Acme Solar Holdings Q1 FY26 earnings call: Acme Solar Holdings Limited secured its first standalone battery energy storage projects of 550 MWh contracted with NHPC, and signed the PPA in one month

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company secured its first standalone battery energy storage projects of 550 MWh contracted with NHPC, and signed the PPA in one month. The company is currently not in favor of using an Indian containerized solution for a large FDRE project because, for 2.5 percentage of cost improvement, the vendor would need to warranty 15 years of performance and the warranty presents a big risk. Operational portfolio of independent power producers stands at 2890 MW, capable of delivering annual steady state project level EBITDA of INR2,000 to INR2,050 crores and an EBITDA yield of around 14 %-15%. Revenue increased by 71.8% for Q1 FY26 on a year-on-year basis, driven by capacity addition and higher CUF; total revenue for Q1 FY '26 was around INR584 crores, a 72% increase year-on-year. FDRE tariffs of up to 4.98 have been signed by discoms for projects with longer hours of storage that supply power even at night.

The numbers management gave

Results

  • EBITDA for Q1 FY '26 was INR531 crores, up 76% year-on-year, and its EBITDA margin was 91%, aided by operational capacity growth and a reduction in the overall percentage cost.
    Show source
    So, the margin is now at 91%.
  • PAT for Q1 FY '26 was INR131 crores, a sharp jump because of capacity growth in the year; PAT margin was 22.4% in Q1 FY26.
    Show source
    PAT is INR131 crores, a very sharp jump, of course, because of the capacity growth we had in this year.
  • Rajasthan accounted for 2250 megawatt of Acme Solar Holdings Limited's operational portfolio and delivered a 30.3% CUF.
    Show source
    It accounts for 2250 megawatt of our operational portfolio delivering an impressive 30.3% CUF.
  • Capex actually done in Q1 was around INR800-odd crores, while orders closed were around INR7,000 crores.
    Show source
    Nikhil Dhingra: Capex actually done is around INR800-odd crores, but the orders closed is around INR7,000 crores.
  • Revenue increased by 71.8% for Q1 FY26 on a year-on-year basis, driven by capacity addition and higher CUF; total revenue for Q1 FY '26 was around INR584 crores, a 72% increase year-on-year. Replaced by a later filing.
  • Days of sales outstanding dropped to 36 days in Q1 FY '26. Replaced by a later filing.
Show 16 more statements

Results

  • The company generated 163 crores units in Q1 FY '26, up over 107% year-on-year, and its capacity utilization factor improved to 28.5% from 27% last year. Replaced by a later filing.

Money and capital

  • Four SECI assets, with a cumulative capacity of 1,200 megawatt, secured CRISIL AA- stable rating within six months of full operations. Each of ACME Solar Holdings Limited’s recently commissioned 4x300 MW SECI ISTS solar projects received a CRISIL AA-/Stable rating.
    Show source
    On credit rating, we are pleased to share that within six months of full operations, our four SECI assets with a cumulative capacity of 1,200 megawatt have secured CRISIL AA- stable rating.
  • The company has started reducing its cost of financing below 8.5%.
    Show source
    We have already started reducing our cost of financing below 8.5% as we speak.
  • The company has placed purchase orders close to INR7,000 crores in this year and plans to order batteries and the rest of the equipment very soon.
    Show source
    We have already placed purchase orders of close to INR7,000 crores in this year and we, as we said that we want to order the battery and we want to order the rest of the equipment very soon.
  • Interest cost on its portfolio, especially operating projects, is close to 8.75% as of the call.
    Show source
    So, our interest cost on a portfolio basis especially for operating projects is close to 8.75% as we speak.
  • The company considers its last 2-3 projects, commissioned in the last 2-3 months, to be under construction and believes their interest rates will also go down.
    Show source
    We still consider under construction we believe that interest rate in those projects will also go down.
  • The RBI rate reduction has not yet flowed through to Acme Solar Holdings Limited's numbers because some projects' annual resets have not arrived and refinancing has not been completed; only one of four ISTS projects has been refinanced, while three remain to be refinanced and are still at more than 9% interest cost.
    Show source
    So, they are still running at more than 9% interest cost.
  • The company has sanctions for interest rates 1% lower than the current rate on three ISTS projects, but has not activated them because it has sufficient liquidity of more than 3,000 crores and does not need the additional debt; it is timing refinancing to avoid early disbursement.
    Show source
    We do have sanctions for let's say 1% lower than that but we have not activated them because we don't need the extra debt which is being provided by these because we have sufficient liquidity of more than 3,000 crores.
  • The company finances capex 75-25 in terms of debt and equity and typically receives revenue 8 to 9 months after weighted average capex is done.
    Show source
    So see, capex is financed 75-25 in terms of debt and equity for us.
  • Capex target for this financial year is close to INR 14,000 crores, with debt for that capex around INR 11,500 crores; the debt will come towards the end of the year because capex in this quarter was INR 800 crores.
    Show source
    So in terms of this financial year, our capex target is close to, let's say, INR 14,000 crores, but it may -- but the weighted average, so the debt for that would be around INR 11,500 crores.
  • ACME Solar Holdings Limited’s net debt to EBITDA was 4.2x as of Q1 FY26, within its targeted range of 5.5x.
    Show source
    How we calculate is basically the operational project debt and the operational project EBITDA.
  • ACME Solar Holdings Limited's net debt to net worth ratio improved to 1.7x during FY '25.
    Show source
    Our net debt to net worth stands at 1.7x which is again very healthy.
  • Weighted average cost of debt was reduced substantially, and the company said it would benefit from base rate and spread reductions because of improvement in credit rating.
    Show source
    We were able to reduce our weighted average cost of debt substantially and we will as we take benefit of the base rate reduction and the spread reduction because of improvement in credit rating.
  • Holding company rating is A+ with positive outlook.
    Show source
    Today our holding company rating is A+ with positive outlook.
  • The company says LC payments will occur toward the end of delivery, just before commissioning, lowering the impact on overall debt and interest cost; interest during construction is capitalized and hits the P&L only when revenue starts increasing.
    Show source
    So the impact on the overall debt and the interest cost will be lower.
  • The company received a disbursement of around INR1,070 crores in Q1 FY '26 for refinancing debt on a 250 MW operational project at a fixed interest rate of 8.5% for 5 years; the interest cost was reduced by 95 basis points. Replaced by a later filing.

What it expects ahead

What management expects

  • The company is currently not in favor of using an Indian containerized solution for a large FDRE project because, for 2.5 percentage of cost improvement, the vendor would need to warranty 15 years of performance and the warranty presents a big risk.
    Show source
    We are currently not in favor of that.
  • The company guided capex of INR12,000 crores to INR 14,000 crores for this year and expects a similar amount for next year; capex is trending downward given battery price falls.
    Show source
    So that is typically for a -- for this year we have guided around INR12,000 crores to INR 14,000 crores of capex.
  • The company expects a significant reduction in interest cost by the end of this financial year, due to interest resets at COD and yearly resets, and loan refinancing; RBI's 50 basis point reduction makes a similar reduction over the next 6 to 8 months a reasonable assumption.
    Show source
    So, I think during this financial year as we end this financial year we are expecting much significant reduction in the interest cost.
  • The NHPC tender is expected to generate around INR70 crores of revenue at its peak.
    Show source
    Of course, it will generate, at its peak, around INR70 crores of revenue.
  • The company says peak-hour tariffs in India are around INR9 and charging costs for the battery are much lower; its merchant project will have 2500-megawatt hour of battery, compared with 550MWh for the NHPC project, and is expected to generate substantially higher revenue.
    Show source
    So there will be a much higher revenue purely from -- much higher than this number of NHPC.
  • The company expects its project ratings to remain consistently in the AA family going forward, with ratings specific to the projects.
    Show source
    I think we expect going forward our rating to be consistently in the AA family, of course specific to rating of the projects.
Show 13 more statements

What management expects

  • The company expects that adding more central REIA projects will contribute significantly to its holding company rating.
    Show source
    But also it will contribute significantly to the holding company rating as we contribute and add more and more central REIA projects.
  • The company may use capital markets for a portion of its future financing, diversifying funding sources to mutual funds, insurance companies, and provident funds.
    Show source
    And so certain mix of this financing going forward could be from capital market, gives us diversification into various fund providers such as mutual funds, insurance companies and also provident funds.
  • The company expects significant interest cost benefits still to come because it has not yet refinanced.
    Show source
    So, there is significant benefit yet to be coming because we have not refinanced yet.
  • The merchant project is five times larger at commissioning than the NHPC project, with substantially higher revenue and profits.
    Show source
    And the revenue and profits are also substantially higher.
  • The company does not want to provide guidance on the merchant-based project and treats it as part of its upside planning; the project has been preponed.
    Show source
    We don’t want to give a guidance on that, since it's a merchant-based project.
  • ACME expects to meet its revenue targets as battery and FDRE projects are commissioned because its PPA is tied up.
    Show source
    So I think depending on these commissionings, we will be meeting those revenue targets, because our PPA is tied up, right?
  • The company expects growth to be much higher than last year. Replaced by a later filing.
    Show source
    It will be much higher than the last year is what we feel.
  • ACME expects to share the results of the second stage of testing in the next two months, three months, before final installation in November, December, or January, February. Replaced by a later filing.
    Show source
    And we should be able to share with you in next two months, three months, that the result of even in the second stage of the testing, before the final installation happens in November, December, or January, February.

Orders

  • The company secured its first standalone battery energy storage projects of 550 MWh contracted with NHPC, and signed the PPA in one month.
    Show source
    In terms of new wins, we secured our first standalone battery energy storage projects of 550 MWh contracted with NHPC.
  • The company signed PPAs for 550 MW of FDRE and solar projects and 550 MWh of standalone BESS projects in Q1 FY '26.
    Show source
    Further, in this quarter, we signed PPAs of 550 MW of FDRE and solar project and 550 MWh are of standalone BESS projects.
  • The company placed orders for over 3.1 GWh of battery energy storage systems with suppliers including Narada and Trina Energy for its under construction capacity.
    Show source
    For our under construction capacity, we have placed orders of over 3.1 GWh of battery energy storage system with suppliers like Narada and Trina Energy.
  • The company has placed purchase orders in excess of around 7,000 crores so far for its under construction portfolio.
    Show source
    So, all in all, we have placed purchase orders in excess of around 7,000 crores so f ar for our under construction portfolio.
  • The company is trying to close 2 gigawatt hour more of battery orders in the next month or so to complete the overall battery requirement, which will be around 4.5, 5 gigawatt hour.
    Show source
    So in the next month or so, we are trying to close 2 gigawatt hour more of orders that will complete the overall battery requirement.

What it is building and selling

Projects and capacity

  • Operational portfolio of independent power producers stands at 2890 MW, capable of delivering annual steady state project level EBITDA of INR2,000 to INR2,050 crores and an EBITDA yield of around 14 %-15%.
    Show source
    With this, our operational portfolio of independent power producers now stands at 2890 MW, capable of delivering an annual steady state project level EBITDA of INR2,000 to INR2,050 crores and an EBITDA yield of around 14 %-15%.
  • Under construction portfolio stands at 4080 MW plus 550 MWh of storage, and 55% of its portfolio has signed PPAs.
    Show source
    With this, our under construction portfolio stands at 4080 MW plus 550 MWh are of storage and 55% of our portfolio has signed PPAs.
  • Grid connectivity is in place for Acme Solar Holdings Limited's entire 4080 MW under construction portfolio.
    Show source
    Further, grid connectivity is in place for the entire 4080 MW of under construction portfolio.
  • The battery system installation capex is typically $100 per kilowatt hour, and the returns for the Andhra Pradesh NHPC project are in the high-teens and much above the company's 16% minimum return threshold; its IRR is lower than FDRE, but its risk is also lower than FDRE.
    Show source
    So the returns are much above that for this project.
  • The company is trying to early commission the BESS part of its contracted portfolio and operationalize it before the COD of the whole FDRE component; approvals have been taken from all counterparties, and the BESS will cater to 50% of the overall demand for this 2.3 gigawatt portfolio, improving pre-COD realizations through merchant prices for peak power.
    Show source
    So before the COD of the whole FDRE component, we are trying to get the battery components operationalized, which will help us improve the realizations pre-COD due to the merchant prices in terms of the peak power.
  • The company has ordered 5.6 gigawatt hour of battery capacity and plans to order another 55% soon.
    Show source
    So right now we have ordered 5.6 gigawatt hour.
Show 36 more statements

Projects and capacity

  • The company plans to install 3 gigawatt hour of batteries this year, another 3 to 3.5 gigawatt hour from January to June, and a further 3 gigawatt hour from June to December, taking the total to 10 gigawatt hour.
    Show source
    Manoj Upadhyay: So our plan is that we order -- we get first 3 gigawatt hour this year to install it.
  • FDRE capex is around INR 11 crores per megawatt and hybrid capex is around INR 8 crores per megawatt.
    Show source
    So capex wise, FDRE is closer to around INR 11 crores per megawatt and so -- and the hybrid is around INR 8 crores per megawatt.
  • The standalone battery project Acme Solar Holdings Limited won has an 18-month commissioning timeline; the customer is responsible for providing land and evacuation, and delays on the customer's side extend the timeline accordingly.
    Show source
    It depends on the size of the project but the project we have won is 18 months and the onus on giving the land and the evacuation lies on the customer.
  • The company is targeting to commission at least 2.5 gigawatt of the 3.1 gigawatt it has ordered by this financial year, in phases, including battery components of FDRE plants and some solar projects.
    Show source
    Our target is to commission if not 3.1 gigawatt at least 2.5 gigawatt by this financial year and we will be doing it in phases.
  • The company plans to add 450 megawatt of capacity and around 2.5 gigawatt hours of battery component of FDRE projects that can generate revenue.
    Show source
    Management: So just to conclude, we would be adding 450 megawatt of capacity and around 2.5 gigawatt hours of battery component of the FDRE projects which we can generate revenue from.
  • The company will charge the whole SJVN project, the NHPC project and the signed SECI 150 megawatt project next year; battery will be charged first, followed by solar according to the substation timeline.
    Show source
    So all these projects will be charged next year.
  • All FDRE projects signed by Acme Solar Holdings Limited before December '24 have a timeline of December '26.
    Show source
    So the timeline of them is December '26.
  • The company aims to complete the period from capex to revenue within six months, and says the weighted average debt addition will be much lower than INR11,500 crores because capex is deferred until shortly before product dispatch.
    Show source
    So that's how -- so the debt will not be addition, weighted average will be much lower than INR11,500 crores.
  • The company has 18 months from June for the NHPC plant and can commission it within six months once the Andhra Pradesh Government gives the go-ahead.
    Show source
    Once they give us the go-ahead, we can easily commission it in six months.
  • ACME tested power electronics reliability by connecting its FDRE system to a 33 kV grid and testing grid variations; it worked well.
    Show source
    They are very, very stable grid, but we wanted to abuse this -- abuse the testing, so we connected to 33 kV and tested all the variation possible in this one, and I'm proud to share with you that it worked very well for so many years.
  • ACME is installing a 10-megawatt hour battery, perhaps in the next two months.
    Show source
    As I shared with you in the last quarter, that apart from this, we are also installing 10-megawatt hour battery perhaps in next two months.
  • ACME is developing a new configuration that it believes will reduce land requirements by 15%, 20% from the next project onwards, allowing existing land in high-radiation areas to accommodate 15%, 20% more solar and helping improve generation.
    Show source
    So ACME started working on new configuration, where we believe from the next project onwards, we should be able to reduce our land requirement by 15%, 20% time, which means that existing land in the high radiation can accommodate 15%, 20% more solar.
  • ACME plans to conduct the second level of perovskite testing, at 50 kilowatts to 100 kilowatts, in the next three months, four months, before moving to a bigger level.
    Show source
    Now we will be moving the second level of the perovskite testing, maybe 50 kilowatts to 100 kilowatts, which we should be doing in next three months, four months, and then moving to the bigger level.
  • ACME Solar Holdings Limited commissioned 350 MW, including its first wind project.
    Show source
    So Q1 FY '26 has been an important quarter for us both in terms of financial results and strategic milestones.
  • The company will complete capex for solar and wind projects, with charging timed to the commissioning of CTU substations at new substations.
    Show source
    In terms of the capex perspective, the capex for the solar, wind all would be done but the charging of those will be done in sync with the commissioning timelines of the CTU substations because those are being done at the new substations.
  • The company is waiting for the Andhra Pradesh Government to give notice to proceed before its equipment arrives, so the Government can complete its readiness work.
    Show source
    So we are waiting for them to give us the notice to proceed.
  • ACME completed five years of continuous testing of its FDRE, comprising battery, solar and the grid; battery degradation was within the limit anticipated for five years of continuous testing.
    Show source
    And we were able to test the battery degradation, and I'm very happy to share with you they were very well within the limit, what we have thought of, of five years of continuous testing.
  • ACME's battery charging and discharging efficiency tests were within assumptions, and the tests indicated the battery can last for five years, ten years, as it was in the charge.
    Show source
    Third is we also wanted to test the charging and discharging efficiency of the battery, and again, I'm proud to share with you that those testings were well within the assumptions and that also shows the battery can last for five years, ten years, as it was in the charge.
  • ACME has operated its energy management system in both manual and automatic modes for the last five years.
    Show source
    For the last five years, we are operating in manual and automatic both mode.
  • The company won the Andhra Pradesh NHPC battery project, which is installed at the customer's premises and does not require the transmission evacuation substation capex typically required for a solar plant. Replaced by a later filing.
  • The company plans to charge some project components before the calendar year and some before March. Replaced by a later filing.
    Show source
    So, definitely some Page 13 of 24 ACME Solar Holdings Limited July 28, 2025 component will be charged before the calendar year and some portion would be charged before March.

Demand and pricing

  • FDRE tariffs of up to 4.98 have been signed by discoms for projects with longer hours of storage that supply power even at night.
    Show source
    Yes, if you look at the FDRE of longer hours, you will find tariffs of up to 4.98 which have been signed by discoms.
  • The peak tariff averaged around 9 hours on a 1 hour basis and 8.78 on a 2 hour basis over the last 12 months.
    Show source
    Page 11 of 24 ACME Solar Holdings Limited July 28, 2025 Nikhil Dhingra: Typically, what we are seeing is around 9 hours is the peak tariff on a 1 hour average basis for the last 12 months and 8.78 is the average for 2 hours in the last 12 months.
  • The NHPC tender has a 15-year contract with a levelized lower tariff constrained by the bid, while merchant sales can target the highest-paying hours.
    Show source
    And it's a 15-year long contract.
  • The company observes that peak tariff timing shifts between late night in summer and morning hours in winter.
    Show source
    So only the timing shifts.

Segments

  • Central off-takers made up 86% of Acme Solar Holdings Limited's overall portfolio.
    Show source
    Of course, the proportion of central off-takers in our overall portfolio has moved to 86% now.
  • An FDRE project can extend to a 24-hour project, while a solar plus storage project may have shorter storage hours, extending up to 4 hours; solar plus storage tenders can have a 2-hour or 4-hour peak, with wind potentially needed to extend supply at a competitive price.
    Show source
    So the FDRE typically can have longer hours of storage, but a solar plus storage may have a shorter hours of storage extending up to 4 hours.
  • The FDRE tenders Acme Solar Holdings Limited has mostly seen typically have 4 hours of storage, while solar plus storage has lower storage hours, such as 2 hours and in some cases 1 hour.
    Show source
    They have been interchangeably used in all the tenders in terms of the FDRE and solar plus storage, but the tenders we have mostly these all FDREs are having 4 hours of storage typically.

Deals and partners

  • Bank of America, Standard Chartered Bank, and India Infradebt Limited entered Acme Solar Holdings Limited's loan book in Q1 FY '26.
    Show source
    And this also marks the entry of new reputed lenders like Bank of America, Standard Chartered Bank, and India Infradebt Limited in our loan book.
  • The 2.52 Omega Urja project has been approved by the state of Madhya Pradesh in a regulatory forum, and SJVN has received consent; the PPA is expected to be signed in July or August, with all state and SJVN approvals in place.
    Show source
    So, this should be signed, if not in July, maybe in August, this 2.52.
  • The NTPC Alpha Renewables 3.32 project is pending with NTPC.
    Show source
    That is something which is pending as of now with NTPC.
  • The 2.52 SJVN project and the 3.25 SECI hybrid project are at an advanced stage; the SECI project has gone to the regulator.
    Show source
    That is again at an advanced stage.
  • The company is discussing with NVVN the signing of the NTPC 2.53 project because NVVN is considering buying it directly rather than through the pooled basis; the proposal's construct is being discussed and Acme Solar Holdings Limited will update after discussions conclude.
    Show source
    The NTPC 2.53, that is something we are discussing with NVVN in terms of the signing, because they are thinking of buying i t directly rather than selling it to the pooled basis.
  • Urja One and Platinum Urja One are at advanced stages with various states, including MP and Chhattisgarh, and Acme Solar Holdings Limited is positive it can conclude the pipeline in another 4 months.
    Show source
    So we are quite positive that we should be able to conclude this whole pipeline in another 4 months.
  • The company stores energy for the AP government through NHPC; NHPC supplies the energy, and Acme Solar Holdings Limited is required to maintain the service level agreement for availability and output based on energy provided during hours required by the AP government.
    Show source
    We are supposed to maintain the service level agreement of availability and output basis the energy provided by them during certain hours of the day as required by them.
  • The NTPC FDRE project is in discussion with various states, and is expected to get signed.
    Show source
    Then another one which is expected to get signed is the NTPC one.

Risks, rules and outside factors

Outside factors

  • The duty difference between the cell and the container is around 5% to 11%, and the cost increase is more or less made up by making in India.
    Show source
    But it is around 5% to 11%.

Rules and policy

  • The Ministry of Power announced a second tranche of the VGF scheme with a total financial outlay of around INR5,400 crores; VGF of around 18 lakh per megawatt hour will be provided to enable development of 30 gigawatt hour of BESS capacity.
    Show source
    VGF around 18 lakh per megawatt hour will be provided under this scheme which will enable development of 30 gigawatt hour of BESS capacity.
  • The Ministry of Power extended the 100% waiver on the ISTS for co-located BESS projects commissioned by June 2028 and pumped hydro storage projects where construction will be awarded before the same date.
    Show source
    On the regulatory front, MOP again extended the 100% waiver on the ISTS for co- Page 3 of 24 ACME Solar Holdings Limited July 28, 2025 located BESS projects commissioned by June 2028 and pumped hydro storage projects where construction will be awarded before the same date.
  • The government reduced VGF because it believes lower VGF will still enable economical rates, and the reduced VGF will lead to a lower tariff for state governments and encourage battery link project development in sync with the ISTS waiver given by the government till 2028.
    Show source
    And we think it's a very good move to at least have this much VGF, because it will lead to a lower tariff for the state government and it will encourage the development of the -- and it is also in sync with the ISTS waiver given by the government till 2028, because the emphasis is on stabilizing the grid, meeting the peak power demand.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Meet Katrodiya: Yes, sir.

    Answer, nikhil dhingra

    Nikhil Dhingra: Looking at the tariff reduction which has happened across the projects. Very competitive rates have come. So government believes that reduced VGF will also be fine in terms of getting the economical rates. So that is why, that is the thought behind reducing the VGF. And we think it's a very good move to at least have this much VGF, because it will lead to a lower tariff for the state government and it will encourage the development of the -- and it is also in sync with the ISTS waiver given by the government till 2028, because the emphasis is on stabilizing the grid, meeting the peak power demand. And this VGF will keep for the whole Page 5 of 24 ACME Solar Holdings Limited July 28, 2025 -- all the state governments interested to keep continuing the momentum they had built on doing these battery link projects. In terms of the projects, we have won, right.

    Answer, nikhil dhingra

    Nikhil Dhingra: We really need to do is the battery installation -- battery system installation. And that is typically done at a capex of $100 per kilowatt hour. So it is much less than that. And the IRR in this is of course lesser than the FDRE, but the risk is also much lesser than the FDRE. So they are in high- teens. So we don't do a project which is less than a 16% return. So the returns are much above that for this project.

  2. Question

    Meet Katrodiya: Yes.

    Answer, nikhil dhingra

    Nikhil Dhingra: So the -- I think the duty difference is more or less made up by the cost increase which we make up by making in India. But it is around 5% to 11%. That is the duty difference in terms of… Manoj Upadhyay: Cell and the… Nikhil Dhingra: Between the cell and the container.

  3. Question

    Meet Katrodiya: Okay.

    Answer, nikhil dhingra

    So we see that this growth will be very high. It will be much higher than the last year is what we feel.

  4. Question

    Meet Katrodiya: Yes, yes.

    Answer, nikhil dhingra

    Nikhil Dhingra: 2.4% you can save, right? Provided the quality of the integrator is as good as what is available in China. And the warranty, as I said, there will be a big lacuna in the warranty. Because if you are getting the containerized solution from India, then the containerized vendor will need to warranty the whole 15 years of performance. So, that's a big risk. For 2.5 percentage of cost improvement, are you willing to sacrifice a large FDRE project revenue? We are currently not in favor of that.

  5. Question

    But what about the energy, the energy that NHPC is supplying that part will be received by NHPC?

    Answer, nikhil dhingra

    Nikhil Dhingra: Correct. So that's an input for us. We are only storing the energy for the AP government through NHPC. So the energy will be supplied by them at the hours. We are supposed to maintain the service level agreement of availability and output basis the energy provided by them during certain hours of the day as required by them.

  6. Question

    Samarth Khandelwal: Understood. Understood. Well, second question is on how is an FDRE project different from a solar plus storage or a solar wind plus storage project?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, FDRE project is essentially same as solar wind and storage project. The difference in FDRE is it could stretch to 24-hour project also. Technically FDRE stands for firm and dispatchable renewable energy. If you implement this definition in the strictest sense of the word you could - - you should supply it for longer duration of power. Typically a solar plus storage tender can have a peak for 2 hours, 4 hours and beyond that you will need to put some bit of wind if you want to extend at a competitive price. So the FDRE typically can have longer hours of storage, but a solar plus storage may have a shorter hours of storage extending up to 4 hours. So that could be one difference.

    Answer, nikhil dhingra

    They have been interchangeably used in all the tenders in terms of the FDRE and solar plus storage, but the tenders we have mostly these all FDREs are having 4 hours of storage typically. In solar plus storage, we have lower hours of storage let's say 2 hours and in some cases 1 hour also.

  7. Question

    Samarth Khandelwal: Okay, perfect. Because FDRE is slightly higher than the plain solar plus storage.

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, yes. Yes, if you look at the FDRE of longer hours, you will find tariffs of up to 4.98 which have been signed by discoms. So because they had longer hours of storage, they have supplied during even the night time also. So that decides the tariff. Page 9 of 24 ACME Solar Holdings Limited July 28, 2025 Moderator: Thank you.

    Answer, nikhil dhingra

    Nikhil Dhingra: So all of it will cater to the contracted capacity only. We are -- what we are doing here is, we are trying and early commission the BESS part of the contracted portfolio. So that -- this 3.1 will be, will basically be catering to the 50% of the overall demand for this 2.3 gigawatt of portfolio. And what we are doing, trying to do is operationalize the BESS part of the system and we have taken, we have taken approvals for that from all the counterparties and others. So before the COD of the whole FDRE component, we are trying to get the battery components operationalized, which will help us improve the realizations pre-COD due to the merchant prices in terms of the peak power. So that's, that's what we are doing and this is all for the, all for the contracted capacity only.

  8. Question

    Nikhil Abhyankar: Okay.

    Answer, nikhil dhingra

    Nikhil Dhingra: So it will be -- so it will be around 4.5, 5 gigawatt hour. We are closing more orders. So in the next month or so, we are trying to close 2 gigawatt hour more of orders that will complete the overall battery requirement.

    Answer, manoj upadhyay

    Manoj Upadhyay: So roughly 2 gigawatt means 2 gigawatt multiplied by 2.5 hour. So you can, roughly the number will be 5 gigawatt hour. So right now we have ordered 5.6 gigawatt hour. So we have ordered 50%, another 56 -- 55% we will be ordering soon.

  9. Question

    Nikhil Abhyankar: Understood.

    Answer, manoj upadhyay

    Manoj Upadhyay: So our plan is that we order -- we get first 3 gigawatt hour this year to install it. Then we get another 3, 3.5 gigawatt hour January to June install it and from June to December again 3 gigawatt hour. So totally taking up to 10 gigawatt hour, that what we have shown in total requirement. Page 10 of 24 ACME Solar Holdings Limited July 28, 2025 Nikhil Abhyankar: Sure.

  10. Question

    Understood, sir. And sir, just a final question on the capex. If you can quantify the capex required for, say, 2.2 gigawatt of under construction capacity that we have?

    Answer, nikhil dhingra

    Nikhil Dhingra: Right, right. So capex wise, FDRE is closer to around INR 11 crores per megawatt and so -- and the hybrid is around INR 8 crores per megawatt. So that is typically for a -- for this year we have guided around INR12,000 crores to INR 14,000 crores of capex. And of course for the next year also similar sort of number. Of course there is a downward trend on the capex given the battery prices fall. So that is the sort of capex number. We have already placed purchase orders of close to INR7,000 crores in this year and we, as we said that we want to order the battery and we want to order the rest of the equipment very soon.

Show 10 more questions
  1. Question

    Nikhil Abhyankar: Sure. And how much was done in Q1, capex?

    Answer, nikhil dhingra

    Nikhil Dhingra: Capex actually done is around INR800-odd crores, but the orders closed is around INR7,000 crores.

  2. Question

    Dhruv Muchhal: Got it. And so you will be early commissioning these projects and effectively probably selling in the merchant market for some time until probably the PPA comes up. So based on your calculation probably on an hour-wise or minute-wise basis, you see that this project will give you the early commissioning gives you that benefit. I mean, gives you superior returns. Is that, I mean, that back-end work we have already done and that makes sense. I mean, across seasons, across time portfolio. So, for example, generally what we see is in winter the demand falls and merchant prices fall. So it is adjusting for all those factors.

    Answer, manoj upadhyay

    Manoj Upadhyay: Yes, yes, we have done it. In fact, what happens, time shifts. Sometimes in the summer, what happens, it is evening and it goes to late night. In the winter it goes in the morning hours. So only the timing shifts. Page 11 of 24 ACME Solar Holdings Limited July 28, 2025 Nikhil Dhingra: Typically, what we are seeing is around 9 hours is the peak tariff on a 1 hour average basis for the last 12 months and 8.78 is the average for 2 hours in the last 12 months.

  3. Question

    Dhruv Muchhal: Got it. Makes sense. Got it. So, second is, on the recent, we are seeing standalone battery projects and you are also participating them. Is the commissioning timeline, shorter there? Typically we have 24 months. Is it shorter in standalone battery projects?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, yes, yes, yes. It is 18 months in... It depends on the size of the project but the project we have won is 18 months and the onus on giving the land and the evacuation lies on the customer. So, if there is a delay on their side, this extends accordingly.

  4. Question

    Dhruv Muchhal: The last question is on a portfolio basis what would be interest cost now be? And given the interest rate scenario, do you see a further scope for this to change in the next 2-3 quarters?

    Answer, rajat singh

    Rajat Singh: Yes. So, our interest cost on a portfolio basis especially for operating projects is close to 8.75% as we speak. But, you know, we are in the process of refinancing a lot of this debt and also there is an interest cost reduction when the COD happens. So, I think during this financial year as we end this financial year we are expecting much significant reduction in the interest cost. One is due to reset of interest on COD as well as yearly reset and also refinancing of these loans. It is very difficult to say at what but because RBI has reduced 50 basis points it will not be unfair to assume that kind of reduction going forward at least over next 6 to 8 months but I think there will be significant reduction in interest cost, yes.

  5. Question

    Dhruv Muchhal: So, this 8.75 is on your constructed portfolio where probably you have reasonably optimized on your debt. So, this is a good representation in terms of what an operational portfolio can give you in terms of debt cost.

    Answer, manoj upadhyay

    Manoj Upadhyay: So, what has happened is actually to clarify, we have the last 2-3 projects which technically they got commissioned in the last 2-3 months. We still consider under construction we believe that interest rate in those projects will also go down.

  6. Question

    Dhruv Muchhal: And also I wanted to understand the question was also to understand the RBI rate reduction benefit has already flown down to our numbers in terms of refinancing or generally some loans have six months, 1 year, that kind of rescheduling? So is that yet to play out?

    Answer, nikhil dhingra

    Nikhil Dhingra: So that has not yet flown down to our numbers because some of our projects have annual reset and those reset have not yet arrived and we have not really refinanced. So, this ISTS project, only one out of the four projects have been refinanced yet. So, three projects are yet to be refinanced. So, they are still running at more than 9% interest cost. We do have sanctions for let's say 1% lower than that but we have not activated them because we don't need the extra debt which is being provided by these because we have sufficient liquidity of more than 3,000 crores. So, we are timing our refinancing as per the requirement because then the lenders push us for taking early disbursement which we don't want. So, there is significant benefit yet to be coming because we have not refinanced yet.

  7. Question

    Ketan Jain: Thank you. So, my first question is on the capacity addition. We've commissioned around 350 megawatt in the first quarter and I think 100 megawatt is near completion. What more can we commission in this year, in FY26, which projects?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, what we are targeting to do other than this 100 megawatt is basically the battery portion of the FDRE plants and also some of the solar projects also but the battery which is our focus area because we are putting up battery at the already charged substations. We have more than 2 gigawatt of centrally connected projects where we are putting battery of our FDRE plants. So, you can say all the 3.1 gigawatt we've ordered. Our target is to commission if not 3.1 gigawatt at least 2.5 gigawatt by this financial year and we will be doing it in phases. So, definitely some Page 13 of 24 ACME Solar Holdings Limited July 28, 2025 component will be charged before the calendar year and some portion would be charged before March. So, that is our target basically from a revenue perspective. In terms of the capex perspective, the capex for the solar, wind all would be done but the charging of those will be done in sync with the commissioning timelines of the CTU substations because those are being done at the new substations.

    Answer, nikhil dhingra

    They are not being done at the existing charged substations. So, that is how we are planning. Management: So just to conclude, we would be adding 450 megawatt of capacity and around 2.5 gigawatt hours of battery component of the FDRE projects which we can generate revenue from.

  8. Question

    Ketan Jain: Sir, also I wanted to ask you on status on PPA for 2 -3 projects, Sigma Urja, Omega Urja which are these two other solar projects and one alpha renewables which is a hybrid project. What is the reason for delay in signing of these PPA’s. Are we seeing any v isibility in the near term?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, I will give you project by project status on Omega Urja first. So, Omega Urja, the state of Madhya Pradesh has already got it approved in a regulatory forum. So, the consent has also been received by SJVN. So, I think because of the administrative things, it is expected to be signed this month because all sorts of approvals are there from state and SJVN. So, this should be signed, if not in July, maybe in August, this 2.52. There are no hurdles to it as far as we are aware. Then in terms of the 3 point – the NTPC Alpha Renewables 3.32 one.

    Answer, nikhil dhingra

    That is something which is pending as of now with NTPC. But I can tell you which ones we know are at the advanced stage. So, this 2.52 SJVN is at the advanced stage. Then you have the hybrid 3.25 of SECI. That is again at an advanced stage. This is again gone to the regulator. It is in two states.

    Answer, nikhil dhingra

    One is in Bihar, and another is in UP. So this again should be signed in July. Sorry, August, Renewtech. As per our information, of course, SECI is leading it. But this is what we are aware of. Then another one which is expected to get signed is the NTPC one. Again, that is in discussion with in various states, the FDRE one.

    Answer, nikhil dhingra

    The NTPC 2.53, that is something we are discussing with NVVN in terms of the signing, because they are thinking of buying i t directly rather than selling it to the pooled basis. So that proposal we are discussing with NVVN. They are trying to change the construct of that. We are discussing with them, and we will update as soon as the discussion concludes. So that's there. Other than that, the Urja One and Platinum Urja One, they are also in advanced stages with various states, including MP and Chhattisgarh. So we are quite positive that we should be able to conclude this whole pipeline in another 4 months.

  9. Question

    Ketan Jain: Any one particular project which you can say that this project we are targeting, like full FDRE commissioning, maybe next year, maybe in a couple of years?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, so basically, the whole SJVN project will be charged. The NHPC will be charged. So there are all of these projects, and even the SECI 150 megawatt, which is already signed, that will be charged. So all these projects will be charged next year. The substation timelines are basically staggered throughout the year. So all these projects will be charged next year. How it will be done is, the battery will be charged first, and the solar and the solar component, because we are primarily doing solar, will be charged as per the substation timeline.

    Answer, nikhil dhingra

    So all of them will be charged, whatever PPAs we have signed. See, all the PPAs we have signed got signed from, you can say, till December '24. All these FDRE projects got signed before December '24. So the timeline of them is December '26. So we have not signed in this calendar year any FDRE. All the tenders which we have signed are very recent. One previously we'd signed.

  10. Question

    Vikram Datwani: Got it. So that would actually answer my follow-up as well as to how we can play the merchant market in the early commissioning of the NHPC battery project. Okay, that answers my questions.

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. So see, capex is financed 75-25 in terms of debt and equity for us. And typically what we have seen is post-capex, we get revenue within 8 to 9 months of that capex, weighted average capex being done. So in terms of this financial year, our capex target is close to, let's say, INR 14,000 crores, but it may -- but the weighted average, so the debt for that would be around INR 11,500 crores. But that debt will come towards the end of the year because in this quarter, like we said, we did only INR 800 crores of capex. So it is completely back-ended. So the weighted average debt will be much lower than, the addition of the debt will be much lower than the capex.

    Answer, nikhil dhingra

    Because typically we spend the money just one month before the dispatch of the product. So the whole designing period, the whole, you can say, the ordering period, the capex is deferred. So from the delivery to the operationalization, that is our efficiency comes wherein we try and operationalize the plant immediately post the key equipment arrival at the site. So the whole site is ready before the key equipments come. So from the capex to the revenue, typically, as I said, our effort is to get it done in six months, not more than that. So that's how -- so the debt will not be addition, weighted average will be much lower than INR11,500 crores. It will be, I can't say the number right now, but it will be much lower than that.

    Answer, rajat singh

    Rajat Kumar Singh: And also because, as Nikhil explained earlier, the debt will be largely coming in terms of LC payments, which will happen towards the fag end of the delivery when the -- just before the commissioning happens. So the impact on the overall debt and the interest cost will be lower. And also during the construction phase, the IDC has all capitalized, right? So only when the revenue starts increasing, the interest cost hits the P&L. Nikhil Dhingra: And one more thing, during LC phase, we are trying to take buyer's credit also.

    Answer, nikhil dhingra

    Nikhil Dhingra: NHPC tender. So NHPC tender is not a large revenue project. Of course, it will generate, at its peak, around INR70 crores of revenue. So it is… Raman KV: Okay.

    Answer, nikhil dhingra

    Nikhil Dhingra: Annual revenue. And it is -- of course, we have 18 months from, let's say, June. So we have that much timeline, but we are all for early commissioning of this plant. And we are working with the Andhra Pradesh Government to get their readiness with us. Then we can easily commission it. Once they give us the go-ahead, we can easily commission it in six months. So that's much level of preparedness we have.

    Answer, nikhil dhingra

    So we are waiting for them to give us the notice to proceed. This is their readiness. Because we don't want our equipment to come and they are still sorting out their bit of work. That is what we don't want to do, because...

    Answer, nikhil dhingra

    Nikhil Dhingra: It will be slightly higher. Because -- it will be actually quite higher, sorry. Because in an NHPC tender, you are constrained by the bid you made. And it's a 15-year long contract. So there is a levelized lower tariff. But as we mentioned in replies to one of the questions, the unit rate for a peak power in India, because you are free to sell in whatever hour you want to sell. So you choose the highest paying hour.

    Answer, nikhil dhingra

    And there the tariffs are around INR9. And the charging cost is much lower for the battery, as you know, because you can see the tariffs which are Page 21 of 24 ACME Solar Holdings Limited July 28, 2025 prevailing for charging cost. So there will be a much higher revenue purely from -- much higher than this number of NHPC. And the quantum is also much, much higher. Like we said, we are going to charge 2500- megawatt hour of battery, whereas this project only has… Manoj Upadhyay: 550MWh Nikhil Dhingra: 550MWh of battery.

    Answer, manoj upadhyay

    So it's 5 times larger commissioning. And the revenue and profits are also substantially higher.

    Answer, nikhil dhingra

    Nikhil Dhingra: So we don't want to -- yes. Yes. Yes. Yes. We don’t want to give a guidance on that, since it's a merchant-based project. So it's all part of our upside planning. It's something we have preponed, right?

    Answer, nikhil dhingra

    Nikhil Dhingra: So see, that is also a function of what we just spoke about in the previous reply. So like we are trying to commission these battery projects, which are the components of the FDRE. Then we are commissioning the FDRE projects. So I think most of the researc h analysts have done the math. So I think depending on these commissionings, we will be meeting those revenue targets, because our PPA is tied up, right? Our costs have some upsides. So I think that is what you can expect.

    Answer, manoj upadhyay

    Manoj Upadhyay: Thank you all for asking a very, very relevant question. And thank you to the entire team that they have delivered a very good performance. As you are all aware that ACME is known for innovation and technology, so I wanted to brief you, and I saw some of the questions also you all have touched on. I would like to share with you that last week we finished five years of continuous testing of the FDRE, which is the battery, solar and the grid together. And we were able to test the battery degradation, and I'm very happy to share with you they were very well within the limit, what we have thought of, of five years of continuous testing. Page 22 of 24 ACME Solar Holdings Limited July 28, 2025 We were also able to test the power electronics reliability because they had to interact with the grid and we collected -- we selected the very poor grid to interact, because normally our grid in the FDRE is connected to 400 kV or 220 kV. They are very, very stable grid, but we wanted to abuse this -- abuse the testing, so we connected to 33 kV and tested all the variation possible in this one, and I'm proud to share with you that it worked very well for so many years.

Questions about this call

When was the Acme Solar Holdings Q1 FY26 earnings call transcript filed?
Acme Solar Holdings filed the transcript with the exchange on 1 Aug 2025. This page is built from that transcript.
What does this page list?
87 statements from the transcript across 10 topics, 64 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 20 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Acme Solar Holdings Q1 FY26 concall: Acme Solar Holdings Limited secured its first standalone battery energy storage projects of 550 MWh contracted with NHPC, and signed the PPA in one month · DalalOS