Tata Power expects peak power to cross about 270 gigawatts in the next 1 to 2 months because of the heat wave across the country and the prediction of a severe impact because of El Nino. Tata Power expects 50% of its nearly 5 gigawatt of in-house projects under implementation to be completed in this financial year and the remaining 50% in FY '28. Tata Power's EBITDA increased by nearly 11% to INR16,090 crores in FY '26 because of strong performance in generation, transmission, distribution and renewables. Power demand increased by 2% in the last quarter. Tata Power's debt is approximately INR56,000 crores.
The numbers management gave
Results
- Tata Power's EBITDA increased by nearly 11% to INR16,090 crores in FY '26 because of strong performance in generation, transmission, distribution and renewables.
Show source
And the EBITDA, which has also gone up by nearly 11% to INR16,090 crores because of the strong performance of our existing businesses of generation, transmission, distribution and renewables.
- Tata Power's EBITDA increased by nearly 10% to INR4,216 crores compared to INR3,829 crores last year in the same quarter.
Show source
During the quarter also, we have seen our EBITDA has jumped by nearly 10% to INR4,216 crores compared to INR3,829 crores last year.
- Tata Power's PAT increased by 8% to INR1,416 crores compared to INR1,306 crores last year in the same quarter.
Show source
PAT has gone up by 8% to INR1,416 crores compared to INR1,306 crores last year in the same quarter.
- Tata Power's solar cell and module manufacturing plant delivered a PAT of INR857 crores during the year, more than double the previous year.
Show source
We have seen during the year, the plant has delivered a PAT of INR857 crores, which is more than double of the previous year.
- Tata Power's rooftop solar business had a PAT of nearly INR500 crores, INR499 crores, through the year.
Show source
And we have also seen not only in the quarter but through the year, the performance has been exceedingly well with a PAT of nearly INR500 crores, INR499 crores.
- Odisha DISCOM's PAT was INR809 crores this year, compared with INR439 crores in the previous year.
Show source
This year, we have a PAT of INR809 crores.
Show 13 more statements
Results
- Tata Power is operating the Mundra plant under Section 11, with the understanding that the tariff will be as per the SPPA, and this has been accounted for in its quarterly results.
Show source
We are already operating the plant under Section 11 but with the understanding that the tariff will be as per the SPPA, and that has been accounted for in our quarterly results.
- Tata Power received about INR333 crores of regulatory approvals in FY '25.
Show source
In fact, if you look at FY '25, we had about INR333 crores of regulatory approvals coming in.
- Tata Power had INR783 crores reflected this year from regulatory approvals.
Show source
This year, as you rightly picked up, INR783 crores is reflected.
- In some cases of curtailment, power evacuation allowed was at least 60%; in some places it was 80%, and in others 20% or 25%.
Show source
In some places, they have allowed 80%, in some places, it is at 20%, 25%.
- Tata Power’s rooftop business grew by 100% last year.
Show source
So, you have seen last year, it has grown by 100%.
- Tata Power recognized deferred tax in its books in quarter 4 because it has better visibility of profits in subsequent years and expects to utilize some carry forward losses within the time frame.
Show source
And as such, from a statutory purpose, we have to recognize the deferred tax in the books, which we have done in quarter 4 now.
- The service concession agreement balance movement in working capital relates to capex for the TBCB project.
Show source
Management: Capex related to TBCB project, it is there in the working capital.
- Rooftop solar installations doubled. Replaced by a later filing.
Show source
Similarly, rooftop solar has done exceedingly well with doubling of the installations.
Money and capital
- Tata Power's debt is approximately INR56,000 crores.
Show source
On the balance sheet also, I find that our debt is at approximately INR56,000 crores.
- Tata Power's capital expenditure was nearly INR13,000 crores in the last financial year.
Show source
And this is in spite of a capital expenditure of nearly INR13,000 crores in the last financial year.
- Tata Power expects capex of about INR25,000 crores for FY '27.
Show source
That is what we are expecting.
- Tata Power's capex next year is INR25,000 crores, including INR15,000 crores for 2.5 gigawatt of solar and wind, as well as capex for pumped storages, pure hydro and transmission; Tata Power's sense is that it will have a similar kind of capital outlay going forward.
Show source
But then you have capex coming up in pumped storages, capex coming up in pure hydro, so a combination of all of this -- transmission as well, so I think a combination of all of this, next year is INR25,000 crores, our sense is probably going forward also, we'll have a similar kind of capital outlay.
- Tata Power's net debt-to-underlying EBITDA was 3.3 and its net debt-to-equity was 1.2.
Show source
Our net debt to underlying EBITDA is 3.3 and our net debt to equity is 1.2, which is very competitive for infrastructure and power industry.
What it expects ahead
What management expects
- Tata Power expects peak power to cross about 270 gigawatts in the next 1 to 2 months because of the heat wave across the country and the prediction of a severe impact because of El Nino.
Show source
We do expect that in next 1 to 2 months, this will cross about 270 gigawatts.
- Tata Power's missed projects from last year will be completed in this financial year; its yearly investment target remains the same, although some projects may be deferred by a quarter or 2.
Show source
And those which we missed out in the last year, we will complete all of them in this financial year.
- Tata Power is looking at a ballpark 2 gigawatt of commissioning next year, possibly slightly higher if everything goes well.
Show source
But I think you kind of alluded to the 2 gigawatt of commissioning next year, which is kind of a ballpark number that we're also looking at.
- Tata Power expects Indonesian coal prices to be within plus/minus 5% of that range, with no major deviation.
Show source
And we expect that prices will be within plus/minus 5% in that range.
- Tata Power’s rooftop business target is to reach 20% in the next 3 years.
Show source
And our target is that in next 3 years, we will do 20%.
- Tata Power expects its rooftop business to grow by at least 50% to 60% in FY '27.
Show source
So, I do expect that in FY '27, the rooftop market, the rooftop business will grow, if not by 100%, at least by 50%, 60%.
Show 10 more statements
What management expects
- Tata Projects expects to start making profit from FY '27, as its subsequent projects have good margins.
Show source
And I do expect that in FY '27, it will be back, and it will start making profit from FY '27.
- Tata Power expects future renewable projects to be hybrid with storage rather than pure solar or pure wind, and expects them to offer more attractive returns than projects bid out in the last 2 years.
Show source
And those will be much attractive in terms of the returns compared to the type of projects, which have been bid out in the last 2 years.
- Tata Power expects all of its Odisha circles to reach the 12% to 13% range in the next 4 to 5 years, with loss reduction of about 2% every year as a ballpark number.
Show source
And based on that, we do expect that all of them will come in 12% to 13% range in the next 4 to 5 years.
- Tata Power expects demand to increase in both peaking requirement and energy requirement.
Show source
So, we do expect that the demand will increase both in terms of peaking requirement and energy requirement.
- Tata Power expects some amount to materialize from a pipeline of regulatory assets it is contesting and discussing, but says it is difficult to quantify or predict the outcome or whether it will be lower or higher.
Show source
But yes, we would expect some amount to materialize.
- Tata Power will do no third-party projects this year; everything it does will be in-house.
Show source
So everything that we will do will be in-house.
- Tata Power is examining new coal-based generation opportunities and will look at them if the tariff is attractive and there is a bankable PPA.
Show source
If there is a good opportunity and we find that the tariff is attractive and it's a bankable PPA, we'll definitely look at those.
- Tata Power expects to maintain similar discipline while going forward with new investments in the coming years. Replaced by a later filing.
Show source
And we do expect that we will maintain similar discipline while going forward with our new investments in the coming years.
- Tata Power expects a lot of consistency in capex phasing in the current year. Replaced by a later filing.
Show source
So from a capex phasing point of view, I think you will see in the current year, a lot of consistency coming in.
- Indonesian coal will be virtually flat. Replaced by a later filing.
Show source
Praveer Sinha: It will be virtually flat for Indonesian coal.
What it is building and selling
Projects and capacity
- Tata Power expects 50% of its nearly 5 gigawatt of in-house projects under implementation to be completed in this financial year and the remaining 50% in FY '28.
Show source
50% of it will be completed in this financial year and the balance 50% in FY '28.
- Tata Power is going to start work on a new 10 gigawatt wafer and ingot plant in 2 phases to cater to its cell and module plant, which will require Indian made wafers from 1st June 2028 onwards.
Show source
We have informed you that we are going to start work in our new 10 gigawatt of wafer and ingot plant in 2 phases, and that will cater to our existing operations of cell and module plant, which will require Indian made wafers from 1st June 2028 onwards.
- Tata Power had about 5 gigawatts of pipeline, and a lot of things will start materializing from quarter 1 onwards.
Show source
And as you can see, we have about 5 gigawatts of pipeline as we speak.
- Tata Power expects to carry out virtually 2,500 megawatt of project implementation internally and maybe a little more this year.
Show source
And last year, we did about 2,500 megawatt of total project implementation.
- All 5 units of the Mundra plant are operating.
Show source
Praveer Sinha: The full plant is operating all the 5 units.
- Tata Power expects to complete in FY '27 projects it missed out on last year, including large utility scale, distribution, transmission and hydro projects.
Show source
These are not just large utility scale, but it is also including the distribution projects and the transmission projects and the hydro projects where work is going.
Show 24 more statements
Projects and capacity
- The nuclear plants are small modular 2 x 220 megawatt plants.
Show source
These are small modular 2 x 220 megawatt plants.
- Tata Power expects to be able to do DPR in next 6 months' time for some of the nuclear projects, especially in some of the states.
Show source
And we do expect that some of them, especially some of the states, we will be able to do DPR in next 6 months' time.
- Tata Power's current pipeline includes the 2,800-megawatt pump hydro at Shirwata, where work will start in this financial year, and Bhutan hydro projects of 600 plus 1,125 where financing arrangements have been signed with World Bank; the 1125 Bhutan project will come in 2031, '32, and some projects will come in '30, '31.
Show source
So, this includes the 2,800-megawatt pump hydro at Shirwata, where the work will start in this financial year.
- The 5 gigawatt renewable capacity referred to on Slide 7 is installed capacity.
Show source
Sanjeev Churiwala: This is the installed capacity.
- Mumbai transmission adds INR1,000 crores of capex every year; on a 70-30 basis, return on equity applies to 30%, plus certain O&M.
Show source
Praveer Sinha: Mumbai transmission adds every year INR1,000 crores of capex.
- Tata Power had about 600 megawatts of projects lined up in the previous quarter.
Show source
We are now in this quarter, trying to complete some of the projects around 600 megawatts of large utility scale.
- Tata Power's planned large utility-scale projects and hydro projects in Bhutan and its pumped hydro project at Bhivpuri will involve large capital expenditure.
Show source
Page 3 of 19 The Tata Power Company Limited May 12, 2026 Our distribution business everywhere will continue to grow, and we will have large capital expenditure as planned in our large utility scale projects as also in our hydro projects in Bhutan and the pumped hydro project that we are implementing in Bhivpuri.
- Tata Power's planned projects that could not be executed in the last quarter were large utility-scale projects, solar projects, wind projects and transmission line projects; execution was delayed by right-of-way issues and delays in transmission systems to be built by others under TBCB, including ISTS projects.
Show source
We have fallen short because some of the projects that we were planning to execute in the last quarter could not happen.
- Tata Power has tied up all the wind turbines needed for its wind projects and is going to implement those projects alongside solar projects; the projects are hybrid.
Show source
Page 13 of 19 The Tata Power Company Limited May 12, 2026 And for that, we have already tied up all the wind turbines, which have to go, and we are going to implement all those wind projects apart from the solar project.
- Tata Power’s projects are hybrid FDRE projects, not stand-alone solar or stand-alone wind.
Show source
These are not stand-alone solar or stand-alone wind but these are all part of the hybrid FDRE projects that we are.
- Some of Tata Power's projects require domestic cells, and the majority of its projects have domestic cell and modules.
Show source
So out of the projects that we have, we find that majority are with domestic cell and modules.
- The PPA is agreed and is in the final stages of regulatory approval; approval is expected in the next few months. Replaced by a later filing.
Show source
And that process is in the final stages, and we do expect next few months that approval will come in.
- Tata Power’s manufacturing plant is positioned to cater to large utility scale and rooftop solar. Replaced by a later filing.
Show source
So, I think our manufacturing plant is very well positioned to cater to large utility scale as well as to rooftop solar.
- A larger chunk of the commissioning will be towards hybrid and FDREs. Replaced by a later filing.
Show source
Sanjeev Churiwala: It will be a combination of all of this, but larger chunk would be towards hybrid and FDREs.
Demand and pricing
- Power demand increased by 2% in the last quarter.
Show source
We saw in the last quarter that the increase in demand was very modest of 2%.
- Power demand has gone up by 5% to 6% from April onwards.
Show source
And we are now seeing from April onwards that the demand has gone up by 5% to 6%.
- Peak power touched 256 gigawatts.
Show source
And the peak power also has touched 256 gigawatts.
- Mumbai demand has crossed 4,600.
Show source
And we are already seeing in many places, Mumbai has crossed 4,600.
- Delhi demand is more than 6,500.
Show source
Delhi is more than 6,500.
Segments
- Tata Power will use whatever it manufactures to meet its own requirements, including rooftop requirements.
Show source
So whatever we are going to manufacture, we are going to meet our own requirements.
Deals and partners
- Tata Power has concluded the SPPA with Gujarat and is finalizing it with the other 4 states, which it expects to complete in the next 4 to 6 weeks.
Show source
We have now concluded the SPPA with Gujarat, and we are in the process of finalizing it with all the other 4 states, which we expect in next 4 to 6 weeks, we will complete.
- Tata Power is in discussions with Tata Steel and some large data centres about renewable projects offered with storage projects, including pumped hydro.
Show source
We are in discussions with Tata Steel and some of the other large data centres, which are coming up.
- Tata Power is working on aspects that need to be finalized with Nuclear Power Corporation; discussions are detailed, but finalizing the arrangement will take some more time.
Show source
So quite detailed discussions but it will take some more time for us to finalize the arrangement.
- Coal cost is pass-through under Tata Power's SPPA with Gujarat, and whatever the cost of coal will be paid for.
Show source
Praveer Sinha: Coal cost is pass-through.
Risks, rules and outside factors
Risks and disputes
- The regulatory commission has promised that the Delhi DISCOM regulatory asset will be amortized over 6 years up to 2032, and Tata Power expects implementation as set out in the affidavit provided.
Show source
And the regulatory commission has promised that this will be amortized over 6 years up to 2032.
Outside factors
- Coal and shipping prices have seen very nominal increases in the last 2 months.
Show source
There is, of course, a small increase in the prices of coal and shipping but those are very, very nominal increases that has been seen in the last 2 months.
- Tata Power's imported coal-based plants have had no impact, and adequate coal supply is coming.
Show source
We have also seen that for our imported coal-based plants, there has been no impact per se.
- Tata Power continues to work with transmission companies and CTU to reduce curtailment and evacuate all the power; where GNA is in place and curtailment occurs, Tata Power is reimbursed the cost on the supply basis.
Show source
In cases where we have the GNA and curtailment takes place, there, of course, we are reimbursed the cost on the supply basis.
- Increased power demand is met mainly by coal-based plants and hydro plants, supported by renewable solar and wind during solar hours and wind hours. Replaced by a later filing.
Show source
The increased demand is met mainly by our coal-based plants and hydro plants and also renewable solar and wind supporting them during solar hours and wind hours.
Rules and policy
- Effective 1st June 2026, only Indian-made cell has to be used, and some projects implemented in FY '27 will require Indian-made cells and modules because they are not grandfathered.
Show source
So, some of the projects, which will get implemented in FY '27 will require Indian-made cells and modules.
Show 3 more statements
Rules and policy
- Tata Power is hearing that more taxes will be imposed on exports of coal, but the matter has been under discussion for the last many months and the eventual decision remains to be seen.
Show source
The second is that we are hearing that there will be some more taxes that will be imposed on export of coal.
- The Mundra plant’s billing is being done as per the SPPA and the overall understanding reached with the procurers and the Ministry of Power.
Show source
The billing that is being done is being done as per the SPPA, as per the overall understanding that has been reached with them as well as with Ministry of Power.
- Tata Power’s rooftop projects requiring a government subsidy have to use Indian-made cell and module, and its existing manufacturing plant will cater to that requirement.
Show source
That will be catered from our existing manufacturing plant.
Everything else said on the call
What management stressed
- Tata Power is committed to enhancing generation capacity, transmission, distribution and hydro generation facilities in the country and Bhutan. Replaced by a later filing.
Show source
And we are committed to enhance our generation capacity has also enhance our transmission distribution and hydro generation facilities in the country and also in Bhutan.
Group structure
- Tata Projects has completed its legacy dedicated freight corridor and refining project in Barmer projects, with very little left, and expects their impact to be very minimal going forward.
Show source
And we expect that those legacy projects impact will be very minimal going Page 12 of 19 The Tata Power Company Limited May 12, 2026 forward.
Other
- The recurring nature of transmission business increases depends on asset capitalization timing, the deferred tax created by it, and the profitability of the particular plant; it is not a yearly phenomenon.
Show source
So yes, I think it's not a yearly phenomenon but depends upon the asset capitalization and the profitability of that particular plant.
- IEL’s recurring amount is based on capex.
Show source
Management: That is based on capex, pure capex.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Sumit Kishore: Good evening, Dr. Sinha. You mentioned in your opening remarks that the capex for the financial year has been INR130 billion. This is meaningfully below the guidance that you had given to us in November in Odisha, which was INR250 billion. So, what really led to that guidance with 4 months remaining in the fiscal seeing such a sharp decline? And what is your guidance -- realistic guidance for FY '27? And what will it comprise in terms of the end projects? That's my first question. Page 4 of 19 The Tata Power Company Limited May 12, 2026 Praveer Sinha: Yes, Sumit, so I agree that our guidance was, I don't think INR25,000 crores, but it was, I think, about INR22,000 crores.
Answer, praveer sinha
We have fallen short because some of the projects that we were planning to execute in the last quarter could not happen. And these projects are typically relating to the large utility scale projects, solar projects or wind projects or the transmission line projects. Many of the places, the right of way got delayed. Many of the places, the transmission system was to be done by someone else under the TBCB. We were supposed to use that transmission system for evacuating, that got delayed, and you have seen there have been a large number of reports of many TBCB projects, especially ISTS projects getting delayed. We are now in this quarter, trying to complete some of the projects around 600 megawatts of large utility scale. Similarly, in the pipeline are some of the transmission projects that we are executing as the ROW issues are resolved.
Answer, praveer sinha
So, these are not that these will not come. It's just that the phasing has got impacted. And those which we missed out in the last year, we will complete all of them in this financial year. So that's why our target of yearly investment continues to be the same. And there may be certain deferment by a quarter or 2. But otherwise, we are very much on track.
Question
Sumit Kishore: No, sir, I was referring to the slide in your Bhubaneswar presentation, which shows INR25,000 crores of capex. So the second question is on the Delhi distribution business, where in the last 2 quarters, there have been regulatory favourable prior period regulatory orders. The quantum was INR4.6 billion in Q3. It was INR3.2 billion in Q4 at the EBITDA level and the profit level positive impacts have also been shown. So can you -- can Mr. Sanjeev sort of clarify what is the entire benefit that you have taken because of prior period regulatory orders at EBITDA and profit level in FY '26 and FY '25, how much is expected? It is very difficult to predict. But what sort of claims do
Answer, sanjeev churiwala
Sanjeev Churiwala: Yes. So I think what you're saying is relevant, but give a little context to that. The good part is whenever you see the regulatory upside, those are pertaining to matters a few years back, either those regulatory approvals were denied or deferred. So as a result , we are very happy that many of those past regulatory clearances are now coming in. Page 5 of 19 The Tata Power Company Limited May 12, 2026 And this is not the first time that we are getting the clearances. This happens every year. In fact, if you look at FY '25, we had about INR333 crores of regulatory approvals coming in.
Answer, sanjeev churiwala
This year, as you rightly picked up, INR783 crores is reflected. Next year, too, we will have something. But to quantify at this stage, it might be very, very difficult because there are a pipeline of regulatory assets that we are kind of contesting and discussing. And as you are aware, it's very difficult to predict an outcome on a regulatory settlement or regulatory clearances. But yes, we would expect some amount to materialize. Now whether that is lower or higher, sitting today is very difficult. But my sense is as and when every quarter passes on, we should be able to give you a better understanding on that.
Question
Sumit Kishore: Sure. Just one last bookkeeping question. What is the IPP RE capacity that you expect to add in FY '27? What will be the phasing of that capacity? And would it be right to expect that for the solar component there is the module and cell would be supplied from Tata Power's own manufacturing unit?
Answer, sanjeev churiwala
Sanjeev Churiwala: The second question is very clear forward. That's the whole purpose why we have put up the cell and module manufacturing. And I think that we are kind of quite integrated that we are able to kind of have the entire line-up of cells modules locked in on all the pipelines. And as you can see, we have about 5 gigawatts of pipeline as we speak. And a lot of things will start materializing this time around from quarter 1 onwards. So from a capex phasing point of view, I think you will see in the current year, a lot of consistency coming in.
Answer, praveer sinha
Praveer Sinha: Also, Sumit, last year, we did a huge amount of third-party projects. This year, we don't have third party. So everything that we will do will be in-house. And last year, we did about 2,500 megawatt of total project implementation. So you can imagine that 2,500 will be virtually internal that we will carry out and maybe a little more.
Question
Sumit Kishore: So if you deliver, for instance, 2 gigawatt of solar project, then the requirement of module cell will be 2 into 1.4, the multiplying factor. about 2.8 out of your capacity will go into -- in this example, it will go into your own capacity addition. Is that the right understanding? Page 6 of 19 The Tata Power Company Limited May 12, 2026 Praveer Sinha: Exactly.
Answer, praveer sinha
And then we have rooftop. So whatever we are going to manufacture, we are going to meet our own requirements.
Question
Sumit Kishore: Sure. So the intrasegment elimination should basically reflect that in FY '27?
Answer, sanjeev churiwala
Sanjeev Churiwala: Yes. And that is largely around the RPT compliance in terms of the margins but are very, very consistent. So that should not be posing a problem for you to kind of do your modelling as well. But I think you kind of alluded to the 2 gigawatt of commissioning next year, which is kind of a ballpark number that we're also looking at. And if everything goes well, maybe it could be slightly higher than that.
Answer, praveer sinha
Praveer Sinha: No. But everything is not solar.
Question
Puneet Gulati: Yes, thank you so much, and congrats on good performance. My first question is on Odisha, where you've been giving phenomenal performance year-after-year. Do you still see room for more efficiencies, or should we sort of pencil in future growth more from regulated equity growth only?
Answer, praveer sinha
Praveer Sinha: We get to see much better than this in the next financial year. And I think next financial year possibly will be the best year for Odisha DISCOMS because many of the initiatives that we had taken in the last few years have started showing results. Some of the initiatives were taken last year. And the impact of it, you will see in this year. I think Odisha performance next year should possibly peak in terms of the type of results you would see.
Question
Puneet Gulati: Okay. That's very interesting. And second is on the hydro side. You started taking large exposures to hydro now. And is the PPA already in place or would you be looking to sign PPA in some time? Page 7 of 19 The Tata Power Company Limited May 12, 2026 Praveer Sinha: It is in advanced stage of approval.
Answer, praveer sinha
As you know that while the PPA is agreed, it has to go through a regulatory approval process. And that process is in the final stages, and we do expect next few months that approval will come in.
Question
Puneet Gulati: Understood. And lastly, if you can comment on the regulatory asset wind down in Delhi DISCOM. Supreme Court had indicated an intention to wind this down. Any progress there?
Answer, praveer sinha
Praveer Sinha: Yes. So both the Supreme Court and APTEL are monitoring that. And the regulatory commission has promised that this will be amortized over 6 years up to 2032. And we are closely monitoring that. They have already given an affidavit under which they will amortize it. And we expect that it will get implemented as per the affidavit that they have provided.
Question
Apoorva Bahadur: Okay, sir. And in your disclosure for renewable business, we see that the PLF for solar is lower due to lower resource availability. And also there's a comment on curtailment. Can you quantify the impact of curtailment in FY '26 and your expectation in FY '27?
Answer, praveer sinha
Praveer Sinha: So the curtailment are happening in a few places. That also is not on a continuous basis. So very difficult for us to say that how much of curtailment will happen. Also, some of the lines have been commissioned. So it is not that there is full curtailment part of - - so in some cases, at least 60%, they have allowed to evacuate. In some places, they have allowed 80%, in some places, it is at 20%, 25%. So it's a moving target, which is there.
Answer, praveer sinha
And we continue to work with the transmission companies and CTU to ensure that the curtailment is reduced, and we are able to evacuate all the power. In cases where we have the GNA and curtailment takes place, there, of course, we are reimbursed the cost on the supply basis. Page 8 of 19 The Tata Power Company Limited May 12, 2026 Apoorva Bahadur: And sir, for next year, FY '27, the target we have for adding solar capacity, do we have permanent GNA for all those substations or some of it is still on temporary GNA.
Question
Apoorva Bahadur: Makes sense, sir. Sir, lastly, if you can provide some colour on the Indonesian coal prices, especially after the West Asian war, the index is backward looking. So what's your take over there? How the prices should move this year as well as there was some news flow around potential tax imposition by the Indonesian government on coal mining. So if we can have some view on that as well would be very helpful?
Answer, praveer sinha
Praveer Sinha: So one is on the coal prices, there has not been too much of movement. And we expect that prices will be within plus/minus 5% in that range. We're not expecting lot of deviation. The second is that we are hearing that there will be some more taxes that will be imposed on export of coal. But this has been under discussion for the last many months. So, let's see what eventually gets decided.
Answer, praveer sinha
Praveer Sinha: It will be virtually flat for Indonesian coal.
Show 19 more questions
Question
Apoorva Bahadur: Sure, sir. Sir, lastly, I mean, if I may just squeeze in one more. In your cash flow statement, there's an item of movement in balance related to service concession agreement. So, what is this regarding because we see it has been a drag on cash flow for this year?
Answer, sanjeev churiwala
Sanjeev Churiwala: Capex related to HBA, TBCB project. Management: Capex related to TBCB project, it is there in the working capital.
Question
Ketan Jain: Sir, my first question is on the Mundra plant. Is the entire plant operating under the supplementary PPA terms? Or is it only the Gujarat part? Is the rest under operating on the section level?
Answer, praveer sinha
Praveer Sinha: The full plant is operating all the 5 units. The Section 11 is to facilitate the operation of the plant and give time to the procurers to get the necessary approval. The billing that is being done is being done as per the SPPA, as per the overall understanding that has been reached with them as well as with Ministry of Power. Ketan Jain: Understood. So my next question is on the key growth drivers, which segments do you see to contribute most in the coming next 2 years for EBITDA growth?
Question
Satyadeep Jain: Okay. Fair enough. Sir, just a clarification on the RE captive use of modules and cell that you mentioned. As per the order, any new tender after 1st September, the developers have to use domestic cell but there is no mandate before that. So, given the tariffs that you bid for don't reflect that the domestic cell requirement, why would you look to use domestic cell in your FY '27 commissioning, given I believe this year, you would be commissioning projects that were awarded before September '25, right? Just trying to understand there. And secondly would be solar rooftop. So, you executed 1.7 gigawatts, which means almost 40% market share. Is that something you are looking at
Answer, praveer sinha
Praveer Sinha: So we are definitely looking to enhance our market share. And our target is that in next 3 years, we will do 20%. And having said that, we expand our rooftop business. So, you have seen last year, it has grown by 100%. And I definitely expect in this year also, it will grow substantially more than what is expected from the market at this time. So, I do expect that in FY '27, the rooftop market, the rooftop business will grow, if not by 100%, at least by 50%, 60%. So, you will see exceedingly good performance from rooftop business going forward.
Answer, praveer sinha
I also expect that most of our rooftop and you know that for rooftop, if you have to get the government subsidy, then it has to use Indian-made cell and module. That will be catered from our existing manufacturing plant. Also going forward, effective 1st June 2026, you have to use only Indian-made cell. And many of the projects are not grandfathered. So, some of the projects, which will get implemented in FY '27 will require Indian-made cells and modules. So, I think our manufacturing plant is very well positioned to cater to large utility scale as well as to rooftop solar.
Question
Sir, I missed the FY '27 capex guidance. Could you please repeat it? Page 11 of 19 The Tata Power Company Limited May 12, 2026 Praveer Sinha: It's about INR25,000 crores.
Answer, praveer sinha
That is what we are expecting. As I mentioned to you, those projects, which we missed out last year, we'll ensure that those get completed in this financial year. And these are a range of projects. These are not just large utility scale, but it is also including the distribution projects and the transmission projects and the hydro projects where work is going.
Question
Mohit Kumar: My first question on the Note number 5 of the consolidated P&L. There is an amount mentioned of INR250 crores deferred tax assets. Can you clarify whether we need to adjust or increase the taxes by INR250 crores to arrive at the profit for the quarter?
Answer, sanjeev churiwala
Sanjeev Churiwala: So, as you are aware, this is a deferred tax noncash. So basically, given our future profitability projections, so I think that will give you some genesis as to where it is coming from. We have, of course, carry forward losses. And of course, when you look at the stand-alone book, everything has to be adjusted against the stand -alone to fully recognize this. We have better visibility of profits in the subsequent years now. And we feel that some of the carry forward losses can now be utili zed within the time frame. And as such, from a statutory purpose, we have to recognize the deferred tax in the books, which we have done in quarter 4 now.
Question
Mohit Kumar: My second question is the Tata Projects. It has been making losses for -- it was making losses prior to FY '24, I guess. And '24 was the first year, I think, where we have started making profit. FY '26 again, I think there' a loss. FY '25, they loss. FY '26 again, they a loss. What is your outlook on the same for as we enter FY '27, '28? Do you think the losses will get restricted now?
Answer, praveer sinha
Praveer Sinha: What has happened in Tata Projects is they had legacy projects such as the dedicated freight corridor project from the refining project in Barmer and some other projects which are there. Fortunately, all those projects have now been completed and very little of it is left. And we expect that those legacy projects impact will be very minimal going Page 12 of 19 The Tata Power Company Limited May 12, 2026 forward. The subsequent projects that Tata Projects have got have good margins. And I do expect that in FY '27, it will be back, and it will start making profit from FY '27.
Question
Mohit Kumar: One more question, if I can squeeze in. We haven't seen accretion to the under- development RE portfolio for a long time. How are you thinking about bidding for new assets for renewables given the, of course, the structural headwinds right now? Do you still want to remain on the pause? Or do you think we can start adding to the portfolio from FY '27 onwards?
Answer, praveer sinha
Praveer Sinha: Yes. So, as we mentioned to you that many of the places, there were 2 challenges. One was the transmission lines have got delayed and there is no point in taking a project and not able to implement it because the transmission system or the power evacuation system is not ready. Secondly, we have now come up with a unique solution where we can offer renewable projects along with the storage projects, the pumped hydro project. And going forward, we are looking for that sort of arrangement. These types of arrangements are not only with utilities but also with large C&I customers, steel companies. We are in discussions with Tata Steel and some of the other large data centres, which are coming up.
Answer, praveer sinha
And we do expect that going forward, we will not do pure solar or pure wind, but it will be hybrid with storage. And those will be much attractive in terms of the returns compared to the type of projects, which have been bid out in the last 2 years.
Question
Rupesh Rai: Sir, in terms of commissioning, you have mentioned -- yes, sorry. So, in terms of commissioning, I think you mentioned we'll be adding 2.5 gigawatts this year and 2.5 similar number next year and further like 1.5 to 1.7 gigawatt is solar. But if I look at the pipeline, then solar number is pretty small, like 600-odd megawatts only. So, is this -- I mean, like are we adding FDRE or complex FDRE, I think if you can give colour or maybe a breakup of 2.5 between this?
Answer, praveer sinha
Praveer Sinha: So those details are there. In which slide it is there? In Slide 7, we have given the breakup. And those are the type of projects that you would see, which will be a combination of solar and wind. I agree that there are large number of wind projects, which are there. Page 13 of 19 The Tata Power Company Limited May 12, 2026 And for that, we have already tied up all the wind turbines, which have to go, and we are going to implement all those wind projects apart from the solar project. But these are all hybrid projects.
Answer, praveer sinha
These are not stand-alone solar or stand-alone wind but these are all part of the hybrid FDRE projects that we are.
Answer, sanjeev churiwala
Sanjeev Churiwala: In case you are only referring to this and looking at pure solar, you also look at FDRE and hybrid. They will also have component of solar as well.
Question
Rupesh Rai: Okay. But is it fair to say that a large part of maybe like 1.6, 1.7 gigawatt will be FDRE in this commissioning?
Answer, sanjeev churiwala
Sanjeev Churiwala: It will be a combination of all of this, but larger chunk would be towards hybrid and FDREs. Rupesh Rai: Okay. Got it. And then in terms of commissioning, I think last year for our business, we have added the 1-odd gigawatt. And now we are seeing like probably a pickup for us. So, I mean, is it fair to say probably the issues on transmission and other infra-related issues that are kind of behind us and probably things are much better?
Question
Rupesh Rai: Okay. And maybe one last thing. Anything that we can share that we are doing at Tata Power for nuclear as such? And anything that you're seeing any traction that is happening on the ground? That's my last question, sir.
Answer, praveer sinha
These are small modular 2 x 220 megawatt plants. And we do expect that some of them, especially some of the states, we will be able to do DPR in next 6 months' time. And we are also parallelly working on some of the Page 14 of 19 The Tata Power Company Limited May 12, 2026 other aspects, which needs to be finalized with Nuclear Power Corporation. So quite detailed discussions but it will take some more time for us to finalize the arrangement.
Question
Nikhil Nigania: Hi. Thank you. I had just one question. I know the company has taken a stance to not add any new coal-based generation capacity. I wanted to check if there is any change in that view given so many states are coming up with coal-fired power plant tenders?
Answer, praveer sinha
Praveer Sinha: We are examining that. If there is a good opportunity and we find that the tariff is attractive and it's a bankable PPA, we'll definitely look at those.
Question
Nikhil Nigania: Got it. Understood. And if I may ask just one more question. I think an earlier question on the use of domestic, the cells you are producing. I understand the use for the rooftop solar segment. But on the utility scale side, most of your tenders are pre the 2025 dates. So, I believe they should not be needing DCR cells. So, anything I'm missing there?
Answer, praveer sinha
Praveer Sinha: I think some of them do require domestic. So, we are working on that because they will bid under those conditions that you will be using domestic cell and modules. So out of the projects that we have, we find that majority are with domestic cell and modules.
Question
Rajesh Majumdar: Yes, good evening, sir. And thanks for the opportunity. I had a couple of questions. On your Slide 7, the current operational capacity is 16.7 gigawatts and including pipeline is 26.3, which means an addition of 10 gigawatts. So, is this the FY30 figure, 26.3 or how should we take this figure? That was the first question. Page 15 of 19 The Tata Power Company Limited May 12, 2026 Praveer Sinha: This would be, I would say...
Answer, praveer sinha
Praveer Sinha: Yes. So, this is the current pipeline. So, this includes the 2,800-megawatt pump hydro at Shirwata, where the work will start in this financial year. And all the existing, that means the Bhutan hydro, 600 plus 1,125 where we have already signed the financing arrangement with World Bank. So, this takes care of all. Some of them will come up in 2031, '32, that is the 1125 Bhutan project will come in that year. Some will come in '30, '31.
Question
Rajesh Majumdar: And sir, your capex figure of INR25,000 crores, if you take an addition of 2 gigawatts per annum, then the capex is roughly about, say, on the higher side, maybe INR12,000 crores to INR15,000 crores. Does this mean that INR10,000 crores of regulated capex will happen in FY27?
Answer, sanjeev churiwala
Sanjeev Churiwala: No, I think it's not about regulated capex, but a combination of all the capex that Dr. Sinha spoke about. Of course, 2.5 gigawatt of solar and wind, that as you rightly said, that INR15,000 crores. But then you have capex coming up in pumped storages, capex coming up in pure hydro, so a combination of all of this -- transmission as well, so I think a combination of all of this, next year is INR25,000 crores, our sense is probably going forward also, we'll have a similar kind of capital outlay.
Question
Rajesh Majumdar: And sir, my last question is, we have signed the SPPA with Gujarat, of course. But now if there is an export duty or royalty, which comes from Indonesia, then how does that work with the SPPA, and how does it impact the negotiations with the other states going forward?
Answer, praveer sinha
Praveer Sinha: Coal cost is pass-through. So, whatever is the cost of coal will be paid for. So that's the type of arrangement that we have.
Question
Anuj Upadhyay: Yes, Hi Sir, Thanks for the opportunity. Sir, need one clarification on how should we read Slide 7 and Slide 32 together? Because Slide 7, where we have highlighted 5 gigawatt of renewable capacity, of which, I guess, 1 gigawatt is a combination of plain wind and solar capacity? Whereas we have 4 gigawatt a combination of, I guess, 2.5 of FDRE and rest the hybrid project at the RTC. But if I see your FY32 slides, where we have highlighted the time line of the FDRE and hybrid wind getting commissioned, the contracted capacity comes only to the tune of 1,200 megawatt. So does the 5,000 gigawatt of renewable capacity is the actual installed capacity or the contracted installed ca
Answer, sanjeev churiwala
Sanjeev Churiwala: This is the installed capacity. Installed capacity given the Slide 34.
Question
Anuj Upadhyay: Okay. And my second question belongs to your Odisha projects. Again, to a prior question, you mentioned that next year probably we'll be peaking out in terms of the Page 17 of 19 The Tata Power Company Limited May 12, 2026 performance. So apart from Northern circle, I believe other areas still have in the range of 18% kind of an AT&C? So, what kind of loss reduction trajectory we can assume for the other 3 circles and to what level it can go? I mean, like North Odisha is already at around 10%, whereas others are already at 18%. So, to what level we can expect the loss to further go down and by what timeline, sir?
Answer, praveer sinha
Praveer Sinha: There is a trajectory that has been agreed with the Odisha regulator. And based on that, we do expect that all of them will come in 12% to 13% range in the next 4 to 5 years. So, you can expect that you will reduce about 2% every year in that sort of reduction will be a ballpark number.
Question
Apoorva Bahadur: Okay. So, this increase is recurring for transmission business?
Answer, sanjeev churiwala
Sanjeev Churiwala: No, that depends upon the asset capitalization timing and the deferred tax that is created because of that. So yes, I think it's not a yearly phenomenon but depends upon the asset capitalization and the profitability of that particular plant. Page 18 of 19 The Tata Power Company Limited May 12, 2026 Apoorva Bahadur: Okay.
Question
And same thing in IEL as well?
Answer, praveer sinha
Praveer Sinha: It's based on capex only. That is also capex. Management: That is based on capex, pure capex. It is recurring.
Answer, praveer sinha
Praveer Sinha: Mumbai transmission adds every year INR1,000 crores of capex. So, on a 70-30, you will have a return on equity on 30%. So that's what you need to consider plus certain O&M. Apoorva Bahadur: Very clear, sir. Thank you.
Questions about this call
- When was the Tata Power Company Q4 FY26 earnings call transcript filed?
- Tata Power Company filed the transcript with the exchange on 15 May 2026. This page is built from that transcript.
- What does this page list?
- 78 statements from the transcript across 13 topics, 43 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 29 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.