Tata Power Company Q1 FY26 earnings call: Tata Power has plans to add more than 2 gigawatt per year to its in-house order book

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The transcript does not name its quarter. Q1 FY26 is worked out from the date it was filed.

Tata Power has plans to add more than 2 gigawatt per year to its in-house order book. Tata Power expects nearly 1,600 megawatt of own utility scale projects to come up in the next three quarters, enhancing the operating capacity of its renewable business. Tata Power expects its pumped hydro project to be commissioned by 2028-29; work started in the last quarter. Tata Power commissioned 652 megawatt this quarter, nearly double the quantity commissioned in last year's same quarter; 560 megawatt was for third party and 92 megawatt for its own utility scale. The PM Surya Ghar program has said 1 crore households, while the country has 25 crore households.

The numbers management gave

Results

  • Tata Power commissioned 652 megawatt this quarter, nearly double the quantity commissioned in last year's same quarter; 560 megawatt was for third party and 92 megawatt for its own utility scale.
    Show source
    We have commissioned this quarter a record 652 megawatt which is nearly double of the quantity that was commissioned in last year's same quarter and out of which 560 is for third party and 92 is for our own utility scale.
  • Tata Power's net debt to underlying EBITDA was 2.93 and net debt to equity was 1.08 this quarter.
    Show source
    Net debt to underlying EBITDA is 2.93 and net debt to equity is 1.08 which is I think one of the best in the industry.
  • Tata Power commissioned 652 this year, compared with about 350 last year, nearly double the amount commissioned last year.
    Show source
    Last year, we were at about 350 and this year we have done 652.
  • Tata Power implemented nearly 650 megawatt in this quarter and plans to substantially increase commissioning in the coming quarter.
    Show source
    So, we need to look from that perspective that what is our pipeline and our readiness to commission this and we have been able to successfully implement nearly 650 megawatt in this quarter and have plans to substantially increase in the coming quarter.
  • At Mundra, availability was say 90%, while power scheduling was only 60%.
    Show source
    But scheduling they do only 60%.
  • Tata Power's loss was Rs. 65 crores this quarter, compared to Rs. 8 crores profit last year.
    Show source
    Management: Subhadeep, the loss was Rs. 65 crores this quarter compared to Rs. 8 crores profit last year.
Show 7 more statements

Results

  • Tata Power supplied 1,000 units in March last year, 8,000 units in March this year and 20,000 units in June this year, and hopefully will supply 40,000 to 50,000 units per month in the later part of this year.
    Show source
    This year, June, we supplied 20,000 units and hopefully later part of this year, we will supply 40,000 to 50,000 units per month.
  • Tata Power's Delhi distribution entity had a one-off order of Rs. 164 crores last year; on a like-to-like basis, it did much better this quarter, with 134 against 123 after removing 164 from 287.
    Show source
    Against that, we have done 134.
  • Tata Power’s performance in Indonesia was muted because coal prices there came down.
    Show source
    But other than that all the others are doing very well.
  • Tata Power’s power scheduling was lower during the first quarter because of the early monsoon, reducing revenue, although power availability was always there.
    Show source
    During the first quarter, because of the early monsoon, the scheduling of power took place less.
  • Tata Power’s revenue was also affected because coal prices were soft.
    Show source
    And the second is of course, the coal prices were soft.

Money and capital

  • Tata Power spent Rs. 3,700 crores this quarter against its full year plan of Rs. 25,000 crores.
    Show source
    We spent in this quarter Rs. 3,700 crores against our full year plan of Rs. 25,000 crores and we are on track to implement all those projects.
  • Tata Power's net debt increased by nearly Rs. 2,900 crores to Rs. 47,578 crores compared with the previous quarter.
    Show source
    Our net debt has gone up by nearly Rs. 2,900 crores to Rs. 47,578 crores and in spite of this increase in net debt compared to the previous quarter, our leverage ratios have been very, very stable.

What it expects ahead

What management expects

  • Tata Power expects nearly 1,600 megawatt of own utility scale projects to come up in the next three quarters, enhancing the operating capacity of its renewable business.
    Show source
    We expect nearly 1,600 megawatt of own utility scale projects to come up in the next three quarters and that will help us in enhancing the operating capacity of the renewable business.
  • Tata Power expects to bring the figure in the 17%-18% range down to about 10% in the next 3 years; the reductions seen in the last 4 years are expected to continue and help deliver better returns.
    Show source
    We do expect that in the next 3 years, we will bring down to about 10% range and the type of reductions that we have seen in last 4 years, this trend will continue and that will help us in getting better returns.
  • Tata Power expects collection efficiency to consistently become 100%, as in Delhi and Mumbai.
    Show source
    We do expect that this will consistently become 100% as we see in Delhi and Mumbai, where we have our distribution setup.
  • Tata Power expects to operate all 5 units continuously for the balance of the year once the Supplementary PPA (SPPA) is finalized.
    Show source
    We do expect that as soon as the SPPA (Supplementary PPA) is finalized, we will be in a position to operate all the 5 units continuously for the balance of the year.
  • Tata Power says the Supplementary PPA (SPPA) would be either something like what it gets in Section-11 or a little lower, but in that range.
    Show source
    This will be either something like what we get in Section-11 or a little lower than that, but it will be in that range that it would be there.
  • Tata Power expects 80% availability at Mundra on an overall year basis, on which it gets 100% capacity charge.
    Show source
    And we expect that on an overall year basis, we will have 80% availability on which we get 100% capacity charge.
Show 8 more statements

What management expects

  • Tata Power will operate at 80% once the supplementary PPA is finalized and will get 100% fixed cost, and it does not expect any under-recovery.
    Show source
    Based on what we operated in first quarter and what is our plan to operate in the rest of the year once the SPPA is finalized, we will be doing 80% on which we get 100% fixed cost.
  • Tata Power is in active discussions with a large number of C & I customers and thinks the whole 1,000 megawatt of Bhivpuri PSP capacity will get tied up very quickly; it is also looking at starting work on another 1,800 megawatt.
    Show source
    So, there is a huge demand especially for all companies who want to have signed under RE100 or want to supply their products to countries in Europe and UK which have the cross -border carbon tax.
  • Tata Power expects this quarter's manufacturing output to be much higher than the last quarter because of better yield and efficiency.
    Show source
    This has now further stabilized and we do expect that this quarter will be much higher than the last quarter because of better yield and efficiency.
  • Tata Power expects the Supplementary PPA (SPPA) to be much more than the PPA, to protect it from future increases in the cost of pool and ensure consistency of supply going forward.
    Show source
    Secondly, this will definitely be much more than the PPA, otherwise there is no need of doing the SPPA and it will also protect us from any increases in cost of pool that happens in future.
  • Tata Power expects rooftop business volume to increase tremendously because demand is huge and not many players can cater to it.
    Show source
    What you will see is that the volume will increase tremendously because there is a huge demand and as you rightly mentioned there are not many players who are able to cater to that.
  • Tata Power expects its TOPCon line cells, transmission and distribution business CAPEX, and new renewable projects to start being reflected next year.
    Show source
    So, all those will start getting reflected next year.
  • Tata Power’s yearly commissioning plan, based on its project pipeline, will be implemented; the company is geared up with the required equipment and land. Replaced by a later filing.
    Show source
    So, our yearly plan, whatever we have based on the projects that we have in our pipeline will get implemented and we are fully geared up for that in terms of the equipment and land that is required.

Orders

  • Tata Power has plans to add more than 2 gigawatt per year to its in-house order book.
    Show source
    This year itself we will be doing more than 2 gigawatt of commissioning.

What it is building and selling

Projects and capacity

  • Tata Power expects its pumped hydro project to be commissioned by 2028-29; work started in the last quarter.
    Show source
    We have already started work on our pumped hydro project in the last quarter and we expect that this will get commissioned by 2028-29.
  • Work on Tata Power's Bhutan project started in January this year and it will be commissioned in 29.
    Show source
    Similarly, the work on the Bhutan project started in January this year that will also get commissioned in 29.
  • Tata Power has a pipeline of 5.4 gigawatt of its own projects where it is the developer; it wants to complete these in the next 2 years before considering third-party projects, and has paused taking outside orders in the meantime.
    Show source
    So, in next 2 years, we want to complete all this and then see if we have capability to take up third- party projects.
  • Tata Power is waiting for finalization of the Supplementary PPA (SPPA) before starting the plant.
    Show source
    So, we are waiting for this finalization of the SPPA before we start the plant.
  • With fewer orders for third party, Tata Power’s subsequently commissioned higher capacity will be for its own internal utility scale project.
    Show source
    So, now that we do not have too much of orders for third party, subsequently as you will see much higher capacity that we get that commission and those will be for our own internal utility scale project.
  • Tata Power is executing projects that prescribe Indian made cells and DCR cells and models.
    Show source
    So, we are executing number of projects which have prescribed that it should be only Indian made cells, DCR cells and models should be there.
Show 7 more statements

Demand and pricing

  • The PM Surya Ghar program has said 1 crore households, while the country has 25 crore households.
    Show source
    The country, you know PM Surya Ghar, has said 1 crore households.
  • Tata Power says there is huge demand from companies that want to be signed under RE100 or supply products to countries in Europe and UK that have the cross-border carbon tax.
    Show source
    So, there is a huge demand especially for all companies who want to have signed under RE100 or want to supply their products to countries in Europe and UK which have the cross -border carbon tax.
  • Tata Power is building brand and demand for its rooftop product to become number one, or to become number one with better service and quality of supply. Replaced by a later filing.
    Show source
    And this is a brand and a demand for this product that we are building in the market so that we become number one or we are already number one but become number one with a much better service and quality of supply in this.

Segments

  • Tata Power uses its own cell and module for practically 100% of its rooftop business, which is DCR.
    Show source
    Rooftop business practically 100% is now our own cell and module DCR Page 5 of 19 The Tata Power Company Limited August 1, 2025 and also in many of our projects we are using our own cell and module.
  • Tata Power’s reach in the market has improved and is increasing as it adds channel partners and market segments in which it supplies. Replaced by a later filing.
    Show source
    And today our reach in the market has improved and it is further getting enhanced as we continue to add more of channel partners and market segments in which we are supplying.

Deals and partners

  • Tata Power expects to conclude an arrangement with all five procurer states within August for power supply through 2038, as a template for the next 13 years.
    Show source
    We are since then in a very detailed discussion with all the 5 procurer states and all the details, papers have been shared with them and we do expect that we will be able to conclude to an arrangement acceptable to all the 5 procurers and us within August and we continue to work with them on finalizing this so that this becomes the template for the supply of power for next 13 years up to 2038.
  • Tata Power is in discussion with Tata Steel and many other Tata Group companies.
    Show source
    But yes, we are in discussion with Tata Steel as also with many other Tata Group companies.

Risks, rules and outside factors

Risks and disputes

  • The order was dated 1st July, Tata Power has until 30th of September to file an appeal, and it expects the matter to be heard and decided in about 6 to 9 months.
    Show source
    Normally, it takes about 6 to 9 months for the matter to be heard and decided.

Outside factors

  • Tata Power expects international coal prices to remain softer for at least the next few years, making Mundra Power attractive in the merit order.
    Show source
    As all of you are aware with these lower coal prices, international coal prices, the cost Page 2 of 19 The Tata Power Company Limited August 1, 2025 of Mundra Power is very attractive in the merit order and we do expect that this price will continue to be softer at least for next few years and hence the attractiveness of Mundra plant is there.
  • Tata Power says Mundra coal prices have come down and are expected to remain in the same range going forward, keeping the power very competitive.
    Show source
    And since the coal prices have come down and it is expected to be in the same range, going fo rward also it will remain very, very competitive.

Rules and policy

  • From 1st of April, the multi year tariff has been implemented in Maharashtra, with a slight dispute over the tax applicable on the tariff side and the regulatory side; the matter has been disclosed separately.
    Show source
    Management: So, that is basically from the current year starting from 1st of April, the multi year tariff has been implemented in Maharashtra and that is a slight dispute going on in terms of the tax that is applicable on the tariff side and the regulatory side and hence that has been disclosed separately.
  • Effective 1st June 20 26, all projects will require DCR cells and models.
    Show source
    But effective 1st June 20 26, for all projects you will require DCR cells and models.
  • Tata Power’s cell plants are scheduled for inspection next week; cell suppliers are added to ALMM-II as inspections are completed.
    Show source
    I am told that they are inspecting next week.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Sumit Kishore: So, this is one last point regarding Mundra, while you have given ample clarification, but in terms of your strategy, in case, given the past track record of arriving at a resolution with the procurer, till what time are you prepared to wait before you restart the plant and start supply ing in tune with your contract? Dr. Praveer Sinha: So, we had number of discussions in last one month and there is a consensus that is building because one is that Mundra in merit order is very competitive and it makes sense for everyone to procure this power rather than buy from exchange or from other sources at a much higher source.

    Answer, praveer sinha

    And since the coal prices have come down and it is expected to be in the same range, going fo rward also it will remain very, very competitive. So, it is a win -win for everyone and I do expect that there is a huge pressure amongst these procurers also that they need to conclude this quickly . Page 7 of 19 The Tata Power Company Limited August 1, 2025 Sumit Kishore: Thank you.

  2. Question

    Satyadeep Jain: Hi, thank you. Just want to clarify when you are selling supplying module to for rooftop and all, would that also be at similar price that we see or would that be a different DCR realization? Just trying to understand the arm's length. Dr. Praveer Sinha: See, every pricing is based on the market demand and supply.

    Answer, praveer sinha

    Rooftop has a different demand and supply and a different price range in which they operate d and you need to compete over there vis-à-vis other players with similar types and quality of modules. So, those prices are at arm's length and is independently negotiated between both businesses.

  3. Question

    Satyadeep Jain: Okay. Just on the commissioning, I am not sure if I missed in the prepared part. The commissioning, as you can understand, there is a spillover but overall industry saw a lot of significant increase in commissioning in this quarter, possibly some spillover from fourth quarter. What led to relatively muted commissioning for Tata Power in this quarter compared to the entire industry? Just generally trying to understand was there specific one-off reasons? Dr. Praveer Sinha: See, we have commissioned much more than what we had commissioned last year.

    Answer, praveer sinha

    Last year, we were at about 350 and this year we have done 652. So, we have done nearly double of what we had commissioned last year. So, we need to look from that perspective that what is our pipeline and our readiness to commission this and we have been able to successfully implement nearly 650 megawatt in this quarter and have plans to substantially increase in the coming quarter. So, our yearly plan, whatever we have based on the projects that we have in our pipeline will get implemented and we are fully geared up for that in terms of the equipment and land that is required. Page 8 of 19 The Tata Power Company Limited August 1, 2025 Satyadeep Jain: Okay.

  4. Question

    One quick question if I can squeeze or follow up to Mundra. Just trying to understand that not running the plant, obviously, the under -recovery on fuel front, given where coal prices are, would be lower than the recovery on the fixed cost. So, this is a strategy that then there is supplementary PPA, you will not operate. Just clarifying, I think you mentioned in the last answer, but that would be a strategy no matter what happens, you will not operate the plant till the supplementary PPA is signed. And any maybe indication of what that based on the conversations, what are the timelines are we looking at as we look at the supplementary PPA and in what form and shape would it look like? Would

    Answer, praveer sinha

    Secondly, this will definitely be much more than the PPA, otherwise there is no need of doing the SPPA and it will also protect us from any increases in cost of pool that happens in future. And to that extent, the consistency of supply going forward will be ensured. This will be either something like what we get in Section-11 or a little lower than that, but it will be in that range that it would be there.

  5. Question

    Anuj Upadhyay: Hi sir. Thanks for the opportunity and congrats on good set of numbers. Sir, again a follow-up question on your rooftop business. While we see even in the previous quarter where our cell plant is more partially operational, we did close to around 13 %-14% kind of a margin and considering the fact that the DCR supply has been quite constrained off late, the people who have access to it are meeting a very high margin by selling it to the third party. So, just want to get a sense on your rooftop business by using our own DCR cell and modules. Is there a probability that our margins in the rooftop segment can go further northward from 14 %-15% or it would be passed on at a pricing

    Answer, praveer sinha

    And today our reach in the market has improved and it is further getting enhanced as we continue to add more of channel partners and market segments in which we are supplying. We are making good returns in that and I think we will continue to make the type of returns that you have seen. What you will see is that the volume will increase tremendously because there is a huge demand and as you rightly mentioned there are not many players who are able to cater to that. And this is a brand and a demand for this product that we are building in the market so that we become number one or we are already number one but become number one with a much better service and quality of supply in this.

  6. Question

    Anuj Upadhyay: That is helpful, sir. And secondly on your underperformance across the JV segment, has it largely to do with the coal underperformance in Indonesia or some other element to it? Page 10 of 19 The Tata Power Company Limited August 1, 2025 Dr. Praveer Sinha: So, basically the coal prices in Indonesia has come down and that is why our performance over there is muted.

    Answer, praveer sinha

    But other than that all the others are doing very well.

  7. Question

    Mahesh Patil: Yes. And we can assume this would be the 100 going forward, let us say around 2 gigawatt of commissioning? Dr. Praveer Sinha: More than that.

    Answer, praveer sinha

    This year itself we will be doing more than 2 gigawatt of commissioning. So, now that we do not have too much of orders for third party, subsequently as you will see much higher capacity that we get that commission and those will be for our own internal utility scale project.

  8. Question

    And sir, in terms of let us say PPA signing or transmission connectivity, are there any challenges in terms of even for the installed projects, let us say transmission availability, are there some challenges? We have heard about some issues in this quarter. Dr. Praveer Sinha: Those are the localized issues in terms of land or evacuation and all that.

    Answer, praveer sinha

    Those are things that we keep on addressing as we implement these projects.

  9. Question

    Mahesh Patil: Okay, sir. And sir, in this development, the issue with Kleros Capital Partners, would you like to share some update on this? Dr. Praveer Sinha: So, we have already given in the notes, and you can see that since the matter is sub- judice, we cannot speak much on that.

    Answer, praveer sinha

    So, whatever we have provided in the notes, that is our stand.

  10. Question

    Apoorva Bahadur: Hi, sir. Thank you for the opportunity and congratulations on the results. A couple of questions. I first of all wanted to check that recently the list of cell suppliers under ALMM-II was released. I think there were 5 or 6 players which are identified. Can you give any color why we were not on that list? Dr. Praveer Sinha: On the cell, because they have not completed the inspection.

    Answer, praveer sinha

    I am told that they are inspecting next week. So, as and when they complete the inspection of plants, they keep on adding. So, they will add as soon as they complete the inspection.

Show 16 more questions
  1. Question

    Apoorva Bahadur: Sure, sir. That is helpful. I also seen in your presentation where you comment on individual businesses, so for the standalone business, a reason for decline in revenue has been attributed to change in the annual availability assumptions at Mundra. So, can you share what is the overall impact of these changes on the revenue? How much is the under recovery we are assuming at Mundra? Dr. Praveer Sinha: We are not assuming any under recovery because in the first quarter, we already had 90% availability.

    Answer, praveer sinha

    And we expect that on an overall year basis, we will have 80% availability on which we get 100% capacity charge. Page 12 of 19 The Tata Power Company Limited August 1, 2025 Apoorva Bahadur: So, in that case, why is it impacting our standalone revenue?

  2. Question

    Dr. Praveer Sinha: No, revenue will be less depending upon the scheduling of power.

    Answer, praveer sinha

    During the first quarter, because of the early monsoon, the scheduling of power took place less. But the availability of power was always there. So, availability was say 90%. But scheduling they do only 60%. Then that is why the revenue. And the second is of course, the coal prices were soft.

  3. Question

    Apoorva Bahadur: Sure, sir. Thank you so much.

    Answer, praveer sinha

    Based on what we operated in first quarter and what is our plan to operate in the rest of the year once the SPPA is finalized, we will be doing 80% on which we get 100% fixed cost. And we don't expect any under-recovery. Subhdeep: But that's under the assumption that the supplementary PPA is signed. And in case there are delays, then one could expect some under-recoveries between them? Dr. Praveer Sinha: Yes, but since we are expecting that this is in final stage, it should hopefully be finalized.

    Answer, praveer sinha

    We have considered a loss of Rs. 65 crores from our... Management: Subhadeep, the loss was Rs. 65 crores this quarter compared to Rs. 8 crores profit last year. Subhdeep: Understood. Perfect. Thank you so much.

    Answer, praveer sinha

    So, continue to consider anything which will help us improve our performance based on the demand supply and how many other plants are coming, similar plants are coming. So, this is definitely under discussion. Avish: Okay. Thank you so much.

  4. Question

    Aniket Mittal: Yes, thank you. A couple of questions on EPC front. So, when I look at the third-party utility scale order book that has come down fairly drastically this quarter, just to understand, is this like a conscious decision where we do not want to take these utility scale projects now or how do I look at that piece going forward? Dr. Praveer Sinha: We have a pipeline of 5.4 gigawatt of our own projects in which we are the developers.

    Answer, praveer sinha

    So, for us, the focus is that how do we first cater to this 5.4 megawatt. So, in next 2 years, we want to complete all this and then see if we have capability to take up third- party projects. So, that is why we have taken a pause on that and we will first complete our project and then look at outside orders.

  5. Question

    Aniket Mittal: Fair. That is very clear. The second question was just to delve a bit into the rooftop market. We continue to see very good orders over here. Let us say if you were to take Page 14 of 19 The Tata Power Company Limited August 1, 2025 a 3 to 5 year view on this segment, how do you look at annual sort of installation happening within the rooftop segment and if you can break that up between both C &I and residential that would be great? Dr. Praveer Sinha: Just to give you an idea that last year March, we supplied 1,000 units.

    Answer, praveer sinha

    This year, March, we supplied 8,000 units. This year, June, we supplied 20,000 units and hopefully later part of this year, we will supply 40,000 to 50,000 units per month. So, the demand is humongous. The country, you know PM Surya Ghar, has said 1 crore households. We have actually in the country 25 crore households. So, whatever we will do will be still very small compared to the total market opportunity which is there. So, I would leave it to you to guess and estimate that what sort of demand will be there for next 5-10 years.

  6. Question

    Aniket Mittal: Just one clarification regarding this. When we talk about the DCR applicability, this is currently applicable only on the residential spaces. The DCR is not there for C&I rooftops. Is that correct? Dr. Praveer Sinha: So, the anything where the government funding is there or subsidy is there, so whether it is rooftop or it is PM, the KUSUM program, there you have to, also there are number of projects which insist on DCR model.

    Answer, praveer sinha

    So, we are executing number of projects which have prescribed that it should be only Indian made cells, DCR cells and models should be there. But effective 1st June 20 26, for all projects you will require DCR cells and models.

  7. Question

    Satyadeep Jain: Hi. Thank you for the follow-up. Just on the Bhivpuri PSP, now that you have commenced construction, historically you were open to the idea of keeping this entire capacity open till maybe later stages. Are you still holding on to that thought? Keep it open and you will maybe look at signing agreements as you get closer to commissioning? Page 15 of 19 The Tata Power Company Limited August 1, 2025 Dr. Praveer Sinha: No. We are already in active discussion with large number of C &I customers and I think the whole 1,000 megawatt will get tied up very quickly and that is why we are now also looking at starting work on the another 1,800 megawatt.

    Answer, praveer sinha

    So, there is a huge demand especially for all companies who want to have signed under RE100 or want to supply their products to countries in Europe and UK which have the cross -border carbon tax. So, I think we will be able to tie up all the quantities with various subsidies.

  8. Question

    Satyadeep Jain: So, just somebody like Tata Steel, I know all these RE-RTC would be relevant for steel and aluminum and all. Could Tata Steel be a potential customer for this? Because we have not seen any steel company tie up PSP yet. So, I am just trying to understand. Dr. Praveer Sinha: Because the PSPs have not come to that extent.

    Answer, praveer sinha

    But yes, we are in discussion with Tata Steel as also with many other Tata Group companies.

  9. Question

    Sushil Choksey: Congratulations on very stable result. So, my first question is on solar cell capacity. Where are we today and what is the efficiency of Mono PERC and TOPCon? And second thing is what is the run rate on module 2? Dr. Praveer Sinha: So, we have already shared with you that how much of cell and module we have supplied in the first quarter and now the plant has got further stabilized and we will see further improvement in the performance of the plant.

    Answer, praveer sinha

    And right now most of it is the Mono PERC. But soon we will start supplying even modules using TOPCon cells. And I think there is a huge demand for all this and we will continue to meet the requirement of the market.

  10. Question

    Sushil Choksey: Okay. What is your, based on the new rules which are effective 1st of June next year, what kind of demand India will have for cell requirements? Dr. Praveer Sinha: There are lot of consultant reports which are there.

    Answer, praveer sinha

    We can share with you some of those consultant reports.

  11. Question

    Sushil Choksey: But if you just throw a ballpark number? Dr. Praveer Sinha: I do not know the ballpark number.

    Answer, praveer sinha

    But I can share with you the reports which are there in the news.

  12. Question

    Sushil Choksey: How are you seeing the demand on rooftop solar and KUSUM scheme from our perspective and competition? Dr. Praveer Sinha: Yes, I mentioned to you there are whole lot of reports which are there.

    Answer, praveer sinha

    You can get in touch with Rajesh. He will be able to share some reports with you.

  13. Question

    Vishal Periwal: Yes, sir. Thanks for the opportunity. Sir, on the start of our Delhi distribution entity, the slide talks about there has been a lower demand which led to decline in revenue. But what would be the reason that it is slowing through a PAT, the decline? Because what we understand is, it is a regulated business and the PAT should matter much. So, if you can explain? Page 17 of 19 The Tata Power Company Limited August 1, 2025 Dr. Praveer Sinha: Last year, we had a one-off order of Rs. 164 crores.

    Answer, praveer sinha

    So, on a like-to-like, if you see, we have done much better in this quarter. So, if you remove 164 from 287, it becomes 123. Against that, we have done 134.

  14. Question

    Vishal Periwal: Okay, got it. In terms of our EBITDA growth, we have started at a good growth rate this year. But once a base is stabilized, maybe like the solar cell and module for this year, next year, I mean, according to you, what could be a growth driver for us that we can visualize? Dr. Praveer Sinha: There are a whole lot of things that we are doing.

    Answer, praveer sinha

    We still have to start getting the cells from the TOPCon line, the CAPEX that we are doing in our transmission business, in our distribution business, in our new renewable projects that we are setting up. So, all those will start getting reflected next year.

  15. Question

    Arun Selvan: Hi, just a quick question. With respect to the awards, I think that you are considering all options. I just wanted to check if, have we actually filed either an appeal or an application to set aside the quantum award? And any estimates on what would be the timeline for the higher court to take a decision on that? Dr. Praveer Sinha: So, we are given 90 days to file the appeal.

    Answer, praveer sinha

    The order was dated 1st July. So, we have time till 30th of September and we find that much before. Normally, it takes about 6 to 9 months for the matter to be heard and decided. So, that's the timeline that we are expecting.

  16. Question

    Arun Selvan: Okay. Thank you.

    Answer, praveer sinha

    If you have any other queries, please connect with my colleagues, Rajesh and Kasturi and we will be more than happy to provide you the details. Also, if there are any inputs, any suggestions on improving the type of presentation that we have shared or more details that you require, we will be happy to incorporate that and improve the quality of presentation which is being shared with all of you. Once again, thank you and all the best and have a great weekend. Thank you.

Questions about this call

When was the Tata Power Company Q1 FY26 earnings call transcript filed?
Tata Power Company filed the transcript with the exchange on 6 Aug 2025. This page is built from that transcript.
What does this page list?
46 statements from the transcript across 11 topics, 28 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 26 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Tata Power Company Q1 FY26 concall: Tata Power has plans to add more than 2 gigawatt per year to its in-house order book · DalalOS