Bid pipeline was between 1.5 to 2 gigawatts, over and above its existing order book. The company expects growth of 60% to 70% over what it did last year, with growth possibly a little higher, and is planning for that growth because it has sufficient order book to execute. The company said its IPP portfolio was already more than 1.2 gigawatts in hand and that it would slowly build IPP and try to complete what it already had on the plate before moving on to IPP. The company had done Rs. 711 crores till half year, almost 75% of what it did in the whole last year. The company said its debt to equity would never go beyond 2:1 and would be between 1.5:1, even with full-fledged expansion CAPEX.

The numbers management gave

Results

  • The company had done Rs. 711 crores till half year, almost 75% of what it did in the whole last year.
    Show source
    Salim Yahoo: See, I don't know what you have seen, till half year we have already done Rs. 711 crores, which is almost 75% of what we have done in the whole last year.
  • The company said EBITDA margins on its GUVNL projects in IPP would be around 85% to 90%, because after setting up the plant there is no other cost apart from nominal O&M cost.
    Show source
    So, if you look at my GUVNL projects, my EBITDA margin in IPP would be around 85 % to 90%.
  • The company said its blended EBITDA would be around 33% to 37% and that increasing the IPP mix would improve its PAT margin and EBITDA margin.
    Show source
    So, overall if I see that at present my blended EBITDA would be around 33 % to 37%.
  • The company said that in the prior year IPP revenue was around 13% to 14% and CPP revenue was 86%.
    Show source
    So, at present, if you see last year, it was around 13% to 14% of IPP revenue and rest all 86% was CPP revenue.
  • The company said its net cash accruals improved and receivables and working capital cycle improved in the first half of FY25, with approximately Rs. 59 crores positive cash flow compared with around Rs. 57 crores negative cash flow in March.
    Show source
    Now we have 60 , approximately Rs. 59 crores as a positive cash flow, which was around Rs. 57 crores in March negative cash flow .
  • Using trackers would increase CUF by between 3% to 4%.
    Show source
    Salim Yahoo: If we do tracker and all, there will be increase in percentage of between 3% to 4%.
Show 5 more statements

Results

  • In H1, IPP contributed 13% to 14% and CPP contributed 86% to 87%; KPI Green Energy does not expect a drastic change in the IPP and CPP mix through the full year, but expects changes in coming years.
    Show source
    Salim Yahoo: In H1 I can tell you that 13% to 14% was the contribution of IPP and rest all 86% to 87% was CPP.
  • The group has already achieved PAT of 365 cr; KPI Green Energy's aim is for every Company to reach that level as fast as possible.
    Show source
    So, similarly you can say that 365 cr for the group level , already PAT is achieved.

Money and capital

  • The company said its debt to equity would never go beyond 2:1 and would be between 1.5:1, even with full-fledged expansion CAPEX.
    Show source
    But one thing I can assure you, that our debt to equity will never go beyond 2:1.
  • The company said its financials showed land value of approximately Rs. 100 odd crores, while overall pricing would be around Rs. 1,000 crores.
    Show source
    But overall the pricing would be around Rs. 1,000 crores, I can say.
  • The company said it had no cost for lease land other than the lease it had to pay.
    Show source
    So, there is no cost for me for the lease land other than the lease that I have to pay for the land.

What it expects ahead

What management expects

  • The company expects growth of 60% to 70% over what it did last year, with growth possibly a little higher, and is planning for that growth because it has sufficient order book to execute.
    Show source
    So, we expect that the growth will be in the range of 60% to 70% growth of what we have done last year.
  • The company said its H1 margin would be a little higher compared to the overall margin and that it would be able to maintain a PAT margin of 16% to 18%.
    Show source
    So, H1 margin will be a little bit higher compared to the overall margin, but we will be able to maintain our margin of 16% to 18% between that on the PAT level.
  • The company said that after completing its entire GUVNL order, its PAT margin, then around 16% to 18%, might rise to 20% to 22% if it increased IPP mix in total revenue.
    Show source
    So, if I complete my entire order of GUVNL, after that our PAT margin, which is around 16% to 18%, might go up to 20% to 22%, if I increase my IPP mix in the total revenue.
  • Net realization going forward would be around Rs. 4 to Rs.5, as its IPP in GUVNL is a bigger scale; it currently has 177 to 180 megawatts in IPP for C&I customers, and GUVNL will be adding approximately one gigawatt more.
    Show source
    Salim Yahoo: See, net realization going forward would be around Rs. 4 to Rs.5 because my IPP in GUVNL is a bigger scale.
  • The company expects its operating margin to be in the range of 32% to 33%, as in full year FY24; operating margins are higher in the first half when milestone billing results in lower cost of goods sold and raw material requirements.
    Show source
    So, from that point of view, we will have a higher operating margin, but we will be able to maintain what was earlier also, or you can say the full year FY24, what was the margin, this will be in the range of 32% to 33% only.
  • When KPI Green Energy completes its entire IPP order book, around 80% of IPP revenue would come from government through a GUVNL project and around 20% from C&I customers.
    Show source
    So, on the IPP side, you can say that 80% odd would come from the revenue from government, that is a GUVNL project, and 20% odd would come from the revenue from C&I customers, which we already have signed and some of them will get signed.
Show 6 more statements

What management expects

  • The company expects revenue from its CPP side to be around 50-50 between tender-based projects such as MAHAGENCO and projects with players such as Aditya Birla Group or Ayana.
    Show source
    So, altogether I can say we might have a 50%-50% on the CPP side.
  • Once KPI Green Energy completes 1.2 gigawatt of IPP orders, IPP revenue will be more than around 30%.
    Show source
    Page 21 of 25 KPI Green Energy Limited November 11, 2024 Salim Yahoo: Once I complete is 1.2 gigawatt of IPP orders, then the IPP percentage will be in the revenue will be more than around 30%.
  • The company wants to keep debt equity minimal of 2:1, not beyond that, and will cautiously decide which orders to bid for after 1 or 1.5 years based on the future outlook and its ability to take leverage on the balance sheet and P&L.
    Show source
    As I told earlier also, we want to keep debt equity minimal of 2:1, not beyond that.
  • The company said its margins depended on the mix and that it would be able to maintain them. Replaced by a later filing.
    Show source
    But we will be able to maintain the margins.

Orders

  • Bid pipeline was between 1.5 to 2 gigawatts, over and above its existing order book.
    Show source
    Salim Yahoo: The pipeline that we are looking at present is between 1.5 to 2 gigawatts.
  • The company had a CPP order book of 1.1 gigawatt, with an average completion timeline by September 25; 50% of the order book would be executed this year and 50% would flow down to next year, and the company said it would complete it before September on average.
    Show source
    Salim Yahoo: If you see this, 1.1 gigawatt is my CPP order book.

What it is building and selling

Projects and capacity

  • The company said its IPP portfolio was already more than 1.2 gigawatts in hand and that it would slowly build IPP and try to complete what it already had on the plate before moving on to IPP.
    Show source
    Salim Yahoo: Mostly CPP, because IPP we already have more than 1.2 gigawatts in hand.
  • The company had 3000 plus acre of land in FY25 Quarter 2; around 500 to 600 acres was own land and the rest was lease land under 27 to 28 year leases with farmers.
    Show source
    Salim Yahoo: So, if you see that, in FY25 Quarter 2, what we have mentioned that in our presentation also that we have 3000 plus acre of land.
  • The company expects to complete the CPP segment by September ‘25 and the entire IPP order in phases by mid of FY27.
    Show source
    But the entire final completion of the entire IPP order would happen by mid of FY27.
  • The company has 2.3 kind of giga order of evacuation available with it.
    Show source
    So, if you look at we have 2.3 kind of giga order of evacuation also available with us.
  • The company is planning to complete its entire 1.2 gigawatt within the next 1 to 1.5 years.
    Show source
    Whereas the milestones are concerned, milestone as I told you, we are planning to complete this entire 1.2 gigawatt within next 1 to 1.5 years.
  • The company has set up a 10 megawatt plant in the subsidiary absorbed from its promoter and is setting up a few more plants there.
    Show source
    So, we have already started, we have set up a small plant of 10 megawatt and we are already setting up a few more plants over there in that subsidiary.
Show 3 more statements

Segments

  • The company has not entered battery storage and has no intention at present to enter it; it will consider the sector, with any eventual decision depending on the board's assessment of the benefits and cons.
    Show source
    Salim Yahoo: No. At present, we have not entered or we are not having any intention for entering into battery storage.
  • The company is already doing hybrid plants, which it describes as a natural RTC kind of thing, but not totally RTC.
    Show source
    But nevertheless, we are doing hybrid, so which you can say a natural RTC kind of a thing, not totally RTC, but hybrid plants we are already doing.
  • The company said that IPP requires financial closure and consideration of factors on the debt and equity sides. Replaced by a later filing.
    Show source
    Because IPP, as you are aware, there needs to be a financial closure.

Everything else said on the call

Group structure

  • The subsidiary absorbed from KPI Green Energy Limited’s promoter had evacuation approval for more than 100 megawatt and a land bank.
    Show source
    Salim Yahoo: Yes, so that subsidiary was taken with an intention because that subsidiary has an evacuation approval more than 100 megawatt, it had a land bank also.
  • The company has a separate Company for Green Hydrogens and may set up a plant in KPI to sell power from its existing IPP plants to green hydrogen, depending on the circumstances.
    Show source
    The only thing that the support at KPI Green, if it has a green power, green electron that is existing IP P plants where from which green hydrogen is required we will set up a plant in KPI and we will sell the power to green hydrogen that might be our first thought depending on.

Other

  • The company said the amount was between 2,5000 crores and 3,000 crores.
    Show source
    Salim Yahoo: Yes, between 2,5000 crores to 3,000 crores.
  • The company will have a separate call for KP Energy. Replaced by a later filing.
    Show source
    Salim Yahoo: No, we will be having separate call for KP Energy also.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    So, the kind of competition in the upcoming orders, how do you see that? Like upcoming order will continue to flow in the manner that they have been flowing in recent past or how the picture looks like?

    Answer, salim yahoo

    Salim Yahoo: Garvit, you need to understand that KPI is one of the players who has more than a decade of experience, whether it is wind, whether it is solar. So, very few player has these kinds of capabilities, both wind and solar, and we have those capabilities. So, execution of order is an important part because all the players have orders as there is a lot of potential in the market, all players have orders. But it is to be seen that who has the capability to execute on a timely basis without any overruns. And that is where KPI’s USP is that, it is one of the strong executor. And if you see that all the orders that we have got because of our execution capabilities. So, from a KPI side, I can tell you that, order everybody will have it.

    Answer, salim yahoo

    Now it's the time that will tell you that which of the players are capable of executing the order on a timely basis. And here it is a track record of KPI that always speaks on itself. So, we don't have to speak because there is a decade experience and a hybrid execution experience, which is solar and wind both. So, we stand out over there. That's what I think .

  2. Question

    Sagar Tanna: What is our outstanding EPC book sir, in terms of crores ?

    Answer, salim yahoo

    Salim Yahoo: If I tell you, the total CPP, what we call it EPC, it's around 1.1 gigawatt of CPP business, what we call that. Now the CPP business, if I want to calculate, it will be because some projects are along with the material, you can say the panel or the wind turbine, and some projects come without them. So, overall, if you can see that, if one gigawatt approximately if I take, if you calculate 2.5 crores to 3 c rores per megawatt that would be the order book you can see that in the EPC site at present.

  3. Question

    Sagar Tanna: These are roughly 2,500 crores, is that a fair number?

    Answer, salim yahoo

    Salim Yahoo: Yes, between 2,5000 crores to 3,000 crores.

  4. Question

    Sagar Tanna: And sir, so how much of it would have been won in the current financial year in FY25?

    Answer, salim yahoo

    Salim Yahoo: As I told you, we do billing on a milestone basis. So, it is very difficult to actually tell you that exactly how much megawatt or something which we will get. So, it is very difficult to depend on the existing. But as I told you, our topline will be 60% to 70% minimum growth over the last year topline. Page 5 of 25 KPI Green Energy Limited November 11, 2024 Sagar Tanna: My question was not on the growth, sir.

  5. Question

    In terms of EPC order wins, how much did we win in the current financial year?

    Answer, salim yahoo

    Salim Yahoo: So, almost you can say that out of this 70% to 80% has been won in the current financial years in FY24-25.

  6. Question

    Sagar Tanna: And what is the order pipeline for the second half?

    Answer, salim yahoo

    Salim Yahoo: See, out of this 3,000 odd crore of the total order that we have in hand, okay, there will be a lot of overflow from this financial year to the next financial year. So, you can say that approximately Rs. 1,200 crores – Rs. 1,300 crores would be something that out of that, 40%-50% we are planning to close it this year. So, that will be, the remaining would be outflow for the next year.

  7. Question

    Aashish Rampuriya: I think what the previous participant was also asking, what is the bid pipeline right whether in terms of gigawatt or crores that we have? I am not going to order book but the bid that you would have placed or the conversation that we have.

    Answer, salim yahoo

    Salim Yahoo: The pipeline that we are looking at present is between 1.5 to 2 gigawatts. That is the bid pipeline that we are looking at, where we are participating and all. Over and above the existing order book that I have.

  8. Question

    Aashish Rampuriya: And this is across CPP and IPP?

    Answer, salim yahoo

    Salim Yahoo: Mostly CPP, because IPP we already have more than 1.2 gigawatts in hand. So, IPP we will slowly, slowly build because we already have on the plate. We will try to complete that as much as possible. Post that, we will start moving on to IPP. Because IPP, as you are aware, there needs to be a financial closure. There has to be a lot of factors which need to be taken into consideration on the debt side and equity side.

  9. Question

    Aashish Rampuriya: There are also some conversations around the international expansion, right? So, along with that, if you can also throw the status of expansion into nearby states of, I think we have shown Rajasthan and MP, if I am not wrong given the investor presentation. So, if you can throw some light in terms of that expansion, international as well as domestic states nearby?

    Answer, salim yahoo

    Salim Yahoo: First, we will talk about the domestic expansion. We are already, as I told you, we have already moved on to Maharashtra. We have plans to move to Andhra. We have plans to move to Page 6 of 25 KPI Green Energy Limited November 11, 2024 Rajasthan. We have plans to other states also, the neighboring state. But the one which we have close is, one is Maharashtra. Rajasthan and all are at we can say that final stages where we are doing the discussions only.

    Answer, salim yahoo

    Talking about the international, we are at a nascent state. We have discussions. We have a lot of inquiry from international players. We have spoken to them. But at present, I will not be able to give you any details about that. But I can assure you that very soon you will see KPI at an international level moving on competing with international players also.

  10. Question

    Aashish Rampuriya: But any nearby state that we're talking about and the fact that you said the focus will be CPP, should I assume that the conversation in the nearby states are the corporates to sort of under the CPP segment?

    Answer, salim yahoo

    Salim Yahoo: Mostly CPP as I told you because IPP as I earlier also told that we have to look at a lot of factors when it comes to IPP. So, any state entering CPP will be a very favorable segment where I can enter fast. IPP will take a little bit time because there are rules and regulations depending on each and every state, what are the electricity act over there or the state wise. So, that has to be taken into consideration.

Show 17 more questions
  1. Question

    Aashish Rampuriya: Last question from my side and I will join the queue. KP energy disclosed that they got some order, significant order from KPI Green. Now I think they spoke about phase 1, phase 2, phase 3, but I was surprised that they also spoke about doing solar work for us. Can you show some color on that because I think they specialize in wind, right?

    Answer, salim yahoo

    Salim Yahoo: Yes. Let me just explain you. We have one GUVNL tender for IPP for setting up IPP of 1 gigawatts. And from that, order has been given to KP Energy, which has experience in wind, which has experience in solar also. They have set up their own plant of solar also. So, we have transferred majority of the order to them, so that they can execute our order faster. Because KP energy we know, they can execute faster compared to any other players.

    Answer, salim yahoo

    And it is a hybrid order that we have got on the IPP and solar altogether. So, hybrid also has a solar component. So, combined order we have given it to them, except for some components like maybe panel or something, which we might purchase directly.

  2. Question

    Aashish Rampuriya: Okay, and it was driven by the perspective to meet timelines considering the solar aspect. Wind, I totally understand. Just want to understand the fact that we have given also solar to them is it because it was a combined order so had to be structured together or was it more for the sake of managing timelines and things like that?

    Answer, salim yahoo

    Salim Yahoo: See two things important, one is that surely timeline, you know our internal Company or a group Company will understand our timelines, deadlines, everything better than any other outside players. Secondly, as I told you, we have a hybrid. So, in hybrid also they are working in that region. So, in hybrid solar also they will work in that region. So, automatically it becomes feasible for us to give the entire order to them because they are anyway have their manpower, everything on the ground. So, why not utilize the same manpower other than setting up another one? So, that was the key idea behind giving the order.

  3. Question

    What was that related to?

    Answer, salim yahoo

    Salim Yahoo: It is a subsidiary of KPI, Sun Drops Energia Private Limited. In that subsidiary, anyway, I mean, promoter has to infused a lot of unsecured loan to support capex of new plant over there. So, it was said that, rather than returning it back, why not give promoter a small stake in the Company? So, that was a better option rather than curtailing the cash flows and giving it back to the promoter. So, that's where the entire thought came into picture. And then we thought that why not? Because anyway, it is a subsidiary of KPI, where even the promoter has a majority stake.

  4. Question

    Aashish Rampuriya: So, what percentage stake has been given in the subsidiary on Sun Drop?

    Answer, salim yahoo

    Salim Yahoo: I think that is there on the public domain. I don't have a figure right now.

  5. Question

    Parth Kotak: Sir, I have two questions, mainly on the order book and execution . One, as you rightly mentioned, your current order book is around 1.2 gigawatts, which would be about Rs. 2200 crores-Rs. 2300 crores. Could you elaborate on the anticipated timelines for order execution, especially for the large orders from MAHAGENCO and corporate clients?

    Answer, salim yahoo

    Salim Yahoo: If you see this, 1.1 gigawatt is my CPP order book. So, we have timeline to complete them by, an average timeline is that by September 25, we will have to complete this order. So, that's why I told you that the 50% of the order book will get executed this year, and 50% will flow down to that next year. So, yes, on an average, I will complete it before September. Parth Kotak: Just I am asking this because obviously we've mentioned it in the past that our average execution is about 9 months to 10 months on a conservative basis, but MAHAGENCO would be a separate territory that we would be doing CPP, right. So, that's why primarily the question. So, second question would be on debt and capital structure.

    Answer, salim yahoo

    Salim Yahoo: So, we all know that we already have 1.2 gigawatt of IPP projects. So, naturally, I mean, there will be a debt which will come. But it will not come at one go. It will come in a phase-wise. So, we will be doing our Khavda project, which is already in execution mode. So, a part of that debt will come from the Khavda, which is around 500 crores to 600 crores. And post that, that will also be for the other GUVNL project that we have won, 370 megawatt hybrid & 250 megawatt Solar,.

    Answer, salim yahoo

    So, there will be a debt which will come, but it will come in a phase-wise manner. But one thing I can assure you, that our debt to equity will never go beyond 2:1. It will be between 1.5:1 only. So, we are pretty gung-ho on that, that we will maintain our debt to equity, even if we go full-fledged expansion CAPEX. Page 8 of 25 KPI Green Energy Limited November 11, 2024 Moderator: Thank you.

    Answer, salim yahoo

    Salim Yahoo: If I want to give a little bit understanding of our model, so we have IPP and CPP. IPP adds to the bottomline, because IPP margins, EBITDA margins are very high. So, if you look at my GUVNL projects, my EBITDA margin in IPP would be around 85 % to 90%. Because after I set up the plan t, there is no other cost other than the only O &M cost which is very nominal. So, what overall at the Company level if I want to see my PAT margin is derived by both the segments. So, overall if I see that at present my blended EBITDA would be around 33 % to 37%. But as I go forward, when I increase the mix of IPP, my EBITDA, my PA T margin will also improve and my EBITDA margin will also improve.

    Answer, salim yahoo

    So, if I complete my entire order of GUVNL, after that our PAT margin, which is around 16% to 18%, might go up to 20% to 22%, if I increase my IPP mix in the total revenue. So, at present, if you see last year, it was around 13% to 14% of IPP revenue and rest all 86% was CPP revenue. So, it depends upon the mix. But we will be able to maintain the margins. So, that is sure for us. Drishtant: Actually, the reason behind the question is, I am not sure at what rate you're selling, let's say, units to your current private clients. And based on the reverse bidding, I just wanted to make sure that that price is pretty much in line and given that you see 85% odd EBITDA margins on IPP even on the GUVNL orders that's quite comforting.

    Answer, salim yahoo

    Thanks for the clarification. Then the next question is in fact on the land that you currently hold on your books. So , I understand you have about something in the range of 3000 acres of land. Any rough estimate you can provide in terms of what would be the current value on an average even on a per acre basis? Just to kind of get a sense of what the value of this land would really be because on books obviously you will be carrying value and one is not aware what the real values is.

    Answer, salim yahoo

    Salim Yahoo: So, if you see that, in FY25 Quarter 2, what we have mentioned that in our presentation also that we have 3000 plus acre of land. Now in this there are two types of lands. One is the Long term lease land, what we call as 27 to 28 year lease that we do with the farmer and we take those land and another is the own land. Now the own land would be around 500 to 600 acres and the rest of the entire land is a lease land. So, there is no cost for me for the lease land other than the lease that I have to pay for the land. Whereas the other parcel, which is my own parcel, what we call as 500 to 600 acre, that would be at around Rs. 1.5 crores to Rs. 2 crores per acre because this is close to the substation, close to the road, close to the highway. So, that is something which we have, but we have not reassessed the land on our 500 to 600 acres and the rest of the entire land is a lease land.

    Answer, salim yahoo

    So, there is no cost for me for the lease land other than the lease that I have to pay for the land. Whereas the other parcel, which is my own parcel, what we call as 500 to 600 acre, that would be at around Rs. 1.5 crores to Rs. 2 crores per acre because this is close to the substation, close to the road, close to the highway. So, that is something which we have, but we have not reassessed the land on our financial. So, in our financials, you will find Page 9 of 25 KPI Green Energy Limited November 11, 2024 the land value of approximately Rs. 100 odd crores. But overall the pricing would be around Rs. 1,000 crores, I can say. Drishtant: That's exactly what I wanted. So, Rs. 1.5 crores to Rs. 2 crores average you're saying per acre of the own land.

    Answer, salim yahoo

    Salim Yahoo: Yes. Drishtant: That's clarified. The next question sir, on cash flows and specifically very important from an equity investor's perspective, as you know how valuation work on the free cash flow basis. So, this will make some sense on the cash flow from operations, which have essentially been negative at least over the past 2 to 3 years. This first half of course I do see a Rs. 60 crore odd positive cash flow from operations. Any reason behind the negative cash flow of course there's the build up of the trade receivables. But going forward can we expect, let’s say an improvement on the cash flow front specifically, I mean on the cash flow from operation than on the free cash flow front or do you expect let's say negative cash flows to kind of continue given that you will be continuing to build receivables because of working with larger clients and on larger projects where obviously credit will be much more favorable for the other party, maybe less favorable.

    Answer, salim yahoo

    Salim Yahoo: If you look at my cash flows, last time I think the question was asked by one of the investors, we clearly told them this is a temporary phenomena, the negative cash flow last time. If you see in the March 24 results which was around 57 crores negative. That was basically because we told that, even Dr. Faruk Patel has told that in one of the event, that this is because we have taken bigger orders and there was some milestones towards the land, towards the evacuation, everything which was investment made and then there was long payments will come later. So, debtors also increased during that period. But now if you see in this first half of FY25, you see my net cash accruals has also improved , my receivables have gone down and other factors which are you know my working capital cycle also has improved , because that point of view, if you see my cash flows have improved. Now we have 60 , approximately Rs. 59 crores as a positive cash flow, which was around Rs. 57 crores in March negative cash flow . So, we clearly told last time also that, that was a temporary phenomena.

  6. Question

    What do you think is the tentative date of completion of our current order book, which comes to 2.41 gigawatt?

    Answer, salim yahoo

    Salim Yahoo: So, as I told you, the CPP segment we expect to close by September ‘25. And the IPP segment, we have just signed the PPA. So, two years from now, Mid of FY27 will be the entire completion. It will be done in phase-wise. But the entire final completion of the entire IPP order would happen by mid of FY27.

  7. Question

    Gaurav Sharma: One small question. Faruk sir had mentioned in an interview with NDTV Profit that the Company plans to add 2000 acres of land bank. So, how do we plan to fund this acquisition of the land bank and is this acquisition for our current order book or our future order book?

    Answer, salim yahoo

    Salim Yahoo: This is for both, for current and then we will be acquiring 2000-acre land bank. See, land acquisition is a continuous process in KP I because we have order books. And this exercise we keep on having evidence and because you know, you won't get the entire 2 thousand acre in one go at one location or anything. So, we have to keep on acquiring nearby locations. So, that process will be already started and that is something from the day KPI started is always you know focused on two important parame ters in the renewable energy which creates an order one is land, another is evacuation. So, if you look at we have 2.3 kind of giga order of evacuation also available with us.

  8. Question

    So, you told that this is Rs. 3 crores per megawatt. So, if I convert, can I say that the order book is of approximately Rs. 7,200 covers? Is my understanding correct or please correct me?

    Answer, salim yahoo

    Salim Yahoo: See, net realization going forward would be around Rs. 4 to Rs.5 because my IPP in GUVNL is a bigger scale. So, what we have done in IPP in C&I customers at present, we have 177 to 180 megawatts. And GUVNL is approximately will be adding one gigawatt more. So, automatically, you will see that the average, it will come to around between Rs. 4 to Rs. 5. Page 14 of 25 KPI Green Energy Limited November 11, 2024 Pavan: So, in terms of execution, are there any challenges that you're seeing in terms of grid evacuation or like in terms of transformer availability? Or you will see there are no risks, and then you're very confident that you will be able to commission the 1.15 gigawatt in the next one year.

  9. Question

    Mayank Manikya: I have two questions. The first one is regarding the operating profit margin. So, recently in recent quarters, we have done around 37% or 38% the OPM, but before that, we were at around 31% to 32%. So, going forward, how will this margin be maintained? How should I look at this margin? Will it be sustainable? Will it reduce or can you please?

    Answer, salim yahoo

    Salim Yahoo: In previous one of the questions, I already explained that the operating margin, we do billing on a milestone basis In the first half last year also if you compare it with that the first half we have a higher operating margin because lot of billing which is done, there is lesser you can say the cost of goods sold, the raw material requirement or whatever it is. So, from that point of view, we will have a higher operating margin, but we will be able to maintain what was earlier also, or you can say the full year FY24, what was the margin, this will be in the range of 32% to 33% only.

  10. Question

    Preet Jain: What will be your future revenue mix from private players and total revenue from government? What will be your total percentage of revenue from government and total percentage of revenue from private players?

    Answer, salim yahoo

    Salim Yahoo: Going forward if I complete the entire order book in the IPP side if I say, okay. Let's speak about IPP and CPP separately. So, on the IPP side, you can say that 80% odd would come from the revenue from government, that is a GUVNL project, and 20% odd would come from the revenue from C&I customers, which we already have signed and some of them will get signed. On the CPP side, it would be around, I presume it to be 50-50, because there are bigger players like MAHAGENCO and all where we are doing the CPP project also, tender based and there are also players like Aditya Birla Group or Ayana which we are doing. So, altogether I can say we might have a 50%-50% on the CPP side.

  11. Question

    Akhilesh Kumar: Just one last small question. Like we have a plan for as a group in hydrogen, green hydrogen as well. So, again, sometimes suddenly we see some of our promoters stake moving here and there and we are acquiring our group Company and you have many group companies, many unlisted sales. So, do we have any plan of Green Hydrogens for it from KPI Green or it will be a separate entity?

    Answer, salim yahoo

    Salim Yahoo: At present, we have a separate Company for the Green Hydrogens. So, we will be setting up a new plant. The only thing that the support at KPI Green, if it has a green power, green electron that is existing IP P plants where from which green hydrogen is required we will set up a plant in KPI and we will sell the power to green hydrogen that might be our first thought depending on. I mean there is a separate Company where we are already moving fast on the green hydrogen Page 19 of 25 KPI Green Energy Limited November 11, 2024 surely you have some good news about starting a prototype or you know working on that on the green hydrogen.

  12. Question

    Aashish Rampuriya: Battery energy storage systems and so on so forth, right?

    Answer, salim yahoo

    Salim Yahoo: No. At present, we have not entered or we are not having any intention for entering into battery storage. But surely, we will look at the sector batt ery, because you know when it comes to RTC , round the clock, it is one of the key ingredients that has to be a part of that. But nevertheless, we are doing hybrid, so which you can say a natural RTC kind of a thing, not totally RTC, but hybrid plants we are already doing. So, we have not taken any call at present, is at nascent state, we have not entered into batteries, but we have companies we will be thinking over it depending upon what the board decides finally after looking the various benefits and the cause and cons.

  13. Question

    Aashish Rampuriya: What I am asking to understand. Salimji, we have seen the impact, I mean what is the percentage gain now? So, typical CUF number is….

    Answer, salim yahoo

    Salim Yahoo: If we do tracker and all, there will be increase in percentage of between 3% to 4%.

  14. Question

    Samrat Shah: Thank you. And my other question is in H1 what was the percentage of IPP versus CPP and in H2 can we expect the IPP percentage to move up, so that the margins can even further improve because the IPP contributes bottomline is what Faruk bhai always says.

    Answer, salim yahoo

    Salim Yahoo: In H1 I can tell you that 13% to 14% was the contribution of IPP and rest all 86% to 87% was CPP. Since we are doing bigger orders in IPP and this will be GUVNL 240 megawatt and all. So, till the full year I don't think that there will be a drastic change in the mix of the IPP and the CPP. But after that coming years there will be changes which you will see in the IPP and the CPP. Samrat Shah: Because in the recent interview in NDTV Profit, he has given a guidance of IPP percentage moving to 30%. So, can we expect this in the next financial year? Page 21 of 25 KPI Green Energy Limited November 11, 2024 Salim Yahoo: Once I complete is 1.2 gigawatt of IPP orders, then the IPP percentage will be in the revenue will be more than around 30%.

    Answer, salim yahoo

    Salim Yahoo: As I told you earlier, there was one question which was on that you had a vision of 1 gigawatt by FY25 which I told you that for the group level we have already achieved and now we are going to achieve. So, similarly you can say that 365 cr for the group level , already PAT is achieved. We are now and Faruk sir when he speaks about , he speaks about group but now he's aiming that every Company should try to reach there as fast as possible , but that vision was at the group level only. Subash: And also like this conference call is very helpful for the individual investors. So, would there be a call for KP Energy also separately in the future or can we ask KP Energy questions also in the same call that you arranged for KPI Green. Salim Yahoo: No, we will be having separate call for KP Energy also. Nevertheless, I mean, I would have allowed you, but in the interest of time, we will do it on the KP Energy call also because KP Energy is going on NSE also on the 14th of this month.

  15. Question

    Lehar Jain: See, from my understanding what I get is like now we have some financial constraints and we are forced to give orders, subcontract it to other group concerns or even other concerns. So , going down the lane, in future, we might not be in a position to bid for IPP orders. And so the Company's profitability might come down. So, how you see 3 years down the lane, how you foresee our projections for CPP and IPP?

    Answer, salim yahoo

    Once we complete this order, because we also have to see how much leverage we can take on the balance sheet and the P&L. We don't want the balance sheet to be too leverage. As I told earlier also, we want to keep debt equity minimal of 2:1, not beyond that. So, from that point of view, we will take a cautious call depending upon the future outlook, after 1 or 1.5 years, which are the orders which we will be bidding out.

  16. Question

    Lehar Jain: But we see that the bulk orders which come say from NTPC or the likes of that companies these are all mostly on IPP basis. So, the opportunity, probably the peak opportunity might be lost?

    Answer, salim yahoo

    Salim Yahoo: I will take the second question first. In GUVNL project, until and unless I energize, and when the entire plant gets commissioned, only after that the energize, if the PP A allows me, then I can do a part sale. Whereas the milestones are concerned, milestone as I told you, we are planning to complete this entire 1.2 gigawatt within next 1 to 1.5 years. So, milestone will be depending on the IPP side. CPP as I told you, by September 25, we will have to, whatever order book we have 1.1 gigawatt or something on the CPP side will surely close that by September 20th.

  17. Question

    Akhilesh Kumar: This is just a quick one. Wanted you to know about one subsidiary we have absorbed from our promoter some time back. How is the progress there? That subsidiary has been contributing anything as of now?

    Answer, salim yahoo

    Salim Yahoo: Yes, so that subsidiary was taken with an intention because that subsidiary has an evacuation approval more than 100 megawatt, it had a land bank also. So, that subsidiary was taken with an Page 24 of 25 KPI Green Energy Limited November 11, 2024 intention to set up a plant. So, we have already started, we have set up a small plant of 10 megawatt and we are already setting up a few more plants over there in that subsidiary. So, the progress is already there. It has evacuation and land so it is easy for us to set up the plant faster.

Questions about this call

When was the KPI Green Energy Q2 FY25 earnings call transcript filed?
KPI Green Energy filed the transcript with the exchange on 15 Nov 2024. This page is built from that transcript.
What does this page list?
36 statements from the transcript across 8 topics, 29 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 27 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.
KPI Green Energy Q2 FY25 concall: KPI Green Energy Limited's bid pipeline was between 1.5 to 2 gigawatts, over and above its existing order book · DalalOS