Tata Power Company Q4 FY25 earnings call: Tata Power Solar's EPC arm had an order book of about close to Rs. 11,000-odd crores

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Tata Power Solar's EPC arm had an order book of about close to Rs. 11,000-odd crores. Tata Power expects power-demand growth of about 5% this year and expects peak demand this year to reach about 270 gigawatts, after seeing 2% growth in April. Tata Power commissioned 166 gigawatts of capacity in the quarter. Tata Power's reported PAT in the March quarter was Rs. 1,306 crores, nearly 25% higher, and adjusted PAT was Rs. 1,288 crores, 16% higher than last year's Rs. 1,109 crores. Tata Power has third-party EPC obligations to complete in the next six months and does not have excess capacity at least until the 3rd Quarter.

The numbers management gave

Results

  • Tata Power's reported PAT in the March quarter was Rs. 1,306 crores, nearly 25% higher, and adjusted PAT was Rs. 1,288 crores, 16% higher than last year's Rs. 1,109 crores.
    Show source
    Our reported PAT is nearly 25% higher in the March quarter, which is at Rs. 1,306 crores, while the adjusted PAT is 16% higher at Rs. 1,288 crores compared to last year's Rs. 1,109 crores.
  • Tata Power's Q4 EBITDA increased 14% to Rs. 3,829 crores compared to last year's Rs. 3,358 crores.
    Show source
    Our Q4 EBITDA has also increased 14% to Rs. 3,829 crores compared to last year's Rs. 3,358 crores.
  • In FY '25, Tata Power's PAT exceeded Rs. 5,000 crores for the first time, underlying EBITDA was more than Rs. 15,000 crores, and reported revenue rose 5% to Rs. 64,502 crores.
    Show source
    Page 2 of 19 The Tata Power Company Limited May 14, 2025 Coming to the full year: FY '25 has been a historic year where for the first time the Company has posted a PAT in excess of Rs. 5,000 crores, and underlying EBITDA has been more than Rs. 15,000 crores, while the reported revenue has gone up by 5% to Rs. 64,502 crores.
  • Tata Power's PAT before exceptional in FY '25 was Rs. 5,197 crores, a 26% increase year on year.
    Show source
    The PAT before exceptional has gone to Rs. 5,197 crores, which is a 26% increase on year-on- year basis.
  • Tata Power's underlying EBITDA in FY '25 increased 10% to Rs. 15,261 crores.
    Show source
    And the underlying EBITDA has increased by 10% to Rs. 15,261 crores.
  • Tata Power's solar rooftop business revenue rose 40% to Rs. 865 crores and EBITDA rose 72% to Rs. 132 crores in the quarter.
    Show source
    In our solar business, especially the solar rooftop business, our revenues have gone up by 40% in the quarter to Rs. 865 crores and EBITDA has gone up by 72% to Rs. 132 crores.
Show 26 more statements

Results

  • Tata Power's rooftop business had sales of nearly 782 megawatts peak, revenue of Rs. 2,210 crores and PAT of Rs. 209 crores for the full year.
    Show source
    For the full year, our rooftop business had sales of nearly 782 megawatts peak with a revenue of Rs. 2,210 crores and PAT of Rs. 209 crores.
  • Tata Power supplied nearly 3,300 megawatts of modules during the year.
    Show source
    In this year though we started production a little late, in the whole year we have supplied nearly 3,300 megawatts of modules.
  • Tata Power supplied 913 megawatts of modules and 650 megawatts of cells in the quarter; reported revenue was Rs. 1,500 crores and EBITDA margin was 27%.
    Show source
    And the reported revenue of this quarter was Rs. 1,500 crores and the EBITDA margin has gone up to 27%.
  • TP Solar reported revenue of Rs. 5,337 crores, EBITDA of Rs. 875 crores and PAT of Rs. 422 crores for the full year.
    Show source
    For the full year, TP Solar has reported revenue of Rs. 5,337 crores, EBITDA of Rs. 875 crores and PAT of Rs. 422 crores.
  • Tata Power's T&D business revenue was Rs. 9,590 crores and PAT was Rs. 616 crores in the quarter.
    Show source
    In our T&D business also, which actually has shown record performance this year, in the quarter our revenue was Rs. 9,590 crores, PAT of Rs. 616 crores.
  • Tata Power's T&D business revenue was Rs. 39,122 crores and PAT was Rs. 2,000 crores for the full year.
    Show source
    For the full year, the revenue of T&D business is Rs. 39,122 crores and a PAT of Rs. 2,000 crores.
  • Odisha Discoms' PAT increased to Rs. 439 crores from Rs. 307 crores in the previous year.
    Show source
    In fact, in Odisha Discoms, our PAT increased to Rs. 439 crores from Rs. 307 crores in the previous year.
  • The CERC order dated 3rd January 2003 pertains to an earlier quarter, and there was no impact in this quarter.
    Show source
    Sanjeev Churiwala: There is no impact in this quarter.
  • Tata Power's rooftop business delivered close to Rs. 860 crores, Rs. 870 crores in top line revenues with a very healthy PAT margin in the 4th Quarter of FY '25.
    Show source
    When you look at the numbers of rooftop for the quarter we have kind of delivered close to about Rs. 860 crores, Rs. 870 crores in terms of the top line revenues with a very healthy PAT margin.
  • Tata Power's rooftop business was operating with 600-plus channel partners in the 4th Quarter of FY '25.
    Show source
    We are kind of operating with 600-plus channel partners and we want to ensure that the growth that we have in the 4th Quarter we can continue this growth in the coming quarters as well.
  • Mundra's full-year PAT benefited because its plant continued to run on Section-11 with five units this year versus four last year, when one unit was down, and from a regulatory upside of almost Rs. 332-odd crores that had been pending for almost a decade and was reported in earlier quarters.
    Show source
    A, suppose last year and this year the plant continues to run on Section-11, last year one unit was down so we were running on four units, this year we are running on the five units, so to the extent there's better contribution coming through.
  • Tata Power's PAT margin was consistent at about 5% and its EBITDA margin was closer to 8% to 9%, the targeted range, in the quarter under discussion.
    Show source
    And if you see the EBITDA margin and PAT margin, PAT margin is consistent about 5% and EBITDA margin is beyond that, closer to 8% to 9%.
  • Tata Power's EPC business delivered a margin close to 5% in the quarter under discussion.
    Show source
    EPC business, if you look at it, we are delivering a margin of close to 5%.
  • Tata Power's EPC margin was 5% for FY '25, compared with 3.3% for the last full year; the company said it had targeted 5%.
    Show source
    For the full year as well, we are delivering at 5%.
  • Tata Power's wind PLF is normally in the range of 19.5% to 20%.
    Show source
    And normally when we look at the wind PLF, we are in the zone of 19.5% to 20%.
  • Tata Power’s third-party EPC work contributes to the consolidated profit of the renewable businesses, and DCR cells supplied to those businesses will add to profits; Tata Power has a backlog of that work.
    Show source
    So kind of if you look at a console basis, all the DCR cell that goes to third-party EPC businesses that we are doing and we do have a backlog of that, that will add up to the profits.
  • Odisha's better profitability was driven by continuous reductions in AT&C losses, better efficiencies, billing and collection, despite ECL provisioning to clear some past dues.
    Show source
    On Odisha, of course, as you can see there is a continuous reduction in the AT& C losses, better efficiencies has come in, better billing and better collection have happened.

Money and capital

  • Tata Power's CAPEX was Rs. 4,100 crores in the last quarter and Rs. 16,200 crores for the whole year.
    Show source
    We had a CAPEX of Rs. 4,100 crores in the last quarter, and in the whole year we had a CAPEX of Rs. 16,200 crores.
  • Tata Power plans CAPEX of Rs. 25,000 crores in the coming year.
    Show source
    And in the coming year we have a plan of having a CAPEX of Rs. 25,000 crores.
  • Tata Power's net debt was Rs. 44,700 crores.
    Show source
    In spite of such a large CAPEX, we have been able to have the net debt at Rs. 44,700 crores.
  • Tata Power's net debt to underlying EBITDA was 2.93, less than 3, and its net debt to equity was 1.0, compared to 1.1 in the previous quarter.
    Show source
    And our net debt to underlying EBITDA continues to be less Page 4 of 19 The Tata Power Company Limited May 14, 2025 than 3, it is actually at 2.93, and our net debt to equity is at 1.0 compared to 1.1 in the previous quarter.
  • Tata Power's CAPEX plan for FY '26 and subsequent years is on track.
    Show source
    Tata Power is committed to go for very calibrated growth and our CAPEX plan not only for FY '26 but for subsequent years is on track.
  • Tata Power’s CAPEX layout for next year is close to Rs. 25,000-odd crores, with around 60% allocated to renewable businesses and about 30% odd to transmission and distribution; the allocation may change depending on the situation on the ground.
    Show source
    Sanjeev Churiwala: We have about a CAPEX layout of close to about Rs. 25,000-odd crores for next year.
  • Moody's recently upgraded the outlook on Tata Power from Ba1 stable to Ba1 positive.
    Show source
    In fact, Moody's has recently upgraded the outlook on Tata Power from Ba1 stable to Ba1 positive.
  • Tata Power did not subscribe to Tata Projects’ rights issue because it is focusing on core businesses and plans to use its money for its own CAPEX growth.
    Show source
    And since we are now focusing on our core businesses, we have not subscribed to that.
  • Internal accrual is supporting the investment required for Tata Power's pumped storage project while financial closure is pending.
    Show source
    So, notwithstanding the financial closures, the internal accrual is supporting the investment that is required for the project.

What it expects ahead

What management expects

  • Tata Power expects power-demand growth of about 5% this year and expects peak demand this year to reach about 270 gigawatts, after seeing 2% growth in April.
    Show source
    Though in the month of April we have only seen 2% growth, we do expect that this year the peak demand will increase to something like 270 gigawatts.
  • Tata Power is on track to double its PAT and EBITDA by FY '30.
    Show source
    And as we had shared with you last year, we are on track to double our PAT and EBITDA by FY '30.
  • Tata Power expects its rooftop business to nearly double in FY '26, with initiatives alongside the government PM Surya Ghar project, especially in Odisha, UP, Rajasthan, Assam and Maharashtra.
    Show source
    And in the coming year, that is FY '26, we expect that this will nearly double considering that huge initiatives are being taken by us along with the government PM Surya Ghar project, especially in Page 3 of 19 The Tata Power Company Limited May 14, 2025 the states of Odisha, UP, Rajasthan, Assam and Maharashtra.
  • Tata Power expects production of both cells and modules to exceed 3,700 megawatts in the coming year.
    Show source
    With both the cell and module line fully operational, we do expect that in the coming year we will cross the 3,700 megawatts of production of both cells and modules.
  • Tata Power expects to commission nearly 2.5 gigawatts to 2.7 gigawatts of renewable projects this year.
    Show source
    This year we will commission nearly 2.5 gigawatts to 2.7 gigawatts of renewable projects.
  • Tata Power expects improvement in its solar cell business: production was 650 megawatts in Q4, while more than 3.700 megawatts is expected in FY '26, bringing the full impact of production in that financial year.
    Show source
    You will only see improvement of it because in Q4 we produced 650 megawatts while in FY '26 we are expecting more than 3.700 megawatts.
Show 20 more statements

What management expects

  • Tata Power expects nearly 1 gigawatt of supply to be required for rooftop solar.
    Show source
    And again, nearly 1 gigawatt will be required over there.
  • Tata Power may deliver about 1 gigawatt or around that amount for third-party EPC in the next year.
    Show source
    Sanjeev Churiwala: I think next year for sure we may have about the delivery of 1 gigawatt or around so, to be done for the third-party EPC.
  • Section-11 has been extended for two months, and Tata Power is working with the government toward a revised PPA; management said it was too early to predict the outcome for the entire year or comment on how '26 will look.
    Show source
    As of now, Section-11 has been extended for two months.
  • Tata Power expects peak demand to reach 270 this year, based on data from IMD, compared with a peak of 250 last year.
    Show source
    So, it all depends.
  • Tata Power expects its distribution business performance to improve further in the coming year as operations stabilize and service quality work takes effect.
    Show source
    And we do expect that with the operations stabilizing and a whole lot of work that has been done in improving the quality of service, this performance will further improve in the coming year.
  • Tata Power is looking at opportunities to expand its distribution business, especially in states where the distribution bidding process will start in the latter part of this month.
    Show source
    With all our distribution business, whether it is in Odisha, Delhi, Mumbai and Ajmer doing very good, the Company is also looking at the opportunities to expand, especially in some of the states where the distribution bidding process will start in the latter part of this month.
  • Tata Power expects to increase its footprint in UP, where a big distribution bidding process is starting.
    Show source
    And we do expect that, especially in UP where the big process is starting, we will be able to increase our footprint.
  • Tata Power's investments in hydro projects in Bhutan, pumped hydro projects in its existing hydro businesses, T&D investments in transmission lines and distribution projects, and renewables are expected to sustain company performance and profit growth over the next few quarters.
    Show source
    And we do believe that our investments in hydro projects in Bhutan, pumped hydro projects in our existing hydro businesses, T&D investments in our transmission lines and distribution projects, as well as in our renewables will help us to sustain the good performance of the Company and maintain the track record of growth in profit for next few quarters.
  • Tata Power expects better performance from its module line in the coming year as it has stabilized.
    Show source
    Similarly, the module line also has now stabilized, and you will see much better performance in the coming year.
  • Tata Projects has an ambitious plan and may perform very well and start making a profit in the next one to three years.
    Show source
    And hopefully in the next one to three years, they will perform very well and start making a profit.
  • Tata Power may consider a stressed asset or an asset that has been in operation for some period, but this is speculative and there is no immediate plan to pursue anything of that kind.
    Show source
    But as I mentioned to you, if there's some stressed asset or some asset which is there, and typically they would have been in operation for some period, we can look at that.
  • Tata Power's cell and module margins will further improve as efficiency and yields improve, and the company expects much better returns and margins in future projects.
    Show source
    So, you can consider much better returns and a much better margin in the future projects.
  • Odisha Discoms' performance in future quarters will be consistent with the performance seen in Q4, following streamlining of the process.
    Show source
    And the performance in the future quarters will be consistent to what sort of performance you have seen in Q4.
  • Tata Power is waiting for the government to amend the law to allow private sector participation in nuclear power plants and amend the civil liability law; once there is more clarity, it will share its plan to implement SMRs and other types of nuclear plants.
    Show source
    And once we get more clarity on that, we can share with you our plan to implement SMRs and other type of nuclear plants.
  • The bid documents for UP privatization are expected by the end of this month, after a consultant was appointed.
    Show source
    And what I understand , by the end of this month the bid documents will come and we will get some better clarity on that.
  • Tata Power is on track to make up the delayed work in the coming quarters. Replaced by a later filing.
    Show source
    And we are on track to make up in the coming quarters.
  • Tata Power expects the plant to work at full capacity, with all the required steps taken by the company. Replaced by a later filing.
    Show source
    So you can assume that the plant will work at full capacity for which all the steps have been taken by the Company.

Orders

  • Tata Power Solar's EPC arm had an order book of about close to Rs. 11,000-odd crores.
    Show source
    Sanjeev Churiwala: It should be about close to Rs. 11,000-odd crores.
  • The wind plant orders are in the final stages and are expected to be completed in the next three to four weeks.
    Show source
    In the final stages, hopefully in the next three to four weeks.
  • Tata Power has a huge backlog of orders that it needs to execute. Replaced by a later filing.
    Show source
    Page 6 of 19 The Tata Power Company Limited May 14, 2025 Dr. Praveer Sinha: I think we have huge backlog of orders that we need to execute.

What it is building and selling

Projects and capacity

  • Tata Power commissioned 166 gigawatts of capacity in the quarter.
    Show source
    We also in the quarter commissioned 166 gigawatts of capacity.
  • Tata Power expects nearly 5.5 gigawatts of renewables capacity to be added in the next six months to 24 months; land for most of the projects has been acquired, as has connectivity.
    Show source
    We also have a very good pipeline of our renewables business where nearly 5.5 gigawatts of capacity will get added in the next six months to 24 months, where land for most of the projects have been acquired as also the connectivity.
  • Tata Power hopes to have nearly 70% clean and green energy by 2030; work has started on the 1,000 megawatts Bhivpuri pumped hydro project, and work on the 1,800 megawatts Shirawata pumped hydro project will start in the later part of the year.
    Show source
    And we do hope that our target to have nearly 70% clean and green energy by 2030 will be possible, not only with the renewables projects that we are setting up, but also the pumped hydro project where the work has already started in the 1,000 megawatts Bhivpuri project and work in 1,800 megawatts Shirawata pumped hydro will start in the later part of the year.
  • Work on Tata Power's 600 megawatts Khorlochhu project in Bhutan started on 1 January, and Tata Power expects the project to be completed by November ‘29.
    Show source
    Our project in Bhutan, the 600 megawatts Khorlochhu project, the work has already started from 1 January, and we expect that by November ‘29, the project will be completed.
  • Tata Power's solar cell and module plant at Tirunelveli is fully operational, with each operating at more than 90%.
    Show source
    Coming to our manufacturing of solar cell and module: The plant is now fully operational at Tirunelveli, and they are operating at more than 90% each.
  • Tata Power completed 2.3 gigawatts of projects last year.
    Show source
    Last year we actually completed the 2.3 gigawatts of projects.
Show 12 more statements

Projects and capacity

  • Tata Power will continue operating 4 gigawatts of Mono-PERC and 300 megawatts of TOPCon lines, maximizing the technology and efficiency currently used; it will examine TOPCon when opportunity and market demand arise.
    Show source
    But right now, we will continue with the operation of these lines.
  • Tata Power is working on financial closure for its 1,000 megawatts Pumped Storage Power Plant, with discussions happening with banks and a few months still needed to close.
    Show source
    Sanjeev Churiwala: So, yes, we are working on financial closure.
  • Pumped hydro can provide power 365 days for eight hours every day.
    Show source
    Pumped hydro has a unique ability to give this power 365 days for eight hours every day.
  • Tata Power's transmission lines were delayed by right of way issues, which the company has sorted out.
    Show source
    The second is some of the transmission lines that we were doing, those also got delayed because of right of way issues.
  • Tata Power expects to complete in this quarter the work it could not complete in the last quarter; the implementation timeline was delayed, not deferred.
    Show source
    And whatever we could not complete in the last quarter, we will be able to meet all those in this quarter.
  • Tata Power continues to acquire land in various places and apply for connectivity as a long-term investment strategy, so it does not have to begin seeking these when it wins a project.
    Show source
    So, as a long-term investment strategy, we continue to acquire land in various places, and also keep on applying for connectivity, so that we do not have to start looking for it when we win the project.
  • Tata Power executes utility-scale and group captive projects for various industries and Tata Group companies, and plans to be quite aggressive in acquiring land and obtaining connectivity from those locations.
    Show source
    So we definitely would be quite aggressive in the acquisition of land, as also getting the necessary connectivity from these locations.
  • Tata Power is developing pumped hydro to provide bundled power with solar and wind for utility-scale projects and C&I customers; this is a work in progress and will take at least six more months to finalize.
    Show source
    This will take at least six more months for us to get finalized, so that we have maximum value for the investment that we are making in this project.

Segments

  • Tata Power has third-party EPC obligations to complete in the next six months and does not have excess capacity at least until the 3rd Quarter.
    Show source
    So, at least till this 3rd Quarter we do not have any excess capacity.
  • Most of the cells and modules Tata Power produces will be consumed by the company itself, and Tata Power has a huge pipeline of orders to execute.
    Show source
    And most of these cells and modules that we will produce will get consumed ourselves.
  • Tata Power arranges batteries from suppliers and combines them with solar and wind projects as part of its complex renewable projects and hybrid solution.
    Show source
    So, we arrange source batteries from suppliers and combine it with solar and wind projects that we set up.

Deals and partners

  • UP appointed a consultant to work on the bid process for two Discoms. Replaced by a later filing.
    Show source
    Dr. Praveer Sinha: UP have appointed a consultant to work on the bid process for two Discoms.

Risks, rules and outside factors

Risks and disputes

  • The CERC order supports Tata Power in collecting its receivables.
    Show source
    Sanjeev Churiwala: This order is kind of more supporting us in terms of collecting our receivables.

Outside factors

  • Mundra plant is designed for imported coal, whose chemical characteristics differ from domestic coal, and Tata Power says switching to domestic coal does not make sense given those requirements and the high transportation cost from eastern India; a change would make sense only with an arrangement that reduces coal and transportation costs.
    Show source
    So, because of that reason, for us it does not make sense to go for domestic coal.

Everything else said on the call

What management stressed

  • Tata Power is prioritizing capital allocation to its growth businesses in renewable and transmission and distribution, while remaining opportunistic about opportunities. Replaced by a later filing.
    Show source
    But as of now, we are kind of more determined to ensure our capital allocation goes to our growth businesses, which is in the renewable and transmission and distribution.

Group structure

  • Tata Projects’ management may decide at an appropriate time whether to pursue a listing or other steps to make the business more robust. Replaced by a later filing.
    Show source
    And maybe at the appropriate time Tata Projects’ management will take a decision on what they need to pursue to make it more robust in terms of a listing or whatever they have to do.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Sumit Kishore: Good evening, sir. My first question is in relation to CAPEX. On the 3rd Quarter call you had expressed confidence that the Company would be able to achieve its target of Rs. 210 billion of CAPEX that you had set for yourselves , and which would have implied nearly Rs. 9,000 crores to Rs. 10,000 crores of CAPEX in Q4. So, what led to the shortfall on CAPEX? And even in the December Analysts Meet we spoke about 588 megawatts of renewable capacity addition in Q4 against which 166 megawatts have got added. So what are the challenges here which delayed your CAPEX and your capacity addition targets given that they were just three months out? That's the first question. Dr. Praveer S

    Answer, praveer sinha

    There were some delays in execution of projects. One was in the renewables, some of the locations, the transmissions, and evacuation system, which is Page 5 of 19 The Tata Power Company Limited May 14, 2025 being done by the other companies, they could not be set up . And because of those delays we could not complete the project in time and evacuate the power. The second is some of the transmission lines that we were doing, those also got delayed because of right of way issues. We have been able to sort that out. And whatever we could not complete in the last quarter, we will be able to meet all those in this quarter. So, it's not that they have been deferred but it's just that the implementation timeline has got a little delayed for various reasons.

    Answer, praveer sinha

    And we are on track to make up in the coming quarters.

  2. Question

    Sumit Kishore: Sure. So the transmission evacuation issues are largely sorted to commission 2.5 gigawatts plus of renewable in FY '26 like you targeted? Dr. Praveer Sinha: Yes.

    Answer, praveer sinha

    This year we will commission nearly 2.5 gigawatts to 2.7 gigawatts of renewable projects. Last year we actually completed the 2.3 gigawatts of projects.

  3. Question

    Sumit Kishore: Yes. My compliments on your very strong performance in the solar cell business operationally, both for very high levels of capacity utilization and the ramp up in cell production seen soon after commissioning. But it seems that the margin performance is also very strong, and it appears to be driven by a third-party sale of modules which are integrated with cells in the 4th Quarter. So, is this something that is likely to continue at this scale in FY '26 where you said you will have almost 3,700 megawatts of module and cell production? So, how should we think about the third-party mix? And any volatility through the year that you expect because of your internal requirements, if

    Answer, praveer sinha

    You will only see improvement of it because in Q4 we produced 650 megawatts while in FY '26 we are expecting more than 3.700 megawatts. So, you can expect the full impact of production coming in the financial year. Similarly, the module line also has now stabilized, and you will see much better performance in the coming year. So you can assume that the plant will work at full capacity for which all the steps have been taken by the Company. Sumit Kishore: Sir my question was on, what will be the proportion of third -party sale in your solar module and cell business, because that is not going to get eliminated on consolidation? Page 6 of 19 The Tata Power Company Limited May 14, 2025 Dr. Praveer Sinha: I think we have huge backlog of orders that we need to execute.

    Answer, praveer sinha

    We ourselves have large projects and it's for our own Company. In addition to that, we have some third- party EPC obligations which we need to complete in the next six months. So, at least till this 3rd Quarter we do not have any excess capacity. In addition to that , as I mentioned to you, we are going to increase the supply to rooftop solar. And again, nearly 1 gigawatt will be required over there. So I think that we have a huge pipeline of orders to be executed. And most of these cells and modules that we will produce will get consumed ourselves.

    Answer, praveer sinha

    Maybe in subsequent years we might have some extra capacity for third-party.

    Answer, sanjeev churiwala

    Sanjeev Churiwala: And just to add to what Dr. Sinha said, when we say in-house consumption, even our third-party EPC that we do, finally the profit will also boil down to the consolidated profit of the renewal businesses. So kind of if you look at a console basis, all the DCR cell that goes to third-party EPC businesses that we are doing and we do have a backlog of that, that will add up to the profits.

  4. Question

    Sumit Kishore: Okay. So your third-party order backlog is how big right now for module cells?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: I think next year for sure we may have about the delivery of 1 gigawatt or around so, to be done for the third-party EPC. Sumit Kishore: Beyond the solar Rooftop?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: Yes, Sumit, it's beyond solar Rooftop. Dr. Praveer Sinha: Yes.

  5. Question

    Mohit Kumar: Yes. Good evening, sir. Thanks for the opportunity. My first question was, there was a news in the media that you are rethinking about exiting coal business, is that true? If true, are you also exploring organic growth?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: Yes. I think there are mixed reactions that you see in the papers and all. I think as Dr. Sinha said, we will be opportunistic. If some opportunities come, we will see. But as of now, we are kind of more determined to ensure our capital allocation goes to our growth businesses, which is in the renewable and transmission and distribution. Page 7 of 19 The Tata Power Company Limited May 14, 2025 Mohit Kumar: Understood.

  6. Question

    Sir, my second question is, there is a Note Number 2 which talk s about some adjustment from the CERC judgment. What is the impact of that Note Number 2 in this particular quarter?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: There is no impact in this quarter. This pertains to the earlier quarter, which we have already discussed, the CERC order dated 3rd January 2003.

  7. Question

    Mohit Kumar: Yes. They say they issued the final order in claim of, so you have trued up the amount. So that is what it says, that's why I am trying to chime in.

    Answer, sanjeev churiwala

    Sanjeev Churiwala: This order is kind of more supporting us in terms of collecting our receivables.

  8. Question

    Mohit Kumar: So there is no material impact in this quarter, is that right?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: We have about a CAPEX layout of close to about Rs. 25,000-odd crores for next year. And if I do a breakup, around 60% of the layout allocation will happen in our renewable businesses. Given that we are also growing our transmission and distribution, CAPEX of about 30% odd will go there and the remaining are there. But this will remain dynamic. This is a broad allocation that we are starting the year. But depending upon the situation on the ground, the allocation might change.

  9. Question

    Apoorva Bahadur: Hi, sir. Thank you for the opportunity. A couple of questions, sir, firstly on the cell module manufacturing business. I see in your presentation that we have commissioned a TOPCon pilot line as well, would you mind throwing some update on that? I mean, when do we intend to upgrade our PERC capacity? Page 8 of 19 The Tata Power Company Limited May 14, 2025 Dr. Praveer Sinha: So, right now we will continue with the 4 gigawatts of Mono-PERC and 300 megawatts of TOPCon.

    Answer, praveer sinha

    So that whatever technology we have used and the efficiency that we are getting, we maximize on that. Whenever the opportunity and the market demand is there for TOPCon, we will examine it at that stage. But right now, we will continue with the operation of these lines.

  10. Question

    Apoorva Bahadur: Okay. Lastly, I wanted to understand our strategy for Tata Projects. I think we have been holding this business for quite some time, have been getting diluted here, twice there has been a rights issue. So, how do we sort of look at this business? The intent is to hold it till a possible listing or maybe a sale to the parent at some time? Dr. Praveer Sinha: So, as you are aware that Tata Projects came up with rights issue.

    Answer, praveer sinha

    And since we are now focusing on our core businesses, we have not subscribed to that. And we want to use our money for our own CAPEX growth, which we have planned. As far as Tata Projects is concerned, they have an ambitious plan. And hopefully in the next one to three years, they will perform very well and start making a profit. And maybe at the appropriate time Tata Projects’ management will take a decision on what they need to pursue to make it more robust in terms of a listing or whatever they have to do.

Show 20 more questions
  1. Question

    Apoorva Bahadur: Great, sir. One last question, if I can squeeze it in, and this is regarding the ordering for the wind plants. Wanted to know if we are through with all the orders that could be placed? Dr. Praveer Sinha: Yes.

    Answer, praveer sinha

    In the final stages, hopefully in the next three to four weeks.

  2. Question

    Thank you. First, Mr. Sinha, just a clarification question. My question is to what you responded to Mohit's question on the media articles around thermal. It seems you indicate that if there's an opportunity that comes along, you may look at it. Is that a strategic change? Because the earlier target was that you will phase out all the coal plants that you have by 2045 or something. Is there a change in that strategy that you might be opportunistic, and you may not phase out all the coal plants, you may look at coal? I know the word opportunistic, but that means you are open to evaluating different opportunities if there's a change in strategy, just want to understand that. Dr. Praveer Sinha:

    Answer, praveer sinha

    So, it's the end date of where we will divest or we will close down the plants by 2045 for all the coal-based plants where we have the PPAs. But as I mentioned to you, if there's some stressed asset or some asset which is there, and typically they would have been in operation for some period, we can look at that. But these are, again, very speculative at this stage. There's no plan per se that we are immediately going for anything like that.

  3. Question

    Satyadeep Jain: Okay. Just on the RE, I know you acquired more ISTS connectivity, and there have been some delays in transmission evacuation. Now, what is your intent, you are acquiring more transmission connectivity? And given your targets, given the issues we have seen in transmission ROW, is that why you are holding off on maybe more aggressively building pipelines beyond the next two years? What’s the thought there, and what's driving that strategy, whatever may be exercising caution on building future pipeline? Dr. Praveer Sinha: So, as you are aware, there are challenges in acquisition of land and getting evacuation permission.

    Answer, praveer sinha

    So, as a long-term investment strategy, we continue to acquire land in various places, and also keep on applying for connectivity, so that we do not have to start looking for it when we win the project. And as you are aware, we do a large number of projects, not only utility-scale, but also under group captive for various industries as also for many of the group companies in Tata Group. So we definitely would be quite aggressive in the acquisition of land, as also getting the necessary connectivity from these locations.

  4. Question

    Satyadeep Jain: Okay. Just one question if I can squeeze on very high margins you report in rooftop solar, and also Odisha Discoms I think there is some ECL provisioning write back is done. Just wanted to understand that ECL provisioning and what basically drove the profitability in Odisha, and also the rooftop solar? Thank you. Page 10 of 19 The Tata Power Company Limited May 14, 2025 Dr. Praveer Sinha: So, Odisha Discoms is a different business and that has nothing to do with the rooftop, excepting for the fact that they do support rooftop initiative that we take in Odisha.

    Answer, praveer sinha

    So I think we need to look at both of them separately rather than at once.

  5. Question

    Satyadeep Jain: No, sir. Separately, but just want to understand what happened in those two different businesses? Just what led to high profitability in solar rooftop in that quarter? And also separately, Discom also reported very high profit, and it seems like there is some ECL provisioning write back, just wanted to understand two different businesses what led to the good performance here.

    Answer, sanjeev churiwala

    Sanjeev Churiwala: So I think you are right, there are two different businesses. On Odisha, of course, as you can see there is a continuous reduction in the AT& C losses, better efficiencies has come in, better billing and better collection have happened. And back on this we have better profitability. They are having some ECL provisioning in terms of clearing up some of the past dues. But even after providing for those ECL provisioning we delivered a very good set of numbers in Odisha. And hopefully, we have created a good baseline to kind of grow from here. So that's on Odisha.

    Answer, sanjeev churiwala

    On the rooftop businesses, I think the 4th Quarter has been a phenomenal quarter for us where we have delivered good growth. When you look at the numbers of rooftop for the quarter we have kind of delivered close to about Rs. 860 crores, Rs. 870 crores in terms of the top line revenues with a very healthy PAT margin. And that demonstrates our ability to penetrate the market, capturing the market share, getting a premium for our product based on a high amount of trust that the consumer has. We are kind of operating with 600-plus channel partners and we want to ensure that the growth that we have in the 4th Quarter we can continue this growth in the coming quarters as well.

  6. Question

    Mohit Kumar: Yes. Hi. Thanks for the opportunity. Sir one clarification is that, the Government of India has come out with the new Shakti Scheme, which allowed imported coal-based power plant to source coal from the domestic sources. Do you think it makes sense for Mundra to tie up the domestic coal in the long term? Page 11 of 19 The Tata Power Company Limited May 14, 2025 Dr. Praveer Sinha: The Mundra plant is designed for imported coal, and imported coal has different chemical characteristics.

    Answer, praveer sinha

    It's not just the heat rate but what is the sulfur content, nitrogen content, what is the ash content. So there are a whole lot of chemical characteristics that it needs to comply to. So we need to consider all these aspects when we go for change in coal. So, because of that reason, for us it does not make sense to go for domestic coal. Secondly, the cost of coal if we get from eastern part of India, especially in terms of the transportation cost, is very high. And for us, until and unless we are able to have a very differentiated arrangement which brings down the cost of coal, and also brings down the transportation cost, it will not make real sense to move to any other coal than what we are using at the moment.

  7. Question

    Mohit Kumar: Understood. The second question is, is there any update on the financial closure of the Pumped Storage Power Plant which you are building up the facility with 1,000 megawatts?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: So, yes, we are working on financial closure. The discussions are happening with the banks. We have just started the work, so we still have a few months to close that. Dr. Praveer Sinha: Yes.

    Answer, praveer sinha

    But the work is going on at the pumped storage project. So, notwithstanding the financial closures, the internal accrual is supporting the investment that is required for the project.

  8. Question

    Rajesh Bhojani: Yes. Thank you, ma'am, for the opportunity. I was interested if the Company is expanding in battery energy storage system? Dr. Praveer Sinha: Yes.

    Answer, praveer sinha

    We set up those projects as a part of the complex renewable projects. So, we arrange source batteries from suppliers and combine it with solar and wind projects that we set up. So, it's a part of the hybrid solution that we are implementing.

  9. Question

    Thank you.

    Answer, sanjeev churiwala

    Sanjeev Churiwala: So, if you are looking at the full year PAT, there are a couple of things there. A, suppose last year and this year the plant continues to run on Section-11, last year one unit was down so we were running on four units, this year we are running on the five units, so to the extent there's better contribution coming through. And that's the key reason. And there we have one of the regulatory upside coming in for Mundra, which was pending for the last almost a decade now, which has been reported in the earlier quarters, almost at a figure of Rs. 332-odd crores. So that is because of that. Bharanidhar: Understood. So, what would be the outlook for '26, sir, regarding Section-11?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: It all depends. It's too difficult for us to predict the outcome for the entire year. As of now, Section-11 has been extended for two months. And we are also trying to very amicably work along and get into a revised PPA with them, with the government. So, it's too early for us tom kind of comment as to how '26 will look like. But we are working towards the resolution. Bharanidhar: Understood.

    Answer, sanjeev churiwala

    And some updates on the UP privatization of Discoms and where is it at and when it is likely to be opened the bid, that would be helpful. Dr. Praveer Sinha: UP have appointed a consultant to work on the bid process for two Discoms.

    Answer, praveer sinha

    We are also part of it, and hopefully, we would like to do something out there. But I think we are still working for good. Bharanidhar: Okay. Thank you so much. And all the best. Page 13 of 19 The Tata Power Company Limited May 14, 2025 Moderator: Thank you.

  10. Question

    Atul Tiwari: Yes, sir. Thanks a lot. Sir, again on the pumped storage plants where you have started the work, what is the status of long-term PPAs there? Are you looking at something? And in case the PPA is not there, do you think financial closure will be possible from financial institution side? Dr. Praveer Sinha: So, pumped hydro is being developed to basically give bundled power along with solar and wind.

    Answer, praveer sinha

    This will be done for both the utility-scale projects as well as for many of our C&I customers. This is a work in progress. This will take at least six more months for us to get finalized, so that we have maximum value for the investment that we are making in this project. As you know that many of the companies have to go for 24/7 renewable power as well as many of the Discoms are wanting to do that. Pumped hydro has a unique ability to give this power 365 days for eight hours every day. So, I think we need to position it in such a way that whether industries or utilities, they want certainty on the pumped hydro plant, they will be going for this along with the other renewable sources.

  11. Question

    Anuj Upadhyay: Yes. Hi. Thanks for the opportunity, sir. Sir, firstly on the EPC margin excluding the rooftop segment, it still struggles to cross 5% at EBITDA level EPC for the Q4. So, the reason behind that? And secondly, your wind PLF continues to struggle to cross 20% kind of a level, so what actually has been impacting the wind performance out here?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: So, I think if you see the presentation that has been uploaded, I will just tell you the slide number. And if you see the EBITDA margin and PAT margin, PAT margin is consistent about 5% and EBITDA margin is beyond that, closer to 8% to 9%. And that's the targeted range we want to be in. So I think we are doing absolutely fine with respect to margins in our businesses.

  12. Question

    Anuj Upadhyay: So, I guess the consol margin comes at around 8% to 9%, but the EPC is still in the range of 5% to 6%? I am referring to your slides only, sir. Page 14 of 19 The Tata Power Company Limited May 14, 2025 Sanjeev Churiwala: Yes.

    Answer, sanjeev churiwala

    EPC business, if you look at it, we are delivering a margin of close to 5%.

  13. Question

    Anuj Upadhyay: Yes. So, I mean, initially the sense was that the EPC segment, excluding the rooftop I am saying, could scale up a level of around 7% to 8%. So that time we had this concern that we had orders which were at a low margin business, and we had actually executed those low margin EPC work, so the upcoming orders would be of a healthy margin. But still we see the margins to struggle somewhere in the range of 5% to 6% only.

    Answer, sanjeev churiwala

    Sanjeev Churiwala: I do not know where we are kind of missing your expectation. In slide number 62, for the quarter, for the EPC we delivered less than 3%. For the full year as well, we are delivering at 5%. And throughout the EPC business, and I think for the last couple of years we have said that we kind of want to maintain a margin profile of 5%. So that has been very consistent as well. And it's kind of done better than the previous year now. You see, for the last full year, when the margin was 3.3%, I very clearly remember we said that we are targeting 5%, and this year we are delivering 5%.

  14. Question

    Anuj Upadhyay: Wind PLF which continues to be at around 20% PLF. Dr. Praveer Sinha: So, see, what happens is whether it is wind or solar, what we need to ensure is the availability of the plant. And the availability of all these plants has been in the 99-plus range. The PLF is dependent upon the wind speed or what is the solar level. So, last year the wind speeds in many places were not very good. And that is why the wind PLFs are low. But our plant availability continues to be very high in all places.

    Answer, sanjeev churiwala

    Sanjeev Churiwala: Yes. And I think to be very precise, slide number 61 of the presentation has the full detail. And normally when we look at the wind PLF, we are in the zone of 19.5% to 20%. And that is what perhaps is the right zone.

  15. Question

    Aniket Mittal: Yes, sir. Thank you for the opportunity. My first question is on the cell and module operations. So just to understand, could you talk about what sort of realizations you will be getting in the market for these external sales, both for DCR and non-DCR module sales? And secondly, sort of heading into FY '26, what sort of EBITDA margin do you think this entity can make? Dr. Praveer Sinha: See, as I mentioned to you, we are not selling these DCR modules as such.

    Answer, praveer sinha

    A very small quantity we sell, depending upon the timelines in which it is required. Mostly it is being used in-house for our in-house projects or for the third-party EPCs that we are executing, for which we already had an order earlier with us. So, to that extent, we may not be able to share what sort of price will be applicable for the sale of just the DCR modules. You can see the margins which is there, the Q4 margin is just an indication. Going forward, it will further improve because the efficiency and the yields are improving. So, you can consider much better returns and a much better margin in the future projects.

  16. Question

    Aniket Mittal: Okay. And just one bookkeeping question, for your Tata Power Solar EPC arm, what's the overall order book currently?

    Answer, sanjeev churiwala

    Sanjeev Churiwala: It should be about close to Rs. 11,000-odd crores.

  17. Question

    Rajesh Majumdar: Yes. Good evening, everyone. So I have another question Odisha Discoms, we have seen a sharp jump in the profitability in Q4 as well as for the year for Odisha Discoms. So how sustainable is this? And what would be a kind of long run kind of PAT we can assume from this? Will it be slightly lower than this or will it be slightly higher than this? Dr. Praveer Sinha: So Odisha Discoms had their huge challenges because there were a lot of issues regarding billing, collection, meters.

    Answer, praveer sinha

    And they were also large, old outstanding. We have been able to take care of all those things, including ECL provision. And what you have seen in Q4, a similar trend you will observe because the whole process has now been streamlined. And the performance in the future quarters will be consistent to what sort of performance you have seen in Q4.

  18. Question

    Rajesh Majumdar: Right. And sir, my other question is a bit of a general question for you , because you have always said in the last couple of calls that the peak demand is likely to hit 270 this year. But so far the demand trends are not suggesting anywhere near that number. So I know last year we had a base effect kind of impact on the power demand , is there any risk of the power demand again being in low -single-digits this year? Dr. Praveer Sinha: So, last year we had the peak of 250 and this year, based on the data that we have from IMD, we are expecting that it will go to 270.

    Answer, praveer sinha

    So, it all depends. The summer has just started, and we normally have a long summer right up to August. So, let us wait and watch.

  19. Question

    Sumit Kishore: Thanks for the opportunity again. My first question is to Dr. Sinha, you had articulated the opportunity and keen interest that Tata Power has in the nuclear and SMR market that is likely to open up to private sector. Has there been any progress in terms of any tender invited by the government for private sector participation? We were reading that there were some companies which had immense interest, has that moved forward? Dr. Praveer Sinha: So, we are waiting for the change in the law wherein the government has to amend the law in allowing private sector participation in nuclear power plants, also the civil liability law.

    Answer, praveer sinha

    And once we get more clarity on that, we can share with you our plan to implement SMRs and other type of nuclear plants. Page 18 of 19 The Tata Power Company Limited May 14, 2025 Sumit Kishore: And just a follow-up question on this UP privatization, we are hearing that five circles are going to be demarcated for private sector participation.

  20. Question

    So, is there any condition that one private player cannot take more than one or two circles or can take more than? Dr. Praveer Sinha: We are still waiting for the bid documents.

    Answer, praveer sinha

    They have appointed a consultant. And what I understand , by the end of this month the bid documents will come and we will get some better clarity on that.

Questions about this call

When was the Tata Power Company Q4 FY25 earnings call transcript filed?
Tata Power Company filed the transcript with the exchange on 16 May 2025. This page is built from that transcript.
What does this page list?
80 statements from the transcript across 11 topics, 48 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 30 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Tata Power Company Q4 FY25 concall: Tata Power Solar's EPC arm had an order book of about close to Rs. 11,000-odd crores · DalalOS