Oil India Q1 FY27 earnings call: Oil India Limited expects to achieve close to 1 MMT each quarter this year

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company expects to achieve close to 1 MMT each quarter this year. The company drilled 17 new wells during Q1 FY 2026-27, comprising 7 exploratory wells and 10 development wells. The company produced 1.707 million oil and oil equivalent during Q1 FY 2026-27. About 55% of Oil India Limited's current acreage holding is offshore, with a chunk in deep offshore and ultra deep offshore. The company spent around INR3,050 crores in Q1 FY 2026-27: INR450 for survey, INR1,230 crores for exploratory drilling, INR700 for development drilling, 350 for capital equipment and projects, and around 350 on investment in subsidiaries, joint ventures and overseas investment.

The numbers management gave

Results

  • The company produced 1.707 million oil and oil equivalent during Q1 FY 2026-27.
    Show source
    From operational point of view, we have achieved 1.707 million oil and oil equivalent of production during this quarter.
  • The company produced 0.95 MMT of crude oil in Q1 FY 2026-27, an increase of 11 plus percentage on year-to-year basis.
    Show source
    The crude oil production for the quarter was 0.95 MMT, which has increased by 11 plus percentage on year-to-year basis.
  • Daily crude oil production reached 10,921 MT per day on 27th of June 2026, its highest ever daily production.
    Show source
    Our daily crude oil production has ramped up to 10,921 MT per day on 27th of June 2026, which was highest ever daily production the company has ever recorded.
  • Natural gas production increased by 0.4% quarter-to-quarter in Q1 FY 2026-27.
    Show source
    The natural gas production on quarter-to-quarter has increased by 0.4%.
  • Numaligarh Refinery Limited (NRL), Oil India Limited's material subsidiary, had gross refinery margin of USD35.95 per barrel in Q1 FY 2026-27, compared with USD5.02 per barrel in the previous year.
    Show source
    From financial front, the crude oil price realization was USD98.73 per barrel vis-a-vis USD66.20 per barrel as compared to the previous year.
  • Natural gas price was USD7.19 per MMBtu in Q1 FY 2026-27, compared with 6.72$ in the previous quarter of the last financial year.
    Show source
    The natural gas price stood at USD7.19 per MMBtu in this quarter as compared to 6.72$ in the previous quarter of the last financial year.
Show 34 more statements

Results

  • Standalone operating revenue was INR7,958 crores in Q1 FY27, its highest ever quarterly revenue since it got listed in the financial year 2009-2010.
    Show source
    The standalone operating revenue of Q1 FY27 is INR7,958 crores, which is highest ever quarterly revenue earned by Oil India Limited since it got listed in the financial year 2009-2010.
  • The company achieved its highest ever EBITDA of 4,605 crores in Q1 FY 2026-27, with a margin of 54% plus compared with 34% plus in the previous quarter of the last year.
    Show source
    We have also achieved the highest ever EBITDA during this quarter, which is 4,605 crores, as the margin is 54% plus as compared to 34% plus in the previous quarter of the last year.
  • Profit before tax was 3,742 crores in Q1 FY 2026-27, its highest ever quarterly profit after its listing with the stock exchanges.
    Show source
    The profit before tax for this quarter is 3,742 crores, which is highest ever quarterly profit achieved by the company after its listing with the stock exchanges.
  • The company achieved its highest ever PAT of INR2,870 crore in Q1 FY27, compared with INR813 crores in the previous year.
    Show source
    We have also achieved the highest ever PAT in this year which is INR2,870 crore as compared to INR813 crores in the previous year.
  • Earning per share was Rs. 17.65 per quarter in Q1 FY 2026-27, compared with Rs. 5 per share in the previous quarter.
    Show source
    Our earning per share stood at Rs. 17.65 per quarter as compared to Rs. 5 per share in the previous quarter.
  • Numaligarh Refinery Limited (NRL), Oil India Limited's material subsidiary, had operating income of INR9,146 crores in Q1 of FY26, 45% higher than Q1 of FY26.
    Show source
    The operating income of our material subsidiary was INR9,146 crores, which was 45% higher vis-a-vis Q1 of FY26.
  • Numaligarh Refinery Limited (NRL), Oil India Limited's material subsidiary, had refinery capacity utilization of 105% and distillate yield of 87% in Q1 FY 2026-27.
    Show source
    The capacity utilization of the refinery was 105% and the distillate yield is 87% for the quarter.
  • Numaligarh Refinery Limited (NRL), Oil India Limited's material subsidiary, had EBITDA of INR1,843 crores in Q1 FY 2026-27, compared with INR786 crores in the previous year.
    Show source
    The EBITDA was INR1,843 crores as compared to INR786 crores as compared to the previous year.
  • Numaligarh Refinery Limited (NRL), Oil India Limited's material subsidiary, had PAT of INR1,305 crores in Q1 FY 2026-27, compared with INR488 crores in the previous year.
    Show source
    The PAT the company has registered in the current quarter is INR1,305 crores as compared to INR488 crores in the previous year.
  • The company reported consolidated operating revenue of INR12,886 crores and PAT of INR4,026 crores in Q1 FY27; the PAT was its highest after the company got listed with the stock exchange.
    Show source
    From consolidated point of view, I'd like to bring to your knowledge that the company has reported the operating revenue of INR12,886 crores and registered a PAT of INR4,026 crores, which is also highest after the company got listed with the stock exchange.
  • The company said it had produced 1 MMT during the rest of the quarter.
    Show source
    The rest of the quarter we have done 1 MMT.
  • Daily production increased to 11,017 on 3rd of August 2026, from 10,921 for the last quarter.
    Show source
    We have increased it to 11,017 on 3rd of August.
  • NRL's reported GRM in Q1 FY 2026-27 was 35, including around 2 of inventory gain; excluding the inventory gain, GRM was 33, reflecting the difference between diesel and crude prices and MS and diesel and crude prices, whose spreads were extremely high.
    Show source
    See I think the GRM reported was 35.
  • NRL's GRM in the first quarter was around 35, including 2 of inventory gain, and 33 excluding inventory gain, after backing out the discount given to OMCs to keep prices stable.
    Show source
    So now we are clocking in the first quarter around 35.
  • NRL gave OMCs discounts of INR13 per liter for petrol at the start of the first quarter, declining to INR3 per liter by the quarter end, and INR10 per liter for diesel at the start, declining to nil by the quarter end; NRL's GRMs would have been much higher without the discounts.
    Show source
    Bhaskar Jyoti Phukan: See, GRMs would have been much higher, because we have been giving some discount to OMCs and the first quarter it was around, we started off with a very high number of INR13 per liter for petrol and which came eventually came down to INR3 per liter by the end of this.
  • NRL's discounts to OMCs declined from INR13 per liter to INR3 per liter for petrol and from INR10 per liter to nil for diesel.
    Show source
    Bhaskar Jyoti Phukan: 13 to 3 and 10 to nil.
  • The company is shutting down at least 30 wells on average.
    Show source
    So now on an averaging we are shutting down some wells at least 30 wells we are always shutting down.
  • Contract cost margin has gone up around INR146 crores for work being carried out.
    Show source
    Abhijit Das: Yes, the contract cost margin has gone up around INR146 crores [inaudible 62:08] which we are carrying out.
  • Contract cost rose around INR146 crores during the current quarter compared with the previous quarter, mainly because of G&G cost in its offshore blocks; other costs were at par.
    Show source
    Abhijit Das: See the contract cost of around INR146 crores which has gone up during the current quarter as compared to the previous quarter is majorly for our G&G cost in our offshore blocks.
  • Contract cost increase of roughly close to INR150 crores was only G&G cost for its offshore blocks.
    Show source
    It is only G&G cost for our offshore blocks.
  • The company said it was increasing production, citing well intervention and workover activities and systemic improvements to workover practices, including a high-level work over program planning committee.
    Show source
    Earlier days we didn't get such good workover results and we have done many systemic improvements in terms of workover, like we now have a good practice in place which is called HW, high-level work over program planning committee.
  • Excise duty benefit realization has come down because excise duty was calibrated to keep retail prices down, squeezing the excise benefit; the benefit was a sizable number, but not a big number.
    Show source
    So, to that extent, yes, our excise duty benefit realization has come down.
  • G&G cost increased because of its offshore operations and exploration; the rest of the cost items were more or less similar.
    Show source
    So, there has been a hike.
  • The company said it was performing well in workover, well intervention, well optimization and drilling. Replaced by a later filing.
    Show source
    So you can see that we are doing very well in all the three fronts, including workover, well intervention and also well optimization and drilling.
  • Other costs were almost in line compared with the previous year. Replaced by a later filing.
    Show source
    Rest are you can say almost in line as compared to the previous year.

Money and capital

  • The company spent around INR3,050 crores in Q1 FY 2026-27: INR450 for survey, INR1,230 crores for exploratory drilling, INR700 for development drilling, 350 for capital equipment and projects, and around 350 on investment in subsidiaries, joint ventures and overseas investment.
    Show source
    So it sums up to around INR3,050 crores for FY27 Q1.
  • Total budget estimate for FY27 is 8,600, subject to changes and revision during its next review.
    Show source
    Our total budget estimate for the whole year is as of now it is 8,600.
  • Actual expenditure for the previous year was INR13,026 crores.
    Show source
    And actual expenditure for the previous year was INR13,026 crores.
  • The company has invested around INR30,000 crores in NRL expansion capex so far.
    Show source
    Bhaskar Jyoti Phukan: We have invested around INR30,000 crores so far.
  • NRL expects to complete its refinery project at around INR34,000 crores to INR35,000 crores and its PPU project after spending another INR7,200 crores or INR7,300 crores.
    Show source
    So we should be completing the refinery project around INR34,000 crores to INR35,000 crores and we should also be completing the PPU project by spending another INR7,200 crores or INR7,300 crores.
  • NRL's INR30,000 crore total spend includes around INR19,000 crores of borrowings.
    Show source
    Management: So the debt component is INR19,000 crores.
  • The company has a USD1.4 billion foreign investment loan for its Mozambique project on a standalone basis.
    Show source
    Abhijit Das: From standalone point of view for foreign investment, we are having USD1.4 billion loan.
  • NRL has debt of INR19,000 crores plus at the group level.
    Show source
    And from NRL point of view, as sir already told, it is INR19,000 plus crores.
  • Total debt at the group level is around INR37,233 crores.
    Show source
    Total debt in the group level, which is around INR37,233 crores is our total debt.

What it expects ahead

What management expects

  • The company expects to achieve close to 1 MMT each quarter this year.
    Show source
    So at present we are on a path where you can, we can see that we are going to achieve close to 1 MMT each quarter this year.
  • The company expects to achieve 0.95 MMT most probably by this quarter.
    Show source
    Now you are getting 0.950, now 0.95 MMT, which we are going to achieve most probably by this quarter, we should achieve.
  • The company expects to reach 1 MMT every quarter from now onwards if everything remains ceteris paribus and nothing adverse happens in the field.
    Show source
    Page 4 of 22 Oil India Limited August 10, 2026 If everything remains ceteris paribus, then given everything going good and nothing adverse happens in the field, we expect that we will be reaching 1 MMT every quarter from now onwards.
  • The company will have an additional 1.5 MMSCMD by virtue of NRL coming up in that financial year.
    Show source
    Management: We will have an additional 1.5 MMSCMD by virtue of NRL coming up.
  • NRL is expected to start consuming an additional 1.5 MMSCD of gas in the second or third quarter of next financial year; before then, the 1.5 MMSCD can go to the national grid.
    Show source
    So the fact is that NRL is going to start consuming 1.5 additional gas perhaps in the second or third quarter of next financial year, but before that also, this 1.5 MMSCD can find their way to national grid.
  • The company plans to increase the number of wells to be drilled by at least 10% going forward.
    Show source
    And going forward, we would obviously stretch ourselves further and try to again ride on a 10% at least increase in the number of wells to be drilled.
Show 14 more statements

What management expects

  • NRL plans to start actual production in a graded manner from next financial year and expects to reach around 75% of total capacity utilization by the end of 27-28, or around 75% of its rated capacity of 9 million tons at Q4.
    Show source
    So at Q4, I think we will hit around 75% of our rated capacity of 9 million tons.
  • The company will drill the fourth Andaman well by December and expects to assess it by March, about 3 months to 3.5 months later.
    Show source
    So in about 3 months to 3.5 months say by March, we will be able to have some assessment of the fourth well, which is again a pure exploratory venture.
  • The company is using near field exploration, work over, production enhancement, optimization, hydro frac and radial drilling to ramp up production; its FY29 target is around 4.2 and may go beyond that.
    Show source
    If you if you look at our FY29 kind of target, we are targeting around up to around 4.2.
  • Natural gas production next year will be 3.8 BCM.
    Show source
    Trailukya Borgohain: Yes next year it will be 3.8 BCM.
  • The company may shut in up to 60 wells on average if consumption is low.
    Show source
    On an average if there is low consumption we will shut in up to 60 well.
  • Per barrel operating cost is around USD4.5 to USD5 today and is expected to come down to around USD3.5 as it rationalizes facilities and throughput increases.
    Show source
    That's what our expectation is because we will be rationalizing on the facilities and our throughput will be high, so that therefore the operating cost will come to around 3.5.
  • Production this year will be around a minimum of 3.9 MMT and may touch 4 MMT.
    Show source
    So, you can say that it will be around minimum 3.9 will be our production this year.
  • The company has surpassed 11,000, making it possible that production will touch 4 this year.
    Show source
    Abhijit Majumder: Now that we have surpassed 11,000, it is possible that we touch 4 this year itself.
  • The company expects to overcome seasonal challenges and regular shutdowns by existing customers once IGGL and the other facility come into effect.
    Show source
    We will be able to overcome the seasonal challenges that are there, the regular shutdowns that the existing customers that they take, all of those can be overcome once these two facilities come into effect.
  • The company said that once NRL gets into operation, there will be an increase in gas off-take on NRL's side.
    Show source
    Management: There will be an immediate spike in the off-take when NRL comes into being and maybe NRL by end of -- Phukan sir, would you like to add anything here?
  • The company expects to decide by February how many additional wells will be required in Andaman, depending on interpretation to be completed by January.
    Show source
    And by February, we should be able to take a call like how many additional wells we will be required to be drilled in Andaman.
  • The company expects to export gas to the western part of the country and, if required, to the rest of the country once connectivity is available.
    Show source
    I think that is their issue, but once we have this connectivity then we will definitely have it exported to Western part and also if required to the rest of the country.
  • Ability to reach its FY29 production target also depends partly on its own near field exploration.
    Show source
    But that will also depend a little bit of kind of our own near field exploration.
  • The company says all incremental gas production will be new gas at new well price, as the APM part will be over by this time; it plans to extend perforations, conduct more testing and open up areas where gas has already been discovered and tested.
    Show source
    Whatever incremental production will happen will be all new well price, because the APM part will be over by this time because whatever new Page 16 of 22 Oil India Limited August 10, 2026 gas we will be doing, we will be extending our perforations, we will be having more testing and already some areas we have already discovered, we have tested those areas and we know that we have the gas and we will open up those.

What it is building and selling

Projects and capacity

  • The company drilled 17 new wells during Q1 FY 2026-27, comprising 7 exploratory wells and 10 development wells.
    Show source
    Our company has drilled 17 new wells during the quarter, out of which 7 are exploratory wells and 10 are development wells.
  • The company expects to evacuate 3.5 to 4 MMSCMD of additional gas from the area once the pipeline is ready, and plans to send the gas to the rest of India by around December 2027.
    Show source
    So by next year end, we are expecting that all the facilities will be done and if we talk about gas by 2028, we'll be having all the pipeline everything ready and it will go to the rest of India, whatever gas we have, we have additional gas, we are planning to send our additional gas, whatever 3.5 to 4 MMSCMD we will be able to evacuate from that area.
  • The company said 200-meter work remained to be done within the NRL campus and IGGL would be over by end of the next financial year.
    Show source
    Only a 200-meter thing is still to be done within NRL campus and IGGL by end of the next financial it will be over.
  • The company will connect the currently 1 MMSCMD pipeline to IGGL with a 200-meter pipeline from Numaligarh in 2 months or 3 months, enabling it to give DNPL a short shutdown to augment capacity from 1 MMSCMD to 2 MMSCMD immediately and then to 2.5.
    Show source
    The currently the pipeline as you know is 1 MMSCMD and we will be able to connect with a 200-meter pipeline from Numaligarh to IGGL and we will be in a position to give them shutdown so that they augment their capacity from 1 MMSCMD to 2 MMSCMD immediately, then thereafter up to 2.5.
  • The company drilled 74 wells last year and is targeting 100 wells this year, including onshore and offshore wells.
    Show source
    Saloma Yomdo: Like last year we drilled 74 wells and this year we are targeting 100 which includes onshore as well as offshore.
  • The company has acquired and completed 4,200 line kilometers and 5,300 square kilometers of 3D data in the deep waters and ultra deep waters of Mahanadi and KG within a year of the PEL being awarded to it.
    Show source
    In the deep waters and ultra deep waters of Mahanadi and KG, we have already acquired, completed 4,200 line kilometers and 5,300 square kilometers of 3D data within a year of the PEL being awarded to us.
Show 34 more statements

Projects and capacity

  • The company will finish seismic acquisition, processing and interpretation of the Mahanadi and KG basins, covering roughly 40,000 square kilometers, by January.
    Show source
    Page 8 of 22 Oil India Limited August 10, 2026 So by January, we will be finishing the seismic acquisition, processing interpretation of the Mahanadi and KG basins, which is roughly about 40,000 square kilometers.
  • The company has identified possible prospects to be drilled and tendered out its rig requirements; the first rig is expected in June-July 27 and the second by March 28, starting its deep water exploration campaign.
    Show source
    So the first rig is going to come in June-July 27 and the second rig is going to come by March 28.
  • The company will drill one well next year in Mahanadi, with INR800 crores sponsored by the government as part of the stratigraphic well campaign.
    Show source
    And one well we are also going to drill next year in Mahanadi, but that is also going to be sponsored by the government, INR800 crores will be sponsored as part of the stratigraphic well campaign.
  • The company drilled 22 exploratory and 35 development wells in FY25, and 22 exploratory and 52 development wells in FY26; it is targeting 42 exploratory and 57 development wells in FY27.
    Show source
    And FY27 we are targeting 42 exploratory and 57 development wells.
  • NRL's CDU VDU unit was mechanically completed and subjected to OISD and PESO statutory inspections before startup; NRL was otherwise ready for startup in Q1 FY 2026-27.
    Show source
    We have mechanically completed that unit.
  • NRL plans to commission its three units by October or November at best and targets commissioning the remaining units by 31st March 2027.
    Show source
    So these three units will be commissioned by say October or November at best and rest of the units we are still taking a target of commissioning by 31st March 2027.
  • The company has acquired the entire right-of-use (ROU) stretch for the Paradip to Numaligarh pipeline except 8 kilometers.
    Show source
    Entire stretch of ROU barring only 8 kilometers stands acquired as of now.
  • The company mobilized its rig to Vijayapuram 1 and will stimulate the well using hydro frac technology because it had held the well pending proper testing facilities for tight formations; the Vijayapuram testing campaign will take almost the month of August, and Oil India will decide the fate of Vijayapuram 1 after testing in September.
    Show source
    So this will take about a month in Vijayapuram 1 for the testing to be complete.
  • The company will drill a fourth well in Andaman with a jack-up rig by December this year, at a water depth of about 90 meters in the northern part of the Andaman block.
    Show source
    So the fourth well we are going to go in Andaman with a jack- up rig and this we are going to be drilling by December this year.
  • The company has secured 300 square kilometers of 3D seismic data around Vijayapuram 2 and around 300 square kilometers around Vijayapuram 3, and the 600 square kilometers of data is being processed by Schlumberger for completion by October.
    Show source
    So in and around Vijayapuram 2 we took 300 square kilometers of 3D and in and around Vijayapuram 3 also we took around 300 square kilometers of additional 3D.
  • The company expects to complete interpretation of the 3D seismic data by January and, after assessment, quality control and discussion with TOTAL and Petrobras under its technical services agreement, will decide on further Andaman campaign activity, most probably appraisal wells near Vijayapuram 2 and 3.
    Show source
    So after having a detailed discussion with our technical service providers, Based on the new 3D data, we will take the next course of action to undertake the campaign in Andaman in and around Vijayapuram 2 and 3 for which most probably we will be drilling appraisal wells and that will help us to delineate the reservoir further.
  • The Duliajan Feeder Line is expected to be constructed very soon; Oil India Limited has its own right-of-use for most of the route except some 30 kilometer to 40 kilometer, while BPCL and ONGC have right-of-use for other parts.
    Show source
    So this is already going to be constructed very soon.
  • The DNPL project is nearly complete, with a 200-meter stretch within NRL remaining; the stretch will be completed in due course.
    Show source
    DNPL has more or less happened, except for the 200-meter stretch within NRL that will happen in due course, as MD-NRL has already pointed out.
  • Once the 200-meter stretch is in place, DNPL can carry gas to IGGL and eventually to the national gas grid even if NRL does not consume it, because DNPL is a common carrier.
    Show source
    So even if NRL doesn't consume, it can travel to IGGL and eventually to the national gas grid.
  • The company completed the testing sequence at Vijayapuram 3 in July and will undertake an appraisal campaign there based on 300 square kilometre of 3D seismic data it has acquired; after interpretation and prospect generation by April, it will take a final call on Vijayapuram 3.
    Show source
    So, that did not come up in the first quarter and we will be undertaking an appraisal campaign in Vijayapuram 3 also based on the new 300 square kilometre of 3D seismic data that we have acquired.
  • The company will drill an appraisal well in the Vijayapuram 3 area; depending on the 3D seismic campaign, it may examine using the same well to sidetrack and reach a desired position up to 1000 or 2000 meters laterally and horizontally, while its decision on Vijayapuram 1 will follow testing results concluded this month.
    Show source
    And if based on the 3D seismic campaign, we see that Vijayapuram 1 or 3 maybe was not in a proper structural position, then we can always examine the feasibility of utilizing this same well to side track and go to a desired position, which we can go up to 1000 or 2000 meters laterally, horizontally and Vijayapuram 1 will take a call after the testing results, which will be concluded this month.
  • Spending on Vijayapuram 1 has been roughly 1000 crores.
    Show source
    Abhijit Majumder: Vijayapuram 1 spending has been roughly 1000 crores.
  • The company expects the DNPL work to take a few months, two, three months maybe maximum; once completed, it expects more gas evacuation from the present capacity.
    Show source
    Once it is done, then we will have more evacuation of gas from the present capacity also.
  • NRL's DHDT unit is ready, and its SRU unit, required before commissioning DHDT, is almost complete; NRL expects to start DHDT along with SRU in about a couple of months.
    Show source
    SRU unit, which is required prior to commissioning of DHDT unit is almost getting completed, maybe another couple of months time, we should be able to start the DHDT along with SRU.
  • The company will commission the Paradip to Numaligarh pipeline by December.
    Show source
    Bhaskar Jyoti Phukan: By December we will commission the pipeline, yes.
  • The company is targeting mechanical completion of the Paradip to Numaligarh pipeline in October.
    Show source
    October we are taking a target for mechanical completion.
  • The company drilled three wells in Andaman; gas was reported in the second well and flowed continuously in the third well, which was a technical discovery intimated to the DGH.
    Show source
    So that was the technical discovery which we have also intimated to the DGH, which is a statutory authority.
  • The company is preparing to test the sand in its first Andaman well using hydro frac under a separate contract that has been mobilized.
    Show source
    So in the first well, we are now going back, and even as we speak, we are preparing to test the sand there using hydro frac, for which a separate contract has been mobilized.
  • The Duliajan Feeder Line is being built by Indradhanush Gas Grid Limited (IGGL), and Oil India Limited expects to evacuate gas once the line is connected.
    Show source
    So that once that is connected, we have the gas immediately we can evacuate.
  • The company is focusing on DFL and DNPL as long-term infrastructure to help transport gas to other parts of the country; relying mainly on BCPL, NEEPCO and other North-East customers will not enable it to evacuate its potential.
    Show source
    Why we are focusing on DFL, DNPL, these are all long-term things which will help us transport the gas to other parts of the country.
  • The company is ramping up production in Rajasthan as well as in its main producing areas. Replaced by a later filing.
    Show source
    And also we are ramping up production in Rajasthan.

Segments

  • About 55% of Oil India Limited's current acreage holding is offshore, with a chunk in deep offshore and ultra deep offshore.
    Show source
    But you have seen that the current acreage holding that we have, about 55% of them are in offshore.

Deals and partners

  • The company has said it will supply a total of 2.5 to Numaligarh Refinery Limited, or possibly close to 3, once the refinery ramps up production.
    Show source
    I cannot tell that but only thing is that since Numaligarh is coming up and we are like already told that we will be supplying a total of 2.5 to Numaligarh or Page 13 of 22 Oil India Limited August 10, 2026 maybe close to 3 to Numaligarh Refinery Limited, once they start ramping up their production.
  • The company said that if NRL has less intake, gas can be put into the mainline and then into IGGL for distribution to places including NEGDCL and Purba Bharati Gas in Lower Assam.
    Show source
    Now what will happen, when NRL, if there is less intake in NRL, then we can put it into the mainline and put it into the IGGL and when an IGGL can distribute it in the rest of the places they are doing like NEGDCL and also Purba Bharati Gas in Lower Assam.
  • The company said it had transported gas beyond NRL in the past.
    Show source
    That has already happened in the past.
  • The company said formalizing DNPL as a common carrier will help it continue transporting gas beyond NRL.
    Show source
    So that will only help us do what we have already done in the past.
  • TOTAL is reviewing Oil India Limited's data in detail and advising it on the prospect to be drilled.
    Show source
    And most importantly we are also derisking this prospect to be drilled because apart from our in-house and external consultants, TOTAL is also looking at this data in each and every detail and advising us.
  • Petrobras will independently interpret Oil India Limited's data.
    Show source
    They will also be doing an independent interpretation of this data, so that they will also come up with their own independent interpretation.
  • The company is in talks with Assam Gas Company to increase its gas intake, with potential for increased gas consumption if the Government of Assam and Assam Gas Company increase consumption.
    Show source
    So we have -- we still have some upside and we are in talks with our Assam Gas Company, so that they increase their intake, because there are a lot of areas for inroads.

Risks, rules and outside factors

Risks and disputes

  • The company has been providing for GST on royalty since the new requirement was introduced on 1 July 2017.
    Show source
    So it is again not going to impact our financials, because every quarter we were providing for it since this new thing was introduced in 2017, from 1st of July 2017.
  • GST on royalty liability is roughly INR2,500 crores without interest, and the court gave Oil India Limited six weeks to settle it; Oil India Limited is trying to make the payment as quickly as possible.
    Show source
    So our undertaking to the court was that the court has given us six weeks time to settle this and we are trying to kind of make this payment as quickly as possible.
  • Operations in Sivasagar and Charaideo had no material impact from the recent floods.
    Show source
    Trailukya Borgohain: No. In our areas there was no impact.
  • The company has shown the Assam land taxation matter as a contingent liability in its financials, and it has not impacted its financials.
    Show source
    So it has not impacted our financials at all.
  • The Government of Assam’s representative undertook to the court that the law concerning Assam land taxation will be withdrawn; it will be deliberated in the state legislature and the act will be repealed following due process.
    Show source
    So it will be deliberated in the state legislature and following the due process, the act will be repealed.
  • The company will prospectively pay no interest on GST on royalty and will pay the liability as it arises.
    Show source
    We will only be paying the liability as it arises.
Show 6 more statements

Risks and disputes

  • Second-quarter financials will not be impacted by GST on royalty because it has already provided for it, and Oil India Limited will disclose the amount released on account of GST on royalty.
    Show source
    Second quarter financial I mean financials as such is not going to be impacted because we already provided for it, but then we will definitely make a disclosure saying that this much amount has been released on account of GST on royalty.

Outside factors

  • NEEPCO consumes less gas when gas prices rise because it cannot match the price of hydro power, and instead increases hydroelectricity.
    Show source
    So in that case what they do, they a little bit of kind of try to consume less and they try to increase the hydroelectricity.
  • BCPL relies on a subsidy and may not be making significant financial or economic-scale progress.
    Show source
    So in our part of the place actually as far as the economics goes maybe they are not, they are not able to make very great headway in terms of finance and in terms of economy of scale.
  • NRL's discounts have reappeared, and the value is calibrated month on month to reflect the delta between crude and product cycle.
    Show source
    So we are giving now some value, but it gets calibrated month on month to reflect the delta between crude and product cycle.

Rules and policy

  • The Samudra Manthan scheme will provide a maximum ceiling of around 675 crores per well for drilling deep water and ultra deep water wells, and around 10,000 crores will be utilized for common infrastructure hubs; formal integrities are yet to be announced.
    Show source
    The formal integrities are yet to be announced, but it has already been announced that some amount of money will be reimbursed by the government for seismic activities, and around 675 crores per well, which is a maximum ceiling will be provided for drilling deep water and ultra deep water wells.
  • DNPL has received a new mandate from the government, with PNGRB giving it common carrier status.
    Show source
    Now DNPL has got a new mandate from the government, PNGRB has given them as a common carrier.

Everything else said on the call

Other

  • The company said it was conducting integrated planning for new wells through the Exploration & Development portfolio management board (EDPMB), with the Director of Operations as an invitee.
    Show source
    Also on the other hand, we have one particular aspect that is done by Director Exploration & Development, but where I am also an invitee, that is called EDPMB, Exploration & Development portfolio management board similar to workover and production areas, we do for new wells.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Probal Sen: Thank you for the opportunity, sir. Very good afternoon and congratulations on a good set of numbers. Firstly just a clarification, when you mentioned about the production reaching 10,921 tons of oil per day on the 27th June, just wanted to understand what is the run rate right now for the second quarter as such. I mean can we expect it to sort of ramp up and maintain at this level or it was basically just want to get some understanding? Management: Thank you for the question. I am requesting Director Operations to respond to the question.

    Answer, trailukya borgohain

    Trailukya Borgohain: So this is Trailukya Borgohain, Director Operations. So as you have seen that we are ramping up our production this quarter, one of the finest production we got. But as of now also, we are increasing our production because we are doing well in all the three fronts. You can see that one, the first one is the well intervention and work over activities. Earlier days we didn't get such good workover results and we have done many systemic improvements in terms of workover, like we now have a good practice in place which is called HW, high-level work over program planning committee. So this is called planning board meeting, HWPMB. Now what we do is that myself, along with Director Exploration & Development also sits together and do it very, very in an integrated manner, a selection of the wells, everything.

    Answer, trailukya borgohain

    Also on the other hand, we have one particular aspect that is done by Director Exploration & Development, but where I am also an invitee, that is called EDPMB, Exploration & Development portfolio management board similar to workover and production areas, we do for new wells. So where I am also an invitee. So now the things are a little bit different. It is not done in earlier days. We are doing it in a very, very integrated manner along with Exploration & Development. So you can see that we are doing very well in all the three fronts, including workover, well intervention and also well optimization and drilling. So at present we are on a path where you can, we can see that we are going to achieve close to 1 MMT each quarter this year.

    Answer, trailukya borgohain

    The rest of the quarter we have done 1 MMT. Now you are getting 0.950, now 0.95 MMT, which we are going to achieve most probably by this quarter, we should achieve. Page 4 of 22 Oil India Limited August 10, 2026 If everything remains ceteris paribus, then given everything going good and nothing adverse happens in the field, we expect that we will be reaching 1 MMT every quarter from now onwards. So let's see we are keeping our fingers crossed. This is what I can tell you and as of now, after that production we have mentioned 10,921 for the last quarter. We have increased it to 11,017 on 3rd of August. So we are on a -- I think we are on a path where we want to increase our production.

  2. Question

    Probal Sen: Understood, sir. Thank you. The second question was with respect to gas production. Now, I do understand that there are still some monetization challenges. If you can update us a little bit in terms of the progress of the monetization, downstream pipelines that are under different stages of implementation. And when can we expect maybe a ramp up back to the 0.85, 0.86 BCM levels or rather 0.8, 0.83 BCM levels that we were doing earlier. That will be very helpful.

    Answer, trailukya borgohain

    Trailukya Borgohain: Actually, there are many hiccups that happen because of the shutdown of the downstream industries. This is because of that BCPL took shutdown and at some point of time maybe means this is a yearly shutdown they take. The other thing is that seasonal rains will also come now because from October onwards the tea gardens, they will take a little bit less than what we are doing as of now. So on an average what we are expecting is that if this pipeline comes, then we will have the evacuation bottleneck gone out of this whole story. So by next year end, we are expecting that all the facilities will be done and if we talk about gas by 2028, we'll be having all the pipeline everything ready and it will go to the rest of India, whatever gas we have, we have additional gas, we are planning to send our additional gas, whatever 3.5 to 4 MMSCMD we will be able to evacuate from that area. So that is we are planning, we are thinking that it will be by around December 2027 it should happen. Also DNPL also, one small thing is there.

    Answer, trailukya borgohain

    Around 200 meters of line actually is required to be laid inside NRL. Now DNPL has got a new mandate from the government, PNGRB has given them as a common carrier. Now what will happen, when NRL, if there is less intake in NRL, then we can put it into the mainline and put it into the IGGL and when an IGGL can distribute it in the rest of the places they are doing like NEGDCL and also Purba Bharati Gas in Lower Assam. So this is going on. This will take few months, two, three months maybe maximum. Once it is done, then we will have more evacuation of gas from the present capacity also.

  3. Question

    Probal Sen: Got it, sir. So what I understand is FY27. Page 5 of 22 Oil India Limited August 10, 2026 Abhijit Majumder: In fact, in the past as well, we have transported gas beyond NRL.

    Answer, abhijit majumder

    That has already happened in the past. Now this particular communication, formalizing DNPL as common carrier has come. So that will only help us do what we have already done in the past. And as DO has already mentioned that once IGGL comes into being, then there will be no stopping actually. We will be able to overcome the seasonal challenges that are there, the regular shutdowns that the existing customers that they take, all of those can be overcome once these two facilities come into effect. Only a 200-meter thing is still to be done within NRL campus and IGGL by end of the next financial it will be over. So things will be pretty smooth for us as far as gas is concerned.

  4. Question

    Probal Sen: FY29 first quarter?

    Answer, trailukya borgohain

    Trailukya Borgohain: From first quarter onwards. Management: We will have an additional 1.5 MMSCMD by virtue of NRL coming up. This would be in that financial year.

    Answer, trailukya borgohain

    Trailukya Borgohain: So that augmentation has already been done because now once NRL also gets into operation from suppose next January, then definitely there will be increase in gas off-take on their side also. Management: There will be an immediate spike in the off-take when NRL comes into being and maybe NRL by end of -- Phukan sir, would you like to add anything here?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: Yes, I have only a couple of things to add. And as Director Ops has already told that DNPL has become a common carrier. The currently the pipeline as you know is 1 MMSCMD and we will be able to connect with a 200-meter pipeline from Numaligarh to IGGL and we will be in a position to give them shutdown so that they augment their capacity from 1 MMSCMD to 2 MMSCMD immediately, then thereafter up to 2.5. So they were requesting for a shutdown because of the geopolitical thing because it was also -- it would have resulted also in a shutdown of the Numaligarh refinery and we needed diesel and Page 6 of 22 Oil India Limited August 10, 2026 petrol badly because of the geopolitical situation. We were not being allowed to give the shutdown to them. Now that things have eased and we can do away with the shutdown because we can operate with the gas from the IGGL due to this 200-meter connectivity which is going to come in 2 months, 3 months time. We will be in a position to give a very short shutdown to DNPL to augment their capacity to 2 and eventually to 2.5.

    Answer, bhaskar phukan

    That gives a head start of around 1.5 which, if not consumed in NRL can also be given to the national grid. So the fact is that NRL is going to start consuming 1.5 additional gas perhaps in the second or third quarter of next financial year, but before that also, this 1.5 MMSCD can find their way to national grid. That is the limited point that I wanted to make.

  5. Question

    Probal Sen: All right. Perfect sir. Thank you so much, I'll come back if I have more questions and all the best.

    Answer, saloma yomdo

    Saloma Yomdo: Like last year we drilled 74 wells and this year we are targeting 100 which includes onshore as well as offshore. So currently we are on track to achieve that big ambition of drilling, completing 100 wells. And going forward, we would obviously stretch ourselves further and try to again ride on a 10% at least increase in the number of wells to be drilled. Now whatever wells that we are drilling primarily in onshore is from our own resources. But you have seen that the current acreage holding that we have, about 55% of them are in offshore. And a chunk of them are in deep offshore and ultra deep offshore. So with the new PNG rules which have been announced, there are a lot of opportunities for enhanced exploration.

    Answer, saloma yomdo

    For example, if you feel that your block is extending beyond your exploration lease, then you can also place your right for further extension of the – for the lease area to bring it under your exploration campaign. Then there are other things and most recently is the Samudra Manthan which has been announced. The formal integrities are yet to be announced, but it has already been announced that some amount of money will be reimbursed by the government for seismic activities, and around 675 crores per well, which is a maximum ceiling will be provided for drilling deep water and ultra deep water wells. And also some 10,000 crores or something will be utilized for common infrastructure hubs. And so with this especially for our deep water and ultra deep water, we have already worked out and chalked out a plan where we have identified how many wells will be drilling in the deep water and ultra deep water in the next couple of years. Especially since we have already acquired the vintage 2D and 3D data and they are currently being processed and interpreted. In the deep waters and ultra deep waters of Mahanadi and KG, we have already acquired, completed 4,200 line kilometers and 5,300 square kilometers of 3D data within a year of the PEL being awarded to us.

    Answer, saloma yomdo

    Page 8 of 22 Oil India Limited August 10, 2026 So by January, we will be finishing the seismic acquisition, processing interpretation of the Mahanadi and KG basins, which is roughly about 40,000 square kilometers. As of now, we have already identified possible prospects to be drilled and that is the reason why we have already tendered out the rig requirements. So the first rig is going to come in June-July 27 and the second rig is going to come by March 28. And that will kick start our deep water exploration campaign. And one well we are also going to drill next year in Mahanadi, but that is also going to be sponsored by the government, INR800 crores will be sponsored as part of the stratigraphic well campaign. And then the other wells we are going to take up through the Samudra Manthan route where they will be supporting us with the funds. And most importantly we are also derisking this prospect to be drilled because apart from our in-house and external consultants, TOTAL is also looking at this data in each and every detail and advising us.

    Answer, saloma yomdo

    And now Petrobras have also come on board. They will also be doing an independent interpretation of this data, so that they will also come up with their own independent interpretation. So this is in broad what is the outlay that we have for us in the next coming years. Does that answer your question? Vivekanand: Yes. Just small follow-ups. So one is how much capex did you incur in 1Q and if you can give bit more details about the wells drilled?

    Answer, abhijit das

    Abhijit Das: So for the capex, if you have asked the question for how much we have actually spent for Q1 27. The total amount spent is around INR3,050 crores, which for survey we can -- it is INR450, for exploratory drilling it is INR1,230 crores, development drilling we have spent INR700. For our capital equipment and our projects, we have already spent 350 and investment in our subsidiaries and joint ventures and overseas investment was around 350. So it sums up to around INR3,050 crores for FY27 Q1. Our total budget estimate for the whole year is as of now it is 8,600. It will go undergo some changes and revision during our next review. And actual expenditure for the previous year was INR13,026 crores.

    Answer, saloma yomdo

    Saloma Yomdo: So FY25 we drilled 22 exploratory and 35 development wells. FY26 we drilled again 22 and 52, 22 exploratory and 52 development wells. And FY27 we are targeting 42 exploratory and 57 development wells. Vivekanand: Right, thank you. Can you answer my question on NRL now? Thanks a lot.

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: Yes. See, I heard that question on the GRM. See I think the GRM reported was 35. That accounts for around 2 that we have gained in terms of inventory gain. So if you back that out, it will be 33 for GRM. This GRM increase is basically because of the difference between diesel and crude prices, MS and diesel and crude prices. Page 9 of 22 Oil India Limited August 10, 2026 So those spreads were extremely high.

    Answer, bhaskar phukan

    In fact, this is after backing out the discount that we have to give to OMCs to keep the prices stable as a understanding. So therefore, this is the GRM that we had. So generally our GRM hovers around USD7 to USD8 that you may have observed in the last annual reports and all. So now we are clocking in the first quarter around 35. That includes 2 for as inventory gain. If you back it out, it will be 33. So did I answer your question?

  6. Question

    Somaiya V: Yes, hi sir, thanks for the opportunity. So my first question is on NRL expansion. Could you provide us an update in terms of the commissioning? Earlier I believe D2 units were expected to kickstart it. So where are we and what is our expectations in terms of output for this year and also in FY28?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: So as we had in the last interaction, we indicated that in the first quarter, we will be commissioning our CDU VDU. We have mechanically completed that unit. We had subjected it to inspection by OISD followed by PESO. These are statutory inspections that are required to be carried out before we do a startup activity. Otherwise we are ready for startup. DHDT unit is ready. SRU unit, which is required prior to commissioning of DHDT unit is almost getting completed, maybe another couple of months time, we should be able to start the DHDT along with SRU.

    Answer, bhaskar phukan

    So these three units will be commissioned by say October or November at best and rest of the units we are still taking a target of commissioning by 31st March 2027. So having done that, our actual production in a graded manner, we will start from next financial year. Gradually we will hit up to around 75% of the total capacity utilization by end of the year 27-28. So at Q4, I think we will hit around 75% of our rated capacity of 9 million tons. So that is what our plan is.

  7. Question

    Somaiya V: Understood sir. And also on the related infrastructure in terms of the Paradip to Numaligarh pipeline. So there was a few kilometers that was pending. So any updates there, when is that expected to be done?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: Yes. Actually there has been very good progress over there also. Entire stretch of ROU barring only 8 kilometers stands acquired as of now. So we are in a good shape there. We are getting good traction, good support from the governments associated with the ROU because we are traveling through four states. So all of them are supporting us.

  8. Question

    Somaiya V: The timeline by December of this?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: By December we will commission the pipeline, yes. October we are taking a target for mechanical completion. Page 10 of 22 Oil India Limited August 10, 2026 Somaiya V: Understood, sir.

  9. Question

    Somaiya V: Yes, thanks. So just on the capex part on NRL, so also if you could help us what is the net debt at NRL of the INR35,000 crores to INR40,000 crores of expansion capex what much have we expensed so far and what is the plan for the next couple of years?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: We have invested around INR30,000 crores so far. So we should be completing the refinery project around INR34,000 crores to INR35,000 crores and we should also be completing the PPU project by spending another INR7,200 crores or INR7,300 crores. So that is the outlook of capex that we have.

  10. Question

    Somaiya V: The current net debt at NRL and what is the actual cash capex that we have spent so far?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: The 30,000 figure that I spoke is the total spend that we have made. Out of that around 26 will be -- around 19 will be the borrowings that we have done. Management: So the debt component is INR19,000 crores.

Show 8 more questions
  1. Question

    Somaiya V: And console level, including upstream and international?

    Answer, abhijit das

    Abhijit Das: From standalone point of view for foreign investment, we are having USD1.4 billion loan. As far as Oil is concerned, this is only for our Mozambique project. And in consolidated level, another one bond we have from our foreign subsidiary in Singapore, which is USD500 million of bond, which is to be repaid in the next year, 27 May. And from NRL point of view, as sir already told, it is INR19,000 plus crores. So this is in a group level if you sum up these three figures, this will be our debt. Total debt in the group level, which is around INR37,233 crores is our total debt.

  2. Question

    Yogesh Patil: Thanks for taking my question sir and congratulations for the good set of numbers. Question pertains to gas discovery in Vijayapuram, Andaman. What are the upcoming steps or the procedure planned for this field to help us gauge volume reserve and that can be produced Page 11 of 22 Oil India Limited August 10, 2026 commercially? If there is any new exploratory well plan for the Andaman, what would be the timeline for this completion and when can we anticipate the results? This is my first question?

    Answer, saloma yomdo

    Saloma Yomdo: Well, as you are aware, we have drilled so far three wells in Andaman. And the first well we drilled and we went to the second well because the sand that we encountered was tight and with the current testing system, we couldn't test the well. So we decided that we will come back prepared for testing the first well. So we went to the second well where the gas was reported. Then in the second well, but it was flowing very intermittently, but in the third well which we drilled, the gas was flowing continuous. So that was the technical discovery which we have also intimated to the DGH, which is a statutory authority. So in the first well, we are now going back, and even as we speak, we are preparing to test the sand there using hydro frac, for which a separate contract has been mobilized.

    Answer, saloma yomdo

    And the hydro frac is a well stimulation mechanism which can help you to test tight sands, so that the fluid or gas can come out easily. So this will take about a month in Vijayapuram 1 for the testing to be complete. And then we will demobilize this rig, our current rig, semi-submersible rig that we have, because it has completed its contractual tenure. So the fourth well we are going to go in Andaman with a jack- up rig and this we are going to be drilling by December this year. And the fourth well is further up North in the Andaman block at the water depth of about 90 meters. So this rig is actually currently drilling in our KG offshore DSF block. So once we complete this well in KG offshore, which in a few days we will be testing in KG, then we will mobilize this rig to Andaman and drill the fourth well.

    Answer, saloma yomdo

    In the meantime based on the discoveries in Vijayapuram 2 and 3, we have secured additional seismic, 3D seismic data. Because the discoveries which were made were based on 2D data and 2D data interpretation. So we thought we will have an opportunity to map the subsurface better using 3D seismic. So in and around Vijayapuram 2 we took 300 square kilometers of 3D and in and around Vijayapuram 3 also we took around 300 square kilometers of additional 3D. So this 600 square kilometers of 3D data is currently being processed by Schlumberger, which is going to be completed by October. So that by January we have completed the interpretation and then after going through our normal assessment and QC, especially leveraging on the partnership, technical services agreement that we have with TOTAL and Petrobras. So after having a detailed discussion with our technical service providers, Based on the new 3D data, we will take the next course of action to undertake the campaign in Andaman in and around Vijayapuram 2 and 3 for which most probably we will be drilling appraisal wells and that will help us to delineate the reservoir further.

  3. Question

    Yogesh Patil: Any possible timeline that you declared or shared the result in terms of the gas reserves into that field next 6 months, 9 months down the line after doing all this exercise?

    Answer, saloma yomdo

    Saloma Yomdo: Yes. So the fourth well we are going to drill by December. So in about 3 months to 3.5 months say by March, we will be able to have some assessment of the fourth well, which is again a pure exploratory venture. Then the appraisal wells that we are going to drill near Vijayapuram 2 and 3 that will depend on the interpretation that we complete by January. And by February, we should be able to take a call like how many additional wells we will be required to be drilled in Andaman. Yogesh Patil: Sir, my second question related to 8% Y-o-Y decrease in a gas production. How long will the petrochemical and power plants continue to use less gas because we have been seeing this issue of shutdown or less gas consumption from the petrochemical site?

    Answer, trailukya borgohain

    Trailukya Borgohain: Actually we supply suppose as for power consumption we supply to NEEPCO. So NEEPCO what happens is that NEEPCO I would like to label for you, they are having hydro power at the same time and they have the gas based power project. Now when increasing the gas price, they are not actually able to match the price of hydro. So in that case what they do, they a little bit of kind of try to consume less and they try to increase the hydroelectricity. So this is what they do. Number two like you have said about the petchem, so we are basically BCPL survives on kind of what you can call is a subsidy. So in our part of the place actually as far as the economics goes maybe they are not, they are not able to make very great headway in terms of finance and in terms of economy of scale.

    Answer, trailukya borgohain

    I think that is their issue, but once we have this connectivity then we will definitely have it exported to Western part and also if required to the rest of the country. But another thing there is some upside is there, because government of Assam is also taking interest in increasing the domestic supply of gas - CGD. So we have -- we still have some upside and we are in talks with our Assam Gas Company, so that they increase their intake, because there are a lot of areas for inroads. So that gas consumption can increase if Government of Assam, Assam Gas Company increases their consumption. Otherwise this situation continues. I cannot tell that but only thing is that since Numaligarh is coming up and we are like already told that we will be supplying a total of 2.5 to Numaligarh or Page 13 of 22 Oil India Limited August 10, 2026 maybe close to 3 to Numaligarh Refinery Limited, once they start ramping up their production. So as you already told, it is coming, coming up.

    Answer, trailukya borgohain

    Trailukya Borgohain: So the other thing is that we have the DFL Duliajan Feeder Line that is being done by IGGL, Indradhanush Gas Grid Limited. So that once that is connected, we have the gas immediately we can evacuate. There should not be an issue. One good thing about that line is that most of the places we have the ROU, we have our own ROU like they will pass through some in some parts, except some 30 kilometer, 40 kilometer, rest of the places we have the ROU, one is BPCL and the other one is I think ONGC and so there should not be much issue in laying the pipeline. So this is already going to be constructed very soon.

  4. Question

    Yogesh Patil: Sir BCPL consumptions have improved after the maintenance shutdown is over or still the BCPL consumption levels for the gas are still lower in the current quarter Q2 also? Management: BCPL offtake more or less it has picked up and it’s currently stable.

    Answer, abhijit majumder

    Abhijit Majumder: If we look at BCPL, we are basically taking a very narrow view. Why we are focusing on DFL, DNPL, these are all long-term things which will help us transport the gas to other parts of the country. Nearly relying on BCPL or NEEPCO and few other customers in the North-East, we all know that that will not help us evacuate the potential that we have. So BCPL little up down this will not really change the scenario drastically. For us to really have a head start, big head start, this DFL has to kind of happen. DNPL has more or less happened, except for the 200-meter stretch within NRL that will happen in due course, as MD-NRL has already pointed out. So that is the larger picture.

  5. Question

    Varatharajan S: Secondly like there is a small clarification on this issue. Once the 200 meter is completed irrespective of how Numaligarh ramps up, like you are still in a position to put it in the IGGL. So the common carrier is already in place. So you are not dependent entirely on Numaligarh for that additional 1.5?

    Answer, trailukya borgohain

    Trailukya Borgohain: You are you are correct actually. Once this 200 meter is there and DNPL being a common carrier. So even if NRL doesn't consume, it can travel to IGGL and eventually to the national gas grid.

  6. Question

    Sabri Hazarika: Yes, sir, two small questions. Firstly, you mentioned in NRL that you gave some discounts. Was this like the windfall tax related discounts? How much was the quantum? And if not for the discounts, then what could have been the GRMs?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: See, GRMs would have been much higher, because we have been giving some discount to OMCs and the first quarter it was around, we started off with a very high number of INR13 per liter for petrol and which came eventually came down to INR3 per liter by the end of this. And then for diesel, it was started with INR10 per liter and eventually it was nil by the quarter end. So they kept calibrating based on the international price of diesel. So our GRM would have been much higher. So that is what I could have I can confirm eventually.

  7. Question

    Sabri Hazarika: So INR30 per liter to INR3 per liter in petrol and INR10 per liter?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: 13 to 3 and 10 to nil. Those were the kind of discounts that we were required to give to OMCs. Sabri Hazarika: So right now also we are at zero or right now again it has come back?

    Answer, bhaskar phukan

    Bhaskar Jyoti Phukan: No, right now it has again reappeared. So we are giving now some value, but it gets calibrated month on month to reflect the delta between crude and product cycle. Page 15 of 22 Oil India Limited August 10, 2026 Sabri Hazarika: Is it connected to the SAED or it is like independent of the SAED?

    Answer, trailukya borgohain

    Trailukya Borgohain: Yes Mr. Sabri. We are are ramping up the production by doing all work whatever can be done, but to increase to the next level we are also doing some other things like near field exploration. At the same time we are doing like the work over, production enhancement, optimization, these are some of the drives and we are increasing with it getting whatever they get good technologies we can including hydro frac, you can say radial drilling. So we are doing. So we have we have some thoughts in mind to go to 4.2. If you if you look at our FY29 kind of target, we are targeting around up to around 4.2. Maybe it goes beyond that.

    Answer, trailukya borgohain

    But that will also depend a little bit of kind of our own near field exploration. That is one important aspect.

  8. Question

    Sabri Hazarika: Okay. So 4.2 from the main producing area. This doesn't include any deep water, nothing of that sort, right?

    Answer, trailukya borgohain

    Trailukya Borgohain: Mainly main producing areas. And also we are ramping up production in Rajasthan. Sabri Hazarika: Okay. And just one last small question, any impact of the recent floods on your operations?

Questions about this call

When was the Oil India Q1 FY27 earnings call transcript filed?
Oil India filed the transcript with the exchange on 12 Aug 2026. This page is built from that transcript.
What does this page list?
113 statements from the transcript across 10 topics, 69 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 18 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.