.7% and PBT of 5.95% and PAT of 4.28% in the current quarter, that is Q4; as against EBITDA of 8.49%, PBT of 5.97% and PAT of 3.66%.
- ROCE was 14.61% at the end of the financial year '25, against 14.04% at the financial year '24 end.
Show source
And coming to the investor-related ratios, the ROCE stands at 14.61% as against 14.04% at the financial year '24 end.
- EPS was INR 12.10 at the end of Q4, against INR 10.10 in the last year.
Show source
And EPS stands at INR 12.10 as at the end of Q4 against INR 10.10 in the last year.
- The company delivered 5% growth in revenue last year, compared with its guidance to the market of about 15% growth.
Show source
The last year, we had guided the market for about 15% growth, but we have been able to deliver only 5% growth, right?
- Jal Jeevan Mission projects progressed slowly over the last 7 to 8 months because of delayed payments by the client, particularly Jal Jeevan payments by the central government; the company received some part payment in the last 2 to 3 months, but about INR 1,000 crores remained to be received.
Show source
Now -- we received some part payment in the last 2, 3 months, but still about INR 1,000 crores are yet to receive it.
- The company bagged many projects in the fourth quarter of financial year 2024-'25, and mobilizing a project, obtaining land and putting the required ROWs in place takes about 3 to 4 months, delaying the start of billing after project award.
Show source
So, it takes about 3, 4 months time to mobilize the project, get the land, get all the ROWs in place.
- The company received some of the INR 147 crores previously outstanding for capital city projects and has INR 110 crores outstanding at the moment for capital city projects where there was an issue.
Show source
Out of that INR 147 crores, we received some, and we are -- the outstanding at the moment is INR 110 crores for the capital city projects where there was an issue.
- Net working capital improvement in 4Q '25 was due to JJM payment, which the company expected to come in.
Show source
Sanjay Pusarla: No, it was the JJM payment, we are expecting that to come in now.
- Other income in FY '25 included almost INR 44 crores in dividends from Pachhwara and income from the sale of flats in Bangalore.
Show source
Sanjay Pusarla: Other income in FY '25, one is on the dividend, which is almost like INR 44 crores, but that has come from Pachhwara.
- Payments for NCC Limited's Jal Jeevan Mission projects are getting delayed.
Show source
Sanjay Pusarla: Payment is a little getting delayed.
- Execution is impacted when clients do not make the required land, permissions and drawing approvals available.
Show source
So unfortunately, this is something that is going to impact our execution.
- Execution depends on clients certifying bills and making payments on time.
Show source
The third important point is our -- the ability of the clients to make payments, certify bills on time, make payments on time.
- The company will not be able to execute a larger share of its order book unless clients certify bills and make payments on time.
Show source
So, unless those things are in place, we will not be able to really execute from larger share from our order book.
- Projects generally have lower EBITDA and gross margins than the industry because its project mix does not contain many machinery-oriented projects.
Show source
As a result, our EBITDA margin and gross margin is generally low compared to the Page 11of 18 NCC Limited May 16, 202 5 industry level.
Money and capital
- Debt at the beginning of the year was INR 1,005 crores and net debt after cash and cash equivalent was INR 517 crores; at the end of quarter 4, debt was INR 1,484 crores and net debt was INR 710 crores, compared with debt of INR 2,415 crores and net debt of INR 2,344 crores at the end of quarter 3.
Show source
At the end of quarter 4, it stood at INR 1,484 crores and net debt of INR 710 crores.
- Net debt reduced from INR 2,344 crores at the end of Q3 to INR 710 crores at the end of Q4, and debt decreased by INR 931 crores.
Show source
That means the net debt from Q3 ending to Q4 is reduced from INR 2,344 crores to INR 710 crores.
- Debt-to-equity ratio was 0.2% at the end of Q4, against 0.33% at the end of Q3 and 0.15% at the end of March '24.
Show source
The debt-to-equity ratio stands at 0.2% at the end of Q4 as against 0.33% at the end of Q3 and 0.15% at the end of March '24, w orking capital.
- Working capital, excluding cash and margin money deposits, was INR4,374 crores at the end of Q4, equal to 17% of turnover, and working capital days were 77 days.
Show source
At the end of Q4, it stands at INR4,374 crores, which is 17% of the turnover.
- Receivables outstanding at the end of Q4 reduced from INR 3,142 crores to INR3,098 crores, and receivables days decreased from 74 days to 65 days in the current quarter.
Show source
Debtors i.e. receivables, outstanding at the end of Q4 has reduced from INR 3,142 crores to INR3,098 crores, and the number of days also decreased from 74 days to 65 days in the current quarter and unbilled revenue.
- Unbilled revenue stood at INR 5,937 crores, 31% for Q4, against INR6,151 crores, 33% at Q3 ending.
Show source
It stands at INR 5,937 crores, which is 31% for Q4 as against INR6,151 crores, which is 33% at Q3 ending.
- Mobilization advances stood at INR 2,098 crores against INR1,977 crores in Q4, an increase of INR 120 crores, and were 11% of turnover; 79% were interest-bearing and 21% interest-free, with an average interest rate of 9.52% on the interest-bearing advances.
Show source
The mobilization advances stood at INR 2,098 crores as against INR1,977 crores in Q4, increased by INR 120 crores.
- The company incurred capex of INR305 crores in the current financial year, against budgeted capex of INR250 crores for the regular projects.
Show source
We have incurred a capex of INR305 crores in the current financial year as against the budgeted capex of INR250 crores for the regular projects.
- The company decided to declare a dividend of 110%, which will be INR 2.20 per share, with a total outflow of INR 139 crores.
Show source
So as far as the dividend is concerned, this year, it was decided to declare a dividend of 110%, which will be INR 2.20 per share.
- Capex for FY '26 is INR 750 crores.
Show source
And capex for FY '26 is at INR 750 crores.
- Investment in subsidiaries and associates was INR 1,065 crores, compared with INR 1,033 crores.
Show source
Investment is INR 1,065 crores as against INR 1,033 crores.
- Capex was somewhere around INR 305 crores last year; this year it expects a TBM for the Mumbai tunnelling project, expected to cost around INR300 crores, and expects to invest the remaining money in other projects.
Show source
That itself is around INR300 crores.
- The company will fund the INR 300 crores TBM investment from its stand-alone books, and both partners are buying one TBM each and deploying them from the owner side.
Show source
Sanjay Pusarla: Yes, it will be done in the stand-alone books.
- The smart meter project requires total investment of about INR280 crores; NCC Limited expects to invest around INR130 crores by Q2, with the balance dependent on financial closure.
Show source
Sanjay Pusarla: About INR280 crores is the total investment that need to be made.
- The company is relying on bank loans at around 9% to 9.3% instead of mobilization advances when their cost exceeds 11% or 12%; this was one reason debt increased in the year '24-'25, and debt may slowly rise by about INR 200 crores to INR 300 crores every year in the coming years.
Show source
And also in the coming years, the debt may s lowly rise up about INR 200 crores to INR 300 crores every year.
- Interest-bearing advances increased from 53% in '23 to 79% at the end of FY '25; management said this was the main reason the company opted for debt rather than interest mobilization advances.
Show source
As we pass and now at the end of FY '25, the interest-bearing advances are 79%.
- At the end of FY '25, the costing for NCC Limited's mobilized advances was much higher than what it was getting from lenders.
Show source
And the mobilized advances, today, they carry interest and the costing for the mobilized advance at the end of the day is much higher than what we are getting from the lenders.
What it expects ahead
What management expects
- For FY '26, NCC Limited gave guidance for order inflow of INR 22,000 crores to INR 25,000 crores, revenue growth of 10%, and an EBITDA margin between 9% to 9.25%; it said its prospective pipeline was about INR 2.55 lakh crores.
Show source
We have a prospective pipeline of about INR 2.55 lakh crores, and we are pleased to share with you a guidance of INR 22,000 crores to INR 25,000 crores for the order inflow.
- The company said its FY '26 revenue growth guidance of 10% was a handsome growth compared with growth of 5% in the previous year.
Show source
So, when we talk about 10% growth for FY '26, there is a handsome growth, right?
- 10% growth guidance depends on how the government advances the infrastructure segment, how payments are made, client cooperation in execution, and the gestation period of new projects; the company also considered the previous year's Jal Jeevan Mission project experience.
Show source
So, considering all these things, we gave the guidance of 10%.
- The company is looking for improvement at the bottom line, while its EBITDA margin depends on the mix of projects; its larger BSNL project, including O&M, is about INR10,000 crores to INR 11,000 crores.
Show source
So, at this moment, the larger size projects, what we taken up for BSNL about -- including O&M about INR10,000 crores to INR 11,000 crores project.
- The company expects improvement at the bottom line, but not at the EBITDA level, in the next 2 years because its project mix has little capex investment and it does not have a major portfolio of roads.
Show source
So going forward in the next 2 years, we expect an improvement at the bottom line, but not at the EBITDA level.
- Interest cost may increase by another 4% to 5% in FY '26.
Show source
The interest cost may go by another 4% to 5%.
Show 31 more statements
What management expects
- The company said its revenue growth guidance reflected uncertainty in the environment in which it operates and depended primarily on timely payments by clients and how much working capital the company commits.
Show source
So, this is the reason we have shared this guidance with you.
- The company hopes some of its L1 projects will convert into firm orders in the coming quarters.
Show source
Some of those L1 projects, we hope will get converted in the coming quarters.
- Maharashtra smart meter projects had moved slowly last year, but the company has received all clearances to execute them and expects good turnover in the current year.
Show source
But now we have got all the clearances to execute them, and we are showing good progress in these projects, expecting a good turnover in the current year.
- The company expects the provision of portable water connections to lead to wastewater treatment plant and STP projects, and is hopeful that these two sub-verticals will see traction.
Show source
So, we are quite hopeful that going forward, these 2 sub verticals should see some traction.
- The company believes a good number of transportation projects will come up for bidding.
Show source
And we believe that we will see a good number of projects coming up for bidding in transportation segment.
- The company expects some movement and new projects to come up for bidding in the capital city.
Show source
So, we expect to see some movement, some new projects that might come up for bidding in the capital city.
- The company understands that a few projects in the capital city project might come up for bidding this year, but it has to wait and watch.
Show source
We understand that a few projects might also get -- come up for bidding, let's say that, come up for bidding this year as well, but we have to wait and watch.
- The company expects that arranging some CPs and using trades and purchase invoice discounting may bring some savings in the current year.
Show source
We are hopeful that it may bring some savings in the current year.
Orders
- Order book was INR71,568 crores, its FY '25 order bookings were INR 32,888 crores, about 50% more than the upper band of its guidance, standalone revenue increased by 5%, and its EBITDA margin was 9.1%, in line with the guidance shared with the Street.
Show source
We are sitting at the highest ever order book of INR71,568 crores.
- Buildings division had an order book of INR 22,440 crores, about 31% of its total order book.
Show source
We have an order book of INR 22,440 crores.
- Transportation division had an order book of INR17,929 crores, about 25% of its total order book.
Show source
In the Transportation division, we have an order book of INR17,929 crores, which is about 25% of our total order book.
- Electrical T&D division had an order book of INR 16,666 crores as of 31st March, about 23% of its order book.
Show source
Let me repeat, INR 16,666 crores as of 31st March, which is about 23% of our order book.
- Irrigation division had an order book of INR 4,189 crores, about 6% of its order book.
Show source
The order book in the Irrigation division is INR 4,189 crores; I repeat, INR 4,189 crores, which is about 6% of our order book.
- Water division had an order book of INR4,782 crores, 7% of its order book.
Show source
In our Water division, we have an order book of INR4,782 crores, which is 7% of our order book.
- Mining division had an order book of INR 5,555 crores, about 8% of its total order book.
Show source
Similarly, the order book in our Mining division is INR 5,555 crores, which is about 8% of our total order book.
- The company had L1 projects worth about INR 7,000 crores to INR 8,000 crores as of the call.
Show source
As of now, we have an L1 project of about INR 7,000 crores to INR8,000 crores.
- Transportation accounted for about 25% of NCC Limited's total order book, valued at INR 17,929 crores.
Show source
In terms of value, it is INR 17,929 crores.
- Andhra accounts for somewhere around INR 9,500 crores of NCC Limited's overall order book.
Show source
Sanjay Pusarla: It's somewhere around INR 9,500 crores.
- Andhra accounts for INR8,900 crores of NCC Limited's overall order book.
Show source
Neerad Sharma: INR8,900 crores.
- The company has taken around INR 7,127 crores into its current order book; O&M execution after the capex portion is not included, and the order book generally considers only work executable in the next 3 years.
Show source
Out of that, around INR 7,127 crores, I think we have taken in the current order book.
- Almost all the Andhra capital city project orders were received in FY '25 last quarter; INR 600 crores, INR700 crores were received in the April month.
Show source
INR 600 crores, INR700 crores we received in the April month.
- The Ken-Betwa project accounts for around INR4,000 crores of NCC Limited's INR71,000 crores order book.
Show source
What we explained INR71,000 crores, in that INR 4,000 crores are there.
- Of NCC Limited's INR32,888 crores in orders, buildings contributed 26%, or INR 8,447 crores.
Show source
The number is INR 8,447 crores.
- Of NCC Limited's INR32,888 crores in orders, the Transportation division contributed 24%, or INR7,837 crores.
Show source
The value is INR7,837 crores.
- The company received INR 3,338 crores in mining orders, accounting for 10% of order inflow.
Show source
Neerad Sharma: We have made INR 3,338 crores, 10%.
- Order book was Rs.71,568 cr.
Show source
After execution of INR 21,756 crores of work during the 12 months, the order book stands at INR71,568 crores.
- Awards have come from a variety of projects, and metro projects involve both state and central governments as partners.
Show source
Neerad Sharma: The awards that we have got are from a variety of the projects in most of the projects.
- The company has not been very successful in NHAI projects in the past.
Show source
NHAI, unfortunately, we have not been very successful in the NHAI projects in the past.
- The company does not include O&M in its order book until the EPC construction part is done.
Show source
We have not considered O&M in our order book.
- L1 orders are not for the capital city project; they are from all these states put together.
Show source
This is from the -- all these states put together.
- The Ken-Betwa project is part of NCC Limited's order book.
Show source
Sanjay Pusarla: Ken-Betwa is a part of the order book.
What it is building and selling
Projects and capacity
- The company said that about 20% of households remained to be provided with portable water connections under the Jal Jeevan Mission.
Show source
So, this is the update on the Jal Jeevan mission.
- The company had invested about INR 70 crores in smart meter projects.
Show source
We've invested about INR 70 crores in the smart meter projects.
- Total investment to be made in smart meters was INR 280 crores.
Show source
It was INR 280 crores, the total investment needs to be made.
- The Pachhwara coal mining project, which NCC Limited is executing with another joint venture partner, had achieved its rated capacity of 15 million tons per annum; NCC Limited said it was in a position to produce more than 15 million tons in a year and was trying to increase production.
Show source
The Pachhwara coal mining projects where we are executing along with other joint venture partner, almost we have achieved the rated capacity of 15 million tons per annum, that already we achieved.
- West Bengal Power Development Corporation Limited had environment clearance for 15 million tons per year and was trying to enhance the capacity to about 18 million tons, with further increases based on its coal requirements and demand for its power projects.
Show source
And West Bengal Power Development Corporation Limited, they have the environment clearance for 15 million tons per year.
- The company said it could produce more than 15 million tons once West Bengal Power Development Corporation received environment clearance for more than 15 million tons.
Show source
So once the West Bengal Power Development Corporation, that is the client receives that environment clearance for more than 15 million tons , so we're able to produce that one.
Show 15 more statements
Projects and capacity
- The second village's R&R activity for the Pachhwara coal mining project was in progress, and West Bengal had awarded NCC Limited the civil work to build houses for that village; NCC Limited expected to complete the work in 6 to 9 months.
Show source
And the second village is in progress and West Bengal already awarded the civil work to build the houses for the villages of the second village.
- The second village in the Pachhwara coal mining project was to shift to the new houses, leaving NCC Limited with a work front to produce 15 million tons or more, as required by West Bengal.
Show source
So as of this moment and work front is available to do the 15 million tons or more than 15 million tons, whatever West Bengal requires for that one.
- The company said the railway siding was the biggest issue for the Pachhwara coal mining project; West Bengal Power Development Corporation had not awarded the contract to lay the railway line from 50 kilometres to the pit mouth, so coal was still being transported by road and NCC Limited had developed alternative railway sidings.
Show source
And so far, the contract is not awarded to lay the railway line that has to come from 50 kilometres to the pit mouth.
- The company was transporting coal by road through three routes, including two alternative railway sidings, to meet the coal mining project's 50 million tons requirement.
Show source
And at this moment, coal transportation also going and meeting the requirement of the 50 million tons .
- About two-thirds of NCC Limited's Jal Jeevan projects were completed, while one-third remained pending.
Show source
R. S. Raju: About 2/3 of the Jal Jeevan projects were completed.
- Financial closure for NCC Limited's Ray smart meter project was achieved last year, and the company has started running the load.
Show source
Sanjay Pusarla: So, in financial closure for smart meters in the case of Ray, that is already achieved in the last year itself, and we have started running the load.
- Financial closure for NCC Limited's Marathwada smart meter project is yet to happen; the company has received a term sheet from lenders and is yet to proceed to financial closure.
Show source
We are yet to go for the financial closure.
- The company received instructions from the government to increase the pace of execution on its Maharashtra projects, and the government and client have given a green signal to proceed aggressively after all tests were completed.
Show source
Now we have got a very good -- green signal from the government also, from the client also to go aggressively on these projects.
- The company said work and execution at its Andhra Pradesh state capital project sites were progressing well, with clients demanding faster execution.
Show source
And we also feel the same thing from the execution from our teams also that there is a lot of demand from the clients to execute the projects at a very fast pace.
- The GMLR project has received all clearances, and work has started on the approach roads, facilities for the casting yard, the TBM landing station and the cut-and-cover portion.
Show source
Sanjay Pusarla: GMLR project, they have got all the clearances.
- The company completed the first village's R&R activity for the Pachhwara coal mining project and took that village's land out of the project.
Show source
At this moment, the other milestones to fulfil the R&R activity, first village R&R we have completed and accordingly, the land of that village taken out into the project.
- The company has bid for the Ken-Betwa project, and its division has started survey work, mobilized resources, established the site camp and mobilized equipment; work was as per schedule while clearances and permissions were being pursued.
Show source
R. S. Raju: Yes, the Ken-Betwa project, we have bided and already the division started the work, now in the survey work and mobilizing the resources, establishing the site camp and mobilizing the required equipment and all these things are going on.
- The company planned to begin the Ken-Betwa project's real physical work from September onwards.
Show source
And from September onwards, the real physical work will move.
- The company has the required people and machinery to execute its projects. Replaced by a later filing.
Show source
So, this we do have.
Deals and partners
- The company is currently the sole investor in the smart meter project and is looking for partners.
Show source
Sanjay Pusarla: At the moment, it is only the investment from NCCL, and we are on the lookout for the partners.
Everything else said on the call
Group structure
- The company has completely received back its investment and equity in the Vizag land; it received about INR 15 crores from the loan in the current year, expects to receive about INR 120 crores in the next year, and will receive the balance thereafter.
Show source
And whatever loan is there, out of the loan also, we received about INR 15 crores in the current year, expect to receive about INR 120 crores in the next year, balance thereafter.
- The total balance on the Vizag land receipts, including interest, is about INR 375 crores.
Show source
Sanjay Pusarla: It's including interest about INR 375 crores.
- The company created an impairment on its Oman subsidiary because it felt it may not be able to realize what it had invested there.
Show source
So, we have created an impairment of that.
- The company started an LLP to produce specialized concrete girders.
Show source
And we also have another LLP, which we have started for producing some specialized concrete girders.
Other
- The company receives money on time for running projects, and execution is happening on the basis of realization. Replaced by a later filing.
Show source
Sanjay Pusarla: Running projects, we are getting the money realization on time.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Vaibhav Shah: Thank you. On behalf of JM Financial, I welcome everybody to 4Q and FY '25 Earnings Conference Call of NCC Limited. We have from the management today Shri R.S. Raju, Director of Projects; Shri Sanjay Pusarla, Executive Vice President; and Shri Neerad Sharma, Head Strategy and Investor Relations. Now, I hand over the call to the management for opening remarks, post which we can do the Q&A session. Over to you, sir.
Answer, neerad sharma
In the second part, our CFO will give a brief about the financial performance of the company for the fourth quarter and for the financial year '25. In the third and last part, we will attempt to answer all your questions and clarifications. We are happy to share with you the fact that we have achieved the revised guidance shared with you in the last earnings call. We are sitting at the highest ever order book of INR71,568 crores. And in the financial year FY '25, we have booked orders worth INR 32,888 crores, which is about 50% more than the upper band of our guidance shared with you. The revenue on a stand-alone basis increased by 5%, which is in line with the guidance that we have shared with the Street. The EBITDA margin was 9.1%, which is closely in line with the Page 2of 18 NCC Limited May 16, 202 5 guidance that we had shared with you.
Answer, neerad sharma
For the FY '26, that is the current financial year, we are seeing a healthy pipeline of future projects. We have a prospective pipeline of about INR 2.55 lakh crores, and we are pleased to share with you a guidance of INR 22,000 crores to INR 25,000 crores for the order inflow. I repeat the order inflow guidance for the FY '26 is INR 22,000 crores to INR 25,000 crores. The revenue growth of 10% and EBITDA margin between 9% to 9.25%. Now I will very briefly touch upon a few of our large divisions. In our Buildings and Transportation division, we continue to see good traction and healthy pipeline of projects. We have an order book of INR 22,440 crores.
Answer, neerad sharma
I repeat, INR 22,440 crores in the Buildings division, which is about 31% of our total order book. In the Transportation division, we have an order book of INR17,929 crores, which is about 25% of our total order book. The third large division that we have is Electrical T&D. Order book as of end of March is INR16,666 crores. Let me repeat, INR 16,666 crores as of 31st March, which is about 23% of our order book. The order book in the Irrigation division is INR 4,189 crores; I repeat, INR 4,189 crores, which is about 6% of our order book. In our Water division, we have an order book of INR4,782 crores, which is 7% of our order book. Similarly, the order book in our Mining division is INR 5,555 crores, which is about 8% of our total order book.
Answer, neerad sharma
Our order book stands at INR 71,568 crores as at the end of March '25. As you are aware, the order book at the beginning of the year stood at INR 60,437 crores and orders received during the 12-month period is INR32,888 crores, which is the highest orders we have ever received in a financial year. And in Q4, we received orders around INR 19,280 crores. After execution of INR 21,756 crores of work during the 12 months, the order book stands at INR71,568 crores. Coming to the revenues, standalone. Turnover reported in Q4 is INR5,376 crores as against turnover of INR5,446 crores in the previous year. During the 12 months, turnover is INR 19,205 crores as against INR 18,314 crores, which is reported in the previous 12 months.
Answer, neerad sharma
This will record a 5% growth over the previous year. Coming to the standalone. Turnover reported in Q4 is INR 6,131 crores against the turnover of INR6,485 crores in the previous year. During the 12 months, the turnover is INR 22,199 crores as against INR 20,845 crores, showing a growth of around 7%. Page 3of 18 NCC Limited May 16, 202 5 Coming to the profitability, stand-alone. We achieved EBITDA margin of 9.21% for Q4 as against 9.36% of the corresponding quarter of the previous year. And for the 12 months of the financial year '25, we achieved EBITDA of 9.09% as against 9% in 12 months of the previous year.
Answer, neerad sharma
PBT, we achieved 6.2% and PAT we achieved 3.94% in the current quarter, that is Q4 as against PBT of 6.29% and PAT of 3.41% of the corresponding period. Coming to the consolidated profitability. We achieved EBITDA of 9.7% and PBT of 5.95% and PAT of 4.28% in the current quarter, that is Q4; as against EBITDA of 8.49%, PBT of 5.97% and PAT of 3.66%. Coming to the debt movement. The debt at the beginning of the year stood at INR 1,005 crores and net debt after cash and cash equivalent standing at INR 517 crores. At the end of quarter 4, it stood at INR 1,484 crores and net debt of INR 710 crores. And at the end of quarter 3, the same debt was INR 2,415 crores and net debt was INR 2,344 crores.
Answer, neerad sharma
That means the net debt from Q3 ending to Q4 is reduced from INR 2,344 crores to INR 710 crores. There is a decrease in debt by INR 931 crores. The debt-to-equity ratio stands at 0.2% at the end of Q4 as against 0.33% at the end of Q3 and 0.15% at the end of March '24, w orking capital. Working capital, excluding cash and margin money deposits. At the end of Q4, it stands at INR4,374 crores, which is 17% of the turnover. In terms of working capital days, it counts for 77 days. Debtors i.e. receivables, outstanding at the end of Q4 has reduced from INR 3,142 crores to INR3,098 crores, and the number of days also decreased from 74 days to 65 days in the current quarter and unbilled revenue.
Answer, neerad sharma
It stands at INR 5,937 crores, which is 31% for Q4 as against INR6,151 crores, which is 33% at Q3 ending. Coming to the mobilization advances. The mobilization advances stood at INR 2,098 crores as against INR1,977 crores in Q4, increased by INR 120 crores. It is standing at 11% of the turnover. Of these mobilization advances, 79% are interest-bearing and 21% are interest -free. The average interest rate works out to 9.52% on these mobilization advances, which are interest bearing. Coming to the capex .
Answer, neerad sharma
We have incurred a capex of INR305 crores in the current financial year as against the budgeted capex of INR250 crores for the regular projects. So as far as the dividend is concerned, this year, it was decided to declare a dividend of 110%, which will be INR 2.20 per share. Total amount of outflow will be INR 139 crores on this account. And coming to the investor-related ratios, the ROCE stands at 14.61% as against 14.04% at the financial year '24 end. And EPS stands at INR 12.10 as at the end of Q4 against INR 10.10 in the last year. I think with this, I end my presentation. We can invite for the questions.
Question
Shravan Shah: Sir, the first question is on the revenue. So, though we have achieved our revised guidance for FY '25, 5% growth, but compared to the original where we were looking at 15% and now, we are saying 10% growth in FY '26. Don't you think this is on the lower side given the kind of the Page 4of 18 NCC Limited May 16, 202 5 order inflow that we have received, which is even higher than what we were looking at in FY '25?
Answer, neerad sharma
Neerad Sharma: I think you're absolutely right. The last year, we had guided the market for about 15% growth, but we have been able to deliver only 5% growth, right? So, when we talk about 10% growth for FY '26, there is a handsome growth, right? Last year, we have grown at 5% in that range, and now we are talking about 10%. So that's a growth. Now I mean, let us -- I mean, I will also try to dig a bit deeper. This is also a reflection on the ability of our clients to mobilize to make the payments on time.
Answer, neerad sharma
This is a statement also on the uncertain environment that we are operating in. Primarily, this is dependent on the timely payments. It is not only about the execution. At the same time, we have to be cognizant of the fact that how much working capital we are committing. So, this is also a reflection on the ability of our clients to mobilize, make timely payments. So, this is the reason we have shared this guidance with you. Should there be any change going forward, we would be very happy to come to you and update you.
Question
Shravan Shah: Got it. Second, sir, this order inflow of INR 22,000 crores to INR 25,000 crores that we are looking at in FY '26, if you can clarify. I think last time we were having INR 8,000 crores to INR10,000 crores as the L1 orders. So how much L1 do we right now have? And if it is, does this include -- the INR22,000 crores to INR 25,000 crores include the L1? Or are we looking at the fresh INR 22,000 crores to INR 25,000 crores?
Answer, neerad sharma
Neerad Sharma: See, your question has 2 parts. Firstly, the -- some of the L1s that we had talked about in the past got converted in firm orders. And this is something that is reflected in our performance of INR32,888 crores order book. Some of those L1 projects, we hope will get converted in the coming quarters. As of now, we have an L1 project of about INR 7,000 crores to INR8,000 crores.
Question
Shravan Shah: Got it. Sir, a couple of data points. Can you share the stand-alone order inflow for FY '25 and returns on money and for capex for FY '26?
Answer, sanjay pusarla
Sanjay Pusarla: Yes. Retention money as on 31st March '25 is INR 1,870 crores as against INR 1,757 crores of the corresponding previous year -- sorry, INR1,505 crores of the corresponding previous year. And capex for FY '26 is at INR 750 crores.
Question
Shravan Shah: Yes. And lastly, the loans and advances and investment in subsidiaries and associates?
Answer, sanjay pusarla
Sanjay Pusarla: One second. Investment is INR 1,065 crores as against INR 1,033 crores. And the loans are INR452 crores as against INR 354 crores.
Question
Mohit Kumar: And sir, any comment on the slow -moving orders in the book, sir?
Answer, sanjay pusarla
Sanjay Pusarla: It is not a question of slow-moving orders for the guidance at 10%. It is dependent -- as Mr. Neerad said earlier, it is dependent on how the government takes this infrastructure segment and how the payments are going to come and how the clients are going to cooperate in the case of execution. And also, the projects which have come will have a little gestation period. It's not that immediately it gets converted after the order is received. It will have a little gestation period. Considering all those things -- and we have also seen what happened in the previous year in the Jal Jeevan Mission projects. So, considering all these things, we gave the guidance of 10%.
Question
Mohit Kumar: Understood, sir. The second question is, sir, what is the Jal Jeevan Mission order book right now? And are you seeing an improvement in execution and payment?
Answer, sanjay pusarla
Sanjay Pusarla: Payment is a little getting delayed. But otherwise, the order book for Jal Jeevan mission...
Answer, r raju
R. S. Raju: About 2/3 of the Jal Jeevan projects were completed. 1/3 of the projects are still pending. You are aware that for the last 7, 8 months, there is a slow progress because of the delay in the payments by the client, that is Jal Jeevan payments by the central government, particularly. Now -- we received some part payment in the last 2, 3 months, but still about INR 1,000 crores are yet to receive it.
Question
Mohit Kumar: Understood. That's very helpful. Sir, my last question, sir. How is the traction in smart meter execution? Have you achieved any financial closure? If not, when do you think to achieve the financial closure? And any guidance on the order execution in F '26 of the orders?
Answer, sanjay pusarla
Sanjay Pusarla: So, in financial closure for smart meters in the case of Ray, that is already achieved in the last year itself, and we have started running the load. In the case of Marathwada, the financial closure is yet to happen. We have received a term sheet from the lenders. We are yet to go for the financial closure. And as you are aware that these projects in Maharashtra, they were slow moving in the last year. But now we have got all the clearances to execute them, and we are showing good progress in these projects, expecting a good turnover in the current year.
Answer, sanjay pusarla
Sanjay Pusarla: Yes. In the case of Maharashtra projects, we have seen -- we have got even the instructions even from the government also that we can go ahead with the pace of the projects -- increasing the pace of the project execution. And we have been doing it and all the tests; everything has been completed. Now we have got a very good -- green signal from the government also, from the client also to go aggressively on these projects.
Question
Prithvi Raj: Okay. The second one is on the Andhra Pradesh state capital projects. You obviously received a couple of projects in the last few months. Is there any more activity that is happening there? And any more pending orders that you are expecting or everything is done from the state capital side?
Answer, sanjay pusarla
Sanjay Pusarla: From the state capital, you are aware that we have received a good number of orders for the infrastructure development, also for construction of some residential blocks and also the High Court also. So, these are the orders which we have received. About INR9,000 crores, INR 9,500 crores orders are on hand from the capital city. And as we see that the Chief Minister of Andhra Pradesh is announcing every day, some or the other project that he is announcing, but we do not know how much more projects that will be announced in the near future. But as of now, we have projects about INR9,000 crores, INR 9,500 crores. And the work and execution at the sites is in good progress, as we can see from the social media. And we also feel the same thing from the execution from our teams also that there is a lot of demand from the clients to execute the projects at a very fast pace.
Question
Prithvi Raj: Okay. Final question on the debt number. So, what's the target for the end of the year? Do we expect a significant reduction in the debt number? Page 7of 18 NCC Limited May 16, 202 5 R. S. Raju: Yes.
Answer, neerad sharma
So, this is the update on the Jal Jeevan mission. And as you are aware, my colleague has already highlighted that there has been some slow movement in Jal Jeevan mission projects across the companies. I mean, everybody who has been working in this space had faced payment delays, these kinds of issues. So, this is the update on this space as we speak. But going forward, once the households are given portable water connection, naturally, this will lead to lot of wastewater treatment plants, STP kind of projects. So, we are quite hopeful that going forward, these 2 sub verticals should see some traction.
Show 14 more questions
Question
Sarvesh Gupta: And sir, on the transportation road space?
Answer, neerad sharma
Neerad Sharma: Transportation, we have a healthy order book. We have been able to bag good number of projects in the transportation. If we really talk about the -- about 25% of our total order book is from the transportation division. In terms of value, it is INR 17,929 crores. So, it is already about 1/4 of our total order book. And we believe that we will see a good number of projects coming up for bidding in transportation segment.
Question
Sarvesh Gupta: But at an industry level, I think generally, people have not got much of orders. So, I think are your orders more related to the state government side rather than NHAI and MoRT H?
Answer, neerad sharma
Neerad Sharma: The awards that we have got are from a variety of the projects in most of the projects. For example, when we talk about the metro projects, the state government and the central government, they both partner with each other. NHAI, unfortunately, we have not been very successful in the NHAI projects in the past. Page 8of 18 NCC Limited May 16, 202 5 Sarvesh Gupta: Okay.
Question
Okay. And sir, finally, on the guidance. So, I think this question was asked before also. But I think with INR 72,000 crores sort of an order book plus an order inflow of maybe INR20,000 crores, INR 25,000 crores; from that bucket, if we are executing only around INR25,000-odd crores, then it becomes like a very small sort of a ratio of order execution versus the order book. So, I mean, if you can give us some more color as to what are you seeing from the client side? Are they not sort of -- after giving the orders, they are not sort of proceeding to the next steps, including the central government-related orders? Or are we anticipating in any other procedural delays? Why should the order ex
Answer, neerad sharma
Neerad Sharma: The first point that I wanted to share with you was the ability to execute the project. I mean, having the required number of people, machinery, everything to execute the project. So, this we do have. The second important part is whenever a project is announced, the client should make us available all the land, which is required to execute, all the permissions, all the drawing approvals. So, when this link is missing, there is little that we could do. So unfortunately, this is something that is going to impact our execution. The third important point is our -- the ability of the clients to make payments, certify bills on time, make payments on time.
Answer, neerad sharma
So, unless those things are in place, we will not be able to really execute from larger share from our order book. And the fourth important thing that we need to keep in mind is we have been able to bag a lot of projects in the last quarter, that is fourth quarter. So, it takes about 3, 4 months time to mobilize the project, get the land, get all the ROWs in place. So, there is a delay in award of a project and the billing cycle really to start. So, I think these are the 4 important points that I wish to bring to your attention.
Question
Sarvesh Gupta: And on the order inflows also, I think we have guided for a lower order inflow compared to what we have received this year. So, any color on that, sir?
Answer, neerad sharma
Neerad Sharma: I think most -- I mean, my colleague has already touched about -- touched upon this capital city project. So, we were -- fortunately, most of these capital city projects, if not all, got converted in the Q4 of the last financial year. So, we expect to see some movement, some new projects that might come up for bidding in the capital city. So that is the reason, or you could say that the project that we should have ideally bagged in FY '26, we have been able to bag in FY '25. So, if you really add these 2 numbers, they look very attractive, right?
Question
Sarvesh Gupta: How much is Andhra, by the way, sir, of your overall order book?
Answer, sanjay pusarla
Sanjay Pusarla: It's somewhere around INR 9,500 crores.
Answer, neerad sharma
Neerad Sharma: INR8,900 crores. Page 9of 18 NCC Limited May 16, 202 5 Moderator: We take the next question from the line of Vaibhav Shah from JM Financial Limited.
Question
Vaibhav Shah: So, sir, why is it so high the number versus the last year's number? So, are we including smart meter capex as well?
Answer, sanjay pusarla
Sanjay Pusarla: It was somewhere around INR 305 crores. This year, we are expecting the TBM, which will be used for tunnelling project in Mumbai. That is expected to come this year, okay? That itself is around INR300 crores. So, rest of the money is expected to be invested in other projects, capex .
Question
Vaibhav Shah: Okay. And sir, what is the status of the GMLR project?
Answer, sanjay pusarla
Sanjay Pusarla: GMLR project, they have got all the clearances. They have started building the approach roads. They have also started building their facilities for casting yard and also started landing station also for the TBM and they also started for the cut and cover portion of the project, okay? So, these are the things which are happening now. It is expected that TBM machines can arrive any time maybe in the next 1 month, 1.5 months. And thereafter, they should assemble them and put them in place at the landing station and start the work. This is the present status.
Question
Vaibhav Shah: Yes, TBM investment of INR 300 crores, that will be done from the stand-alone books?
Answer, sanjay pusarla
Sanjay Pusarla: Yes, it will be done in the stand-alone books. Both the partners are buying 1, 1 TBM and they are deploying those TBMs from the owner side.
Question
And sir, secondly, what investments are we planning to do in the smart meter project for '26 and '27?
Answer, sanjay pusarla
Sanjay Pusarla: About INR280 crores is the total investment that need to be made. And we are expecting to do around INR130 crores by Q2. And balance investments depend on the financial closure; it needs to be done.
Question
Vaibhav Shah: So, you are planning to bring any -- bring some partner with us? So INR 280 crores would be entirely done by us, or we are still looking out for a partner?
Answer, sanjay pusarla
Sanjay Pusarla: At the moment, it is only the investment from NCCL, and we are on the lookout for the partners. We are scouting for them.
Question
Vaibhav Shah: Okay. Okay. And sir, what is the outstanding number for the receivables from AP? Last year, it was around INR 400 crores.
Answer, sanjay pusarla
Sanjay Pusarla: No, it was INR 147 crores last time, okay, capital city projects. Out of that INR 147 crores, we received some, and we are -- the outstanding at the moment is INR 110 crores for the capital city projects where there was an issue.
Question
Vaibhav Shah: And in running projects?
Answer, sanjay pusarla
Sanjay Pusarla: Running projects, we are getting the money realization on time. And basis there is a realization only, the execution is happening. There is no worry on the running projects.
Question
Vaibhav Shah: Sir, but given the mix of the backlog and the new orders you have received, are we hopeful for an improvement on a Y-o -Y basis or...
Answer, r raju
R. S. Raju: We are looking for improvement at the bottom line. And about this EBITDA margin level, it depends upon the mix of the projects. So, at this moment, the larger size projects, what we taken up for BSNL about -- including O&M about INR10,000 crores to INR 11,000 crores project. The projects which have the more machinery- oriented generally reports the higher margins as a result of high EBITDA margin rise. But in case of NCC, the mix of the projects contains not the much of machinery-oriented projects. As a result, our EBITDA margin and gross margin is generally low compared to the Page 11of 18 NCC Limited May 16, 202 5 industry level. So, in the current coming 2 years, our mix of the projects, particularly the BSNL projects were INR 10,000 crores.
Answer, r raju
There is not much capex investment. So -- and also, we do not have a major portfolio of the roads. Generally, the roads and the mining industry where more machinery we use, generally, they give margin. Then there is a chance of increasing the EBITDA margins. So going forward in the next 2 years, we expect an improvement at the bottom line, but not at the EBITDA level.
Answer, sanjay pusarla
Sanjay Pusarla: So whatever O&M execution to be done after the capex portion, that was not included in the order book. Generally, what we do is that what we can execute in the next 3 years, that only will be considered in the order book. Out of that, around INR 7,127 crores, I think we have taken in the current order book. Balance value of the order book is still lying in the order book.
Answer, neerad sharma
Neerad Sharma: Mr. Gupta, same way for the smart meters also, if you recall, we had a discussion about smart meters. We have not considered O&M in our order book. O&M, we only take into our order book once the EPC part, that is the construction part is done.
Question
Anupam Gupta: Okay. And just one last question. What is the status of the Vizag land receipts?
Answer, sanjay pusarla
Sanjay Pusarla: In the case of Vizag land, whatever investment we have made, it is completely received back and equity. Whatever equity is there; it is received. And whatever loan is there, out of the loan also, we received about INR 15 crores in the current year, expect to receive about INR 120 crores in the next year, balance thereafter.
Questions about this call
- When was the NCC Q4 FY25 earnings call transcript filed?
- NCC filed the transcript with the exchange on 21 May 2025. This page is built from that transcript.
- What does this page list?
- 101 statements from the transcript across 8 topics, 67 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 24 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.