Earnings call
NTPC Q1 FY26 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company revised its FY32 capacity plan upward from 130 gigawatt to 149 gigawatt and aims to invest about INR7 lakh crore by FY32, including additional capex for PSP, green chemicals and BESS. The company had added around 3,050 megawatt of capacity till date, against around 4,000 in the last year. The company reduced forced outage from 4.18% to 3.42% in Q1 and to 3.75% in the entire year, compared with 4.03% in the previous year, through maintenance activities. Share of the country's electricity generation is 24%, while its share of installed capacity is 17%. The RBI allowed NTPC to raise ECB up to US$1 billion to finance its capex requirement.
The numbers management gave
Results
- The company reduced forced outage from 4.18% to 3.42% in Q1 and to 3.75% in the entire year, compared with 4.03% in the previous year, through maintenance activities.
Show source
With the quality overhauling, means maintenance activities, we have been able to reduce our forced outage from 4.18% to 3.42% in Q1 and 3.75% in the entire year compared to the 4.03% in the previous year.
- The company achieved its highest-ever group generation of 439 billion units in FY25.
Show source
In FY25, the company achieved its highest-ever group generation of 439 billion units, reaffirming its leadership in the sector.
- Revenue realization period for trade receivables reached 32 days in FY25, below the regulatory norm of 45 days.
Show source
As you can see that it has reached to 32 days in FY25.
- The company produced 46 million tons of coal in FY25, reflecting 28% year-on-year growth.
Show source
In FY25, the company achieved a production milestone of 46 million tons, reflecting a strong 28% year-on-year growth and underscoring its operational excellence in mining.
- Standalone profit in FY25 was INR 19,649 crore, its highest ever.
Show source
In FY25, the company achieved its highest ever standalone profit of INR 19,649 crore, showcasing our strong financial management and operational efficiency.
- Profit after tax for Q1 FY26 was INR 4,775 crore.
Show source
The momentum has continued in FY26, company posting strong financial results for Q1 FY26, profit after tax for Q1 FY26 stood at INR 4,775 crore.
Show 9 more statements
Results
- Consolidated profit increased 12% in FY25.
Show source
In FY25, the group achieved a notable 12% increase in profit, reflecting the strength of our diversified portfolio and the effectiveness of our growth strategy.
- The company achieved record highs in generation, profitability and revenue realization in FY25.
Show source
FY25 was a landmark year as we achieved record highs in generation, profitability and revenue realization.
- In FY25, NTPC maintained adequate coal availability across all stations through its fuel security measures, ensuring uninterrupted power generation.
Show source
In FY25, these measures enabled us to maintain adequate coal availability across all stations, ensuring uninterrupted power generation.
- Consolidated EBITDA increased in FY25. Replaced by a later filing.
Show source
The group's EBITDA also recorded significant increase, underscoring our capability to deliver strong operational earnings while maintaining disciplined financial management.
Money and capital
- The RBI allowed NTPC to raise ECB up to US$1 billion to finance its capex requirement.
Show source
RBI has allowed us to raise ECB up to US$1 billion to finance the capex requirement.
- The company refinanced INR 4,870 crore of loans, reducing interest rates by 2%, and restructured INR 23,294 crore of loans, achieving a rate cut of more than 1%.
Show source
We have refinanced and with the refinancing and restructuring, INR 4,870 crore of loans were refinanced, reducing interest rates by 2% and restructuring of INR 23,294 crore of loans achieved a rate cut of more than 1%.
- For FY25, NTPC paid an interim dividend of INR 5 in two tranches of INR 2.5 each, and the Board of Directors recommended a final dividend of INR 3.35, subject to shareholders’ approval at the upcoming AGM; the total dividend will become INR 8.35, approximately 42% of its profit.
Show source
Now coming back, it is important to say that, for FY25 NTPC has paid interim dividend of INR 5, and this was in the two tranches of INR 2.5 each and further Board of Directors have recommended final dividend of INR 3.35 subject to the shareholders’ approval in the upcoming AGM.
- The company says financial closure, including debt, for 1 or 2 gigawatt is easily possible.
Show source
So going for the financial closure or maybe tying up the finances including the debt for 1 or 2 gigawatt, it is easily possible from our side.
- The company has maintained a consistent track record of dividend payout for over three decades.
Show source
For over three decades, NTPC has upheld a consistent track record of dividend payout, striking the right balance between rewarding shareholders and reinvesting in future capacity expansion.
What it expects ahead
What management expects
- The company revised its FY32 capacity plan upward from 130 gigawatt to 149 gigawatt and aims to invest about INR7 lakh crore by FY32, including additional capex for PSP, green chemicals and BESS.
Show source
And in that also there is going to be, there will be additional capex, which will be going in the PSP, green chemicals, BESS etc., so put together, we aim to invest about INR7 lakh crore by FY32.
- The company is likely to add around 6 gigawatt of renewable energy this year and had already added about 1.4 gigawatt or 1.3 gigawatt this year.
Show source
This year we are likely to add around 6 gigawatt, that is what we had said and about 1.4 gigawatt or 1.3 gigawatt has already been added in this year.
- The company aims to expand its renewable portfolio from 8 gigawatt at present to 60 gigawatt by 2032.
Show source
In line with its vision for a cleaner energy mix, the company aims to expand its renewable portfolio from 8 gigawatt at present to 60 gigawatt by 2032, reinforcing its leadership in green energy.
- The company targets meeting at least 25% of its coal requirement through captive mining by FY30.
Show source
Looking ahead, NTPC targets meeting at least 25% of its coal requirement through captive mining by FY30, further enhancing fuel security and supply reliability.
- Renewable business may make advanced plans and may not have 100% PPA at a given snapshot.
Show source
So, at a given snapshot, you may not find 100% PPA, you may not find this thing, but that is part of the whole sector.
- The CMD said the nuclear power tariff of INR 6 to INR 8 would stabilize with the passage of time.
Show source
CMD: See, the INR 6 to INR 8 looks to be higher, but with passage of time it will stabilize.
Show 6 more statements
What management expects
- The company said small modular reactors (SMRs) are likely to take a little longer, but will come.
Show source
So ,it looks like that the SMR is going to take a little longer period, but it will come.
- The company expects renewable, nuclear, coal and gas to operate in parallel, and is considering other methods for gas to make power available as per demand, affordable and reliable.
Show source
Page 16 of 24 NTPC Limited August 18, 2025 So, there are many things, renewable, nuclear, then coal, gas is still, we are thinking of some other methods for gas, but I hope that at the next opportunity we will discuss that and we will make sure that the power is available as per the demand, and it is affordable and reliable.
- The company is not aggressive on storage at this point because storage technology and costs are undergoing correction.
Show source
But we are also not that aggressive at this point of time, realizing that there is a lot of correction which is happening in the storage, both technological side as well as the cost side.
- The company is going to emerge as one of the biggest players in nuclear power, alongside NPCIL. Replaced by a later filing.
Show source
The Prime Minister has declared this on 15th August also again, and in addition to NPCIL, we are going to emerge as one of the biggest players.
- The company expects most bids going forward to include some storage. Replaced by a later filing.
Show source
Going forward, most of the b ids may be with some storage.
- The CMD said green hydrogen had experienced some time lag after a period of wait and watch. Replaced by a later filing.
Show source
So, as I said, there was some time lag.
What it is building and selling
Projects and capacity
- The company had added around 3,050 megawatt of capacity till date, against around 4,000 in the last year.
Show source
Till date, we have added around 3050 megawatt, which was against the last years of total around 4000.
- THDC commissioned two pumped hydro units of 250 megawatt each and expects the full 1000 megawatt capacity to be fully operational by October end.
Show source
By October end, we expect that the full 1000 megawatt capacity should be fully operational.
- The company achieved a 100% load on Patratu Unit-1 and expects Unit-1 and Unit-2 to be commissioned by the end of the financial year.
Show source
We have very recently achieved a 100% load on Patratu Unit -1 and in this year, we are expecting that the Unit -1 and Unit-2 will also be commissioned by the end of the financial year.
- The company is trying to produce 50 million ton from captive coal mining this time, compared with almost 45 million ton last year.
Show source
This time we are trying to have 50 million ton.
- The company expects the foundation stone for Mahi Banswara to be laid in the second part of next month; the project is 4x700 megawatt in a joint venture with NPCIL.
Show source
We expect that the foundation stone will be laid in the second part of next month.
- The company targets increasing coal-based plant capacity by around 26 gigawatt in addition to its 62 gigawatt, to 88 gigawatt to 89 gigawatt in the next five years.
Show source
The coal based plants already, we will be putting around 26 gigawatt in addition to our 62 gigawatt, so it should become 88 gigawatt to 89 gigawatt in the next five years.
Show 61 more statements
Projects and capacity
- The company has already awarded, or has work going on, for approximately 16.5 gigawatt to 17 gigawatt of coal-based plant capacity; it targets awarding all these projects in this financial year, with the remaining awards to be made in the next few months.
Show source
We have already awarded, or the work is going on in approximately 16.5 gigawatt to 17 gigawatt.
- The company has 83 gigawatt of installed capacity and a further 31 gigawatt of capacity under construction.
Show source
Presently, NTPC is having 83 gigawatt installed capacity and a further 31 gigawatt capacity is under construction.
- The company added 4 gigawatt of new capacity in FY25 and an additional 3 gigawatt in FY26.
Show source
In FY25, we added a 4 gigawatt of new capacity, followed by an additional 3 gigawatt in FY26.
- The company has a goal of installing 30 gigawatt of nuclear capacity by 2047, contributing to the nation's 100 gigawatt target.
Show source
Coming to our steps in the new frontiers, NTPC has entered the nuclear energy domain with an ambitious goal of installing 30 gigawatt of nuclear capacity by 2047, contributing significantly to the nation's 100 gigawatt target.
- ASHVINI, NTPC's joint venture with NPCIL, is developing four 700 megawatt reactors at Mahi Banswara, Rajasthan, with all necessary government approvals in place.
Show source
This is developing four 700 megawatt reactors at Mahi Banswara, Rajasthan, with all necessary government approvals in place.
- The NTPC group plans to develop 21370 megawatt of pump storage capacity.
Show source
The NTPC group has an ambitious plan to develop 21370 megawatt of pump storage capacity.
- Tehri PSP's 500 megawatt capacity recently commenced commercial operation, with an additional 500 megawatt capacity scheduled to come online within the current fiscal.
Show source
Recently, 500 megawatt capacity of Tehri PSP commenced commercial operation with additional 500 megawatt capacity scheduled to come online within the current fiscal.
- The company has been allocated 5600 megawatt of PSP projects across Tamil Nadu, Maharashtra, Chhattisgarh and Madhya Pradesh and aims to commission 3 to 5 gigawatt of capacity by FY32.
Show source
We have been allocated 5600 megawatt of PSP project across Tamil Nadu, Maharashtra, Chhattisgarh and Madhya Pradesh and we aim to commission 3 to 5 gigawatt of capacity by FY32.
- The company has completed feasibility studies for 19 projects, and detailed project reports for four projects are in an advanced stage of preparation.
Show source
Feasibility studies for 19 projects are complete and detailed project report for four projects are in advanced stage of preparation.
- The company has commissioned a 150 kg/day green hydrogen plant at NETRA using treated water from an STP and is preparing to launch a one TPD facility at Simhadri that will harness sea water.
Show source
In green hydrogen, we have commissioned a 150 kg/day plant using treated water from an STP at NETRA and are preparing to launch a one TPD facility at Simhadri that will harness sea water.
- The company is constructing a 160 MWh CO2 based storage system at Kudgi, Vanadium Redox Flow Batteries at NETRA and 3.6 MWh phase change material systems at Dadri.
Show source
In energy storage, we are constructing a 160 MWh CO2 based storage system at Kudgi, Vanadium Redox Flow Batteries at NETRA and 3.6 MWh phase change material systems at Dadri.
- The company has 31 gigawatt of capacity under construction and plans to add 7.2 gigawatt through new thermal orders to ensure a reliable base load supply.
Show source
Moving to our present visibility in terms of growth trajectory, NTPC is poised for a robust growth with 31 gigawatt of capacity under construction and plans to add 7.2 gigawatt through new thermal orders to ensure a reliable base load supply.
- The company is targeting 3 to 5 gigawatt of pump storage PSP by 2032 and plans to award 2.8 gigawatt of nuclear capacity within this fiscal year.
Show source
The company is also pioneering advancements in energy storage, targeting 3 to 5 gigawatt of pump storage PSP by 2032 and is making a strategic entry into nuclear power with 2.8 gigawatt of capacity planned to be awarded within this fiscal year.
- The company has nine coal mines and mined 45 million metric ton against a peak capacity of 91.6 million metric ton.
Show source
Turning to the coal mining front, NTPC's group manages a robust asset base of nine coal mines with a combined peak capacity of 91.6 million metric tons per annum.
- The company expects additions of 26 to 27 gigawatt to around 62 gigawatt, bringing capacity to around 88 to 89 as of today.
Show source
So, it should be around 88 to 89 as of today.
- INR 7 lakh crore breakup includes around 2 gigawatt of Nuclear.
Show source
CMD: I think Nuclear is only around 2 gigawatt in that.
- 60 gigawatt renewable energy plan by 2030 will comprise a mix of PPAs, flexible utilization and merchant power.
Show source
But what we are doing, this REIA or the PPAs, This is going to be a mix of the two in the sense that there will be PPAs, there will be some flexible utilization, there will be some merchant.
- The company expects roughly 20 gigawatt of the initial 30 gigawatt renewable energy phase over the current year plus the next two years, with the balance in the following two years.
Show source
Director (Finance): Out of this, the initial phase 30 gigawatt if you talk about that, over the next 3 years, current year plus next two years would be roughly around 20 gigawatt and the balance would be in the next 2 years.
- For NTPC Limited's current year's 4465 megawatt renewable capacity, land connectivity is 100% and PPA is 87% tied up.
Show source
As far as the current year's 4465 megawatt is concerned, 100% land connectivity is there, PPA is 87% tied up.
- For NTPC Limited's next year's 8196 megawatt renewable capacity, close to 80% of PPA is tied up, 100% of land is available and 82% connectivity is available.
Show source
Next year 8196 megawatt is there, close to 80% PPA is tied up and 100% again land and 82% connectivity is available.
- For NTPC Limited's 8 gigawatt renewable capacity in the year next, more than 93% of land is tied up, 76% connectivity is available and close to 60% of PPA is in place.
Show source
And for the year next, 8 gigawatt, more than 93% of land is tied up, 76% connectivity is there and close to 60% of the PPA is in place.
- Battery storage approach can store daytime energy and allow coal power plants to operate at 70% rather than bringing them down to 55%.
Show source
The idea is that during the daytime, the power should be made available from those states, so that instead of bringing down to 55%, we can stick to, let us say, go to 70% or so and we can store that energy during the daytime.
- CO2 battery at Kudgi has a capacity of 160 megawatt hour and is planned to be commissioned by July next.
Show source
And let me again reiterate here, and you can ask Mr. Shaswattam in detail who are interested, that our CO2 battery, which is 160 megawatt hour, which is going on in Kudgi at present, so we will invite you to visit that place.
- The company had procured land around 12 years back for an imported coal-based plant of 2000 megawatt at Pudimadaka.
Show source
So, with the land we had procured way back, around 12 years back, for the imported coal-based plant for 2000 megawatt, okay?
- The Pudimadaka project is expected to involve around INR 85,000 crore of total investment.
Show source
So, let us not get into the numbers there, but the Pudimadaka itself is going to be around INR 85,000 crore total investment.
- The company expects the total investment in Pudimadaka to be around INR 80 to 85,000 crore.
Show source
So put together, it will be around INR 80 to 85,000 crore of the total investment in that.
- The estimated cost of nuclear power is somewhere between INR 15 crore to INR 20 crore per megawatt.
Show source
So, there are some estimates as of now that it will be somewhere between INR 15 crore to INR 20 crore per megawatt.
- The estimated tariff for nuclear power is in the range of anywhere between INR 6 to INR 8, depending on the project's cost.
Show source
If that is going to be the cost, tariff will be in the range of anywhere between INR 6 to INR 8.
- The estimated nuclear power tariff of INR 6 to INR 8 is a rough figure as of today and depends on interest rates.
Show source
Depending on the interest rates, this is rough figure as of today.
- The company said it is investing in thermal power and corrected the figure under discussion to 27.
Show source
CMD: No, 27.
- The company Group plans to add 21,370 MW of pumped storage projects, including 11,000 MW under NTPC and 10,370 MW via THDC and NEEPCO.
Show source
The NTPC group has an ambitious plan to develop 21370 megawatt of pump storage capacity.
- NEEPCO received approval and had more or less started work on the Tato-I, Tato-II and Heo projects; management said NEEPCO's capacity would double in the next five to six years.
Show source
So, whatever the plants were there in NEEPCO, it is going to be doubled by next five to six years.
- Bangladesh project, commissioned last financial year, had both units operational.
Show source
Another significant thing that I must mention that our Bangladesh project, which was commissioned last financial year, but I think then both the units are operational and there had been concern on that.
- The foundation stone or groundbreaking of NTPC's Sampoor project in Sri Lanka was done by the Prime Minister and President of Sri Lanka last to last month.
Show source
The foundation stone or the groundbreaking, rather, of our Sampoor project in Sri Lanka was done by Honorable Prime Minister and President of Sri Lanka last to last month.
- The company has no immediate plan to start a new greenfield coal-based power project and is seeking to add capacity at existing pit head plants, where coal will be cheaper, land is in hand and the time will be shorter.
Show source
As you will be knowing. long back we had declared that we don't have any immediate plan to start new greenfield coal-based power project, because we have advantage with respect to the others that we have sufficient space in our existing plant and that too also in the pit head plants.
- At NTPC's Pudimadaka hydrogen hub, NTPC is advancing projects to convert flue gas CO2 to ethanol, produce sustainable aviation fuel, develop India's first CO2 pipeline and establish the world's first CO2 based green urea plant.
Show source
At our Pudimadaka hydrogen hub, we are advancing a series of global first, converting flue gas CO2 to ethanol, producing sustainable aviation fuel, developing India's first Page 9 of 24 NTPC Limited August 18, 2025 CO2 pipeline and establishing world's first CO2 based green urea plant.
- The company said equipment constraints and delays in transmission networks and rights of way for transmission lines and water lines make Brownfield expansion a better option than starting new greenfield projects.
Show source
Brownfield expansion, in my opinion, makes far better sense than starting the new greenfield.
- The company ties up PPAs while participating in bids, builds land-bank inventories and makes strategic tie-ups with other states for joint ventures, with sourcing and application progressing concurrently.
Show source
We keep tying up PPA on one side, participating in the bid, we create inventories of land banks, strategic tie-ups with other states for joint ventures.
- The company can take the risk of creating an inventory of renewable projects and sign PPAs as they come.
Show source
CMD: By the way, we are one of the companies where we can take a risk of going ahead with some kind of creating the inventory of the project and if the PPA is coming, on the way we can sign that.
- Battery storage approach could apply in almost every state, with forward-looking states expected to adopt it.
Show source
At least all the forward- looking states will be definitely jumping on this side, we believe.
- The company annulled the proposed imported coal-based plant.
Show source
So, we annulled that.
- The company does not contemplate any pumped storage plants in NGEL at this stage.
Show source
Director (Finance): NGEL, we don't contemplate any PSPs, at this stage.
- The CMD said NTPC was considering whether the total investment for Pudimadaka would be on NGEL's balance sheet or whether NTPC could facilitate others and charge them.
Show source
Whether we are going to do from total on the balance sheet of NGEL, or whether we can also try to start having the model of facilitating others and try to charge.
- The company has the appetite to add another double-digit number in its existing plants. Replaced by a later filing.
Show source
We have the appetite to add another double-digit number in our existing plants.
- The next long-duration energy storage project after the one in Italy is getting commissioned; it does not require critical minerals like BESS, has no size restriction, and its storage duration can be modulated. Replaced by a later filing.
Show source
So, there is one which is in Italy and this is the next one which is getting commissioned.
Demand and pricing
- The company said energy storage prices would come down. Replaced by a later filing.
Show source
So, with that, there is going to be some kind of price coming down in case of energy storage also.
Segments
- Share of the country's electricity generation is 24%, while its share of installed capacity is 17%.
Show source
Our share in the country's electricity generation is 24%, with just 17% installed capacity.
- Vision 2032 covers a diversified portfolio spanning conventional power, clean green power, green hydrogen and its derivatives, with a presence across the entire energy value chain.
Show source
Our Vision 2032 charts a bold transformation into a leading energy major, anchored in a diversified portfolio spanning conventional power, clean green power, green hydrogen and its derivatives, along with a strong presence across the entire energy value chain.
- Non-solar-hour connectivity available in existing connectivity provides an avenue for existing players to co-locate storage, and if they cannot do so, the opportunity will be available to others, optimizing existing connectivity.
Show source
Director (Finance): With this emerging concept on non-solar hour connectivity, which is available in the existing connectivity, that gives an avenue for going in for a co-located storage for the existing player also.
- The company said coal plant PLF will be less and less as more RE is injected, while nuclear power will be more insulated and provide sustained, durable base load.
Show source
So, from that point of view, it becomes a very sustained, durable base load coming forward.
- C&I sales are made through power purchase agreements and the open access system as bilateral contracts between sellers and buyers.
Show source
So, this is a bilateral contract.
- The company said C&I arrangements are negotiated, and may include a cost-plus arrangement.
Show source
But there can be an arrangement where we can have a cost-plus arrangement also on a negotiated basis.
- R&D wing NETRA is undertaking endeavors on the molecular business. Replaced by a later filing.
Show source
Page 19 of 24 NTPC Limited August 18, 2025 Director (Finance): Apart from NGEL, there are some endeavors on the molecular business, which our R&D wing NETRA is doing, which I was mentioning in my presentation.
- Nuclear power will predominantly have a must-run characteristic. Replaced by a later filing.
Show source
Director (Finance): See, one significant thing is nuclear is going to be predominantly having a characteristic of a must-run.
Deals and partners
- The company said power available to states through the battery arrangement is available at INR 10, and the states can use it at peak time without extra infrastructure other than the BESS.
Show source
But at the same time, this power, which is available to them, this is available at INR 10.
- The company has signed MOUs with state governments to identify suitable land parcels and facilitate identification of land and development of nuclear project sites.
Show source
In addition, we have signed MOUs with state governments to identify suitable land parcels and facilitate for identification of land and development of nuclear project sites.
- The company has already won one green chemicals bid and another bid is ongoing.
Show source
And I did mention, and you can get further detail from Mr. Panda, that we have already won one, and there is another bidding going on at present.
- The company is discussing with some states providing the same power available from its plants during the day in evening peak hours at an incremental cost and incremental rate.
Show source
And there is a time we are also discussing with some of the states that whatever plant we have put up and that power, whatever is available during the day, we can provide the same power at an incremental cost and incremental rate, whatever it is, in the evening peak hour s. Page 17 of 24 NTPC Limited August 18, 2025 So those things are bound to come.
- The company said an off-taker could join hands with it or invest in the Pudimadaka project.
Show source
And if, let's say there is an off taker, he wants to join hands with us, or he wants to invest in that, we should be flexible on that.
- The company is setting up a RE facility for Indian Oil Corporation to off-take.
Show source
Indian Oil Corporation, for instance, we are setting up a RE facility to be off-taken by them.
- Power off-taker for the arrangement is Hindalco, and the arrangement is not in the regulated regime.
Show source
But to keep your reply short, this is not in the regulated regime.
Risks, rules and outside factors
Outside factors
- Low-cost financing has allowed it to maintain competitive tariffs in regulated business and enhance cost efficiency in the renewable energy segment.
Show source
Our ability to secure low-cost financing has allowed us to maintain competitive tariffs in regulated business, while enhancing cost efficiency in the renewable energy segment.
- The company said lower evening ambient temperatures increase transmission-line capacity, allowing more power to be fed in.
Show source
Otherwise, also there is a scope for around 10% in those lines, but during the evening hours when the ambient temperature is relatively lower, you can feed in more power.
- The company said the cost of coal-based power goes up if coal plants are backed down.
Show source
That figure is also being talked about for the coal based, and if it is going to be backed down, this cost goes up.
Rules and policy
- Flue gas desulphurization (FGD) investment will not put it at a disadvantage because it operates under a cost-plus regulated regime.
Show source
But you can take it clearly that whatever investment we are doing, that's not going to put us at a disadvantageous position.
- The company made FGD investment only after clearance and paused further investment once the notification was issued; CEA and the ministry are working on criteria for new projects and which ones to take up.
Show source
Just to inform you people here that we have taken a pause at that, once this notification was issued.
- The company has kept FGD on hold for new projects while CEA's committee decides the financial guidelines; costs for old projects are already covered on a cost-plus basis, and NTPC expects compensation for completed FGD work.
Show source
For the new projects, following the guideline, we have kept the FGD on hold.
Show 2 more statements
Rules and policy
- For NTPC's regulated returns, the cost of power will be reduced when interest rates fall.
Show source
Answer is yes.
- Under cost-plus arrangements, changes in interest rates may be translated into the tariff, and the benefit of a lower interest rate will be passed on to the customer.
Show source
So, the benefit of that lower interest rate will be passed on to the customer.
Everything else said on the call
Group structure
- NPUNL is NTPC's newly formed subsidiary dedicated to harnessing advanced nuclear technologies.
Show source
Second is NPUNL, our newly formed subsidiary is dedicated to harnessing advanced nuclear technologies.
- The company has acquired one asset in its joint venture with ONGC, and Hindalco is the off-taker of the power.
Show source
CMD: We have acquired one asset in our joint venture with ONGC.
- Green chemicals will be part of NTPC Green. Replaced by a later filing.
Show source
CMD: You have already said, the green chemicals will be part of the NTPC Green.
Other
- Small modular reactors (SMRs) can be as large as 200 megawatt for BSMR, what NPCIL is doing, or 470 megawatt for what Rolls-Royce is doing.
Show source
It can be as big as 200 megawatt what BSMR, what NPCIL is doing, or it can be even the 470 megawatt what Rolls-Royce is doing, so on.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
This transcript does not separate questions and answers, so they are not listed here.
Questions about this call
- When was the NTPC Q1 FY26 earnings call transcript filed?
- NTPC filed the transcript with the exchange on 25 Aug 2025. This page is built from that transcript.
- What does this page list?
- 106 statements from the transcript across 11 topics, 58 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- No. This transcript does not separate the questions from the answers, so they are not listed. The statements by topic still cover what management said.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.