Earnings call
Power Grid Corporation of India Q3 FY25 earnings call: Up to Q3, Power Grid had a 50% share in annual tariff, a 58% share in NCT cost and a 57% share in number of TBCB projects won
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
Up to Q3, Power Grid had a 50% share in annual tariff, a 58% share in NCT cost and a 57% share in number of TBCB projects won. Power Grid has a target of 50% renewable energy consumption by 2025. Power Grid had 1,518 transmission lines, 1,79,594 circuit kilometres of transmission lines, 280 substations and 5,52,961 MVA capacity. Power Grid's transmission system availability was 99.81% for the last nine months. Power Grid signed its first Green Loan Agreement for $200 million with Sumitomo Mitsui Banking Corporation, Japan, to fund Power Grid RE projects.
The numbers management gave
Results
- Power Grid's transmission system availability was 99.81% for the last nine months.
Show source
Our transmission system availability is maintained at par with world best utilities, and it is 99.81%.
- Power Grid commissioned 1,399 circuit kilometres of transmission lines and 9,185 MVA transformer capacity in Q3 and Nine Months ended 31.12.2024.
Show source
We have commissioned 1,399 circuit kilometre of transmission lines in Q3 and also 9,185 MVA capacity of transformers.
- Power Grid's project execution expenditure in Q3 and Nine Months ended 31.12.2024 was ₹7,649 crores, compared with ₹3,444 crores in FY '24.
Show source
Then in project execution, our performance in Q3 we have done expenditure of ₹7,649 crores as against ₹3,444 crores in last year, FY '24.
- Power Grid's CapEx for the last nine months was ₹17,651 crores, compared with ₹7,690 crores last year.
Show source
And during last nine months, our CapEx has been ₹17,651 crores as against ₹7,690 crores last year.
- Power Grid capitalised assets worth ₹3,417 crores in Q3, compared with ₹1,784 crores in Q3 last year.
Show source
In capitalisation also in Q3, we have capitalised assets worth ₹3,417 crores as against ₹1,784 crores asset in last year.
- Power Grid commissioned ₹7,423 crores worth of assets in the last nine months, compared with ₹5,780 crores last year.
Show source
And in the last nine months, we have commissioned ₹7,423 crores worth assets as compared to ₹5,780 crores last year.
Show 43 more statements
Results
- Power Grid had 0.24 trippings per line during the last nine months.
Show source
And in reliability, trippings per line is 0.24 trippings per line during the last nine months.
- Power Grid's standalone income and profit after tax in Q3 and Nine Months ended 31.12.2024 were ₹11,609 crores and ₹3,894 crores, respectively.
Show source
On a standalone basis, our income in Q3 has been ₹11,609 crores and profit after tax ₹3,894 crores.
- Power Grid's consolidated income and profit after tax in Q3 and Nine Months ended 31.12.2024 were ₹11,743 crores and ₹3,862 crores, respectively.
Show source
On a consol basis, income is ₹11,743 crores and PAT ₹3,862 crores.
- Power Grid's standalone transmission charges, consultancy, other income and total income for nine months were ₹30,092 crores, ₹357 crores, ₹3,394 crores and ₹33,843 crores, respectively; profit after tax was ₹11,017 crores.
Show source
For the last nine months, on a standalone basis, total income is ₹33,843 crores and PAT ₹11,017 crores.
- Power Grid's consolidated transmission charges, consultancy services, telecom and other income for nine months in FY '25 were ₹32,368 crores, ₹427 crores, ₹722 crores and ₹1,352 crores, respectively; total income was ₹34,869 crores, EBITDA was ₹30,148 crores and profit after tax was ₹11,379 crores.
Show source
On consol basis, total income for last nine months was ₹34,869 crores and the profit after tax ₹11,379 crores.
- Power Grid's earnings per share were ₹12.23 per share and book value per share was ₹98.51.
Show source
Earnings per share, ₹12.23 per share.
- Power Grid's debt-equity ratio was 59:41 and return on net worth for nine months was 12.42%.
Show source
Debt-equity ratio 59:41 and return on net worth in nine months is 12.42%.
- Power Grid's income for previous periods was ₹63 crores, compared with ₹237 crores in Q3 last year.
Show source
The key financial parameters, the income for previous periods, ₹63 crores as against the last year in Q3, ₹237 crores.
- Power Grid's interest on differential tariff was ₹102 crores in Q3, compared with ₹184 crores during Q3 quarter of '24.
Show source
Interest on differential tariff is ₹102 crores as against ₹184 crores during Q3 quarter of '24.
- Power Grid's interest from subsidiaries was ₹560 crores, compared with ₹371 crores last year.
Show source
Interest from subsidiaries, ₹560 crores as against ₹371 crores last year.
- Power Grid's incentive from transmission assets was ₹150 crores, compared with ₹151 crores.
Show source
Incentive from transmission assets, ₹150 crores as against ₹151 crores.
- Power Grid's dividend from JVs was ₹3 crores, compared with ₹1 crore.
Show source
Dividend from JVs, ₹3 crores as against ₹1 crore.
- Power Grid's dividend from subsidiaries was ₹423 crores, compared with ₹149 crores, and dividend from associates and others was ₹32 crores, compared with ₹20 crores.
Show source
Dividend from subsidiaries, ₹423 crores as against ₹149 crores, and dividend from associates and others, ₹32 crores as against ₹20 crores.
- PowerTel added 12 new customers in Q3, and its telecom network backbone availability was 100%.
Show source
In Q3, we have added 12 numbers of new customers and our backbone availability of telecom network has been 100%.
- Power Grid billed ₹27,989 crores and realised ₹28,404 crores, with realisation efficiency of 101.48% in Q3 and Nine Months ended 31.12.2024.
Show source
We have done billing of ₹27,989 crores with realisation of ₹28,404 crores; realisation efficiency has been 101.48%.
- Power Grid's outstanding dues were ₹4,380 crores at the end of Q3, with major dues from Tamil Nadu, UP, Telangana and Madhya Pradesh.
Show source
And at the end of quarter 3, it has become ₹4,380 crores with major dues from Tamil Nadu, UP, Telangana and Madhya Pradesh.
- Power Grid's CapEx through 31st January was ₹19,480 crores and capitalisation through 31st January '25 was ₹7,906 crores.
Show source
Till 31st January, our Page 6 of 23 CapEx has been ₹19,480 crores and capitalisation till 31st January '25 ₹7,906 crores.
- Power Grid's CapEx in the last quarter was around ₹10,000 crores.
Show source
If you see that last quarter, we have done a CapEx of maybe around ₹10,000 crores.
- The impact of CERC tariff regulations on the O&M portion was around ₹140 crores in Q3, compared with Q3 of FY '24.
Show source
Ravisankar: This impact of CERC tariff regulations, the O&M portion is around ₹140 crores in Q3.
- Power Grid's 39% stake portion of EESL's losses was ₹140 crores for nine months, included in the consolidated results.
Show source
For the nine months, it is around ₹140 crores, it is included in the consol, our portion, 39% of our stake amounts to ₹140 crores for nine months.
- The tariff award of projects was ₹2,077 crores for nine months.
Show source
Ketan Jain: Yeah, ₹2,077 crores for nine months.
- Power Grid's tariff for nine months was ₹8,027 crores.
Show source
Tyagi: For nine months tariff is ₹8,027 crores.
- Regulated tariff income decreases each year as loan interest reduces based on depreciation recovery; recovering around ₹12,000 crores to ₹13,000 crores of depreciation results in transmission income falling by around ₹700 crores to ₹900 crores a year, using a 7.5% to 8% interest thumb rule.
Show source
So, if I recover around ₹12,000 crores, ₹13,000 crores of a depreciation, to that extent, if you say a thumb rule like 7.5%, 8% at the interest, so naturally around ₹700 crores to ₹800 crores, ₹900 crores for transmission income is bound to come down every year.
- Transmission income was expected to fall by around ₹600 crores to ₹650 crores for the nine months, but it did not fall by that extent because the company added more assets.
Show source
So, when I say that when the revenue is supposed to come down by like ₹800 crores, ₹900 crores in a year and if you compare for the nine months, maybe around ₹600 crores, ₹650 crores, it is bound to come down, but it is not coming down because we are adding more assets.
- Power Grid’s share of loss from the EESL JV was ₹140 crores in Q3 and contributed to the decline in consolidated profit compared with standalone profit.
Show source
Ravisankar: That is because actually, we have a loss of some of the JVs like we have one JV EESL, which was our share of loss is ₹140 crores.
- Power Grid’s profit was affected by an approximately ₹140 crores impact each quarter under the CERC order.
Show source
It is also hitting our profit also by almost ₹140 crores each quarter.
- Regulated-business transmission income is bound to decrease, but its PAT will remain the same because PAT is based on return on equity; new commissioned assets are added, limiting the decrease.
Show source
But the fact remains that the PAT will remain same because that is based on the return on equity.
- Power Grid said its PAT was lower than last year because one-time CERC order impacts and interest and differential amounts between the date of commercial operation and order dates had contributed less to the bottom line in the current year.
Show source
That is also the reason that your PAT has come down compared to last year.
Money and capital
- Power Grid signed its first Green Loan Agreement for $200 million with Sumitomo Mitsui Banking Corporation, Japan, to fund Power Grid RE projects.
Show source
We have secured our first Green Loan Agreement of $200 million was signed with Sumitomo Mitsui Banking Corporation, Japan, for funding RE projects of Power Grid.
- Power Grid's gross fixed assets as on 31st December 2024 were ₹2,88,801 crores, capital work-in-progress was ₹29,603 crores, debt was ₹1,29,288 crores and net worth was ₹91,620 crores.
Show source
Other financial parameters, our gross fixed assets as on 31st December 2024 is ₹2,88,801 crores.
- Regulated equity was estimated at ₹80,000 crores to ₹83,000 crores as at end of December '24.
Show source
So maybe in the range of ₹80,000 crores to ₹83,000 crores will be the regulated equity.
- The company estimates that ₹5,000 crores to ₹6,000 crores of equity will be required, including for TBCB and RTM projects, if next year's CapEx is ₹25,000 crores.
Show source
Tyagi: So, if you consider say ₹25,000 crores CapEx next year, so maybe between ₹5,000 crores to ₹6,000 crores will be required including TBCB and RTM projects.
- $200 million borrowing from Sumitomo has an interest rate of around 1%, including the spread, based on TONA as the reference rate; foreign exchange rate variation depends on movement of the Japanese currency.
Show source
Ravisankar: It is based on the TONA is the reference rate and the borrowing interest rate is around 1%, including the spread.
- The company can explore raising debt through other markets to fund its large CapEx pipeline, rather than replacing domestic debt; it is exploring other markets because TONA is now at a competitive rate after refraining from other markets while SOFR was close to 5 or 4.5 over the last four or five years.
Show source
Now since the TONA is almost at a very competitive rate, we are exploring the other markets.
- $200 million borrowing has a greenshoe of another 150 million, bringing the total close to ₹3,000 crores if converted into Indian rupees, and the company will explore similar markets further.
Show source
So maybe since this comes up with a greenshoe of another 150 million, so this is 200 million plus another $150 million will be close to ₹3,000 crores, if you convert it into Indian rupees.
- Power Grid's CapEx was ₹12,500 crores last year and is going to be ₹23,000 crores this year.
Show source
This year, it is going to be ₹23,000 crores.
- Power Grid's first dividend was ₹4.5 per share and its second interim dividend was ₹3.25 per share, for a total of ₹7.75 per share; it hopes to pay about ₹9 per share in this financial year because of its CapEx requirement.
Show source
Today, we have ₹4.5 was the first dividend, and this is a second interim dividend, ₹3.25, so put together ₹7.75.
- Power Grid said increasing project commissioning would help maintain its dividend to some extent and that its dividend would not fall very steeply to ₹2 or ₹3, which it said was not permitted under DIPAM guidance.
Show source
It's not going to fall very steeply to like ₹2 or ₹3 something like that.
- Projects normally have 30pc equity and a return on equity of about 15pc.
Show source
And TBCB, it's free for us to put any equity, but so far, we are almost maintaining 20%.
- Power Grid's international credit rating was BBB-, at par with Sovereign rating, and its domestic credit rating was AAA.
Show source
Our international credit rating is at par with Sovereign rating, BBB- and domestic credit rating is AAA.
- The company has no near-future plan to disinvest its assets in Power Grid Infrastructure Investment Trust (PG InvIT) because of the new NMP guidelines.
Show source
But after new NMP guidelines, now we are not able to disinvest our assets in this PG InvIT, so we don't have plan in near future to disinvest our Power Grid assets because of NMP guidelines.
- Power Grid expects higher equity infusion for its CapEx requirements and may reduce its dividend further.
Show source
So, we require more and more equity to be infused for our CapEx requirements.
- Power Grid adopted securitisation of cash flows for monetisation, raised bonds and opened a TRA account to hold money for debt servicing.
Show source
So, of our monetisation, we have adopted the route of securitisation of the cash flows and through which we raised the bonds and then we opened TRA account where we used to put the money for servicing the debts.
What it expects ahead
What management expects
- Power Grid has a target of 50% renewable energy consumption by 2025.
Show source
We have a target of 50% of renewable energy consumption by 2025.
- Power Grid is targeting capitalisation of about ₹18,000 crores for the full year.
Show source
So, we are targeting in the same range about that ₹18,000 crores.
- Power Grid expects the project awards for FY '26 to be similar to FY '25, in line with the NEP plan of about ₹6 lakhs for interstate projects.
Show source
So FY '26 also, it will be similar to FY '25.
- Target is to commission about ₹25,000 crore of projects next year, about ₹35,000 crores the following year and another ₹35,000 crores the year after that.
Show source
So, every year, that means next year, we will have target about ₹25,000 crore projects, which will be required to be commissioned.
- The company expects capitalisation of about ₹23,000 crores up to March this year.
Show source
Tyagi: CapEx, like this year, we are telling it is about ₹23,000 crores up to March.
- The company expects CapEx of ₹28,000 crores to ₹30,000 crores for FY '26 and ₹35,000 crores for FY '27.
Show source
And for FY '26, it will be in the range of about ₹28,000 crores to ₹30,000 crores.
Show 16 more statements
What management expects
- Power Grid's FY '27 CapEx may exceed ₹35,000 crores because a number of projects are under pipeline.
Show source
So, considering those projects, maybe FY '27, it may go more than ₹35,000 crores also.
- Power Grid expects the Pang-Kaithal project bid to be awarded in the first quarter of FY '26, after queries from prospective bidders Hitachi and Siemens are clarified.
Show source
And maybe in the first quarter of FY '26, it is likely to be awarded.
- The company expects green loans from other markets to provide a benefit in the rate of at least a few bps.
Show source
Naturally, the other markets, whoever the lenders, encourage the green loan, and we expect that there should be a benefit in the rate of at least for a few bps.
- Power Grid plans to consider another state for smart meters only after gaining experience with its meters in Gujarat; so far, it is focusing on completing the Gujarat project and is not considering any other state.
Show source
But so far, we are not considering any other state other than, we are focusing on completion of this project.
- Power Grid expects revenue and PAT to increase as it commissions more projects.
Show source
And going forward, when we commission more and more projects, naturally, the revenue as well as PAT also will increase.
- Power Grid expects its project capitalisation and CapEx to increase because it has many projects in hand, leading to higher revenue and profit.
Show source
And we have many projects in hand, and our project capitalisation and CapEx is going to Page 22 of 23 increase.
Orders
- Up to Q3, Power Grid had a 50% share in annual tariff, a 58% share in NCT cost and a 57% share in number of TBCB projects won.
Show source
Up to Q3, we have share of 50% in annual tariff in TBCB projects, 58% in terms of NCT cost and 57% in terms of number of projects won.
- Power Grid won the Khavda project; the bid difference between Power Grid and the other party was 0.25%.
Show source
So there were a difference of only 0.25%.
- For the Fatehpur to Bhadla-III project, Adani Transmission won at about ₹3,500 crores, while Power Grid had won the project at ₹3,700 crores considering Rajasthan's land policy after 14th June 2024; Power Grid revised its bids and decided not to go beyond the L1 limit because the project was not in its range.
Show source
So, they have won in about ₹3,500 crores and considering the land policy in Rajasthan after this 14th June 2024 and earlier, we won this project in ₹3,700 crores.
- Power Grid won projects costing ₹63,909 crores up to December '24 and ₹19,828 crores in Q3.
Show source
Tyagi: Up to December '24, it is ₹63,909 crores.
- Projects worth about ₹52,000 crores are under bidding.
Show source
Already, there are about projects worth ₹52,000 crores under bidding.
- Power Grid has an order for about 67 lakhs smart meters to be installed in Uttar Gujarat and Madhya Gujarat.
Show source
Tyagi: For smart meters, we have this order of about 67 lakhs meters to be installed in Uttar Gujarat and Madhya Gujarat.
- Power Grid has around ₹52,000 crores of projects under bidding.
Show source
You indicated about ₹52,000 crores of projects under bidding.
- Power Grid said its traditional strike rate in bidding is 50%, and it may add another ₹25,000 crores to ₹27,000 crores to its ₹1,43,000 crores of projects, bringing the total to around ₹1,70,000 crore.
Show source
So, when I say today, ₹1,43,000 crores, you add another ₹27,000 crores, so this will become around ₹1,70,000 crore.
- PowerTel received its first International Long Distance business order in Q3.
Show source
We have received first International Long Distance business order in Q3.
- Power Grid's works in hand to be executed exclude CWIP.
Show source
Sumit, what we have shown in the last quarter, actually, this is the works in hand which are to be executed, that is excluding the CWIP.
What it is building and selling
Projects and capacity
- Power Grid had 1,518 transmission lines, 1,79,594 circuit kilometres of transmission lines, 280 substations and 5,52,961 MVA capacity.
Show source
We have 1,79,594 circuit kilometre, 280 substations, 5,52,961 MVA capacity.
- Power Grid's interregional transfer capacity was 99,580 megawatt, 84% of total interregional capacity of India.
Show source
Our interregional transfer capacity is 99,580 megawatt, which is 84% of total interregional capacity of India.
- Power Grid was remotely operating 281 substations from its control centre at Manesar as on 31 December 2024.
Show source
We are remotely operating 281 substations from our control centre at Manesar, as on 31 December 2024.
- Power Grid procured land from SIPCOT in Chennai for Disaster Recovery Zone-2 Data Centre at Chennai.
Show source
Then land has been procured from SIPCOT in Chennai for Disaster Recovery Zone-2 Data Centre at Chennai.
- Transmission assets worth about ₹2,55,368 crores are to be added in various states for the intrastate transmission system, as per NEP.
Show source
Then in various states for intrastate transmission system, as per NEP, about ₹2,55,368 crores worth transmission assets are going to be added.
- The total CapEx for the transmission system will be ₹9,16,142 crores up to 2032.
Show source
And total CapEx summary for transmission system will be ₹9,16,142 crores up to 2032.
Show 32 more statements
Projects and capacity
- Power Grid's CapEx plan for financial year '25 is ₹23,000 crores, including ₹3,914 crores for RTM projects, about ₹14,209 crores for TBCB projects and ₹4,877 crores for other works.
Show source
For financial year '25, our CapEx plan is now ₹23,000 crores, which includes RTM projects worth ₹3,914 crores, then TBCB projects about ₹14,209 crores and other works ₹4,877 crores.
- The company has about ₹147,000 crores of projects in hand and about ₹29,000 crores in progress.
Show source
Tyagi: FY '26 because whatever projects like we have projects about say, ₹147,000 crores in hand and about ₹29,000 crores in progress.
- The company has almost ₹1,76,000 crores of projects to be commissioned in the next five years, including HVDC Leh to Pang, which is to be commissioned in the next five years, and Khavda to Nagpur, which is to be commissioned in the next 4.5 years.
Show source
So put together, we have almost ₹1,76,000 crores projects which are to be commissioned in next five years, because this includes HVDC Leh to Pang which is to be commissioned in the next five years.
- The company has about ₹1,08,000 crores of AC section projects to be commissioned in the next three years.
Show source
So, if we subtract these costs, so AC section will be about ₹1,08,000 crores projects are to be commissioned in the next three years.
- The company has the Khavda to Nagpur project, with a market-condition cost of about ₹35,000 crores compared with an NCT cost of ₹24,000 crores.
Show source
Tyagi: We have already two projects in our hand, one is Khavda to Nagpur, which is almost worth ₹35,000 crores, although NCT cost wise ₹24,000 crores, but as per the market conditions that cost is going to be about ₹35,000 worth crores.
- Pang to Leh project is worth more than ₹20,000 crore, is under bidding, and will be executed in the next five years.
Show source
Second one is Pang to Leh, which is, again, more than ₹20,000 crore project, which will be executed in the next five years.
- The KPS3 Khavda to South Olpad project is under bidding with an NCT cost of about ₹12,000 crores.
Show source
One is already under bidding from KPS3 Khavda to South Olpad, with NCT cost of about ₹12,000 crores.
- The executed cost of the Khavda-Nagpur project will be somewhere ₹35,000 crores, compared with an NCT cost of ₹24,000 crores.
Show source
Now I'm saying that total executed cost will be somewhere ₹35,000 crores.
- The executed cost of the Fatehpur-Bhadla project may be about ₹24,000 crores to ₹25,000 crores, compared with an NCT cost of ₹12,000 crores; Power Grid Corporation of India Limited is not executing the project.
Show source
So similarly, in the case of Fatehpur-Bhadla also, although NCT cost was ₹12,000 crores, but the executed cost may be about ₹24,000 crores, ₹25,000 crores.
- The company has a pipeline of almost ₹1 lakh crore of projects, excluding HVDC and offshore projects, which have a commissioning timeline of another three years; commissioning of projects worth ₹25,000 crores to ₹30,000 crores may happen over the next three to four years.
Show source
Ravisankar: As our chairman has already told that we have a pipeline of almost ₹1 lakh crore of our projects, excluding the HVDC and offshore projects, which have a time line of another three years for commissioning.
- RTM includes offshore and Pang-Kaithal projects of around ₹22,700 crores and ₹13,600 crores, respectively, and the company can assume around ₹40,000 crores to ₹45,000 crores will be added in the regulatory business, including a few bays extensions and other items.
Show source
Around ₹40,000 crores to ₹45,000 crores you can assume we'll be adding up in the regulatory business also.
- Power Grid expects at least one or two connecting transmission lines to be completed by March; the transmission line and substation will add at least ₹1,500 crore of assets.
Show source
So, with this transmission line and substation at least ₹1,500 crore assets will be added here.
- Power Grid's Khavda-II (KPS2) and Khavda-III (KPS3) GIS stations will each be in the range of about ₹1,000 crores.
Show source
Each will be in the range of about ₹1,000 crores.
- Power Grid's Khavda-II, Khavda-III and connecting transmission-line assets together will be about ₹3,500 crores.
Show source
So, each will be ₹1,000 crores and ₹1,000 crores, so put together ₹3,500 crores.
- Power Grid is hopeful that the Navsari-to-Magarwada line and project will be commissioned by February; the project is in the range of about ₹1,500 crores.
Show source
Then Navsari to Magarwada, this line is almost getting ready by February, and we are hopeful that this project will also be commissioned by February, this will again be in the range of about ₹1,500 crores.
- Power Grid's Kurnool station is getting ready in another 20 days, and the transmission line from the existing Kurnool-II station to the new Kurnool-III station is in an advanced stage of completion; the project will also be commissioned.
Show source
So that will also be commissioned.
- Power Grid expects around ₹10,000 crore of assets to be completed by March because the projects are in an advanced stage of completion.
Show source
So put together, we are expecting that around ₹10,000 crore assets are likely to be completed by March because all are in advanced stage of completion.
- Power Grid implemented dynamic line loading in India for controlling power flow in transmission lines based on temperature, wind speed and other ambient conditions.
Show source
In asset management, for the first time in India, we have implemented dynamic line loading for controlling power flow in transmission line depending on temperature, wind speed and other ambient conditions.
- Power Grid commissioned a new station at Sikar-II in October.
Show source
During Q3, new station at Sikar- II was commissioned in October.
- PowerTel enabled fibre to home broadband for end users in Tura town of Meghalaya in the Northeastern region.
Show source
And PowerTel also Page 5 of 23 enabled fibre to home broadband for providing reliable Internet for the end users in Tura town of Meghalaya in Northeastern region.
- The company has formed a joint venture company for intrastate projects with Rajasthan, and the Government of Rajasthan is identifying projects for execution.
Show source
As far as the JV for intrastate with Rajasthan, we have already formed the joint venture company.
- The company is mitigating procurement challenges for transformers by bulk procuring them irrespective of projects in hand, to ensure adequate transformers and reactors for future project requirements.
Show source
So, we are mitigating this challenge by procuring under bulk procurement, transformers we are procuring irrespective of the projects in hand.
- The company is discussing with GIS suppliers to start manufacturing in India, while suppliers are ramping up manufacturing capacity for GIS, transformers and reactors.
Show source
So, we are discussing with GIS suppliers so that they can start manufacturing in India.
- The company is targeting a two-year timeframe, especially for substations where transformers or reactors are commissioned, but RoW issues are causing some transmission-line delays.
Show source
So, some delays are happening because of RoW issues.
- The company is taking up transmission-project delays with the Ministry of Power and state administration to minimise them, but acknowledges challenges in completing transmission projects within two years.
Show source
But still, we are taking up with the Ministry of Power and the state administration to minimise the delays but let me accept that there are challenges in completion of these transmission projects within two years.
- Adani won the Bhadla to Fatehpur project.
Show source
And other than these two projects, one project had been won by Adani, which is Bhadla to Fatehpur.
- Power Grid is trying to complete the Bhadla-to-Sikar-II project in Rajasthan, but it is very difficult.
Show source
One more project in Rajasthan is Bhadla to Sikar-II, which we are trying to complete, but it is very difficult, but we are trying to complete this project also.
- Power Grid said there was no concrete development or intimation that it would receive the Andaman RTM project.
Show source
So as of now, there is no concrete development or we got any intimation of getting that through RTM.
- Power Grid is executing the Leh-Kaithal project using VSC technology, not LCC.
Show source
Tyagi: No. From the start itself that we are executing this project at VSC only, not LCC.
Deals and partners
- Power Grid signed a 10-year master agreement with EPRI USA, a non-profit energy research and development organisation, to help with transmission system construction, operation and maintenance and promote energy transition and sustainability.
Show source
We have signed a 10-year master agreement with EPRI USA, a non-profit energy research and development organisation.
- Power Grid is tying up with various states for green tariff for its substations to offer green power.
Show source
We are now tying up with various states for green tariff for our substations to offer the facility of green power.
- Power Grid's Khavda-Nagpur HVDC project has been ordered on Hitachi; design engineering work has started, Bhoomi Puja has been completed at the site, and execution will start very shortly.
Show source
Tyagi: HVDC project Khavda-Nagpur is already ordered, it is ordered on Hitachi.
Risks, rules and outside factors
Rules and policy
- Transferring revenue rights to an InvIT or another entity attracts GST of 18%, which makes the transfer not lucrative to Power Grid shareholders after discounting the transmission charges for GST.
Show source
So, when we examine the revenue, rights are to be transferred to the InvIT or any other entity, it attracts a GST of 18%, which is, again, not lucrative to the shareholders of Power Grid, because ultimately in the transmission charges, if you get after discounting 18% GST, it's not value decretive.
- The National Monetisation Pipeline guidelines, published in August 2021, envisage that assets of central CPSEs are not transferred permanently and only revenue rights are given; Power Grid has not added further assets because transferring shares is not permitted under the guidelines.
Show source
And that is the reason that we have not further added the assets because once we have to add the assets means, we will have to transfer the shares, which is not permitted in the National Monetisation Pipeline guidelines.
Everything else said on the call
Group structure
- Power Grid has not put equity into EESL for almost a year and will not put further equity into it.
Show source
So we are not putting further equity in that.
Other
- Power Grid was ranked first in Net Profit and Dividend Declared, and second in Gross Block, Net Worth and Contribution to Exchequer in the Public Enterprises Survey '23-'24.
Show source
As per Public Enterprises Survey '23-'24, we have been given first rank in Net Profit; first rank in Dividend Declared; second rank in Gross Block; second rank in Net Worth and second rank in Contribution to Exchequer.
- Power Grid was granted a patent for a system and method for health assessment of transformers and reactors.
Show source
Also, Power Grid has been granted patent for system and method for health assessment of transformers and reactors.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
This transcript does not separate questions and answers, so they are not listed here.
Questions about this call
- When was the Power Grid Corporation of India Q3 FY25 earnings call transcript filed?
- Power Grid Corporation of India filed the transcript with the exchange on 12 Feb 2025. This page is built from that transcript.
- What does this page list?
- 114 statements from the transcript across 9 topics, 86 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- No. This transcript does not separate the questions from the answers, so they are not listed. The statements by topic still cover what management said.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.