Earnings call
KPI Green Energy Q3 FY25 earnings call: KPI Green Energy secured contracts with Coal India Limited in quarter 3 for a 300-megawatts AC ground-mounted solar PV project
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company secured contracts with Coal India Limited in quarter 3 for a 300-megawatts AC ground-mounted solar PV project. The company has a target of 10-gigawatts participation at the group level up to 2030. The company had an overall group portfolio of 5.2-plus gigawatts, including 1.4 gigawatts commissioned and a 3.8-plus gigawatts order book. The company reported total revenue of INR 466.1 crores in the quarter ended December 31, 2024, a 40.6% increase compared to the same quarter last year. The average cost is INR 3 crores to INR 4 crores per megawatt, while government tenders offer around INR 2.75 to INR 3 per unit; when the government started the subsidiary through JNMRE, Jawaharlal Nehru Mission Renewable Energy, the cost per megawatt was INR 15 crores and the cost per unit was INR 15. Today, the cost per megawatt is around INR 3.5 crores to INR 4 crores and the average parity is INR 3 per unit.
The numbers management gave
Results
- The company reported total revenue of INR 466.1 crores in the quarter ended December 31, 2024, a 40.6% increase compared to the same quarter last year.
Show source
Over the past quarters, we have delivered strong results with total revenue of INR 466.1 crores, a superb 40.6% increase compared to the same quarter last year.
- The company reported EBITDA of INR 144.54 crores in the quarter ended December 31, 2024, a 38% year-on-year growth.
Show source
Our EBITDA for quarter 3 reached INR 144.54 crores, reflecting a 38% year-on-year growth, while our profit before tax surged to INR 114.94 crores, marking an increase of over 60%.
- The company reported profit before tax of INR 114.94 crores in the quarter ended December 31, 2024, an increase of over 60%.
Show source
Our EBITDA for quarter 3 reached INR 144.54 crores, reflecting a 38% year-on-year growth, while our profit before tax surged to INR 114.94 crores, marking an increase of over 60%.
- The company reported profit after tax of INR 85.15 crores in the quarter ended December 31, 2024, up by 68.26% compared to the previous year's quarter.
Show source
Most impressively, our profit after tax climbed to INR 85.15 crores, up by 68.26% compared to the previous year’s quarter.
- The company reported total revenue of INR 1,177.35 crores for the nine months ended December 31, 2024, a 59.5% increase over INR 737 crores in the corresponding period of the previous fiscal year.
Show source
Our total revenue for the 9-month period has reached INR 1,177.35 crores, representing a 59.5% increase Page 3 of 31 KPI Green Energy Limited February 11, 2025 over the INR 737 crores in the corresponding period of the previous fiscal year.
- EBITDA grew to INR 411.44 crores for the nine months ended December 31, 2024, an increase of 66%, surpassing its full-year EBITDA for FY '23-'24.
Show source
This robust performance is further highlighted by our EBITDA, which grew to INR 411.44 crores, an impressive 66% increase.
Show 12 more statements
Results
- The company reported profit before tax of INR 302.2 crores for the nine months ended December 31, 2024, a 93% increase from last year.
Show source
Our profit before tax for the 9 months stood at INR 302.2 crores, a significant 93% increase from the last year, while our profit after tax reached INR 221.1 crores, reflecting an 86% growth over the previous period.
- The company reported profit after tax of INR 221.1 crores for the nine months ended December 31, 2024, an 86% growth over the previous period.
Show source
Our profit before tax for the 9 months stood at INR 302.2 crores, a significant 93% increase from the last year, while our profit after tax reached INR 221.1 crores, reflecting an 86% growth over the previous period.
- Fixed solar plants have around 18% PLF on average.
Show source
On the fixed, we have around 18% of PLF on an average.
- Tracker-based solar plants have 23% to 24% PLF, depending on location.
Show source
And the tracker base, you'll find we have at least 23% to 24% kind of, depending upon the location and everything.
- Net rate is INR 6; its gross rate is around INR 7 plus and sometimes reaches INR 8.
Show source
Salim Yahoo: Sorry, I'm saying net, that is at a net level, INR 6.
- The CPP segment's profitability margin at EBITDA level would be around 20%.
Show source
Salim Yahoo: See, on the CPP segment, I mean, profitability margin at EBITDA level would be around 20% Aman Soni: No, you mentioned we are protected on that particular side, raw material prices.
- Running plants set up 6 years ago are producing 18% on the fixed.
Show source
Salim Yahoo: As I told you that what we are getting on our running plants on the fixed is 18%, which have been set up 6 years ago, which is one of the best in the industry, I can tell you.
- The company said its margins had not gone down; the small dip was due to seasonality and milestone billing.
Show source
It's because of milestone billing that we do.
Money and capital
- The pledge on Faruk sir's total share is 45%; the total pledge is around 21% to 22% of the total pledge, was given as collateral in 2019, '20, and was not for raising fund.
Show source
So at present, the pledge that is there, I think it's 45% of what Faruk sir's total share is.
- Earlier plants are debt free, so their revenue is free cash flow.
Show source
And the earlier plants all are debt free, so that revenue is free cash flow.
- Collateral pledge was given long before the company's listing when it took funds from PFC, Power Finance Corporation; the pledge is still in place, and no funds were raised through pledging shares.
Show source
There is no fund raise through pledging of shares.
- SBI gave a positive response that it will start releasing the pledge after KPI Green Energy Limited approached SBI and gave it a letter.
Show source
And the same pledge is being carried on till now by SBI because that loan is already paid and also, but SBI is giving new loans but we have already given a letter and we have approached SBI also, and they have given a positive response that they will start releasing the pledge also.
What it expects ahead
What management expects
- GUVNL projects have an average rate of INR 3 per unit, and the GUVNL projects are bigger.
Show source
So, on an average, INR 3 unit kind of rate for the GUVNL project, and the GUVNL projects are bigger.
- Combining KPI Green Energy's existing portfolio, which earns INR 6-odd today, with the GUVNL projects would bring the rate to around INR 4 or INR 4.5 per unit.
Show source
So, if I look at the entire portfolio, which I'm getting INR 6-odd today for my existing portfolio, if I combine both of them, I would reach at around INR 4 or INR 4.5 unit, because then the INR 3 per unit also will play in.
- In the quarter ended December 31, 2024, IPP accounted for 13% and CPP for 87% of the business; KPI Green Energy plans to take the IPP component to 22% to 21% going forward and expects to maintain its PAT margin because its business combines CPP and IPP.
Show source
I can tell you that going forward, our IPP component, which at present, I think, is 13% i.e. 13% is IPP this quarter and 87% is the CPP, which we plan to take it to the level of 22% to 21% kind of going forward.
- For C&I CPP, KPI Green Energy Limited charges approximately INR 4 lakh to INR 5 lakh per megawatt per year for O&M, with an escalation of 2% to 3% year-on-year; after the free O&M period, its 362 MW CPP installed capacity is expected to generate around INR 36 crores annually from O&M and lease, including INR 5 lakh per annum per megawatt for lease.
Show source
So at present, for example, if I have a CPP installed capacity of 362 MW, you can say that per year going forward, you'll see around, because a year or something we give free O&M. So from -- you can say once this all matures, you will have around 362 megawatts which will give you INR 36 crores of O&M and lease because we also charge INR 5 lakh for lease per annum per megawatt.
- The company said its IRR would not reduce because the plants it is setting up now are at a lower cost than those set up earlier, making its IRR better.
Show source
But believe me, my IRR won't reduce because the plant that we are setting now are at a lower cost compared to one which we have set earlier.
- The company expects cash flow to be positive next quarter; cash flows were also positive last year.
Show source
So next quarter, we'll surely see cash flow positive.
Show 5 more statements
What management expects
- The company has a target of 10-gigawatts participation at the group level up to 2030. Replaced by a later filing.
Orders
- The company had more than 2.86 gigawatt of order book as shown in the presentation; as of Jan 15, it had approximately 2.86 gigawatt of order book.
Show source
But I can give you a megawatt that we had shown in the presentation, we have approximately 2.86 gigawatt of as on Jan 15.
- 100% of KPI Green Energy Limited's order book includes O&M; on the CPP side, the company handles O&M for an initial 3 years, with a minimum 2 to 3 years required, and it expects most customers to continue O&M with the company afterward.
Show source
Salim Yahoo: I would say 100% of the order book includes O&M. On the CPP -- see, IPP is my own, so I can, I mean, that is my O&M only.
- Coal India's DC capacity would be around 400 MW plus.
Show source
Salim Yahoo: DC Coal India would be around 400 MW plus.
- The company secured contracts with Coal India Limited in quarter 3 for a 300-megawatts AC ground-mounted solar PV project. Replaced by a later filing.
What it is building and selling
Projects and capacity
- The company had an overall group portfolio of 5.2-plus gigawatts, including 1.4 gigawatts commissioned and a 3.8-plus gigawatts order book.
Show source
As of today, if you look at our overall group level, we have a robust portfolio of 5.2 -plus gigawatts with 1.4 gigawatts already commissioned and a strong 3.8 -plus gigawatts order book.
- The company has 3.8 gigawatts under the pipeline.
Show source
You know that what Siddharth told just now, 3.8 gigawatts under the pipeline.
- The company started execution in Maharashtra with a 100-megawatt AC solar project.
Show source
So, we have also started our execution in Maharashtra with 100 -megawatt AC solar project.
- 240-megawatt DC solar project at Khavda in Gujarat is progressing ahead of schedule.
Show source
Notably, our flagship project, 240-megawatt DC solar project at Khavda in Gujarat is progressing ahead of schedule, which is a trademark that we always try to close our project before the schedule that is given to us.
- As of January 15, 2025, KPI Green Energy's installed capacity had grown to over 533 megawatts, supported by an order book of 2,869 megawatts, or 2.86 gigawatts.
Show source
On the operational side, as of January 15, 2025, installed capacity has grown to over 533 megawatts, supported by a strong order book of 2,869 megawatts, that is 2.86 gigawatts.
- The company had power evacuation capacity of 2.59 gigawatts and a land bank exceeding 4,180 acres.
Show source
With a power evacuation capacity of 2.59 gigawatts and a land bank exceeding 4,180 acres, we are well positioned to capitalize on future opportunities and drive our expansion in the renewable energy space.
Show 21 more statements
Projects and capacity
- The tracker-based system cost can range from INR 3.25 crores to INR 3.95 crores depending on customization, land size and design; straight land costs less, while land that is not totally straight costs more because each row needs a different structure and a tracker.
Show source
Salim Yahoo: you can say that depending upon the customization, depending upon the size of land and everything, the design, it might go from INR 3.25 crores to INR 3.95 crores depending upon how the land is.
- The company takes all land for its IPP projects on lease and does not invest in land; the payback period for IPP projects ranges from 7 to 8 years.
Show source
But the payback period ranges from 7 to 8 years for IPP projects.
- The design life of solar panels is generally 20 years, and no panel has crossed two decades of design life.
Show source
Alok Das: So, the thing is like solar industries, which was first installed in the commercial scale setting of Gujarat, 20 years generally is the design life.
- The plant will be 240-megawatt DC and will be energized in phases depending on GSS; the plant will be completed before March, with the majority completed before March.
Show source
It will be energized depending upon the phase also, there might be some -- depending upon GSS again, I'm telling, GSS, but we will complete the plant before and the majority of the plant will be completed before March.
- Approximately 2,000 acres are utilized and 2,000 acres are yet to be utilized; KPI Green Energy is adding more land to its land bank at a faster pace as it takes on large projects.
Show source
Salim Yahoo: Approximately, I think 2,000 acres would be utilized and 2,000 acres, which is yet to be utilized.
- The company has signed almost 500-megawatt of wind and solar projects at the beginning, which is to be escalated.
Show source
We have signed almost 500-megawatt kind of wind, solar at the beginning and followed -- that is to be escalated.
- The company has started execution of its Khavda projects and expects to energize one plant ahead of schedule; it targets completing construction within 12 to 15 months, compared with the 2 years from signing PPAs usually given for construction.
Show source
We target that we will close it within 12 to 15 months.
- The company invested its own equity and started work on another 50 megawatts plant before financial closure.
Show source
Even before the financial closure, we have invested our own equity, and we have started working on that plant also.
- The company can execute a pure solar project within 6 to 8 months if it deploys all its resources.
Show source
Salim Yahoo: See, executing, if we go full fledge and we put all our resources, we can do within -- if it is pure solar, it can be done within 6 to 8 months also.
- The company can complete a 100-megawatt project within 6 to 8 months if it is pure execution without land or evacuation; for projects such as Mahagenco, land collection and evacuation take around 18-odd months, and evacuation and land account for much of the project timeline.
Show source
But when it comes to land, when it comes to -- so usually like Mahagenco, we have got 18-odd months or something.
- INR 900 crores Khavda project is its own IPP project and its capex, so the company will not bill for it; Coal India and Aditya Birla are EPC contracts for which the company does billing.
Show source
So I'll not do the billing for that, okay?
- IPP installed capacity was 171 megawatts as of June 30, 2024.
Show source
As on that day itself, 171-megawatt has been live.
Demand and pricing
- The average cost is INR 3 crores to INR 4 crores per megawatt, while government tenders offer around INR 2.75 to INR 3 per unit; when the government started the subsidiary through JNMRE, Jawaharlal Nehru Mission Renewable Energy, the cost per megawatt was INR 15 crores and the cost per unit was INR 15. Today, the cost per megawatt is around INR 3.5 crores to INR 4 crores and the average parity is INR 3 per unit.
Show source
Today, they are in parity again The cost for megawatt is around INR 3.5 crores to INR 4 crores, and the parity is, on an average, we get INR 3 per unit.
Segments
- The company has completed almost 3 gigawatt of projects overall in the industry.
Show source
And we have done a lot of bigger projects, more than -- almost 3 gigawatt of projects we have done overall in this industry.
- The company said the wind portion costs around INR 6 crores to INR 8 crores per megawatt and the solar portion ranges from INR 3 crores to INR 3.75 crores, INR 3.85 crores depending on land and other factors.
Show source
And when it comes to the solar portion, it ranges from INR 3 crores to INR 3.75 crores, INR 3.85 crores depending upon the land and everything.
- The company provides end-to-end EPC services, O&M capabilities and the RESCO model for renewable energy projects.
Show source
Our expertise spans end-to-end EPC services, O&M capabilities and the RESCO model, ensuring that we deliver reliable, sustainable and scalable renewable solutions.
- The company has signed PPAs for its IPP.
Show source
Salim Yahoo: PPA, Yes, the PPAs are signed for my IPP.
Deals and partners
- The company requested at least 1,500 megawatt of solar potential in Odisha; GRIDCO, a local body, said it would call investors who signed an MOU after Utkarsh Odisha and provide them with available resources.
Show source
So we have requested at least 1,500 megawatt kind of solar potential that state.
- The company buys from Tier 1 companies including Waaree and Emmvee.
Show source
Salim Yahoo: The pricing is a very, what we say, confidential information from, I can tell you, we buy from Tier 1 companies like Waaree, Emmvee, we purchase.
- The company expanded its renewable portfolio through strategic MOUs with the government of Rajasthan and Odisha.
Show source
And further, we have expanded our renewable portfolio through strategic MOUs with the government of Rajasthan and Odisha.
- All CPP projects have signed PPAs before orders are given; Coal India signed a PPA with GUVNL before giving KPI Green Energy Limited the orders. Replaced by a later filing.
Risks, rules and outside factors
Outside factors
- For KPI Green Energy's IPP projects, if module cost increases, the tender allows an equivalent increase in the rate.
Show source
And on the IPP side, if there is an increase in the module cost, the tender allows increase in the rate is also equivalent.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Garvit Goyal: And order in hand also for IPP segment?
Answer, salim yahoo
Salim Yahoo: Yes, IPP segment, we have already considered -- you need to understand, in IPP, we have to invest our own capital and set up the plant and sell the power. So that is our IPP segment. So, in IPP segment, we already have sufficient order book, for which we have tied up with the bankers and the financial institution for the debt capital which is required. Now we have a lot of inquiries where we want to do IPP, but we have to keep in mind our leverage and we have to keep in mind our repaying capacity, , our rating and other factors So that's the reason -- we have enough book right now for IPP. Once we see that this book starts getting executed and completed to a certain limit, then we will start adding more and more IPP. That's why in IPP, we have taken approximately 1.3 gigawatt s from GUVNL itself. So, we will start working on that ’we have already started working on the first 50 megawatt, then 370.
Answer, salim yahoo
So, once we start moving progress in that, then we will add up more IPP.
Question
Garvit Goyal: Okay. And thirdly, like looking at the geopolitical tensions, and we all know that we are having our old plants in India and our customer base is also based out of India. So, we are having no connection, as far as revenue is concerned, with the rest of the world. But looking at the supply chain things, like are we facing any issues related to supply chain that may impact our margins going ahead or a shortage of the components that we use in our project execution or anything like that, sir?
Answer, salim yahoo
Salim Yahoo: We do meticulous planning before taking the orders for the CPP side. And on the IPP side, if there is an increase in the module cost, the tender allows increase in the rate is also equivalent. So, I don't think we will face any problems on the supply chain side also. As far as the execution is concerned, we are well geared up for executing . And supply chain, we take care of that. We do a proper planning for that. So, I don't think -- neither the price will impact us, nor the availability will impact us.
Question
So, what is the specific reason for it? And what is the guidance for the rest of the year and years coming ahead?
Answer, salim yahoo
So again, you will find a little bit shrinking there. So, it's a seasonality factor. It is not that the margins have gone down. It is just that you see the trend of last year also, you'll find similar. If you see last year, we had around 33% to 34% in the second quarter, and third quarter, again, 30%, 31%, again, something like that. So, it will be a small dip because of the way the billing is happening. It's because of milestone billing that we do.
Answer, salim yahoo
Salim Yahoo: Yes, I'll tell you. See, in IPP, we have 2 kinds of plants. One is fixed in the solar side and another is tracker based, okay? Because when we started long back, at that time, fixed was something which was in thing, so we have done. So, some portfolio is fixed. On the fixed, we have around 18% of PLF on an average. And the tracker base, you'll find we have at least 23% to 24% kind of, depending upon the location and everything.
Answer, salim yahoo
And as far as the wind portfolio, we have hybrid also. So, the wind itself will give you 34% to 35% of PLF Hrishil: And sir, what is this tracker based? Like can you explain this?
Answer, salim yahoo
So, it keeps on moving. It's a moving and it's a non -moving, you can say, in a simple language. Hrishil: And sir, then currently out of 171 megawatts, which we have solar installation capacity. So, can you like tell how much will be tracker based and how much will be the fixed?
Answer, salim yahoo
Salim Yahoo: Sorry, I'm saying net, that is at a net level, INR 6. Gross will go around INR 7 plus something. Sometimes it goes up to INR 8 also. There also, you have different factors. So, if it is not utilized, then we get APPC rate also, and we also get the customers' minimum utilization rate. So, it's a different calculation that has to be done. Hrishil: Okay.
Answer, salim yahoo
Salim Yahoo: See, going forward, what we have -- we are setting up the IPP for GUVNL, where the rates are fixed. So, on an average, INR 3 unit kind of rate for the GUVNL project, and the GUVNL projects are bigger. So, if I look at the entire portfolio, which I'm getting INR 6-odd today for my existing portfolio, if I combine both of them, I would reach at around INR 4 or INR 4.5 unit, because then the INR 3 per unit also will play in. But believe me, my IRR won't reduce because the plant that we are setting now are at a lower cost compared to one which we have set earlier. So automatically, my IRR is better. And the earlier plants all are debt free, so that revenue is free cash flow. Hrishil: Okay.
Question
Aman Soni: Sir, I missed on that CPP part, like how we are protected on margin side in CPP segment?
Answer, salim yahoo
Salim Yahoo: See, on the CPP segment, I mean, profitability margin at EBITDA level would be around 20% Aman Soni: No, you mentioned we are protected on that particular side, raw material prices.
Question
Hardik Gandhi: Just tracker based since that's more efficient for you guys. So, I'm assuming you would be putting up that one.
Answer, salim yahoo
Salim Yahoo: you can say that depending upon the customization, depending upon the size of land and everything, the design, it might go from INR 3.25 crores to INR 3.95 crores depending upon how the land is. If it is a straight land, it will be less cost. If it is a land which is not totally straight, then it will be a little bit costly, because then every row will have a different structure and you have to put a tracker for every row,. Page 9 of 31 KPI Green Energy Limited February 11, 2025 Alok Das: Yes, and this is a pure technical question you have asked.
Question
Hardik Gandhi: Understood. Understood. Sir, and what would be a good payback period for the IPP projects which we are taking up, since we are purchasing the land also, along with that we are putting -- I'm assuming this INR 3.5 crores, approx cost, depending, it excludes the land also, right?
Answer, salim yahoo
Salim Yahoo: At present, we are taking all land on lease only. So, we are not investing in land . But the payback period ranges from 7 to 8 years for IPP projects.
Question
Hardik Gandhi: Okay. So, what is the actual useful life? I know that -- I've read it online that the useful life of a solar module, given the latest technology, they mentioned it as a 20-year frame. But on reality, it's somewhat different. So, what would be the actual useful life of a panel?
Answer, alok das
Alok Das: So, the thing is like solar industries, which was first installed in the commercial scale setting of Gujarat, 20 years generally is the design life. So, after the design life, based on the depreciation of the panel, so we have to just see the survival, whatever these things. So not a single panel crossed 2 decades design life. So, it is going on. This is for the solar part. But generally, government is also very clear. Suppose after 20 years or 25 years, CPA reason, so they want to see the healthiness of the connectors of the solar panel as well as the wind machines.
Question
Hardik Gandhi: Understood, sir. Understood. So, since you mentioned there's a long 8-year payback period and along with that, the asset keeps on depreciating and since we don't know, so is there a possibility that in the sixth or seventh year, there's a drastic reduction in the output of the solar panels?
Answer, salim yahoo
Salim Yahoo: As I told you that what we are getting on our running plants on the fixed is 18%, which have been set up 6 years ago, which is one of the best in the industry, I can tell you.
Question
Hardik Gandhi: So, you mentioned 80%, Is that correct?
Answer, salim yahoo
Salim Yahoo: Yes, see, pledging, let me be clear on this. This pledging is a collateral. We have given a collateral long back, even before the listing of the company. We had given collateral when we had taken funds from PFC, Power Finance Corporation. So, it was a collateral which is still there. There is no fund raise through pledging of shares. Let us be clear on that.
Question
Kush Pranao: Right, sir. And regarding operating cash flow.
Answer, salim yahoo
Salim Yahoo: Cash flow. See, cash flow will be positive. And if you see, this quarter, we don't put the balance sheet. So next quarter, we'll surely see cash flow positive. I think last year also cash flows were positive only.
Show 12 more questions
Question
That's great. And the plant will be, like say, deemed operational only when we have the entire 200 megawatt energized, or it will be in phases?
Answer, salim yahoo
Salim Yahoo: So, plant will be 240-megawatt DC. It will be energized depending upon the phase also, there might be some -- depending upon GSS again, I'm telling, GSS, but we will complete the plant before and the majority of the plant will be completed before March. Akhilesh Kumar: Okay. Congratulations for the great performance.
Question
Ashish Rampuria: So out of this 4,000 acres, right, what percentage will be today free to be deployed or not used at this point in time?
Answer, salim yahoo
Salim Yahoo: Approximately, I think 2,000 acres would be utilized and 2,000 acres, which is yet to be utilized. And we are adding more and more. So, now you'll see a rampant growth in the availability of land bank because we are taking big, big projects so we'll keep on adding at a faster pace.
Question
Ashish Rampuria: Got it. This MOU we have done with Rajasthan government and Odisha government, can you throw some light in terms of the capacity we're talking about? Is it IPP, CPP, what time duration and so on and so forth?
Answer, alok das
We Page 14 of 31 KPI Green Energy Limited February 11, 2025 have already created one of our establishments in Jaipur already. So, we want to create this job maybe by next 3 to 6 months. And not only that, what the progress is happening, CMO office is regularly following with us. What are the development, what kind of support they require. So that means the willingness of the government, political will is also there and followed by our -- on a fortnight or a monthly basis follow-up. So we are going ahead for our target. We have signed almost 500-megawatt kind of wind, solar at the beginning and followed -- that is to be escalated.
Answer, alok das
So these jobs that are going on as far as Rajasthan is concerned. Odisha, recently we have signed. So we have also done the similar kind of approach for wind and solar and some part of the other technologies. So we have requested at least 1,500 megawatt kind of solar potential that state. So they are also -- that GRIDCO, which is a local body, they said that we want to call in after the Utkarsh Odisha happened recently. So they will call all sort of investors who have signed the MoU, and they will give us the resource where it's available. So accordingly, we will even plan for the state of Odisha also in a similar way what we are planning for Rajasthan.
Question
Vaibhav Lohia: Okay. So as we are going forward, like more portion of our revenue will be from IPP segment. So what type of PAT margins can we expect at blended levels for FY '26 and going ahead?
Answer, salim yahoo
Salim Yahoo: PAT margin -- we'll be able to maintain the PAT margin because our business is a combination of CPP and IPP. I can tell you that going forward, our IPP component, which at present, I think, is 13% i.e. 13% is IPP this quarter and 87% is the CPP, which we plan to take it to the level of 22% to 21% kind of going forward. So automatically, once my CPP increases, both of them increase, so we will be able to maintain the margin. Page 16 of 31 KPI Green Energy Limited February 11, 2025 Moderator: The next question is from the line of Mitesh Vora, an Individual Investor.
Answer, salim yahoo
Salim Yahoo: I think pledging question, I already answered that this is not pledge for raising fund. It is just a collateral given and that was given long back in 2019, '20 when our first plant was setting up and Power Finance Corporation at that time wanted a little bit comfort because we were a smaller player at that time. And the same pledge is being carried on till now by SBI because that loan is already paid and also, but SBI is giving new loans but we have already given a letter and we have approached SBI also, and they have given a positive response that they will start releasing the pledge also. So at present, the pledge that is there, I think it's 45% of what Faruk sir's total share is. So it would be around -- on the total pledge, it would be around 21% to 22%. But this is, again, I'm highlighting, people are getting that this pledge is not for fund raise. It was earlier given and it is just a collateral.
Question
Rajat Gupta: Noted. Noted, sir. And one more last question. Regarding the IPP segment, the revenue seems to be started generating as per the PPA after 7, 8 years, as you mentioned. So the earlier project we have set up, is that the revenue has started from our earlier project that is being set up under IPP?
Answer, salim yahoo
Salim Yahoo: We have already started execution. As I told you, one of our Khavda projects is ahead of schedule. So we'll be energizing that plant done ahead of schedule. The other plants also like 50 Page 19 of 31 KPI Green Energy Limited February 11, 2025 megawatts, again, we have started the plant. Even before the financial closure, we have invested our own equity, and we have started working on that plant also. So believe me, usually, the gestation period or the period for construction given by the PPA is 2 years from signing the PPAs. We target that we will close it within 12 to 15 months.
Answer, salim yahoo
Salim Yahoo: See, there is no impact because we are not a new player that are entering the market for the first time. We have been in this industry for more than decades. And we are the only player which has capability of wind as well as solar. So, very few players have these capabilities in development. And we have done a lot of bigger projects, more than -- almost 3 gigawatt of projects we have done overall in this industry. So we have those expertise. And I understand there will always be challenges, but we are well prepared for those challenges, and we have a good team, which includes ex GEDA, GETCO, retired IPS officers, IAS officers, which give us the guidance and they help us in facing these challenges.
Answer, salim yahoo
Salim Yahoo: It is very difficult to value because orders are different. Like at present, I have more than 2.86 gigawatt of order book, which is there as shown in the presentation. Out of this, there will be orders which are some orders like conglomerate like Aditya Birla order, which will be without materials like panel and anything. There will be orders without windmill and anything. And there will be orders with windmill with panels also like Mahagenco or anything. So exactly bifurcating them is not -- because the figure will not tally up with that because every order has a different, what we say, calculations. But I can give you a megawatt that we had shown in the presentation, we have approximately 2.86 gigawatt of as on Jan 15.
Answer, salim yahoo
Salim Yahoo: See, hybrid, I mean, if I say, around INR 6 crores to INR 8 crores for the wind portion, you can say, INR 6 crores to INR 8 crores per megawatt for the wind portion. And when it comes to the solar portion, it ranges from INR 3 crores to INR 3.75 crores, INR 3.85 crores depending upon the land and everything. All factors are there. It's just a ballpark figure. But exactly, it depends upon the land and depends upon the evacuation, how far, as Dr. Alok Das has told us that evacuation -- all these factors play a role when it comes to the pricing of the IPOs.
Question
Agastya Dave: I have full faith in your capabilities. My question was slightly different. So let's suppose you get a brand-new order today and you start working on it. So how long will it take for you to execute Page 21 of 31 KPI Green Energy Limited February 11, 2025 the entire project? Let's say, the project is 100 megawatts solar with tracker and you have the land available with you. So with that, how long does it take for you to execute that for you?
Answer, salim yahoo
Salim Yahoo: See, executing, if we go full fledge and we put all our resources, we can do within -- if it is pure solar, it can be done within 6 to 8 months also. This is very short period depending upon all other factors. If the evacuation is on the other side. Like if you see, Khavda project, we are, again, doing it in a record timeline. And that is also a tracker base.
Question
Parin Gala: Sir, margin part is not special, sir. I was saying -- and when there is a lot of competition, there are a lot of bidders for one particular project itself and reverse auction, still the prices are pretty high. I'm just trying to understand that when cost of per megawatt has come down, the unit prices, in fact, instead of going down have gone up. That is what I'm trying to understand that logic.
Answer, salim yahoo
Salim Yahoo: If you see on an average, INR 3 crores to INR 4 crores per megawatt is the cost. And the unit prices that government tenders and everything is giving around INR 2.75 to INR 3, which is in parity, which has been -- because I know the sector long back when government started the subsidiary through JNMRE, Jawaharlal Nehru Mission Renewable Energy. Page 23 of 31 KPI Green Energy Limited February 11, 2025 So at that time, the cost per megawatt was INR 15 crores, and the cost per unit was INR 15. Today, they are in parity again The cost for megawatt is around INR 3.5 crores to INR 4 crores, and the parity is, on an average, we get INR 3 per unit.
Question
Parin Gala: It is on lease, but even lease prices are higher, right?
Answer, salim yahoo
Salim Yahoo: No. So private -- I mean, still, I don't think it is a major component of the entire project cost. Majority goes towards the panel only. So panel derives the profitability also to an extent, I can say. Page 24 of 31 KPI Green Energy Limited February 11, 2025 Parin Gala: So my other question is, Salimji, in this entire order book of 2.8 gigawatts that we have, what portion of that order book also has O&M component to it?
Answer, salim yahoo
Salim Yahoo: I would say 100% of the order book includes O&M. On the CPP -- see, IPP is my own, so I can, I mean, that is my O&M only. CPP side, the initial 3 years -- the condition always is there that minimum 2 to 3 years O&M has to be handled by us. And later on, they will think. But believe me, we have technologies and everything which are robotic cleanings and everything. So naturally, they will continue to O&M with us only, most of it.
Question
Parin Gala: So sir, in the next 2 to 3 years, what kind of O&M revenues can we expect out of whatever we will execute, approx?
Answer, salim yahoo
Salim Yahoo: See, for what we say, C&I CPP, our revenue for O&M, I charge approximately INR 4 lakh to INR 5 lakh per megawatt per year with an escalation of 2% to 3% year-on-year. So at present, for example, if I have a CPP installed capacity of 362 MW, you can say that per year going forward, you'll see around, because a year or something we give free O&M. So from -- you can say once this all matures, you will have around 362 megawatts which will give you INR 36 crores of O&M and lease because we also charge INR 5 lakh for lease per annum per megawatt. So approximately INR 36 crores which would be what we can say a ballpark figure for this 362. And Whatever we add will keep on adding to that.
Question
Parin Gala: Sir, last question, this INR 5 lakh of land lease is also per year per megawatt, right?
Answer, salim yahoo
Krishna. See, every project has its own characteristic. So if the project is pure execution without any land, without any evacuation or anything, I might compete, as I told you, within -- I put full force and I can complete 100-megawatt within 6 to 8 months also, not an issue before that also. But when it comes to land, when it comes to -- so usually like Mahagenco, we have got 18-odd months or something. We have to complete the land collection and evacuation is also an important part. So any project timeline, major time goes into the evacuation of the land. Whereas the solar projects, I would say, setting up a solar project will not be a big challenge.
Question
Samrat Shah: So on a rough basis, approximate basis, the Khavda project is of INR 900 crores, coal India is of INR 1,300 crore and Aditya Birla is of INR 450 crores. If you add up, it comes to around INR 2,000...
Answer, salim yahoo
Salim Yahoo: Khavda project, INR 900 crores we are talking about is the IPP project. That is my own project. That is my capex. So I'll not do the billing for that, okay? Now Coal India, as I told you – for Coal India. Aditya Birla, again, I mean, it is an EPC contract. So we are doing billing.
Question
Samrat Shah: Right, sir. And one last part, sir. A personal request. Whenever Faruk bhai is free, I would like to fly from Chennai and meet him because of creating immense wealth for me and my family. So just from your end if you would arrange this.
Answer, salim yahoo
Salim Yahoo: Yes, Period so your revenue generation depends upon the period, how much period that plant was energized. For example, if a plant is energized from December, so automatically, that capacity will get added, but the generation will not get added because it gets energiz ed from December. So some energized from October. So it's a linear calculation that is to be. Pavan: What I mean to say is that the 171-megawatt has been live from June quarter end at least. So for the entire...
Answer, salim yahoo
Salim Yahoo: Sir, let me explain you. IPP installed capacity till Jan 15, we have mentioning in the presentation that we have shared, right, this quarter. So it is still -- that is as on that date, it is 171. But it's not that, that 171 started from the 1st day of October. So that was... Pavan: Q1 FY '25 presentation, which is as on 30th June 2024 end. As on that day itself, 171-megawatt has been live.
Answer, salim yahoo
So all the factors have been taken into consideration. Page 29 of 31 KPI Green Energy Limited February 11, 2025 Pavan: Sir, my question was because the 14% seems like a large drop? That's the question. But I understand. Sir, the second question is Coal India order is of 300 megawatts AC, right? How much would it be in DC?
Answer, salim yahoo
Salim Yahoo: DC Coal India would be around 400 MW plus. Pavan: So 30% will be the 1.3 is the conversion ratio.
Answer, salim yahoo
Salim Yahoo: PPA, Yes, the PPAs are signed for my IPP. Pavan: What about the CPP project, sir? Are you aware whether all the projects are signed?
Answer, salim yahoo
Salim Yahoo: CPP project, I do the EPC. So the PPAs are signed. For example, Coal India has signed PPA with GUVNL. And after that only, they have given us the orders. So all CPP projects, PPAs are signed and after that only they give us the order. Pavan: Got it, sir. The last question from me.
Answer, salim yahoo
Salim Yahoo: The pricing is a very, what we say, confidential information from, I can tell you, we buy from Tier 1 companies like Waaree, Emmvee, we purchase. But pricing is something that even my supplier will not allow me to disclose his pricing in the public forum. Pavan: Okay. Sir, you can tell us whether it is above 14 per watt or less than 14 per watt.
Questions about this call
- When was the KPI Green Energy Q3 FY25 earnings call transcript filed?
- KPI Green Energy filed the transcript with the exchange on 18 Feb 2025. This page is built from that transcript.
- What does this page list?
- 57 statements from the transcript across 9 topics, 46 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 22 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.