Earnings call
Power Grid Corporation of India Q1 FY27 earnings call
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
The company had won 6 transmission projects in inter-state and intra-state bidding by July 2026, with total gross annual tariff of about Rs. 2,200 crores. POWERGRID has Rs. 300 crore of revenue that will start accruing when the regulator issues orders for deemed DOCO status for systems built under the regulatory tariff regime (RTM mode). The company commissioned about 1,635 circuit kilometers in Q1 FY27, almost 35% of last year's achievement in the first quarter of Q1. Gross fixed assets stood at about Rs. 3.25 lakh crore plus in Q1 FY27. The Government of India held about 51.34% of Power Grid Corporation of India Limited as of 30th June, 2026.
The numbers management gave
Results
- Gross fixed assets stood at about Rs. 3.25 lakh crore plus in Q1 FY27.
Show source
As far as the highlights and overview, pleased to inform that the gross fixed assets stand at about Rs. 3.25 lakh crore plus.
- The company had about 1,86,000 circuit kilometers of transmission lines in Q1 FY27.
Show source
The transmission lines in terms of circuit kilometers are about 1,86,000 circuit kilometers.
- The company had transformation capacity of 6,34,516 MVA and about 291 substations as of 30th June, 2026.
Show source
Transformation capacity is 6,34,516 MVA with about 291 substations which it encompasses.
- System availability was 99.8% as of 30th June, 2026.
Show source
The system availability continues to be one of the highest in terms of 99.8%.
- Capitalization in Q1 FY27 was about Rs. 5,277 crores against Rs. 1,683 in the last quarter, almost 3.13 times the last-quarter achievement; guidance was Rs. 30,000 crore.
Show source
So , as against 1,683, we stand about Rs. 5,277 crores as far as capitalization is concerned.
- The sector's billing stood at about Rs. 10,963 crore and realization at about 104%, or Rs. 11,404 crore, in Q1 FY27.
Show source
And robust collections continue to be there in the sector, with the billing standing at about Rs. 10,963 crore, and the realization about 104%, that is Rs. 11,404 crore.
Show 33 more statements
Results
- The number of receivable days came down from 19.41 in the previous quarter to about 12 days in Q1 FY27.
Show source
A comparison with the previous quarter and the current quarter visibly indicates that the number of receivable days come down from 19.41 to about 12 days.
- Consolidated PAT was about Rs. 3,598 crore in Q1 FY27, compared to Rs. 3,631 crore in the previous quarter.
Show source
The PAT stands at about Rs. 3,598 crore compared to Rs. 3,631 crore of the previous quarter.
- Transmission charges increased by about Rs. 790 crore in Q1 FY27 owing to new assets commissioned.
Show source
And I would like to say over here that the total increase in the transmission charges, that's about Rs. 790 crore owing to the new assets which have been commissioned.
- Revenue was reduced by about Rs. 330 crore due to depreciation and Rs. 230 crore owing to interest because of the difference between petitions filed and orders issued by the regulator, for a total regulatory downside of about Rs. 560 crore in Q1 FY27.
Show source
So, this amounts to about Rs. 560 crore was the downside owing to the regulatory nature of revenue.
- Effective PAT would have been plus Rs. 247 crore but for the regulatory characteristic, while it stood at about minus Rs. 33 crores, a reduction of about 1% in Q1 FY27.
Show source
So while the effective PAT would have been plus Rs. 247 crore, but for the regulatory characteristic, it stands about minus Rs. 33 crores, a reduction of about 1%.
- Gross fixed assets increased from Rs. 2,92,446 crore to Rs. 3,25,671 crore in Q1 FY27.
Show source
The financial performance continues to be strong in terms of the gross fixed assets continue to move upwards from Rs. 2,92,446 crore to Rs. 3,25,671 crore.
- Capital work in progress increased from Rs. 41,610 crore to Rs. 50,419 crore in Q1 FY27.
Show source
The capital work in progress from Rs. 41,610 crore to Rs. 50,419 crore.
- Net worth improved from Rs. 96,482 crore to Rs. 1,04,028 crore in Q1 FY27.
Show source
The net worth improving from Rs. 96,482 crore to Rs. 1,04,028 crore.
- Earnings per share stood at 3.87 and book value per share at about 111.85 in Q1 FY27.
Show source
And the ratios accordingly owing to the increased net worth having an impact of earnings per share standing at 3.87, and book value per share about 111.85.
- Income from previous periods was plus Rs. 8 crore in Q1 and minus Rs. 22 crore in Q1 of '27.
Show source
Other key information: The income from previous periods, Q1 there was plus Rs. 8 crore and Q1 of '27 is Rs. minus 22 crore.
- Interest in the differential tariff decreased from Rs. 257 crore to Rs. 22 crore in Q1 FY27.
Show source
The interest in the differential tariff which I was saying so was from Rs. 257 crore stands at Rs. 22 crore.
- Consultancy revenue was Rs. 252 crore and telecom revenue was Rs. 391 crore in Q1 FY27.
Show source
On the consultancy and telecom front, the Q1 of FY27 stands at Rs. 252 crore and Rs. 391 crore, respectively.
- Depreciation and interest stood at about Rs. 330 crore in Q1 FY27, and interest owing to the differential between its filing and the CERC order date stood at about Rs. 230 crore.
Show source
B. Vamsi Rama Mohan: For Q1, depreciation and interest, which stands about Rs. 330 crore and owing to the interest because of the differential between our filing and also the CERC order date, that stands about Rs. 230 crore.
- POWERGRID says capitalization that occurred 12 years ago will have an impact because of the regulatory characteristics of the transmission industry.
Show source
B. Vamsi Rama Mohan: See, as you rightly said, what capitalization happened 12 years ago, that will definitely have an impact, because that is the characteristic of the industry itself, the transmission industry under the regulatory regime.
- POWERGRID said interest of Rs. 230 crore on the differential between CERC orders was no longer available, reducing profitability in Q1 FY27.
Show source
Like for example, the interest owing to the differential between the CERC orders standing at Rs. 230 crore is no longer available now.
- POWERGRID’s additional revenue from interest accrued during tariff-order delays was Rs. 230 crore in Q1 of '26 and '27; the component was significant in Q1 of the previous year, dwindled as the regulator issued orders, and is presently not significant.
Show source
So, presently, that component is not significant, so you find a variance between the Q1 of the previous year and Q1 of the current year to the extent of Rs. 230 crore for the Q1 of '26 and '27.
- The Rs. 230 crore difference between Q1 of the previous year and Q1 of the current year reflects interest revenue accrued during tariff-order delays, which dwindled as the regulator issued orders.
Show source
So, presently, that component is not significant, so you find a variance between the Q1 of the previous year and Q1 of the current year to the extent of Rs. 230 crore for the Q1 of '26 and '27.
- The Rs. 230 crore interest component was available to POWERGRID in Q1 last year, but is not presently available because CERC has issued the final orders.
Show source
So, there is a component of interest which is accrued to the developer, in this case as what I was saying Rs. 230 crore was the quantum which was available to us in Q1 last year.
- The differential between DOCO and the CERC order generated an interest-related revenue stream before the tariff order, creating an upside of about Rs. 230 crore in Q1 FY27.
Show source
That is what is visible to the extent of about Rs. 230 crore.
- POWERGRID's transmission lines increased by Rs. 788 crores in Q1 FY27.
Show source
Otherwise, the transmission lines have increased by Rs. 788 crores over here in this quarter.
- The about Rs. 247 crore additional PAT related to the combined trajectory of TBCB and RTM projects, with TBCB accounting for the lion's share.
Show source
The combination of both TBCB and the trajectory of the RTM projects put together, with the lion's share being that of the TBCB, yes.
- Capitalization was about Rs. 5,277 crore in Q1 FY27.
Show source
So, glad to inform as I was stating in my initial statements also, the quantum of capitalization which has happened in the Q1 stands about Rs. 5,277 crore.
- The dividend from Power Grid Corporation of India Limited's JV and subsidiaries was lower owing to the held-for-sale status of Torrent, Sikkim Power and Parbati Koldam.
Show source
The dividend from the JV and subsidiaries is less owing to the status of held for sale of Torrent, Sikkim Power and Parbati Koldam, so the figures reflect the situation over there.
- POWERGRID said a write-back on account of a particular asset class that was available in the previous quarter was not available in Q1 FY27, reducing profitability.
Show source
And also, the write-back on account of a particular asset class, which was there in the previous quarter, is not available over here.
- POWERGRID said the impact on its financials was mainly due to interest on the differential between CERC's orders and a write-back on account of one of the projects last year.
Show source
B. Vamsi Rama Mohan: Major impact is basically interest on the differential between the CERC's orders and also the write-back on account of one of the projects last year which has happened.
- POWERGRID said the impact was mainly due to interest on the differential between provisional and final. Replaced by a later filing.
Show source
But by and large, the impact is because of the interest on differential between provisional and final.
Money and capital
- The Government of India held about 51.34% of Power Grid Corporation of India Limited as of 30th June, 2026.
Show source
The market position, the shareholding of Government of India continues to be about 51.34%.
- The company had a market cap of Rs. 2.66 lakh crore, FII shareholding of 24.33% and DII shareholding of 20.70% as of 30th June, 2026.
Show source
Market cap Rs. 2.66 lakh crore, and the FII shareholding, DII shareholding at 24.33% and 20.70% respectively.
- Capex in Q1 FY27 was more than 10% of what it achieved last year in the quarter, against guidance of Rs. 37,000 crore.
Show source
The guidance what was given as Rs. 37,000 crore, we are pleased to inform that compared to last year, we have the capex is more than 10% what we have achieved in this quarter in Q1 itself.
- POWERGRID said the Rs. 13,000 crore of equity invested in the TBCB business for operational and under-construction projects was funded through internal accruals.
Show source
B. Vamsi Rama Mohan: Internal accruals.
- POWERGRID's operational TBCB investment increased from Rs. 4,671 crore last year to Rs. 9,965 crore.
Show source
This is the mainstay, as what you're saying, the lion's share of the projects presently are under the TBCB regime, and there is competition in terms of securing these projects.
- The company signed a green loan agreement of JPY80 billion with JBIC, riding on the subsidiary towards hedging which the Government of India has announced.
Show source
POWERGRID has signed a loan agreement with JBIC, signed a green loan agreement of JPY80 billion, riding on the subsidiary towards hedging which the Government of India has announced.
- POWERGRID said it is capable of funding its foreseen growth through its internal revenue mechanism.
Show source
POWERGRID has a strong internal revenue mechanism, and it is capable enough to take care of the quantum of growth what we are foreseeing.
What it expects ahead
What management expects
- POWERGRID has Rs. 300 crore of revenue that will start accruing when the regulator issues orders for deemed DOCO status for systems built under the regulatory tariff regime (RTM mode).
Show source
Management: Rs. 300 crore.
- The company expects neighbouring countries to get associated in strengthening the grid beyond the borders. Replaced by a later filing.
Show source
So, we expect that the neighbouring countries get associated in strengthening the grid beyond the borders.
- POWERGRID said the new requirements could give a further boost to transmission projects and make them happen faster. Replaced by a later filing.
Show source
So, this is going to give further boost, and it could be that much faster as well.
- Lower equipment prices would improve POWERGRID’s earnings. Replaced by a later filing.
Show source
While we would want and definitely, obviously, if the price is coming down, it will have a much better impact in terms of sweetening the revenues of POWERGRID in terms of the earnings of POWERGRID will be that much sweeter, as to be hoped.
Orders
- The company had won 6 transmission projects in inter-state and intra-state bidding by July 2026, with total gross annual tariff of about Rs. 2,200 crores.
Show source
Page 3 of 21 Power Grid Corporation of India Limited August 07, 2026 TBCB front, the competition if you are talking about, the success till July 2026 in inter-state as well as intra-state, 6 transmission projects altogether have been successfully won, with a total gross annual tariff about Rs. 2,200 crores.
- Of 19 projects bid during this period, Power Grid Corporation of India Limited was successful in 6, including an intra-state project; its cumulative performance was about 47% as far as ISTS goes.
Show source
The performance stands at about 47% cumulative as well as the ISTS goes, and including both inter-state and intra-state, total 19 projects were bid during this period, of which POWERGRID was successful in 6 projects.
Show 4 more statements
Orders
- Rs. 1.75 lakh crore of works in hand included TBCB of about Rs. 1.46 lakh crores, RTM of about Rs. 25,000 crore, and smart metering, data center and BESS business of about Rs. 4,200 crore; Rs. 50,000 crore was CWIP.
Show source
Total outlook for the sector, the value in terms of Rs. 1.75 lakh crore, which are the works in hand for POWERGRID, which includes both TBCB and RTM and others.
- Bidding pipeline was Rs. 1.19 lakh crore and its long-term outlook was about more than Rs. 15 lakh crore.
Show source
The bidding pipeline is also very strong in terms of Rs. 1.19 lakh crore, and the long-term outlook is also very secure, about more than Rs. 15 lakh crore, which is there.
- The company had Rs. 73,875 crore of projects under bidding and about Rs. 45,000 crore to be floated, totaling about Rs. 1.19 lakh crore in the bidding pipeline.
Show source
Bidding pipeline, under bidding, Rs. 73,875 crore, and which are to be floated are about Rs. 45,000 crore, with total projects which are to be under bidding in the pipeline about Rs. 1.19 lakh crore.
- Consultancy business received 16 domestic orders and 3 international orders in Q1 FY27, with a footprint in about 25 countries.
Show source
On the consultancy front, the domestic front we had 16 orders and on the international 3 orders, and the country footprint is about 25 countrie s what the consultancy footprint stands.
What it is building and selling
Projects and capacity
- The company commissioned about 1,635 circuit kilometers in Q1 FY27, almost 35% of last year's achievement in the first quarter of Q1.
Show source
The major elements which have been commissioned in the quarter FY27 are about 1,635 circuit kilometers and which is almost 35% of the last year's achievement in the first quarter of Q1, we achieved almost 35% of what we achieved last year.
- The company added about 10,500 MVA of transformation capacity in Q1 FY27.
Show source
The transformation capacity stands about 10,500 MVA.
- The company commissioned the 765 kV Kurnool III - Maheshwaram, 765kV Dausa - Beawar in Rajasthan, 400 kV new Navsari- Kala, and 400 kV Kadapa - Ananthapuram transmission lines in Q1 FY27.
Show source
The transmission lines which have been commissioned during this period are 765 kV Kurnool III - Maheshwaram, 765kV Dausa - Beawar in Rajasthan, a 400 kV new Navsari- Kala, 400 kV Kadapa - Ananthapuram again in Andhra Pradesh.
- The company added transformation capacity in Bikaner III substation, KPS3, Fatehgarh III and Padghe, and 400 kV systems in Jabalpur PS, Satna substation, Ananthapuram and Fatehgarh III in Q1 FY27.
Show source
The transformation capacity has been added in Bikaner III substation, KPS3, Fatehgarh III, Padghe, and the 400 kV systems include Jabalpur PS, Satna substation, Ananthapuram and Fatehgarh III.
- After June '26, Power Grid Corporation of India Limited completed the 765 kV Raichur-Koppal II PS line and 400 kV Gadag II-Koppal II PS in Karnataka, and 400 kV Bikaner II and Bikaner III in Rajasthan; these projects are by and large associated with RE generation in the respective states.
Show source
Added to this, after June '26, the major systems which have been completed are 765 kV Raichur-Koppal II PS line in the state of Karnataka, 400 kV Gadag II-Koppal II PS and that also is in the state of Karnataka, and 400 kV Bikaner II and Bikaner III in state of Rajasthan.
- POWERGRID said Rs. 1.19 lakh crore was standing immediately and Rs. 7.9 lakh crore was to be immediately bid out.
Show source
Immediately it is standing as Rs. 1.19 lakh crore, and Rs. 7.9 lakh crore is to be immediately bid out.
Show 22 more statements
Projects and capacity
- POWERGRID said the Rs. 7.9 lakh crore would be spread across another 3 years or so, as the systems are needed by '35, '36.
Show source
So, the Rs. 7.9 lakh crore would be spread across maybe another 3 years or so, because we need the systems by '35, '36.
- POWERGRID said its general estimates for the Rs. 7.9 lakh crore projects could reflect costs from any massive escalation during the period.
Show source
So, should there be a massive escalation, it obviously would get reflected in these costs.
- POWERGRID said the systems being planned reflect a growth trajectory aimed at achieving 900 GW non-fossil capacity by 2035-36.
Show source
As we move forward, we'll get more clarity on this, but these are the quantum of systems which would be coming up, keeping in view kind of the growth trajectory, achieving 900 GW non-fossil capacity by 2035-36.
- One HVDC project is already in POWERGRID’s pipeline, and another project is expected to gain traction by '27.
Show source
B. Vamsi Rama Mohan: See, as you're aware, one of the project of HVDC is already in the pipeline, and by '27, there's traction for another project to come into the pipeline over there.
- Almost 21 HVDC projects are under consideration depending on the evolution of generation and load centers; the 900 GW report of CEA includes about 14 HVDC projects and the Brahmaputra basin has about 6 HVDC projects.
Show source
And having said that, almost 21 HVDC projects are there depending upon the evolution of the generation and the load centers, because we need both the points for us to identify the projects.
- POWERGRID said Government of India land-compensation guidelines were not factored into the estimates, and the compensation amount could only be assessed after the MRC rate is finalized.
Show source
So obviously, this has not been factored while working upon the estimates, and it is presently not possible to actually even factor in the quantum because that would be emerging only once the MRC rate has been finalized.
- POWERGRID said the compensation impact could differ by project location, with high urban areas and rural areas having different impacts.
Show source
It could be project-specific, depending upon the location, high urban areas and rural areas, that would have a different impact.
- POWERGRID said states need time to settle on a mechanism for the MRC under the land-compensation guidelines, and that resolving the issue could make transmission-system construction faster.
Show source
So, as and when this particular issue is overcome, I'm sure it will be that much faster rather than we finding it difficult in building up transmission systems.
- POWERGRID said if the land-compensation guidelines are accepted and compensation is paid to landowners, they could ease implementation of transmission systems.
Show source
If these guidelines are well accepted Page 9 of 21 Power Grid Corporation of India Limited August 07, 2026 and it's translating into reality with the compensation duly being paid to the landowner, I'm sure it would be bringing that ease in implementing of the transmission systems.
- POWERGRID said right-of-way challenges remain, with increased urbanization and other infrastructure requiring coexistence while building systems for adequate evacuation in the country.
Show source
Having said that, the challenge of ROW is there, cannot be wished away.
- Initial bids for the Rajasthan Phase IV Barmer Complex HVDC project have been submitted and are being evaluated by the bid process coordinator; the bid process coordinator’s next steps are yet to be announced.
Show source
B. Vamsi Rama Mohan: The timelines are that these bids have been submitted, the initial offers have been submitted.
- International HVDC projects linking Sri Lanka, Andaman and Myanmar are under active consideration.
Show source
And the international HVDC projects linking Sri Lanka and Andaman and Myanmar, they also have actively under consideration.
- POWERGRID has discussed battery storage with the concerned RPCs in the Northern Region and Western Region, obtained their clearances and filed petitions before the regulator.
Show source
With the regulator coming out first with that regulation, the amendment which you are stating so, so we have already had discussions with the concerned RPCs at both at the Northern Region and the Western Region, and having their clearances, we moved forward and we submitted our petitions are also filed before the regulator.
- The company is implementing the Koppal, Gadag and Bidar-Maheshwaram projects, which are expected to be on par with other projects as they come into capitalization.
Show source
And we are also looking for good number of projects, that is the Koppal, Gadag and the Bi dar- Maheshwaram, these projects also will be on par, apart from other projects which we are implementing there.
- The company has achieved One Nation One Grid, One Frequency and describes One Sun, One World, One Grid as a future extension that would require integration with other countries and diplomatic relations.
Show source
One Nation One Grid, One Frequency, POWERGRID has already achieved that particular objective, and this would be the next extension what we need to reach out.
- Planners will examine the availability and timelines of HVDC projects and plan the systems accordingly; there is good traction for visible HVDC projects in the country. Replaced by a later filing.
Show source
So, there is good traction as far as the HVDC projects which are visible in the country.
Segments
- POWERGRID transmission charges are not governed by power flow; its tariff is in rupees per annum, not rupees per megawatt-hour, and its revenue is not linked to generation.
Show source
So, be rest assured that the revenue is not linked to the generation.
- For POWERGRID's TBCB projects, revenue starts flowing after deemed DOCO status applies following a specified period, without needing to go to the regulator.
Show source
And as far as TBCB goes, there is no such need to go to the regulator, and it is considered as deemed DOCO after a specified period, so the revenue starts flowing over there.
- Underutilization or generation not coming will not affect POWERGRID's revenues and earnings.
Show source
So, the generation not coming or being underutilized will not have an impact on the revenues of and the earnings of POWERGRID.
Deals and partners
- Subsidiary PowerTel provided connectivity to Andaman and Nicobar.
Show source
And on the telecom front, the connectivity to Andaman and Nicobar has also been provided by POWERGRID 's subsidiary, that is PowerTel.
- The company established its first international long-distance communication to Nepal, adding business to its telecom division.
Show source
The first international long -distance communication established to Nepal, so adding up more business to the telecom division.
- POWERGRID said it is giving manufacturers greater visibility through bulk procurement rather than project-specific procurements, building OEM confidence and encouraging capacity establishment; it said this was reflecting in better price discovery and timelines.
Show source
And looking into the POWERGRID, POWERGRID has taken an initiative of trying to give much more visibility to the manufacturers in terms of procuring it in bulk rather than project-specific procurements.
Risks, rules and outside factors
Outside factors
- Transmission investment drivers included plans of the CEA and the Ministry, the National Electricity Plan, an anchor program of 900 plus gigawatt by 2035-'36 involving Rs. 7.9 lakh crore, hydro potential in the northeast portion of Brahmaputra Basin of about Rs. 6.4 lakh crores, and data centers of about 71 GW.
Show source
The strategic drivers powering up the transmission system investment cycle, as you are aware, the plans of the CEA and the Ministry, the National Electricity Plan, the anchor program of 900 plus gigawatt by 2035-'36, Rs. 7.9 lakh crore, and the hydro potential in the northeast portion of Brahmaputra Basin, about Rs. 6.4 lakh crores. and the data centers emerging to be one of the strongest intake for the transmission systems to evolve, about 71 GW.
- POWERGRID’s equipment prices are quite stabilized, and management expects better progress on prices in the months to come; increased supply may reduce prices and availability timelines, while raw-material costs continue to affect equipment costs.
Show source
So, we see that the prices are quite stabilized over here, and in the year in the days or the months to come, we should see much better progress as far as the price go.
Rules and policy
- The Government of India revised transmission-line implementation timelines to about 26 to 30 months plus, after a private-party timeline of 18 months for a 765 kV double circuit line was recognized as impractical.
Show source
So now, Government of India has revisited these timelines and improved upon, which now stands about 26 to 30 months plus.
- The regulator recognizes the cost of debt as depreciation in the tariff and unwinds that cost over 12 years; after 12 years, the debt is supposed to be fully repaid and only the equity portion remains.
Show source
The trajectory of the tariff of the regulator is that they recognize the tariff towards the cost of loan, that is the cost of debt, they recognize it as depreciation, and they unwind that particular cost in 12 years.
- When there is a delay in the regulator issuing an order on POWERGRID’s tariff petition, POWERGRID is entitled to interest at SBI MCLR plus 150 basis points during the intervening period.
Show source
The second part of it is, as we file a petition towards the for the tariff, and if there is a delay in the issuance of the order by the regulator, then during the intervening period, there is an interest which is accrued to the company, POWERGRID, SBI MCLR plus 150 basis points is what we are entitled to receive during the period because the order has not come into position by the regulator.
- A recent amendment to the terms of tariff regulations provides for integrated storage systems such as batteries to be developed by transmission developers including POWERGRID; POWERGRID has filed petitions before the regulator after obtaining consent from the Northern and Western Region RPCs, and is working on BESS storage systems under section 62 of the Electricity Act, subject to traction from other stakeholders.
Show source
So, POWERGRID is also working upon this very clearly, I mean very intensely, and we have also filed petitions before the regulator after obtaining the consent from the Northern and the Western Region RPCs.
Show 3 more statements
Rules and policy
- The Government of India has allowed 4 companies within the country following a recent notification, and POWERGRID will adhere to Government of India guidelines when procuring equipment from neighbouring countries where it has options.
Show source
B. Vamsi Rama Mohan: See, as you're aware, with the recent notification, 4 of the companies within the country have been allowed by the Government of India.
- Foreign exchange losses in POWERGRID's regulatory account can be passed through under the regulated regime.
Show source
B. Vamsi Rama Mohan: Pass through.
- Extensions to Power Grid Corporation of India Limited's existing substations are considered by the NCT; implementation may be assigned under RTM to the regulated entity or entity that owns the asset class, or may be awarded through bidding.
Show source
They look forward to the best way of implementing it, and at times it is given to the regulated entity who is already there, or the entity who is already owning that asset class over there, so he is given the opportunity to undertake this under the RTM.
Everything else said on the call
Other
- POWERGRID will examine whether to improve disclosure so investors can better analyse its performance. Replaced by a later filing.
Show source
We will do that.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
Question
Apoorva Bahadur: Hi, sir. I hope I am audible. This is Apoorv a from IIFL Capital. Thank you for the opportunity. Sir, you touched upon this on the drag which is coming from decline in depreciation, normative depreciation, as well as some regulatory differences. Would be helpful if you can quantify this drag in deprec iation and its impact on revenue. How much would that be for this quarter?
Answer, b mohan
B. Vamsi Rama Mohan: For Q1, depreciation and interest, which stands about Rs. 330 crore and owing to the interest because of the differential between our filing and also the CERC order date, that stands about Rs. 230 crore. So, it would be about Rs. 560 crore the drag on account of the regulatory characteristic. Page 6 of 21 Power Grid Corporation of India Limited August 07, 2026 Apoorva Bahadur: Okay, okay, sir.
Question
And how do we see this, sir, going ahead, especially because I think depreciation probably will pick a little bit more pace? I recall in the last cycle we added a lot of capacity around 2014, '15, '16 that time, so that would be completing 12 years. How should we think about that, sir?
Answer, b mohan
B. Vamsi Rama Mohan: See, as you rightly said, what capitalization happened 12 years ago, that will definitely have an impact, because that is the characteristic of the industry itself, the transmission industry under the regulatory regime. So, this is the quantum of capitalization what has happened in the previous 12 years, it would have an impact. But then that is a part of the regulatory characteristic, so that should not be a cause of concern because that is the way how the revenues and the expenses are taken care of.
Question
Apoorva Bahadur: Sir, if I'm not wrong, this should have been profit neutral, right? Because there's a reduction in revenue and a reduction in the expense as well. Yet, I believe it had an impact on profitability. Could you help us sort of reconcile that, because despite the Rs. 28,000 crore capitalization last year, profits have remained largely flat.
Answer, b mohan
B. Vamsi Rama Mohan: Yes. One is that certain components, which otherwise were available in the previous quarters, some couldn't have been available. Like for example, the interest owing to the differential between the CERC orders standing at Rs. 230 crore is no longer available now. And also, the write-back on account of a particular asset class, which was there in the previous quarter, is not available over here. So, this has an effect of bringing it down. Added to that, Sudharshan, you may add to this. The depreciation what is being accounted for as well as the tariff which is there, there would be always a differential in that.
Answer, b mohan
Management: Yes sir, that also is having a marginal difference in depreciation and interest because it will not match what is the notional what has taken in the regulation. Because of that, there is a marginal impact, marginal impact. But by and large, the impact is because of the interest on differential between provisional and final.
Answer, b mohan
B. Vamsi Rama Mohan: Major impact is basically interest on the differential between the CERC's orders and also the write-back on account of one of the projects last year which has happened. So, that differential is actually what is visible on the financials.
Question
Apoorva Bahadur: Understood. And sir, just one last question. If you can share, of the Rs. 13,000 crore of equity which we have invested in the TBCB business so far for both operational and under-construction projects, how much of that would have been funded by taking debt at the standalone or parent level or is it all of it is through equity itself or cash? Management: All of it is through equity only. Internal accruals.
Answer, b mohan
B. Vamsi Rama Mohan: Internal accruals. POWERGRID has a strong internal revenue mechanism, and it is capable enough to take care of the quantum of growth what we are foreseeing.
Question
Apoorva Bahadur: Sure, sir. Understood. Thanks a lot. All the best. Page 7 of 21 Power Grid Corporation of India Limited August 07, 2026 B. Vamsi Rama Mohan: Thank you.
Answer, b mohan
B. Vamsi Rama Mohan: This one, I should say that is kind of a medium part. Immediately it is standing as Rs. 1.19 lakh crore, and Rs. 7.9 lakh crore is to be immediately bid out. Based upon the traction what we are receiving, there is going to be continuous inflow of projects into the system. So, the Rs. 7.9 lakh crore would be spread across maybe another 3 years or so, because we need the systems by '35, '36. The next 3 to 4 years this will have to be spread across. So, that the systems will have to be available in '35, '36. So, considering about 2 to 3 years of the construction period, so these projects should be visible, should be on bar in the next 3 to 4 years.
Answer, b mohan
But having said that, it will be by and large dependent upon the others also because transmission is an offshoot of generation. So, the quantum of generation coming up, not only generation, understand, here it would be the data centers, the green hydrogen, these are new set of requirements where it is going to push the transmission system, not limited to merely a generator, it also has a new specific loads which are coming in terms of green hydrogen, data center, green ammonia, and we already see few of the projects already taking position in terms of the eastern and western parts of the country. So, this is going to give further boost, and it could be that much faster as well. Bharanidhar: Understood. Related to the same thing, is inflation and other cost escalation built in this estimate by the government or is there a scope for increase in this total Rs. 7.9 lakh crore in the future?
Answer, b mohan
B. Vamsi Rama Mohan: See, these are general estimates. Obviously, it would be difficult to factor in the quantum of escalations what would be happening during this period of time. So, should there be a massive escalation, it obviously would get reflected in these costs. Bharanidhar: So, there is a scope for increase in this number. Okay. And again, related to the same Rs. 7.9 lakh crore number, just to clarify, this will also include cost of acquiring land, right? And if so, whether the new land rates according to the new guidelines by Ministry of Power, the last 1 year, 2 years, is it been incorporated or you think that will also, result in some scope increase in the cost because it may not have been included?
Answer, b mohan
You see, these guidelines which have been notified by the Government of India regarding the land compensation in terms of the right of way challenges what we have witnessed in the transmission line, few of the states, initially it was Delhi and Haryana who have adopted it. You see recently Gujarat also adopting it, and other states following suit. So obviously, this has not been factored while working upon the estimates, and it is presently not possible to actually even factor in the quantum because that would be emerging only once the MRC rate has been finalized. So, as we move forward, we get more clarity as to what extent of compensation would be included in these systems. It could be project-specific, depending upon the location, high urban areas and rural areas, that would have a different impact. As we move forward, we'll get more clarity on this, but these are the quantum of systems which would be coming up, keeping in view kind of the growth trajectory, achieving 900 GW non-fossil capacity by 2035-36. Bharanidhar: Understood.
Answer, b mohan
B. Vamsi Rama Mohan: Sure. Earlier, as you recall, the timeline taken for a transmission line was about 36 to 40 months. Subsequently, there was a lot of demand that from the private parties that they would be implementing the systems in much tighter timelines, and it has gone to the extent of 18 months was the timeline given to a 765 kV double circuit line, which is quite a challenging timeline. So, over a period of time, it has been now recognized and realized that these timelines are not practical in terms of implementing transmission systems. So now, Government of India has revisited these timelines and improved upon, which now stands about 26 to 30 months plus. So, this is going to make sure that whatever projects are there are having adequate timeline for them to implement. So as far as the policy goes, yes, it has been recognized that transmission lines do take time in terms of implementing them.
Answer, b mohan
The second part of it is the land compensation with the guidelines coming in and with the states taking forward, few of the states taking over, there will be some settling time for them to actually arrive at the mechanism for the MRC. There could be nuances in each of the state as to how they would be dealing it. So, as and when this particular issue is overcome, I'm sure it will be that much faster rather than we finding it difficult in building up transmission systems. If these guidelines are well accepted Page 9 of 21 Power Grid Corporation of India Limited August 07, 2026 and it's translating into reality with the compensation duly being paid to the landowner, I'm sure it would be bringing that ease in implementing of the transmission systems. Having said that, the challenge of ROW is there, cannot be wished away. With more increased urbanization, increased other infrastructures coming into the picture, so we will have to coexist and build these systems to ensure adequate evacuation in the country. Bharanidhar: Sure.
Answer, b mohan
B. Vamsi Rama Mohan: Equipment supply, with the high-intensity growth in this sector, obviously the existing capacities at times have a challenge in trying to provide the supplies. And looking into the POWERGRID, POWERGRID has taken an initiative of trying to give much more visibility to the manufacturers in terms of procuring it in bulk rather than project-specific procurements. This has given the confidence to the OEMs, so they have started establishing good quantum of capacities, which I'm sure is now reflecting in terms of better discovery of prices and also better timelines. And eventually, it is going to be doing good to the sector, so the stress on the equipment supplies which was there some time back should not be as much what it was before. So that is going to ease. Bharanidhar: So, you're telling that the equipment supply challenge we had in high-capacity transformers or GIS substations is significantly lesser now?
Answer, b mohan
B. Vamsi Rama Mohan: This will be-- Yes, it would not be as bad as what it was before because the manufacturers are also now ready to take on the additional capacity requirements. So, there is ramping up capacity in the country as well, so that is going to do a lot of good to the sector in terms of timely availability of the equipment. Bharanidhar: And obviously because government has recently allowed few Chinese companies also to be able to bid, that will also probably ease the equipment supply starting, right?
Question
Ketan Jain: Hi, good morning, sir. My name is Ketan, I'm from Avendus Spark. So, wanted to double-check on a follow-up question from previous participant. On the difference in tariff from CERC and our filing, what is the reason behind this? Is it that CERC has not approved some of our expenses? Page 10 of 21 Power Grid Corporation of India Limited August 07, 2026 B. Vamsi Rama Mohan: No, I think I should put some clarity over here.
Answer, b mohan
The trajectory of the tariff of the regulator is that they recognize the tariff towards the cost of loan, that is the cost of debt, they recognize it as depreciation, and they unwind that particular cost in 12 years. That's the nature of the tariff what the regulator gives. After 12 years, the entire debt is supposed to be done away with, and then it's only the equity portion. So, the characteristic of the tariff in itself will fall down after 12 years because the component towards the repayment of the loan is to be addressed within that time. So that is the way how the tariff has been governed. So that is one part, the trajectory of the tariff of the regulator. The second part of it is, as we file a petition towards the for the tariff, and if there is a delay in the issuance of the order by the regulator, then during the intervening period, there is an interest which is accrued to the company, POWERGRID, SBI MCLR plus 150 basis points is what we are entitled to receive during the period because the order has not come into position by the regulator.
Answer, b mohan
So, all of that is also an additional revenue which comes into POWERGRID. As and when the orders are issued by CERC, that particular component obviously wouldn't exist. Such component was significantly available for us in Q1 in the previous year. And as the year progressed, the orders started being issued by the regulator, so that particular component dwindled. So, presently, that component is not significant, so you find a variance between the Q1 of the previous year and Q1 of the current year to the extent of Rs. 230 crore for the Q1 of '26 and '27. So, this is the nature of the regulatory regime which we are bound with. There is no other concern in terms of regulator not allowing any tariff and all, absolutely there's no such issue.
Answer, b mohan
The time taken by the regulator, because he's also stressed with a good number of petitions, and he has a cycle to dispose them off, but during that period, he makes sure that the developer is not at loss. So, there is a component of interest which is accrued to the developer, in this case as what I was saying Rs. 230 crore was the quantum which was available to us in Q1 last year. But as the year progressed, CERC started giving the orders, because their cycle will have to come through, so presently that particular revenue provision is naturally not available now. We get the orders, the final orders are already on the board.
Question
Ketan Jain: Understood. Thanks for your elaborate answer. So, if I understand, if I have to calculate the adjusted profit, I need to add Rs. 230 crore to the Q1 FY27 profit and also adjust the base for the writing back of any liability. What was that amount, sir?
Answer, b mohan
B. Vamsi Rama Mohan: Rs. 33 crore which was available in the last quarter is not available to-- there was one provision of write-in of a particular company. KSK Mahanadi? KSK Mahanadi. That's not available. Page 11 of 21 Power Grid Corporation of India Limited August 07, 2026 Ketan Jain: So, to calculate the adjusted profit, I should reduce the base profit by Rs. 33 crore and increase the current profit to by Rs. 230 crore.
Question
Atul Tiwari: Yes, sir. Sir, this is Atul here from J.P. Morgan. Sir, my question is on again on equipment supply status. So, especially for some equipment like transformers, the industry had seen quite a bit of increase in price rise over past few years because of a lot of ordering. But now has the situation started to normalize and are the prices stable and are they coming down? Because we gather that a lot of capacity is being added by vendors, which you also alluded to. And does it have a scope for reducing, at least to some extent, the cost of implementing the projects?
Answer, b mohan
B. Vamsi Rama Mohan: Yes. As far as the increase in capacity as the nature or the law goes, with more players, more capacity in supplies, obviously it would have it will be having a reducing impact on the both the price as well as the timelines, availability of the systems. But having said that, the raw material, which is required for the transformers and all, that is the factor which will continue to impress upon the costing of this equipment over here. A combination of increased supplies and a combination and the raw material costs would have an eventual impact on the price line of those equipment. So, we see that the prices are quite stabilized over here, and in the year in the days or the months to come, we should see much better progress as far as the price go. While we would want and definitely, obviously, if the price is coming down, it will have a much better impact in terms of sweetening the revenues of POWERGRID in terms of the earnings of POWERGRID will be that much sweeter, as to be hoped.
Question
Atul Tiwari: And sir, what is the status of the award of Rajasthan Phase IV Barmer Complex HVDC project? What are the timelines here?
Answer, b mohan
B. Vamsi Rama Mohan: The timelines are that these bids have been submitted, the initial offers have been submitted. They're being evaluated by the bid process coordinator. And the next steps as what the BPC will have to take will have to be announced. So, the bids have been su bmitted. That's the status.
Question
Jinesh Karia: Yes, thank you for the opportunity, sir. So, you have mentioned a very strong pipeline going ahead from the Brahmaputra basin RE requirement, data center, GH2 opportunity. Any thoughts on how can we see the HVDC pipeline for the next 3 to 5 years? And any thoughts on whether we can have preponement of any of the capex that we have mentioned beyond '35, any thoughts on that? That is the first question.
Answer, b mohan
B. Vamsi Rama Mohan: See, as you're aware, one of the project of HVDC is already in the pipeline, and by '27, there's traction for another project to come into the pipeline over there. We look forward for that. And having said that, almost 21 HVDC projects are there depending upon the evolution of the generation and the load centers, because we need both the points for us to identify the projects. So, the 900 GW report of CEA has about 14 HVDC projects and the Brahmaputra basin has about 6 HVDC projects. And the international HVDC projects linking Sri Lanka and Andaman and Myanmar, they also have actively under consideration. Depending upon the evolution of the technology, the ease in availability of these systems and the costing of these systems will have an impact in the planner deciding to go towards the HVDC. To tilt towards HVDC, we need to have the availability of because they have a long gestation period, these HVDC projects, and also they have significant costs.
Answer, b mohan
So, the planner will have to carefully examine the availability of the these projects and their requisite timelines and accordingly plan these systems. So, there is good traction as far as the HVDC projects which are visible in the country.
Show 12 more questions
Question
Jinesh Karia: Got it, sir. So, like you mentioned cost overruns would one be one of the factors that to determine the timing and quantum of HVDC projects, any thoughts on how BESS as a system would play a role in the upcoming 5 years? Given rising side pressure from OEM capacity coming in might go down, but commodity inflation from for the OEMs' raw material can still drive up the pricing. So, any thoughts on HVDC being complemented with BESS or getting converted through BESS to some other technology? Any thoughts on that front? And just to follow up on that, what kind of equipment would we or any other transmission player would be procuring from Chinese OEMs who have received approvals from
Answer, b mohan
B. Vamsi Rama Mohan: Yes, multiple questions over here, I should say. The replacement of HVDC with a BESS, as I don't think so it would be exactly so in that manner. BESS has its own utility and HVDC comes with its own utility part. So, these two components in the planner planning part will be taken by the planner and CEA put together. They will be seeing because it is not a static scenario. Page 13 of 21 Power Grid Corporation of India Limited August 07, 2026 What we need to appreciate is that the power sector is not a static scenario, with more generation coming in different locations, more data centers, or more loads having in different positions, this is continuously dynamic in nature. So, given the situation, given the costing of these systems, BESS, HVDC, and other alternative systems, including 1,200 kV HVAC systems, all these things are actively considered before finalizing upon that particular component which will have to be taken up, which is most suitable at that point of time.
Answer, b mohan
So, this the planner will evolve, and I'm sure that they are looking at it. Having said that, on the BESS front, the regulator also has recently come up with an amendment to the terms of tariff regulations, under which he's expecting that the integrated storage systems, that is the batteries or such kind of a systems, are given a provision that even the transmission developer like POWERGRID also can develop. So, POWERGRID is also working upon this very clearly, I mean very intensely, and we have also filed petitions before the regulator after obtaining the consent from the Northern and the Western Region RPCs. So, this is another opportunity for POWERGRID also to work into the BESS storage systems under the regulatory portion, that is under section 62 of the Electricity Act. So, we are working on that as well, but this largely depends upon the traction what is being given by the other stakeholders.
Question
Jinesh Karia: Thanks, and just if you could just follow up on the Chinese OEMs, the equipment that we plan to purchase, the kind of equipment which we plan to purchase from the Chinese OEMs who have received approvals.
Answer, b mohan
B. Vamsi Rama Mohan: See, as you're aware, with the recent notification, 4 of the companies within the country have been allowed by the Government of India. Having said that, POWERGRID continues to be in adherence to the guidelines what are notified by the Government of India from time to time, and to the extent whatever we have the options for procuring these equipment from the neighbouring countries, POWERGRID will be adhering to that.
Question
Sumit Kishore: Thanks for the opportunity. My question is the equity investment in operational TBCB projects has gone up from Rs. 4,671 crore last year to Rs. 9,965 crore. Could you give us a sense, given TBCB is the main driver of growth, I mean what is the colour that you can provide us on the consolidated performance of TBCB in terms of revenue, EBITDA and PAT? And also give us a sense on what kind of return on the invested equity in operational TBCB projects you have been able to secure? Page 14 of 21 Power Grid Corporation of India Limited August 07, 2026 B. Vamsi Rama Mohan: The operational part associated in TBCB operational has moved from Rs. 4,671 to Rs. 9,965.
Answer, b mohan
This is the mainstay, as what you're saying, the lion's share of the projects presently are under the TBCB regime, and there is competition in terms of securing these projects. Obviously, we need to tread a path of both growth and profitability, and POWERGRID is continuing to make sure that there is both growth and profitability in its endeavours whatever we are doing. And then the returns are also, if that is the specific question, I should say returns are also well- calibrated to make sure that the investor is comfortable with those returns. Because it's not one single project which will be determining it. It's multiple projects. Each of the project comes with its own nice piece, and after execution, the quantum and the quantum of claims which are there, all of this put together will be giving the effective returns, and POWERGRID is well safe and also making sure that all the returns are well within the interests of the shareholders.
Question
Sumit Kishore: One request here is that because your business growth is largely driven by TBCB now, could you make a separate disclosure in terms of what the consolidated, you know, contribution from TBCB projects is to the P&L? That is the main growth driver for the company. So, what is the consolidated revenue, consolidated EBITDA, consolidated profit for TBCB, that will help us analyse the company better. There are periodical, you know, regulatory adjustments which anyway are in a business where the pace of growth has slowed down quite considerably. But we are not able to appreciate your results, given the key underlying driver of growth, the transparency on the disclosures is not allowin
Answer, b mohan
B. Vamsi Rama Mohan: I do appreciate the concern. In fact, it is an equal concern from my side as well, that you need to appreciate certain regulatory pulls or pushes actually impacts the POWERGRID 's financials. I think we will examine that, and with these kind of meets or such other platforms which are there or maybe better disclosures, we will try to make sure that this is properly reaching out to the analysts and the investors alike, so that they continue to appreciate and have confidence on the company as to how we are moving forward. We will examine that. Management: So as per the regulator, what we have to disclose, we have already disclosed.
Answer, b mohan
B. Vamsi Rama Mohan: We will examine that. We will do that. Thank you so much for that particular insight. We are also equally concerned that the true reflection of what we are performing should be there with the investors so that they can analyse us that much better. As we have seen during these discussions, the primary concern was their inability to judge that there is a regulatory drag, which is but very natural and nothing much cause of concern, as what is happening there, which I've already explained in my previous statements.
Question
Sumit Kishore: Just one more question. Given the nature of capacity addition is more leaning towards solar, and could you give us a sense of, are there any major transmission lines of POWERGRID which are grossly underutilized at the moment because renewable projects have not come up, and POWERGRID transmission lines have got commissioned? And in those cases, are you facing any challenges in terms of, you know, both operationally and recovering your dues from customers? Page 15 of 21 Power Grid Corporation of India Limited August 07, 2026 B. Vamsi Rama Mohan: Okay.
Answer, b mohan
I should say the extent of the transmission charges of POWERGRID are not governed by the power flow. So, it is not that only power flows POWERGRID starts getting its revenue. So , meaning that it is quite safe that once we commission the asset, the revenue starts flowing. Whatever the mechanisms what the regulator has identified, so there are provisions where we continue to get our tariff. So, my tariff is not rupees per megawatt-hour, it is rupees per annum. So, be rest assured that the revenue is not linked to the generation. But having said that, definitely it is a cause of concern in case if the generator has not come on time, the load is not there on time.
Answer, b mohan
So, the picture we bifurcate two parts. One part is that the systems which are built under the regulatory tariff regime, that is the RTM mode, we need to go to the regulator and get the clearance for the deemed DOCO status. So, we have a good amount of revenues which will also flow as and when the regulator gives the orders. So that revenue also will start accruing now. So, it's to the extent of, what is that amount? Management: Rs. 300 crore.
Answer, b mohan
B. Vamsi Rama Mohan: Rs. 300 crore of revenue. So, these are these are regulatory, so as and when the regulatory regulator starts hearing these petitions, that revenue also will start accruing. And as far as TBCB goes, there is no such need to go to the regulator, and it is considered as deemed DOCO after a specified period, so the revenue starts flowing over there. So, the generation not coming or being underutilized will not have an impact on the revenues of and the earnings of POWERGRID. Sumit Kishore: No. Thank you so much.
Question
Satyadeep Jain: Okay, because just trying to correlate Rs. 2,200 crores annual revenue seems large, given typically historically revenue by gross block numbers. Just I'll maybe take it offline on the NCT cost estimate. Also, the CERC notification back in March had suggested that, and which was also one of the things you noted on regulated ROE on transmission projects …. sorry Not Transmission, BESS projects. BESS is also now part of transmission elements. So, when do you realistically expect to get some BESS projects awarded to you on regulated return basis? Is there any visibility you have that you expect some sizable work in hand from that? Page 16 of 21 Power Grid Corporation of India Lim
Answer, b mohan
With the regulator coming out first with that regulation, the amendment which you are stating so, so we have already had discussions with the concerned RPCs at both at the Northern Region and the Western Region, and having their clearances, we moved forward and we submitted our petitions are also filed before the regulator. So, we have to understand any new system which is coming, there will be a lot of challenges in trying to do it. There will be some settling time for this particular concept. The battery is not considered as transmission element, as what you are saying, it is considered as that element whoever is doing it. If the generator is doing it, it's considered as a generation element. Where the transmission, it's a transmission element. But this regulation has actually allowed a transmission company to get into the integrated storage business, that is battery included.
Answer, b mohan
So, POWERGRID has already taken initial actions, and we have moved very fast in terms of about a couple of months, it has taken 2 to 3 months after the regulation where we could also reach out to the stakeholders in the RPCs and also then file the petition before the regulator. Having said that, we will have to await the regulator's position what he would like to look into it, and the other stakeholders. Then it will mature. Once it is so, we will obviously come forward and let you know what the status is. But the present status is we have already moved forward. We have done all the groundwork, all the homework is done, and we already filed the petitions. So, just this is as per the procedure of the regulation itself.
Question
Satyadeep Jain: Okay. So just one quick question on the profitability for this quarter. So, previous participant also alluded, you mentioned there was interest accrued while you're waiting for tariff of about Rs. 200 crores. Now that you've got the tariff, it seems I'm not sure on a Y-o-Y basis that should impact your profitability comparison too much, but there is some forex impact also. Just wanted to see, are you able to pass that on? And because we're not able to see PAT growth, does that otherwise mean that the TBCB projects you commissioned, which is also what the previous participant was asking, that in the first year you don't have much PAT from the entire TBCB projects you commissio
Answer, b mohan
B. Vamsi Rama Mohan: The tariff continues to accrue the entire year after the CERC order comes over there. But until then, there is a revenue stream which comes owing to the interest because of the differential between the DOCO and the CERC order. That is the reason there is a n upside. Obviously, when we compare with that upside with any other figure, there would be a difference. That is what is visible to the extent of about Rs. 230 crore. On the capitalization which has occurred, the transmission charges should have gone up to Rs. 788 crore, as far as the earnings go, on the top line should have gone by Rs. 788 crore, owing to the transmission lines which have been commissioned, and correspondingly, the PAT should Page 17 of 21 Power Grid Corporation of India Limited August 07, 2026 have been about Rs. 247 crore also that should have moved up. But for the regulatory drag, which is an inherent and a natural way how the regulator's assets all these years which is moving, that is visible here, which is actually bringing it down to the numbers what you're seeing.
Answer, b mohan
Otherwise, the transmission lines have increased by Rs. 788 crores over here in this quarter.
Question
Satyadeep Jain: You're saying Rs. 247 crore additional PAT from all the TBCB projects commissioned in the last one year, is that what you're saying?
Answer, b mohan
B. Vamsi Rama Mohan: Not limited to TBCB. The combination of both TBCB and the trajectory of the RTM projects put together, with the lion's share being that of the TBCB, yes.
Question
Satyadeep Jain: Okay, so in the FX losses that you had in the regulatory account, what is, are you able to pass that on? Is that also one-off or there was some pass through?
Answer, b mohan
B. Vamsi Rama Mohan: Pass through. Can be passed. It's well taken care of because the regulated regime has that particular comfort which provides to the developers.
Question
Satyadeep Jain: Got it. Thank you so much.
Answer, b mohan
B. Vamsi Rama Mohan: Yes. The transmission systems are not coming, unlike other businesses which have a cycle of every quarter or every year, the transmission systems do have a cycle based upon the timeline given for implementation over there, taking into account the ROW challenges. So, glad to inform as I was stating in my initial statements also, the quantum of capitalization which has happened in the Q1 stands about Rs. 5,277 crore. And we are also looking for good number of projects, that is the Koppal, Gadag and the Bi dar- Maheshwaram, these projects also will be on par, apart from other projects which we are implementing there. So, as we move forward, the projects come into capitalization, and I'm sure that this number would be that much steadier and improve. Dhruv: Sure, sir. So, the second thing is, I was trying to do a consol minus standalone, trying to imply the TBCB numbers largely.
Question
Mohit Pandey: Yes, good afternoon, sir. Sir, my question is on grid strengthening projects. So, I understand there will be incremental projects for strengthening the existing grid as renewables penetration increases, for example, for adding energy. So, in cases where we already have, we are the owners of the assets, will those strengthening projects come to us on regulated mode or will they typically be via TBCB? And whether these projects are already a part of the Rs. 7.9 lakh crore pipeline? That would be the first question. Page 19 of 21 Power Grid Corporation of India Limited August 07, 2026 B. Vamsi Rama Mohan: All projects which have to come are obviously in the pipeline only, whether
Answer, b mohan
And as far as the existing systems, substations what we have, should there be any extensions which will have to be done there, this is taken care by the NCT. They look forward to the best way of implementing it, and at times it is given to the regulated entity who is already there, or the entity who is already owning that asset class over there, so he is given the opportunity to undertake this under the RTM. And sometimes we see that it is also given under the bidding route, which is a combination of both these things. There's no specific rule as to how it happens, we have seen both these things happening. It's no specific way.
Question
Mohit Pandey: Understood, sir. Sir, and on the One Sun, One World, One Grid, when do we realistically see projects or any sense on that?
Answer, b mohan
B. Vamsi Rama Mohan: Obviously, we need to, as we have evolved from a state to a region and region to a country, so the more we are integrated, the better we are in terms of utilizing the resources that much more effectively. So going beyond the country, it does have an additional component to tide over. We need to bridge that gap with the diplomatic relations with that country. If that is done, this would be one of the finest ways in terms of integrating the, because the telecom network has already been integrated, as you see the entire world is now under one internet. So eventually, as we move forward, this should be the answer so that the ups and downs which are there in a typical sector are well taken care of, and it should move forward, this particular concept of One Sun, One World and One Grid. One Nation One Grid, One Frequency, POWERGRID has already achieved that particular objective, and this would be the next extension what we need to reach out. So, the moment one or two countries we are able to integrate, which other countries are doing elsewhere in the world, so we are going to stitch this particular network across the world.
Questions about this call
- When was the Power Grid Corporation of India Q1 FY27 earnings call transcript filed?
- Power Grid Corporation of India filed the transcript with the exchange on 14 Aug 2026. This page is built from that transcript.
- What does this page list?
- 87 statements from the transcript across 10 topics, 57 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- Yes. 22 questions and management's answers are listed in the order they were asked, as the transcript prints them.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.