Garden Reach Shipbuilders & Engineers Q3 FY25 earnings call: Garden Reach Shipbuilders & Engineers Limited's order book stood at ₹23,877 crore as on 31st December and comprised 40 platforms from 10 projects

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

Order book stood at ₹23,877 crore as on 31st December and comprised 40 platforms from 10 projects. GRSE expects no major design changes from 17 Alpha to 17 Bravo and plans to bid for the P-17 Bravo project with confidence and reasonable aggression, drawing on its experience building the P-17. First ship had reached almost 90% progress, its second almost 65%, and its third about 50%. Revenue from operations grew 38% over the corresponding quarter, from ₹923 crore to ₹1,271 crore, in Q3 FY25. The government target is to increase its share of the global commercial fleet to 20% by 2047.

The numbers management gave

Results

  • PAT grew 11% from ₹88 crore to ₹98 crore, and operating profit increased from ₹37 crore to ₹62 crore, in Q3 FY25.
    Show source
    The PAT has gone up by 11% from ₹88 crore to ₹98 crore, and the operating profit has gone up from ₹37 crore to ₹62 crore.
  • Operating profit margin increased from 4.03% to 4.85% in Q3 FY25.
    Show source
    That means operating profit margin has gone up from 4.03% to 4.85%.
  • Earnings per share increased from ₹7.70 to ₹8.57 in Q3 FY25.
    Show source
    Earnings per share, again, showing a rise from ₹7.70 to ₹8.57.
  • PAT for the third quarter was ₹98 crores, which was 4%.
    Show source
    Ramesh Bhojwani: And the PAT was ₹98 crores, which was 4%.
  • Revenue from operations grew 38% over the corresponding quarter, from ₹923 crore to ₹1,271 crore, in Q3 FY25; revenue from operations was ₹1,271 crore, PAT was ₹98 crore, and EBITDA was ₹147 crore in the third quarter.
    Show source
    Our revenue from operations registered a 38% growth over the last corresponding quarter from ₹923 crore to ₹1,271 crore.
  • Revenue from operations was ₹3,434 crore, EBITDA was ₹421 crore, and PAT was ₹283 crore in 9 months.
    Show source
    In 9 months, revenue from operations was ₹3,434 crore, and the EBITDA was ₹421 crore, and the PAT was ₹283 crore.
Show 4 more statements

Results

  • Margins on the P-17 Alpha project are good.
    Show source
    If the P-17 Alpha project, our margins are good.
  • Revenue from operations grew 38% over the corresponding quarter, from ₹923 crore to ₹1,271 crore, in Q3 FY25. Replaced by a later filing.

Money and capital

  • GRSE's cash and bank balance as at 31st December, 2024 was ₹3,214 crore.
    Show source
    Dash: Cash and bank balance, this is as on 31st December, 2024 is ₹3,214 crore.
  • GRSE's owned fund was ₹577 crore as of 31st December, 2024.
    Show source
    Out of that, our owned fund is ₹577 crore.

What it expects ahead

What management expects

  • GRSE expects no major design changes from 17 Alpha to 17 Bravo and plans to bid for the P-17 Bravo project with confidence and reasonable aggression, drawing on its experience building the P-17.
    Show source
    And our confidence is that having built the P-17, and since we do not expect any major design changes over 17 Alpha to 17 Bravo, so we will be bidding with that kind of confidence and reasonable aggression.
  • The company expects to maintain a CAGR between 20% to 25% over a 5-year period.
    Show source
    But we'll be able to maintain a CAGR between 20% to 25% over a 5-year period.
  • The company expects to maintain PAT margin above 8%; it was 7-point something in this particular quarter, but the company expects to correct that by the end of the financial year.
    Show source
    I have been consistent in my views on this, that we'll be able to maintain PAT margin above 8%.
  • Revenue recognition from the Next-Generation Corvette is expected to commence from 2027, when GRSE's dip is expected to start.
    Show source
    And the revenue recognition from that will commence from 2027.
  • GRSE is taking a calibrated approach to export opportunities, has invested in revitalizing one facility, and is looking for a twofold increase in exports within one year and at least a fourfold increase from the current value in the next four years.
    Show source
    So, I'll say on a conservative basis, we'll be looking at a twofold increase within one year, and at least a fourfold increase from the current value in the next four years.
  • The Next-Generation Corvette bid is expected to be opened within three months, around April, and contract signing is expected to take around six months after the price bid opens; all four bidders have cleared the technical bids.
    Show source
    The Next-Generation Corvettes, the bid likely to be opened, conservative, within three months.
Show 19 more statements

What management expects

  • The Next-Generation Destroyer is still in liquid form.
    Show source
    NGD, the Next-Generation Destroyer, is still in liquid form.
  • The P-17 Bravo RFP could come out by the end of calendar year 2025; from RFP to L1 determination could take around seven months to price bid opening, followed by six months for contract signing and two years for revenue recognition, which would start in 2029 if P-17 Bravo comes through. Replaced by a later filing.

Orders

  • Order book stood at ₹23,877 crore as on 31st December and comprised 40 platforms from 10 projects.
    Show source
    Our current order book, as on 31st December stands at ₹23,877 crore.
  • The Next-Generation Corvette has an AoN of ₹36,000 crore; the L1 shipyard is assessed to receive ₹25,000 crore to ₹30,000 crore, above the approximately ₹22,000 crore indicated by a calculation, and the L2 shipyard is expected to receive around ₹15,000 crore to ₹16,000 crore in a ratio of around 5:3.
    Show source
    But my assessment is that it could be well beyond that, which means it could be between ₹25,000 crore to ₹30,000 crore for the L1 shipyard.
  • The P-17 Bravo project has an AoN of around ₹70,000 crore, with each ship valued at around ₹10,000 crore; the L1 shipyard would get 4 ships and the L2 shipyard would get 3 ships.
    Show source
    So, the L1 shipyard would get 4 ships; and the L2 shipyard would get 3 ships.
  • The 18-ship NG-FPV project is likely to have an order value of around ₹3,000 crore and to go to a single shipyard.
    Show source
    Page 6 of 23 So here, the order value is likely to the tune of around ₹3,000 crore.
  • GRSE expects the 5-ship NGSVL (Survey Vessel Large) next-generation survey vessel project for the Indian Navy to have an order value of around ₹3,500 crore and go to a single shipyard.
    Show source
    We expect the order value to be around ₹3,500 crore.
  • GRSE does not expect the cost of a waterjet FAC ship, including the NG factor, to exceed ₹100 crore to ₹120 crore per ship; the project could be valued at around ₹3,500 crore.
    Show source
    We do not expect the cost of a waterjet FAC ship or even with the NG factor to go beyond ₹100 crore to ₹120 crore.
  • The 120 Fast Interceptor Craft project is valued at around ₹2,500 crore.
    Show source
    Then comes the 120 Fast Interceptor Craft around ₹2,500 crore.
  • The Navy will issue an RFP for 2 more Multi-Purpose Vessels, after 2 ships currently being constructed by Larsen & Toubro shipyard at Kattupalli; the project could be valued at ₹1,200 crore to ₹1,400 crore.
    Show source
    This could be to the tune of ₹1,200 crore to ₹1,400 crore.
  • Exports account for about 4% of GRSE’s order book as of the date of the call.
    Show source
    Right now, as on date, just about 4% of GRSE’s order book is coming from exports.
  • GRSE’s order book is ₹23,877 crore, of which about ₹970 crore is from exports.
    Show source
    Our total order book is ₹23,877 crore, and just about ₹970 odd crore is coming from exports.
  • Current order book is ₹23,000- odd crore and, unless it gets fresh orders, is expected to come down to around ₹22,000 crore something by end of this financial year; it is expected to last, including new projects signed, up to 2029.
    Show source
    See, our current order book, of course, is ₹23,000- odd crore, which hopefully will come down to around ₹22,000 crore something by end of this financial year unless we get some fresh orders.
  • The four bidders for the Next-Generation Corvette, the 8 in number project, are Goa Shipyard, Larsen & Toubro shipyard, Mazagon Dock and GRSE.
    Show source
    It is Goa Shipyard, Larsen & Toubro shipyard, Mazagon Dock and GRSE.
  • The ₹36,000 crore Next-Generation Corvette project cost could rise to ₹42,000 crore or ₹45,000 crore, and the conservative estimate is that the L1 shipyard could get ₹25,000 crore to ₹28,000 crore, mainly because of justifiable inflation in equipment costs.
    Show source
    So conservative estimate is that the L1 shipyard could get in the range of ₹25,000 crore to ₹28,000 crore, let us say.
  • GRSE's current order book, excluding the three projects and export platforms, will expire by 2029.
    Show source
    I'll answer the first question without considering these 3 projects or the export platforms that we are very confident of getting, keeping that aside, the current order book will expire by 2029.
  • For Garden Reach Shipbuilders & Engineers Limited's Next-Generation Corvette project, the RFP had been issued, bids submitted by four shipyards, and technical evaluation completed; the company expects the price bid to be opened in a couple of months.
    Show source
    The technical evaluation has been completed, and we expect the price bid to be opened in a couple of months.
  • At least three Coast Guard RFPs were converted to orders in the last financial year.
    Show source
    Coast Guard, at least 3 RFPs have been converted to orders in the last financial year.
  • For P-17 Bravo, GRSE expects the RFP by end of the current calendar year; if it comes by then, the L1 and L2 shipyards are expected to be known by mid of calendar year '26, with the L1 shipyard to get an order around ₹40,000 crore and the L2 shipyard an order of ₹30,000 crore. Replaced by a later filing.

What it is building and selling

Projects and capacity

  • First ship had reached almost 90% progress, its second almost 65%, and its third about 50%.
    Show source
    And just to give you an updated status, we have almost touched 90% progress on the first ship, almost 65% on the second ship, and about 50% on the third ship.
  • Survey Vessel Large project for the Indian Navy comprises 4 ships; two had been delivered and commissioned into the Navy.
    Show source
    Two ships have been already delivered, and they have been commissioned into the Navy.
  • The company intends to deliver two more ships in its Survey Vessel Large project during this calendar year, with the third expected by June and the fourth by July/August 2025.
    Show source
    Two more ships, Page 4 of 23 we intend delivery during this calendar year, which means the third ship, we expect to be delivered by June, and the fourth ship by July/August 2025.
  • The second ship in Garden Reach Shipbuilders & Engineers Limited's Survey Vessel Large project had reached around 85% physical progress, and the third around 72%.
    Show source
    The second ship has almost touched around 85% physical progress, and the third ship is around 72%.
  • First ship in the Anti-Submarine Shallow Water Craft project had undergone full power trials and was ready for delivery; the company was confident of delivering it by 15th of March this year.
    Show source
    We are confident of delivering this vessel by 15th of March this year.
  • 4-ship New-Generation Offshore Patrol Vessels project was on track, and its first 2 ships had reached almost 40% physical progress.
    Show source
    The first 2 ships, we almost touched 40% physical progress.
Show 21 more statements

Projects and capacity

  • The company intends to launch the first 2 ships of its New-Generation Offshore Patrol Vessels project during this calendar year; the project's delivery timelines extend to 2028-2029 for the last ship.
    Show source
    We intend launching of these ships during this calendar year.
  • GRSE has 3 fully usable shipyards in Kolkata and has hired some facility; its shipbuilding capacity was 20 ships last year and has increased to 24 ships already.
    Show source
    We have increased it to 24 ships already.
  • GRSE plans to increase its shipbuilding capacity to 28 ships by the end of calendar year 25, but says that capacity will remain inadequate to meet requirements and it cannot take on some offers.
    Show source
    With what we have by end of this year, that means the end of the calendar year 25, we'll be increasing to 28 ships.
  • The top 3 shipbuilders have capacity for 24 ships today.
    Show source
    So, let's say in the top 3, our capacity today is 24 ships.
  • GRSE's delivery schedule had not been exceeded as of the call, and the first delivery for the P-17 Alpha project is August 2025.
    Show source
    First delivery is August 2025.
  • The company expects to deliver the first P17 Alpha Project ship in the mid of the next calendar year and plans to deliver the last ship during the mid of the calendar year 2026.
    Show source
    Yes, we'll be able to deliver the ship ahead of the contracted time, which is the first ship is to be delivered by August this year; the second ship by February next year; and the third ship by August 2026.
  • The Anti-Submarine Shallow Water Craft project comprises 16 ships, with 8 being constructed by Garden Reach Shipbuilders & Engineers Limited and 8 by another PSU shipyard.
    Show source
    Coming to the ASW Shallow Water Craft project actually, this is a 16-ship project, 8 being undertaken by GRSE and 8 by Cochin Shipyard.
  • The company intends to complete its 8-ship Anti-Submarine Shallow Water Craft project by FY27.
    Show source
    Our contract delivery time line is by October, 2026.
  • First ship had successfully completed basin trials and was intended to go to sea for sea trials by end of this month.
    Show source
    Basin trials is the harbour trials, have been successfully completed.
  • The company intends to start production of the commercial platform for its German client; design activities were in progress.
    Show source
    We intend starting the production.
  • The company intends to commence production of the commercial platform for its German client by July this year.
    Show source
    We intend commencing production by July this year.
  • The company had commenced production of the Oceanographic Research Vessel and intends to carry out its keel-laying milestone by July this year.
    Show source
    And we intend doing the first milestone activity, that is the keel laying of the vessel by July this year, and is on track.
  • Preparatory activities for Garden Reach Shipbuilders & Engineers Limited's acoustic research vessel were in progress.
    Show source
    The acoustic research vessel, preparatory activities are in progress.
  • GRSE says it needs to expand beyond Kolkata because Kolkata has an inherent draft limitation, and it will look at a facility outside Kolkata to avoid matching construction to the tide and doing construction afloat.
    Show source
    It is with that intent that we'll be looking at facility outside Kolkata.
  • GRSE is upgrading its virtual reality lab, which it set up six years before and now considers obsolete.
    Show source
    So, we are upgrading that.

Demand and pricing

  • The government target is to increase its share of the global commercial fleet to 20% by 2047.
    Show source
    The stated target of the government is to increase this to 20% by 2047.

Segments

  • GRSE's Survey Vessel Large, Landing Craft Utility and Anti-Submarine Corvette projects each have more than 85% indigenization; for warship building, 100% of the hull, around 70% of auxiliary machinery and around 50% of weapons are indigenous, amounting to around 85% or more indigenous content overall.
    Show source
    All put together, the figure I mentioned, around 85% plus is indigenous content.
  • In a project cost, around 65% comes from equipment and sensors procured and around 20% from labour; around 70% to 75% of the labour is outsourced.
    Show source
    In the project cost, around 65% come from the equipment and sensors that we procure, and around 20% comes from the labour.

Deals and partners

  • The company had signed contracts for 6 ships of the 8-ship Multi-Purpose Vessel Project with its German client and will sign the contract for the balance 2 ships by 31st of March.
    Show source
    Contract for 6 ships have been already signed, and we will be signing the contract for the balance 2 ships by 31st of March.
  • The company was declared L1 for 2 Coastal Research Vessels for the Geological Survey of India, and contract negotiations were in progress; the company expects the contract to be signed by 31st March.
    Show source
    In addition, we have been declared L1 for another set of Research Vessels for the Geological Survey of India, 2 Coastal Research Vessels.
  • The company had a closed-door meeting with Rolls-Royce to further the 31 Waterjet FAC co-production project.
    Show source
    We had a closed-door meeting with Rolls-Royce to further this project.

Risks, rules and outside factors

Outside factors

  • The Indian Coast Guard's capital acquisition budget increased by about 26% in this year.
    Show source
    Just to put things into perspective, I was making notes, so somewhere I had written down, that Coast Guard budget for capital acquisition, they have increased, I think, by 26% or something in this year.

Rules and policy

  • The government has set aside a ₹25,000 crore corpus for the Maritime Development Fund and plans to provide assistance as equity or debt, with 49% investment from the government and the remaining 51% from industry, for shipbuilding projects or shipbuilding infrastructure.
    Show source
    What the government is planning is to provide assistance in terms of either equity or debt with 49% investment from the government.
  • A shipowner who breaks a ship within India can receive a credit equal to 40% of its scrap value toward shipbuilding in India, as financial assistance; the government offers credit equal to 40% of a ship's scrap value when a ship is broken in India, which can be used as direct government assistance if a ship is built in India.
    Show source
    40% of the scrap value of the ship broken would be credited into my shipbuilding.
  • The government offers credit equal to 40% of a ship's scrap value when a ship is broken in India, which can be used as direct government assistance if a ship is built in India. Replaced by a later filing.

Everything else said on the call

People and governance

  • GRSE has about 2,000 permanent manpower, including around 520 officers.
    Show source
    It's just about 2,000 people.

Other

  • The company was rated Excellent for two consecutive years, including '23 and '24, and attained 96.5 out of a score of 100.
    Show source
    And out of a score of 100, we have attained 96.5.
  • The Indian coastline was measured at 7,516 kilo meters and, after a recent survey, is around 11,000 kilo meters.
    Show source
    But after a recent survey, you can check it up, you can Google it, it is around 11,000 kilo meters.
  • GRSE has around 6,000 people working on its premises on an average per day.
    Show source
    We have around 6,000 people working in our premises on an average per day.
  • GRSE makes provision for liquidation damages as per Ind AS 115 only when it exceeds the delivery schedule.
    Show source
    And the provision is made only when we'll exceed the delivery schedule.
  • The speaker said Garden Reach Shipbuilders & Engineers Limited's job has virtually doubled. Replaced by a later filing.
    Show source
    Ramesh Bhojwani: Our job has virtually doubled.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

This transcript does not separate questions and answers, so they are not listed here.

Questions about this call

When was the Garden Reach Shipbuilders & Engineers Q3 FY25 earnings call transcript filed?
Garden Reach Shipbuilders & Engineers filed the transcript with the exchange on 20 Feb 2025. This page is built from that transcript.
What does this page list?
72 statements from the transcript across 12 topics, 59 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
No. This transcript does not separate the questions from the answers, so they are not listed. The statements by topic still cover what management said.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
Garden Reach Shipbuilders & Engineers Q3 FY25 concall: Garden Reach Shipbuilders & Engineers Limited's order book stood at ₹23,877 crore as on 31st December and comprised 40 platforms from 10 projects · DalalOS