Earnings call
Tata Power Company Q3 FY26 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The transcript names the quarter but not the year. The year is worked out from the date it was filed.
The company expects more states to come up for distribution-sector public-private partnerships in the next 6 to 9 months, based on incentives and concessions, especially states with huge financial losses in their distribution business. The company has done 1.9 gigawatt, including third party and 600 megawatt of its own capacity addition. EBITDA increased nearly 12% year-on-year to Rs. 3,913 crores for the quarter, compared to the previous year. Under the Prime Minister's Surya Ghar program, 1 crore houses were supposed to be done and 25 lakhs had been done; another 50 lakhs, or 5 million, were added in this budget. Net debt to underlying EBITDA is 3.4 and net debt to equity is 1.2; it expects its calibrated growth to continue in future quarters.
The numbers management gave
Results
- EBITDA increased nearly 12% year-on-year to Rs. 3,913 crores for the quarter, compared to the previous year.
Show source
Looking at the financial performance of the Company for the quarter, we have given a very strong operational and financial performance with the EBITDA increase of nearly 12% year-on- year at Rs. 3,913 crores compared to the previous year.
- PAT increased marginally to Rs. 1,194 crores for the quarter despite Mundra being non-operational and having a substantial hit.
Show source
Similarly, the PAT has increased marginally to Rs. 1,194 crores, despite Mundra being non-operational for the quarter and having a substantial hit because of that.
- EBITDA jumped 12% year-on-year to Rs. 11,874 crores for the 9-months, compared to Rs 10,639 crores.
Show source
For the 9-months, the EBITDA has jumped 12% year-on-year to Rs. 11,874 crores as compared to Rs 10,639 crores.
- PAT was up 7% for the 9-month period to Rs 3,702 crores.
Show source
Similarly, the PAT is up by 7% for the 9- month period to Rs 3,702 crores.
- Solar cell and module manufacturing plant profit after tax went up to nearly Rs. 251 crores in the quarter, compared to Rs. 112 crores last year.
Show source
This quarter, what we have seen is many of our new businesses have come to age, whether we look at our solar cell and module manufacturing, where there has been a huge increase in our plant profit after tax, which has gone up to nearly Rs. 251 crores in the quarter compared to Rs. Page 2 of 17 The Tata Power Company Limited February 4, 2026 112 crores last year.
- Solar cell and module manufacturing plant delivered a PAT of Rs. 592 crores for the 9-month period, an increase of 154% compared to Rs. 233 crores in the last year 9-months.
Show source
For the 9-month period, the plant has delivered a PAT of Rs. 592 crores, which is an increase of 154% compared to Rs. 233 crores in the last year 9-months.
Show 33 more statements
Results
- The company crossed one gigawatt in the 9-months period in rooftop, and executed 372 megawatt in this quarter compared to 173 MW in the previous year.
Show source
We crossed one gigawatt in the 9-months period and in Q3, in this quarter, we executed 372 megawatt compared to 173 MW in the previous year.
- Rooftop PAT increased to Rs. 111 crores in the quarter, compared to Rs. 60 crores last year.
Show source
The rooftop PAT has increased in the quarter to Rs. 111 crores compared to Rs. 60 crores last year.
- Rooftop PAT was Rs. 324 crores in the 9-month period, compared to Rs. 110 crores in the previous year 9-months.
Show source
In the 9-month period, it has gone to Rs. 324 crores compared to Rs. 110 crores in the previous year 9-months.
- Odisha Discoms profit went up to Rs. 226 crores in the quarter, compared to Rs. 86 crores last year.
Show source
The profit of Odisha Discoms has gone up to Rs. 226 crores in the quarter compared to Rs. 86 crores last year.
- Odisha Discoms profit went to Rs. 505 crores in the 9-month period, compared to Rs. 164 crores in the previous year, 9-months.
Show source
And in the 9- month period, it has gone to Rs. 505 crores compared to Rs. 164 crores in the previous year, 9- months.
- The company had a positive EBITDA impact of Rs. ~300 crores from Mundra last year, which was not present this year and was compensated by its rooftop, manufacturing and Odisha businesses.
Show source
That is not there this year and that is being compensated from our rooftop business, from our manufacturing business and our Odisha business.
- Delhi Discom had a one-off from a regulatory order for truing up tariffs for 2022-2023.
Show source
There is a one-off that we have got in Delhi Discom because of the regulatory order that we got for truing up of our tariffs for 2022-2023.
- The company booked closer to about Rs. 800 odd crores of losses for the 9 months.
Show source
Sanjeev Churiwala: I think all put together when we look at 9 months, it is closer to about Rs. 800 odd crores of losses that we have booked.
- Mundra plant had been shut for 6 months, and the company did not receive capacity charges while the plant was shut.
Show source
Because Mundra has been shut for 6 months now and of course when the plant is shut, we do not get the capacity charges.
- The company booked Rs. 800 crores as a loss for Mundra.
Show source
So to that extent the Rs. 800 crores have been booked as a loss.
- TPDDL had a total regulatory impact of about Rs. 344 crores for 6 months, compared with a similar true-up impact of Rs. 333 crores last year; the corresponding same period last year also had a Rs. 332 crores order impact for Mundra.
Show source
Sanjeev Churiwala: For 6 months, which again to your earlier point, we have been reporting that in the earlier quarter and this quarter, the total regulatory impact at TPDDL is about Rs. 344 crores.
- TPDDL's regulatory impact reduced PAT by about Rs. 344 crores in the third quarter.
Show source
Sanjeev Churiwala: In the third quarter, PAT impact is about Rs. 344 crores on TPDDL regulatory impact.
- TPDDL's regulatory impact provided an EBITDA benefit of Rs. 460 crores in the third quarter.
Show source
Sanjeev Churiwala: Yes, so it is Rs. 460 crores at the EBITDA level.
- A negative PAT margin on a project, most likely in Solar EPC, was eliminated for positive Rs. 60 crores because of the contractual nature of the agreement.
Show source
So, one of the projects could be a negative PAT margins for most likely for the Solar EPC, which now has been eliminated for positive Rs. 60 crores.
- Solar EPC's overall PAT was positive at Rs. 183 crores.
Show source
Sanjeev Churiwala: As you can see, Solar EPC overall PAT is Rs. 183 crores.
- Rs. 60 crores was included in elimination for in-house supply contracts that had a loss, as required by the accounting standard.
Show source
So, as a result, Rs. 60 crores is in elimination.
- Maithon commissioned the FGD and is receiving regulatory returns on the regulatory asset, with an impact of about 15 odd crores.
Show source
So, that impact of that is about 15 odd crores.
- The true-up order for 2022-23 added Rs. 400 crores of regulatory assets to the company.
Show source
The true-up order has come for 2022-23, which has given another Rs. 400 crores additional regulatory assets to the company.
- The regulatory asset came down by Rs. 460 crores during the quarter.
Show source
But in actual, during the quarter, it has come down by Rs. 460 crores.
- Tata Power's module sales breakup was about 168 megawatt peak for ALMM and 795 megawatt peak for DCR, about 962 megawatt peak in total.
Show source
Both put together is about 962.
- Tata Power's Odisha discoms had better performance in the quarter and in the 9-month of this year following work that brought about a financial and operational turnaround.
Show source
And that is why you are seeing a much better performance in this quarter as well as in the 9-month of this year.
- Tata Power’s Odisha distribution business earned about close to Rs. 800 crores of cash in Quarter 3.
Show source
Sanjeev Churiwala: And to add to your question whether it is converted to cash, absolutely if you look at Quarter 3 itself, when we look at the distribution cash flows, largely Odisha, we have earned about close to Rs. 800 crores of cash only for the quarter.
- Tata Power targets a PAT margin of close to 5% to 6% every quarter on the EPC side, although quarter-to-quarter true-ups could pose challenges.
Show source
Sanjeev Churiwala: I think on the EPC side, we kind of target PAT margin of close to 5% to 6% every quarter.
- Tata Power’s solar rooftop margin is about 14.5%, and its large projection rooftops margin is close to about 9.1%.
Show source
Solar rooftops, about 14.5% and then we look at large projection rooftops, it is close to about 9.1%.
- Tata Power delivers a PAT margin of about close to 8% on a consolidated basis.
Show source
And PAT margin, we are kind of delivering on a consol basis which is about close to 8%.
- Tata Power expects its sustainable PAT margin to be reflected in Quarter 3 at 7.6% and in 9-months at 7.8%.
Show source
Because even Quarter 3, when we look at the Quarter 3, PAT margin is 7.6 and 9-months is also 7.8.
- Existing portfolio of businesses increased and helped raise EBITDA for this quarter, notwithstanding the Delhi Discom one-off.
Show source
But notwithstanding that also, there has been increase in our existing portfolio of businesses and that has helped us for the increase in EBITDA for this quarter.
- Tata Power's collection and billing efficiencies have improved, and the performance of Odisha discoms has improved every quarter over the last three years.
Show source
And the performance of Odisha discoms have improved tremendously.
- Odisha discoms' billing coverage has improved, losses have reduced, and electricity spilling has reduced drastically.
Show source
Loss reduction has happened.
- The performance of all four Odisha discoms has been very good. Replaced by a later filing.
Show source
So, I think overall the performance of all the 4 discoms has been very good.
Money and capital
- Net debt to underlying EBITDA is 3.4 and net debt to equity is 1.2; it expects its calibrated growth to continue in future quarters.
Show source
We are always working towards improving our performance and to that extent you will see that our financial metrics are very, very conservative and we continue in spite of the type of CAPEX that we are incurring, we continue to have a net debt to underlying EBITDA of 3.4 and a net debt to equity of 1.2 and we expect that the type of calibrated growth we have will continue in future quarters also.
- Tata Power expects to spend close to 15,000 crores-20,000 crores-25,000 crores of CAPEX every year and intends to maintain its debt equity and debt to EBITDA profile on a very conservative basis.
Show source
So, we are on a very comfortable journey, given that we will be spending close to 15,000 crores-20,000 crores-25,000 crores of CAPEX every year.
- Maithon is a regulatory asset, and Tata Power is not doing any CAPEX there; Tata Power expects the debt to reduce as it continues earning cash from the regulatory asset.
Show source
So, as per the regulatory asset, we will keep on earning the cash over there and to that extent, the debt will only reduce.
What it expects ahead
What management expects
- The company expects more states to come up for distribution-sector public-private partnerships in the next 6 to 9 months, based on incentives and concessions, especially states with huge financial losses in their distribution business.
Show source
Similarly, we are expecting some more announcements on the distribution sector in the next 6 to 9 months whereby certain more states will come up for public- private partnerships based on some of the other incentives and concessions to be provided to them, especially to states which have huge financial losses in their distribution business.
- Target this year was to set up 2.6 gigawatt, including third party and its own capacity.
Show source
We have already done 1.9 gigawatt which includes third party and also it includes 600 megawatt of our own capacity addition.
- The company expects to complete another 400 to 500 megawatt of projects in this quarter and has projects which will come up in 2027, mostly its own, as its third party projects including SJVN, MSEDCL and NHPC have got over.
Show source
We have another 400 to 500 megawatt of project which we are pursuing which we expect to complete in this quarter and then we have projects which will come up in 2027, wherein most of the projects will be our own because all our so- called third party projects have got over including the SJVN, MSEDCL, NHPC.
- Tata Power will add another 500 megawatt in this quarter and will do 2.7 gigawatts in this financial year.
Show source
Dr. Praveer Sinha: So, this year, we will do something like another 500 megawatts.
- Tata Power will do 100% of the so-called 2.5 for itself from FY'27 onwards.
Show source
But next year, the so-called 2.5, we will do 100% for ourselves.
- Rooftop additions in India in this year will be at least 50% to 60% more than last year, and Tata Power expects additions to continue increasing going forward.
Show source
And I think the capacity adds that you are seeing last year, at least 50% to 60% more will happen in this year and we will continue to see the increase going forward.
Show 9 more statements
What management expects
- From 1st June, only DCR cells and DCR modules are utilized, and Tata Power expects more of its own cells and modules in the next two quarters.
Show source
But I think in the next two quarters, we will have more of our own cells and our own modules, because from 1st June only DCR cell and DCR modules are utilized.
- Tata Power has capacity to execute 2.7 gigawatts next year and may add more than 2.5 gigawatts, up to 3 gigawatts of capacity.
Show source
We may do more than 2.5 while we have taken the initial estimate of 2.5, we can go up to 3 gigawatts of capacity add.
- The company will start discussing the SPPA on a similar basis with the other states and may start operating the plant by the end of this month.
Show source
And on a similar basis, we will parallelly start discussing with the other states so that we are in a position to start operation of the plant, maybe by the end of this month.
- After the SPPA was agreed with Gujarat except for one point, Tata Power Company Limited will circulate it to other states and, once it gets their in-principle approval, will try to operate the plant and schedule power to them based on their acceptance.
Show source
Now that the SPPA is agreed with Gujarat, leave one point, we will be circulating this to other states and once we get their in-principle approval, we will try to start operating the plant and scheduling it to them based on their acceptance.
- The company hopes to find out the other procurer states’ comfort level in the next few weeks and then start scheduling power.
Show source
So, hopefully in the next few weeks, we should be able to find out the comfort level of the other procurer state and then we will start scheduling the power.
- Tata Power expects the cells it produces to be fully consumed internally.
Show source
So, you will see more or less that whatever cell that we produce is fully consumed internally.
- The company expects its new businesses to further stabilize and produce better results in future quarters. Replaced by a later filing.
Show source
I think what is important is that many of our new businesses have now started showing results and in the future quarters, they will further stabilize and produce much better results than what we have seen in the previous quarters.
- Customers who have installed smaller rooftop capacities are expected to augment them in future as their energy requirements increase. Replaced by a later filing.
Show source
We would also find that people will, those who have put up smaller capacities will augment it in future based on their increase in energy requirement.
- Tata Power expects the speed of rooftop additions in India to increase further. Replaced by a later filing.
Show source
I do expect that the speed will go much further.
What it is building and selling
Projects and capacity
- The company has done 1.9 gigawatt, including third party and 600 megawatt of its own capacity addition.
Show source
We have already done 1.9 gigawatt which includes third party and also it includes 600 megawatt of our own capacity addition.
- Tata Power has a pipeline of nearly 5.5 gigawatts of projects to execute within the next two years.
Show source
As you are aware, we have a pipeline of nearly 5.5 gigawatts of projects, which we need to execute.
- The company got a letter of intent in the last quarter for the Hinjewadi line and expects some more projects in this quarter.
Show source
We also got a letter of intent in the last quarter for the Hinjewadi line and we are expecting some more projects in this quarter also.
- The company expects work on its PSP project in Bhivpuri and hydro plant in Bhutan to meet the timelines it has set for both projects.
Show source
Work on all our other businesses, especially our PSP project in Bhivpuri and our hydro plant in Bhutan are going at full swing and they will meet the timelines that have been set by us for both these projects.
- Some wind projects will be commissioned in this quarter, and many wind projects and some solar projects will be commissioned between this quarter and the next quarter.
Show source
So, I think many of the wind projects will get commissioned, as also some solar projects will get commissioned between this quarter and the next quarter.
- Tata Power is implementing the ULA scheme, or utility-led scheme, in Odisha.
Show source
We are doing it in Odisha, which is known as the ULA scheme, utility-led scheme, which is there.
Show 13 more statements
Projects and capacity
- Tata Power received third-party orders much earlier than its own capacity orders, which it received last year; execution is proceeding based on the agreed timelines.
Show source
So, based on the timelines that have been agreed with, these are getting executed.
- Tata Power is timing project completion with transmission-line completion because many transmission lines were delayed, to avoid projects being stranded and unutilized when transmission lines are unavailable.
Show source
As you are aware, many of the transmission lines got delayed and we are now timing the project completion with the transmission line completion so that it should not be that these projects are left stranded and unutilized when the transmission lines are not available.
- Tata Power's intrastate projects have not faced as much transmission-line challenge as its interstate projects.
Show source
But in interstate transmission lines, there have been challenges.
- Tata Power's third-party and internal projects were synchronized with the commissioning of transmission lines.
Show source
Our projects that we were doing for third parties were synchronized with the commissioning of those transmission lines.
- Some transmission lines that were due last year are expected by March this year, may be delayed until May or June this year, or are expected by December.
Show source
Some places, some of the lines which were supposed to come last year have got delayed and they are expected by March this year, or maybe it may go up to May, June this year and some by December.
- Tata Power is examining the technology, equipment and size for its Wafer and Ingot plan, and will take some more time to make the final decision.
Show source
And we will take some more time to take the final decision.
- Tata Power said the project pipeline can be sufficiently developed once some of the big sum up and some of the new lines are awarded. Replaced by a later filing.
Show source
So, I think we will have to see how quickly some of the big sum up and some of these new lines are awarded, so that the project pipeline can be sufficiently developed.
Demand and pricing
- Under the Prime Minister's Surya Ghar program, 1 crore houses were supposed to be done and 25 lakhs had been done; another 50 lakhs, or 5 million, were added in this budget.
Show source
In this budget, another 50 lakhs have been added, 5 million has been added.
- Many C&I customers and customers seeking larger capacities of 10 kilowatt and above are adopting rooftop solar without financial support.
Show source
Without the financial support also, we are finding that a lot of C&I customers are also going as also customers who want larger capacities, 10 kilowatt and above.
Segments
- New projects will cater to its own department. Replaced by a later filing.
Show source
So, all the new projects that will come up will be catering to our own department.
Deals and partners
- The company hopes to close the remaining SPPA point with Gujarat in the next 2-3 weeks.
Show source
We hope that in the next 2-3 weeks, we will be able to close that.
- The company has concluded the arrangement with Gujarat on all SPPA issues except one point.
Show source
We have been able to now conclude the arrangement with Gujarat on all the issues of the SPPA, except one point.
- TP Solar will provide modules to Genco, and Solar EPC will provide services to Genco and third parties.
Show source
So, TP Solar will provide services to the Genco in terms of supply of modules.
Risks, rules and outside factors
Outside factors
- Tata Power expects to get highest price realization when input material costs rise, because output material costs also rise for everyone manufacturing modules in the country.
Show source
So, by these phenomena, we will get highest price realization.
- Tata Power said the mix of solar and wind in most of its projects means there is not going to be any substantial impact from the increase in input material costs.
Show source
So, from whatever we know, there is not going to be any substantial impact.
Rules and policy
- The company expects the Electricity Act Amendment, once put in Parliament for approval in this budget session, to bring more opportunities for parallel licensing in the country.
Show source
On our distribution business, we expect that some changes will happen by way of the Electricity Act Amendment and we are expecting that once the Electricity Act Amendment is put in the Parliament for approval in this budget session, we will get many more opportunities on parallel licensing in the country.
- Tata Power said renewable projects are getting delayed because of connectivity issues, existing connectivity approvals have been given with no fresh approvals being given, and the pace of renewable projects coming up will be a little slower until new evacuation lines are set up.
Show source
So, all the existing connectivity approvals have been given and there is no fresh approval being given.
Everything else said on the call
Group structure
- The 400 kV Koteshwar–Rishikesh transmission line project was executed under NRSS XXXVI Transmission Limited (NRSS), acquired by Resurgent Power Ventures Pte Limited, a joint venture promoted by Tata Power, ICICI Bank Limited and global investors.
Show source
We were able to commission some of our TBCB projects such as the 400 kV Koteshwar-Rishikesh transmission line.
Other
- Mundra and other thermal power plants are assessed at the PAT level.
Show source
Sanjeev Churiwala: At the PAT level because for Mundra and other thermal power plants, PAT level matters the most.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Mohit Kumar: Good evening, sir and congratulations on the strong numbers in solar manufacturing and solar rooftop especially. My first question is on Mundra. Of course, you are trying to resolve with the Gujarat and you will subsequently go to the other procurers. My question is, till the time we get the final resolution from the other procurers, is it fair to assume that you'll be able to run the capacity which you only link to Gujarat in the interim? Dr. Praveer Sinha: This is all under discussion.
Answer, praveer sinha
We had a few months back a joint meeting of all the procurers during which it was agreed that Gujarat will take the lead in finalizing the SPPA term. Now that the SPPA is agreed with Gujarat, leave one point, we will be circulating this to other states and once we get their in-principle approval, we will try to start operating the plant and scheduling it to them based on their acceptance. So, hopefully in the next few weeks, we should be able to find out the comfort level of the other procurer state and then we will start scheduling the power.
Question
Mohit Kumar: Understood. My second question is, how do you think about the renewable capacity addition over the next three months? I think the target we have set for ourselves was 2-2.5 gigawatt, if I remember correctly. I think you added on 600 megawatt if I am not wrong in the last nine months. Do you think we will still be able to meet that 2-gigawatt target? Dr. Praveer Sinha: So, our target this year was that we will set up 2.6 gigawatt which included third party and ourselves.
Answer, praveer sinha
We have already done 1.9 gigawatt which includes third party and also it includes 600 megawatt of our own capacity addition. We have another 400 to 500 megawatt of project which we are pursuing which we expect to complete in this quarter and then we have projects which will come up in 2027, wherein most of the projects will be our own because all our so- called third party projects have got over including the SJVN, MSEDCL, NHPC. So, all the new projects that will come up will be catering to our own department.
Question
Sumit Kishore: Good evening, sir. When I look at the Q3 FY'26 EBITDA to Q3 FY'25 the delta of Rs. 432 crores, it is almost entirely explained by the bump up that has happened in the Delhi distribution business. Although the Delhi distribution business has seen a 2% decline in power purchase and sale, there seems to be some regulatory adjustment there which has bumped up the EBITDA. So, why hasn't it been properly called out in accounts in the presentation and what are the details there because it seems to be explaining the whole growth for the quarter? Dr. Praveer Sinha: What you have to do is this.
Answer, praveer sinha
You have to see the increase in EBITDA considering that last year we had EBITDA impact from Mundra where there was a positive EBITDA of Rs. ~300 crores. That is not there this year and that is being compensated from our rooftop business, from our manufacturing business and our Odisha business. There is a one-off that we have got in Delhi Discom because of the regulatory order that we got for truing up of our tariffs for 2022-2023. But notwithstanding that also, there has been increase in our existing portfolio of businesses and that has helped us for the increase in EBITDA for this quarter.
Question
Sumit Kishore: Okay, but what is the impact for 9-months that you have trued up in your numbers, if not the 3rd Quarter?
Answer, sanjeev churiwala
Sanjeev Churiwala: I think all put together when we look at 9 months, it is closer to about Rs. 800 odd crores of losses that we have booked.
Question
Sumit Kishore: Which is losses for Mundra?
Answer, sanjeev churiwala
Sanjeev Churiwala: For Mundra only, yes. Because Mundra has been shut for 6 months now and of course when the plant is shut, we do not get the capacity charges. Now 6 months, the plant is still there. So to that extent the Rs. 800 crores have been booked as a loss.
Question
Sumit Kishore: This is at the EBITDA level or the PAT level?
Answer, sanjeev churiwala
Sanjeev Churiwala: At the PAT level because for Mundra and other thermal power plants, PAT level matters the most. Page 5 of 17 The Tata Power Company Limited February 4, 2026 Sumit Kishore: Okay, asking is for Delhi distribution, for the 9-month period, what is the true-up benefit that you have taken in numbers?
Answer, sanjeev churiwala
Sanjeev Churiwala: For 6 months, which again to your earlier point, we have been reporting that in the earlier quarter and this quarter, the total regulatory impact at TPDDL is about Rs. 344 crores. We also had a similar true-up impact last year of Rs. 333 crores. That is there, plus in the last year, corresponding same period, we had the order impact for Mundra at Rs. 332 crores. All of that have been appropriately reported in the accounts.
Question
Sumit Kishore: 3rd Quarter only also. Because you are saying that the 6-month number was clearly mentioned.
Answer, sanjeev churiwala
Sanjeev Churiwala: In the third quarter, PAT impact is about Rs. 344 crores on TPDDL regulatory impact.
Question
Sumit Kishore: So, the EBITDA benefit is more?
Answer, sanjeev churiwala
Sanjeev Churiwala: Yes, so it is Rs. 460 crores at the EBITDA level.
Question
Sumit Kishore: Yes, I am looking at the cluster-wise performance. So, because you are doing projects which Tata Power is setting up on its own books, I am assuming that part of the modules are going from your manufacturing facility to your own projects. So, which is why the elimination needs to happen on consolidation because it is being consumed by your own entity. So, why is the elimination a positive number?
Answer, sanjeev churiwala
Sanjeev Churiwala: That is what I am saying. So, if you look at the renewable, you have this Genco, Solar EPC, TP Solar. So, TP Solar will provide services to the Genco in terms of supply of modules. Similarly, the Solar EPC will also do the services for Genco and as well as the third party. So, of course, there are many, many projects within that. However, if any project is having a negative loss because of the contractual nature of the agreement, that also needs to be eliminated. So, one of the projects could be a negative PAT margins for most likely for the Solar EPC, which now has been eliminated for positive Rs. 60 crores.
Question
Sumit Kishore: There was a loss which you have made in the Solar EPC business because the elimination has then become a positive thing.
Answer, sanjeev churiwala
Sanjeev Churiwala: As you can see, Solar EPC overall PAT is Rs. 183 crores. It is positive. But let us say there are 100 different projects happening, which include in-house supply. So, as per the accounting standard, any contract which even has a loss for in-house supply also needs to be eliminated. So, as a result, Rs. 60 crores is in elimination.
Show 22 more questions
Question
Sumit Kishore: This is very clear. Just one last point. There is some positive impact for FGD recovery in Q3 and 9 months for Maithon, which also seems to be bumping up the number quite dramatically on a year-on-year basis in Q3 particularly. So, what is that impact? That is my last question.
Answer, sanjeev churiwala
Sanjeev Churiwala: So, we have commissioned the FGD for Maithon. And given that this is a regulatory asset, we are getting the regulatory returns. So, that impact of that is about 15 odd crores. And you will see that reckoning happening in the subsequent quarters now.
Question
Apporva Bahadur: Hi, sir. Thank you for the opportunity. Sir, you briefly mentioned about more opportunities on the distribution from the PPP side, possibly due to some sort of a package for the discoms. Can you give some more color on that? What sort of package are we posing over here? Dr. Praveer Sinha: So, there are many states who have huge financial losses.
Answer, praveer sinha
And so, some of those states will be given the opportunity of a long-term loan at zero rate of interest. But there will be certain caveats in terms of they need to go for PPP and only against that they will be given. So, those are states which are already identified in terms of the type of financial losses they have. And it is expected that once that is announced, we will have a few states who will be availing that opportunity and going for PPP. Apporva Bahadur: So, when should we expect this around, any timelines? Dr. Praveer Sinha: I think in the next 6 to 9 months, this should happen.
Question
Apporva Bahadur: Okay. Understood. Sir, I also wanted to sort of understand our strategy on the rooftop side. Commendable, I mean, the improvement that has happened and the growth and profitability. But has it reached some sort of a peak revenue or a peak profit or do we foresee more growth here? And secondly, any plans of cross-selling more, especially on the storage side? Dr. Praveer Sinha: Well, this is the tip of the iceberg, I would say.
Answer, praveer sinha
And the opportunity is phenomenal. What we are seeing is, again, the Prime Minister's Surya Ghar program, 1 crore houses were supposed to be done. We have already done only 25 lakhs. So, there is a huge number. In this budget, another 50 lakhs have been added, 5 million has been added. So, there is a huge opportunity with the type of financial support that is being provided. Without the financial support also, we are finding that a lot of C&I customers are also going as also customers who want larger capacities, 10 kilowatt and above.
Answer, praveer sinha
So, I think this is a business which is going to be there for a very, very long time. We would also find that people will, those who have put up smaller capacities will augment it in future based on their increase in energy requirement. And this business, I do feel it is something which is very futuristic and will keep on improving going forward.
Question
Apporva Bahadur: Okay, sir. Sir, lastly, one theoretical question. Now that we are close to solving Mundra in terms of the supplemental PPA, in case the government again sort of implements Section 11, because the last time it implemented, it was not just for Tata Power, but for all the imported coal-based assets. So, does Section 11 supersede the supplementary PPA or will we be kept out of the purview? Page 8 of 17 The Tata Power Company Limited February 4, 2026 Dr. Praveer Sinha: Section 11 is imposed when there is a shortage of power.
Answer, praveer sinha
And hopefully, before that happens, we should be in a position to close this arrangement because this power is required by all the procurer states and if they go for Section 11, they have to pay more. So, it makes more sense for them to go ahead and finalize the SPPA rather than going to Section 11.
Question
Apporva Bahadur: Okay, sir. Thank you so much. All the best.
Answer, praveer sinha
Let's wait for that clarity to come from the government. Puneet: Okay. Secondly, on the Delhi distribution side, there was this talk about reducing regulated assets. But in this quarter, the number has gone up again. Any progress that you're seeing there or it's a slow outcome? Dr. Praveer Sinha: So, the regulatory asset per se has gone down.
Answer, praveer sinha
But what has happened is that there is one more order that has come. The true-up order has come for 2022-23, which has given another Rs. 400 crores additional regulatory assets to the company. So, that's why it's looking high. But in actual, during the quarter, it has come down by Rs. 460 crores. So, it's come down by Rs. 460 crores. Puneet: Okay, understood. And lastly, if you can talk about which are the big renewable projects that you will commission in FY'27?
Answer, praveer sinha
There are some more wind projects which will get commissioned in this quarter. So, I think many of the wind projects will get commissioned, as also some solar projects will get commissioned between this quarter and the next quarter. Puneet: Understand. And what should be the run rate for the year that we should assume for your own and separate? Dr. Praveer Sinha: So, this year, we will do something like another 500 megawatts.
Answer, praveer sinha
But next year, the so-called 2.5, we will do 100% for ourselves. Puneet: Okay. So, FY'27 onwards. Dr. Praveer Sinha: Yes.
Question
Ketan Jain: Thank you. Good evening, sir. Congratulations on a strong performance in rooftop and module manufacturing. Just on the rooftop side, what's your outlook on the rooftop addition in India? I think, year-to-date, we have added around 7 to 7.5 gigawatts. Will this continue going forward in '27 and '28? Dr. Praveer Sinha: I think if you look at the stage of rooftop addition in the country, as also by us, it has increased tremendously with much better supply chain, much better channel partner, much better arrangement to supply and erect information.
Answer, praveer sinha
I do expect that the speed will go much further. Also, the government has come up with a new scheme, which is the state discoms have been asked to go ahead and implement it. We are doing it in Odisha, which is known as the ULA scheme, utility-led scheme, which is there. And I think the capacity adds that you are seeing last year, at least 50% to 60% more will happen in this year and we will continue to see the increase going forward.
Question
Ketan Jain: Understood. Thanks, sir. So, my next question is on the module manufacturing. I could see that we have sold around 960 megawatt of modules. And we have also produced 960 megawatt of cells. So, is it right to assume that all of these cells are DCR module cells? Dr. Praveer Sinha: So, in the last quarter, we had some ALMM, that is, imported cells we had used, because the order was for supply of imported cells with domestic modules.
Answer, praveer sinha
But I think in the next two quarters, we will have more of our own cells and our own modules, because from 1st June only DCR cell and DCR modules are utilized. So, you will see more or less that whatever cell that we produce is fully consumed internally.
Question
Ketan Jain: Understood, sir. So, the 962 megawatt is all the external sales which we have done?
Answer, sanjeev churiwala
Sanjeev Churiwala: Largely, as mentioned for Rooftop and our own businesses. And the rough breakup is a small quantity of about 168 megawatt peak for ALMM and DCR we have done 795 megawatt peak. Both put together is about 962.
Question
Ketan Jain: So, external would be just 20%-25%?
Answer, sanjeev churiwala
Sanjeev Churiwala: External would be even smaller than that. Very small percentage.
Question
Dr. Praveer Sinha: It's very difficult to...
Answer, sanjeev churiwala
Sanjeev Churiwala: I think it's difficult for us to give a breakup because a large quantity of that is in-house consumed in our various businesses. But if you look at the P&L, which is also uploaded, we will have an EBITDA margin of close to 28% for the quarter. And for 9 months, we are delivering close to 24% of EBITDA margin.
Question
Ketan Jain: And just one addition to this is, what are the challenges are we facing in execution of our own capacity? Or is it a strategical call that we are first finishing our third-party order book and then focusing on our existing, our own capacity or is there any challenges you're facing in execution? Dr. Praveer Sinha: This was timing issue only.
Answer, praveer sinha
So, the third-party orders we had received much earlier. And our own capacity, our orders that we got last year. So, based on the timelines that have been agreed with, these are getting executed.
Question
Satyadeep Jain: Hi, thank you. Sir, I just wanted to ask on renewable energy execution once again. I know you're looking at 1 gigawatt broadly commissioning this year. In the last nine months, it's been 600 megawatt against industry at 38 gigawatt. Even if you strip out solar rooftop, that's about 30 gigawatt, 2% market share for Tata Power. And that 1 gigawatt that you're looking at now is despite third-party execution, the initial expectation was 1.5 to 2 gigawatt. So, there seems to be a miss and we are seeing it across the board for some of the larger players, misses in terms of execution. But the industry is still adding a lot of capacity, which means it's a long, very long tail. In cas
Answer, praveer sinha
And that means that we have inherent capacity to execute such large capacity and we will add another 500 megawatt in this quarter. So, 2.7 gigawatts we will be doing in this financial year. If we look at next year, we have a capacity to execute 2.7. We may do more than 2.5 while we have taken the initial estimate of 2.5, we can go up to 3 gigawatts of capacity add. As you are aware, we have a pipeline of nearly 5.5 gigawatts of projects, which we need to execute. So, within the next two years, we will execute. Also, it's not just executing the project, but also the timeline when the transmission line comes up.
Answer, praveer sinha
As you are aware, many of the transmission lines got delayed and we are now timing the project completion with the transmission line completion so that it should not be that these projects are left stranded and unutilized when the transmission lines are not available. So, I think it's a question of better planning, better phasing, and staggering it in such a way that it is able to produce as soon as they are implemented and the power can be executed.
Question
Satyadeep Jain: Let me ask it another way. When the year started, obviously, you're looking at 1.5-2 gigawatts if it roll back one year ago. So, at that time also, you had the third party order book. So, is it not some delay in execution, transmission or is it purely that compared to initial expectations, you prioritized third party book? And the delay in commissioning transmission has been an industry- wide phenomenon. But despite that, we are looking at 38 gigawatts capacity for the entire industry. But still, are you saying the delay in commissioning for capacity delayed capacity commissioning for certain players more than it did for others? Just in the context of overall addition, trying
Answer, praveer sinha
The intrastate projects, the challenge of transmission lines is not so much. But in interstate transmission lines, there have been challenges. Our projects that we were doing for third parties were synchronized with the commissioning of those transmission lines. For our internal projects, again, it was synchronized. Some places, some of the lines which were supposed to come last year have got delayed and they are expected by March this year, or maybe it may go up to May, June this year and some by December. So, that's why the project completion has to be staggered in such a way that it meets the timeline for evacuation. Otherwise, there's no point in setting up of the plant if the power cannot be evacuated.
Question
Satyadeep Jain: Perfect. Sir, one more question on Odisha. Just we are seeing increase in income. Largely, it seems to be reduction in ECL losses. Just wanted to understand what is driving that reduction in ECL and is it also reflected in actual increase in cash profit? Is it mainly accrual or actually your cash receipts have also increased significantly in Odisha and what has led to that ECL reduction? Dr. Praveer Sinha: Well, I think our collection efficiencies have improved.
Answer, praveer sinha
Our billing efficiency has improved. And the performance of Odisha discoms have improved tremendously. If you track it in last three years, the performance has been improving every quarter. And the coverage of billing has Page 12 of 17 The Tata Power Company Limited February 4, 2026 been better. Loss reduction has happened. Spilling of electricity which was there has reduced drastically. So, I think overall the performance of all the 4 discoms has been very good.
Answer, praveer sinha
And we need to acknowledge that the type of work that they have done to bring about a turnaround, not only financially, but also operationally is phenomenal. And that is why you are seeing a much better performance in this quarter as well as in the 9-month of this year.
Answer, sanjeev churiwala
Sanjeev Churiwala: And to add to your question whether it is converted to cash, absolutely if you look at Quarter 3 itself, when we look at the distribution cash flows, largely Odisha, we have earned about close to Rs. 800 crores of cash only for the quarter.
Question
Girish Achhipalia: Thank you, sir. So, my question was on your Wafer and Ingot plan, where are we right now and what is the size and any state incentives? That was the first question, sir. Dr. Praveer Sinha: This is under discussion.
Answer, praveer sinha
We are examining the technology, equipment, size, all those things. And we will take some more time to take the final decision.
Question
Girish Achhipalia: Okay. And from China, we are seeing wafer and polysilicon prices increase. Currently, we have, I think, more than 5 gigawatts under construction. So, how much of an equity IRR impact does this cost? Because you would be sourcing some of the raw materials from there, if you can quantify? Dr. Praveer Sinha: So, if the input material cost goes up, the output material cost also, because this is true for everyone who is manufacturing the modules in the country.
Answer, praveer sinha
So, by these phenomena, we will get highest price realization.
Question
Girish Achhipalia: Yes, I mean, but your EBITDA for your utility scale projects remains the same, but your gross block increases, right? So, I wanted to understand the equity IRR impact. Is it like 300 bps, 400 bps, or is it lower? Dr. Praveer Sinha: It is not having a great impact because we also have a mix of solar and wind in most of our projects.
Answer, praveer sinha
So, from whatever we know, there is not going to be any substantial impact.
Question
Anuj Upadhyay: Hi, sir. Thanks for the opportunity. The first is on the margin front across your EPC and the rooftop. So, during the quarter, the margin has fallen across both the segment. And probably I was of an opinion that with the complete operation of your cell and module capacity, this margin volatility across the EPC should come down significantly. So, could you just explain the reason for this fall in EPC margin and rooftop?
Answer, sanjeev churiwala
Sanjeev Churiwala: I think on the EPC side, we kind of target PAT margin of close to 5% to 6% every quarter. But if you look at within quarter-to-quarter, depending upon the true-up, there could be challenges. But by and large, that's what we have been targeting. Because if you look at the overall solar EPC margins, it's a very healthy margin overall. Solar rooftops, about 14.5% and then we look at large projection rooftops, it is close to about 9.1%. And PAT margin, we are kind of delivering on a consol basis which is about close to 8%.
Question
Anuj Upadhyay: Okay. So, this is what it should be on a sustainable basis?
Answer, sanjeev churiwala
Sanjeev Churiwala: That's what we think. Because even Quarter 3, when we look at the Quarter 3, PAT margin is 7.6 and 9-months is also 7.8.
Question
Anuj Upadhyay: Okay. And secondly, on a debt profile, sir, I can understand on the regulatory side where debt can go up. But say for companies like Maithon and your Coal SPV, the debt across the respective businesses has largely remained stagnant. So, any timeline on when can we expect the debt reduction happening over there?
Answer, sanjeev churiwala
Sanjeev Churiwala: I think the debt, what we see from a console basis, we have a debt equity of 1.2, a debt to underlying EBITDA of 3.4. So, we are on a very comfortable journey, given that we will be spending close to 15,000 crores-20,000 crores-25,000 crores of CAPEX every year. We will have debt in the books, but we want to ensure that we maintain our debt equity and debt to EBITDA profile on a very conservative basis.
Question
Anuj Upadhyay: For Maithon and Coal SPV. Page 14 of 17 The Tata Power Company Limited February 4, 2026 Sanjeev Churiwala: Maithon is a regulatory asset.
Answer, sanjeev churiwala
We are not doing any CAPEX. So, as per the regulatory asset, we will keep on earning the cash over there and to that extent, the debt will only reduce.
Question
Aniket Mittal: Actually, I had a question more at a sector level to understand. So, we have obviously seen renewable awarding pretty much dry up. And there seems to be some sort of deadlock here with 40 gigawatts of PPA unsigned. Just to understand your thoughts, what's the pushback that Discoms are having on signing PPAs? And when do you think renewable awarding in the country can sort of come back? Dr. Praveer Sinha: I think the renewable projects are getting delayed because of the connectivity issue.
Answer, praveer sinha
And in such time, new evacuation lines are set up. The pace at which the renewable projects are coming up. it will be a little slower. So, all the existing connectivity approvals have been given and there is no fresh approval being given. And until that happens, there's no point in tying up new renewable projects. So, I think we will have to see how quickly some of the big sum up and some of these new lines are awarded, so that the project pipeline can be sufficiently developed.
Questions about this call
- When was the Tata Power Company Q3 FY26 earnings call transcript filed?
- Tata Power Company filed the transcript with the exchange on 9 Feb 2026. This page is built from that transcript.
- What does this page list?
- 79 statements from the transcript across 11 topics, 48 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 32 questions and management's answers are listed in the order they were asked, as the transcript prints them.